CN107697812A - A kind of cantilever crane set up for bridge subsection transport - Google Patents
A kind of cantilever crane set up for bridge subsection transport Download PDFInfo
- Publication number
- CN107697812A CN107697812A CN201710915264.3A CN201710915264A CN107697812A CN 107697812 A CN107697812 A CN 107697812A CN 201710915264 A CN201710915264 A CN 201710915264A CN 107697812 A CN107697812 A CN 107697812A
- Authority
- CN
- China
- Prior art keywords
- supporting leg
- bridge
- main couple
- cantilever crane
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 claims description 7
- 239000010959 steel Substances 0.000 claims description 7
- 238000010276 construction Methods 0.000 abstract description 30
- 238000009417 prefabrication Methods 0.000 abstract description 13
- 230000032258 transport Effects 0.000 description 12
- 238000009434 installation Methods 0.000 description 6
- 239000000725 suspension Substances 0.000 description 3
- 244000261422 Lysimachia clethroides Species 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000009408 flooring Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 238000004873 anchoring Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000003032 molecular docking Methods 0.000 description 1
- 238000012876 topography Methods 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C17/00—Overhead travelling cranes comprising one or more substantially horizontal girders the ends of which are directly supported by wheels or rollers running on tracks carried by spaced supports
- B66C17/06—Overhead travelling cranes comprising one or more substantially horizontal girders the ends of which are directly supported by wheels or rollers running on tracks carried by spaced supports specially adapted for particular purposes, e.g. in foundries, forges; combined with auxiliary apparatus serving particular purposes
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a kind of cantilever crane set up for bridge subsection transport, it includes two main couples be arrangeding in parallel(1), main couple(1)Between be provided with middle cross beam(2), main couple(1)Top is provided with lifting dolly(3), main couple(1)The middle supporting leg being connected with bridge floor is provided with below middle part(4), main couple(1)The rear support leg being connected with bridge floor is provided with below rearward end(5), the cantilever crane also includes and main couple(1)The rear slip supporting leg being slidably connected(6).The present invention bridge prefabrication section splice during have it is simple in construction, be easy to set up, section transport it is more convenient the advantages of, reduce construction quantities and construction difficulty, improve construction safety coefficient, the construction period is shorter, splicing precision it is higher.
Description
Technical field
The present invention relates to a kind of equipment for bridge construction, particularly a kind of cantilever crane set up for bridge subsection transport.
Background technology
During bridge erection is constructed, the means spliced typically by prefabricated subsection are set up;Build first
Bridge tower, completion erection is then fixedly connected with by prefabricated bridge subsection lifting and with bridge tower.Apply at present carrying out erection to bridge
In man-hour, because prefabricated subsection build is larger, bridge tower is higher, and during splicing is set up, quantities is larger, and difficulty of construction is higher,
Construction risk is higher, and the duration is longer.In bridge prefabrication section, splicing is more during setting up at present is applied using erection crane
Work, but because erection crane need to set pre-splicing field in work progress under tower, it is not only larger by the influence of topography, and high-altitude is risen
Crane operation lifting altitude is higher, pre-splicing field under tower is had a great influence during work high above the ground, working security is relatively low, while uses bridge floor
Each tie point is both needed to set construction platform when loop wheel machine carries out lifting operation, sets operation relatively complicated, causes the construction period longer.
Therefore, at present in bridge prefabrication section splicing exist during setting up loop wheel machine set difficulty is higher, section transport is relatively complicated,
The shortcomings that construction work amount is larger, difficulty of construction is higher, construction risk is higher and the duration is longer.
The content of the invention
It is an object of the present invention to provide a kind of cantilever crane set up for bridge subsection transport.The present invention is in bridge
Prefabricated subsection splice during have it is simple in construction, be easy to set up, section transport it is more convenient the advantages of, reduce construction
Quantities and the difficulty of construction, improve construction safety coefficient, and the construction period is shorter, and splicing precision is higher.
Technical scheme:A kind of bridge subsection that is used for transports the cantilever crane set up, including two be arranged in parallel
Main couple, middle cross beam is provided between main couple, is provided with lifting dolly above main couple, lifting dolly can on main couple longitudinal direction
Mobile, lower section is provided with the middle supporting leg being connected with girder in the middle part of main couple, is provided with below main couple rearward end after being connected with girder
Supporting leg, the cantilever crane also include the rear slip supporting leg being slidably connected with main couple.
In a kind of foregoing cantilever crane set up for bridge subsection transport, the lifting dolly includes upending frame, rises
Hanging dolly can walk on upending frame, realize the direction across bridge movement of lifting dolly;The lifting dolly also includes rotary hanger, revolves
Rotary lifting is connected by steel wire rope cabling with lifting dolly, and rotary hanger can carry out full circle swinging, and framework is provided with below rotary hanger
Suspender.
In a kind of foregoing cantilever crane set up for bridge subsection transport, wherein the middle cross beam is packaged type crossbeam,
Supporting leg is installed below middle cross beam both ends.
In a kind of foregoing cantilever crane set up for bridge subsection transport, the middle supporting leg and rear support leg are liftable
Supporting leg.
Compared with prior art, by supporting leg in setting and rear support leg, two are set to put down above middle supporting leg and rear support leg
Capable main couple, and lifting dolly is set above main couple, it is more convenient to build, and need to only be set in construction in steel girder joint
Steel girder and the prefabricated bridge installation of bridge subsection can be carried out by putting construction platform, reduce quantities and the construction of construction
Difficulty, and pre-splicing field can be arranged on bridge floor, it is easy to bridge prefabrication section to transport and splice, while reduce work high above the ground
Point, workmen is reduced, improve working security, reduce the construction period.
The using effect of the artificial checking cantilever crane of application, by practice of construction by cantilever crane with present frequently with bridge
Face loop wheel machine contrasts, and concrete outcome is as shown in table 1:
In summary, the present invention bridge prefabrication section splice during have it is simple in construction, be easy to set up, section transport compared with
For it is convenient the advantages of, reduce construction quantities and construction difficulty, improve construction safety coefficient, the construction period is shorter,
It is higher to splice precision.
Brief description of the drawings
Fig. 1 is the structural representation of the present invention;
Fig. 2 is the side structure schematic diagram of the present invention;
Fig. 3 is hoisting process schematic diagram of the present invention.
Mark in accompanying drawing for:1- main couples, 2- middle cross beams, 3- lifting dollies, supporting leg in 4-, 5- rear support legs are sliding after 6-
Dynamic supporting leg, 7- upending frames, 8- lifting jacks, 9- rotary hangers, 10- frame lifting appliances, 11- supporting legs.
Embodiment
The present invention is further illustrated with reference to the accompanying drawings and examples, but be not intended as to the present invention limit according to
According to.
Embodiment.A kind of cantilever crane set up for bridge subsection transport, as shown in Figure 1 to Figure 3, including two parallel
The main couple 1 of setting, middle cross beam 2 is provided between main couple 1, the top of main couple 1 is provided with lifting dolly 3, and lifting dolly 3 can be in master
Vertically moved on truss 1, the middle part of main couple 1 lower section is provided with the middle supporting leg 4 being connected with bridge floor, is provided with below the rearward end of main couple 1
The rear support leg 5 being connected with bridge floor, the cantilever crane also include the rear slip supporting leg 6 being slidably connected with main couple 1.
The lifting dolly 3 includes upending frame 7, and lifting dolly 3 can walk on upending frame 7, realizes that lifting dolly 3 is horizontal
Bridge is to movement;The lifting dolly 3 also includes rotary hanger 9, and rotary hanger 9 is connected by steel wire rope cabling with lifting dolly 3,
Rotary hanger 9 can carry out full circle swinging, and the lower section of rotary hanger 9 is provided with frame lifting appliance 10;Wherein the middle cross beam 2 is packaged type crossbeam,
The both ends supported underneath leg 11 of middle cross beam 2;The middle supporting leg 4 and rear support leg 5 are liftable supporting leg.
Operation principle:Cantilever crane walking process, the gooseneck of reach middle cross beam 2 to the anchor tie plate position for having completed beam section
On, the rear supporting leg 6 that slides is moved near middle supporting leg 4, the point midway that dolly is moved between middle cross beam 2 and middle supporting leg 4, is put down
Frame lifting appliance 10 to bridge floor, middle supporting leg 4 and rear support leg 5 shrinks, and reduces the height of main couple 1, makes the supporting leg of middle cross beam 2 and rear sliding
Supporting leg is supported on bridge floor, releases the anchor measure of rear support leg 5, and middle supporting leg 4 and rear support leg 5 continue to shrink, and leave bridge floor, middle cross beam
2 and the rear supporting leg 6 that slides drive main couple 1 to move forward, lifting dolly 3 is synchronously moved rearwards, when after slide supporting leg 6 after and prop up
During leg 5, stop movement.Supporting leg 4 and rear support leg 5 in jacking, supporting leg is slid after making and departs from bridge floor, it is rear to slide the adjustment of supporting leg forward end
One segment distance, then middle supporting leg 4 and rear support leg 5 shrink away from bridge floor, the rear supporting leg that slides is supported on bridge floor again, middle cross beam 2
Main couple 1 is driven to move forward again with rear slip supporting leg 6, lifting dolly 3 is synchronously moved rearwards, and central supporting leg 4 is located at anchor drawing
When at plate above gooseneck, stop main couple 1 and move forward.Supporting leg 4 and rear support leg 5 in jacking, main couple 1 is raised to operation height,
The supporting leg of middle cross beam 2 and rear sliding supporting leg is set to depart from bridge floor, middle cross beam 2 is moved near rear support leg 5, and anchoring rear support leg 5 is in steel master
On beam crossbeam, the installation frame suspender 10 of dolly 3 is lifted by crane, prepares lifting operation.
During the splicing of bridge prefabrication section is set up, cantilever crane is built in girder front end, anchors rear support leg 5, lifting dolly 3,
Middle cross beam 2, rear sliding supporting leg are moved to the rearward end of main couple 1, and then installing frame is set a roof beam in place suspender on lifting dolly 3, is prepared
Lifting operation;During construction, by travelling bogie, bridge prefabrication section is transported to cantilever crane rear, in bridge out of pre-splicing field first
Installation frame suspender 10 on prefabricated subsection, and be connected with rotary hanger 9 on lifting dolly 3, bridge prefabrication section is carried out assembly
After, you can carry out next bridge prefabrication section assembling.
Lift by crane dolly 3 and lift by crane bridge prefabrication section, walked to girder front end, and adjust bridge prefabrication section in good time to bridge
Midline position, middle cross beam 2 follows lifting dolly 3 to move ahead, and is fixed in the middle position of supporting leg 4, and lifting dolly 3 proceeds to installation
The anchor tie plate crossbeam position+10cm places parking of section.
Rotary hanger 9 is operated, rotates 90 degree of steel girder section to installation site by rule, it is pre- that lifting dolly 3 transfers bridge
Section processed is alignd with having installed section, and lifting dolly 3 adjusts bridge prefabrication section docking location, installs connecting plate and high intensity spiral shell
Bolts, suspension cable and prefabricated bridge, floorings are installed and are installed in place in order by cantilever crane, suspension cable successively just and
Two, the wet seam of floorings of constructing, after concrete strength reaches 100%, stretch-draw prestressing force and suspension cable, cantilever crane are run to
On the beam section middle cross beam 2, repeat the above steps and carry out next bridge prefabrication section installation.
Claims (4)
- A kind of 1. cantilever crane set up for bridge subsection transport, it is characterised in that:Including two main couples be arrangeding in parallel (1), main couple(1)Between be provided with middle cross beam(2), main couple(1)Top is provided with lifting dolly(3), main couple(1)Below middle part Provided with the middle supporting leg being connected with girder(4), main couple(1)The rear support leg being connected with girder is provided with below rearward end(5), it is described outstanding Arm loop wheel machine also includes and main couple(1)The rear slip supporting leg being slidably connected(6).
- A kind of 2. cantilever crane set up for bridge subsection transport according to claim 1, it is characterised in that:Described Hang dolly(3)Including upending frame(7);The lifting dolly(3)Also include rotary hanger(9), rotary hanger(9)Pass through steel wire rope Cabling and lifting dolly(3)Connection, rotary hanger(9)Lower section is provided with frame lifting appliance(10).
- A kind of 3. cantilever crane set up for bridge subsection transport according to claim 1, it is characterised in that:In described Crossbeam(2)For packaged type crossbeam, middle cross beam(2)Supporting leg is installed below both ends(11).
- A kind of 4. cantilever crane set up for bridge subsection transport according to claim 1, it is characterised in that:In described Supporting leg(4)And rear support leg(5)For liftable supporting leg.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710915264.3A CN107697812A (en) | 2017-09-30 | 2017-09-30 | A kind of cantilever crane set up for bridge subsection transport |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710915264.3A CN107697812A (en) | 2017-09-30 | 2017-09-30 | A kind of cantilever crane set up for bridge subsection transport |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107697812A true CN107697812A (en) | 2018-02-16 |
Family
ID=61183259
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710915264.3A Pending CN107697812A (en) | 2017-09-30 | 2017-09-30 | A kind of cantilever crane set up for bridge subsection transport |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107697812A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109629448A (en) * | 2019-01-28 | 2019-04-16 | 中铁大桥局集团有限公司 | The synchronous device and method for setting up girder and floorings |
CN109733995A (en) * | 2019-01-28 | 2019-05-10 | 青岛长永机械工程有限公司 | A kind of prefabricated pipe gallery of Urban Underground is laid with hoisting machine and construction method |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2385636A1 (en) * | 1977-03-28 | 1978-10-27 | Mecatel | Structure for installing bridge girders - has secondary supports slidable on guides to allow attachment to piers which follow curve |
JPH0579018A (en) * | 1991-09-18 | 1993-03-30 | P S Co Ltd | Bridge girder laying device |
CN101581073A (en) * | 2008-07-10 | 2009-11-18 | 中铁大桥局股份有限公司 | Downlink movable mould frame and walking method thereof |
CN102303819A (en) * | 2011-08-12 | 2012-01-04 | 中国水电建设集团铁路建设有限公司 | Railway bridge sound barrier upright hoisting trolley |
CN103590340A (en) * | 2013-10-31 | 2014-02-19 | 河北工业大学 | Lower guide beam walking type bridge erection machine contraction and folding cantilever beam system |
CN103669211A (en) * | 2013-08-22 | 2014-03-26 | 中铁四局集团有限公司 | Hydraulic type multifunctional suspension-assembling girder lifting machine and steel box girder assembling method |
CN104261280A (en) * | 2014-09-17 | 2015-01-07 | 徐工集团工程机械股份有限公司 | Engineering machinery and changeable track base plate device thereof |
CN207293976U (en) * | 2017-09-30 | 2018-05-01 | 贵州桥梁建设集团有限责任公司 | A kind of cantilever crane set up for bridge subsection transport |
-
2017
- 2017-09-30 CN CN201710915264.3A patent/CN107697812A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2385636A1 (en) * | 1977-03-28 | 1978-10-27 | Mecatel | Structure for installing bridge girders - has secondary supports slidable on guides to allow attachment to piers which follow curve |
JPH0579018A (en) * | 1991-09-18 | 1993-03-30 | P S Co Ltd | Bridge girder laying device |
CN101581073A (en) * | 2008-07-10 | 2009-11-18 | 中铁大桥局股份有限公司 | Downlink movable mould frame and walking method thereof |
CN102303819A (en) * | 2011-08-12 | 2012-01-04 | 中国水电建设集团铁路建设有限公司 | Railway bridge sound barrier upright hoisting trolley |
CN103669211A (en) * | 2013-08-22 | 2014-03-26 | 中铁四局集团有限公司 | Hydraulic type multifunctional suspension-assembling girder lifting machine and steel box girder assembling method |
CN103590340A (en) * | 2013-10-31 | 2014-02-19 | 河北工业大学 | Lower guide beam walking type bridge erection machine contraction and folding cantilever beam system |
CN104261280A (en) * | 2014-09-17 | 2015-01-07 | 徐工集团工程机械股份有限公司 | Engineering machinery and changeable track base plate device thereof |
CN207293976U (en) * | 2017-09-30 | 2018-05-01 | 贵州桥梁建设集团有限责任公司 | A kind of cantilever crane set up for bridge subsection transport |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109629448A (en) * | 2019-01-28 | 2019-04-16 | 中铁大桥局集团有限公司 | The synchronous device and method for setting up girder and floorings |
CN109733995A (en) * | 2019-01-28 | 2019-05-10 | 青岛长永机械工程有限公司 | A kind of prefabricated pipe gallery of Urban Underground is laid with hoisting machine and construction method |
CN109629448B (en) * | 2019-01-28 | 2023-10-20 | 中铁大桥局集团有限公司 | Device and method for synchronously erecting girder and bridge deck |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208815424U (en) | A kind of bridge descending hanging basket | |
CN104195952A (en) | Steel box girder erection method applied to steel and concrete hybrid girder cable-stayed bridge | |
CN107013038B (en) | A kind of steel structure slipping of building roof lighting Zhongting changes column construction method | |
CN105000482B (en) | Tower crane with walking mechanism | |
CN208087078U (en) | A kind of boom hoisting of large span steel reinforced concrete combination beam Bridge Erector | |
CN212079327U (en) | Hydraulic pressure regulation formula side wall template platform truck | |
CN104612061A (en) | Suspended and open type novel hanging basket device and construction method thereof | |
CN108179816A (en) | A kind of deviation sliding and lifting device and method | |
CN111139743A (en) | Method for improving speed of highway beam frame and installation method of gantry crane | |
CN106044552A (en) | Multi-leg rubber-tired track-laying crane and construction method thereof | |
CN111038940A (en) | Rail mounted is used for hoist and mount traction system of transportation | |
CN107503296A (en) | Bailey bridge installation method | |
CN207293976U (en) | A kind of cantilever crane set up for bridge subsection transport | |
CN110723677B (en) | Auxiliary lifting trolley for precast beam | |
CN107268455B (en) | Concrete girder gooseneck composite structure beam cradle construction method | |
CN107697812A (en) | A kind of cantilever crane set up for bridge subsection transport | |
CN103437301A (en) | Method for mounting construction hanging basket of suspended pouring section of single plane cable-stayed bridge | |
CN114808747A (en) | Multifunctional bridge girder erection machine and bridge girder erection construction method | |
JP3150572B2 (en) | Bridge erection equipment | |
CN207987749U (en) | Ride cable-styled erection crane | |
CN104746432B (en) | The feasible bridge guidance tape in plate-beam transports installs car | |
CN208533370U (en) | A kind of Bridge Erector of large span steel reinforced concrete combination beam erection construction | |
CN106837376B (en) | Bind module turnover device for subway tunnel section of jurisdiction | |
CN108086168A (en) | Ride cable-styled erection crane | |
CN203684019U (en) | Height and span adjustable track laying machine for subway construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180216 |
|
RJ01 | Rejection of invention patent application after publication |