CN102345273B - 连续刚构桥施工挂篮的同步移篮装置 - Google Patents

连续刚构桥施工挂篮的同步移篮装置 Download PDF

Info

Publication number
CN102345273B
CN102345273B CN201010243305.7A CN201010243305A CN102345273B CN 102345273 B CN102345273 B CN 102345273B CN 201010243305 A CN201010243305 A CN 201010243305A CN 102345273 B CN102345273 B CN 102345273B
Authority
CN
China
Prior art keywords
sliding beam
outer sliding
hanging basket
external sliding
cradle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201010243305.7A
Other languages
English (en)
Other versions
CN102345273A (zh
Inventor
吴彪
余甦
吴旭东
官辉国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Changda Highway Engineering Co Ltd
Original Assignee
Guangdong Changda Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Changda Highway Engineering Co Ltd filed Critical Guangdong Changda Highway Engineering Co Ltd
Priority to CN201010243305.7A priority Critical patent/CN102345273B/zh
Publication of CN102345273A publication Critical patent/CN102345273A/zh
Application granted granted Critical
Publication of CN102345273B publication Critical patent/CN102345273B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种连续刚构桥施工挂篮的同步移篮装置,包括主桁架、主桁架前端的横梁、固定在桥面的纵移轨道、外滑梁、挂篮主体和锚固在混凝土的外滑梁滑梁架,外滑梁的前端与横梁的吊杆铰接,另一端承接在外滑梁滑梁架的滚轮上,在外滑梁的后端、外滑梁与吊杆铰接处及横梁上均安装有转向滑轮,在已浇筑梁段设有预埋环,钢丝绳固定在外滑梁滑梁架底部中间位置,然后向后绕过外滑梁尾部的转向滑轮,再向前绕过外滑梁前端的转向滑轮,继续向上绕过横梁上的转向滑轮,最终通过手拉葫芦固定在前一段已浇筑的箱梁混凝土预埋环上;本发明能够同步移动挂篮主体的前端和后端以及翼板、侧模和底篮、操作方便、安全。

Description

连续刚构桥施工挂篮的同步移篮装置
技术领域
    本发明涉及刚构桥的施工设备,尤其是一种连续刚构桥施工挂蓝的同步移动装置。
背景技术
   连续刚构桥是目前大跨径混凝土桥梁最常用的桥型之一,具有场地适应性强、跨越能力大,正常情况下后期维护费用低的优势而被广泛使用。
   目前,现有的桥梁施工用挂篮,尤其是连续刚构桥施工用挂篮,其主要包括桥面主桁、横梁、外滑梁、纵移轨道、外滑梁滑梁架和挂篮主体,外滑梁的前端与横梁的吊杆铰接,另一端承接在外滑梁滑梁架的滚轮上。另外挂篮主体的前端与横梁吊杆连接,后端与悬吊在外滑梁的后吊杆连接。移篮时,在移动桥面主桁的同时,需要人工在桥面下挂篮上通过拉动绕过外滑梁后端转向滑轮并固定在外滑梁悬吊轮吊杆下面的钢丝绳,以达到推动外滑梁前进的目的,该种移动外滑梁的方式,很难控制外滑梁与桥面主桁同步前进,造成移篮的困难,同时人工在桥面以下操作危险性高,外侧模系统难以与整个挂篮同步前进,造成移篮困难,同时坠落事故经常发生,危险性高。
发明内容
本发明的目的在于提供一种能够同步移动挂篮主体的前端和后端、操作安全的连续刚构桥施工挂篮的同步移篮装置。
为实现上述目的,本发明所采用的技术方案是:一种连续刚构桥施工挂篮的同步移篮装置,包括主桁架、主桁架前端的横梁、固定在桥面的纵移轨道、外滑梁、挂篮主体和锚固在混凝土的外滑梁滑梁架,主桁架固定在纵移轨道上,外滑梁的前端与横梁的吊杆铰接,另一端承接在外滑梁滑梁架的滚轮上,挂篮主体的前端与吊杆的下端铰接,挂篮主体的后端通过后吊杆悬吊在外滑梁上,在外滑梁的后端、外滑梁与吊杆铰接处及横梁上均安装有转向滑轮,在已浇筑梁段设有预埋环,钢丝绳固定在外滑梁滑梁架底部中间位置,然后向后绕过外滑梁尾部的转向滑轮,再向前绕过外滑梁前端的转向滑轮,继续向上绕过横梁上的转向滑轮,最终固定在前一段已浇筑的箱梁混凝土预埋环上。
所述外滑梁后端的转向滑轮有两个,它们在同一竖直线上。
所述吊杆和后吊杆上均设有长度调节孔,可调节吊杆、后吊杆的长度,以适应不用厚度箱梁的浇筑。
所述主桁架的底部设有与纵移轨道相配合的移动轮。
所述主桁架下部设有可推动主桁架纵向移动的液压千斤顶。
本发明采用上述结构后,通过在外滑梁的后端、外滑梁与吊杆铰接处及横梁上设置转向滑轮,在已浇筑梁段设有预埋环,钢丝绳固定在外滑梁滑梁架底部中间位置,然后向后绕过外滑梁尾部的转向滑轮,再向前绕过外滑梁前端的转向滑轮,继续向上绕过前上横梁上的转向滑轮,最终固定在前一段已浇筑的箱梁混凝土预埋环上;因此,前移主桁架时,绕在横梁转向滑轮的钢丝绳也向前移动,则钢丝绳同时产生一个后拉力拉住外滑梁滑梁架使之保持垂直状态,防止其随挂篮主体的外侧模向前移动而折损外滑梁滑梁架,同时通过这条钢丝绳对外滑梁提供向前的动力,达到使外滑梁与主桁架同步前进,使挂篮主体的前端和后端同步移动目的,避免了吊杆折损;避免了人工到桥面以下推动外滑梁前进,大大提高了移篮的安全性。
附图说明
下面结合附图和具体实施方式对本发明作进一步详细说明。
图1为本发明结构图。
图中:1主桁架,101移动轮,102液压千斤顶,2横梁, 3纵移轨道,4外滑梁,5挂篮主体,6外滑梁滑梁架,601滚轮,7吊杆,8后吊杆,9、10、11转向滑轮,12预埋环,13钢丝绳,14手拉葫芦,15长度调节孔。
具体实施方式
图1所示,本发明的连续刚构桥施工挂篮的同步移篮装置,包括主桁架1、主桁架1前端的横梁2、固定在桥面的纵移轨道3、外滑梁4、挂篮主体5和锚固在混凝土的外滑外滑梁滑梁架6,主桁架1固定在纵移轨道3上,外滑梁4的前端与横梁2的吊杆7铰接,另一端承接在外滑梁滑梁架6的滚轮601上,挂篮主体5的前端与吊杆7下端铰接,挂篮主体5的后端通过后吊杆8悬吊在外滑梁4上,本技术方案中,在外滑梁4的后端安装有转向滑轮9,在外滑梁4与吊杆7铰接处装有转向滑轮10,横梁2上安装有转向滑轮11,在已浇筑梁段固定有预埋环12,钢丝绳13固定在外滑梁滑梁架底部中间位置,然后向后绕过外滑梁4尾部的转向滑轮9,再向前绕过外滑梁4前端的转向滑轮10,继续向上绕过横梁2上的转向滑轮11,最终固定在前一段已浇筑的箱梁混凝土预埋环12上。所述外滑梁4后端的转向滑轮9为两个,它们设在同一竖直线上。在吊杆7和后吊杆8上均设有长度调节孔15,可调节吊杆、后吊杆的长度,以适应不用厚度箱梁的浇筑。所述主桁架1的底部设有与纵移轨道3相配合的移动轮101。在主桁架1下部设有可推动主桁架1纵向移动的液压千斤顶102。移动挂篮时,松开主桁架1的固定螺栓,主桁架前移,同时绕在横梁2转向滑轮11的钢丝绳13也向前移动,则钢丝绳13同时产生一个后拉力拉住外滑梁滑梁架6使之保持垂直状态,防止其随挂篮主体5的外侧模向前移动而折损外滑梁滑梁架6,同时通过这条钢丝绳13对外滑梁4提供向前的动力,达到使外滑梁4与主桁架1同步前进,使挂篮主体1的前端和后端同步移动目的,避免了吊杆7折损;避免了人工到桥面以下推动外滑梁4前进的危险性,大大提高了移篮的安全性。

Claims (5)

1.一种连续刚构桥施工挂篮的同步移篮装置,包括主桁架(1)、主桁架(1)前端的横梁(2)、固定在桥面的纵移轨道(3)、外滑梁(4)、挂篮主体(5)和锚固在混凝土的外滑梁滑梁架(6),主桁架(1)固定在纵移轨道(3)上,外滑梁(4)的前端与横梁(2)的吊杆(7)铰接,另一端承接在外滑梁滑梁架(6)的滚轮(601)上,挂篮主体(5)的前端与吊杆(7)的下端铰接,挂篮主体(5)的后端通过后吊杆(8)悬吊在外滑梁(4)上,其特征在于:在外滑梁(4)的后端、外滑梁(4)与吊杆(7)铰接处及横梁(2)上安装有转向滑轮(9、10、11),在已浇筑梁段设有预埋环(12),钢丝绳(13)固定在外滑梁滑梁架(6)底部中间位置,然后向后绕过外滑梁(4)尾部的转向滑轮(9),再向前绕过外滑梁(4)前端的转向滑轮(10),继续向上绕过横梁(2)上的转向滑轮(11),最终通过手拉葫芦(14)固定在前一段已浇筑的箱梁混凝土预埋环(12)上。
2.根据权利要求1所述的连续刚构桥施工挂篮的同步移篮装置,其特征在于:所述外滑梁(4)后端的转向滑轮(9)有两个,它们在同一竖直线上。
3.根据权利要求1所述的连续刚构桥施工挂篮的同步移篮装置,其特征在于:所述吊杆(7)和后吊杆(8)上均设有长度调节孔(15)。
4.根据权利要求1所述的连续刚构桥施工挂篮的同步移篮装置,其特征在于:所述主桁架(1)的底部设有与纵移轨道(3)相配合的移动轮(101)。
5.根据权利要求1所述的连续刚构桥施工挂篮的同步移篮装置,其特征在于:所述主桁架(1)下部设有可推动主桁架(1)纵向移动的液压千斤顶(102)。
CN201010243305.7A 2010-08-02 2010-08-02 连续刚构桥施工挂篮的同步移篮装置 Active CN102345273B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010243305.7A CN102345273B (zh) 2010-08-02 2010-08-02 连续刚构桥施工挂篮的同步移篮装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010243305.7A CN102345273B (zh) 2010-08-02 2010-08-02 连续刚构桥施工挂篮的同步移篮装置

Publications (2)

Publication Number Publication Date
CN102345273A CN102345273A (zh) 2012-02-08
CN102345273B true CN102345273B (zh) 2015-04-15

Family

ID=45544317

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010243305.7A Active CN102345273B (zh) 2010-08-02 2010-08-02 连续刚构桥施工挂篮的同步移篮装置

Country Status (1)

Country Link
CN (1) CN102345273B (zh)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103306212B (zh) * 2013-06-28 2015-08-26 上海申伸强建设有限公司 可多向转动的挂篮行走后悬挂结构及其应用方法
CN106958345B (zh) * 2017-05-16 2022-08-02 简华炽 一种可调节刚性挂篮
CN116065537A (zh) * 2021-11-24 2023-05-05 中建筑港集团有限公司 一种连续工作型阻水密封装置的使用方法
CN114775428A (zh) * 2022-03-30 2022-07-22 苏武 智能控制电动葫芦移动挂蓝的行走装置及施工方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1916289A (zh) * 2006-08-28 2007-02-21 杨秋利 菱形桁架式挂篮
JP2008038449A (ja) * 2006-08-04 2008-02-21 Sumitomo Mitsui Construction Co Ltd 橋桁の構築方法
CN201109899Y (zh) * 2007-08-30 2008-09-03 中铁大桥局集团第一工程有限公司 下滑梁式施工挂篮
CN201169749Y (zh) * 2008-03-26 2008-12-24 中铁四局集团有限公司 简装销接三角形挂篮
JP2009057685A (ja) * 2007-08-29 2009-03-19 Sumitomo Mitsui Construction Co Ltd 移動吊支保工
CN201250384Y (zh) * 2008-08-29 2009-06-03 山东黄河工程集团有限公司 一种挂篮
CN201473889U (zh) * 2009-06-12 2010-05-19 中铁二十二局集团第一工程有限公司 斜拉三角挂篮
CN201770945U (zh) * 2010-08-02 2011-03-23 广东省长大公路工程有限公司 连续刚构桥施工挂篮的同步移篮装置

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008038449A (ja) * 2006-08-04 2008-02-21 Sumitomo Mitsui Construction Co Ltd 橋桁の構築方法
CN1916289A (zh) * 2006-08-28 2007-02-21 杨秋利 菱形桁架式挂篮
JP2009057685A (ja) * 2007-08-29 2009-03-19 Sumitomo Mitsui Construction Co Ltd 移動吊支保工
CN201109899Y (zh) * 2007-08-30 2008-09-03 中铁大桥局集团第一工程有限公司 下滑梁式施工挂篮
CN201169749Y (zh) * 2008-03-26 2008-12-24 中铁四局集团有限公司 简装销接三角形挂篮
CN201250384Y (zh) * 2008-08-29 2009-06-03 山东黄河工程集团有限公司 一种挂篮
CN201473889U (zh) * 2009-06-12 2010-05-19 中铁二十二局集团第一工程有限公司 斜拉三角挂篮
CN201770945U (zh) * 2010-08-02 2011-03-23 广东省长大公路工程有限公司 连续刚构桥施工挂篮的同步移篮装置

Also Published As

Publication number Publication date
CN102345273A (zh) 2012-02-08

Similar Documents

Publication Publication Date Title
CN107059640B (zh) 用于预制节段梁逐跨施工的架桥机及其施工方法
CN104631335B (zh) 大吨位架桥机及其施工方法
CN201770945U (zh) 连续刚构桥施工挂篮的同步移篮装置
CN107725078B (zh) 一种采面顺槽循环自移超前支护系统及轨道自移系统
CN201003145Y (zh) 上行自行式移动模架
CN109653105B (zh) 箱梁桥悬臂施工挂篮主桁系统及其使用方法
CN101250856B (zh) 梯形挂篮及其施工方法
CN105421249A (zh) 一种拖吊结合式新型挂篮结构及施工方法
CN102345273B (zh) 连续刚构桥施工挂篮的同步移篮装置
RU2381326C1 (ru) Устройство для подъема и монтажа блоков пролетного строения
CN103998690A (zh) 自行式可移动模架系统
CN107747282B (zh) 上跨既有线旧桥梁体整体拆除方法
CN201400500Y (zh) 异型高耸建筑施工用带平台式多功能升降机
CN106593469A (zh) 一种用于仰拱施工的台车
CN215252400U (zh) 一种波形钢腹板施工自承式同步吊架系统
CN103866699A (zh) 无轨道式行走挂篮
CN207987749U (zh) 骑索式桥面吊机
CN105735142A (zh) 一种用于预应力混凝土桥梁预制节段逐跨拼装施工的架桥机
CN102926330B (zh) 一种适用于桥梁施工用挂蓝的安装方法
CN205975365U (zh) 现浇箱梁复合式移动模架
CN108086168A (zh) 骑索式桥面吊机
CN202416190U (zh) 后浇翼缘板的预制箱梁模架
CN103061262B (zh) 一种跨缆吊机及其应用方法
CN207551862U (zh) 一种皮带卷卸载装置
CN111042004A (zh) 一种挂篮轨道梁走行方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant