CN208815424U - A kind of bridge descending hanging basket - Google Patents
A kind of bridge descending hanging basket Download PDFInfo
- Publication number
- CN208815424U CN208815424U CN201821282171.8U CN201821282171U CN208815424U CN 208815424 U CN208815424 U CN 208815424U CN 201821282171 U CN201821282171 U CN 201821282171U CN 208815424 U CN208815424 U CN 208815424U
- Authority
- CN
- China
- Prior art keywords
- basket
- main
- hanging basket
- bridge
- main truss
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000000725 suspension Substances 0.000 claims abstract description 13
- 229910000831 Steel Inorganic materials 0.000 claims description 16
- 239000010959 steel Substances 0.000 claims description 16
- 238000004873 anchoring Methods 0.000 claims description 7
- 238000005452 bending Methods 0.000 claims description 6
- 238000000034 method Methods 0.000 claims description 6
- 238000005096 rolling process Methods 0.000 claims description 6
- 239000000969 carrier Substances 0.000 claims description 4
- 238000010276 construction Methods 0.000 abstract description 11
- 230000003014 reinforcing Effects 0.000 abstract description 6
- 238000009434 installation Methods 0.000 abstract description 4
- 238000010923 batch production Methods 0.000 abstract description 3
- 230000001737 promoting Effects 0.000 abstract description 3
- 230000000875 corresponding Effects 0.000 description 3
- 238000010586 diagram Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 241001669679 Eleotris Species 0.000 description 1
- 210000004279 Orbit Anatomy 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 230000015271 coagulation Effects 0.000 description 1
- 238000005345 coagulation Methods 0.000 description 1
- 230000003028 elevating Effects 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 238000003032 molecular docking Methods 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 230000001360 synchronised Effects 0.000 description 1
Abstract
The utility model belongs to equipment for bridge construction technical field, more particularly to a kind of bridge descending hanging basket, solve that deck type Hanging Basket built-in fitting is more, big from great, occupied space, Hanging Basket walking security risk is high, reinforcing bar live can only also be bound, the operation difficulty big influence construction period, and existing descending hanging basket has the problem of security risk, including main truss system, suspension system, anchor system and running gear during large-sized concrete Cantilever Beam Construction.The utility model is designed reasonably, built-in fitting needed for having entirety is few, from heavy and light, occupy little space, reinforcing bar can be using batch production processing integral hoisting installation accuracy is high, walking risk is small, easy to operate, the construction advantages such as rapidly;It is applied widely, there is certain promotional value and application value.
Description
Technical field
The utility model belongs to equipment for bridge construction technical field, and in particular to a kind of bridge descending hanging basket.
Background technique
Hanging Basket is the capital equipment in bridge cantilever construction, currently used cradle structure include deck type triangle hanging basket,
Diamond-Shape Form Traveler, truss hang kep and hybrid Hanging Basket etc., such Hanging Basket are arranged at the top of beam body, this kind of Hanging Basket built-in fitting
It is more, big from great, occupied space, Hanging Basket walking security risk is high, reinforcing bar also can only scene bind, the big influence of operation difficulty is constructed
Duration.
In view of the foregoing drawbacks, those skilled in the relevant art design the downstriker used for cable-stayed bridge dragging suspension basket and hang
Basket, as application No. is a kind of descending hanging baskets disclosed in CN201410400749.5.Including bottom platform, it is set to bridge bottom,
It includes stringer, front beam, rear cross beam sum number passage stringer, and front beam, rear cross beam distinguish one in front and one in back lateral connection stringer, number
Passage stringer connects front beam and rear cross beam;Template system, including template and bracket, bracket are set to the left and right of bottom platform
Both ends;Pull cord system, positioned at the front end of stringer;Anchor system, including sunpender and rear elevating lever, sunpender, which is anchored at, has poured coagulation
On soil;Stop system is deep into concrete preformed hole and is set to above main longitudinal grider middle-end;And running gear, it is installed on
The front end and middle part of stringer comprising walking support sunpender, walking support and Hanging Basket liquid in place is exercised before Hanging Basket for pushing
Cylinder pressure, walking support sunpender are anchored on casting concrete, and walking support is installed on walking support boom foot.Though the invention
It so can solve corresponding technical problem, but primarily directed to the improvement of cable-stayed bridge dragging suspension basket, do not have universal significance.
In addition, a kind of utility model application No. is CN201120190226.4 discloses a kind of master of descending hanging basket
Purlin suspension arrangement, including rear upper beam, are horizontally installed on and have poured beam upper front end;Two C-arms, one end pass through connection respectively
Part is fixed in two ends of rear upper beam, and downwards, horizontal ends protrude into the through slot of main truss hanger the other end;Main truss
Hanger, and has poured beam central symmetry, and its underpart is articulated with hanging basket main truss, and middle part is equipped with through slot, and there are multiple sunpenders to wear on top
It is separated in rear cross beam corresponding position, or releasing sunpender, main truss hanger with beam has been poured after having poured beam and rear cross beam hanging, hangs over c-type
On the supporting surface of the horizontal ends of arm.This utility model is designed to provide a kind of sky that can effectively realize descending hanging basket
Forward, and the main truss suspension arrangement of the descending hanging basket with certain bearing capacity are carried, to solve to pour when the concrete of Anterior Segment
It builds after finishing, by the unloaded hanging basket advancing problem big to next segment difficulty, but structure is relatively easy is more suitable for tonnage not
Big bridge uses, and for large-scale concrete Cantilever Beam Construction, there is a certain security risk.
Summary of the invention
Deck type Hanging Basket built-in fitting is more, Hanging Basket walking safety wind big from great, occupied space in order to solve for the utility model
Danger is high, and reinforcing bar live can only also be bound, the operation difficulty big influence construction period, and existing descending hanging basket is in large-sized concrete
There is the problem of security risk during Cantilever Beam Construction, provide a kind of bridge descending hanging basket.
The utility model is achieved by the following technical solution: a kind of bridge descending hanging basket, including main truss system, outstanding
Crane system, anchor system and running gear, main truss system include that main couple, rear upper beam and C-type beam, main couple are symmetricly set on
The both ends of upper beam afterwards, rear upper beam initial setting up on O block and be parallel to bridge width setting, C-type beam be arranged rear
Between upper beam and main couple, running gear includes track, pipe bending cylinder and main couple reaction wheel, length direction of the track along bridge
It being symmetrical arranged, rail superior portion is provided with rail wheel, and rail wheel is arranged in track wheel carrier, and track wheel carrier is connect with pipe bending cylinder,
It is provided with front beam between before two symmetrically arranged main couples, the preceding sunpender perpendicular to ground, preceding sunpender are connected on front beam
Beam is dragged before being connected with bottom basket in bottom, and rear upper beam is connected with back strap, and back strap bottom is connected with and drags Liangping row before the basket of bottom
Joist after the basket of bottom is provided with bottom basket bottom girder between joist after Tuo Liang and bottom basket before the basket of bottom, joist and bottom after Tuo Liang, bottom basket before the basket of bottom
Basket bottom girder collectively forms bottom basket system, and front beam lower part is provided with symmetrical central bearing point anchoring fining twisted steel, wherein
Every Pin main couple uses 4 40 fining twisted steels of φ, and there are the hydraulic self-locking jack of counter-force and main truss in the rear fulcrum position of main couple
Frame reaction wheel installs preceding No. 0 block in front beam and is internally provided with interior skid beam, using jack that two internal model skid beams are temporarily fixed flat
Surely, interior skid beam is lifted by crane again after front beam is installed, rear end is mounted on lifting lug prior to interior skid beam, is then moved forward
Interior skid beam is connected and fixed the finish rolling screw thread lifting lug installed on its front end and front beam, and internal model and bracket are provided in interior skid beam.
Main couple is in inverted trapezoidal structure, is made of main truss top boom, main truss lower boom and main truss web member, and main truss winds up
Bar, main truss lower boom and main truss web member are channel steel make-up and the rectangular rod piece being welded to form.
Suspension system includes front beam, interior skid beam, back strap, preceding sunpender and C-type beam, front beam by model HN500 ×
200 hot rolled H-shaped group of weldering processing, back strap use specification to be process for 25 × 160 Q345 steel plate, and preceding sunpender uses
Diameter is the fining twisted steel of φ 32.
The specified features and beneficial effect that the utility model has compared with prior art are:
The utility model is designed reasonably, have entirety needed for built-in fitting it is few, from heavy and light, occupy little space, reinforcing bar can be adopted
With batch production processing integral hoisting installation accuracy is high, walking risk is small, the easy to operate, advantages such as rapid of constructing;Meanwhile this is practical
Novel structural integrity is strong, improves the stress performance of Hanging Basket entirety, applied widely, is used especially for large-scale concrete
The construction of cantilever beam has certain promotional value and application value.
Detailed description of the invention
Fig. 1 is the side assembly structure diagram of the utility model;
Fig. 2 is the structural schematic diagram of Section A-A in Fig. 1;
Fig. 3 is the structural schematic diagram of section B-B in Fig. 1.
In figure: 1- main couple, 1-1- main truss top boom, 1-2- main truss lower boom, 1-3- main truss web member drag before the basket of the bottom 2-1-
Beam, joist after the basket of the bottom 2-2-, the bottom 2-3- basket bottom girder, 3-1- central bearing point anchor fining twisted steel, 3-2- counter-force hydraulic self-locking thousand
Jin pushes up, 4-1- front beam, skid beam in 4-2-, 4-3- back strap, sunpender before 4-4-, 4-5-C type beam, upper beam after 5-, 5-1- rail
Road, 5-2- pipe bending cylinder, 5-3- main couple reaction wheel, 5-4- rail wheel, 6-1- external mold and bracket, 6-2- internal model and bracket, 7-
1- workbench, 7-2- guardrail, 7-3- ladder, 7-4- jack.
Specific embodiment
The utility model is further elaborated in referring to Fig.1~Fig. 3, and of the present invention is a kind of bridge downstriker extension
Basket.Descending hanging basket includes main truss system, bottom basket system, anchor system, suspension system, running gear, outer modular system, interior module system
The parts such as system, subsystem.
Wherein: main couple 1 is truss structure, by main truss top boom 1-1, main truss top boom 1-2 and main truss web member 1-3 group
At, and the square-section rod piece that above-mentioned component is welded to form by the common hot-rolled steel channel of model 40b by make-up.
Bottom basket: it is made of joist 2-2 after joist 2-1, bottom basket before the basket of bottom and bottom basket bottom girder 2-3.Before the basket of bottom joist 2-1 and
Joist 2-2 is welded by hot rolled H-shaped group of model HN450 × 200 after the basket of bottom, and bottom basket bottom girder 2-3 uses model
HN350 × 200 are hot rolled H-shaped to be process.
Anchor system: the central bearing point anchoring fining twisted steel 3-1 of descending hanging basket is for anchoring main couple 1, every Pin main truss
Frame 1 uses 4 40 fining twisted steels of φ, and rear fulcrum provides support reaction using the hydraulic self-locking jack 3-2 of counter-force.
Suspension system: it is made of front beam 4-1, interior skid beam 4-2, back strap 4-3, preceding sunpender 4-4 and C-type beam 4-5, preceding cross
Beam 4-1 is processed by hot rolled H-shaped group of weldering of model HN500 × 200;Back strap 4-3 use specification for 25 × 160 Q345
Steel plate, sunpender use diameter for the fining twisted steel of φ 32.
Running gear: including track 5-1, pipe bending cylinder 5-2 and main couple reaction wheel 5-3.
Template system: including external mold and bracket 6-1, internal model and bracket 6-2.
Subsystem: including workbench 7-1, guardrail 7-2, ladder 7-3 and jack 7-4 etc..
The assembled process of descending hanging basket described in the utility model:
1. surveying setting-out
Before form traveler hoisting, the sundries being located on the face bridge 0# Duan Liang should be cleaned out, precise measurement is indicated in bridge
Line and vertical control point, hanging basket track 5-1 and support position, two sets of Hanging Baskets in 1 0# beam section should be symmetrically installed simultaneously, it is ensured that
Beam body both ends stress balance.
2. attachment rail 5-1
Walking rails 5-1 is placed in 0# beam section top surface, track is anchored on beam body top surface by track 5-1 after placing.
Track 5-1 must not have track 5-1 connector (i.e. two rail rail docking phenomenons) in splicing at sliding support.
3. installing running part and C-type beam support
The movable bearing support of upper beam 5 after support is installed on track 5-1 first, then upper beam after 5 is placed on support
Operating position, rear upper beam 5 is steady with sleeper supporting, holds rear upper beam in four direction using 4 3T jacks and consolidates.
4. installing C-type beam 4-5 and main couple 1
First main couple reaction wheel 5-3, jacking cylinder are mounted on main couple in advance in the place of bridge pier lower part, then will
C-type beam 4-5 and main couple 1 are assembled, then by more than assembled good 1 integral hoisting to beam portion of C-type beam 4-5 and main couple,
It is assembled with the rear upper beam 5 having good positioning, the anchoring sunpender between C-type beam 4-5 and rear upper beam 5 is installed, sunpender upper end connects
C-type beam 4-5 flange plate top beam body is connect, lower end connects flange plate lower part C-type beam body, keeps rear upper beam 5 and C-type beam 4-5 secured
Hold around in beam body, at the same by near the main couple reaction wheel 5-3 of two sides to drawing finish rolling deformed bar to pass through web and fastening.
5. installing front beam 4-1 and rear upper beam 5
Front beam 4-1 and rear upper beam 5 are lifted on main couple 1, front beam 4-1 and rear upper beam 5 are adopted with main couple 1
With bolt anchor connection, all connection bolts must use high-strength bolt, then install on front beam 4-1 and rear upper beam 5
Finish rolling screw thread sunpender.
6. installing Hanging Basket bottom basket
(1) before Hanging Basket bottom basket being installed, platform assembly Hanging Basket bed die is set up under bridge pier, must assure that in the installation of Hanging Basket bed die
Bed die template flatness adjusts the forward and backward crossbeam of bed die in same plane.
(2) two groups of pulley blocks are respectively set in the forward and backward suspension centre of main couple 1, hang wirerope on the forward and backward crossbeam of bed die, so
Afterwards with hoist engine lifting bed die to corresponding position, after the completion of lifting, two bottom anchor structures on joist, are then installed after first installing
Each suspension centre and articulated mounting on forward and backward crossbeam.
7. installing side form
By side form and edge of a wing truss, assembling is finished in place under bridge, is promoted on the inside of side form to main couple 1 with lifting equipment,
It is fixed temporarily, props up and adjust strut.
8. installing internal model skid beam and template
(1) interior skid beam 4-2 is hung in advance to 0# beam section before front beam 4-1 and rear upper beam 5 are installed, using
Chain is temporarily fixed steady by two interior skid beam 4-2.Front beam 4-1 and rear upper beam 5 play internal model skid beam after being installed again
It hangs, first the rear end interior skid beam 4-2 is mounted on lifting lug, then moving forward interior skid beam 4-2 makes the front end interior skid beam 4-2 and front beam
The finish rolling screw thread lifting lug installed on 4-1 and rear upper beam 5 is attached, and completes the installation of internal model skid beam system.
(2) internal model truss is hung piece by piece and is mounted in internal model skid beam, after fixation, block-by-block installs inside molding plate.
9. successively installing each position workbench, guardrail and ladder
10. locking whole sunpenders and suspender belt after adjusting external mold of outer die and internal model absolute altitude
The moving process of descending hanging basket described in the utility model:
The measuring track 5-1 center line on the beam face for poured segment clears up the concrete surface within the scope of track 5-1
Leveling.The connector of adjacent orbit 5-1 should be smooth.Check whether the safety device of each key position when traveling Hanging Basket adds, it is each to sell
In place whether the split pin of axis.The sunpender on the forward and backward crossbeam of bed die is loosened, so that bed die system is detached from beam body bottom plate by gravity.
Adjusting side mould screw rod outward, and side form template is pulled using jack auxiliary, it is detached from 5~15cm of beam body web, loosens front beam
5~15cm of front overhang sunpender on 4-1 and rear upper beam 5.For anchoring the finish rolling screw thread of main couple 1 on upper beam 5 after after loosening
Sunpender releases and locks to the part of main couple 1 in the vertical direction, rear 5 support of upper beam laid down, after slowly releasing main couple 1
The mechanical caging of jacking cylinder is held, jacking cylinder is withdrawn, makes Hanging Basket entire lowering, leans forward, so that the inverse buckling wheel of flange plate bottom
With both rail wheel 5-4 of rear 5 lower part of upper beam collective effect, depend on Hanging Basket integrally on beam body top plate and flange plate.?
Bolt hangs φ 22.5mm wirerope on hook plate afterwards, and 10 tons of guide chains are respectively installed in two sides wirerope front end.During traveling, left and right two
The truss of side will keep synchronous, should suitably slow down close at beam-ends 1m.Traveling in place, after timely installment work anchor and it is rear after on
Beam support rises main couple rear end jacking cylinder, loosens inverse buckling wheel.The position adjustment of main couple 1 is correct, it is flat to lift bed die
Its rear end anchoring is installed in place by platform.Bottom die platform adjustment is correct, the suspension sunpender of locking front and back upper beam.By outer side mold
Plate adjustment is correct, locking suspention, anchor rod.
The utility model built-in fitting is few, from heavy and light, occupy little space, reinforcing bar can be using batch production processing integral hoisting peace
The advantages such as precision is high, walking risk is small, easy to operate, construction is rapid are filled, it is applied widely, with certain promotional value and answer
With value.
Claims (3)
1. a kind of bridge descending hanging basket, it is characterised in that: including main truss system, suspension system, anchor system and running gear,
Main truss system includes main couple (1), rear upper beam (5) and C-type beam (4-5), and main couple (1) is symmetricly set on rear upper beam (5)
Both ends, rear upper beam (5) initial setting up on O block and be parallel to bridge width setting, C-type beam (4-5) be arranged rear
Between upper beam (5) and main couple (1), running gear includes track (5-1), pipe bending cylinder (5-2) and main couple reaction wheel (5-
3), track (5-1) is symmetrical arranged along the length direction of bridge, and the top track (5-1) is provided with rail wheel (5-4), rail wheel (5-
4) be arranged in track wheel carrier, track wheel carrier is connect with pipe bending cylinder (5-2), before two symmetrically arranged main couples (1) between set
It is equipped with front beam (4-1), the preceding sunpender (4-4) perpendicular to ground is connected on front beam (4-1), the preceding sunpender bottom (4-4) connects
It is dragged beam (2-1) before being connected to bottom basket, rear upper beam (5) is connected with back strap (4-3), and the bottom back strap (4-3) is connected with and bottom basket
Before drag beam (2-1) parallel bottom basket after joist (2-2), drag before the basket of bottom and be provided with bottom basket between joist (2-2) after beam (2-1) and bottom basket
Bottom girder (2-3) drags before the basket of bottom joist (2-2) and bottom basket bottom girder (2-3) after beam (2-1), bottom basket to collectively form bottom basket system,
The lower part front beam (4-1) is provided with symmetrical central bearing point anchoring fining twisted steel (3-1), wherein every Pin main couple (1) is adopted
With 4 40 fining twisted steels of φ, the rear fulcrum position of main couple (1) has the hydraulic self-locking jack of counter-force (3-2) and main couple anti-
Wheels (5-3) installs preceding No. 0 block at front beam (4-1) and is internally provided with interior skid beam (4-2), using jack that two internal models are sliding
Beam is temporarily fixed steady, and front beam (4-1) lifts by crane interior skid beam (4-2) after being installed again, prior to interior skid beam (4-2) will after
End is mounted on lifting lug, and then moving forward interior skid beam (4-2) hangs the finish rolling screw thread installed on its front end and front beam (4-1)
Ear is connected and fixed, and internal model and bracket (6-2) are provided on interior skid beam (4-2).
2. a kind of bridge descending hanging basket according to claim 1, it is characterised in that: main couple (1) is in inverted trapezoidal structure,
It is made of main truss top boom (1-1), main truss lower boom (1-2) and main truss web member (1-3), and under main truss top boom (1-1), main truss
Chord member (1-2) and main truss web member (1-3) are channel steel make-up and the rectangular rod piece being welded to form.
3. a kind of bridge descending hanging basket according to claim 1, it is characterised in that: suspension system includes front beam (4-
1), interior skid beam (4-2), back strap (4-3), preceding sunpender (4-4) and C-type beam (4-5), front beam (4-1) by model HN500 ×
200 hot rolled H-shaped group of weldering processing, back strap (4-3) use specification to be process for 25 × 160 Q345 steel plate, preceding sunpender
(4-4) uses diameter for the fining twisted steel of φ 32.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821282171.8U CN208815424U (en) | 2018-08-10 | 2018-08-10 | A kind of bridge descending hanging basket |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821282171.8U CN208815424U (en) | 2018-08-10 | 2018-08-10 | A kind of bridge descending hanging basket |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208815424U true CN208815424U (en) | 2019-05-03 |
Family
ID=66272900
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821282171.8U Active CN208815424U (en) | 2018-08-10 | 2018-08-10 | A kind of bridge descending hanging basket |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208815424U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111764668A (en) * | 2020-07-17 | 2020-10-13 | 汤仁超 | Steel structure bridge truss installation system and installation process |
CN113174866A (en) * | 2021-05-12 | 2021-07-27 | 中交二公局东萌工程有限公司 | High-pier continuous steel bridge bracket and construction method |
CN113338168A (en) * | 2021-06-24 | 2021-09-03 | 中交二航局第四工程有限公司 | Cantilever beam construction is with hanging basket with high security |
-
2018
- 2018-08-10 CN CN201821282171.8U patent/CN208815424U/en active Active
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111764668A (en) * | 2020-07-17 | 2020-10-13 | 汤仁超 | Steel structure bridge truss installation system and installation process |
CN111764668B (en) * | 2020-07-17 | 2022-03-01 | 湖南凯博杭萧建筑科技股份有限公司 | Steel structure bridge truss installation system and installation process |
CN113174866A (en) * | 2021-05-12 | 2021-07-27 | 中交二公局东萌工程有限公司 | High-pier continuous steel bridge bracket and construction method |
CN113338168A (en) * | 2021-06-24 | 2021-09-03 | 中交二航局第四工程有限公司 | Cantilever beam construction is with hanging basket with high security |
CN113338168B (en) * | 2021-06-24 | 2023-01-10 | 中交二航局第四工程有限公司 | Hanging basket with high safety for cantilever beam construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208815424U (en) | A kind of bridge descending hanging basket | |
CN102094392B (en) | Lower supported hanging basket in bridge construction and application thereof | |
CN109944170A (en) | Continuous beam with high-pier end bay Cast-in-Situ Segment and closure section integrated construction system and construction method | |
CN103074854B (en) | Rear supporting point triangular bracket hanging basket and bridge construction method using same | |
CN201169749Y (en) | Simple-mounted pin connection triangle hanging basket | |
CN106381814A (en) | Cast-in-cantilever structure of movable crane formwork of zigzag-form steel web continuous box beam and construction method of cast-in-cantilever structure | |
CN102134832B (en) | Movable support and movable support assisted method for erecting steel box beams through non-variable amplitude frame beam crane | |
CN110055908B (en) | Demolition construction method of upstroke movable formwork for bridge construction | |
CN102926330B (en) | Installation method of hanging basket suitable for bridge construction | |
CN110700119A (en) | Upper traveling system of assembled Bailey beam hanging basket and design method thereof | |
CN201972099U (en) | Through type hanging basket in bridge construction | |
CN205932963U (en) | Many landing legs tire formula tracklaying crane | |
CN212479255U (en) | Construction equipment for two linings of anchor chamber vault of suspension bridge tunnel | |
CN108086168A (en) | Ride cable-styled erection crane | |
CN102225580B (en) | Method for longitudinally moving box girder internal mold | |
CN205529915U (en) | Ladder type masts type hangs pieces together loop wheel machine | |
CN201588172U (en) | Integral single-tower non-dorsal-cord cable-stayed-bridge king tower lifting template | |
CN112695650A (en) | Downward movable formwork method construction method for shoal variable-curve wide cast-in-place beam | |
CN210856948U (en) | Cable-passing type bridge floor crane for central double-cable-plane cable-stayed bridge | |
CN203049471U (en) | Rear fulcrum triangular bracket hanging basket | |
CN207987749U (en) | Ride cable-styled erection crane | |
CN111622781A (en) | Construction equipment and method for suspension bridge tunnel anchor chamber vault secondary lining | |
CN110528401A (en) | Suspended pouring construction hanging basket system | |
CN111042004A (en) | Hanging basket track beam traveling method | |
CN210341665U (en) | Installation device for corrugated steel web of suspension casting bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |