A kind of bridge hanging basket template and its installation method Download PDF

Info

Publication number
CN110117934A
CN110117934A CN201910295407.4A CN201910295407A CN110117934A CN 110117934 A CN110117934 A CN 110117934A CN 201910295407 A CN201910295407 A CN 201910295407A CN 110117934 A CN110117934 A CN 110117934A
Authority
CN
China
Prior art keywords
hanging basket
template
bed die
bridge
installation method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910295407.4A
Other languages
Chinese (zh)
Inventor
孔恒
卢长炯
赵福元
杨立
马琼
于广
曹开斌
于洪涛
王渭
吴晓杰
狄晓萌
白宗杰
何琦威
谢生彦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Municipal Construction Co Ltd
Beijing No 6 Municipal Construction Engineering Co Ltd
Original Assignee
Beijing Municipal Construction Co Ltd
Beijing No 6 Municipal Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Municipal Construction Co Ltd, Beijing No 6 Municipal Construction Engineering Co Ltd filed Critical Beijing Municipal Construction Co Ltd
Priority to CN201910295407.4A priority Critical patent/CN110117934A/en
Publication of CN110117934A publication Critical patent/CN110117934A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of bridge hanging basket Formwork Installation Methods, belong to technical field of bridge construction, solve existing Formwork Installation Method and are laid with to template, it may occur that the problem of Hanging Basket related concrete falling accident;Steps are as follows: the template needed for choosing Hanging Basket respectively according to construction plan, levelling is carried out after template installation, correction, tighten whole bolts, pull rod and support, Hanging Basket bed die, the installation of external mold is completed with cradle construction step sequence, Hanging Basket bed die, external mold is separately mounted on Hanging Basket bed die mounting platform and external mold mounting platform, backform carries out restructuring or again prefabricated in flange plate and chamber, and the bulkhead re-worked is placed in corresponding beam section beam-ends, this invention ensures that the quality of hanging basket for bridge construction, template disassembly simultaneously is easy for installation, it is pollution-free to concrete surface, it long-acting can be used for multiple times, construction cost is saved.

Description

A kind of bridge hanging basket template and its installation method
Technical field
The present invention relates to technical field of bridge construction more particularly to a kind of bridge hanging basket template and its installation methods.
Background technique
Bridge engineering mainly studies bridge water way survey, determines bridge aerodynamics, considers navigation and line requirements to determine bridge floor Highly, considering that substrate is not washed away or frost heave is to determine embedded depth of foundation, design diversion structure etc., bridge style designs, Bridge structure design, bridge construction, rating bridge, bridge testing, bridge maintenance aspect, Hanging Basket is the master in bridge cantilever construction Equipment is wanted, truss-like, cable-stayed type, fashioned iron formula and four kinds hybrid can be divided by structure type, according to concrete cantilever construction work Various forms Hanging Basket feature, weight is comprehensively compared, using steel type, construction in the requirement of skill requirement and design drawing to Hanging Basket Technique etc.;Hanging Basket design principle: from heavy and light, structure is simple, more stable and stronger, move forward and be convenient to mount and dismount, have it is stronger repeatable Usability deforms the features such as small after stress, and Hanging Basket down space is sufficient, it is possible to provide larger operation side is conducive to reinforcing bar mould Plate constructing operation.
It needs to be laid with Hanging Basket template in beam body in Hanging Basket installation process, the template of Hanging Basket is divided into bed die, external mold, the edge of a wing Backform in plate and chamber, the bed die of Hanging Basket, external mold, flange plate, backform is all made of plank sheathing in chamber, is pacified using existing template Dress method is laid with template, it may occur that the related concrete falling accident of Hanging Basket, therefore, it is proposed that a kind of bridge hanging basket template And its installation method.
Summary of the invention
The purpose of the present invention is to provide a kind of bridge hanging basket template and its installation methods, to solve existing template peace Dress method is laid with template, it may occur that the problem of Hanging Basket related concrete falling accident.
To achieve the above object, the invention provides the following technical scheme:
A kind of bridge hanging basket Formwork Installation Method, steps are as follows:
S1, Hanging Basket is chosen respectively according to construction plan needed for template, wherein Hanging Basket bed die, external mold, flange plate, chamber Interior backform is all made of plank sheathing, and levelling, correction are carried out after template installation, and template top relative relief is less than 2mm, and diagonal error is small After 5mm, whole bolts, pull rod and support are tightened;
The installation of S2, Hanging Basket bed die, external mold are completed with cradle construction step sequence, and Hanging Basket bed die, external mold are separately mounted to Hanging Basket On bed die mounting platform and external mold mounting platform, backform is because of presstressed reinforcing steel pore-forming pipeline location difference, ruler in flange plate and chamber The easily damaged reason of very little different and demoulding, backform carries out restructuring or again prefabricated in flange plate and chamber, and will re-work Bulkhead is placed in corresponding beam section beam-ends;
S3, box girder segment filling concrete finish, and the side form of non-bearing is removed when reaching 70% design strength by maintenance Plate;
S4, plug mould is removed, then the bolt on block-by-block disassembly plug mould strikes plug mould in disassembly process It beats, the plate face and yoke of internal model and hole mould are extracted out after breaking from hole, then clean arrangement with water, are stored indoors, in case next time It uses;
S5, disassembly external mold, after pumping split bolt, first pull interior side form with jack, remove inside lower end part template, so Loosen interior skid beam sunpender with jack afterwards, promote its interior backform truss and backform is driven to be detached from beam section top plate, suspended basket in place after, adjust Whole beam section bed die absolute altitude, and keep outer side mold in place.
As a further solution of the present invention: template with a thickness of 1-2cm.
As the present invention further scheme: template with a thickness of 1.5cm.
As further scheme of the invention: in step S2, the installation method of Hanging Basket bed die mounting platform are as follows: bed die is flat Then platform installs bottom die platform rear cross beam, and be anchored in and applied with sunpender using integral hoisting after assembled or installation on ground in situ Work beam section, front beam are installed and are anchored in preceding upper beam with sunpender, lateral connection is then installed and carried out to stringer, front and back is hung Stage+module, operating platform installation before then carrying out finally complete end template installation.
In conclusion the beneficial effects of the present invention are: this invention ensures that the quality of hanging basket for bridge construction, while template Dismantle it is easy for installation, it is pollution-free to concrete surface, long-acting can be used for multiple times, save construction cost.
Specific embodiment
The technical scheme in the embodiments of the invention will be clearly and completely described below, it is clear that described implementation Example is only a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, this field is common Technical staff's every other embodiment obtained without making creative work belongs to the model that the present invention protects It encloses.
Embodiment 1
A kind of bridge hanging basket Formwork Installation Method, steps are as follows:
S1, Hanging Basket is chosen respectively according to construction plan needed for template, wherein Hanging Basket bed die, external mold, flange plate, chamber Interior backform is all made of plank sheathing, and levelling, correction are carried out after template installation, and template top relative relief is less than 2mm, and diagonal error is small After 5mm, whole bolts, pull rod and support are tightened;
The installation of S2, Hanging Basket bed die, external mold are completed with cradle construction step sequence, and Hanging Basket bed die, external mold are separately mounted to Hanging Basket On bed die mounting platform and external mold mounting platform, backform is because of presstressed reinforcing steel pore-forming pipeline location difference, ruler in flange plate and chamber The easily damaged reason of very little different and demoulding, backform carries out restructuring or again prefabricated in flange plate and chamber, and will re-work Bulkhead is placed in corresponding beam section beam-ends;
S3, box girder segment filling concrete finish, and the side form of non-bearing is removed when reaching 70% design strength by maintenance Plate;
S4, plug mould is removed, then the bolt on block-by-block disassembly plug mould strikes plug mould in disassembly process It beats, the plate face and yoke of internal model and hole mould are extracted out after breaking from hole, then clean arrangement with water, are stored indoors, in case next time It uses;
S5, disassembly external mold, after pumping split bolt, first pull interior side form with jack, remove inside lower end part template, so Loosen interior skid beam sunpender with jack afterwards, promote its interior backform truss and backform is driven to be detached from beam section top plate, suspended basket in place after, adjust Whole beam section bed die absolute altitude, and keep outer side mold in place.
Template with a thickness of 1-2cm;
Template with a thickness of 1.5cm;
In step S2, the installation method of Hanging Basket bed die mounting platform are as follows: bottom die platform is using assembled or installation on ground in situ Then integral hoisting afterwards installs bottom die platform rear cross beam, and is anchored in beam section of having constructed with sunpender, front beam is installed and uses sunpender It is anchored in preceding upper beam, lateral connection is then installed and carried out to stringer, stage+module is hung into front and back, operation is flat before then carrying out Platform installation finally completes end template installation.
Embodiment 2
A kind of bridge hanging basket template based on the Formwork Installation Method of bridge hanging basket described in embodiment 1.
In conclusion the beneficial effects of the present invention are: this invention ensures that the quality of hanging basket for bridge construction, while template Dismantle it is easy for installation, it is pollution-free to concrete surface, long-acting can be used for multiple times, save construction cost.
It is obvious to a person skilled in the art that invention is not limited to the details of the above exemplary embodiments, Er Qie In the case where without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the present invention is by appended power Benefit requires rather than above description limits, it is intended that all by what is fallen within the meaning and scope of the equivalent elements of the claims Variation is included within the present invention.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiments being understood that.

Claims (7)

1. a kind of bridge hanging basket Formwork Installation Method, which is characterized in that steps are as follows:
S1, Hanging Basket is chosen respectively according to construction plan needed for template, template installation after carry out levelling, correction, tighten whole Bolt, pull rod and support;
The installation of S2, Hanging Basket bed die, external mold are completed with cradle construction step sequence, and Hanging Basket bed die, external mold are separately mounted to Hanging Basket bed die On mounting platform and external mold mounting platform, backform carries out restructuring or again prefabricated in flange plate and chamber, and will re-work Bulkhead is placed in corresponding beam section beam-ends;
S3, box girder segment filling concrete finish, and the side template of non-bearing is removed when reaching 70% design strength by maintenance;
S4, plug mould is removed, then the bolt on block-by-block disassembly plug mould beats plug mould in disassembly process, interior The plate face and yoke of mould and hole mould are extracted out after breaking from hole, then clean arrangement with water, and storage indoors, is used in case of next time;
S5, disassembly external mold, after pumping split bolt, first pull interior side form with jack, remove inside lower end part template, then use Jack loosens interior skid beam sunpender, promotees its interior backform truss and backform is driven to be detached from beam section top plate, suspended basket in place after, adjust beam Section bed die absolute altitude, and keep outer side mold in place.
2. bridge hanging basket Formwork Installation Method according to claim 1, which is characterized in that template top relative relief is less than 2mm, diagonal error are less than 5mm.
3. bridge hanging basket Formwork Installation Method according to claim 2, which is characterized in that in step S2, Hanging Basket bed die The installation method of mounting platform are as follows: then it is flat to install bed die using integral hoisting after assembled or installation on ground in situ for bottom die platform Platform rear cross beam, and it is anchored in beam section of having constructed with sunpender, front beam is installed and is anchored in preceding upper beam with sunpender, then to stringer Lateral connection is installed and carried out, stage+module is hung into front and back, operating platform installation before then carrying out finally completes end template peace Dress.
4. bridge hanging basket Formwork Installation Method according to claim 3, which is characterized in that template with a thickness of 1-2cm.
5. bridge hanging basket Formwork Installation Method according to claim 4, which is characterized in that template with a thickness of 1.5cm.
6. bridge hanging basket Formwork Installation Method according to claim 5, which is characterized in that Hanging Basket bed die, external mold, the edge of a wing Backform is all made of plank sheathing in plate, chamber.
7. a kind of bridge hanging basket template based on any bridge hanging basket Formwork Installation Method of claim 1-6.
CN201910295407.4A 2019-04-12 2019-04-12 A kind of bridge hanging basket template and its installation method Pending CN110117934A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910295407.4A CN110117934A (en) 2019-04-12 2019-04-12 A kind of bridge hanging basket template and its installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910295407.4A CN110117934A (en) 2019-04-12 2019-04-12 A kind of bridge hanging basket template and its installation method

Publications (1)

Publication Number Publication Date
CN110117934A true CN110117934A (en) 2019-08-13

Family

ID=67520913

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910295407.4A Pending CN110117934A (en) 2019-04-12 2019-04-12 A kind of bridge hanging basket template and its installation method

Country Status (1)

Country Link
CN (1) CN110117934A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114790698A (en) * 2022-05-06 2022-07-26 中铁上海工程局集团第五工程有限公司 Hanging basket formwork assembling process for bridge construction

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100013429A (en) * 2008-07-31 2010-02-10 계문교 Mold apparatus for forming concrete girder of bridge
CN102094392A (en) * 2011-03-03 2011-06-15 中铁四局集团第一工程有限公司 Lower supported hanging basket in bridge construction and application thereof
CN103850185A (en) * 2014-02-20 2014-06-11 中交三航局第三工程有限公司 Multi-truss type hanging basket for super-wide type bridge construction
CN105625195A (en) * 2016-03-16 2016-06-01 河南大建桥梁钢构股份有限公司 Novel SCC construction-method moving hanging basket for corrugated steel webs and construction method of hanging basket
CN104612061B (en) * 2015-02-05 2016-08-24 中铁上海工程局集团第五工程有限公司 A kind of suspension open type hanging basket device and construction method thereof
CN106978783A (en) * 2017-05-16 2017-07-25 中铁八局集团第二工程有限公司 The Hanging Basket poured for skew web plate formula continuous beam cantilever
JP2018135688A (en) * 2017-02-22 2018-08-30 三井住友建設株式会社 Bridge pier and construction method thereof
CN108611989A (en) * 2018-08-08 2018-10-02 贵州路桥集团有限公司 A kind of box arch bridge cantilever pouring Hanging Basket
CN108824199A (en) * 2018-06-27 2018-11-16 贵州路桥集团有限公司 The Arch Bridge Construction method of underneath type Hanging Basket

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100013429A (en) * 2008-07-31 2010-02-10 계문교 Mold apparatus for forming concrete girder of bridge
CN102094392A (en) * 2011-03-03 2011-06-15 中铁四局集团第一工程有限公司 Lower supported hanging basket in bridge construction and application thereof
CN103850185A (en) * 2014-02-20 2014-06-11 中交三航局第三工程有限公司 Multi-truss type hanging basket for super-wide type bridge construction
CN104612061B (en) * 2015-02-05 2016-08-24 中铁上海工程局集团第五工程有限公司 A kind of suspension open type hanging basket device and construction method thereof
CN105625195A (en) * 2016-03-16 2016-06-01 河南大建桥梁钢构股份有限公司 Novel SCC construction-method moving hanging basket for corrugated steel webs and construction method of hanging basket
JP2018135688A (en) * 2017-02-22 2018-08-30 三井住友建設株式会社 Bridge pier and construction method thereof
CN106978783A (en) * 2017-05-16 2017-07-25 中铁八局集团第二工程有限公司 The Hanging Basket poured for skew web plate formula continuous beam cantilever
CN108824199A (en) * 2018-06-27 2018-11-16 贵州路桥集团有限公司 The Arch Bridge Construction method of underneath type Hanging Basket
CN108611989A (en) * 2018-08-08 2018-10-02 贵州路桥集团有限公司 A kind of box arch bridge cantilever pouring Hanging Basket

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
匿名: "挂篮悬臂现浇施工方案", 《道客巴巴》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114790698A (en) * 2022-05-06 2022-07-26 中铁上海工程局集团第五工程有限公司 Hanging basket formwork assembling process for bridge construction

Similar Documents

Publication Publication Date Title
CN105908777A (en) Comprehensive pipe gallery sliding mold and application method thereof
CN104895318A (en) Aluminum alloy template system and construction method of same
CN102936962A (en) Construction method of slanting cantilever steel structure supported by temporary steel frame
CN102505708B (en) Construction method of tunnel at oversized cross section open cut area in track traffic
CN107059920B (en) Loess formation piping lane construction technology
CN102913248B (en) The overall upset hanging template of wholecircle and formwork erection, release method
CN104746435A (en) Wide-angle Y-shaped pier column construction method
CN103452126B (en) Light combined hanging box with recyclable baseplate steels and construction technology thereof
CN201367728Y (en) Derrick-less hydraulic slip form device used for reinforced concrete water tower supporting tube construction
CN103510469B (en) Construction method for manufacturing thin-walled hollow pier
CN106894346B (en) A kind of the continuous beam bridge construction method
CN105586867A (en) Installation method for over-length over-weight steel reinforcement cage
CN102116051A (en) Layer-by-layer overhanging structure lifting method
CN105586833A (en) Construction method for integrally forming large cast-in-place thin-wall high pier through stiff skeleton reinforcement cage
CN104831632A (en) Upper transverse beam and lower transverse beam construction method for bridge cable bent tower
CN102286932B (en) Construction method for off-site assembling and automatic mounting on bridge of mobile mould bridge abutment
CN110117934A (en) A kind of bridge hanging basket template and its installation method
CN109629449A (en) A kind of steel case arch bridge arch springing toughened internal stress installation locating support and alignment method
CN102587665B (en) Pouring method of coupled shear wall structure
CN102561689A (en) Construction method for cantilever lifting scaffold
CN106284989A (en) The sliding form bracing system of double track and complete construction method
CN203755173U (en) Formwork device used for hydraulic climbing of bridge high pier
CN112012473B (en) Integrated steel formwork for wall body of cantilever rib type of sewage pool
CN109235871A (en) Variable section structure aluminum alloy mould plate construction method
CN105586987B (en) Open trench tunnel open type agent structure side wall Bailey bracket formwork and its construction technology

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Kong Heng

Inventor after: Wu Xiaojie

Inventor after: Di Xiaomeng

Inventor after: Bai Zongjie

Inventor after: He Qiwei

Inventor after: Xie Shengyan

Inventor after: Lu Changjiong

Inventor after: Zhao Fuyuan

Inventor after: Yang Li

Inventor after: Ma Qiong

Inventor after: Yu Guang

Inventor after: Cao Kaibin

Inventor after: Yu Hongtao

Inventor after: Wang Wei

Inventor before: Kong Heng

Inventor before: Wu Xiaojie

Inventor before: Di Xiaomeng

Inventor before: Bai Zongjie

Inventor before: He Qiwei

Inventor before: Xie Shengyan

Inventor before: Lu Changjiong

Inventor before: Zhao Fuyuan

Inventor before: Yang Li

Inventor before: Ma Qiong

Inventor before: Yu Guang

Inventor before: Cao Kaibin

Inventor before: Yu Hongtao

Inventor before: Wang Wei

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190813