CN111622781A - Construction equipment and method for suspension bridge tunnel anchor chamber vault secondary lining - Google Patents

Construction equipment and method for suspension bridge tunnel anchor chamber vault secondary lining Download PDF

Info

Publication number
CN111622781A
CN111622781A CN202010529223.2A CN202010529223A CN111622781A CN 111622781 A CN111622781 A CN 111622781A CN 202010529223 A CN202010529223 A CN 202010529223A CN 111622781 A CN111622781 A CN 111622781A
Authority
CN
China
Prior art keywords
trolley
construction
connecting plate
lining
suspension bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010529223.2A
Other languages
Chinese (zh)
Other versions
CN111622781B (en
Inventor
徐翾玄
沈国宁
祁建林
焦文政
孙嘉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
East China Construction Co Ltd Of Cccc Second Highway Engineering Co ltd
Original Assignee
CCCC SHEC Second Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC SHEC Second Engineering Co Ltd filed Critical CCCC SHEC Second Engineering Co Ltd
Priority to CN202010529223.2A priority Critical patent/CN111622781B/en
Publication of CN111622781A publication Critical patent/CN111622781A/en
Application granted granted Critical
Publication of CN111622781B publication Critical patent/CN111622781B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明属于桥梁施工设备技术领域,具体提供了一种用于悬索桥隧道锚锚室拱顶二衬施工设备及方法,包括台车、台架、移动轨道、牵引单元、施工模板,施工模板连接在台车的外侧,台车、台架和牵引单元依次连接,台车和台架均连接在移动轨道上,解决了现有隧道锚前锚室二衬拱顶施工时,搭设脚手架工程量较大,满堂支架与前锚室圆弧形拱顶支撑处于不稳定状态,混凝土浇筑时受力易发生偏移,造成满堂支架的偏载,施工过程把控难度较大,施工存在安全隐患问题,具有结构简单、使用方便,施工安全,可满足施工需要。

Figure 202010529223

The invention belongs to the technical field of bridge construction equipment, and specifically provides a construction equipment and method for the secondary lining of an anchor chamber of a suspension bridge tunnel, including a trolley, a gantry, a moving track, a traction unit, and a construction template. On the outside of the trolley, the trolley, the platform and the traction unit are connected in sequence, and the trolley and the platform are connected on the moving track, which solves the problem of the large amount of scaffolding construction during the construction of the second-lined vault of the existing anchor chamber in front of the tunnel anchor. , the full house support and the arc-shaped vault support of the front anchor room are in an unstable state, and the force is easily offset during concrete pouring, resulting in the eccentric load of the full house support. The structure is simple, the use is convenient, and the construction is safe, which can meet the construction needs.

Figure 202010529223

Description

一种用于悬索桥隧道锚锚室拱顶二衬施工设备及方法A kind of construction equipment and method for the second lining of the vault of the anchor chamber of the suspension bridge tunnel

技术领域technical field

本发明属于桥梁施工设备技术领域,具体涉及一种用于悬索桥隧道锚锚室拱顶二衬施工设备及方法。The invention belongs to the technical field of bridge construction equipment, and in particular relates to a construction equipment and a method for the secondary lining of an anchor chamber of a suspension bridge tunnel.

背景技术Background technique

在悬索桥隧道式锚碇锚室二衬施工中,由于锚碇隧洞为倾斜结构,且隧洞坡度较大,无法采用隧道二衬所用大型衬砌台车施工。根据以往经验,隧道式锚碇前锚室二衬一般采用满堂脚手架支架模板体系进行混凝土浇筑。由于前锚室二衬施工时锚固系统已施工完成,且主缆索股在入锚处间距小,搭设满堂脚手架须穿过主缆,施工过程极易对主缆造成损伤。此外,华丽高速金安金沙江大桥锚碇前锚室洞室空间体积大,搭设脚手架工程量较大。同时,前锚室拱顶为圆弧形拱顶,且与水平夹角为42°,满堂支架与圆弧形拱顶支撑处于不稳定状态,混凝土浇筑时受力易发生偏移,造成满堂支架的偏载,施工过程把控难度较大,施工存在安全隐患。In the construction of the second lining of the tunnel-type anchorage chamber of the suspension bridge, due to the inclined structure of the anchorage tunnel and the large slope of the tunnel, the large-scale lining trolley used for the second lining of the tunnel cannot be used for construction. According to past experience, the second lining of the tunnel-type anchorage front anchor chamber generally adopts the full-house scaffolding bracket formwork system for concrete pouring. Because the anchoring system has been completed during the construction of the second lining of the front anchor room, and the distance between the main cable strands at the anchorage point is small, the scaffolding must pass through the main cable when erecting the full house, and the main cable is easily damaged during the construction process. In addition, the cavern of the anchor chamber in front of the anchorage of the Jinan Jinsha River Bridge on the Huali Expressway is large, and the amount of scaffolding is large. At the same time, the dome of the front anchor room is an arc-shaped vault, and the included angle with the horizontal is 42°. The full-house bracket and the arc-shaped vault support are in an unstable state, and the force is easily displaced during concrete pouring, resulting in the full-house bracket. It is difficult to control the construction process, and there are potential safety hazards in the construction.

为了解决隧道锚前锚室二衬拱顶施工问题,设计一种锚室拱顶二衬混凝土浇筑施工设备,以简便施工并提高施工安全性。In order to solve the construction problem of the second lining vault of the anchor chamber in front of the tunnel anchor, a concrete pouring construction equipment for the second lining of the anchor chamber vault is designed to facilitate the construction and improve the construction safety.

发明内容SUMMARY OF THE INVENTION

本发明提供的一种用于悬索桥隧道锚锚室拱顶二衬施工设备及方法,目的是克服现有技术中隧道锚前锚室二衬拱顶施工时,搭设脚手架工程量较大,满堂支架与前锚室圆弧形拱顶支撑处于不稳定状态,混凝土浇筑时受力易发生偏移,造成满堂支架的偏载,施工过程把控难度较大,施工存在安全隐患问题。The invention provides a construction equipment and method for the secondary lining of the arch of the anchor chamber of the suspension bridge tunnel. It is in an unstable state with the arc-shaped dome support of the front anchor room, and the force is easily offset during concrete pouring, resulting in eccentric load of the full-house support. It is difficult to control the construction process, and there are potential safety hazards in construction.

为此,本发明提供了一种用于悬索桥隧道锚锚室拱顶二衬施工设备,包括台车、台架、移动轨道、牵引单元、施工模板,施工模板连接在台车的外侧,台车、台架和牵引单元依次连接,台车和台架均连接在移动轨道上。To this end, the present invention provides a construction equipment for the second lining of the dome of the anchor chamber of the suspension bridge tunnel, including a trolley, a platform, a moving track, a traction unit, and a construction template. The construction template is connected to the outside of the trolley, and the trolley , the platform and the traction unit are connected in sequence, and the trolley and the platform are connected on the moving track.

所述牵引单元包括牵引机、牵引钢丝绳和转向轮,台架、转向轮和牵引机依次通过牵引钢丝绳连接;所述牵引机为牵引卷扬机或手拉葫芦。The traction unit includes a traction machine, a traction wire rope and a steering wheel, and the platform, the steering wheel and the traction machine are sequentially connected by the traction wire rope; the traction machine is a traction hoist or a chain hoist.

所述台车还包括移位器,台车通过移位器连接移动轨道。The trolley further includes a shifter, and the trolley is connected to the moving track through the shifter.

还包括挂架,挂架的数量为2组且2组挂架左右水平对称分布在前锚室的左侧墙和右侧墙,挂架上面沿前锚室轴线方向连接移动轨道。It also includes hangers. The number of hangers is 2 groups, and the two sets of hangers are distributed horizontally and symmetrically on the left and right walls of the front anchor room. The hangers are connected to the moving track along the axis of the front anchor room.

还包括千斤顶,千斤顶的底部连接挂架的上面,千斤顶的上面接触连接台车的下面。It also includes a jack, the bottom of the jack is connected to the top of the hanger, and the top of the jack is connected to the bottom of the trolley.

所述挂架还包括挂座和预埋件,挂架通过挂座连接预埋件,预埋件连在前锚室的侧墙内。The hanger also includes a hanger seat and a pre-embedded part, the hanger is connected to the pre-embedded part through the hanger seat, and the pre-embedded part is connected to the side wall of the front anchor chamber.

所述台架的临空侧设置护栏。A guardrail is arranged on the airside side of the platform.

所述台车包括多榀拱架和横联,多榀拱架自前向后依次等间距分布,多榀拱架之间通过横联连接;每榀拱架包括横撑、左斜撑、右斜撑、第一连接板和第二连接板,左斜撑的左端通过第二连接板连接拱架,左斜撑的右端和横撑的左端通过第一连接板连接,横撑的右端和右斜撑的左端通过第一连接板连接,右斜撑的右端通过第二连接板连接,横撑水平位于拱架的上部内侧,左斜撑和右斜撑左右对称分布在拱架的下部内侧。The trolley includes multiple arches and horizontal links, the multiple arches are distributed at equal intervals from front to back, and the multiple arches are connected by horizontal links; each arch includes a horizontal brace, a left oblique brace, a right oblique brace brace, the first connecting plate and the second connecting plate, the left end of the left oblique brace is connected to the arch through the second connecting plate, the right end of the left oblique brace and the left end of the cross brace are connected by the first connecting plate, and the right end of the horizontal brace and the right oblique brace are connected by the first connecting plate. The left end of the brace is connected by the first connecting plate, the right end of the right diagonal brace is connected by the second connecting plate, the transverse brace is horizontally located on the upper inner side of the arch frame, and the left diagonal brace and the right diagonal brace are symmetrically distributed on the lower inner side of the arch frame.

所述第一连接板和第二连接板均与拱架焊接连接,横撑与第一连接板、左斜撑与第一连接板和第二连接板、右斜撑与第一连接板和第二连接板均采用螺栓连接。The first connecting plate and the second connecting plate are welded to the arch frame, the horizontal brace is connected to the first connecting plate, the left diagonal brace is connected to the first connecting plate and the second connecting plate, and the right diagonal brace is connected to the first connecting plate and the first connecting plate The two connecting plates are connected by bolts.

一种用于悬索桥隧道锚锚室拱顶二衬施工方法,具体步骤为:牵引机将台架牵引至预施工拱顶位置安装防水板和钢筋,完成后将台车牵引至该安装位置,台车就位后将台车及施工模板整体顶起至施工模板安装位置,对施工模板进行调整,确认其与设计位置一致后将台车及施工模板固定,然后进行混凝土浇筑,完成拱顶一个段落浇筑,浇筑的混凝土养护期后下放台车至移动轨道上,牵引机将台车牵引至下一段落进行施工A construction method for the second lining of the dome of the anchor chamber of a suspension bridge tunnel, the specific steps are: a tractor pulls a platform to a pre-construction dome position to install a waterproof plate and a steel bar, and after completion, the trolley is pulled to the installation position, and the platform After the car is in place, lift the trolley and the construction formwork as a whole to the installation position of the construction formwork, adjust the construction formwork, confirm that it is consistent with the design position, fix the trolley and the construction formwork, and then pour concrete to complete a section of the vault Concreting, after the poured concrete curing period, lower the trolley to the moving track, and the tractor will pull the trolley to the next stage for construction

本发明的有益效果:本发明提供的这种用于悬索桥隧道锚锚室拱顶二衬施工设备,包括台车、台架、移动轨道、牵引单元、施工模板,施工模板焊接连接在台车的外侧,施工模板采用钢模板,台车、台架和牵引单元依次连接,台车和台架通过移位器在移动轨道上移动。通过牵引机将台架牵引至预施工拱顶位置,安装防水板、钢筋,完成后将台车牵引至该位置,台车就位后将台车及施工模板整体顶起至施工模板安装位置,对施工模板进行调整,确认与设计位置一致后再在台车拱架底部垫垫板垫实,将台车及施工模板固定,然后进行混凝土浇筑,完成拱顶一个段落浇筑。混凝土养护期后去除台车底部垫板,放台车至移位器上,牵引至下一段落进行施工;本发明将常规钢管支架模板体系转换为台车模板体系(台车和施工模板)进行混凝土浇筑施工,施工过程与主缆无接触,避免了施工过程中对主缆的损伤,同时无需大批量钢管材料的投入,最大化的节约了施工成本,通过牵引钢丝绳牵引台车在移动轨道内移动,牵引方便,在当前段落混凝土浇筑完毕后即可立即开始下一施工段落钢筋、防水板安装,施工安全高效,操控实用性强,可解决满堂支架施工安全可靠性不足的问题,为项目创造良好的施工经济效益;该发明在先施工锚固系统,后施工锚室二衬的工况下应用效果良好,值得在类似工程中进一步推广应用。Beneficial effects of the present invention: The construction equipment for the second lining of the dome of the anchor chamber of the suspension bridge tunnel provided by the present invention includes a trolley, a platform, a moving track, a traction unit, and a construction template, and the construction template is welded and connected to the trolley. On the outside, the construction formwork is made of steel formwork, the trolley, the gantry and the traction unit are connected in sequence, and the trolley and the gantry move on the moving track through the shifter. Pull the platform to the pre-construction vault position by the tractor, install the waterproof plate and steel bar, and pull the trolley to this position after completion. Adjust the construction formwork, confirm that it is consistent with the design position, and then place a pad at the bottom of the trolley arch, fix the trolley and the construction formwork, and then carry out concrete pouring to complete the one-stage pouring of the vault. After the concrete curing period, remove the bottom plate of the trolley, put the trolley on the shifter, and pull it to the next stage for construction; the present invention converts the conventional steel pipe support formwork system into the trolley formwork system (trolley and construction template) for concrete For pouring construction, there is no contact with the main cable during the construction process, which avoids the damage to the main cable during the construction process. At the same time, there is no need to invest in large quantities of steel pipe materials, which saves the construction cost to the greatest extent. The trolley is pulled through the traction wire rope to move in the moving track. , The traction is convenient. After the concrete pouring of the current section is completed, the installation of steel bars and waterproof panels in the next construction section can be started immediately. The construction is safe and efficient, and the control is practical. The construction economic benefits of the invention are good; the invention has a good application effect under the condition that the anchoring system is constructed first, and the second lining of the anchor chamber is constructed later, and it is worthy of further popularization and application in similar projects.

附图说明Description of drawings

以下将结合附图对本发明做进一步详细说明。The present invention will be further described in detail below with reference to the accompanying drawings.

图1是用于悬索桥隧道锚锚室拱顶二衬施工设备拱顶段施工正面图Figure 1 is the front view of the construction of the vault section of the construction equipment used for the second lining of the vault in the anchor room of the suspension bridge tunnel

图2是用于悬索桥隧道锚锚室拱顶二衬施工设备拱顶段施工侧面图;Figure 2 is a side view of the construction of the vault section of the construction equipment used for the second lining of the vault of the anchor chamber of the suspension bridge tunnel;

图3是拱架结构主视图;Figure 3 is a front view of the arch structure;

图4是台车结构俯视图;Figure 4 is a top view of the trolley structure;

图5是台架结构侧视图;Figure 5 is a side view of the gantry structure;

图6是台架结构主视图。FIG. 6 is a front view of the stand structure.

附图标记说明:1、台车;2、台架;3、移动轨道;4、移位器;5、牵引机;6、牵引钢丝绳;7、挂架;8、千斤顶;9、挂座;10、预埋件;11、施工模板;12、转向轮;1-1、拱架;1-2、横联;1-3、横撑;1-4、左斜撑;1-5、右斜撑;1-6、第一连接板;1-7、第二连接板;2-1、台架拱架;2-2、台架横联;2-3、第一横联;2-4、第二横联;2-5、第一斜撑;2-6、第二斜撑;2-7、第三斜撑;2-8、护栏。Description of reference numerals: 1. Trolley; 2. Platform; 3. Moving track; 4. Shifter; 5. Tractor; 6. Traction wire rope; 7. Hanging frame; 8. Jack; 9. Hanging seat; 10. Embedded parts; 11. Construction formwork; 12. Steering wheel; 1-1, arch frame; 1-2, transverse joint; 1-3, transverse brace; 1-4, left diagonal brace; 1-5, right Diagonal bracing; 1-6, the first connecting plate; 1-7, the second connecting plate; 2-1, the gantry arch; 2-2, the gantry horizontal connection; 2-3, the first horizontal connection; 2- 4. The second horizontal joint; 2-5, the first diagonal bracing; 2-6, the second diagonal bracing; 2-7, the third diagonal bracing; 2-8, the guardrail.

具体实施方式Detailed ways

实施例1:Example 1:

如图1和图2所示,一种用于悬索桥隧道锚锚室拱顶二衬施工设备,包括台车1、台架2、移动轨道3、牵引单元、施工模板11,施工模板11连接在台车1的外侧,台车1、台架2和牵引单元依次连接,台车1和台架2均连接在移动轨道3上。As shown in Figures 1 and 2, a construction equipment for the second lining of the dome of the anchor chamber of a suspension bridge tunnel includes a trolley 1, a platform 2, a moving track 3, a traction unit, and a construction template 11. The construction template 11 is connected to the Outside the trolley 1 , the trolley 1 , the platform 2 and the traction unit are connected in sequence, and the trolley 1 and the platform 2 are both connected to the moving track 3 .

通过牵引单元将台架2牵引至预施工拱顶位置,安装防水板、钢筋,完成后将台车1牵引至该位置,台车1就位后将台车1及施工模板11整体顶起至施工模板安装位置,对施工模板11进行调整,确认其与设计位置一致后再在台车1底部用垫板垫实,将台车1及施工模板11固定,然后进行混凝土浇筑,完成拱顶一个段落浇筑,混凝土养护期后去除台车底部垫板,放台车1至移动轨道上,牵引至下一段落进行施工;施工模板为钢模板;本发明将常规钢管支架模板体系转换为台车模板体系(台车和施工模板)进行混凝土浇筑施工,施工过程与主缆无接触,避免了施工过程中对主缆的损伤,同时无需大批量钢管材料的投入,最大化的节约了施工成本,通过牵引单元牵引台车1在移动轨道内移动,牵引方便,在当前段落混凝土浇筑完毕后即可立即开始下一施工段落钢筋、防水板安装,施工安全高效,操控实用性强,可解决满堂支架施工安全可靠性不足的问题,为项目创造良好的施工经济效益;该发明在先施工锚固系统,后施工锚室二衬的工况下应用效果良好,值得在类似工程中进一步推广应用。Pull the platform 2 to the pre-construction vault position by the traction unit, install the waterproof plate and steel bar, and pull the trolley 1 to this position after completion. The installation position of the construction formwork, adjust the construction formwork 11, confirm that it is consistent with the design position, and then use a backing plate at the bottom of the trolley 1 to fix the trolley 1 and the construction formwork 11, and then pour concrete to complete a vault. Stage pouring, remove the bottom plate of the trolley after the concrete curing period, put the trolley 1 on the moving track, and pull it to the next stage for construction; the construction formwork is a steel formwork; the present invention converts the conventional steel pipe support formwork system into a trolley formwork system (Trolley and construction formwork) for concrete pouring construction, the construction process has no contact with the main cable, which avoids damage to the main cable during the construction process. The unit traction trolley 1 moves in the moving track, and the traction is convenient. After the concrete pouring of the current section is completed, the steel bar and waterproof board installation of the next construction section can be started immediately. The construction is safe and efficient, and the operation is practical. The problem of insufficient reliability creates good construction economic benefits for the project; the invention has a good application effect under the condition that the anchoring system is constructed first, and the second lining of the anchor chamber is constructed later, and it is worthy of further popularization and application in similar projects.

实施例2:Example 2:

在实施例1的基础上,所述牵引单元包括牵引机5、牵引钢丝绳6转向轮12,台架2、转向轮12和牵引机5依次通过牵引钢丝绳6连接;所述牵引机5为牵引卷扬机或手拉葫芦。牵引机5布置于隧道锚洞口门架或隧道锚洞口,牵引机5的数量可根据实际情况进行调节,例如两台牵引机牵引,分别走四线,手拉葫芦牵引作为备用,结构简单,适应性强;牵引卷扬机牵引相较手拉葫芦速度快,施工稳定;手拉葫芦则是设备相对简单,可根据实际情况进行选择,适应性强。On the basis of Embodiment 1, the traction unit includes a traction machine 5, a traction wire rope 6, a steering wheel 12, and the gantry 2, the steering wheel 12 and the traction machine 5 are sequentially connected by the traction wire rope 6; the traction machine 5 is a traction winch or chain hoist. The tractor 5 is arranged on the portal frame of the tunnel anchor hole or the tunnel anchor hole. The number of tractors 5 can be adjusted according to the actual situation. Compared with the chain hoist, the pulling speed of the traction hoist is faster, and the construction is stable; the chain hoist is relatively simple equipment, which can be selected according to the actual situation and has strong adaptability.

所述台车1还包括移位器4,台车1通过移位器4连接移动轨道3。移位器4便于台车1在移动轨道上滑动,减少摩擦,省时省力,提高工作效率。The trolley 1 further includes a shifter 4 , and the trolley 1 is connected to the moving track 3 through the shifter 4 . The shifter 4 facilitates the sliding of the trolley 1 on the moving track, reduces friction, saves time and effort, and improves work efficiency.

如图5所示,所述台架2的临空侧设置护栏2-8。台架2采用型钢整体焊接,临空侧均设置护栏2-8防护,结构简单稳定,降低成本,安全性高。如图5和图6所示,台架包括多榀台架拱架2-1和台架横联2-2,多榀台架拱架2-1自前向后依次通过台架横联2-2连接,每榀台架拱架2-1包括第一横联2-3、第二横联2-4、第一斜撑2-5、第二斜撑2-6和第三斜撑2-7,第一横联2-3水平连接在台架拱架2-1的上部,台架拱架2-1的中部左侧和右侧水平对称连接第二横联2-4,第一横联2-3的左端和台架拱架2-1的中部左侧的第二横联2-4右端之间、第一横联2-3的右端和台架拱架2-1的中部右侧的第二横联2-4左端之间均通过支架连接,台架拱架2-1的左端和台架拱架2-1的中部左侧的第二横联2-4右端之间、台架拱架2-1的右端和台架拱架2-1的中部右侧的第二横联2-4左端之间均通过第一斜撑2-5连接,第一横联2-3的左部和台架拱架2-1的中部左侧的第二横联2-4右端之间、第一横联2-3的右部和台架拱架2-1的中部右侧的第二横联2-4左端之间均通过第二斜撑2-6连接,台架拱架2-1的顶端通过第三斜撑2-7分别连接第一横联2-3的左部和右部。第一横联2-3、第二横联2-4、第一斜撑2-5、第二斜撑2-6和第三斜撑2-7加强台架拱架2-1,结构简单稳定。As shown in FIG. 5 , guardrails 2 - 8 are provided on the airside side of the platform 2 . The platform 2 is integrally welded with profiled steel, and guardrails 2-8 are provided on the air side for protection, the structure is simple and stable, the cost is reduced, and the safety is high. As shown in Figures 5 and 6, the gantry includes a multi-frame gantry arch 2-1 and a gantry cross-connection 2-2. The multi-frame gantry arch 2-1 passes through the gantry cross-connection 2- 2 connections, each gantry arch 2-1 includes a first cross link 2-3, a second cross link 2-4, a first diagonal brace 2-5, a second diagonal brace 2-6 and a third diagonal brace 2 -7, the first horizontal link 2-3 is horizontally connected to the upper part of the gantry arch 2-1, the left and right sides of the middle part of the bench arch 2-1 are horizontally symmetrically connected to the second horizontal link 2-4, the first Between the left end of the horizontal link 2-3 and the right end of the second horizontal link 2-4 on the left side of the middle part of the gantry arch 2-1, the right end of the first horizontal link 2-3 and the middle part of the bench arch 2-1 The left end of the second horizontal link 2-4 on the right side is connected by a bracket, and the left end of the bench arch 2-1 and the right end of the second horizontal link 2-4 on the left side of the middle part of the bench arch 2-1 are connected , The right end of the gantry arch 2-1 and the left end of the second horizontal link 2-4 on the right side of the middle part of the gantry arch 2-1 are connected by the first diagonal brace 2-5, and the first horizontal link 2- Between the left part of 3 and the right end of the second horizontal link 2-4 on the left side of the middle part of the gantry arch 2-1, the right part of the first horizontal link 2-3 and the right part of the middle part of the bench arch 2-1 The left ends of the second horizontal links 2-4 are connected by the second diagonal brace 2-6, and the top of the gantry arch 2-1 is connected to the left side of the first horizontal link 2-3 through the third diagonal brace 2-7 respectively. part and right part. The first horizontal link 2-3, the second horizontal link 2-4, the first diagonal brace 2-5, the second diagonal brace 2-6 and the third diagonal brace 2-7 reinforce the gantry arch 2-1 with a simple structure Stablize.

实施例3:Example 3:

在实施例2的基础上,还包括挂架7,挂架7的数量为2组且2组挂架7左右水平对称分布在前锚室的左侧墙和右侧墙,挂架7上面沿前锚室轴线方向连接移动轨道3。挂架数量根据台车施工受力计算结果确定,本工程台车下面2组共6个挂架,挂架每边各3个,左右对称分布;移动轨道3为滑移轨道,滑移轨道采用槽钢制作且布置于前锚室的左侧墙和右侧墙侧墙的挂架7上,左侧墙的挂架7的上面和右侧墙的挂架7上面须处于同一平面上,以保证滑移轨道与挂架全部紧贴便于台车移动。On the basis of Embodiment 2, it also includes hangers 7. The number of hangers 7 is 2 groups, and the two groups of hangers 7 are horizontally symmetrically distributed on the left and right walls of the front anchor room. The upper edge of the hangers 7 The axial direction of the front anchor chamber is connected to the moving track 3 . The number of pylons is determined according to the calculation results of the construction force of the trolley. There are 6 pylons in two groups under the trolley in this project, 3 pylons on each side, symmetrically distributed on the left and right; the moving track 3 is a sliding track, and the sliding track adopts The channel steel is made and arranged on the hanger 7 of the left side wall and the right side wall of the front anchor room. Make sure that the sliding rail and the hanger are all in close contact with each other to facilitate the movement of the trolley.

还包括千斤顶8,千斤顶8的底部连接挂架7的上面,千斤顶8的上面接触连接台车1的下面。千斤顶8构造简单、重量轻、便于携带,移动方便,可很好的将台车和施工模板顶起及放下,操作简单稳定。It also includes a jack 8 , the bottom of the jack 8 is connected to the top of the hanger 7 , and the top of the jack 8 is in contact with the bottom of the trolley 1 . The jack 8 is simple in structure, light in weight, easy to carry, and easy to move.

所述挂架7还包括挂座9和预埋件10,挂架7通过挂座9连接预埋件10,预埋件10预埋在前锚室的侧墙内。预埋件10在前锚室侧墙施工时预埋,连接采用爬锥及预埋钢筋,便于安装拆除,所用挂架7采用现有挂架改制,亦可根据实际情况自行加工。The hanger 7 further includes a hanger 9 and an embedded part 10 , the hanger 7 is connected to the embedded part 10 through the hanger 9 , and the embedded part 10 is embedded in the side wall of the front anchor room. The pre-embedded parts 10 are pre-embedded during the construction of the side wall of the front anchor room, and the connection adopts climbing cones and pre-embedded steel bars, which is convenient for installation and removal.

实施例4:Example 4:

如图3和图4所示,在实施例3的基础上,所述台车1包括多榀拱架1-1和横联1-2,多榀拱架1-1自前向后依次等间距分布,多榀拱架1-1之间通过横联1-2连接;每榀拱架1-1包括横撑1-3、左斜撑1-4、右斜撑1-5、第一连接板1-6和第二连接板1-7,左斜撑1-4的左端通过第二连接板1-7连接拱架1-1,左斜撑1-4的右端和横撑1-3的左端通过第一连接板1-6连接,横撑1-3的右端和右斜撑1-5的左端通过第一连接板1-6连接,右斜撑1-5的右端通过第二连接板1-7连接,横撑1-3水平位于拱架1-1的上部内侧,左斜撑1-4和右斜撑1-5左右对称分布在拱架1-1的下部内侧。设置横撑1-3、左斜撑1-4、右斜撑1-5加强拱架1-1,结构简单稳定。As shown in FIG. 3 and FIG. 4 , on the basis of Embodiment 3, the trolley 1 includes a multi-arch frame 1-1 and a cross-link 1-2, and the multi-bar arch frame 1-1 is equally spaced from front to back. Distribution, multiple arches 1-1 are connected by horizontal links 1-2; each arch 1-1 includes horizontal braces 1-3, left diagonal braces 1-4, right diagonal braces 1-5, and the first connection The plate 1-6 and the second connecting plate 1-7, the left end of the left diagonal brace 1-4 is connected to the arch 1-1 through the second connecting plate 1-7, the right end of the left diagonal brace 1-4 and the cross brace 1-3 The left end is connected by the first connecting plate 1-6, the right end of the cross brace 1-3 and the left end of the right diagonal brace 1-5 are connected by the first connecting plate 1-6, and the right end of the right diagonal brace 1-5 is connected by the second connection The plates 1-7 are connected, the transverse brace 1-3 is horizontally located on the inner side of the upper part of the arch frame 1-1, and the left diagonal brace 1-4 and the right diagonal brace 1-5 are symmetrically distributed on the lower inner side of the arch frame 1-1. The cross brace 1-3, the left diagonal brace 1-4, and the right diagonal brace 1-5 are arranged to strengthen the arch 1-1, and the structure is simple and stable.

所述第一连接板1-6和第二连接板1-7均与拱架1-1焊接连接,横撑1-3与第一连接板1-6、左斜撑1-4与第一连接板1-6和第二连接板1-7、右斜撑1-5与第一连接板1-6和第二连接板1-7均采用螺栓连接。第一连接板1-6和第二连接板1-7均与拱架1-1焊接连接,焊接连接保证横撑1-3与左斜撑1-4或右斜撑1-5稳固连接在拱架1-1上,提高结构的整体稳定性;横撑1-3与第一连接板1-6、左斜撑1-4与第一连接板1-6和第二连接板1-7、右斜撑1-5与第一连接板1-6和第二连接板1-7均采用螺栓连接,便于安装、拆卸,操作简单方便。The first connecting plate 1-6 and the second connecting plate 1-7 are welded and connected to the arch 1-1, the horizontal brace 1-3 is connected to the first connecting plate 1-6, and the left diagonal brace 1-4 is connected to the first connecting plate 1-6. The connecting plate 1-6 and the second connecting plate 1-7, and the right diagonal brace 1-5 are connected with the first connecting plate 1-6 and the second connecting plate 1-7 by bolts. The first connecting plate 1-6 and the second connecting plate 1-7 are both welded and connected to the arch 1-1, and the welded connection ensures that the cross brace 1-3 is firmly connected to the left diagonal brace 1-4 or the right diagonal brace 1-5. On the arch 1-1, the overall stability of the structure is improved; the cross brace 1-3 and the first connecting plate 1-6, the left diagonal brace 1-4 and the first connecting plate 1-6 and the second connecting plate 1-7 , The right diagonal brace 1-5 is connected with the first connecting plate 1-6 and the second connecting plate 1-7 by bolts, which is convenient for installation and disassembly, and the operation is simple and convenient.

实施例5:Example 5:

一种用于悬索桥隧道锚锚室拱顶二衬施工方法,牵引机5将台架2牵引至预施工拱顶位置安装防水板和钢筋,完成后将台车1牵引至该安装位置,台车1就位后将台车1及施工模板11整体顶起至施工模板安装位置,对施工模板11进行调整,确认其与设计位置一致后将台车1及施工模板11固定,然后进行混凝土浇筑,完成拱顶一个段落浇筑,浇筑的混凝土养护期后下放台车1至移动轨道3上,牵引机5将台车1牵引至下一段落进行施工;A construction method for the second lining of the dome of the anchor chamber of the tunnel of a suspension bridge. The tractor 5 pulls the platform 2 to the pre-construction dome position to install the waterproof plate and the steel bar, and after the completion, the trolley 1 is pulled to the installation position. 1 After being in place, lift the trolley 1 and the construction formwork 11 to the installation position of the construction formwork as a whole, adjust the construction formwork 11, confirm that it is consistent with the design position, and fix the trolley 1 and the construction formwork 11, and then carry out concrete pouring, After completing the pouring of one section of the vault, lower the trolley 1 to the moving track 3 after the poured concrete curing period, and the tractor 5 pulls the trolley 1 to the next stage for construction;

本发明提供的这种用于悬索桥隧道锚锚室拱顶二衬施工设备,通过牵引机5将台架2牵引至预施工拱顶位置,安装防水板、钢筋,完成后将台车1牵引至该位置,台车1就位后用千斤顶8将台车1及施工模板11整体顶起至施工模板安装位置,对施工模板11进行调整无误后再在台车1拱架1-1底部垫钢板垫实,将台车1及施工模板11固定,然后进行混凝土浇筑,完成拱顶一个段落浇筑,混凝土养护期后去除台车底部钢板,千斤顶8下放台车1至移位器4上,牵引至下一段落进行施工;本发明将常规钢管支架模板体系转换为台车模板体系(台车和施工模板)进行混凝土浇筑施工,施工过程与主缆无接触,避免了施工过程中对主缆的损伤,同时无需大批量钢管材料的投入,最大化的节约了施工成本,通过牵引钢丝绳牵引台车在移动轨道内移动,牵引方便,在当前段落混凝土浇筑完毕后即可立即开始下一施工段落钢筋、防水板安装,施工安全高效,操控实用性强,可解决满堂支架施工安全可靠性不足的问题,为项目创造良好的施工经济效益;该发明在先施工锚固系统,后施工锚室二衬的工况下应用效果良好,值得在类似工程中进一步推广应用。The present invention provides the construction equipment for the second lining of the dome of the anchor chamber of the suspension bridge tunnel. The platform 2 is pulled to the pre-construction dome position by the tractor 5, the waterproof plate and the steel bar are installed, and after completion, the trolley 1 is pulled to the At this position, after the trolley 1 is in place, use the jack 8 to lift the trolley 1 and the construction formwork 11 as a whole to the installation position of the construction formwork. After the construction formwork 11 is adjusted correctly, a steel plate is placed at the bottom of the arch frame 1-1 of the trolley 1. Cushion, fix the trolley 1 and the construction formwork 11, and then pour the concrete to complete the pouring of the vault. The construction is carried out in the next paragraph; the present invention converts the conventional steel pipe support formwork system into a trolley formwork system (a trolley and a construction formwork) for concrete pouring construction, and the construction process is not in contact with the main cable, thereby avoiding damage to the main cable during the construction process. At the same time, there is no need to invest a large amount of steel pipe materials, which saves the construction cost to the greatest extent. The trolley is pulled through the traction wire rope to move in the moving track, which is convenient for traction. After the concrete pouring of the current section is completed, the next construction section can be started immediately. Reinforcement and waterproofing Slab installation, safe and efficient construction, strong control practicability, can solve the problem of insufficient safety and reliability of full-house support construction, and create good construction economic benefits for the project. The application effect is good, and it is worthy of further promotion and application in similar projects.

本发明的描述中,需要理解的是,若有术语“左”、“右”、“右”等指示的方位或位置关系为基于附图所示的方位或位置关系,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此附图中描述位置关系的用语仅用于示例性说明,不能理解为对本专利的限制。In the description of the present invention, it should be understood that the orientation or positional relationship indicated by the terms "left", "right", "right", etc. is based on the orientation or positional relationship shown in the drawings, rather than indicated or implied. The device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, so the terms describing the positional relationship in the accompanying drawings are for illustrative purposes only and should not be construed as a limitation on the present patent.

以上例举仅仅是对本发明的举例说明,并不构成对本发明的保护范围的限制,凡是与本发明相同或相似的设计均属于本发明的保护范围之内。The above examples are only examples of the present invention, and do not constitute a limitation on the protection scope of the present invention, and all designs that are identical or similar to the present invention belong to the protection scope of the present invention.

Claims (10)

1.一种用于悬索桥隧道锚锚室拱顶二衬施工设备,其特征在于:包括台车(1)、台架(2)、移动轨道(3)、牵引单元、施工模板(11),施工模板(11)连接在台车(1)的外侧,台车(1)、台架(2)和牵引单元依次连接,台车(1)和台架(2)均连接在移动轨道(3)上。1. a kind of construction equipment for the second lining of the dome of the anchor chamber of the suspension bridge tunnel, it is characterized in that: comprise trolley (1), platform (2), moving track (3), traction unit, construction template (11), The construction formwork (11) is connected to the outside of the trolley (1), the trolley (1), the platform (2) and the traction unit are connected in sequence, and the trolley (1) and the platform (2) are both connected to the moving track (3) )superior. 2.如权利要求1所述的用于悬索桥隧道锚锚室拱顶二衬施工设备,其特征在于:所述牵引单元包括牵引机(5)、牵引钢丝绳(6)和转向轮(12),台架(2)、转向轮(12)和牵引机(5)依次通过牵引钢丝绳(6)连接;所述牵引机(5)为牵引卷扬机或手拉葫芦。2. The construction equipment for the second lining of the dome of the anchor chamber of the suspension bridge tunnel according to claim 1, wherein the traction unit comprises a traction machine (5), a traction wire rope (6) and a steering wheel (12), The platform (2), the steering wheel (12) and the tractor (5) are sequentially connected by a traction wire rope (6); the tractor (5) is a traction hoist or a chain hoist. 3.如权利要求1所述的用于悬索桥隧道锚锚室拱顶二衬施工设备,其特征在于:所述台车(1)还包括移位器(4),台车(1)通过移位器(4)连接移动轨道(3)。3. The construction equipment for the second lining of the dome of the anchor chamber of the suspension bridge tunnel according to claim 1, wherein the trolley (1) further comprises a shifter (4), and the trolley (1) passes through the shifter (4). The positioner (4) is connected to the moving track (3). 4.如权利要求1所述的用于悬索桥隧道锚锚室拱顶二衬施工设备,其特征在于:还包括挂架(7),挂架(7)的数量为2组且2组挂架(7)左右水平对称分布在前锚室的左侧墙和右侧墙,挂架(7)上面沿前锚室轴线方向连接移动轨道(3)。4. The construction equipment for the second lining of the dome of the anchor chamber of the suspension bridge tunnel according to claim 1, characterized in that: it also comprises a hanger (7), and the quantity of the hanger (7) is 2 groups and 2 groups of hangers (7) The left and right are symmetrically distributed on the left and right walls of the front anchor chamber, and the top of the hanger (7) is connected to the moving track (3) along the axial direction of the front anchor chamber. 5.如权利要求4所述的用于悬索桥隧道锚锚室拱顶二衬施工设备,其特征在于:还包括千斤顶(8),千斤顶(8)的底部连接挂架(7)的上面,千斤顶(8)的上面接触连接台车(1)的下面。5. as claimed in claim 4 for suspension bridge tunnel anchor chamber vault two lining construction equipment, it is characterized in that: also comprise a jack (8), the bottom of the jack (8) is connected to the top of the hanger (7), the jack The upper surface of (8) contacts the lower surface of the connecting trolley (1). 6.如权利要求4所述的用于悬索桥隧道锚锚室拱顶二衬施工设备,其特征在于:所述挂架(7)还包括挂座(9)和预埋件(10),挂架(7)通过挂座(9)连接预埋件(10),预埋件(10)预埋在前锚室的侧墙内。6. The construction equipment for the second lining of the dome of the anchor chamber of the suspension bridge tunnel according to claim 4, wherein the hanger (7) further comprises a hanger (9) and an embedded part (10), the hanger (7) The frame (7) is connected to the embedded part (10) through the hanging seat (9), and the embedded part (10) is embedded in the side wall of the front anchor room. 7.如权利要求1所述的用于悬索桥隧道锚锚室拱顶二衬施工设备,其特征在于:所述台架(2)的临空侧设置护栏(2-8)。7 . The construction equipment for the second lining of the vault of the anchor chamber of a suspension bridge tunnel according to claim 1 , wherein a guardrail ( 2 - 8 ) is arranged on the air-side of the platform ( 2 ). 8 . 8.如权利要求1所述的用于悬索桥隧道锚锚室拱顶二衬施工设备,其特征在于:所述台车(1)包括多榀拱架(1-1)和横联(1-2),多榀拱架(1-1)自前向后依次等间距分布,多榀拱架(1-1)之间通过横联(1-2)连接;每榀拱架(1-1)包括横撑(1-3)、左斜撑(1-4)、右斜撑(1-5)、第一连接板(1-6)和第二连接板(1-7),左斜撑(1-4)的左端通过第二连接板(1-7)连接拱架(1-1),左斜撑(1-4)的右端和横撑(1-3)的左端通过第一连接板(1-6)连接,横撑(1-3)的右端和右斜撑(1-5)的左端通过第一连接板(1-6)连接,右斜撑(1-5)的右端通过第二连接板(1-7)连接,横撑(1-3)水平位于拱架(1-1)的上部内侧,左斜撑(1-4)和右斜撑(1-5)左右对称分布在拱架(1-1)的下部内侧。8. The construction equipment for the second lining of the vault of the anchor chamber of the suspension bridge tunnel according to claim 1, characterized in that: the trolley (1) comprises a multi-arch arch (1-1) and a transverse link (1- 2), the multiple arches (1-1) are distributed at equal intervals from front to back, and the multiple arches (1-1) are connected by horizontal links (1-2); each arch (1-1) Including cross brace (1-3), left brace (1-4), right brace (1-5), first connecting plate (1-6) and second connecting plate (1-7), left brace The left end of (1-4) is connected to the arch (1-1) through the second connecting plate (1-7), and the right end of the left diagonal brace (1-4) and the left end of the cross brace (1-3) are connected through the first connection The plates (1-6) are connected, the right end of the cross brace (1-3) and the left end of the right diagonal brace (1-5) are connected through the first connecting plate (1-6), and the right end of the right diagonal brace (1-5) Connected by the second connecting plate (1-7), the transverse brace (1-3) is horizontally located on the upper inner side of the arch (1-1), the left diagonal brace (1-4) and the right diagonal brace (1-5) are left and right Symmetrically distributed on the lower inner side of the arch (1-1). 9.如权利要求8所述的用于悬索桥隧道锚锚室拱顶二衬施工设备,其特征在于:所述第一连接板(1-6)和第二连接板(1-7)均与拱架(1-1)焊接连接,横撑(1-3)与第一连接板(1-6)、左斜撑(1-4)与第一连接板(1-6)和第二连接板(1-7)、右斜撑(1-5)与第一连接板(1-6)和第二连接板(1-7)均采用螺栓连接。9. The construction equipment for the second lining of the dome of the anchor chamber of the suspension bridge tunnel according to claim 8, wherein the first connecting plate (1-6) and the second connecting plate (1-7) are both connected with The arch (1-1) is connected by welding, the cross brace (1-3) is connected with the first connecting plate (1-6), and the left diagonal brace (1-4) is connected with the first connecting plate (1-6) and the second connecting plate (1-6) The plate (1-7) and the right diagonal brace (1-5) are connected with the first connecting plate (1-6) and the second connecting plate (1-7) by bolts. 10.一种用于悬索桥隧道锚锚室拱顶二衬施工方法,其特征在于:具体步骤为:牵引机(5)将台架(2)牵引至预施工拱顶位置安装防水板和钢筋,完成后将台车(1)牵引至该安装位置,台车(1)就位后将台车(1)及施工模板(11)整体顶起至施工模板安装位置,对施工模板(11)进行调整,确认其与设计位置一致后将台车(1)及施工模板(11)固定,然后进行混凝土浇筑,完成拱顶一个段落浇筑,浇筑的混凝土养护期后下放台车(1)至移动轨道(3)上,牵引机(5)将台车(1)牵引至下一段落进行施工。10. A construction method for the second lining of the dome of the anchor chamber of a suspension bridge tunnel, characterized in that: the concrete steps are: a tractor (5) pulls the platform (2) to a pre-construction dome position to install a waterproof plate and a steel bar, After completion, the trolley (1) is towed to the installation position. After the trolley (1) is in place, the trolley (1) and the construction formwork (11) are jacked up as a whole to the construction formwork installation position, and the construction formwork (11) is carried out. Adjust and confirm that it is consistent with the design position, fix the trolley (1) and the construction template (11), and then carry out concrete pouring, complete the pouring of one segment of the vault, and lower the trolley (1) to the moving track after the concrete curing period. (3) On, the tractor (5) pulls the trolley (1) to the next stage for construction.
CN202010529223.2A 2020-06-11 2020-06-11 A device and method for constructing the secondary lining of the anchor chamber vault of a suspension bridge tunnel Active CN111622781B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010529223.2A CN111622781B (en) 2020-06-11 2020-06-11 A device and method for constructing the secondary lining of the anchor chamber vault of a suspension bridge tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010529223.2A CN111622781B (en) 2020-06-11 2020-06-11 A device and method for constructing the secondary lining of the anchor chamber vault of a suspension bridge tunnel

Publications (2)

Publication Number Publication Date
CN111622781A true CN111622781A (en) 2020-09-04
CN111622781B CN111622781B (en) 2025-01-24

Family

ID=72258405

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010529223.2A Active CN111622781B (en) 2020-06-11 2020-06-11 A device and method for constructing the secondary lining of the anchor chamber vault of a suspension bridge tunnel

Country Status (1)

Country Link
CN (1) CN111622781B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113236316A (en) * 2021-05-11 2021-08-10 中交二公局第二工程有限公司 Method for mounting prestressed finished cable of tunnel anchor
CN113668392A (en) * 2021-08-11 2021-11-19 中建桥梁有限公司 Construction method for large-inclination-angle tunnel type anchorage secondary lining support
CN113914897A (en) * 2021-09-27 2022-01-11 中铁十四局集团建筑工程有限公司 Movable vault secondary lining template rack and connection cavern rack moving structure
CN114320367A (en) * 2021-12-31 2022-04-12 安徽水利开发有限公司 City gate hole type small end face tunnel and construction method
GB2629668A (en) * 2024-01-25 2024-11-06 Grupo Empresarial Tecozam Sl Formwork carriage for the construction of tunnel vaults

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102606172A (en) * 2012-04-09 2012-07-25 湖南五新重型装备有限公司 Hydraulic self-propelled large-gradient concrete pouring trolley
CN103939113A (en) * 2014-05-14 2014-07-23 中铁二局股份有限公司 Suspension rail type construction trolley
CN104033163A (en) * 2014-05-06 2014-09-10 中铁十七局集团第二工程有限公司 One-time concrete-pouring forming method of bottom plate and side walls of hydraulic tunnel
CN104948203A (en) * 2015-04-29 2015-09-30 中铁隧道集团三处有限公司 Integral construction method for inclined-shaft tunnel linings and asymmetric mid-wall linings
CN107130982A (en) * 2017-06-30 2017-09-05 云南公投建设集团隧道工程有限公司 Large Longitudinal Slope two serves as a contrast concrete construction equipment and construction method
CN110593124A (en) * 2019-10-11 2019-12-20 中交二公局第五工程有限公司 Suspension bridge anchorage front anchor chamber top cover plate and construction method thereof
CN110670491A (en) * 2019-10-29 2020-01-10 中国铁建大桥工程局集团有限公司 Front anchor chamber roof cast-in-place construction device and construction method
CN212479255U (en) * 2020-06-11 2021-02-05 中交二公局第二工程有限公司 A construction equipment for the second lining of the vault of the anchor chamber of the suspension bridge tunnel

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102606172A (en) * 2012-04-09 2012-07-25 湖南五新重型装备有限公司 Hydraulic self-propelled large-gradient concrete pouring trolley
CN104033163A (en) * 2014-05-06 2014-09-10 中铁十七局集团第二工程有限公司 One-time concrete-pouring forming method of bottom plate and side walls of hydraulic tunnel
CN103939113A (en) * 2014-05-14 2014-07-23 中铁二局股份有限公司 Suspension rail type construction trolley
CN104948203A (en) * 2015-04-29 2015-09-30 中铁隧道集团三处有限公司 Integral construction method for inclined-shaft tunnel linings and asymmetric mid-wall linings
CN107130982A (en) * 2017-06-30 2017-09-05 云南公投建设集团隧道工程有限公司 Large Longitudinal Slope two serves as a contrast concrete construction equipment and construction method
CN110593124A (en) * 2019-10-11 2019-12-20 中交二公局第五工程有限公司 Suspension bridge anchorage front anchor chamber top cover plate and construction method thereof
CN110670491A (en) * 2019-10-29 2020-01-10 中国铁建大桥工程局集团有限公司 Front anchor chamber roof cast-in-place construction device and construction method
CN212479255U (en) * 2020-06-11 2021-02-05 中交二公局第二工程有限公司 A construction equipment for the second lining of the vault of the anchor chamber of the suspension bridge tunnel

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113236316A (en) * 2021-05-11 2021-08-10 中交二公局第二工程有限公司 Method for mounting prestressed finished cable of tunnel anchor
CN113236316B (en) * 2021-05-11 2024-07-12 中交二公局第二工程有限公司 Tunnel anchor prestress finished rope installation method
CN113668392A (en) * 2021-08-11 2021-11-19 中建桥梁有限公司 Construction method for large-inclination-angle tunnel type anchorage secondary lining support
CN113668392B (en) * 2021-08-11 2023-02-21 中建桥梁有限公司 Construction method for large-inclination-angle tunnel type anchorage secondary lining support
CN113914897A (en) * 2021-09-27 2022-01-11 中铁十四局集团建筑工程有限公司 Movable vault secondary lining template rack and connection cavern rack moving structure
CN114320367A (en) * 2021-12-31 2022-04-12 安徽水利开发有限公司 City gate hole type small end face tunnel and construction method
CN114320367B (en) * 2021-12-31 2023-08-04 安徽水利开发有限公司 City gate opening type small-end-face tunnel and construction method
GB2629668A (en) * 2024-01-25 2024-11-06 Grupo Empresarial Tecozam Sl Formwork carriage for the construction of tunnel vaults
GB2629668B (en) * 2024-01-25 2025-05-07 Grupo Empresarial Tecozam Sl Formwork carriage for the construction of tunnel vaults

Also Published As

Publication number Publication date
CN111622781B (en) 2025-01-24

Similar Documents

Publication Publication Date Title
CN111622781A (en) Construction equipment and method for suspension bridge tunnel anchor chamber vault secondary lining
US11634877B2 (en) Method for removal of temporary support system for road bridge pre-fabricated small box girder-type concealed bent cap, and equipment therefor
CN101922143B (en) Cover beam construction method
CN110700119B (en) Design construction method of walking system on assembled bailey beam hanging basket
CN105971274A (en) Cantilever support frame formwork system and construction method thereof
CN106744351A (en) The method of hoisting the main girder of the cable-stayed bridge by using the cable crane
CN211420881U (en) Movable formwork for concrete construction of overhanging wing plate of steel-concrete composite beam
CN212479255U (en) A construction equipment for the second lining of the vault of the anchor chamber of the suspension bridge tunnel
CN105370027B (en) The construction method of steel supporting platform structure is integrally lifted in high-rise hanging structure
CN107697812A (en) A kind of cantilever crane set up for bridge subsection transport
CN110700112A (en) Movable formwork for concrete construction of overhanging wing plate of steel-concrete composite beam and construction method
CN116853963B (en) A hoisting device and hoisting method for main beam of cable-stayed bridge
CN205529915U (en) Ladder type masts type hangs pieces together loop wheel machine
CN207293976U (en) A kind of cantilever crane set up for bridge subsection transport
CN115948988B (en) One-time cast-in-situ construction method by continuous beam bracket method
CN210395127U (en) Assembled Bailey beam hanging basket upper walking system
CN116695589A (en) A construction method for overall assembly and lifting of a dragline hanging basket structure
CN212077660U (en) Large-span wide width bridge girder rhombus hanging basket construction structure
CN210798994U (en) Concrete structure wall body unilateral template structure
CN111593874B (en) Support system and construction method for super-high-rise residential transfer layer super-heavy cantilevered components
CN112482241A (en) Walking type hanging bracket for post-pouring section of box girder flange plate and construction method thereof
CN111395850A (en) Assembled tower frame for cable hoisting system and erection method
CN220976316U (en) Railway beam bridge crane equipment
CN218345960U (en) Construction structure of cross-river bridge
CN219080110U (en) Steel-pipe column support construction safety platform device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20250323

Address after: 210000 No. 396 Binjiang Avenue, Jiangbei new area, Nanjing, Jiangsu

Patentee after: East China Construction Co., Ltd. of CCCC Second Highway Engineering Co.,Ltd.

Country or region after: China

Address before: 710119 No.29, No.1 Enterprise Park, West Avenue, high tech Zone, Xi'an City, Shaanxi Province

Patentee before: CCCC-SHEC SECOND ENGINEERING Co.,Ltd.

Country or region before: China