CN102720373A - 一种建筑物移位转向方法 - Google Patents

一种建筑物移位转向方法 Download PDF

Info

Publication number
CN102720373A
CN102720373A CN2012101939253A CN201210193925A CN102720373A CN 102720373 A CN102720373 A CN 102720373A CN 2012101939253 A CN2012101939253 A CN 2012101939253A CN 201210193925 A CN201210193925 A CN 201210193925A CN 102720373 A CN102720373 A CN 102720373A
Authority
CN
China
Prior art keywords
displacement
turning
building
underpin
roller bearing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012101939253A
Other languages
English (en)
Other versions
CN102720373B (zh
Inventor
贾强
张鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Jianzhu University
Original Assignee
Shandong Jianzhu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Jianzhu University filed Critical Shandong Jianzhu University
Priority to CN201210193925.3A priority Critical patent/CN102720373B/zh
Publication of CN102720373A publication Critical patent/CN102720373A/zh
Application granted granted Critical
Publication of CN102720373B publication Critical patent/CN102720373B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明公开了一种建筑物移位转向方法,1)需要转向的建筑物,移位前浇筑制作转向前移位轨道、转向后移位轨道和转向前托换梁;2)将柱或墙与基础截断,并通过牵引或顶推设备移至转向位置;3)在转向后移位轨道上铺设钢滚轴,在钢滚轴上支撑槽钢作为底部模板浇筑制作转向后托换梁;4)将转向前托换梁下的滚轴附近的槽钢切割,将滚轴取出,建筑物荷载的传递途径由移位前托换梁、移位前滚轴、移位前轨道转变为移位后托换梁、移位后滚轴、移位后轨道;5)安装移位后的牵引或顶推设备,继续移位。本发明不需要千斤顶顶升完成滚轴调向,避免因顶升变形产生的附加内力;在转向后的轨道上铺设滚轴后制作转向后托换梁,梁底变形小,平整度高,有利于移位。

Description

一种建筑物移位转向方法
 
技术领域
本发明土木建筑技术领域,尤其是一种建筑物移位转向方法。
背景技术
目前,建筑物移位过程中,有时不能一次达到预定地点,需要通过中间转向才能成功到位。若建筑物重量较轻,采用滑块作为行走装置,只需要将牵引装置调换方向,不需要处理滑块就可顺利完成转向。而采用滚轴或滑车作为行走装置,由于滚轴或滑车只能向单一方向运动,转向问题就变得复杂。
通常的建筑物移位,在柱(墙)两侧建造移位轨道,在移位轨道上铺设钢滚轴,在钢滚轴上支撑槽钢作为底部模板浇筑制作钢筋混凝土托换梁,托换梁两侧夹住柱(墙),并与柱(墙)通过植筋等方法相连。移位前截断柱(墙)与基础的连接,建筑物上部荷载的传递途径从截断前的通过柱(或墙)、基础传至地基,变成了通过柱(或墙)、托换梁、滚轴、移位轨道传至地基。此时,建筑物变成了可移动结构,通过前方钢丝绳的牵引或后方千斤顶的顶推即可移动。
需要转向的建筑物,除了浇筑制作转向前的移位轨道和托换梁,还需要浇筑制作转向后的的移位轨道和托换梁。而转向后的托换梁如果和转向前的托换梁同时浇筑会存在以下两个问题:(1)转向后的托换梁的底部模板不可能支撑在钢滚轴上。因为此时建筑物尚未移至转向轨道,不可能在转向后的轨道上摆放滚轴。转向后的托换梁的底部模板顶撑会直接支撑在地基土上,如果地基变形大,会造成转向后的托换梁底部不平整,严重影响转向后的移位行进。(2)行至转向位置时,转向后的托换梁下的滚轴安放和转向前托换梁下的滚轴取出也较困难。
中国专利 ZL200510046654.9 公开了一种建筑物移位的转向方法,当建筑物移位至转向位置时,利用动力设备(千斤顶)支顶在上轨道梁和下轨道梁中间,使其发生弹性变形,使轨道梁中间的孔隙增大,这样就可以调整滚轴,使建筑物能够转向移位。该方法的缺点是顶升会在托换结构和上部结构中产生附加内力,严重时会造成开裂。
发明内容
本发明的目的是为克服上述现有技术的不足,提供一种建筑物移位转向方法,该方法不需要千斤顶顶升完成滚轴调向,避免因顶升变形产生的附加内力;在转向后的轨道上铺设滚轴后制作转向后的托换梁,梁底的变形很小,平整度高,有利于移位。
为实现上述目的,本发明采用下述技术方案:
一种建筑物移位转向方法,步骤如下:
1)针对需要转向的建筑物,移位前只铺设转向前托换梁下的滚轴,浇筑制作转向前托换梁、转向前移位轨道和转向后移位轨道;
2)将柱或墙与基础截断,并通过牵引或顶推设备移至转向位置;
3) 在转向后移位轨道上铺设转向后托换梁下的滚轴,在钢滚轴上支撑槽钢作为底部模板浇筑制作转向后托换梁;
4) 将转向前托换梁下的滚轴附近的槽钢切割,将转向前托换梁下的滚轴取出,此时,建筑物荷载的传递途径由移位前的转向前托换梁、转向前托换梁下的滚轴、移位前的转向前移位轨道转变为移位后的转向后托换梁、转向后托换梁下的滚轴、移位后的轨道;
5) 安装移位后的牵引或顶推设备,继续移位。
本发明的有益效果是,不需要千斤顶顶升完成滚轴调向,避免因顶升变形产生的附加内力;在转向后的轨道上铺设滚轴后制作转向后托换梁,梁底的变形很小,平整度高,有利于移位。转向前托换梁取出滚轴时有轻度破坏,但已不影响转向后的移位。
附图说明
图1 是转向前移位建筑立面图;
图2是转向后移位建筑立面图;
图3 是移位建筑托换梁的平面图;
图4 是移位轨道转向处平面图;
图中:1—转向前移位轨道;2—转向后移位轨道;3—转向前托换梁;4—转向后托换梁;5—柱或墙;6—建筑物;7—转向前托换梁下的滚轴;8——转向后托换梁下的滚轴。具体实施方式
下面结合附图和实施例对本发明进一步说明。
如图1-图4所示,一种建筑物移位转向方法,步骤如下:
1)针对需要转向的建筑物6,移位前只铺设转向前托换梁下的滚轴7,浇筑制作转向前移位轨道1、转向后移位轨道2和转向前托换梁3;
2)将柱或墙5与基础截断,并通过牵引或顶推设备移至转向位置;
3) 在转向后移位轨道2上铺设转向后托换梁下的滚轴8,在转向后托换梁下的滚轴8上支撑槽钢作为底部模板浇筑制作转向后托换梁4;
4) 将转向前托换梁下的滚轴7附近的槽钢切割,将转向前托换梁下的滚轴7取出,此时,建筑物6荷载的传递途径由移位前的转向前托换梁3、转向前托换梁下的滚轴7、转向前的转向前移位轨道1转变为移位后的转向后托换梁4、转向后托换梁下的滚轴8、转向后的轨道2;
5) 安装移位后的牵引或顶推设备,继续移位。
本发明不需要千斤顶顶升完成滚轴调向,避免因顶升变形产生的附加内力;在转向后的轨道上铺设滚轴后制作转向后托换梁,梁底的变形很小,平整度高,有利于移位。转向前托换梁取出滚轴时有轻度破坏,但已不影响转向后的移位。
上述虽然结合附图对本发明的具体实施方式进行了描述,但并非对本发明保护范围的限制,所属领域技术人员应该明白,在本发明的技术方案的基础上,本领域技术人员不需要付出创造性劳动即可做出的各种修改或变形仍在本发明的保护范围以内。

Claims (1)

1.一种建筑物移位转向方法,其特征是,步骤如下:
1)针对需要转向的建筑物,移位前只铺设转向前托换梁下的滚轴,浇筑制作转向前托换梁、转向前移位轨道和转向后移位轨道;
2)将柱或墙与基础截断,并通过牵引或顶推设备移至转向位置;
3) 在转向后移位轨道上铺设转向后托换梁下的滚轴,在钢滚轴上支撑槽钢作为底部模板浇筑制作转向后托换梁;
4) 将转向前托换梁下的滚轴附近的槽钢切割,将转向前托换梁下的滚轴取出,此时,建筑物荷载的传递途径由移位前的转向前托换梁、转向前托换梁下的滚轴、移位前的转向前移位轨道转变为移位后的转向后托换梁、转向后托换梁下的滚轴、移位后的轨道;
5) 安装移位后的牵引或顶推设备,继续移位。
CN201210193925.3A 2012-06-13 2012-06-13 一种建筑物移位转向方法 Active CN102720373B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210193925.3A CN102720373B (zh) 2012-06-13 2012-06-13 一种建筑物移位转向方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210193925.3A CN102720373B (zh) 2012-06-13 2012-06-13 一种建筑物移位转向方法

Publications (2)

Publication Number Publication Date
CN102720373A true CN102720373A (zh) 2012-10-10
CN102720373B CN102720373B (zh) 2014-08-06

Family

ID=46946224

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210193925.3A Active CN102720373B (zh) 2012-06-13 2012-06-13 一种建筑物移位转向方法

Country Status (1)

Country Link
CN (1) CN102720373B (zh)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102913000A (zh) * 2012-10-23 2013-02-06 山东建筑大学 建筑物移位开发利用地下空间的方法
CN102979317A (zh) * 2012-12-19 2013-03-20 山东建筑大学 具有双向滚轴隔震支座的建筑物移位就位方法
CN103233588A (zh) * 2013-04-18 2013-08-07 叶长青 带筏板基础建筑物的平移方法
CN106285040A (zh) * 2016-08-19 2017-01-04 山东建筑大学 利用轨道高差实现建筑物移位转向的方法
CN106320736A (zh) * 2016-08-19 2017-01-11 山东建筑大学 建筑物移位爬坡抬升转向方法
CN108999225A (zh) * 2018-07-24 2018-12-14 山东建筑大学 旋转移位砖混结构建筑物纠倾法
CN110805305A (zh) * 2019-11-12 2020-02-18 山东建筑大学 一种高层建筑物爬坡移位方法
CN113914658A (zh) * 2021-10-29 2022-01-11 山东建筑大学 一种顶管托换装置及建筑物顶升托换方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB738397A (en) * 1951-12-08 1955-10-12 Christiani & Nielsen Ets Apparatus for the transportation of loads and chiefly buildings
CN1089008A (zh) * 1993-10-09 1994-07-06 阮蔚文 建筑物搬迁方法
CN2249787Y (zh) * 1995-06-16 1997-03-19 高继良 一种建筑物整体平移装置
CN1208103A (zh) * 1998-07-16 1999-02-17 赵启 建筑物整体平移的装置和方法
CN2402764Y (zh) * 1999-01-23 2000-10-25 李海森 建筑物或构筑物整体迁移装置
CN2470461Y (zh) * 2001-02-26 2002-01-09 黄鹏 高层大型建筑整体升降转向平移装置
CN1710225A (zh) * 2005-06-09 2005-12-21 大连久鼎特种建筑工程有限公司 建筑物移位的转向方法
JP4195406B2 (ja) * 2004-03-17 2008-12-10 積水化学工業株式会社 既存建物の免震化工法および該工法により免震化された免震建物

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB738397A (en) * 1951-12-08 1955-10-12 Christiani & Nielsen Ets Apparatus for the transportation of loads and chiefly buildings
CN1089008A (zh) * 1993-10-09 1994-07-06 阮蔚文 建筑物搬迁方法
CN2249787Y (zh) * 1995-06-16 1997-03-19 高继良 一种建筑物整体平移装置
CN1208103A (zh) * 1998-07-16 1999-02-17 赵启 建筑物整体平移的装置和方法
CN2402764Y (zh) * 1999-01-23 2000-10-25 李海森 建筑物或构筑物整体迁移装置
CN2470461Y (zh) * 2001-02-26 2002-01-09 黄鹏 高层大型建筑整体升降转向平移装置
JP4195406B2 (ja) * 2004-03-17 2008-12-10 積水化学工業株式会社 既存建物の免震化工法および該工法により免震化された免震建物
CN1710225A (zh) * 2005-06-09 2005-12-21 大连久鼎特种建筑工程有限公司 建筑物移位的转向方法

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102913000A (zh) * 2012-10-23 2013-02-06 山东建筑大学 建筑物移位开发利用地下空间的方法
CN102913000B (zh) * 2012-10-23 2014-08-06 山东建筑大学 建筑物移位开发利用地下空间的方法
CN102979317A (zh) * 2012-12-19 2013-03-20 山东建筑大学 具有双向滚轴隔震支座的建筑物移位就位方法
CN103233588A (zh) * 2013-04-18 2013-08-07 叶长青 带筏板基础建筑物的平移方法
CN103233588B (zh) * 2013-04-18 2015-07-29 叶长青 带筏板基础建筑物的平移方法
CN106285040A (zh) * 2016-08-19 2017-01-04 山东建筑大学 利用轨道高差实现建筑物移位转向的方法
CN106320736A (zh) * 2016-08-19 2017-01-11 山东建筑大学 建筑物移位爬坡抬升转向方法
CN106320736B (zh) * 2016-08-19 2018-05-08 山东建筑大学 建筑物移位爬坡抬升转向方法
CN106285040B (zh) * 2016-08-19 2018-06-29 山东建筑大学 利用轨道高差实现建筑物移位转向的方法
CN108999225A (zh) * 2018-07-24 2018-12-14 山东建筑大学 旋转移位砖混结构建筑物纠倾法
CN110805305A (zh) * 2019-11-12 2020-02-18 山东建筑大学 一种高层建筑物爬坡移位方法
CN113914658A (zh) * 2021-10-29 2022-01-11 山东建筑大学 一种顶管托换装置及建筑物顶升托换方法

Also Published As

Publication number Publication date
CN102720373B (zh) 2014-08-06

Similar Documents

Publication Publication Date Title
CN102720373A (zh) 一种建筑物移位转向方法
CN106320736B (zh) 建筑物移位爬坡抬升转向方法
CN201581899U (zh) 隧道施工栈桥液压驱动步履式自行装置
CN103233867B (zh) 桩体扶正与纠偏系统
CN204457802U (zh) 一体浇筑式模板台车
CN108265618B (zh) 一种高架桥柱墩基础地下逆向增层施工方法
CN106285040B (zh) 利用轨道高差实现建筑物移位转向的方法
CN104533460A (zh) 换撑式模板台车和地下通道混凝土浇筑的施工方法
CN108999225B (zh) 旋转移位砖混结构建筑物纠倾法
CN105220720B (zh) 湿陷性黄土地区建筑物基础加固桩及其压桩施工方法
JP6382119B2 (ja) 鋼殻エレメントの発進装置及びそれを用いた鋼殻エレメントの発進方向の調整方法
JP2019094732A (ja) 移動装置および既存構造物の移動方法
CN106837346A (zh) 一种tbm步进过站施工流程
CN106939605B (zh) 一种护坡砌块的搬运设备和搬运方法
CN206127827U (zh) 散料摊铺装置
CA2529655A1 (en) Lifting construction method and raising/lowering equipment of boiler module
CN202688884U (zh) 公路架桥机后支腿行走支撑升降机构
CN207673044U (zh) 一种既有建筑的移位装置
CN203795435U (zh) 一种对撑加固结构
CN109184259B (zh) 建筑物的滑移施工技术
CN102979318A (zh) 具有滑动支座的建筑物移位和隔震就位方法
CN108316671B (zh) 通过调整滚轴直径实现建筑物移位转向的方法
CN204059197U (zh) 挂篮行走系统
CN111503367A (zh) 贯穿高速涵洞内的桁架管道安装方法
CN201212122Y (zh) 一种轮式陆地移动钻机轨道底座

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant