CN104695335B - Construction method and construction device of integral binding and hoisting of steel bars in upward mobile formwork - Google Patents

Construction method and construction device of integral binding and hoisting of steel bars in upward mobile formwork Download PDF

Info

Publication number
CN104695335B
CN104695335B CN201510018530.3A CN201510018530A CN104695335B CN 104695335 B CN104695335 B CN 104695335B CN 201510018530 A CN201510018530 A CN 201510018530A CN 104695335 B CN104695335 B CN 104695335B
Authority
CN
China
Prior art keywords
framework
mold
movable framework
upstroke movable
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510018530.3A
Other languages
Chinese (zh)
Other versions
CN104695335A (en
Inventor
赵飞
王杰
钱有伟
詹崇谦
王瑞
陈学鲁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG HENGHUN MACHINERY Co Ltd
Second Engineering Co Ltd of CTCE Group
Original Assignee
SHANDONG HENGHUN MACHINERY Co Ltd
Second Engineering Co Ltd of CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG HENGHUN MACHINERY Co Ltd, Second Engineering Co Ltd of CTCE Group filed Critical SHANDONG HENGHUN MACHINERY Co Ltd
Priority to CN201510018530.3A priority Critical patent/CN104695335B/en
Publication of CN104695335A publication Critical patent/CN104695335A/en
Application granted granted Critical
Publication of CN104695335B publication Critical patent/CN104695335B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to upstroke movable framework steel bar overall binding lifting construction engineering method and constructing device, casting concrete at the framework of steel reinforcement in exterior sheathing is formed box beam;Strong health preserving, stretch-draw, mud jacking and the sealing off and covering anchorage working procedure such as the box beam pouring molding is carried out;Meanwhile, previous hole is poured on the concrete box girder of molding and mold has been set, assembling reinforcement skeleton along the longitudinal direction on mold.Afterwards upstroke movable framework via advance to next across, after being adjusted in place, being delivered in upstroke movable framework by mold by framework of steel reinforcement, and be hoisted in exterior sheathing achieve synchronization job by boom hoisting by framework of steel reinforcement, the construction period in each hole can shorten about sky.Relative to traditional construction technique, meet large span, large-tonnage and the requirement of high headroom.It is equally applicable simultaneously for the situation that cannot arrange straddle truck walking track under the bridge floors such as offshore construction.

Description

上行式移动模架钢筋整体绑扎吊装施工工法及施工装置Construction method and construction device of integral binding and hoisting of steel bars in upward mobile formwork

技术领域 technical field

本发明涉及桥梁建造技术领域,具体涉及一种上行式移动模架钢筋整体绑扎吊装施工工法及施工装置。 The invention relates to the technical field of bridge construction, in particular to a construction method and a construction device for integrally binding and hoisting steel bars of an upward mobile formwork frame.

背景技术 Background technique

移动模架造桥机是一种自带模板,利用承台或墩柱作为支承,对桥梁进行现场浇筑的施工机械。移动模架施工工序为流水作业,工序依次为:1.移动模架过孔、调整就位;2.绑扎底、腹板钢筋、布置预应力钢束;3.拼装内模;4.绑扎顶板钢筋、穿钢绞线;5.浇筑箱梁砼;6.等强养生;7.张拉、压浆、封锚。每孔梁的施工周期约为18天。移动模架施工工序必须在上道工序完成后才能进行下一道工序。目前,现有的钢筋骨架整体吊装方案为:在钢筋绑扎胎具中将钢筋骨架绑扎成型,在钢筋骨架上安装吊装桁架增加钢筋骨架刚度,通过2台龙门吊将钢筋骨架整体吊装入模。此方案较多的应用在梁场的预制混凝土梁施工中。移动模架施工如果采取此种方案,那么龙门吊需横跨施工桥梁,且满足大跨度、高净空要求,同时需要在桥面下设置龙门吊行走轨道。此种方案大部分情况很难实施,主要原因如下:1.对龙门吊要求高,必须满足大跨度、大吨位、高净空等要求;2.当墩柱高度过高时,龙门吊无法满足施工要求;3.对于海上施工等桥面下无法设置龙门吊行走轨道的,无法满足施工要求。 The mobile formwork bridge building machine is a construction machine with its own formwork, which uses the cap or pier column as a support to pour the bridge on site. The construction process of the mobile formwork is a flow operation, and the steps are as follows: 1. Move the formwork through the hole and adjust it in place; 2. Bind the bottom, web steel bars, and arrange prestressed steel beams; 3. Assemble the inner mold; 4. Bind the top plate 5. Pouring box girder concrete; 6. Equal strength maintenance; 7. Tensioning, grouting, and anchor sealing. The construction period of each beam is about 18 days. The mobile formwork construction process must be completed before the next process can be carried out. At present, the existing overall hoisting scheme of the steel frame is as follows: the steel frame is bound and formed in the steel bar binding mold, the hoisting truss is installed on the steel frame to increase the rigidity of the steel frame, and the entire steel frame is hoisted into the mold by two gantry cranes. This scheme is mostly used in the construction of precast concrete beams in beam yards. If such a scheme is adopted for mobile formwork construction, the gantry crane needs to span the construction bridge and meet the requirements of large span and high clearance. At the same time, it is necessary to set the gantry crane walking track under the bridge deck. This kind of scheme is difficult to implement in most cases, the main reasons are as follows: 1. The gantry crane has high requirements and must meet the requirements of large span, large tonnage, and high clearance; 2. When the height of the pier column is too high, the gantry crane cannot meet the construction requirements; 3. For offshore construction and other bridge decks where the gantry crane walking track cannot be installed, the construction requirements cannot be met.

发明内容 Contents of the invention

本发明为了克服以上技术的不足,提供了一种有效缩短施工工期且满足大跨度、高净空要求的上行式移动模架钢筋整体绑扎吊装施工工法及施工装置。 In order to overcome the deficiencies of the above technologies, the present invention provides a construction method and construction device for integral binding and hoisting of steel bars in an upward mobile formwork that effectively shortens the construction period and meets the requirements of large span and high clearance.

本发明克服其技术问题所采用的技术方案是: The technical scheme that the present invention overcomes its technical problem adopts is:

本上行式移动模架钢筋整体绑扎吊装施工工法,包括如下步骤: The overall binding and hoisting construction method of the upward mobile formwork steel bar includes the following steps:

a)将外模板中的钢筋骨架处浇筑混凝土形成箱梁; a) Concrete is poured at the reinforcement skeleton place in the outer formwork to form a box girder;

b)对已浇筑成型的箱梁进行等强养生、张拉、压浆和封锚施工工序; b) Carry out equal-strength maintenance, tensioning, grouting and anchoring construction procedures for the poured box girder;

c)在对步骤a)以及步骤b)施工的同时,对前一孔已浇筑成型的混凝土箱梁上设置胎具,在胎具上沿纵向方向绑扎下一孔箱梁底板钢筋、腹板钢筋、布置预应力钢束、拼装内模、绑扎顶板钢筋以及穿钢绞线最终形成钢筋骨架,所述钢筋骨架的数量与移动模架内所需箱梁数量相同; c) While step a) and step b) are being constructed, a mold is set on the concrete box girder that has been poured in the previous hole, and the bottom plate steel bar and web steel bar of the next hole box girder are bound longitudinally on the mold , arranging prestressed steel tendons, assembling internal formwork, binding roof reinforcement and passing steel strands to finally form a reinforcement skeleton, the number of the reinforcement skeleton is the same as the number of box girders required in the mobile formwork;

d)步骤a)以及步骤b)施工完毕后,上行式移动模架过孔行进到下一跨; d) After step a) and step b) are completed, the upward moving formwork advances to the next span through the hole;

e) 上行式移动模架调整到位后,将已绑扎完毕的钢筋骨架由胎具内输送至上行式移动模架中,并通过起吊装置将钢筋骨架吊运至外模板中; e) After the upward mobile formwork is adjusted in place, the steel frame that has been bound is transported from the mold to the upward mobile formwork, and the steel frame is hoisted to the outer formwork by the lifting device;

f)再次执行步骤a)至步骤e); f) performing step a) to step e) again;

本发明还包括一种上行式移动模架钢筋整体绑扎吊装施工工法的施工装置,包括沿纵向设置于混凝土箱梁上的胎具、沿纵向安装于胎具上的导轨Ⅱ、设置于胎具上用于将钢筋骨架运送至上行式移动模架后端的纵向输送装置Ⅰ、设置于上行式移动模架内的用于将钢筋骨架从混凝土箱梁处纵向移动至上行式移动模架内的纵向输送装置Ⅱ以及用于将上行式移动模架内的钢筋骨架吊运至外模板内的吊运装置,所述胎具中设置有与钢筋骨架外形相匹配的凹槽,所述凹槽的长度与上行式移动模架内所需箱梁数量长度之和相配,所述上行式移动模架后端两侧的两个侧支腿之间的间距大于钢筋骨架的宽度。 The present invention also includes a construction device for the integral binding and hoisting construction method of upward mobile formwork steel bars, which includes a mold set longitudinally on the concrete box girder, a guide rail II installed longitudinally on the mold, and a mold set on the mold Longitudinal conveying device for transporting the steel skeleton to the rear end of the upward mobile formwork Ⅰ, the longitudinal conveying device set in the upward mobile formwork for longitudinally moving the steel skeleton from the concrete box girder to the upward mobile formwork Device II and the hoisting device for hoisting the steel frame in the upward mobile formwork to the outer formwork, the mold is provided with a groove that matches the shape of the steel frame, and the length of the groove is the same as The sum of the number and length of the required box girders in the upward mobile formwork matches, and the distance between the two side legs on both sides of the rear end of the upward mobile formwork is greater than the width of the steel skeleton.

为了方便在胎具中制作钢筋骨架,还包括沿纵向设置于混凝土箱梁上的导轨Ⅰ、塔吊以及安装于塔吊下端的行走轮Ⅰ,所述塔吊位于胎具的后端。 In order to facilitate the production of steel skeletons in the mold, it also includes guide rails 1 arranged longitudinally on the concrete box girder, a tower crane, and a walking wheel I installed at the lower end of the tower crane. The tower crane is located at the rear end of the mold.

上述纵向输送装置Ⅰ包括分别沿纵向设置于胎具上端两侧的导轨Ⅱ、位于胎具上端的起吊桁架以及分别安装于起吊桁架下端两侧的若干千斤顶,所述千斤顶的下端安装有行走轮Ⅱ,所述胎具通过行走轮Ⅱ滑动设置于导轨Ⅱ上,钢筋骨架通过螺杆利用螺母紧固吊挂于起吊桁架的下端。 The above-mentioned longitudinal conveying device I includes guide rails II arranged longitudinally on both sides of the upper end of the mold, a lifting truss located at the upper end of the mold, and several jacks respectively installed on both sides of the lower end of the lifting truss. The lower ends of the jacks are equipped with walking wheels II , the tire is slidably arranged on the guide rail II through the walking wheel II, and the steel bar frame is fastened and hung on the lower end of the lifting truss through the screw rod and the nut.

上述纵向输送装置Ⅱ包括分别沿纵向安装于上行式移动模架内的导轨Ⅲ以及若干吊运小车,所述吊运小车的下端两侧分别设置有若干行走轮Ⅲ,所述吊运小车通过行走轮Ⅲ滑动设置于导轨Ⅲ上。 The above-mentioned longitudinal conveying device II includes guide rails III installed longitudinally in the upward mobile formwork and several hoisting trolleys, and a number of walking wheels III are respectively arranged on both sides of the lower end of the hoisting trolleys, and the hoisting trolleys pass through The wheel III is slidably arranged on the guide rail III.

上述吊运装置包括横向设置于上行式移动模架后端与前端的横梁Ⅰ和横梁Ⅱ,所述横梁Ⅰ和横梁Ⅱ上分别滑动安装有起吊天车Ⅰ和起吊天车Ⅱ。 The above-mentioned lifting device includes crossbeam I and crossbeam II arranged laterally at the rear end and front end of the upward mobile formwork, and the beam I and beam II are respectively slidably mounted with crane crane I and crane crane II.

为了防止干涉,位于两个侧支腿中间位置处的若干中支腿通过销轴铰接安装于上行式移动模架的后端,油缸的尾端铰接安装于上行式移动模架上,其活塞杆头端铰接安装于中支腿上,当油缸的活塞杆全部伸出时,所述中支腿转动至与混凝土箱梁平行。 In order to prevent interference, a number of middle legs located in the middle of the two side legs are hingedly installed on the rear end of the upward moving formwork through pin shafts, and the tail end of the oil cylinder is hingedly installed on the upward moving formwork. The head end is hingedly installed on the middle leg, and when the piston rod of the oil cylinder is fully stretched out, the middle leg turns to be parallel to the concrete box girder.

为了便于移动胎具,上述胎具通过托运小车滑动设置于导轨Ⅰ上。 In order to facilitate the movement of the mold, the tire mold is slidably set on the guide rail Ⅰ through the consignment trolley.

本发明的有益效果是:由于当把钢筋骨架浇筑成混凝土箱梁时,可以同时进行绑扎底、腹板钢筋、布置预应力钢束以及拼装内模的钢筋骨架的制作过程,以便于上行式移动模架过孔时继续快速将制作好的钢筋骨架运送至外模板内。实现了同步作业,每一孔的施工周期可缩短5天左右。相对于传统施工工艺,不需龙门吊,因此满足了大跨度、大吨位以及高净空的要求。解决了当墩柱过高时传统的龙门吊吊运钢筋骨架无法满足施工要求的问题。同时对于海上施工等桥面下无法设置龙门吊行走轨道的情况也同样适用。 The beneficial effects of the present invention are: when pouring the steel frame into a concrete box girder, the process of binding the bottom, web steel bars, arranging prestressed steel beams and assembling the steel frame of the inner mold can be carried out at the same time, so as to facilitate upward movement When the formwork passes through the hole, continue to quickly transport the prepared steel skeleton to the outer formwork. Synchronous operation is realized, and the construction period of each hole can be shortened by about 5 days. Compared with the traditional construction technology, there is no need for gantry cranes, so it meets the requirements of large span, large tonnage and high clearance. It solves the problem that the traditional gantry crane cannot meet the construction requirements when the pier column is too high. At the same time, it is also applicable to the situation where the gantry crane running track cannot be set under the bridge deck such as offshore construction.

附图说明 Description of drawings

图1为本发明的主视结构示意图; Fig. 1 is the front view structure schematic diagram of the present invention;

图2为图1中的A-A向剖面结构示意图; Fig. 2 is a schematic diagram of the cross-sectional structure of A-A in Fig. 1;

图3为图1中的B-B向剖面结构示意图; Fig. 3 is a schematic diagram of a cross-sectional structure along B-B in Fig. 1;

图4为图1中的C向结构示意图; Fig. 4 is a schematic diagram of the C-direction structure in Fig. 1;

图5为图1中的D-D向剖面结构示意图; Fig. 5 is a schematic diagram of a D-D cross-sectional structure in Fig. 1;

图6为图1中的E-E向剖面结构示意图; Fig. 6 is the E-E in Fig. 1 to sectional structure schematic diagram;

图中,1.混凝土箱梁 2.上行式移动模架 3.塔吊 4.胎具 5.托运小车 6.中支腿 7.侧支腿 8.横梁Ⅰ 9.横梁Ⅱ 10.起吊天车Ⅰ 11.起吊天车Ⅱ 12.吊运小车 13.导轨Ⅰ 14.行走轮Ⅰ 15.起吊桁架 16.导轨Ⅱ 17.行走轮Ⅱ 18.钢筋骨架 19.螺杆 20.导轨Ⅲ 21.行走轮Ⅲ 22.外模板。 In the figure, 1. Concrete box girder 2. Upward mobile formwork 3. Tower crane 4. Mold 5. Consignment trolley 6. Middle outrigger 7. Side outrigger 8. Beam I 9. Beam II 10. Crane I 11. Lifting Crane II 12. Lifting Trolley 13. Guide rail Ⅰ 14. Traveling wheel Ⅰ 15. Lifting truss 16. Guide rail Ⅱ 17. Traveling wheel Ⅱ 18. Steel skeleton 19. Screw 20. Guide rail Ⅲ 21. Traveling wheel Ⅲ 22. Outer formwork.

具体实施方式 detailed description

下面结合附图1至附图6对本发明做进一步说明。 The present invention will be further described below in conjunction with accompanying drawings 1 to 6.

本发明克服其技术问题所采用的技术方案是: The technical scheme that the present invention overcomes its technical problem adopts is:

本上行式移动模架钢筋整体绑扎吊装施工工法,包括如下步骤: The overall binding and hoisting construction method of the upward mobile formwork steel bar includes the following steps:

a)将外模板22中的钢筋骨架18处浇筑混凝土形成箱梁;b)对已浇筑成型的箱梁进行等强养生、张拉、压浆和封锚施工工序;c)在对步骤a)以及步骤b)施工的同时,对前一孔已浇筑成型的混凝土箱梁上设置胎具4,在胎具4上沿纵向方向绑扎下一孔箱梁底板钢筋、腹板钢筋、布置预应力钢束、拼装内模、绑扎顶板钢筋以及穿钢绞线最终形成钢筋骨架18,钢筋骨架18的数量与移动模架内所需箱梁数量相同;d)步骤a)以及步骤b)施工完毕后,上行式移动模架2过孔行进到下一跨;e) 上行式移动模架2调整到位后,将已绑扎完毕的钢筋骨架18由胎具4内输送至上行式移动模架2中,并通过起吊装置将钢筋骨架18吊运至外模板22中;f)再次执行步骤a)至步骤e)。由于当把钢筋骨架浇筑成混凝土箱梁时,可以同时进行绑扎底、腹板钢筋、布置预应力钢束以及拼装内模的钢筋骨架18的制作过程,以便于上行式移动模架2过孔时继续快速将制作好的钢筋骨架18运送至外模板22内。实现了同步作业,每一孔的施工周期可缩短5天左右。相对于传统施工工艺,不需龙门吊,因此满足了大跨度、大吨位以及高净空的要求。解决了当墩柱过高时传统的龙门吊吊运钢筋骨架18无法满足施工要求的问题。同时对于海上施工等桥面下无法设置龙门吊行走轨道的情况也同样适用。 a) Concrete is poured at the reinforcement skeleton 18 in the outer formwork 22 to form a box girder; b) the poured box girder is subjected to equal-strength maintenance, tensioning, grouting and anchoring construction procedures; c) in step a) And while step b) is being constructed, a mold 4 is set on the concrete box girder that has been poured and formed in the previous hole, and the bottom plate reinforcement, web reinforcement, and prestressed steel of the next hole are bound on the mold 4 along the longitudinal direction. Bundle, assemble the inner mold, bind the roof reinforcement and pass the steel strands to finally form the steel skeleton 18, the number of the steel skeleton 18 is the same as the number of box girders required in the mobile formwork; d) after step a) and step b) are completed, The upward mobile formwork 2 passes through the hole and advances to the next span; e) after the upward mobile formwork 2 is adjusted in place, the steel bar skeleton 18 that has been bound is transported to the upward mobile formwork 2 from the mold 4, and Lifting the reinforcement frame 18 into the outer formwork 22 by means of a lifting device; f) performing steps a) to e) again. When pouring the reinforced skeleton into a concrete box girder, the process of binding the bottom, the web steel bars, arranging the prestressed steel strands and assembling the reinforced skeleton 18 of the inner mold can be carried out at the same time, so that when the upward mobile formwork 2 passes through the hole Continuing to transport the fabricated steel bar skeleton 18 into the outer formwork 22 quickly. Synchronous operation is realized, and the construction period of each hole can be shortened by about 5 days. Compared with the traditional construction technology, there is no need for gantry cranes, so it meets the requirements of large span, large tonnage and high clearance. It solves the problem that the traditional gantry crane cannot meet the construction requirements for hoisting and transporting the steel bar frame 18 when the pier column is too high. At the same time, it is also applicable to the situation where the gantry crane running track cannot be set under the bridge deck such as offshore construction.

本发明还包括一种上行式移动模架钢筋整体绑扎吊装施工工法的施工装置,包括沿纵向设置于混凝土箱梁1上的胎具4、沿纵向安装于胎具4上的导轨Ⅱ 16、设置于胎具4上用于将钢筋骨架18运送至上行式移动模架2后端的纵向输送装置Ⅰ、设置于上行式移动模架2内的用于将钢筋骨架18从混凝土箱梁1处纵向移动至上行式移动模架2内的纵向输送装置Ⅱ以及用于将上行式移动模架2内的钢筋骨架18吊运至外模板22内的吊运装置,胎具4中设置有与钢筋骨架18外形相匹配的凹槽,凹槽的长度与上行式移动模架2内所需箱梁数量长度之和相配,上行式移动模架2后端两侧的两个侧支腿7之间的间距大于钢筋骨架18的宽度。将需要使用的钢筋骨架18在胎具4中制作完毕,并以此通过纵向输送装置Ⅰ、纵向输送装置Ⅱ以及吊运装置运送到外模板22内,可以实现浇筑箱梁砼、等强养生以及张拉、压浆和封锚时,同步进行钢筋骨架18的制作,提高了施工效率,满足大跨度、高净空的要求。 The present invention also includes a construction device for the integral binding and hoisting construction method of upward mobile formwork steel bars, including a mold 4 longitudinally arranged on the concrete box girder 1, a guide rail II 16 longitudinally installed on the mold 4, a set The longitudinal conveying device I on the mold 4 is used to transport the steel skeleton 18 to the rear end of the upward mobile formwork 2, and the longitudinal conveying device I installed in the upward mobile formwork 2 is used to longitudinally move the steel skeleton 18 from the concrete box girder 1 The longitudinal conveying device II to the upward mobile formwork 2 and the lifting device for hoisting the steel skeleton 18 in the upward mobile formwork 2 to the outer formwork 22, the mold 4 is provided with the steel skeleton 18 A groove with a matching shape, the length of the groove matches the sum of the lengths of the required box girders in the upward mobile formwork 2, and the distance between the two side legs 7 on both sides of the rear end of the upward mobile formwork 2 Greater than the width of the steel skeleton 18. The steel skeleton 18 to be used is manufactured in the mold 4, and transported to the outer formwork 22 through the longitudinal conveying device I, the longitudinal conveying device II and the hoisting device, so as to realize pouring of box girder concrete, equal-strength maintenance and During tensioning, grouting and anchor sealing, the steel skeleton 18 is manufactured simultaneously, which improves the construction efficiency and meets the requirements of large span and high clearance.

还可以包括沿纵向设置于混凝土箱梁1上的导轨Ⅰ 13、塔吊3以及安装于塔吊3下端的行走轮Ⅰ 14,所述塔吊3位于胎具4的后端。通过塔吊3可以在胎具4中制作钢筋骨架18时,起到吊运的作用加快了钢筋骨架18的制作效率。塔吊3可以通过行走轮Ⅰ 14沿导轨Ⅰ 13纵移,进一步提高了使用的便利性。 It may also include a guide rail I 13 arranged longitudinally on the concrete box girder 1 , a tower crane 3 and a traveling wheel I 14 installed at the lower end of the tower crane 3 , and the tower crane 3 is located at the rear end of the mold 4 . When the steel frame 18 can be made in the mold 4 by the tower crane 3 , it plays the role of hoisting and speeds up the production efficiency of the steel frame 18 . The tower crane 3 can pass the walking wheel Ⅰ 14 moves vertically along the guide rail I 13, further improving the convenience of use.

纵向输送装置Ⅰ可以为如下结构,其包括分别沿纵向设置于胎具4上端两侧的导轨Ⅱ 16、位于胎具4上端的起吊桁架15以及分别安装于起吊桁架15下端两侧的若干千斤顶,千斤顶的下端安装有行走轮Ⅱ 17,胎具4通过行走轮Ⅱ 17滑动设置于导轨Ⅱ 16上,钢筋骨架18通过螺杆19利用螺母紧固吊挂于起吊桁架15的下端。当在胎具4中制作好钢筋骨架18后,利用螺杆19通过螺母将起吊桁架15与钢筋骨架18连接固定。之后使千斤顶驱动起吊桁架15上升,将钢筋骨架18从胎具中脱离。之后起吊桁架15通过行走轮Ⅱ 17纵移至上行式移动模架2的尾端。而将钢筋骨架18固定到起吊桁架15上进行运送,可以提高钢筋骨架18的整体刚度。 The longitudinal conveying device I may have the following structure, which includes guide rails II 16 arranged longitudinally on both sides of the upper end of the mold 4, a lifting truss 15 located at the upper end of the mold 4, and several jacks respectively installed on both sides of the lower end of the lifting truss 15, The lower end of the jack is equipped with traveling wheels II 17, and the mold 4 is slidably arranged on the guide rail II through the traveling wheels II 17 16, the steel bar frame 18 is fastened and hung on the lower end of the lifting truss 15 through the screw rod 19 with nuts. After making the steel bar skeleton 18 in the mold 4, utilize the screw rod 19 to connect and fix the lifting truss 15 and the steel bar skeleton 18 through nuts. Afterwards, the jack drives the lifting truss 15 to rise, and the reinforcement frame 18 is separated from the mold. Lifting truss 15 longitudinally moves to the tail end of upward type movable formwork 2 by traveling wheel II 17 afterwards. And fixing the reinforcement frame 18 on the lifting truss 15 for transportation can improve the overall rigidity of the reinforcement frame 18 .

纵向输送装置Ⅱ可以为如下结构,其包括分别沿纵向安装于上行式移动模架2内的导轨Ⅲ 20以及若干吊运小车12,吊运小车12的下端两侧分别设置有若干行走轮Ⅲ 21,吊运小车12通过行走轮Ⅲ 21滑动设置于导轨Ⅲ 20上。当钢筋骨架18的头端进入上行式移动模架2内之后,将起吊桁架通过螺杆19利用螺母紧固与吊运小车12下方,并逐步向上行式移动模架2中纵向移动,并逐步依次将起吊桁架15与其余的吊运小车12连接固定,最终实现将起吊桁架15带动钢筋骨架18纵移至上行式移动模架2中。 The longitudinal conveying device II can have the following structure, which includes guide rails III 20 installed in the upward mobile formwork 2 along the longitudinal direction and a number of lifting trolleys 12, and a number of walking wheels III 21 are respectively arranged on both sides of the lower end of the lifting trolley 12 , the hoisting trolley 12 is slidably set on the guide rail III 20 through the traveling wheels III 21 . After the head end of the steel bar skeleton 18 enters the upward mobile formwork 2, the lifting truss is fastened under the lifting trolley 12 through the screw rod 19 using nuts, and gradually moves longitudinally upward in the upward mobile formwork 2, and gradually The hoisting truss 15 is connected and fixed with the rest of the hoisting trolleys 12, and finally the hoisting truss 15 drives the reinforcement frame 18 to vertically move into the upward mobile formwork 2.

吊运装置可以为如下结构,其包括横向设置于上行式移动模架2后端与前端的横梁Ⅰ 8和横梁Ⅱ 9,横梁Ⅰ 8和横梁Ⅱ 9上分别滑动安装有起吊天车Ⅰ 10和起吊天车Ⅱ 11。当吊运小车12将钢筋骨架18输送到位后,起吊天车Ⅰ 10和起吊天车Ⅱ 11将起吊桁架15两端吊住,并横向沿着横梁Ⅰ 8和横梁Ⅱ 9移动,最终将钢筋骨架18吊运至外模板22出,实现将钢筋骨架18移送到位。 The hoisting device may have the following structure, which includes crossbeam I 8 and crossbeam II 9 arranged laterally at the rear end and front end of the upward mobile formwork 2, and the crossbeam I 8 and crossbeam II 9 are respectively slidably installed with crane crane I 10 and Lifting crane Ⅱ 11. After the hoisting trolley 12 transports the reinforcement frame 18 into place, the hoisting crane I 10 and the hoisting crane II 11 hang the two ends of the hoisting truss 15, and move laterally along the beam I 8 and the beam II 9, and finally the reinforcement frame 18 is hoisted to outer formwork 22 to go out, realizes that steel bar skeleton 18 is moved to put in place.

位于两个侧支腿7中间位置处的若干中支腿6通过销轴铰接安装于上行式移动模架2的后端,油缸的尾端铰接安装于上行式移动模架2上,其活塞杆头端铰接安装于中支腿6上,当油缸的活塞杆全部伸出时,中支腿6转动至与混凝土箱梁1平行。通过油缸驱动中支腿6摆动以便于钢筋骨架18进入,又不影响上行式移动模架的支撑强度。 A number of middle legs 6 located in the middle of the two side legs 7 are hingedly mounted on the rear end of the upward mobile formwork 2 through pin shafts, and the tail end of the oil cylinder is hingedly mounted on the upward mobile formwork 2, and its piston rod The head end is hingedly installed on the middle leg 6, and when the piston rod of the oil cylinder is fully stretched out, the middle leg 6 rotates to be parallel to the concrete box girder 1. The middle support leg 6 is driven by the oil cylinder to swing so that the reinforcement skeleton 18 enters without affecting the support strength of the upward moving formwork.

胎具4通过托运小车5滑动设置于导轨Ⅰ 13上。托运小车5与塔吊3共用导轨Ⅰ 13,当上行式移动模架过孔行进到下一跨时,胎具4可以通过托运小车5纵向行走的施工完毕的混凝土箱梁1上,以便于下一阶段继续施工。进一步提高了便利性。 The mold 4 is slidably arranged on the guide rail I 13 by the consignment trolley 5 . Consignment trolley 5 and tower crane 3 share guide rail Ⅰ 13. When the upward moving formwork advances to the next span through the hole, the mold 4 can pass through the completed concrete box girder 1 that the consignment trolley 5 travels longitudinally, so as to continue the construction in the next stage. Convenience is further improved.

Claims (7)

  1. null1. a upstroke movable framework steel bar overall binding lifting construction device,It is characterized in that: include longitudinally disposed mold (4) on concrete box girder (1)、Along longitudinally mounted guide rail II (16) on mold (4)、It is arranged at the upper longitudinal conveying device I for framework of steel reinforcement (18) being transported to upstroke movable framework (2) rear end of mold (4)、Be arranged in upstroke movable framework (2) for longitudinal conveying device II that framework of steel reinforcement (18) is longitudinally moved in upstroke movable framework (2) from concrete box girder (1) and for the framework of steel reinforcement (18) in upstroke movable framework (2) is hoisted to the handling apparatus in exterior sheathing (22),Described mold (4) is provided with the groove matched with framework of steel reinforcement (18) profile,Required box beam quantity length sum matches the length of described groove with in upstroke movable framework (2),Spacing between two side legs (7) of described upstroke movable framework (2) both sides, rear end is more than the width of framework of steel reinforcement (18),The construction using this device is: a) framework of steel reinforcement (18) the place casting concrete in exterior sheathing (22) is formed box beam;B) strong health preserving, stretch-draw, mud jacking and the sealing off and covering anchorage working procedure such as the box beam pouring molding is carried out;C) while step a) and step b) is constructed, previous hole is poured mold (4) has been set on the concrete box girder of molding, on mold (4), in next hole box beam baseplate reinforcing bar of colligation along the longitudinal direction, web reinforcement, arrangement prestress steel bundle, assembly, mould, colligation roof steel bar and steel strand ultimately form framework of steel reinforcement (18), and the quantity of described framework of steel reinforcement (18) box beam quantity required with in mobile formwork is identical;D) step a) and step b) construction after, upstroke movable framework (2) via advance to next across;E) after upstroke movable framework (2) is adjusted in place, framework of steel reinforcement (18) complete for colligation is delivered in upstroke movable framework (2) by mold (4), and by boom hoisting, framework of steel reinforcement (18) is hoisted in exterior sheathing (22);F) step a) to step e) is again performed.
  2. Upstroke movable framework steel bar overall binding lifting construction device the most according to claim 1, it is characterized in that: also including longitudinally disposed guide rail I (13) on concrete box girder (1), tower crane (3) and be installed on the road wheel I (14) of tower crane (3) lower end, described tower crane (3) is positioned at the rear end of mold (4).
  3. Upstroke movable framework steel bar overall binding lifting construction device the most according to claim 1, it is characterized in that: described longitudinal conveying device I includes the most longitudinally disposed in the guide rail II (16) of mold (4) both sides, upper end, it is positioned at the lifting truss (15) of mold (4) upper end and is respectively arranged in some jack of lifting truss (15) both sides, lower end, the lower end of described jack is provided with road wheel II (17), described mold (4) is slideably positioned on guide rail II (16) by road wheel II (17), framework of steel reinforcement (18) utilizes nut fastening to be hung on the lower end of lifting truss (15) by screw rod (19).
  4. Upstroke movable framework steel bar overall binding lifting construction device the most according to claim 1, it is characterized in that: described longitudinal conveying device II includes respectively along longitudinally mounted guide rail III (20) in upstroke movable framework (2) and some travelling jacks (12), the both sides, lower end of described travelling jack (12) are respectively arranged with several rows travelling wheel III (21), and described travelling jack (12) is slideably positioned on guide rail III (20) by road wheel III (21).
  5. Upstroke movable framework steel bar overall binding lifting construction device the most according to claim 1, it is characterized in that: described handling apparatus includes being horizontally set at upstroke movable framework (2) rear end and the crossbeam I (8) of front end and crossbeam II (9), described crossbeam I (8) and crossbeam II (9) are slidably fitted with lifting overhead traveling crane I (10) and lifting overhead traveling crane II (11) respectively.
  6. Upstroke movable framework steel bar overall binding lifting construction device the most as claimed in any of claims 1 to 5, it is characterized in that: the some middle supporting leg (6) being positioned at two side leg (7) middle position is installed on the rear end of upstroke movable framework (2) by hinge, the tail end of oil cylinder is hinged to be installed on upstroke movable framework (2), its piston rod head end is hinged to be installed on middle supporting leg (6), when the piston rod of oil cylinder all stretches out, described middle supporting leg (6) turns to parallel with concrete box girder (1).
  7. Upstroke movable framework steel bar overall binding lifting construction device the most as claimed in any of claims 1 to 5, it is characterised in that: described mold (4) is slideably positioned on guide rail I (13) by consignment trolley (5).
CN201510018530.3A 2015-01-15 2015-01-15 Construction method and construction device of integral binding and hoisting of steel bars in upward mobile formwork Expired - Fee Related CN104695335B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510018530.3A CN104695335B (en) 2015-01-15 2015-01-15 Construction method and construction device of integral binding and hoisting of steel bars in upward mobile formwork

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510018530.3A CN104695335B (en) 2015-01-15 2015-01-15 Construction method and construction device of integral binding and hoisting of steel bars in upward mobile formwork

Publications (2)

Publication Number Publication Date
CN104695335A CN104695335A (en) 2015-06-10
CN104695335B true CN104695335B (en) 2016-09-14

Family

ID=53342851

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510018530.3A Expired - Fee Related CN104695335B (en) 2015-01-15 2015-01-15 Construction method and construction device of integral binding and hoisting of steel bars in upward mobile formwork

Country Status (1)

Country Link
CN (1) CN104695335B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105862600B (en) * 2016-04-29 2017-06-13 马荣强 Multi-section bridge pouring equipment and construction method thereof
CN105970822B (en) * 2016-06-03 2018-11-30 中铁四局集团有限公司 A 50m double-width upward mobile formwork and its corresponding beam-making construction method
CN106149639B (en) * 2016-08-30 2018-02-27 郑州新大方重工科技有限公司 A kind of mobile formwork of single rectangle top opening enclosed type water conservancy aqueduct construction
CN107338768B (en) * 2017-08-21 2023-04-21 中国葛洲坝集团股份有限公司 Factory type large aqueduct construction system and method
CN109162737A (en) * 2018-10-23 2019-01-08 中铁四局集团第二工程有限公司 A self-lifting steel bar binding trolley
CN111502291B (en) * 2020-05-26 2025-02-25 中铁四局集团第二工程有限公司 A steel frame support device and a steel frame construction method
CN114855642B (en) * 2022-06-07 2023-05-26 中交第二航务工程局有限公司 Integral installation method of reinforcement cage of large-span box girder

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10317327A (en) * 1997-05-23 1998-12-02 Nkk Corp Bridge construction method and bridge structure
KR20030093680A (en) * 2002-06-05 2003-12-11 브이에스엘코리아 주식회사 The construction method of double-t girder bridge by underslung movable scaffolding system
CN101324055A (en) * 2008-08-06 2008-12-17 中铁大桥局股份有限公司 A hoisting device and hoisting method for a box girder integral steel frame
CN201933417U (en) * 2011-01-30 2011-08-17 中交三航局第三工程有限公司 Integral steel reinforcement binding jig suitable for high-speed railway prefabricated box girder
CN102605720B (en) * 2012-03-30 2013-12-11 中铁四局集团第一工程有限公司 Integrated construction equipment for binding and lifting continuous beam steel reinforcement framework and construction method
CN203096617U (en) * 2013-02-04 2013-07-31 中国水利水电第四工程局有限公司 Integral hoisting device for steel reinforcement cage

Also Published As

Publication number Publication date
CN104695335A (en) 2015-06-10

Similar Documents

Publication Publication Date Title
CN104695335B (en) Construction method and construction device of integral binding and hoisting of steel bars in upward mobile formwork
CN107059640B (en) Bridge girder erection machine for prefabricated segmental beam span-by-span construction and construction method thereof
CN101586330B (en) Receding construction method of cradle of continuous girder bridge made of prestressing concrete
CN201010860Y (en) Bridge-building machine for integral construction of downward mobile formwork
CN110820573B (en) Construction method of steel-concrete composite beam of high-pier long-span bridge in mountainous area
CN201003145Y (en) Upward and self-walking type mobile die carrier
CN101787678B (en) Large-span section assembling bridge manufacturing machine and assembling construction process thereof
CN101324055A (en) A hoisting device and hoisting method for a box girder integral steel frame
CN108442255A (en) A mobile formwork bridge-building machine and a construction method for a cast-in-place bridge
CN110344334B (en) Construction method of two-span continuous steel-concrete composite bridge using back-cable bridge erecting machine
CN109267490B (en) A kind of long guide beam type mobile formwork and construction method thereof
CN109267491B (en) A mobile formwork and its construction method
CN115341483B (en) A method for suspended casting and hoisting construction of a continuous rigid frame bridge with steel-concrete hybrid beams
CN109024291A (en) A kind of integration Bridge Erector and its working method
CN110820602A (en) A single-segment box girder bridge erecting machine and its operation method
CN100572673C (en) Span continuous beam bridge fabrication machine in a kind of
CN105484166B (en) A kind of ladder type masts type cantilever loop wheel machine
CN205205685U (en) Span wire pier is function portal device at most
CN102225580B (en) Method for longitudinally moving box girder internal mold
CN106758872A (en) Wavelike steel webplate SCC engineering methods hang movable hanging basket and the method using its construction with car convolution
CN207552933U (en) Reinforced mesh entirety mould-entering device
CN108625270A (en) Nose girder gantry crane installs bridge prefabrication box girder construction method
CN114657884B (en) Construction method of descending movable formwork for bridge abutment assembly and sectional propulsion
CN204401473U (en) Upstroke movable framework steel bar overall binding lifting construction device
CN102071641B (en) Cement beam packs bridge machine cloth supporting leg type integration of transporting and building Bridge Erector and bridge formation engineering method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160914

CF01 Termination of patent right due to non-payment of annual fee