CN102817342A - 一种双壁钢围堰桩基施工平台下原位拼装施工技术 - Google Patents

一种双壁钢围堰桩基施工平台下原位拼装施工技术 Download PDF

Info

Publication number
CN102817342A
CN102817342A CN2012103073503A CN201210307350A CN102817342A CN 102817342 A CN102817342 A CN 102817342A CN 2012103073503 A CN2012103073503 A CN 2012103073503A CN 201210307350 A CN201210307350 A CN 201210307350A CN 102817342 A CN102817342 A CN 102817342A
Authority
CN
China
Prior art keywords
cofferdam
pile foundation
platform
construction
lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012103073503A
Other languages
English (en)
Inventor
王员根
付小莲
李书学
李忠翔
郑自元
李慧明
吴昕
凌喜
纪淑峰
王继东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Science and Industry Group Co Ltd
China Railway Jiujiang Bridge Engineering Co Ltd
Original Assignee
China Railway Science and Industry Group Co Ltd
China Railway Jiujiang Bridge Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Science and Industry Group Co Ltd, China Railway Jiujiang Bridge Engineering Co Ltd filed Critical China Railway Science and Industry Group Co Ltd
Priority to CN2012103073503A priority Critical patent/CN102817342A/zh
Publication of CN102817342A publication Critical patent/CN102817342A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

一种双壁钢围堰桩基施工平台下原位拼装施工技术,桩基与围堰进行上下双重全封闭作业,待围堰定位桩基完成后,在桩基施工平台下安装圆端形平面运输轨道,运用桁车吊装走行进行围堰单元件运输至设计位置定位拼焊,将围堰分节分块为单元件,在已完成的定位桩基处的平台一角开孔,将单元件喂入平台下方,采用C形钩将单元件喂入平面运输轨道正下方,实现无斜拉的吊点转换,将围堰单元件从垂直吊装过渡至水平运输的环节,围堰每节拼装完成后的联动下放。具有安全、快捷、经济的特点,实现了围堰拼装零工期的目标,仅采用很小而少的结构拼装围堰,避免了使用大型水上吊装、拖运设备,节约了大量的成本,同时确保了围堰施工的安全、质量和进度。可广泛应用于高平台深水基础施工。

Description

一种双壁钢围堰桩基施工平台下原位拼装施工技术
技术领域
本发明涉及一种双壁钢围堰桩基施工平台下原位拼装施工技术。
背景技术
水上基础施工多采用先桩后堰的方法,深水围堰拼装方法主要有如下:
1、浮运方案:待桩基施工完成后,拆除水上施工平台,在岸上整体拼装围堰,设置下水滑道,下滑入水,由双拖轮拖运至承台位、定位下沉。
2、平台上现场拼装法:待桩基施工完成后,拆除桩基施工平台,围堰首节拖运至承台位,再搭设水上安装平台进行水上拼装。
以上两种方案均需要投入较多的大型水上设备,施工工期也较长,且占用航道,受航道部门限制。
发明内容
本发明其目的就在于提供一种双壁钢围堰桩基施工平台下原位拼装施工技术,具有安全、快捷、经济的特点,实现了围堰拼装零工期的目标,仅采用很小而少的结构拼装围堰,避免了使用大型水上吊装、拖运设备,节约了大量的成本,同时确保了围堰施工的安全、质量和进度。可广泛应用于高平台深水基础施工。
实现上述目的而采取的技术方案为,桩基与围堰进行上下双重全封闭作业,待围堰定位桩基完成后,在桩基施工平台下安装圆端形平面运输轨道,运用桁车吊装走行进行围堰单元件运输至设计位置定位拼焊,将围堰分节分块为单元件,在已完成的定位桩基处的平台一角开孔,将单元件喂入平台下方,采用C形钩将单元件喂入平面运输轨道正下方,实现无斜拉的吊点转换,将围堰单元件从垂直吊装过渡至水平运输的环节,围堰每节拼装完成后的联动下放。
与现有技术相比本发明具有以下优点。
由于采用了桩基与围堰进行上下双重全封闭作业施工技术,因而具有安全、快捷、经济的特点,实现了围堰拼装零工期的目标,仅采用很小而少的结构拼装围堰,避免了使用大型水上吊装、拖运设备,节约了大量的成本,同时确保了围堰施工的安全、质量和进度。可广泛应用于高平台深水基础施工。
附图说明
下面结合附图对本发明作进一步详述。
图1为围堰安装结构示意图。
图2为本发明中吊装行走装置示意图。
图3为本发明中围堰下沉吊点悬吊示意图。
图4为本发明中围堰下放示意主视图。
图5为图4的侧视图。
具体实施方式
如图1、2、3、4、5所示,桩基与围堰进行上下双重全封闭作业,待围堰定位桩基8完成后,在桩基施工平台5下安装圆端形平面运输轨道1,运用桁车吊装走行进行围堰单元件4运输至设计位置定位拼焊,将围堰分节分块为单元件,在已完成的定位桩基8处的平台一角开有吊装下放孔7,将围堰单元件4喂入平台5下方,采用C形钩将围堰单元件4喂入平面运输轨道正下方,实现无斜拉的吊点转换,将围堰单元件4从垂直吊装过渡至水平运输的环节,围堰每节拼装完成后的联动下放。
所述平面运输轨道1上设有吊装行走装置6,吊装行走装置6下方连接围堰单元件4;所述平面运输轨道1上设有围堰下沉吊点2,所述围堰下沉吊点2上方设有同步下放液压装置9。
实施例,某双线特大桥主桥位于某航运干线河段上,水深条件良好,平均水深10m左右。设计里程范围为DK106+290.10~DK106+849.50,长度为559.40m,中心里程:DK106+537,由5跨连续钢桁梁和两跨32m梁组成,跨度布置从一侧至另一侧为:(36+96+228+96+36)m钢桁梁+2×32m。主桥281#~286#墩跨,其中283#、284#墩为水中主塔墩,施工水位为32.0m。283#墩处爆破后水深为21m,主塔承台为圆端形,厚5.0m,平面尺寸为38×24.8m,采用围堰施工方法。圆端形围堰外轮廓尺寸:40.6m(长)×27.4m(宽)×20.2m(高),围堰双壁侧板厚1.2m。围堰底高程+12m,围堰顶高程+32.2m,承台底高程+14.66m,承台顶高程+19.66m。
本次水上基础采用先桩基堰的施工方法。大型围堰采用在承台位原位分分块拼装的方法进行安装。
水上基础施工基本都采用围堰施工的方法。围堰施工安装圆端形围堰外轮廓尺寸:40.6m(长)×27.4m(宽)×20.2m(高),围堰双壁侧板厚1.2m。围堰底高程+12m,围堰顶高程+32.2m,承台底高程+14.66m,承台顶高程+19.66m。一个围堰重达900t。
采用在桩基施工平台下进行围堰单元件拼装,逐节拼装下放,最后定位下沉,待定位桩基施工完成后,立即进行平台下围堰施工,实现桩堰同时施工,节约施工工期及大型水上设施的投入。
桩基与围堰进行上下双重全封闭作业,待围堰定位桩基完成后,在桩基施工平台下安装圆端形平面运输轨道,运用桁车吊装走行的原理进行围堰单元件运输至设计位置定位拼焊。将围堰合理分节分块,在已完成的定位桩基处的平台一角开孔,将单元件喂入平台下方,采用C形钩将单元件喂入平面运输轨道正下方,实现无斜拉的吊点转换,安全地将围堰单元件从垂直吊装过渡至水平运输的环节。
围堰拼装系统分走行系统、临时吊挂系统及下放吊挂系统三部分。注:
1、从平台桩基布置及栈桥高度两方面设计围堰拼装的空间
栈桥分配梁底至水面高度为7.7m,水上拼装时围堰顶面距水面1m,围堰每节高度定为3m,垂直及水平运输单元件吊具高1.5m,平面运输轨道高0.36m,则有围堰水上拼装总高度为5.86m,空间高度满足要求。平面位置考虑平台桩基应让出围堰单元件走行一圈的轨迹空间。
2、围堰分块分节
为确保围堰能在最高水位时正常拼装,将围堰分为3m一节。根据平台的布置,只能在平台一角开一个8.7×9.2m的口,那么围堰单元件应控制在此范围内,本次分块最大为7.5×1.7×3m,长为7.5m,重7.6t,16t吊机即可以顺利通过开口将单元件喂入平台下方。
3、围堰单元件喂入平台下方
围堰单元件从平台上喂入平台下,但要将单元件送至平台下运输系统则有一个在空中进行吊点转换的动作,为防止转换吊点时出现斜拉的不安全工况,要求平台上吊机要将单元件送至平台下轨道正下方,设置两套吊点,安全地进行吊点转换。因此设计C型钩吊具将围堰单元件喂至平台下平面运输轨道正下方。
4、围堰单元件在平台下的平面运输
要想桩堰同时施工,围堰施工时不能破坏桩基施工平台,只能在桩基施工平台一角将围堰单元件喂至平台下,则需要一个平台下的平面运输系统,利用桁车吊装走行的原理,在平台下围堰壁中心线处设置一个圆端形轨道,采用两台10t电动葫芦联动作为吊装走行动力进行平台运输单元件至设计位置定位拼焊。
5、围堰每节拼装完成后的联动下放
围堰拼装完成一个节后,平台下空间不足以再拼装一节,操作平台标高也不再适用,因此应注水下放。本次采用在围堰上对称设置6套下放吊点,在平台上对应设置6套下放液压起落顶系统,下放前先注水,使下放拉杆在围堰下放至要求标高后及处于受拉状态。6套液压顶油路系统串联,确保同步下放,受力均匀。

Claims (2)

1.一种双壁钢围堰桩基施工平台下原位拼装施工技术,其特征在于,桩基与围堰进行上下双重全封闭作业,待围堰定位桩基(8)完成后,在桩基施工平台(5)下安装圆端形平面运输轨道(1),运用桁车吊装走行进行围堰单元件(4)运输至设计位置定位拼焊,将围堰分节分块为单元件,在已完成的定位桩基(8)处的平台一角开有吊装下放孔(7),将围堰单元件(4)喂入平台(5)下方,采用C形钩将围堰单元件(4)喂入平面运输轨道正下方,实现无斜拉的吊点转换,将围堰单元件(4)从垂直吊装过渡至水平运输的环节,围堰每节拼装完成后的联动下放。
2.根据权利要求1所述的一种双壁钢围堰桩基施工平台下原位拼装施工技术,其特征在于,所述平面运输轨道(1)上设有吊装行走装置(6),吊装行走装置(6)下方连接围堰单元件(4);所述平面运输轨道(1)上设有围堰下沉吊点(2),所述围堰下沉吊点(2)上方设有同步下放液压装置(9)。
CN2012103073503A 2012-08-27 2012-08-27 一种双壁钢围堰桩基施工平台下原位拼装施工技术 Pending CN102817342A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012103073503A CN102817342A (zh) 2012-08-27 2012-08-27 一种双壁钢围堰桩基施工平台下原位拼装施工技术

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012103073503A CN102817342A (zh) 2012-08-27 2012-08-27 一种双壁钢围堰桩基施工平台下原位拼装施工技术

Publications (1)

Publication Number Publication Date
CN102817342A true CN102817342A (zh) 2012-12-12

Family

ID=47301758

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012103073503A Pending CN102817342A (zh) 2012-08-27 2012-08-27 一种双壁钢围堰桩基施工平台下原位拼装施工技术

Country Status (1)

Country Link
CN (1) CN102817342A (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103397649A (zh) * 2013-08-16 2013-11-20 中铁大桥局股份有限公司 双壁钢围堰施工多功能平台及其施工方法
CN103741725A (zh) * 2014-01-17 2014-04-23 天津市市政工程设计研究院 一种沉管隧道最终接头及其岸边干作施工方法
CN105970820A (zh) * 2016-06-03 2016-09-28 中交第二航务工程局有限公司 一种大型围堰u形平台辅助式定位方法
CN106337433A (zh) * 2016-08-30 2017-01-18 中铁十九局集团矿业投资有限公司 基于震动液化砂质地层的施工方法和装置
CN107869144A (zh) * 2017-11-17 2018-04-03 中铁二十二局集团第四工程有限公司 一种预掏槽环封双壁钢围堰深水基础综合施工方法
CN109267749A (zh) * 2018-11-02 2019-01-25 广东省水利水电第三工程局有限公司 一种应用于厚淤泥层的混凝土预制模板施工工艺

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1751835A (en) * 1927-10-27 1930-03-25 Sargent & Lundy Inc Cofferdam and method of construction
JPH1018229A (ja) * 1996-06-28 1998-01-20 Fujita Corp 既設水中構造物の水域仮締切り施工法
JP2005350979A (ja) * 2004-06-11 2005-12-22 Ohbayashi Corp 仮締切構造体および仮締切工法
JP4009028B2 (ja) * 1998-12-25 2007-11-14 鹿島建設株式会社 二重締切り工法で使用する締切り装置および二重締切り工法
CN101205720A (zh) * 2007-12-05 2008-06-25 中铁大桥局股份有限公司 一种超大型钢围堰下放、着床、下沉控制技术
CN101974913A (zh) * 2010-10-15 2011-02-16 中铁三局集团有限公司 桥梁深水基础钻孔桩与围堰平行施工的方法
CN201857618U (zh) * 2010-11-11 2011-06-08 四川路桥桥梁工程有限责任公司 浮式导向平台和钢护筒支撑钻孔平台深水桩基础
CN202359566U (zh) * 2011-12-13 2012-08-01 中交第二公路工程局有限公司 一种桥梁深水软土地基施工围堰

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1751835A (en) * 1927-10-27 1930-03-25 Sargent & Lundy Inc Cofferdam and method of construction
JPH1018229A (ja) * 1996-06-28 1998-01-20 Fujita Corp 既設水中構造物の水域仮締切り施工法
JP4009028B2 (ja) * 1998-12-25 2007-11-14 鹿島建設株式会社 二重締切り工法で使用する締切り装置および二重締切り工法
JP2005350979A (ja) * 2004-06-11 2005-12-22 Ohbayashi Corp 仮締切構造体および仮締切工法
CN101205720A (zh) * 2007-12-05 2008-06-25 中铁大桥局股份有限公司 一种超大型钢围堰下放、着床、下沉控制技术
CN101974913A (zh) * 2010-10-15 2011-02-16 中铁三局集团有限公司 桥梁深水基础钻孔桩与围堰平行施工的方法
CN201857618U (zh) * 2010-11-11 2011-06-08 四川路桥桥梁工程有限责任公司 浮式导向平台和钢护筒支撑钻孔平台深水桩基础
CN202359566U (zh) * 2011-12-13 2012-08-01 中交第二公路工程局有限公司 一种桥梁深水软土地基施工围堰

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103397649A (zh) * 2013-08-16 2013-11-20 中铁大桥局股份有限公司 双壁钢围堰施工多功能平台及其施工方法
CN103397649B (zh) * 2013-08-16 2015-04-29 中铁大桥局股份有限公司 双壁钢围堰施工多功能平台及其施工方法
CN103741725A (zh) * 2014-01-17 2014-04-23 天津市市政工程设计研究院 一种沉管隧道最终接头及其岸边干作施工方法
CN105970820A (zh) * 2016-06-03 2016-09-28 中交第二航务工程局有限公司 一种大型围堰u形平台辅助式定位方法
CN106337433A (zh) * 2016-08-30 2017-01-18 中铁十九局集团矿业投资有限公司 基于震动液化砂质地层的施工方法和装置
CN107869144A (zh) * 2017-11-17 2018-04-03 中铁二十二局集团第四工程有限公司 一种预掏槽环封双壁钢围堰深水基础综合施工方法
CN109267749A (zh) * 2018-11-02 2019-01-25 广东省水利水电第三工程局有限公司 一种应用于厚淤泥层的混凝土预制模板施工工艺

Similar Documents

Publication Publication Date Title
CN102817342A (zh) 一种双壁钢围堰桩基施工平台下原位拼装施工技术
CN110468816B (zh) 一种海上电气平台的滑移式安装方法及系统
KR100623201B1 (ko) 스키드 론칭시스템을 이용한 육상 선박 건조 및 진수방법
CN201065511Y (zh) 薄壁高墩用移动模架造桥机
CN102140779B (zh) 一种移动式现浇支架及箱梁现浇支架移动施工方法
CN106381870B (zh) 一种水泥深层搅拌船桩架系统及成桩方法
CN105109939B (zh) 大跨度结构片的运输工艺
CN101899904B (zh) 转炉塔楼钢结构双向吊装施工方法
CN105484162B (zh) 悬索桥施工岸上加劲梁二次荡移装置及方法
CN104805773A (zh) 施工小曲线桥的节段拼装架桥机
CN104213501B (zh) 一种斜拉式可弯折开启栈桥结构施工方法
CN103133012A (zh) 一种开敞式tbm现浇混凝土仰拱同步衬砌台车
CN204151666U (zh) 一种满足会车要求的钢栈桥
CN102337736A (zh) 海洋石油平台上部模块的安装工艺
CN102367650A (zh) 一种钢管拱桥的施工方法
CN104018426A (zh) 一种钢桁梁安装方法
CN102653938A (zh) 下行式移动模架海上拆除施工工法
CN104805857A (zh) 一种可拆卸循环利用无底钢套箱及其施工方法
CN202389580U (zh) 用于船体总段总组与巨型总段驳运的托架
CN104060543B (zh) 一种预制桥面板的安装装置
CN205329691U (zh) 一种用于水中钢管桩入岩安装的浮式装置
CN204608812U (zh) 一种可拆卸循环利用无底钢套箱
CN106400693A (zh) 一种斜坡道钢箱梁运梁车及运梁方法
CN102381438B (zh) 大型半潜船艏楼上建总段整体提拉安装方法
CN108625270A (zh) 导梁门吊安装桥梁预制箱梁施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20121212