CN102225580B - Method for longitudinally moving box girder internal mold - Google Patents
Method for longitudinally moving box girder internal mold Download PDFInfo
- Publication number
- CN102225580B CN102225580B CN 201110097867 CN201110097867A CN102225580B CN 102225580 B CN102225580 B CN 102225580B CN 201110097867 CN201110097867 CN 201110097867 CN 201110097867 A CN201110097867 A CN 201110097867A CN 102225580 B CN102225580 B CN 102225580B
- Authority
- CN
- China
- Prior art keywords
- box girder
- storage area
- inner formwork
- formwork
- rail wheel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
本发明涉及桥梁箱梁浇筑成型类,特别是一种箱梁内模纵移方法。其特征在于包括如下步骤:吊装箱梁整体钢筋笼至制梁台座上,调整及检验好钢筋笼;在箱梁预制台座上沿纵向依次安装反轨轮及其支撑架,并经制梁台座两端向外延伸铺设安装,以在制梁台座外构成箱梁内模存放区;采用卷扬机牵引处于收缩状态之箱梁内模,将所述箱梁内模沿反轨轮整体由存放区拖拉到制梁台座或由制梁台座拖拉至存放区,实现箱梁内模的纵移,其优点是:内模整体一次从梁体内一端抽出,无需人工拆模板和螺栓,内模全部采用液压油缸进行缩放。螺旋撑杆可悬于主梁上,无需人工搬运出梁体;利用内模自身主梁作为纵移轨道无需另外再铺设钢轨。
The invention relates to casting and forming of bridge box girders, in particular to a method for longitudinally moving inner molds of box girders. It is characterized in that it includes the following steps: hoisting the overall reinforcement cage of the box girder to the beam-making platform, adjusting and inspecting the reinforcement cage; The end is extended outwards for laying and installation to form a box girder inner mold storage area outside the girder base; the box girder inner mold in a contracted state is pulled by a winch, and the box girder inner mold is dragged along the anti-rail wheel from the storage area to the The beam-making pedestal or the beam-making pedestal is dragged to the storage area to realize the longitudinal movement of the inner formwork of the box girder. The advantage is that the whole inner formwork is pulled out from one end of the beam body at one time, and there is no need to manually remove the formwork and bolts. The inner formwork is all carried out by hydraulic cylinders. zoom. The spiral struts can be suspended on the main beam without manually carrying out the beam body; using the main beam of the internal mold as the longitudinal movement track does not require laying additional rails.
Description
技术领域 technical field
本发明涉及桥梁箱梁浇筑成型类,特别是一种箱梁内模纵移方法。 The invention relates to casting and forming of bridge box girders, in particular to a method for longitudinally moving inner molds of box girders.
背景技术 Background technique
在高速公路桥梁建设中,预应力预制箱梁的应用越来越普遍。而其预制箱梁内模多采用组合模板。它是工程施工中使用最多的一种模板形式。它由具有一定模数的若干类型的板块、角模、支撑和连接件组成,用它可以拼出多种尺寸和几何形状。施工时可以在现场直接组装,亦可以预拼装成大块模板或构件模板用起重机吊运安装。组合模板的板块有全钢材制成,亦有用钢框与木(竹)胶合板面板复合制成。组合模板不但用于建筑工程、桥梁工程,地下工程亦广泛应用。但对于低高度组合内模人工进入箱室内拆除模板比较困难,耗时费工,不仅使施工成本增加,而且影响施工进度;此外,在拆除时对模型进行敲击,容易使箱梁内模发生变形,影响以后施工的梁体质量。 In highway bridge construction, the application of prestressed prefabricated box girder is more and more common. And its prefabricated box girder inner mold mostly adopts combined formwork. It is the most widely used formwork form in engineering construction. It is composed of several types of plates with a certain modulus, angle formwork, supports and connectors, and it can be used to spell out various sizes and geometric shapes. It can be directly assembled on site during construction, or it can be pre-assembled into a large formwork or component formwork and hoisted and installed by a crane. The plates of the combined formwork are made of all steel, and are also made of composite steel frames and wood (bamboo) plywood panels. Combined formwork is not only used in construction engineering, bridge engineering, but also in underground engineering. However, it is difficult for the low-height combined internal formwork to enter the box room to remove the formwork, which is time-consuming and labor-intensive, which not only increases the construction cost, but also affects the construction progress; Deformation will affect the quality of the beam body in future construction.
除上述的常见方法之外,在《全自动液压预制箱梁内模系统》申请(专利)号CN200610201284.6中公开了一种内模的移模方法。做法是:内模板由顶模与一对上阴角模和一对下阴角模铰接而成,上斜向油缸连接于顶模与上阴角模之间,下斜向油缸连接于上阴角模与下阴角模之间,在内模板围合成的空腔底部中央沿箱梁进深间隔设有支撑架,支撑架上架设钢轨,钢轨上行走平移小车,平移小车包括走行轮、车架和固定在车架上的支座梁,平移小车的车架延伸至内模板外,其上安放液压泵站及操作台。本发明结构简单,用钢量少,成本低廉,使用操作简单、平移小车可整体行走,方便了内模的整体出入。 In addition to the common methods mentioned above, a method for moving the inner mold is disclosed in the application (patent) No. CN200610201284.6 of "Automatic Hydraulic Prefabricated Box Girder Internal Mold System". The method is: the inner formwork is hinged by a top die, a pair of upper female corner dies and a pair of lower female corner dies, the upper inclined oil cylinder is connected between the top die and the upper female corner die, and the lower inclined oil cylinder is connected to the upper female corner die. Between the corner formwork and the lower female formwork, a support frame is provided along the depth of the box girder in the center of the cavity formed by the inner formwork, and a steel rail is erected on the support frame, and a translation trolley runs on the rail. And the support beam fixed on the frame, the frame of the translation trolley extends to the outside of the inner formwork, and the hydraulic pump station and the operation table are placed on it. The invention has the advantages of simple structure, less steel consumption, low cost, simple use and operation, and the translation trolley can travel as a whole, which facilitates the overall entry and exit of the inner mold.
以上专利所公开的技术方案虽然具有一定的优点,但是需要设置钢轨和平移小车来配合内模的移动,增加了大量的设备辅助施工,在桥梁建设中推广不便;另一方面采用钢轨的话,无法根据实际施工中需求自由延伸,局限性较强。 Although the technical solutions disclosed in the above patents have certain advantages, they need to set rails and translation trolleys to cooperate with the movement of the inner mold, which adds a large amount of equipment to assist construction, and it is inconvenient to promote in bridge construction; on the other hand, if rails are used, it is impossible According to the actual construction needs free extension, strong limitations.
发明内容 Contents of the invention
本发明的目的是根据上述现有技术的不足之处,提供一种箱梁内模纵移方法,该方法利用内模自身主梁作为纵移轨道,并在制梁台座内及其两端向外延伸设置反轨轮及其支撑架,该反轨轮与内模主梁配合设置,通过卷扬机等设备可实现内模在箱梁内的纵移。 The purpose of the present invention is to provide a method for the longitudinal movement of the box girder inner formwork according to the shortcomings of the above-mentioned prior art. The anti-rail wheel and its supporting frame are arranged on the outer extension, and the anti-rail wheel is set in cooperation with the main beam of the inner mold, and the longitudinal movement of the inner mold in the box girder can be realized through hoist and other equipment.
本发明目的实现由以下技术方案完成: The object of the present invention is realized by the following technical solutions:
一种箱梁内模纵移方法,其特征在于包括如下步骤:吊装箱梁整体钢筋笼至制梁台座上,调整及检验好钢筋笼;在箱梁预制台座上沿纵向依次安装反轨轮及其支撑架,并经制梁台座两端向外延伸铺设安装,以在制梁台座外构成箱梁内模存放区;采用卷扬机牵引处于收缩状态之箱梁内模,将所述箱梁内模沿反轨轮整体由存放区拖拉到制梁台座或由制梁台座拖拉至存放区,实现箱梁内模的纵移。 A method for longitudinally moving the inner mold of a box girder, which is characterized in that it includes the following steps: hoisting the overall reinforcement cage of the box girder to the beam-making platform, adjusting and inspecting the reinforcement cage; installing anti-rail wheels and Its supporting frame is extended and installed through the two ends of the beam-making base to form a storage area for the box girder inner mold outside the beam-making base; the box girder inner mold in the shrinking state is pulled by a hoist, and the box girder inner mold is pulled The anti-track wheel is dragged from the storage area to the beam-making pedestal or from the beam-making pedestal to the storage area to realize the longitudinal movement of the inner mold of the box girder.
所述箱梁内模主梁下侧与所述反轨轮的接触面上设置有与所述反轨轮配合之轨道。 A track cooperating with the anti-rail wheel is arranged on the contact surface between the lower side of the main girder of the box girder inner mold and the anti-rail wheel.
所述的其内设置有反轨轮及其支撑架的预制台座数量为复数个,且纵向排列并通过所述存放区之反轨轮及其支撑架过渡连接。 The number of prefabricated pedestals with anti-track wheels and their support frames inside is multiple, arranged vertically and transitionally connected by the anti-track wheels and their support frames in the storage area.
本发明的优点是: The advantages of the present invention are:
1、内模整体一次从梁体内一端抽出,无需人工拆模板和螺栓,内模全部采用液压油缸进行缩放。螺旋撑杆可悬于主梁上,无需人工搬运出梁体。 1. The whole inner mold is pulled out from one end of the beam body at one time, without manually dismantling the formwork and bolts, and the inner mold is all scaled by hydraulic cylinders. The spiral braces can be suspended on the main beam without manual transport out of the beam.
2、利用内模自身主梁作为纵移轨道无需另外再铺设钢轨; 2. Using the main girder of the internal mold as the longitudinal moving track does not need to lay additional rails;
3、内模主梁具有较高的强度和刚度,整套内模既可整体吊装入模,亦可自行滑入钢筋笼内再伸出油缸立模,吊装内模无需吊架和其它特殊吊具,吊装非常方便; 3. The main beam of the inner mold has high strength and rigidity. The whole set of inner mold can be hoisted into the mold as a whole, or can be slid into the steel cage by itself and then stretched out of the cylinder to form the mold. There is no need for hangers and other special lifting tools for hoisting the inner mold , the hoisting is very convenient;
4、内模自重大,可有效防止浇注过程中模板上浮; 4. The inner mold is self-heavy, which can effectively prevent the formwork from floating during the pouring process;
5、内模的支撑架设计了走行起落架,单人即可轻松将支撑架拖出梁体内腔。 5. The supporting frame of the inner mold is designed with a walking landing gear, and a single person can easily drag the supporting frame out of the cavity of the beam body.
附图说明 Description of drawings
附图1为本发明内膜整体结构示意图; Accompanying drawing 1 is a schematic diagram of the overall structure of the inner membrane of the present invention;
附图2为本发明内模中节段撑开状态示意图;
Accompanying
附图3为本发明内模中节段收缩状态示意图;
附图4为本发明内膜纵移过程示意图。 Figure 4 is a schematic diagram of the process of intima longitudinal displacement in the present invention.
具体实施方式 Detailed ways
以下结合附图通过实施例对本发明特征及其它相关特征作进一步详细说明,以便于同行业技术人员的理解: The features of the present invention and other related features will be further described in detail below in conjunction with the accompanying drawings through embodiments, so as to facilitate the understanding of those skilled in the art:
如图1-4所示,标号1-7分别表示:制梁台座1、内模2、反轨轮3、支撑架4、存放区5、轨道6、横梁7。
As shown in Figures 1-4, the labels 1-7 respectively represent: beam-making pedestal 1,
参见图2,本实施例中所涉及的结构主要有内模托架和内膜2: Referring to Figure 2, the structures involved in this embodiment mainly include the inner mold bracket and the inner membrane 2:
内模托架由反轨轮3、横梁7及支撑架4三部分组成。安装内模托架(共8个)时将其整体抬入底板钢筋预留孔中(即利用箱梁底模泄水孔中),同时支撑架4下端螺杆需对应底模上预留孔,通过螺母联结与底模连成一体,保持其整体稳定性。对应的,内模2主梁下侧与所述反轨轮3的接触面上设置有与所述反轨轮配合之轨道6。采用此种结构,利用内模2自身主梁作为纵移轨道无需另外再铺设钢轨,而在两个制梁台座1中部均布若干内模托架后,可使内模2由一个制梁台座1移动至另一个制梁台座1上,之后拆除不再使用的内模托架,铺设到下段待运送的区域。避免了采用在钢轨上移动内膜2方案时,内膜2受限于钢轨长度而无法连续移动,只能采取悬吊移动和滑动相结合的手段。
The inner mold bracket is made up of
结合上述装置结构,以下对于本实施例中方法进行详细描述: In combination with the above device structure, the method in this embodiment is described in detail below:
1、吊装箱梁整体钢筋笼至制梁台座1上,调整及检验好钢筋笼; 1. Lift the overall reinforcement cage of the box girder to the beam-making platform 1, adjust and inspect the reinforcement cage;
2、安装端部及中部反轨轮3及支撑架4至箱梁制梁台座1上相应位置;
2. Install the end and middle
3、采用5t卷扬机牵引内模2,将存放在存放区5中的反轨轮3上的内模2整体拖拉到制梁台座1相应位置;
3. Use a 5t winch to pull the
4、靠液压油缸的支顶作用,内模2按先后顺序逐渐张开撑起;
4. Relying on the supporting effect of the hydraulic cylinder, the
5、待内模2全部张开,人进入内模2,采用螺旋撑杆和销轴对内模2进行支撑加固,再将端模安装到位;
5. After the
6、脱模时人进入箱体内部将内模2加固撑杆取下,操纵放置于内模2外端的液压控制系统,按顺序收缩液压油缸;
6. When demoulding, people enter the box to remove the reinforcement struts of the
7、收完后,内模2整体下降,内模2主梁下端的轨道6落到支撑架4上的反轨轮3上;
7. After receiving, the
8、用5t卷扬机将内模2整体拖拉至梁体,落入存放区5的反轨轮3上;
8. Use a 5t hoist to drag the
整个脱模过程只需4工人,2个小时就能全部完成。 The entire demoulding process only needs 4 workers and can be completed in 2 hours.
上述步骤中应注意以下问题: The following issues should be paid attention to in the above steps:
1、每个工作循环前,检查各限位开关是否可靠,牵引钢丝绳、滑轮及液压系统压力、液面是否正常,滑轮、走行轮轴承座、润滑是否良好,确认正常,方可作业; 1. Before each working cycle, check whether the limit switches are reliable, whether the traction wire rope, pulley and hydraulic system pressure and liquid level are normal, whether the pulley, running wheel bearing seat, and lubrication are in good condition, and work can only be performed after confirming normal;
2、浇注前应对混凝土各部分尺寸进行检查测量,保证相关尺寸和平整度达到要求后方能进行混凝土浇注; 2. Check and measure the dimensions of each part of the concrete before pouring to ensure that the relevant dimensions and flatness meet the requirements before pouring concrete;
3、牵引走行小车模板移动时,随时观察移动方向有无障碍,防止台车跳道和拖挂其他机具设备; 3. When pulling the traveling trolley template to move, observe whether there is any obstacle in the moving direction at any time, so as to prevent the trolley from jumping off the track and dragging other machinery and equipment;
4、混凝土凝固时间不宜太长,强度达到混凝土设计强度的60~70%时需进行脱模,否则会造成脱模困难; 4. The solidification time of concrete should not be too long. When the strength reaches 60~70% of the design strength of the concrete, it needs to be demoulded, otherwise it will cause difficulty in demoulding;
5、纵移走行钢轨若供应紧张,也可以采用工字钢或槽钢背对背焊接都可。 5. If the supply of longitudinal moving rail is tight, I-beam or channel steel can be used for back-to-back welding.
Claims (2)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN 201110097867 CN102225580B (en) | 2011-04-19 | 2011-04-19 | Method for longitudinally moving box girder internal mold |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN 201110097867 CN102225580B (en) | 2011-04-19 | 2011-04-19 | Method for longitudinally moving box girder internal mold |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN102225580A CN102225580A (en) | 2011-10-26 |
| CN102225580B true CN102225580B (en) | 2013-06-12 |
Family
ID=44806597
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN 201110097867 Expired - Fee Related CN102225580B (en) | 2011-04-19 | 2011-04-19 | Method for longitudinally moving box girder internal mold |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN102225580B (en) |
Families Citing this family (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107160542B (en) * | 2017-06-09 | 2019-05-10 | 中铁建大桥工程局集团第五工程有限公司 | Bracket type inner form support system construction method |
| CN107363988B (en) * | 2017-09-07 | 2023-06-27 | 中交二公局第四工程有限公司 | Hydraulic inner mold cog rail traveling system and traveling method of prefabricated box girder |
| CN109203219B (en) * | 2018-11-22 | 2023-09-29 | 湖南五新智能科技股份有限公司 | An automatic longitudinal movement device for box girder internal molds |
| CN112757474A (en) * | 2020-12-30 | 2021-05-07 | 湖南中铁五新钢模有限责任公司 | Method for prefabricating hollow pier stud by integrally overturning inner mold, outer mold and reinforcement cage |
| CN115741955A (en) * | 2022-10-25 | 2023-03-07 | 中铁七局集团有限公司 | Installation method of high-speed rail simply supported box Liang Gangmo system |
| CN116335037A (en) * | 2023-03-13 | 2023-06-27 | 郑州新大方重工科技有限公司 | An automatic hydraulic internal mold system and its construction method |
| CN116537075B (en) * | 2023-06-21 | 2025-10-24 | 中国十九冶集团有限公司 | Method for removing formwork and transporting it in narrow space within prefabricated small box beams |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN200991949Y (en) * | 2007-04-09 | 2007-12-19 | 中铁大桥(郑州)工程机械有限公司 | Box-beam internal mould |
-
2011
- 2011-04-19 CN CN 201110097867 patent/CN102225580B/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| CN102225580A (en) | 2011-10-26 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN207109856U (en) | Piping lane, culvert construction hydraulic steel formwork jumbo | |
| CN102225580B (en) | Method for longitudinally moving box girder internal mold | |
| CN106120563B (en) | Construction method based on Combined movable mould bases cast-in-situ box girder | |
| CN113235472B (en) | A trolley for pouring concrete for slab culvert | |
| CN101581073B (en) | Downlink movable mould frame and walking method thereof | |
| CN101408019B (en) | A construction method of low-height prefabricated box girder internal formwork | |
| CN104631333B (en) | Arch bridge needle beam, stringer and floorings cast-in-place construction travelling bridge and method | |
| CN108442255A (en) | A mobile formwork bridge-building machine and a construction method for a cast-in-place bridge | |
| CN101787678B (en) | Large-span section assembling bridge manufacturing machine and assembling construction process thereof | |
| CN103669215B (en) | Vertical-horizontal overall-sliding type side mold of fulcrum-few support | |
| CN102230381B (en) | Hollow needle beam lining trolley | |
| CN101117791A (en) | Combined mobile formwork base with special-shaped steel box and orthotropic plate bottom formwork and its construction method | |
| CN104310165A (en) | Guide rail type adhesion construction lifter and construction method thereof | |
| CN101736703B (en) | 3000t special bridge girder erection machine for integrally erecting 120m-span double-layer four-line steel beam bridge for highway and railway | |
| CN101457513A (en) | Bridge erection method | |
| CN104695335B (en) | Upstroke movable framework steel bar overall binding lifting construction engineering method and constructing device | |
| CN106149639B (en) | A kind of mobile formwork of single rectangle top opening enclosed type water conservancy aqueduct construction | |
| CN106593469A (en) | Trolley for construction of inverted arch | |
| CN107905124A (en) | A kind of symmetrical expression rigid frame-continuous girder construction technology | |
| CN108086170A (en) | The hole construction method excessively of mobile formwork and mobile formwork | |
| CN214993219U (en) | Concrete placement platform truck is contained to apron | |
| CN115305952A (en) | Self-propelled steel formwork trolley for construction of comprehensive pipe gallery | |
| CN214573768U (en) | A self-climbing slipform pouring system for the second-stage concrete pouring of the door slot | |
| CN107905111A (en) | A kind of rigid frame-continuous girder end bay construction technology | |
| CN107815971A (en) | High mound is from climbing hydraulic pressure mould system that turns over |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20130612 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |
