CN110258352A - Construction method of steel-concrete composite bridge with two spans - Google Patents

Construction method of steel-concrete composite bridge with two spans Download PDF

Info

Publication number
CN110258352A
CN110258352A CN201910699995.8A CN201910699995A CN110258352A CN 110258352 A CN110258352 A CN 110258352A CN 201910699995 A CN201910699995 A CN 201910699995A CN 110258352 A CN110258352 A CN 110258352A
Authority
CN
China
Prior art keywords
bridge
steel
span
construction
spans
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910699995.8A
Other languages
Chinese (zh)
Inventor
李斐然
张存超
张海啸
袁波
刘伟
傅立军
谢理伟
曹旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Provincial Communication Planning and Design Institute Co Ltd
Original Assignee
Henan Provincial Communication Planning and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Provincial Communication Planning and Design Institute Co Ltd filed Critical Henan Provincial Communication Planning and Design Institute Co Ltd
Priority to CN201910699995.8A priority Critical patent/CN110258352A/en
Publication of CN110258352A publication Critical patent/CN110258352A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses the steel reinforced concrete combined bridge construction methods that two bridgings of one kind are done, including step, 1. 2. pre-manufactured steel beam element is constructed bridge pier, Bridge Erector is erected at main bridge first, 3. two cross-locations lift first in place across girder steel, supporting leg edge is set to move along the bridge to the first girder steel bottom plate across pier top position, it is reserved to set up space, then 4. lifting second welds first across girder steel in place, two across girder steel, complete the 5. installation first simultaneously of two system transforms across girder steel " Simply supported non-uniform ", two across prefabricated bridge, and in adjusting 6. the position of supporting leg passes through Bridge Erector and lifts across girder steel hogging moment area concrete at the 7. vertically and horizontally wet joint concrete of two bridge panel of continuous placing and pier top position simultaneously to two, it completes preceding two and 8. repeats the second ~ seven step across construction, complete the construction of integrin bridge.The construction speed of steel reinforced concrete combined bridge can be substantially improved in the present invention, improve the stress of composite structure, be a kind of steel reinforced concrete combined bridge construction method of brand new ideas.

Description

两跨连做的钢混组合桥梁施工方法Construction method of steel-concrete composite bridge with two spans

技术领域technical field

本发明涉及钢混组合梁的施工方法,尤其是涉及一种两跨连做的钢混组合桥梁施工方法。The invention relates to a construction method of a steel-concrete composite beam, in particular to a construction method of a two-span steel-concrete composite bridge.

背景技术Background technique

钢混组合桥梁具有自重较轻、跨越能力较大和施工进度快等多项优点,在交通建设中具有非常明显的经济效益和竞争力,目前国家大力推进钢混组合梁桥的建设。由于施工顺序和施工方法会影响到钢混组合梁桥的成桥状态和受力特性,因此,需要结合实际情况选用合适的施工方法。Steel-concrete composite bridges have many advantages such as light weight, large spanning capacity, and fast construction progress. They have very obvious economic benefits and competitiveness in transportation construction. At present, the country is vigorously promoting the construction of steel-concrete composite beam bridges. Since the construction sequence and construction method will affect the completed state and mechanical characteristics of the steel-concrete composite girder bridge, it is necessary to select an appropriate construction method based on the actual situation.

目前常用的施工方法有以下三种:①支架施工:首先搭设临时安装支架,然后在支架上安装钢梁,再浇筑混凝土桥面板,待混凝土达到设计强度并与钢梁结合成为整体后,拆除支架,其荷载由钢混组合结构共同承担。单纯从材料的利用率上来分析,支架施工优势较为明显,但其对场地要求较高,特别是在跨越深谷、高墩桥梁情况下,采用支架施工是非常不经济的。②顶推施工:在钢梁前设钢导梁,必要时搭设临时墩,然后采用千斤顶顶推的方式将钢梁顶推到位,再在钢梁上安装桥面板,现浇湿接缝。该施工方法在主梁架设时,钢梁受力较为不利,存在正负弯矩作用段,因此往往需要增大钢梁的尺寸和截面,一般在特殊情况下才采用这种施工方法。③架桥机施工:采用架桥机吊升安装钢梁,然后安装桥面板,再现浇桥面板湿接缝部分,形成组合结构。此种施工方法,施工速度相对较快,前期的钢梁和桥面板自重均由钢梁承担,桥面板不受力,后期荷载作用时,组合结构整体受力,综合优势十分明显。由于架桥机在进行吊装施工时,每次吊装一跨,逐孔施工,即每次架设完一孔钢梁后,需要等待横向桥面板湿接缝浇筑完成后,方可进行下一跨的施工,因此,桥面板湿接缝环节的施工速度,直接影响了整个工程的施工进度;并且,在施工过程中,架桥机每次只有一孔在发挥作用,造成架桥机利用率较低;再次,在等跨布置的多跨连续梁施工中,钢梁边跨受力最为不利,而且还需要防止桥梁墩顶负弯矩区开裂。At present, there are three commonly used construction methods: ① Bracket construction: first erect temporary mounting brackets, then install steel beams on the brackets, and then pour concrete bridge decks. After the concrete reaches the design strength and integrates with the steel beams into a whole, remove the brackets , the load is shared by the steel-concrete composite structure. From the analysis of the utilization rate of materials alone, the advantages of bracket construction are more obvious, but it has higher requirements on the site, especially in the case of crossing deep valleys and bridges with high piers, it is very uneconomical to use bracket construction. ②Pushing construction: set up a steel guide beam in front of the steel girder, erect a temporary pier if necessary, then push the steel girder into place by jacking up, then install the bridge deck on the steel girder, and cast in-situ wet joints. When the main girder is erected by this construction method, the force on the steel girder is relatively unfavorable, and there are positive and negative bending moments. Therefore, it is often necessary to increase the size and cross-section of the steel girder. This construction method is generally only used in special cases. ③Bridge erecting machine construction: The bridge erecting machine is used to hoist and install the steel girders, and then install the bridge deck, and reproduce the wet joints of the poured bridge deck to form a composite structure. With this construction method, the construction speed is relatively fast. The self-weight of the steel girders and bridge decks in the early stage are all borne by the steel girders, and the bridge decks are not stressed. When the bridge erecting machine is hoisting, each span is hoisted and constructed hole by hole, that is, after erecting a steel beam each time, it is necessary to wait for the wet joints of the horizontal bridge deck to be poured before proceeding to the next span. construction, therefore, the construction speed of the wet joint link of the bridge deck directly affects the construction progress of the entire project; and, during the construction process, only one hole of the bridge erecting machine is functioning at a time, resulting in a low utilization rate of the bridge erecting machine Thirdly, in the construction of multi-span continuous beams with equal spans, the side spans of the steel beams are most unfavorable for stress, and it is also necessary to prevent cracking in the negative moment zone of the bridge pier top.

发明内容Contents of the invention

本发明提供一种两跨连做的钢混组合桥梁施工方法,目的在于解决现有架桥机施工存在设备利用率较低、施工速度慢以及钢梁和边跨受力不利的问题。The invention provides a construction method for a two-span steel-concrete composite bridge, aiming to solve the problems of low equipment utilization rate, slow construction speed and unfavorable stress on steel girders and side spans existing in the construction of existing bridge erecting machines.

为实现上述目的,本发明可采取下述技术方案:To achieve the above object, the present invention can take the following technical solutions:

本发明所述的两跨连做的钢混组合桥梁施工方法,包括如下步骤:The steel-concrete composite bridge construction method that two spans of the present invention is connected, comprises the steps:

第一步,根据桥梁设计方案,预制钢梁单元,并在钢梁翼缘上设置临时吊片;The first step is to prefabricate steel girder units according to the bridge design plan, and set temporary hanging pieces on the flanges of steel girders;

第二步,待桥梁基桩、桥墩施工完毕后,使架桥机行进至主桥第一、二跨位置,并使架桥机的前、中、后支腿分别站立在桥墩盖梁上,其中,中支腿为两对沿纵桥向滑动设置的伸缩式支腿,且前支腿以外的架桥机支撑横梁长度为单跨钢梁的0.2~0.3倍;In the second step, after the construction of the foundation piles and piers of the bridge is completed, the bridge erecting machine is advanced to the first and second span positions of the main bridge, and the front, middle and rear legs of the bridge erecting machine stand on the pier cover beam respectively. Among them, the middle outriggers are two pairs of telescopic outriggers that slide along the longitudinal direction of the bridge, and the length of the supporting beam of the bridge erecting machine other than the front outriggers is 0.2~0.3 times that of the single-span steel beam;

第三步,吊装第一跨钢梁就位,然后使中支腿沿顺桥向移动至第一跨墩顶位置的钢梁底板上,预留架设空间,接着吊装第二跨钢梁就位;The third step is to hoist the first-span steel girder into place, then move the middle outrigger along the direction of the bridge to the steel girder floor at the top of the first-span pier, reserve space for erection, and then hoist the second-span steel girder into place ;

第四步,将第一、二跨钢梁进行纵向焊接,完成两跨钢梁“简支变连续”的体系转换;The fourth step is to longitudinally weld the steel beams of the first and second spans to complete the system conversion of the two-span steel beams from "simply supported to continuous";

第五步,同时安装第一、二跨的预制桥面板;在此过程中,中支腿从墩顶钢梁底板位置依次升起,沿顺桥向分别移动支撑在墩顶两侧的桥面板上;The fifth step is to install the prefabricated bridge decks of the first and second spans at the same time; during this process, the middle outriggers are sequentially raised from the position of the bottom plate of the steel beam on the pier top, and the bridge decks supported on both sides of the pier top are respectively moved along the bridge direction superior;

第六步,将架桥机吊索末端的吊扣与第一、二跨钢梁上的吊片分别连接后,对两跨钢梁同时提拉,并使吊索的索力在张拉至设定值后锁定,其中,顺桥向墩顶两侧吊索的索力值大于跨中吊索的索力值;The sixth step is to connect the buckle at the end of the sling of the bridge erecting machine to the hanging pieces on the steel beams of the first and second spans respectively, and then lift the steel beams of the two spans at the same time, and make the cable force of the slings stretch to the set point. Lock after setting the value, wherein, the cable force value of the sling along the bridge to the two sides of the pier top is greater than the cable force value of the mid-span sling;

第七步,采取一次浇筑的方式,连续浇筑第一、二跨桥面板的纵横向湿接缝混凝土,以及墩顶位置处的负弯矩区混凝土,待现浇混凝土达到设计强度后,解除吊索与钢梁吊片之间的连接;The seventh step is to adopt a one-time pouring method to continuously pour the vertical and horizontal wet joint concrete of the first and second span bridge decks, as well as the concrete in the negative moment area at the top of the pier. After the cast-in-place concrete reaches the design strength, the lifting The connection between the cable and the steel beam hanger;

第八步,使架桥机向前行进,且每向前行进两跨时,均按照第二~七步所述的方法进行施工,直至整联桥梁架设完成。The eighth step is to make the bridge erecting machine move forward, and every time two spans are moved forward, the construction shall be carried out according to the method described in the second to seventh steps until the erection of the integrated bridge is completed.

本发明施工方法与现有施工方法相比,其优点体现在:Compared with the existing construction method, the construction method of the present invention has the following advantages:

1)本发明改变了原有的施工方式,其以相邻两跨钢梁为单位,连续性吊装,一次性浇筑两跨的桥面板湿接缝及墩顶负弯矩区混凝土,虽然安装每个钢梁的施工速度不变,但是由于节省了一半等待桥面板混凝土达到设计强度的时间,相当于整个施工速度提高了一倍,大大提高了设备的利用率,节省了工程施工费用,产生了直接的经济效益;1) The present invention changes the original construction method, which uses adjacent two-span steel girders as a unit, continuous hoisting, and one-time pouring of concrete for the wet joints of the two-span bridge deck and the negative moment area of the pier top. The construction speed of the steel girder remains unchanged, but half of the time for waiting for the bridge deck concrete to reach the design strength is saved, which is equivalent to doubling the entire construction speed, which greatly improves the utilization rate of equipment, saves construction costs, and generates direct economic benefits;

2)本发明通过架桥机吊索对相邻两跨钢梁进行同时反拉,改善了安装预制桥面板、现浇桥面板湿接缝时边跨钢梁的受力,另外,通过调整吊索索力,采用墩顶附近的索力大于跨中索力的方案,解除吊索拉力以后在墩顶范围内形成预压力,改善了墩顶的负弯矩区开裂问题;2) The present invention pulls back the steel girders of two adjacent spans at the same time through the sling of the bridge erecting machine, which improves the stress on the side span steel girders when installing the prefabricated bridge deck and the wet joint of the cast-in-place bridge deck. For the cable force, the cable force near the top of the pier is greater than the mid-span cable force, and a pre-compression is formed within the range of the pier top after the tension of the sling is released, which improves the cracking problem in the negative moment area of the pier top;

3)本发明在钢梁架设过程中,增设了架桥机尾部加长段,提升了设备的吊装距离,适应了两跨连续架设浇筑的需求;3) In the process of steel girder erection, the present invention adds a lengthening section at the tail of the bridge erecting machine, which improves the hoisting distance of the equipment and meets the needs of continuous erection and pouring of two spans;

4)本发明在施工过程中,首先进行钢主梁的纵向连接,完成“简支变连续”的体系转换,然后再安装桥面板,即:架设钢主梁→简支变连续→安装桥面板;而以往的施工方式则是:架设钢主梁→安装桥面板→简支变连续;使用本发明的施工方法可以提高连续跨径中钢主梁的整体受力性能,对于边跨的受力产生改善。4) In the construction process of the present invention, the longitudinal connection of the steel main girder is firstly carried out to complete the system conversion of "simply supported to continuous", and then the bridge deck is installed, that is: erecting the steel main girder→simply supported to continuous→installing the bridge deck ; while the previous construction method is: erect steel main girder → install bridge deck → simply supported and become continuous; using the construction method of the present invention can improve the overall mechanical performance of the steel main girder in the continuous span, for the force of the side span produce improvements.

综上,本发明可以大幅提升钢混组合桥梁的施工进度,不仅可以产生直接的经济效益,而且本施工方法还可以改善组合结构的受力状态,是一种全新理念的钢混组合桥梁施工方法,在长大跨径钢混组合桥梁中具有广阔的应用前景。In summary, the present invention can greatly improve the construction progress of steel-concrete composite bridges, not only can produce direct economic benefits, but also the construction method can improve the stress state of the composite structure, and is a new construction method for steel-concrete composite bridges , has broad application prospects in long-span steel-concrete composite bridges.

附图说明Description of drawings

图1~7是本发明的施工步骤图。Fig. 1~7 is the construction steps figure of the present invention.

图8是本发明施工中使用的钢梁单元的横断面结构示意图。Fig. 8 is a cross-sectional schematic diagram of the steel beam unit used in the construction of the present invention.

图9是本发明施工中使用的架桥机的结构示意图(省略运梁车)。Fig. 9 is a schematic structural view of the bridge erecting machine used in the construction of the present invention (the beam transporter is omitted).

图10是图3中架桥机对钢梁进行吊装时的横断面示意图。Fig. 10 is a schematic cross-sectional view of the bridge erecting machine in Fig. 3 when hoisting the steel girder.

图11是图5中架桥机对钢梁进行吊点提升时的横断面示意图。Fig. 11 is a schematic cross-sectional view of the bridge erecting machine in Fig. 5 lifting the lifting point of the steel girder.

图12是图9中中支腿与支撑横梁的连接结构示意图。Fig. 12 is a schematic diagram of the connection structure between the middle leg and the supporting beam in Fig. 9 .

具体实施方式Detailed ways

本发明所述的两跨连做的钢混组合桥梁施工方法,适用于钢梁单元跨度为30~120m的情况。下面以六跨一联的钢混连续组合桥梁为例,对本发明的施工方法做更加详细的说明。The construction method of the two-span steel-concrete composite bridge of the present invention is suitable for the situation that the steel girder unit span is 30-120m. Taking the steel-concrete continuous composite bridge with six spans and one connection as an example below, the construction method of the present invention will be described in more detail.

如图1-7所示,本发明主要包括以下步骤:As shown in Figure 1-7, the present invention mainly comprises the following steps:

第一步,根据桥梁设计方案,预制如图8所示的钢梁单元1,该钢梁单元1主要包括腹板1.1和翼缘1.2,且翼缘1.2上焊接有临时吊片1.3。In the first step, according to the bridge design scheme, the steel beam unit 1 shown in Fig. 8 is prefabricated. The steel beam unit 1 mainly includes a web 1.1 and a flange 1.2, and a temporary hanging piece 1.3 is welded on the flange 1.2.

第二步,待桥梁基桩、桥墩施工完毕后,使架桥机2就位。In the second step, after the construction of the bridge foundation piles and bridge piers is completed, the bridge erecting machine 2 is put in place.

如图9所示,架桥机2包括带有前支腿2.1、中支腿2.2、后支腿2.3的支撑横梁2.4,支撑横梁2.4位于前支腿2.1外侧的部分(即加长段a)为钢梁单元1长度的0.3倍,用以提高架桥机2的吊升运输距离;为了解决两跨钢梁连续吊装时中支腿2.2的站位问题,中支腿2.2为两对沿纵桥向滑动设置的伸缩式支腿,每个中支腿2.2顶部均通过电机2.2a驱动的纵向行走轮2.2b与设置在支撑横梁2.4底面的滑轨2.2c相连,且中支腿2.2和支撑横梁2.4之间设置有用于锁定位置的活动式拴扣2.2d(见图12)。当架设钢梁时,两对中支腿2.2全部支撑在墩顶已架设的钢梁底板位置(见图3);当浇筑桥面板湿接缝时,两对中支腿2.2分别支撑在墩顶左右两侧的预制桥面板上(见图5)。支撑横梁2.4上安装有可沿顺桥向和横桥向移动的滑动起吊装置2.5,其包括一对位于支撑横梁2.4上的纵向导轨,纵向导轨上滑动设置有顶部带有电动收绳机的移动横梁,与电动收绳机相连的吊装横梁上安装有用于吊装钢梁的起吊挂钩。在前支腿2.1和后支腿2.3之间的支撑横梁2.4上还安装有多组沿桥长方向间隔设置的收卷装置2.6,每组收卷装置2.6装置至少为两个,分别安装在滑动起吊装置2.5两侧。具体地,每个收卷装置2.6均通过带有锁止卡块的横桥向滑轮与支撑横梁2.4相连,每个收卷装置2.6的吊索2.7末端设置有吊扣2.8。为了改善墩顶负弯矩区开裂的问题,使用时,按照提升吊索装置所处的位置,分为墩顶区和跨中区,且墩顶提升吊索装置的索力值F1和跨中吊索装置的索力值F2大小不同。支撑横梁2.4下方则设置运梁车2.9。As shown in Figure 9, the bridge erecting machine 2 includes a supporting beam 2.4 with a front outrigger 2.1, a middle outrigger 2.2, and a rear outrigger 2.3. 0.3 times the length of the steel girder unit 1, it is used to increase the hoisting and transportation distance of the bridge erecting machine 2; in order to solve the problem of the position of the middle outrigger 2.2 when the two-span steel girders are continuously hoisted, the middle outriggers 2.2 are two pairs The telescopic support leg that slides is set, and the longitudinal travel wheel 2.2b driven by motor 2.2a at the top of each middle support leg 2.2 is connected with the slide rail 2.2c that is arranged on the bottom surface of the support beam 2.4, and the middle support leg 2.2 and the support beam A movable latch 2.2d (see Fig. 12 ) for locking the position is arranged between 2.4. When erecting steel girders, the two pairs of center legs 2.2 are all supported on the bottom plate of the steel beams that have been erected on the top of the pier (see Figure 3); on the prefabricated bridge decks on the left and right sides (see Figure 5). The supporting beam 2.4 is equipped with a sliding lifting device 2.5 that can move along the direction of the bridge and across the bridge, which includes a pair of longitudinal guide rails located on the supporting beam 2.4. The longitudinal guide rails are slidably provided with a mobile hoist with an electric rope drawer on the top. Crossbeam, the hoisting hook that is used for hoisting steel beam is installed on the hoisting crossbeam that links to each other with electric rope take-up machine. On the supporting beam 2.4 between the front outrigger 2.1 and the rear outrigger 2.3, multiple groups of winding devices 2.6 arranged at intervals along the length direction of the bridge are installed, and each group of winding devices 2.6 has at least two devices, which are respectively installed on sliding Lifting device 2.5 both sides. Specifically, each winding device 2.6 is connected to the support beam 2.4 through a horizontal pulley with a locking block, and the end of the sling 2.7 of each winding device 2.6 is provided with a suspension buckle 2.8. In order to improve the problem of cracking in the negative moment area of the pier top, according to the position of the hoisting sling device, it is divided into the pier top area and mid-span area, and the cable force value F1 of the pier top hoisting sling device and mid-span The cable force value F2 of the sling device is different. Below the supporting crossbeam 2.4, a beam transport vehicle 2.9 is set.

架桥机2就位,即使架桥机2行进至主桥第一、二跨位置,使前支腿2.1、中支腿2.2、后支腿2.3分别站立在相应的桥墩盖梁上,此时支撑横梁2.4加长段a位于前支腿2.1以外(见图1)。The bridge erecting machine 2 is in place, even if the bridge erecting machine 2 advances to the first and second spans of the main bridge, so that the front outrigger 2.1, the middle outrigger 2.2, and the rear outrigger 2.3 stand on the corresponding pier cover beam respectively, at this time The extended section a of the support beam 2.4 is located outside the front leg 2.1 (see Figure 1).

第三步,吊装第一跨钢梁就位,然后中支腿2.2沿顺桥向移动至第一跨墩顶位置的钢梁底板上,预留架设空间,接着吊装第二跨钢梁就位。The third step is to hoist the steel beam of the first span into place, then move the middle outrigger 2.2 along the direction of the bridge to the steel beam floor at the top of the pier of the first span, reserve space for erection, and then hoist the steel beam of the second span into place .

具体地,运梁车2.9将第一跨钢梁运至支撑横梁2.4加长段a下方,使用起吊装置2.5吊装钢梁前端,钢梁后端依然放置在运梁车2.9上(见图1),钢梁缓慢前进,待钢梁后端行进至支撑横梁2.4加长段吊装范围内时,吊升钢梁的后端(见图2),进行第一跨钢梁的吊装就位(见图3);之后,中支腿2.2的两对支腿依次抬起,顺桥向移动支撑在已经架设完毕的第一跨钢梁底板上(见图3),支撑处的横断面见图10,然后按照上述步骤,通过运梁车2.9和起吊装置2.5相配合运载第二跨钢梁,并进行吊装就位(见图4)。Specifically, the beam truck 2.9 transports the steel girder of the first span to the bottom of the extended section a of the supporting beam 2.4, uses the hoisting device 2.5 to hoist the front end of the steel beam, and the rear end of the steel beam is still placed on the beam truck 2.9 (see Figure 1). Slowly move forward, and when the rear end of the steel girder reaches the hoisting range of the 2.4 extension section of the supporting beam, lift the rear end of the steel girder (see Figure 2) and hoist the steel beam of the first span into place (see Figure 3); after that, the middle The two pairs of outriggers of outrigger 2.2 are lifted up one by one, move along the bridge direction and support on the steel beam floor of the first span that has been erected (see Figure 3). The cross section of the support is shown in Figure 10, and then follow the above steps to The beam transport vehicle 2.9 and the hoisting device 2.5 cooperate to carry the second-span steel girder and hoist it in place (see Figure 4).

第四步,将第一、二跨钢梁进行纵向焊接,完成两跨钢梁“简支变连续”的体系转换;The fourth step is to longitudinally weld the steel beams of the first and second spans to complete the system conversion of the two-span steel beams from "simply supported to continuous";

第五步,同时安装第一、二跨的预制桥面板3;在此过程中,两对中支腿2.2从墩顶钢梁底板位置依次升起,沿顺桥向移动并分别支撑在墩顶两侧的第一、二跨桥面板3上(图5),支撑横断面示意图见图11;The fifth step is to install the prefabricated bridge decks 3 of the first and second spans at the same time; during this process, the two pairs of middle outriggers 2.2 are sequentially raised from the position of the bottom plate of the steel beam on the top of the pier, moved along the direction of the bridge and supported on the top of the pier respectively On the deck 3 of the first and second spans on both sides (Fig. 5), the cross-sectional schematic diagram of the support is shown in Fig. 11;

第六步,将架桥机2吊索2.7末端的吊扣2.6与第一、二跨钢梁上的吊片1.3分别连接后,对第一、二跨钢梁同时提拉,并使吊索2.7的索力在张拉至设定值后锁定,其中,顺桥向墩顶两侧吊索的索力值F1大于跨中吊索的索力值F2(见图5);In the sixth step, after connecting the buckle 2.6 at the end of the sling 2.7 of the bridge erecting machine 2 to the hanging piece 1.3 on the first and second span steel beams, pull the first and second span steel girders at the same time, and make the sling 2.7 The cable force is locked after being stretched to the set value, wherein the cable force value F1 of the cable hanging along the bridge to the top of the pier is greater than the cable force value F2 of the mid-span hanging cable (see Figure 5);

第七步,连续浇筑第一、二跨桥面板的纵横向湿接缝混凝土4,待现浇混凝土达到设计强度后,解除吊索2.7与钢梁吊片1.3之间的连接(见图6);The seventh step is to continuously pour the vertical and horizontal wet joint concrete 4 of the first and second span bridge decks. After the cast-in-place concrete reaches the design strength, release the connection between the sling 2.7 and the steel beam hanging piece 1.3 (see Figure 6) ;

第八步,使架桥机2向前行进,且每向前行进两跨时,均按照第二~七步所述的方法进行施工,直至整联桥梁架设完成(见图7)。The eighth step is to make the bridge erecting machine 2 move forward, and every time two spans are moved forward, the construction is carried out according to the method described in the second to seventh steps until the erection of the integrated bridge is completed (see Figure 7).

下面对本发明钢混组合梁的施工方法进行原理性说明。The construction method of the steel-concrete composite beam of the present invention is explained in principle below.

受力方面,对于边跨受力改善的情况,可以通过下面的计算予以说明。以50m跨径钢混组合梁为例,跨中设2个吊点,分别按照单跨施工和两跨连续施工的方式进行计算分析,将不同阶段的受力情况对比如下:In terms of force, the improvement of side span force can be explained by the following calculation. Taking the steel-concrete composite beam with a span of 50m as an example, two lifting points are set in the middle of the span, and the calculation and analysis are carried out according to the single-span construction and two-span continuous construction respectively. The stress conditions at different stages are compared as follows:

表1 主要计算结果对比 (单位:MPa)Table 1 Comparison of main calculation results (unit: MPa)

从上述的计算对比结果中可以看出,采用两跨连续浇筑施工的方式,对施工阶段的影响并不明显,但是在成桥状态,钢梁和混凝土桥面板的受力得到大幅的改善,减小了边跨的受力,对于等跨布置桥梁中边跨受力非常有利。最终成桥状态下,跨中截面钢梁的最大拉应力水平较传统无支架施工低45%左右,上缘混凝土最大压应力高43%左右,结构受力更有利。From the above calculation and comparison results, it can be seen that the two-span continuous pouring construction method has no obvious impact on the construction stage, but in the completed bridge state, the stress of the steel girder and concrete bridge deck has been greatly improved, reducing The force of the side span is reduced, which is very beneficial to the force of the side span of the bridge with equal span arrangement. In the final state of the bridge, the maximum tensile stress level of the mid-span steel girder is about 45% lower than that of the traditional construction without supports, and the maximum compressive stress of the upper edge concrete is about 43% higher, which is more favorable for the structure.

施工方面,采用常规单跨施工方法,需要在一跨主梁架设完成后,浇筑混凝土桥面板,平均施工进度约为9天/孔,而采用本发明后,两跨连续浇筑混凝土湿接缝,同等时间浇筑两跨湿接缝,平均浇筑进度为6天/孔,大大提升了施工进度,从而节省了施工费用。现以80m一孔的钢混组合梁为例,进行施工进度的对比。In terms of construction, using the conventional single-span construction method, it is necessary to pour the concrete bridge deck after the erection of the main girder of the first span is completed, and the average construction progress is about 9 days/hole. The wet joints of two spans were poured at the same time, and the average pouring progress was 6 days/hole, which greatly improved the construction progress and saved construction costs. Now take the steel-concrete composite beam with a hole of 80m as an example to compare the construction progress.

表2 单孔施工进度对比Table 2 Comparison of single hole construction progress

综上,采用本发明方法能提高材料的利用指标,同时能改善钢梁和混凝土桥面板的受力,无需增加特殊施工工序和施工机具设备,具有施工便捷等一系列优点。To sum up, the method of the present invention can improve the utilization index of materials, and at the same time, can improve the stress of steel girders and concrete bridge decks, without adding special construction procedures and construction machinery and equipment, and has a series of advantages such as convenient construction.

Claims (1)

1.一种两跨连做的钢混组合桥梁施工方法,其特征在于:包括如下步骤:1. A steel-concrete composite bridge construction method that two spans are connected, is characterized in that: comprise the steps: 第一步,根据桥梁设计方案,预制钢梁单元,并在钢梁翼缘上设置临时吊片;The first step is to prefabricate steel girder units according to the bridge design plan, and set temporary hanging pieces on the flanges of steel girders; 第二步,待桥梁基桩、桥墩施工完毕后,使架桥机行进至主桥第一、二跨位置,并使架桥机的前、中、后支腿分别站立在桥墩盖梁上,其中,中支腿为两对沿纵桥向滑动设置的伸缩式支腿,且前支腿以外的架桥机支撑横梁长度为单跨钢梁的0.2~0.3倍;In the second step, after the construction of the foundation piles and piers of the bridge is completed, the bridge erecting machine is advanced to the first and second span positions of the main bridge, and the front, middle and rear legs of the bridge erecting machine stand on the pier cover beam respectively. Among them, the middle outriggers are two pairs of telescopic outriggers that slide along the longitudinal direction of the bridge, and the length of the supporting beam of the bridge erecting machine other than the front outriggers is 0.2~0.3 times that of the single-span steel beam; 第三步,吊装第一跨钢梁就位,然后使中支腿沿顺桥向移动至第一跨墩顶位置的钢梁底板上,预留架设空间,接着吊装第二跨钢梁就位;The third step is to hoist the first-span steel girder into place, then move the middle outrigger along the direction of the bridge to the steel girder floor at the top of the first-span pier, reserve space for erection, and then hoist the second-span steel girder into place ; 第四步,将第一、二跨钢梁进行纵向焊接,完成两跨钢梁“简支变连续”的体系转换;The fourth step is to longitudinally weld the steel beams of the first and second spans to complete the system conversion of the two-span steel beams from "simply supported to continuous"; 第五步,同时安装第一、二跨的预制桥面板;在此过程中,中支腿从墩顶钢梁底板位置依次升起,沿顺桥向分别移动支撑在墩顶两侧的桥面板上;The fifth step is to install the prefabricated bridge decks of the first and second spans at the same time; during this process, the middle outriggers are sequentially raised from the position of the bottom plate of the steel beam on the pier top, and the bridge decks supported on both sides of the pier top are respectively moved along the bridge direction superior; 第六步,将架桥机吊索末端的吊扣与第一、二跨钢梁上的吊片分别连接后,对两跨钢梁同时提拉,并使吊索的索力在张拉至设定值后锁定,其中,顺桥向墩顶两侧吊索的索力值大于跨中吊索的索力值;The sixth step is to connect the buckle at the end of the sling of the bridge erecting machine to the hanging pieces on the steel beams of the first and second spans respectively, and then lift the steel beams of the two spans at the same time, and make the cable force of the slings stretch to the set point. Lock after setting the value, wherein, the cable force value of the sling along the bridge to the two sides of the pier top is greater than the cable force value of the mid-span sling; 第七步,采取一次浇筑的方式,连续浇筑第一、二跨桥面板的纵横向湿接缝混凝土,以及墩顶位置处的负弯矩区混凝土,待现浇混凝土达到设计强度后,解除吊索与钢梁吊片之间的连接;The seventh step is to adopt a one-time pouring method to continuously pour the vertical and horizontal wet joint concrete of the first and second span bridge decks, as well as the concrete in the negative moment area at the top of the pier. After the cast-in-place concrete reaches the design strength, the lifting The connection between the cable and the steel beam hanger; 第八步,使架桥机向前行进,且每向前行进两跨时,均按照第二~七步所述的方法进行施工,直至整联桥梁架设完成。The eighth step is to make the bridge erecting machine move forward, and every time two spans are moved forward, the construction shall be carried out according to the method described in the second to seventh steps until the erection of the integrated bridge is completed.
CN201910699995.8A 2019-07-31 2019-07-31 Construction method of steel-concrete composite bridge with two spans Pending CN110258352A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910699995.8A CN110258352A (en) 2019-07-31 2019-07-31 Construction method of steel-concrete composite bridge with two spans

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910699995.8A CN110258352A (en) 2019-07-31 2019-07-31 Construction method of steel-concrete composite bridge with two spans

Publications (1)

Publication Number Publication Date
CN110258352A true CN110258352A (en) 2019-09-20

Family

ID=67912503

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910699995.8A Pending CN110258352A (en) 2019-07-31 2019-07-31 Construction method of steel-concrete composite bridge with two spans

Country Status (1)

Country Link
CN (1) CN110258352A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111794109A (en) * 2020-07-16 2020-10-20 中铁十二局集团有限公司 Long-span bridge building machine and technology method for continuous hole-passing of long-span composite beams
CN112627059A (en) * 2020-12-21 2021-04-09 中建八局第三建设有限公司 Pier-beam integrated bridge girder erection machine and via hole construction method
CN113136810A (en) * 2021-05-26 2021-07-20 中交第二航务工程局有限公司 Bridge girder erection machine for integral erection construction of superstructure of long-span bridge and construction method
CN113585099A (en) * 2021-09-28 2021-11-02 中交投资南京有限公司 Deviation monitoring system for double-span synchronous tension bridge girder erection machine and construction method for reinforced concrete composite bridge
CN114351585A (en) * 2020-07-28 2022-04-15 上海宏华海洋油气装备有限公司 Bridge system that erects in succession fast
CN115125847A (en) * 2022-06-22 2022-09-30 保利长大工程有限公司 Steel plate combination beam installation construction method
CN115467239A (en) * 2022-09-28 2022-12-13 河南省交通规划设计研究院股份有限公司 Method for constructing long-span steel-concrete composite beams based on bridge erecting machine

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009221714A (en) * 2008-03-14 2009-10-01 Ps Mitsubishi Construction Co Ltd Composite girder bridge of prestressing steel concrete, and its erection method
CN104179123A (en) * 2014-08-26 2014-12-03 中国铁建大桥工程局集团有限公司 Bridge fabrication machine capable of building and assembling two bridge segments
CN105648919A (en) * 2016-01-18 2016-06-08 中国铁建大桥工程局集团有限公司 Precast segment double-span circulating assembly construction method for prestressed concrete bridge
CN107938520A (en) * 2017-12-14 2018-04-20 河南省交通规划设计研究院股份有限公司 Using the method for vertical drag-line construction steel reinforced concrete combination beam
CN108004931A (en) * 2017-12-14 2018-05-08 河南省交通规划设计研究院股份有限公司 Method of Constructing Steel-Concrete Composite Beams Using Mixed Cables
CN108330842A (en) * 2018-04-19 2018-07-27 郑州新大方重工科技有限公司 A kind of Bridge Erector and construction method of large span steel reinforced concrete combination beam erection construction
KR101885634B1 (en) * 2016-04-26 2018-08-13 (주)승주이엔씨 Corrugated Steel Plate Web-PSC beam And Bridge Construction Method Thereof
CN208087078U (en) * 2018-04-19 2018-11-13 郑州新大方重工科技有限公司 A kind of boom hoisting of large span steel reinforced concrete combination beam Bridge Erector

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009221714A (en) * 2008-03-14 2009-10-01 Ps Mitsubishi Construction Co Ltd Composite girder bridge of prestressing steel concrete, and its erection method
CN104179123A (en) * 2014-08-26 2014-12-03 中国铁建大桥工程局集团有限公司 Bridge fabrication machine capable of building and assembling two bridge segments
CN105648919A (en) * 2016-01-18 2016-06-08 中国铁建大桥工程局集团有限公司 Precast segment double-span circulating assembly construction method for prestressed concrete bridge
KR101885634B1 (en) * 2016-04-26 2018-08-13 (주)승주이엔씨 Corrugated Steel Plate Web-PSC beam And Bridge Construction Method Thereof
CN107938520A (en) * 2017-12-14 2018-04-20 河南省交通规划设计研究院股份有限公司 Using the method for vertical drag-line construction steel reinforced concrete combination beam
CN108004931A (en) * 2017-12-14 2018-05-08 河南省交通规划设计研究院股份有限公司 Method of Constructing Steel-Concrete Composite Beams Using Mixed Cables
CN108330842A (en) * 2018-04-19 2018-07-27 郑州新大方重工科技有限公司 A kind of Bridge Erector and construction method of large span steel reinforced concrete combination beam erection construction
CN208087078U (en) * 2018-04-19 2018-11-13 郑州新大方重工科技有限公司 A kind of boom hoisting of large span steel reinforced concrete combination beam Bridge Erector

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111794109A (en) * 2020-07-16 2020-10-20 中铁十二局集团有限公司 Long-span bridge building machine and technology method for continuous hole-passing of long-span composite beams
CN114351585A (en) * 2020-07-28 2022-04-15 上海宏华海洋油气装备有限公司 Bridge system that erects in succession fast
CN114351585B (en) * 2020-07-28 2023-06-16 四川宏华石油设备有限公司 Bridge system capable of being erected continuously and rapidly
CN112627059A (en) * 2020-12-21 2021-04-09 中建八局第三建设有限公司 Pier-beam integrated bridge girder erection machine and via hole construction method
CN113136810A (en) * 2021-05-26 2021-07-20 中交第二航务工程局有限公司 Bridge girder erection machine for integral erection construction of superstructure of long-span bridge and construction method
CN113136810B (en) * 2021-05-26 2025-06-27 中交第二航务工程局有限公司 A bridge erecting machine and construction method for overall erection of large-span bridge superstructure
CN113585099A (en) * 2021-09-28 2021-11-02 中交投资南京有限公司 Deviation monitoring system for double-span synchronous tension bridge girder erection machine and construction method for reinforced concrete composite bridge
CN115125847A (en) * 2022-06-22 2022-09-30 保利长大工程有限公司 Steel plate combination beam installation construction method
CN115467239A (en) * 2022-09-28 2022-12-13 河南省交通规划设计研究院股份有限公司 Method for constructing long-span steel-concrete composite beams based on bridge erecting machine

Similar Documents

Publication Publication Date Title
CN110258352A (en) Construction method of steel-concrete composite bridge with two spans
CN110344334B (en) Construction method of two-span continuous steel-concrete composite bridge using back-cable bridge erecting machine
CN110130229A (en) It a kind of several juxtaposed double cantilever erections machines and its sets a roof beam in place and passing method
CN105421249A (en) Novel dragging- hoisting combined type hanging basket structure and construction method
CN109024291A (en) A kind of integration Bridge Erector and its working method
CN112160246B (en) Method for installing composite beam
CN107938520A (en) Using the method for vertical drag-line construction steel reinforced concrete combination beam
WO2022233226A1 (en) Three-span cable crane for installation of cable-stayed bridge main girder and construction method therefor
CN115058957A (en) Dual-purpose trestle support structure
CN105088970B (en) Construction method of corrugated steel web PC box girder cable-stayed bridge
CN113120771A (en) Double-side synchronous hoisting equipment suitable for rear cantilever arm of composite-section beam bridge and construction method
CN108004932A (en) Constructed the method for steel reinforced concrete combination beam using beam mode is transported under beam
CN205205685U (en) Span wire pier is function portal device at most
CN102071641B (en) Cement beam packs bridge machine cloth supporting leg type integration of transporting and building Bridge Erector and bridge formation engineering method thereof
CN116853963B (en) A hoisting device and hoisting method for main beam of cable-stayed bridge
CN113931068A (en) Bridge deck crane for mounting steel and concrete superposed beams and beam erecting method thereof
CN108004931B (en) Using the method for mixing drag-line construction steel reinforced concrete combination beam
CN212052371U (en) Hanging basket device for variable width concrete box girder suspension casting construction
CN210368669U (en) Hoisting equipment for two-span continuous construction of combined beam
CN115182265A (en) Integrated bridge girder erection machine used under working condition of dry splicing segment bent cap and construction method
CN112030777B (en) A down-type mobile formwork support bracket spanning transfer construction method
CN105317031B (en) A kind of ship lift main equipment room bridge main beam hanging method
CN219218724U (en) Main girder hanging and paving integrated machine for combined girder cable-stayed bridge
CN111472285A (en) A method for installing the main bridge variable-section continuous steel truss girder using cable crane
CN217627283U (en) Asynchronous hanging basket with triangular truss type hoisting equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190920