CN102094392A - Lower supported hanging basket in bridge construction and application thereof - Google Patents

Lower supported hanging basket in bridge construction and application thereof Download PDF

Info

Publication number
CN102094392A
CN102094392A CN 201110051329 CN201110051329A CN102094392A CN 102094392 A CN102094392 A CN 102094392A CN 201110051329 CN201110051329 CN 201110051329 CN 201110051329 A CN201110051329 A CN 201110051329A CN 102094392 A CN102094392 A CN 102094392A
Authority
CN
China
Prior art keywords
hanging basket
chord
upper chord
top rail
suspension rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 201110051329
Other languages
Chinese (zh)
Other versions
CN102094392B (en
Inventor
梁超
张宏斌
李彬
李波
杨真
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Engineering Co Ltd of CTCE Group
Original Assignee
First Engineering Co Ltd of CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Engineering Co Ltd of CTCE Group filed Critical First Engineering Co Ltd of CTCE Group
Priority to CN 201110051329 priority Critical patent/CN102094392B/en
Publication of CN102094392A publication Critical patent/CN102094392A/en
Application granted granted Critical
Publication of CN102094392B publication Critical patent/CN102094392B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a lower supported hanging basket in bridge construction and application thereof. The invention is characterized in that: the lower supported hanging basket is provided with two primary trusses having inverted trapezoidal structures, and an upper chord shoring jack is arranged between the tail of an upper chord and the bottom surface of a box girder edge board; an upper rear suspender is arranged between the middle of the upper chord and an upper rear crossbeam; the front end of the upper chord is connected with an upper front crossbeam; a lower rear suspender is arranged between the middle of a lower chord and a lower rear crossbeam; the upper front crossbeam is connected with a lower front crossbeam through a front suspender; parallelly arranged bottom basket longitudinal beams are fixedly connected between the lower front crossbeam and the lower rear crossbeam; and a hanging basket bottom die is fixedly arranged on the bottom basket longitudinal beams, and hanging basket side dies are positioned on the inner side of the two primary trusses. The hanging basket travelling mode is improved, a bound framework of steel reinforcement can be integrally hoisted into a bottom die platform space and directly subjected to concreting operation, and the construction period is shortened.

Description

Lower support type Hanging Basket and application thereof in the bridge construction
Technical field
The present invention relates to cradle structure and application thereof in a kind of bridge construction.
Background technology
In bridge construction, Hanging Basket is to be used to have current the requirement and the relatively poor cast-in-place a kind of device of large-span concrete bridge cantilever of foundation condition.
Cradle structure commonly used at present comprises deck type triangle hanging basket, Diamond-Shape Form Traveler, bowstring type Hanging Basket and hybrid Hanging Basket or the like, and the Hanging Basket of these existing forms all is arranged on the top of beam body.The concreting state of various Hanging Baskets is similar with the suffered force mode of Hanging Basket walking states, be to guarantee stability in the cradle construction process, and is must pre-buried fining twisted steel on casting beams body heavy as back anchor or load balance.When hanging blue traveling anti-bearing, glide path and the glide path anchor bar of drawing must be set, wherein, the anti-bearing that draws passes to the beam body of having built by glide path and glide path anchor bar with pulling force, and the glide path anchor bar is clouded on the slideway of all box girder segments.Bottom die platform and external mold are hung traveling on the sliding outside beam, and the length of sliding beam must be built sections above two outward.Mainly there is following problem in this traditional deck type Hanging Basket in construction:
Need the fining twisted steel of pre-buried a greater number when 1, constructing, these built-in fittings are embedded in the case beam and can't reclaim, and cause waste of material;
2, the pre-buried required precision of glide path anchor bar is higher, and the utilization rate again of slideway is extremely low;
3, anti-setting of drawing bearing is comparatively complicated, uneconomical;
4, the space at beam body top is subjected to the restriction of deck type main truss cradle shelf structure, make beam body cage of reinforcement can only be according to the conventional method on bottom die platform the scene advance colligation, operation easier is big, influences the duration;
5, the deck type Hanging Basket moves slowly, must draw bearing to cooperate repeatedly to finish by counter in the process out of shape, time-consumingly takes a lot of work again;
Summary of the invention
The present invention is for avoiding above-mentioned existing in prior technology weak point, provide a kind of can improve Hanging Basket mode out of shape, and can will finish the cage of reinforcement integral body of colligation hang in and directly carry out the concreting operation in the bottom die platform space, with lower support type Hanging Basket and the application thereof in the bridge construction of reduction of erection time.
Technical solution problem of the present invention adopts following technical scheme:
The design feature of the lower support type Hanging Basket in the bridge construction of the present invention is:
Have two and fall trapezoidal main couple, by upper chord, lower chord, be connected between upper chord and the lower chord montant to and brace constitute; At the afterbody of described upper chord and between the bottom surface of casting beams section box beam flange plate upper chord is set and shores jack, and a pair of bottom surface with the described section of casting beams box beam flange plate is set is the road wheel of supporting surface; Between the middle part of described upper chord and back top rail, the back upper hanger is set; The front end of described upper chord is connected with preceding top rail; Between the middle part of described lower chord and back lower transverse beam, suspension rod under the back is set; Before described between top rail and the preceding lower transverse beam before suspension rod be connected;
At described back top rail and between the end face of casting beams section cushion block has been set;
Each end basket longeron that be arranged in parallel is fixedly connected between described preceding lower transverse beam and the back lower transverse beam; The Hanging Basket bed die is fixedly installed on the end basket longeron, and the Hanging Basket side form is positioned at the inboard of described main couple.
It is to carry out according to the following procedure that the present invention uses the characteristics that the lower support type Hanging Basket carries out the method for beam structure construction:
A, carry out the assembly unit of all members of the lower support type Hanging Basket except back top rail and back upper hanger outside the venue, lift to continuous beam " 0 " number piece position after finishing assembly unit, carry out bolt with the back top rail of independent hoisted in position separately at the middle part of upper chord, between upper chord and back top rail, the back upper hanger is installed;
B, regulate back upper hanger, the back length of suspension rod and preceding suspension rod down respectively, what make the lower support type Hanging Basket is in continuous beam " 1 " number piece position, finishes the adjustment of lower support type Hanging Basket;
C, continuous beam " 1 " number piece cage of reinforcement integral hoisting that will finish colligation outside the venue are in place in finishing the lower support type Hanging Basket of adjustment, continuous beam " 1 " number piece cage of reinforcement that hangs in is connected with the reinforcing bar of continuous beam " 0 " number piece end, on the Hanging Basket bed die,, finish the setting of the template in the Hanging Basket by bowl button stent support internal mold;
D, in template concreting, treat after the strong stretch-draw mud jacking such as concrete that suspension rod and back upper hanger carry out the demoulding down by regulating preceding suspension rod, back; Remove the back upper hanger after the demoulding, regulate upper chord and shore jack road wheel is supported on the bottom surface of casting beams section box beam flange plate, be arranged on the back top rail and the cushion block between the end face of casting beams section be replaced by the universal wheel that can walk;
