CN104746435A - Wide-angle Y-shaped pier column construction method - Google Patents

Wide-angle Y-shaped pier column construction method Download PDF

Info

Publication number
CN104746435A
CN104746435A CN201510158219.9A CN201510158219A CN104746435A CN 104746435 A CN104746435 A CN 104746435A CN 201510158219 A CN201510158219 A CN 201510158219A CN 104746435 A CN104746435 A CN 104746435A
Authority
CN
China
Prior art keywords
concrete
layer
steel
floor
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510158219.9A
Other languages
Chinese (zh)
Other versions
CN104746435B (en
Inventor
石丰祥
余流
高璞
王安鑫
刘跃武
周俊龙
李飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN201510158219.9A priority Critical patent/CN104746435B/en
Publication of CN104746435A publication Critical patent/CN104746435A/en
Application granted granted Critical
Publication of CN104746435B publication Critical patent/CN104746435B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • E—FIXED CONSTRUCTIONS
    • E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
    • E—FIXED CONSTRUCTIONS
    • E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00—Bridges characterised by the cross-section of their bearing spanning structure
    • E—FIXED CONSTRUCTIONS
    • E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00—Structural or constructional details of bridges
    • E01D19/02—Piers; Abutments ; Protecting same against drifting ice
    • E—FIXED CONSTRUCTIONS
    • E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00—Material constitution of bridges
    • E01D2101/20—Concrete, stone or stone-like material
    • E01D2101/24—Concrete
    • E01D2101/26—Concrete reinforced
    • E01D2101/268—Composite concrete-metal
    • E—FIXED CONSTRUCTIONS
    • E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00—Material constitution of bridges
    • E01D2101/20—Concrete, stone or stone-like material
    • E01D2101/24—Concrete
    • E01D2101/26—Concrete reinforced
    • E01D2101/28—Concrete reinforced prestressed

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种大角度Y型墩柱的施工方法,该施工方法将Y型墩柱分为第Ⅰ层到第Ⅵ层六个区段进行浇筑,具体为承台上搭设支架浇筑墩柱第Ⅰ层和第Ⅱ层混凝土;安装牛腿、型钢框架、分配梁;锚固第一长斜拉索和短斜拉索;浇筑墩柱第Ⅲ层混凝土;割除第一长斜拉索,拆除第Ⅲ层混凝土的模板;锚固第二长斜拉索;浇筑墩柱第Ⅳ层混凝土和第Ⅴ层混凝土;张拉水平对拉钢绞线,拆除型钢框架上部结构部分和第二长斜拉索;利用型钢框架下部结构部分搭设支架浇筑第Ⅵ层混凝土,浇筑过程中逐渐张拉水平对拉钢绞线到100%。本发明采用节段施工措施和斜拉支承体系,有效解决了原有施工技术难题,保证了结构和施工安全,显著地降低了操作平台成本。

The invention discloses a construction method for a large-angle Y-shaped pier column. In the construction method, the Y-shaped pier column is divided into six sections from the first floor to the sixth floor for pouring. Specifically, the pier column is poured by erecting a support on the cap Concrete for the first and second floors; install corbels, steel frames, and distribution beams; anchor the first long and short stay cables; pour concrete for the third layer of piers; cut off the first long stay cables and dismantle the second Formwork for the concrete of the third floor; anchoring the second long stay cable; pouring the concrete of the fourth floor and the fifth floor of the pier column; tensioning the horizontal tensioned steel strands, removing the upper structure of the steel frame and the second long stay cable; The concrete of the sixth floor is poured by erecting brackets on the lower part of the steel frame, and gradually stretching the horizontal tensioned steel strands to 100% during the pouring process. The invention adopts segmental construction measures and a cable-stayed support system, effectively solves the original construction technical problems, ensures the safety of the structure and construction, and significantly reduces the cost of the operating platform.

Description

A kind of construction method of great-angle Y type pier stud
Technical field
The present invention relates to field of bridge construction, specifically, relate to a kind of bridge Y type pier stud construction method.
Background technology
Closely during the last ten years, there is some prestressed concretes Y type supporting bridge both at home and abroad, comprised Y type and support continuous girder bridge and continuous rigid frame bridge.Compared with straight leg rigid frame bridge, under the V pier effect of prestressed concrete Y type pier continuous rigid frame bridge, girder span can obviously shorten, and the negative bending moment peak value supporting shoulder also reduces to some extent, thus make structure become light and handy and very thin, be conducive to selecting box girder with variable cross section form, profile is comparatively elegant in appearance, as shown in Figure 1.
Wherein, between its " V " shape two oblique limb leg angle be greater than 90 ° can be called great-angle Y type pier stud, this structure is higher to construction technical requirement, is mainly reflected in:
1. structure self the concrete scale of construction is large, can not establish one's own system, need strong support at the pre-structure of the prestressed stretch-draw of top binder;
2. the oblique limb leg of great-angle Y type pier pier shaft operation platform is set up, reinforcing bar binding and the operation easier such as fixing, model sheetinstallat and reinforcing location larger;
3. the reinforcing bar eccentricity issues such as the pre-buried and oblique limb leg of shape of great-angle Y type pier is difficult to control;
4. great-angle Y type pier variable cross-section section reinforcing bar density is high, and the outward appearance of concreting is difficult to control;
5. when the bridge pier of great-angle Y type pier is arranged in the river that riverbed sludge is thicker, river is darker, by the restriction of the depth of water and riverbed earthen condition, erection construction support acquires a certain degree of difficulty, and key issue is that steel pipe pile sedimentation is difficult to control.
Summary of the invention
The present invention is to solve there is the technical problem of above-mentioned multiple difficulty in existing great-angle Y type pier stud construction, a kind of construction method of great-angle Y type pier stud is provided, can ensure that its " V " shape two oblique limb leg coupling part concrete tensile stress does not exceed design allowed band all the time, and ensure structural safety and construction safety.
In order to solve the problems of the technologies described above, the present invention is achieved by following technical scheme:
A kind of construction method of great-angle Y type pier stud, Y type pier stud is divided into the Ith layer to the VIth layer six section to build by this construction method from the bottom to top successively, wherein the Ith layer is the straightway of more than cushion cap, IIth layer is the coupled section of straightway to the transition of oblique limb leg section, IIIth layer is the oblique limb leg section of 2/3 vertical height, IVth layer is the oblique limb leg section of 1/3 vertical height, and the Vth layer is the oblique limb leg extension at binder two ends, and the VIth layer is unsettled section in the middle part of binder; Based on above division, this construction method comprises the steps:
(1) support set up by cushion cap, build pier stud the Ith layer concrete;
(2) support set up by cushion cap, build pier stud the IIth layer concrete; Pre-buried bracket in casting process also sets up the structural steel frame with two-layer section steel beam, and bracket is embedded near the IIth layer concrete upper surface place in advance, the IIth layer concrete of nuzzling in advance bottom structural steel frame;
(3) complete the installation of bracket, and distribution beam bottom is connected to bracket, upper end is connected to stiff skeleton temporarily;
(4) at the structural steel frame both sides difference long suspension cable of anchoring first and short suspension cable; First long suspension cable one end is anchored in lower floor's section steel beam end of structural steel frame, and the other end is anchored in the beam section of corresponding IIIth layer concrete of distribution beam; Short suspension cable one end is anchored in lower floor's section steel beam end of structural steel frame, and the other end is anchored in stiff skeleton;
(5) pier stud the IIIth layer concrete is built;
(6) cut off the first long suspension cable, remove the template of the IIIth layer concrete;
(7) at the long suspension cable of structural steel frame both sides difference anchoring second; Second long suspension cable one end is anchored in the section steel beam end, upper strata of structural steel frame, and the other end is anchored in the beam section that distribution beam corresponds to the IVth layer concrete;
(8) build pier stud the IVth layer concrete and the Vth layer concrete simultaneously;
After (9) the IVth layer concretes and the Vth layer concrete reach design strength, the horizontal steel strand of stretch-draw, to 50% of design load, removes structure division and the second long suspension cable that structural steel frame exceeds binder;
(10) utilize the remaining structure of structural steel frame to set up support, build the VIth layer concrete, in casting process gradually by horizontal steel strand stretch-draw to 100%;
(11) reach after designing requirement intensity until concrete, to the steel Shu Jinhang stretch-draw of Y type pier stud, anchoring, mud jacking;
(12) remaining structure of structural steel frame, horizontal steel strand, distribution beam, short suspension cable and all temporary structures is removed.
Wherein, described structural steel frame is two story frame structures that section steel beam and steel column form, and steel column is welded with stiffening rib, and bean column node adopts high-strength bolt to connect.
Wherein, described distribution beam is by the rectilinear structure of two i shaped steel assembly weldings, is provided with the lumps of wood to fill space between described distribution beam and Y type pier stud oblique limb leg steel form.
Wherein, the pre-buried degree of depth of described bracket is apart from the IIth layer concrete upper surface at least 50cm.
Wherein, described first long suspension cable, described second long suspension cable, described short suspension cable all adopt diameter to be the fining twisted steel of 32mm.
Wherein, described first long suspension cable one end is anchored in lower floor's section steel beam end of structural steel frame, and the other end is anchored in the central point that distribution beam corresponds to the IIIth layer concrete beam section; And described first long suspension cable is perpendicular to described distribution beam.
Wherein, described short suspension cable is parallel with described first long suspension cable.
Wherein, described second long suspension cable one end is anchored in the section steel beam end, upper strata of structural steel frame, and the other end is anchored in the central point that distribution beam corresponds to the IVth layer concrete beam section; And described second long suspension cable is perpendicular to described distribution beam.
The invention has the beneficial effects as follows:
The segmental construction measure that great-angle Y type pier stud construction method of the present invention adopts non-once to build, and adopt the mode of oblique pull supporting system to construct to the oblique limb leg of V-type two, duration and economic dispatch factor are considered, efficiently solve the technical barrier of great-angle Y type pier stud in construction, ensure that structural safety and construction safety, significantly reduce installation and the material cost of operating platform, and have the advantages that can be recycled, further save cost, the construction of prestressed concrete great-angle Y type pier stud can be widely used in.
Accompanying drawing explanation
Fig. 1 is the structural representation of great-angle Y type pier stud;
Fig. 2 is the Y type pier stud concrete delamination cast schematic diagram adopted in construction method of the present invention;
Fig. 3 is the elevation of the oblique pull support system adopted in construction method of the present invention;
Fig. 4 is the plan view of Fig. 3;
Fig. 5 is schematic diagram when building straight line portion (the Ith layer and the IIth layer) pier stud in construction method of the present invention;
Fig. 6 is schematic diagram when building the IIIth layer of pier stud in construction method of the present invention.
In figure: 1, structural steel frame, 2, anchor device, 3-1, the first long suspension cable, 3-2, the second long suspension cable, 4, horizontal steel strand, 5, binder, 6, steel pipe shellfish thunder support platform, 7, short suspension cable, 8, bracket, 9, distribution beam, 10, pier stud, 11, cushion cap, 12, stiff skeleton, 13, full framing.
Detailed description of the invention
For summary of the invention of the present invention, feature and effect can be understood further, hereby exemplify following examples, and coordinate accompanying drawing to be described in detail as follows:
The invention provides a kind of construction method of great-angle Y type pier stud, the Y type pier stud that between " V " shape two oblique limb leg that this construction method is mainly applicable to its pier stud 10 pier shaft, angle is greater than 90 °, this great-angle Y type pier stud can not establish one's own system at the pre-structure of the prestressed stretch-draw of top binder 5, must rely on strong external bracing.
Y type pier stud can be regarded as successively according to the difference of cross sectional shape from lower to upper and comprise straightway, straightway to the coupled section of oblique limb leg section transition, tiltedly limb leg section and binder 5.In the present invention, Y type pier stud concrete adopts placement layer by layer according to the convenience of the setting of oblique pull support system and construction, be divided into the Ith layer to the VIth layer six section, the supporting way of different section in work progress is different, its partitioning standards mainly reasonable concrete square amount that can bear of oblique pull support system and coordinating with construction sequence.As shown in Figure 2, the Ith layer is the straightway of cushion cap more than 11; IIth layer is the coupled section of more than the Ith layer straightway to the transition of oblique limb leg section, and the height of the IIth layer is by cushion cap 11 size restrictions, and its extension should be able to meet to be set up full framing 13 and build on cushion cap 11; IIIth layer is the oblique limb leg section of more than the IIth layer 2/3 vertical height, IVth layer is the oblique limb leg section of more than the IIIth layer 1/3 vertical height, partitioning standards between IIIth layer and the IVth layer is the concrete square amount as far as possible reducing the large sections of oblique limb leg section jib-length, namely be reduce the moment size in moment of flexure, consider the stressing conditions of oblique pull braced structures and the convenience of construction simultaneously; Vth layer is the oblique limb leg extension at binder 5 two ends, and the VIth layer is unsettled section in the middle part of binder 5.Vth layer and the VIth layer divides according to the difference of support pattern, and wherein the weight concrete of the VIth layer bears by the structural steel frame 1 be embedded in pier stud 10 sets up full framing again, and the weight concrete of the Vth layer is born by oblique pull support system.
Y type pier stud longitudinally wide 32.0m, laterally vertical wide 23.0m, pier height 17.169m, wherein the inverted triangle part height 11.085m of the present embodiment, between the oblique limb leg of " V " shape two of inverted triangle part, angle is 103.2 °, Coupling point position concrete section height 2.5m; The oblique limb leg of " V " shape two of this structure can not establish one's own system at the pre-structure of top binder 5 prestressed stretch-draw, and the angle of the oblique limb leg of " V " shape two makes greatly traditional full hall construction bracket platform, reinforcing bar binding and fixing, model sheetinstallat and the constructing operation difficulty such as fixing.
According to above-mentioned size, in the present embodiment, six section partitions of Y type pier stud are specific as follows: the Ith layer is the straightway that cushion cap more than 11 3.6m is high; IIth layer is straightway that more than the Ith layer 5.2m the is high coupled section to the transition of oblique limb leg section; IIIth layer and the IVth layer be oblique limb leg section high for vertical distance 6.2m in 3:2 ratio separately, namely the IIIth layer of to be more than the IIth layer vertical height be 3.72m oblique limb leg section, the oblique limb leg section of the IVth layer of to be more than the IIIth layer vertical height be 2.48m; And the high binder 5 of 1.2m is divided into three parts and builds, unsettled section in the middle part of it the VIth layer is that 18m is long, and each 7m in the Vth layer, oblique limb leg extension at two ends is long; The concrete of the IIIth layer, the IVth layer and the Vth layer needs symmetry to build.
Based on the division of above six concreting parts, the construction method of the great-angle Y type pier stud that the present embodiment provides, its concrete steps are as follows:
(1) on cushion cap 11, set up full framing 13, the reinforcing bar of colligation pier stud 10 the Ith layer concrete, pre-buried corrugated pipe pipeline, installs template; Flat bed stone method is adopted to build the Ith layer concrete, along the long limit successively horizontal stone in face, storehouse, first floor making after vibration compacting, then making vibrates the second layer, every layer of layer thickness is 40cm, reaches the Ith layer concrete Construction Elevation successively; As shown in Figure 5.
(2) on cushion cap 11, set up full framing 13, the reinforcing bar of colligation pier stud 10 the IIth layer concrete, the position of adjustment, fixing corrugated pipe pipeline, installs template; Flat bed stone method is adopted to build the IIth layer concrete, along the long limit successively horizontal stone in face, storehouse, first floor making after vibration compacting, then making vibrates the second layer, every layer of layer thickness is 40cm, reaches the IIth layer concrete Construction Elevation successively; As shown in Figure 5.
In the casting process of the IIth layer concrete, carry out the Embedment Construction of bracket 8 pre-embedded steel slab at the design attitude near the IIth layer of pier stud 10 upper surface, for ensureing that pre-buried effect need ensure that its pre-buried degree of depth is apart from pier stud 10 the IIth layer concrete upper surface at least 50cm.
In the casting process of the IIth layer concrete, set up structural steel frame 1 simultaneously, according in " Code for design of concrete structures ", the calculation requirement of built-in fitting and connector is nuzzled the IIth layer concrete certain depth in advance bottom structural steel frame 1; As shown in Figure 3.The concrete pre-buried degree of depth of structural steel frame 1 can calculate according to 8.3.1 bar tensile reinforcement anchorage length in " Code for design of concrete structures " (GB 50020-2010), and demand fulfillment 9.7 saves detailing requiments concrete in built-in fitting and connector.
Wherein, structural steel frame 1 is two story frame structures (namely section steel beam is provided with two-layer up and down) that section steel beam and steel column form, wherein section steel beam and steel column are made by I70b, and steel column is welded with stiffening rib every 80cm in vertical height, and bean column node adopts high-strength bolt to connect.The upper and lower two-layer section steel beam height of structural steel frame 1 is on the basis of 90 degree of angles meeting the first long suspension cable 3-1, the second long suspension cable 3-2 and outside distribution beam 9 axis as far as possible, and the force request according to oblique pull support system is determined.
(3) the IIth layer concretes complete the welding of bracket 8 after building; Distribution beam 9 bottom is fixedly connected on bracket 8, and distribution beam 9 upper end is first connected with stiff skeleton 12 temporarily, treats that suspension cable and its anchoring are as the strong point; As shown in Figure 3.
Wherein, distribution beam 9 is by the rectilinear structure of 2 I40b shaped steel assembly weldings, and due to the lateral surface of Y type pier stud oblique limb leg section be curved surface, also need add the lumps of wood to fill space between its steel form and distribution beam 9, to ensure that the weight concrete born by Y type pier stud oblique limb leg section outboard template is effectively delivered in distribution beam 9.
(4) the first long suspension cable 3-1 and short suspension cable 7 that anchoring the IIIth layer concrete is corresponding respectively in structural steel frame 1 both sides, the weight concrete of oblique for " V " shape two limb leg can be delivered to structural steel frame 1 by the first long suspension cable 3-1 and short suspension cable 7, so be delivered to built part pier stud 10 on.
First long suspension cable 3-1 is 8, every side, and one end is connected to lower floor's section steel beam end of structural steel frame 1 by anchor device 2; The other end is anchored in distribution beam 9, and concrete anchorage point is the beam section central point that distribution beam 9 corresponds to the IIIth layer concrete lateral surface; And the first long suspension cable 3-1 keeps perpendicular to distribution beam 9 as far as possible.
Short suspension cable 7 is also 8, every side, and one end is connected to lower floor's section steel beam end of structural steel frame 1 by anchor device 2, consistent with the anchor point of corresponding first long suspension cable 3-1; The other end is anchored in the pre-embedded steel slab of stiff skeleton 12 inside; Short suspension cable 7 keeps parallel with the first long suspension cable 3-1 as far as possible; As shown in Figure 3 and Figure 4;
First long suspension cable 3-1 and short suspension cable 7 all adopt Φ 32 finish rolling deformed bar, are all by power.The quantity of the first long suspension cable 3-1 and short suspension cable 7 is arranged according to the width of direction across bridge pier stud 10, and general every side arranges force request and the construction safety that 8 can meet structure.
(5) using steel pipe shellfish thunder support platform 6 as casting platform, the reinforcing bar of colligation pier stud 10 the IIIth layer concrete, pre-buried corrugated pipe pipeline, installs template; Flat bed stone method is adopted to build the IIIth layer concrete, along the long limit successively horizontal stone in face, storehouse, first floor making after vibration compacting, then making vibrates the second layer, every layer of layer thickness is 40cm, reaches the IIIth layer concrete Construction Elevation successively; As shown in Figure 6.
After (6) the IIIth layer concretes are built, cut off the first long suspension cable 3-1 be anchored in the distribution beam 9 of outside, retain the short suspension cable 7 be anchored on stiff skeleton 12, remove the template of the IIIth layer concrete simultaneously, use to facilitate other pier studs;
(7) the second long suspension cable 3-2 that anchoring the IVth layer concrete is corresponding respectively in structural steel frame 1 both sides, the weight concrete of oblique for " V " shape two limb leg can be delivered to structural steel frame 1 by the second long suspension cable 3-2, so be delivered to built part pier stud 10 on.
Second long suspension cable 3-2 is 8, every side, and one end is connected to the section steel beam end, upper strata of structural steel frame 1 by anchor device 2, and the other end is anchored in distribution beam 9, and concrete anchorage point is the beam section central point that distribution beam 9 corresponds to the IVth layer concrete lateral surface; Second long suspension cable 3-2 keeps perpendicular to distribution beam 9 as far as possible; As shown in Figure 3.
Second long suspension cable 3-2 adopts Φ 32 finish rolling deformed bar, is all by power.The quantity of the second long suspension cable 3-2 is arranged according to the width of direction across bridge pier stud 10, and general every side arranges force request and the construction safety that 8 can meet structure.
(8) reinforcing bar of colligation pier stud 10 the IVth layer concrete and the Vth layer concrete while, pre-buried corrugated pipe pipeline, installs template; Flat bed stone method is adopted to build the IVth layer and the Vth layer concrete, along the long limit successively horizontal stone in face, storehouse, first floor making after vibration compacting, then making vibrates the second layer, every layer of layer thickness is 40cm, reaches the Construction Elevation of the Vth layer concrete successively;
(9) after the IVth layer concrete and the Vth layer concrete reach design strength, along the horizontal steel strand 4 of binder 5 lower edge stretch-draw to 50% of design load, horizontal steel strand 4 two ends are anchored in outside distribution beam 9; And temporary fixed between dismountable distribution beam 9 upper end and stiff skeleton 12.Remove structural steel frame 1 exceed the structure division of binder 5 and the IVth layer concrete corresponding the second long suspension cable 3-2, the works for binder 5 is shaping reserves operating space.Now the weight of the oblique limb leg of " V " shape two relies on the horizontal steel strand 4 of stretch-draw 50%, is anchored at short suspension cable 7 between structural steel frame 1 and stiff skeleton 12, bracket 8 strong point common support of distribution beam 9 lower end;
(10) utilize structural steel frame 1 to remove rear remaining structure division and set up support, the reinforcing bar of colligation pier stud 10 the VIth layer concrete, pre-buried corrugated pipe pipeline, installs template; Flat bed stone method is adopted to build the VIth layer concrete, along the long limit successively horizontal stone in face, storehouse, first floor making after vibration compacting, then making vibrates the second layer, every layer of layer thickness is 40cm, reaches the Construction Elevation of the VIth layer concrete successively.In casting process, gradually the stretch-draw of horizontal steel strand 4 to 100%, to resist the pressure that top the VIth layer concrete causes the oblique limb leg of " V " shape.
(11) after whole concrete of Y type pier stud reach designing requirement intensity, to the steel Shu Jinhang stretch-draw of Y type pier stud, anchoring, mud jacking.
(12) now can remove unified to the remaining structure of structural steel frame, horizontal steel strand, short suspension cable and all temporary structures.
Although be described the preferred embodiments of the present invention by reference to the accompanying drawings above; but the present invention is not limited to above-mentioned detailed description of the invention; above-mentioned detailed description of the invention is only schematic; be not restrictive; those of ordinary skill in the art is under enlightenment of the present invention; do not departing under the ambit that present inventive concept and claim protect, can also make the concrete conversion of a lot of form, these all belong within protection scope of the present invention.

Claims (8)

1.一种大角度Y型墩柱的施工方法,其特征在于,该施工方法将Y型墩柱由下至上依次分为第Ⅰ层到第Ⅵ层六个区段进行浇筑,其中第Ⅰ层为承台以上的直线段,第Ⅱ层为直线段向斜肢腿段过渡的耦合段,第Ⅲ层为2/3垂直高度的斜肢腿段,第Ⅳ层为1/3垂直高度的斜肢腿段,第Ⅴ层为系梁两端的斜肢腿延伸段,第Ⅵ层为系梁中部的悬空段;基于以上划分,该施工方法包括如下步骤:1. A construction method for a large-angle Y-shaped pier, characterized in that the construction method divides the Y-shaped pier from bottom to top into six sections from the first floor to the sixth floor for pouring, wherein the first floor It is the straight section above the platform cap, the second floor is the coupling section for the transition from the straight section to the oblique leg section, the third floor is the oblique leg section with 2/3 vertical height, and the fourth floor is the oblique leg section with 1/3 vertical height. For the leg section, the fifth floor is the extension of the oblique legs at both ends of the tie beam, and the sixth floor is the suspended section in the middle of the tie beam; based on the above divisions, the construction method includes the following steps: (1)承台上搭设支架,浇筑墩柱第Ⅰ层混凝土;(1) Set up the bracket on the cap and pour the first layer of concrete for the pier column; (2)承台上搭设支架,浇筑墩柱第Ⅱ层混凝土;浇筑过程中预埋牛腿并搭设具有两层型钢梁的型钢框架,牛腿预埋于靠近第Ⅱ层混凝土上表面处,型钢框架底部预埋进第Ⅱ层混凝土;(2) Set up brackets on the cap and pour the second layer of concrete for the pier column; during the pouring process, the corbels are pre-embedded and a steel frame with two layers of steel beams is erected, and the corbels are pre-buried near the upper surface of the second layer of concrete, The bottom of the steel frame is pre-embedded in the second layer of concrete; (3)完成牛腿的安装,并将分配梁底端连接于牛腿、上端临时连接于劲性骨架;(3) Complete the installation of the corbel, and connect the bottom end of the distribution beam to the corbel and the upper end to the stiff frame temporarily; (4)在型钢框架两侧分别锚固第一长斜拉索和短斜拉索;第一长斜拉索一端锚固于型钢框架的下层型钢梁端部,另一端锚固于分配梁对应第Ⅲ层混凝土的梁段;短斜拉索一端锚固于型钢框架的下层型钢梁端部,另一端锚固于劲性骨架;(4) Anchor the first long stay cable and short stay cable on both sides of the steel frame respectively; one end of the first long stay cable is anchored to the end of the lower steel beam of the steel frame, and the other end is anchored to the distribution beam corresponding to the third The beam section of the first floor concrete; one end of the short stay cable is anchored to the end of the lower steel beam of the steel frame, and the other end is anchored to the stiff frame; (5)浇筑墩柱第Ⅲ层混凝土;(5) Pouring concrete for the third layer of piers; (6)割除第一长斜拉索,拆除第Ⅲ层混凝土的模板;(6) Cut off the first long stay cable and remove the formwork of the third layer of concrete; (7)在型钢框架两侧分别锚固第二长斜拉索;第二长斜拉索一端锚固于型钢框架的上层型钢梁端部,另一端锚固于分配梁对应于第Ⅳ层混凝土的梁段;(7) Anchor the second long stay cables on both sides of the steel frame respectively; one end of the second long stay cables is anchored to the end of the upper steel beam of the steel frame, and the other end is anchored to the distribution beam corresponding to the beam of the fourth floor concrete part; (8)同时浇筑墩柱第Ⅳ层混凝土和第Ⅴ层混凝土;(8) Simultaneously pour the concrete of the fourth floor and the fifth floor of the pier column; (9)第Ⅳ层混凝土和第Ⅴ层混凝土达到设计强度后,张拉水平对拉钢绞线到设计值的50%,拆除型钢框架高出系梁的结构部分和第二长斜拉索;(9) After the concrete of the fourth layer and the fifth layer of concrete reach the design strength, the steel strand is stretched horizontally to 50% of the design value, and the structural part of the steel frame higher than the tie beam and the second long stay cable are removed; (10)利用型钢框架的剩余结构搭设支架,浇筑第Ⅵ层混凝土,浇筑过程中逐渐将水平对拉钢绞线张拉到100%;(10) Utilize the remaining structure of the steel frame to set up supports, pour the sixth layer of concrete, and gradually stretch the horizontal tensioned steel strands to 100% during the pouring process; (11)待混凝土达到设计要求强度后,对Y型墩柱的钢束进行张拉、锚固、压浆;(11) After the concrete reaches the design required strength, tension, anchor and grout the steel beams of the Y-shaped pier column; (12)拆除型钢框架的剩余结构、水平对拉钢绞线、分配梁、短斜拉索及所有临时结构。(12) Remove the remaining structure of the steel frame, the horizontal tensioned steel strands, distribution beams, short stay cables and all temporary structures. 2.根据权利要求1所述的一种大角度Y型墩柱的施工方法,其特征在于,所述型钢框架为型钢梁与型钢柱组成的两层框架结构,型钢柱焊有加劲肋,梁柱节点采用高强螺栓连接。2. the construction method of a kind of large-angle Y-shaped pier column according to claim 1, is characterized in that, described shaped steel frame is the two-layer frame structure that shaped steel beam and shaped steel column are formed, and shaped steel column is welded with stiffener, Beam-column joints are connected by high-strength bolts. 3.根据权利要求1所述的一种大角度Y型墩柱的施工方法,其特征在于,所述分配梁是由两根工字型钢组焊而成的直线形结构,所述分配梁与Y型墩柱斜肢腿钢模板之间设有方木以填充空隙。3. The construction method of a large-angle Y-shaped pier column according to claim 1, wherein the distribution beam is a linear structure formed by welding two I-shaped steels, and the distribution beam and Square logs are placed between the steel formwork of the oblique leg of the Y-shaped pier to fill the gap. 4.根据权利要求1所述的一种大角度Y型墩柱的施工方法,其特征在于,所述牛腿的预埋深度距第Ⅱ层混凝土上表面至少50cm。4. The construction method of a large-angle Y-shaped pier according to claim 1, wherein the pre-embedded depth of the corbel is at least 50 cm from the upper surface of the second layer of concrete. 5.根据权利要求1所述的一种大角度Y型墩柱的施工方法,其特征在于,所述第一长斜拉索、所述第二长斜拉索、所述短斜拉索均采用直径为32mm的精轧螺纹钢。5. the construction method of a kind of large-angle Y-shaped pier column according to claim 1, is characterized in that, described first long cable-stayed cable, described second long cable-stayed cable, described short cable-stayed cable all Finished rolled rebar with a diameter of 32mm is used. 6.根据权利要求1所述的一种大角度Y型墩柱的施工方法,其特征在于,所述第一长斜拉索一端锚固于型钢框架的下层型钢梁端部,另一端锚固于分配梁对应于第Ⅲ层混凝土梁段的中心点;且所述第一长斜拉索垂直于所述分配梁。6. The construction method of a large-angle Y-shaped pier column according to claim 1, wherein one end of the first long stay cable is anchored to the lower section of the steel beam end of the steel frame, and the other end is anchored to the The distribution beam corresponds to the center point of the third layer concrete beam section; and the first long stay cable is perpendicular to the distribution beam. 7.根据权利要求1所述的一种大角度Y型墩柱的施工方法,其特征在于,所述短斜拉索与所述第一长斜拉索平行。7. The construction method of a large-angle Y-shaped pier according to claim 1, wherein the short stay cables are parallel to the first long stay cables. 8.根据权利要求1所述的一种大角度Y型墩柱的施工方法,其特征在于,所述第二长斜拉索一端锚固于型钢框架的上层型钢梁端部,另一端锚固于分配梁对应于第Ⅳ层混凝土梁段的中心点;且所述第二长斜拉索垂直于所述分配梁。8. The construction method of a kind of large-angle Y-shaped pier column according to claim 1, wherein one end of the second long stay cable is anchored to the upper section of the steel beam end of the steel frame, and the other end is anchored to the The distribution beam corresponds to the center point of the concrete beam section of the fourth floor; and the second long stay cable is perpendicular to the distribution beam.
CN201510158219.9A 2015-04-03 2015-04-03 A kind of construction method of great-angle Y type pier stud Active CN104746435B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510158219.9A CN104746435B (en) 2015-04-03 2015-04-03 A kind of construction method of great-angle Y type pier stud

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510158219.9A CN104746435B (en) 2015-04-03 2015-04-03 A kind of construction method of great-angle Y type pier stud

Publications (2)

Publication Number Publication Date
CN104746435A true CN104746435A (en) 2015-07-01
CN104746435B CN104746435B (en) 2016-03-30

Family

ID=53586638

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510158219.9A Active CN104746435B (en) 2015-04-03 2015-04-03 A kind of construction method of great-angle Y type pier stud

Country Status (1)

Country Link
CN (1) CN104746435B (en)

Cited By (29)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105201208A (en) * 2015-08-12 2015-12-30 郑州市第一建筑工程集团有限公司 System for dismantling Y-type pier column oblique rod steel mold
CN105350458A (en) * 2015-11-16 2016-02-24 中国建筑第六工程局有限公司 Construction method of composite structure platform for construction of Y-shaped pier of bridge
CN105625186A (en) * 2015-12-31 2016-06-01 浙江舜杰建筑集团股份有限公司 Method for constructing large-section concrete Y-shaped column
CN105821770A (en) * 2016-04-01 2016-08-03 上海城建市政工程(集团)有限公司 Connecting and locating method for multiple tower roots and large-size concrete bearing platform foundation of steel structure main tower
CN105839541A (en) * 2016-04-29 2016-08-10 贵州桥梁建设集团有限责任公司 Construction method for rigid frame bridge No.0 section non-welding support and structure
CN107974953A (en) * 2017-12-20 2018-05-01 沈阳建筑大学 A kind of method of raising Y type bridge pier shock resistances
CN109083023A (en) * 2018-09-06 2018-12-25 重庆交通大学 Continuous Rigid Frame Bridge Using Stiff Skeleton and Its Construction Method
CN109537470A (en) * 2019-01-03 2019-03-29 中铁北京工程局集团第二工程有限公司 The Y structure construction bracket structure of battered leg stress can be adjusted in real time
CN109706842A (en) * 2019-01-23 2019-05-03 湖南路桥建设集团有限责任公司 A kind of urban viaduct Single column pier capping beam construction device
CN110438882A (en) * 2019-07-31 2019-11-12 广州地铁设计研究院股份有限公司 A kind of self-balancing overhung construction system
CN110805274A (en) * 2019-11-19 2020-02-18 中铁二局集团有限公司 Steel mould of Y-shaped column and pouring method thereof
CN111979918A (en) * 2020-07-08 2020-11-24 中交第二航务工程局有限公司 V-shaped pier combined construction method suitable for marine environment
CN112096095A (en) * 2020-08-21 2020-12-18 中国建筑第八工程局有限公司 Y-shaped column reinforcement hoop structure and construction method thereof
CN112593485A (en) * 2020-12-11 2021-04-02 保利长大工程有限公司 Steel tower cable-stayed support for large cantilever bent cap
CN112681136A (en) * 2020-12-15 2021-04-20 中国建筑第八工程局有限公司 Support structure of hollow pier top template and construction method thereof
CN112695646A (en) * 2021-01-06 2021-04-23 中铁大桥局集团第六工程有限公司 Triangular area construction method of open-web rigid frame bridge
CN113265950A (en) * 2021-05-20 2021-08-17 广东省水利水电第三工程局有限公司 Support for large cantilever bent cap construction and construction method thereof
CN113605241A (en) * 2021-07-29 2021-11-05 中交二公局第三工程有限公司 Large-span cable-stayed beam construction support and method for high-speed road bent frame pier
CN113981830A (en) * 2021-11-11 2022-01-28 中交一公局集团有限公司 V-shaped pier construction method
CN114481840A (en) * 2021-12-28 2022-05-13 交通运输部公路科学研究所 A method for segmented casting of super-high and super-large pier top zero block by double-stressed system
CN115369768A (en) * 2022-08-25 2022-11-22 广州市第三市政工程有限公司 A positioning and strengthening method for steel pipe support on the slope surface of bridge V-shaped pier column
CN115595897A (en) * 2022-12-05 2023-01-13 中建八局第一建设有限公司(Cn) A construction method of reverse cable-stayed T-structure with large cantilever
CN116065492A (en) * 2023-01-04 2023-05-05 中铁十九局集团有限公司 A construction method of cable-stayed support system for Y-shaped bridge piers
CN117188280A (en) * 2023-09-28 2023-12-08 中交三公局第一工程有限公司 A V-shaped pier bridge
CN117230722A (en) * 2023-09-28 2023-12-15 中交三公局第一工程有限公司 A construction method of V-pier near water
CN117344653A (en) * 2023-11-23 2024-01-05 中铁四局集团第四工程有限公司 A bridge construction method for Y-shaped piers
CN117403557A (en) * 2023-11-28 2024-01-16 浙江正方交通建设有限公司 Construction system and method of Y-shaped piers for large-span arched continuous rigid frame bridge
CN117418476A (en) * 2023-12-07 2024-01-19 中国建筑第五工程局有限公司 A concrete integral pouring anti-collapse tensile formwork structure and construction method
CN121473238A (en) * 2025-10-21 2026-02-06 中交一航局第三工程有限公司 A Simple Support Construction Method for Large-Angle Y-Shaped Piers

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5896609A (en) * 1997-11-21 1999-04-27 Lin; Wei-Hwang Safety method of construction a prestressed cable-stay bridge
JP2007231593A (en) * 2006-02-28 2007-09-13 Yoshisuke Kamiya Bridge
CN102168405A (en) * 2011-03-18 2011-08-31 重庆城建控股(集团)有限责任公司 Construction method of steel-concrete mixed Y-shaped tower of low-pylon cable-stayed bridge
CN102505640A (en) * 2011-12-05 2012-06-20 中国建筑第六工程局有限公司 Method for constructing pier column
CN103243635A (en) * 2013-04-28 2013-08-14 李勇 Large-span curvilinear steel truss web member PC (polycarbonate) composite bridge and construction method thereof
CN203639807U (en) * 2013-12-29 2014-06-11 长安大学 Y-shaped pier for concrete filled steel tube truss beam

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5896609A (en) * 1997-11-21 1999-04-27 Lin; Wei-Hwang Safety method of construction a prestressed cable-stay bridge
JP2007231593A (en) * 2006-02-28 2007-09-13 Yoshisuke Kamiya Bridge
CN102168405A (en) * 2011-03-18 2011-08-31 重庆城建控股(集团)有限责任公司 Construction method of steel-concrete mixed Y-shaped tower of low-pylon cable-stayed bridge
CN102505640A (en) * 2011-12-05 2012-06-20 中国建筑第六工程局有限公司 Method for constructing pier column
CN103243635A (en) * 2013-04-28 2013-08-14 李勇 Large-span curvilinear steel truss web member PC (polycarbonate) composite bridge and construction method thereof
CN203639807U (en) * 2013-12-29 2014-06-11 长安大学 Y-shaped pier for concrete filled steel tube truss beam

Cited By (33)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105201208A (en) * 2015-08-12 2015-12-30 郑州市第一建筑工程集团有限公司 System for dismantling Y-type pier column oblique rod steel mold
CN105350458A (en) * 2015-11-16 2016-02-24 中国建筑第六工程局有限公司 Construction method of composite structure platform for construction of Y-shaped pier of bridge
CN105625186A (en) * 2015-12-31 2016-06-01 浙江舜杰建筑集团股份有限公司 Method for constructing large-section concrete Y-shaped column
CN105821770A (en) * 2016-04-01 2016-08-03 上海城建市政工程(集团)有限公司 Connecting and locating method for multiple tower roots and large-size concrete bearing platform foundation of steel structure main tower
CN105839541A (en) * 2016-04-29 2016-08-10 贵州桥梁建设集团有限责任公司 Construction method for rigid frame bridge No.0 section non-welding support and structure
CN107974953B (en) * 2017-12-20 2019-11-15 沈阳建筑大学 A Method of Improving the Seismic Capability of Y-shaped Bridge Pier
CN107974953A (en) * 2017-12-20 2018-05-01 沈阳建筑大学 A kind of method of raising Y type bridge pier shock resistances
CN109083023A (en) * 2018-09-06 2018-12-25 重庆交通大学 Continuous Rigid Frame Bridge Using Stiff Skeleton and Its Construction Method
CN109537470A (en) * 2019-01-03 2019-03-29 中铁北京工程局集团第二工程有限公司 The Y structure construction bracket structure of battered leg stress can be adjusted in real time
CN109706842A (en) * 2019-01-23 2019-05-03 湖南路桥建设集团有限责任公司 A kind of urban viaduct Single column pier capping beam construction device
CN110438882A (en) * 2019-07-31 2019-11-12 广州地铁设计研究院股份有限公司 A kind of self-balancing overhung construction system
CN110805274A (en) * 2019-11-19 2020-02-18 中铁二局集团有限公司 Steel mould of Y-shaped column and pouring method thereof
CN111979918A (en) * 2020-07-08 2020-11-24 中交第二航务工程局有限公司 V-shaped pier combined construction method suitable for marine environment
CN112096095A (en) * 2020-08-21 2020-12-18 中国建筑第八工程局有限公司 Y-shaped column reinforcement hoop structure and construction method thereof
CN112593485A (en) * 2020-12-11 2021-04-02 保利长大工程有限公司 Steel tower cable-stayed support for large cantilever bent cap
CN112593485B (en) * 2020-12-11 2021-07-23 保利长大工程有限公司 Steel tower cable-stayed support for large cantilever bent cap
CN112681136A (en) * 2020-12-15 2021-04-20 中国建筑第八工程局有限公司 Support structure of hollow pier top template and construction method thereof
CN112695646A (en) * 2021-01-06 2021-04-23 中铁大桥局集团第六工程有限公司 Triangular area construction method of open-web rigid frame bridge
CN113265950A (en) * 2021-05-20 2021-08-17 广东省水利水电第三工程局有限公司 Support for large cantilever bent cap construction and construction method thereof
CN113605241A (en) * 2021-07-29 2021-11-05 中交二公局第三工程有限公司 Large-span cable-stayed beam construction support and method for high-speed road bent frame pier
CN113981830A (en) * 2021-11-11 2022-01-28 中交一公局集团有限公司 V-shaped pier construction method
CN114481840A (en) * 2021-12-28 2022-05-13 交通运输部公路科学研究所 A method for segmented casting of super-high and super-large pier top zero block by double-stressed system
CN115369768B (en) * 2022-08-25 2025-04-08 广州市第三市政工程有限公司 Positioning and reinforcing method for steel pipe support on slope surface of bridge V-shaped pier column
CN115369768A (en) * 2022-08-25 2022-11-22 广州市第三市政工程有限公司 A positioning and strengthening method for steel pipe support on the slope surface of bridge V-shaped pier column
CN115595897A (en) * 2022-12-05 2023-01-13 中建八局第一建设有限公司(Cn) A construction method of reverse cable-stayed T-structure with large cantilever
CN116065492A (en) * 2023-01-04 2023-05-05 中铁十九局集团有限公司 A construction method of cable-stayed support system for Y-shaped bridge piers
CN117230722A (en) * 2023-09-28 2023-12-15 中交三公局第一工程有限公司 A construction method of V-pier near water
CN117188280A (en) * 2023-09-28 2023-12-08 中交三公局第一工程有限公司 A V-shaped pier bridge
CN117344653A (en) * 2023-11-23 2024-01-05 中铁四局集团第四工程有限公司 A bridge construction method for Y-shaped piers
CN117403557A (en) * 2023-11-28 2024-01-16 浙江正方交通建设有限公司 Construction system and method of Y-shaped piers for large-span arched continuous rigid frame bridge
CN117418476A (en) * 2023-12-07 2024-01-19 中国建筑第五工程局有限公司 A concrete integral pouring anti-collapse tensile formwork structure and construction method
CN121473238A (en) * 2025-10-21 2026-02-06 中交一航局第三工程有限公司 A Simple Support Construction Method for Large-Angle Y-Shaped Piers
CN121473238B (en) * 2025-10-21 2026-07-03 中交一航局第三工程有限公司 Construction method of large-angle Y-shaped pier simple bracket

Also Published As

Publication number Publication date
CN104746435B (en) 2016-03-30

Similar Documents

Publication Publication Date Title
CN104746435B (en) A kind of construction method of great-angle Y type pier stud
CN110331668B (en) Construction method of bidirectional inclined V-shaped bridge tower of cable-stayed bridge without back cables
CN107165272B (en) Prestressed assembled concrete frame node connecting structure and construction method thereof
CN106702910B (en) A kind of main girder construction technique of the double rope face low-pylon cable-stayed bridges of double tower
CN110700105B (en) Synchronous construction method and formwork used for high pier pier column and tie beam
CN101781879B (en) Construction method of single-pylon cable-stayed bridge without dorsal cables
CN207194146U (en) Prestressed fabricated concrete frame joint connection structure
CN102251657B (en) Arching formwork erecting method for assembled framework beam plate
CN101984189B (en) Construction method of large steel concrete composite multi-terrace slope skewback
CN105625195A (en) Novel SCC construction-method moving hanging basket for corrugated steel webs and construction method of hanging basket
CN104480922B (en) Space truss formwork system and construction method thereof
CN106120568A (en) Cross a river Main Bridge bridge pier secondary locking temporary consolidation structure and construction method
CN107905114B (en) A kind of construction method of large span Successive interference cancellation
CN105220808A (en) Large-span prestressed arch bar site prefabrication construction method of installation
CN103147385B (en) Double-spliced extradosed cable-stayed bridge
CN107476470A (en) Steel pipe built in assembled and GFRP pipe regeneration concrete compound shear walls and its construction method
CN107905124B (en) A kind of symmetrical expression rigid frame-continuous girder construction technology
CN102418425B (en) Prefabrication integral casting building structure system with cast-in-site haunched beams, and construction method for prefabrication integral casting building structure system
CN113638304B (en) Concrete beam type bridge hidden cover beam structure system and construction method thereof
CN111074795A (en) Construction method for pouring continuous beam in cantilever mode spanning existing railway
CN107905115A (en) Through Steel pipe concrete truss combination beamss bridge construction method
CN115387234A (en) Template system of lower beam of ultrahigh rhombic tower pier and construction method
CN107974942B (en) A kind of abrupt slope side rigid frame-continuous girder end bay construction method
CN206902913U (en) A kind of high-altitude long-span overhung structure
CN111395725A (en) Construction method of scaffolding for irregular convex and concave facade structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Wang Anxin

Inventor after: Yu Liu

Inventor after: Gao Pu

Inventor after: Liu Yuewu

Inventor after: Zhou Junlong

Inventor after: Li Fei

Inventor before: Shi Fengxiang

Inventor before: Yu Liu

Inventor before: Gao Pu

Inventor before: Wang Anxin

Inventor before: Liu Yuewu

Inventor before: Zhou Junlong

Inventor before: Li Fei

COR Change of bibliographic data