E, by leading chain block traction back top rail, make Hanging Basket move to next sections of continuous beam, described universal wheel is replaced by cushion block again, and the adjusting upper chord is shored jack breaks away from again to the support of the bottom surface of casting beams section box beam flange plate road wheel, and the back upper hanger is installed;
F, repeating said steps b-f are until the construction of finishing beam structure.
Compared with the prior art, beneficial effect of the present invention is embodied in:
1, the present invention can hang in the cage of reinforcement integral body of finishing colligation in the bottom die platform space by the mode out of shape of improving Hanging Basket, directly carries out the concreting operation, has shortened the site operation cycle greatly.
2, the present invention has selected more rational force way, and stressed clear and definite, simple in structure, the recycling rate of waterused of each working stage of Hanging Basket improves, greatly economization embedded bar material and default operation.
3, the present invention utilizes the upper space of lower support type Hanging Basket, the space of whole cage of reinforcement hoisted in position is provided, its method is simple and reliable, the case beam concrete segment of having built provides the space for the colligation of beam body cage of reinforcement, utilize the synchronism of tie with reinforcing bar and concrete construction and Hanging Basket walking, shorten the construction period.
4, the present invention is according to lower support type Hanging Basket Move Mode, and Hanging Basket is out of shape more stable, and state out of shape no longer becomes the principal element of restriction Hanging Basket safety, has also shortened the Hanging Basket travel time simultaneously.
Description of drawings
Fig. 1 is a lower support type Hanging Basket of the present invention front face;
Fig. 2 is a lower support type Hanging Basket side view of the present invention;
Fig. 3 is a lower support type Hanging Basket plan view of the present invention;
Number in the figure: top rails, 6 back lower transverse beams, 7 backs suspension rods, 10 end basket longerons, 11 Hanging Basket bed dies, 12 Hanging Basket side forms, 13 cushion blocks, 14 casting beams section, 15 casting beams section box beam flange plate, 16 road wheels before the lower transverse beams, 9 before the suspension rod, 8 down before 1 upper chord, 2 lower chords, 3 back top rails, the 4 back upper hangers, 5.
The specific embodiment
Referring to Fig. 1, Fig. 2 and Fig. 3, the form of structure of lower support type Hanging Basket is in the present embodiment:
Lower support type Hanging Basket in the bridge construction in the present embodiment has two and falls trapezoidal main couple, by upper chord 1, lower chord 2, be connected between upper chord 1 and the lower chord 2 montant to and brace constitute; At the afterbody of upper chord 1 and between the bottom surface of casting beams section box beam flange plate 15 upper chord is set and shores jack, and the road wheel 16 that a pair of bottom surface with box beam flange plate is set is supporting surface; Between the middle part of upper chord 1 and back top rail 3, back upper hanger 4 is set; The front end of upper chord 1 is connected with preceding top rail 5; Between the middle part of lower chord 2 and back lower transverse beam 6, suspension rod 7 under the back is set; Suspension rod 9 is connected before between preceding top rail 5 and preceding lower transverse beam 8;
At back top rail 3 and between the end face of casting beams section 14 cushion block 13 has been set;
Each end basket longeron 10 that be arranged in parallel is fixedly connected between preceding lower transverse beam 8 and the back lower transverse beam 6; Hanging Basket bed die 11 is fixedly installed on the end basket longeron 10, and Hanging Basket side form 12 is positioned at the inboard of main couple.
In concrete the enforcement,, can be set to screw rod by each suspension rod, on the position of correspondence, jack is set respectively, adjust the lifting length of screw rod with jack in order to adjust the length of each suspension rod.
Work progress:
1, carries out the assembly unit of all members of the lower support type Hanging Basket except back top rail 3 and back upper hanger 4 outside the venue, lift to continuous beam " 0 " number piece position after finishing assembly unit, carry out bolt with the back top rail 3 of independent hoisted in position separately at the middle part of upper chord 1, between upper chord 1 and back top rail 3, back upper hanger 4 is installed;
2, regulate back upper hanger 4, the back length of suspension rod 7 and preceding suspension rod 9 down respectively, what make the lower support type Hanging Basket is in continuous beam " 1 " number piece position, finishes the adjustment of lower support type Hanging Basket;
3, it is in place in finishing the lower support type Hanging Basket of adjustment to finish continuous beam " 1 " number piece cage of reinforcement integral hoisting of colligation outside the venue, continuous beam " 1 " number piece cage of reinforcement that hangs in is connected with the reinforcing bar of continuous beam " 0 " number piece end, on Hanging Basket bed die 11,, finish the setting of the template in the Hanging Basket by bowl button stent support internal mold; Cage of reinforcement can carry out colligation on the beam section 14 of having built;
4, concreting in template is treated after the strong stretch-draw mud jacking such as concrete, and suspension rod 7 and back upper hanger 4 carry out the demoulding down by suspension rod 9, back before regulating; Remove back upper hanger 4 after the demoulding, regulate upper chord and shore jack road wheel 16 is supported on the bottom surface of casting beams section box beam flange plate 15, the cushion block 13 that will be arranged between the end face of back top rail 3 and continuous beam " 0 " number piece is replaced by the universal wheel that can walk; Continuous beam " 0 " number piece is casting beams section 14;
5, by leading chain block traction back top rail 3, make Hanging Basket move to next sections of continuous beam, universal wheel is replaced by cushion block 13 again, and the adjusting upper chord is shored jack breaks away from again to the support of the bottom surface of casting beams section box beam flange plate 15 road wheel 16, and back upper hanger 4 is installed;
6, repeating step 2-6 is until the construction of finishing beam structure.

Claims (2)

1. the lower support type Hanging Basket in the bridge construction is characterized in that:
Have two and fall trapezoidal main couple, by upper chord (1), lower chord (2), be connected between upper chord (1) and the lower chord (2) montant to and brace constitute; At the afterbody of described upper chord (1) and between the bottom surface of casting beams section box beam flange plate (15) upper chord is set and shores jack, and the road wheel (16) that a pair of bottom surface with the described section of casting beams box beam flange plate (15) is set is supporting surface; Back upper hanger (4) is set between the middle part of described upper chord (1) and back top rail (3); The front end of described upper chord (1) is connected with preceding top rail (5); Between the middle part of described lower chord (2) and back lower transverse beam (6), suspension rod (7) under the back is set; Suspension rod (9) is connected before between top rail before described (5) and the preceding lower transverse beam (8);
At described back top rail (3) and between the end face of casting beams section (14) cushion block (13) has been set;
Each end basket longeron (10) that be arranged in parallel is fixedly connected between described preceding lower transverse beam (8) and the back lower transverse beam (6); Hanging Basket bed die (11) is fixedly installed on the end basket longeron (10), and Hanging Basket side form (12) is positioned at the inboard of described main couple.
2. an application rights requires 1 described lower support type Hanging Basket to carry out the method for beam structure construction, it is characterized in that carrying out according to the following procedure:
A, carry out outside the venue except back top rail (3) and the assembly unit of all members of the lower support type Hanging Basket the upper hanger (4) afterwards, lift to continuous beam " 0 " number piece position after finishing assembly unit, carry out bolt with the back top rail (3) of independent hoisted in position separately at the middle part of upper chord (1), back upper hanger (4) is installed between upper chord (1) and back top rail (3);
B, regulate back upper hanger (4), the back length of suspension rod (7) and preceding suspension rod (9) down respectively, what make the lower support type Hanging Basket is in continuous beam " 1 " number piece position, finishes the adjustment of lower support type Hanging Basket;
C, continuous beam " 1 " number piece cage of reinforcement integral hoisting that will finish colligation outside the venue are in place in finishing the lower support type Hanging Basket of adjustment, continuous beam " 1 " number piece cage of reinforcement that hangs in is connected with the reinforcing bar of continuous beam " 0 " number piece end, go up by bowl button stent support internal mold at Hanging Basket bed die (11), finish the setting of the template in the Hanging Basket;
D, in template concreting, treat after the strong stretch-draw mud jacking such as concrete, by regulate preceding suspension rod (9), back down suspension rod (7) and afterwards upper hanger (4) carry out the demoulding; Remove back upper hanger (4) after the demoulding, regulate upper chord and shore jack road wheel (16) is supported on the bottom surface of casting beams section box beam flange plate (15), will be arranged on back top rail (3) and the cushion block (13) between the end face of casting beams section (14) be replaced by the universal wheel that can walk;
E, by leading chain block traction back top rail (3), make Hanging Basket move to next sections of continuous beam, described universal wheel is replaced by cushion block (13) again, the adjusting upper chord is shored jack breaks away from again to the support of the bottom surface of casting beams section box beam flange plate (15) road wheel (16), and back upper hanger (4) is installed;
F, repeating said steps b-f are until the construction of finishing beam structure.
CN 201110051329 2011-03-03 2011-03-03 Lower supported hanging basket in bridge construction and application thereof Active CN102094392B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110051329 CN102094392B (en) 2011-03-03 2011-03-03 Lower supported hanging basket in bridge construction and application thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110051329 CN102094392B (en) 2011-03-03 2011-03-03 Lower supported hanging basket in bridge construction and application thereof

Publications (2)

Publication Number Publication Date
CN102094392A true CN102094392A (en) 2011-06-15
CN102094392B CN102094392B (en) 2012-05-02

Family

ID=44127643

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110051329 Active CN102094392B (en) 2011-03-03 2011-03-03 Lower supported hanging basket in bridge construction and application thereof

Country Status (1)

Country Link
CN (1) CN102094392B (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102605720A (en) * 2012-03-30 2012-07-25 中铁四局集团第一工程有限公司 Integrated construction equipment for binding and lifting continuous beam steel reinforcement framework and construction method
CN102653937A (en) * 2012-05-10 2012-09-05 中铁四局集团第一工程有限公司 Concrete construction template bracket for high speed rotary road of automobile test field and construction method
CN103774557A (en) * 2014-01-22 2014-05-07 中铁大桥局股份有限公司 Variable-width movable construction platform
CN104762882A (en) * 2015-04-16 2015-07-08 天津城建大学 Bridge segment lifting device and method
CN106223208A (en) * 2016-09-18 2016-12-14 中国铁建大桥工程局集团有限公司 A kind of large overhanging beam anti-high wind flow-guiding type hanging basket formwork of construction
CN108867406A (en) * 2018-06-14 2018-11-23 中铁三局集团有限公司 A kind of construction method for being applicable in base-supporting Hanging Basket closure segment and quickly positioning
CN110067211A (en) * 2019-04-23 2019-07-30 中建市政工程有限公司 A kind of bridge flange plate stripper apparatus and its construction method
CN110117934A (en) * 2019-04-12 2019-08-13 北京市政建设集团有限责任公司 A kind of bridge hanging basket template and its installation method
CN111576248A (en) * 2020-05-29 2020-08-25 中铁七局集团有限公司 Dismantling method for cantilever cast-in-situ beam hanging basket system
CN113338168A (en) * 2021-06-24 2021-09-03 中交二航局第四工程有限公司 Cantilever beam construction is with hanging basket with high security
CN113358470A (en) * 2021-06-04 2021-09-07 山东理工大学 Out-of-plane stable single steel truss test model
CN113863167A (en) * 2021-10-22 2021-12-31 中建三局集团有限公司 Descending type suspension casting hanging basket and construction method thereof
CN114892536A (en) * 2022-06-27 2022-08-12 广州市市政集团有限公司 A walking structure for hanging No. one outside template of pouring box girder

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10019050C1 (en) * 2000-04-18 2001-11-29 Matthias Braun Platform for building bridges, has a central section for preparing a sandwich panel base, which comprises a front platform for assembling steel sections and rear platform for fitting cantilever components
CN2486597Y (en) * 2001-08-06 2002-04-17 湖南省公路桥梁建设总公司 Construction hanging basket for building
CN2597531Y (en) * 2002-11-21 2004-01-07 广东省长大公路工程有限公司第一分公司 Single rope face tracting rope hanging cage
EP1378608A1 (en) * 2002-07-05 2004-01-07 VSL International AG Method for preparation of reciprocal pressing surfaces of segments of a construction
CN200967931Y (en) * 2006-08-23 2007-10-31 四川路桥建设股份有限公司 Side-truss cradle for suspension pouring arch-type bridge
CN201065513Y (en) * 2007-06-06 2008-05-28 宏润建设集团股份有限公司 Beret truss type hanging basket
CN201972099U (en) * 2011-03-03 2011-09-14 中铁四局集团第一工程有限公司 Through type hanging basket in bridge construction

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10019050C1 (en) * 2000-04-18 2001-11-29 Matthias Braun Platform for building bridges, has a central section for preparing a sandwich panel base, which comprises a front platform for assembling steel sections and rear platform for fitting cantilever components
CN2486597Y (en) * 2001-08-06 2002-04-17 湖南省公路桥梁建设总公司 Construction hanging basket for building
EP1378608A1 (en) * 2002-07-05 2004-01-07 VSL International AG Method for preparation of reciprocal pressing surfaces of segments of a construction
CN2597531Y (en) * 2002-11-21 2004-01-07 广东省长大公路工程有限公司第一分公司 Single rope face tracting rope hanging cage
CN200967931Y (en) * 2006-08-23 2007-10-31 四川路桥建设股份有限公司 Side-truss cradle for suspension pouring arch-type bridge
CN201065513Y (en) * 2007-06-06 2008-05-28 宏润建设集团股份有限公司 Beret truss type hanging basket
CN201972099U (en) * 2011-03-03 2011-09-14 中铁四局集团第一工程有限公司 Through type hanging basket in bridge construction

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102605720A (en) * 2012-03-30 2012-07-25 中铁四局集团第一工程有限公司 Integrated construction equipment for binding and lifting continuous beam steel reinforcement framework and construction method
CN102605720B (en) * 2012-03-30 2013-12-11 中铁四局集团第一工程有限公司 Integrated construction equipment for binding and lifting continuous beam steel reinforcement framework and construction method
CN102653937A (en) * 2012-05-10 2012-09-05 中铁四局集团第一工程有限公司 Concrete construction template bracket for high speed rotary road of automobile test field and construction method
CN102653937B (en) * 2012-05-10 2014-05-07 中铁四局集团第一工程有限公司 Concrete construction template bracket for high speed rotary road of automobile test field and construction method
CN103774557A (en) * 2014-01-22 2014-05-07 中铁大桥局股份有限公司 Variable-width movable construction platform
CN103774557B (en) * 2014-01-22 2015-11-18 中铁大桥局集团有限公司 A kind of luffing packaged type operation platform
CN104762882A (en) * 2015-04-16 2015-07-08 天津城建大学 Bridge segment lifting device and method
CN104762882B (en) * 2015-04-16 2016-06-15 天津城建大学 Bridge subsection hanging apparatus and hanging method
CN106223208A (en) * 2016-09-18 2016-12-14 中国铁建大桥工程局集团有限公司 A kind of large overhanging beam anti-high wind flow-guiding type hanging basket formwork of construction
CN106223208B (en) * 2016-09-18 2017-10-31 中国铁建大桥工程局集团有限公司 A kind of anti-high wind flow-guiding type hanging basket formwork of large overhanging beam construction
CN108867406A (en) * 2018-06-14 2018-11-23 中铁三局集团有限公司 A kind of construction method for being applicable in base-supporting Hanging Basket closure segment and quickly positioning
CN110117934A (en) * 2019-04-12 2019-08-13 北京市政建设集团有限责任公司 A kind of bridge hanging basket template and its installation method
CN110067211A (en) * 2019-04-23 2019-07-30 中建市政工程有限公司 A kind of bridge flange plate stripper apparatus and its construction method
CN111576248A (en) * 2020-05-29 2020-08-25 中铁七局集团有限公司 Dismantling method for cantilever cast-in-situ beam hanging basket system
CN113358470A (en) * 2021-06-04 2021-09-07 山东理工大学 Out-of-plane stable single steel truss test model
CN113358470B (en) * 2021-06-04 2022-09-13 山东理工大学 Out-of-plane stable single steel truss test model
CN113338168A (en) * 2021-06-24 2021-09-03 中交二航局第四工程有限公司 Cantilever beam construction is with hanging basket with high security
CN113338168B (en) * 2021-06-24 2023-01-10 中交二航局第四工程有限公司 Hanging basket with high safety for cantilever beam construction
CN113863167A (en) * 2021-10-22 2021-12-31 中建三局集团有限公司 Descending type suspension casting hanging basket and construction method thereof
CN114892536A (en) * 2022-06-27 2022-08-12 广州市市政集团有限公司 A walking structure for hanging No. one outside template of pouring box girder

Also Published As

Publication number Publication date
CN102094392B (en) 2012-05-02

Similar Documents

Publication Publication Date Title
CN102094392B (en) Lower supported hanging basket in bridge construction and application thereof
CN103074854B (en) Rear supporting point triangular bracket hanging basket and bridge construction method using same
CN202766975U (en) Novel deck erection crane
CN208815424U (en) A kind of bridge descending hanging basket
CN108004927B (en) Double-limb triangular hanging basket and construction method for cantilever beam section of large-span continuous rigid frame bridge
CN101586330A (en) Receding construction method of cradle of continuous girder bridge made of prestressing concrete
CN101210419A (en) Inside and outside beam system bridge fabrication machine for small radius curve concrete box girder construction and construction method thereof
CN208087078U (en) A kind of boom hoisting of large span steel reinforced concrete combination beam Bridge Erector
CN203049470U (en) Hanging basket walking system
CN101324055A (en) Lifting equipment and method of box girder integral steel reinforcement framework
CN103669217B (en) A kind of rear-support hanging basket and its entirety change width method for traversing
CN206902566U (en) A kind of arch rib bridge girder cantilever construction Hanging Basket
CN107100074A (en) A kind of lower bearing arch bridge concrete bridge deck construction method
CN110258352A (en) The steel reinforced concrete combined bridge construction method that two bridgings are done
CN108103945A (en) A kind of whole landing mould bases of cast-in-situ box girder
CN201972099U (en) Through type hanging basket in bridge construction
CN114808722A (en) Construction method of cable-stayed bridge reinforced concrete main beam
CN102134832A (en) Movable support and movable support assisted method for erecting steel box beams through non-variable amplitude frame beam crane
CN203049471U (en) Rear fulcrum triangular bracket hanging basket
CN105735142A (en) Bridge girder erection machine for prestressed concrete bridge precast section span-by-span splicing construction
CN207987749U (en) Ride cable-styled erection crane
CN102071641A (en) Integral bridge girder erection machine of distributed landing leg type transportation rack of concrete beam packing bridge crane and bridge girder erection engineering method thereof
CN107761575A (en) Ultra-wide box beam Hanging Basket and its bottom basket system
CN110344334A (en) Steel reinforced concrete combined bridge construction method is done using two bridgings of dorsal funciculus formula Bridge Erector
CN205711767U (en) Bridge Erector for Prestressed Concrete Bridges prefabricated subsection construction of splicing span by span

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant