CN108103945A - A kind of whole landing mould bases of cast-in-situ box girder - Google Patents
A kind of whole landing mould bases of cast-in-situ box girder Download PDFInfo
- Publication number
- CN108103945A CN108103945A CN201711389770.XA CN201711389770A CN108103945A CN 108103945 A CN108103945 A CN 108103945A CN 201711389770 A CN201711389770 A CN 201711389770A CN 108103945 A CN108103945 A CN 108103945A
- Authority
- CN
- China
- Prior art keywords
- lifting
- mould bases
- lifting unit
- oil cylinder
- cast
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2/00—Bridges characterised by the cross-section of their bearing spanning structure
- E01D2/04—Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The present invention relates to construction of cast-in-situ box-beam equipment technical fields, the whole landing mould bases of specially a kind of cast-in-situ box girder, it solves time-consuming and laborious using conventional frame body during box girder construction, it is relatively low using mobile formwork sexual valence, the problem of lacking high safety performance landing mould bases simultaneously, it is included in the symmetrically arranged fore-stock in adjacent pier stud center line both ends and after-poppet, the box beam external mold with support is connected on template cross member, template cross member top is provided with counterweight away from pier stud center, fore-stock and after-poppet include frame body, main lifting cylinder is fixed on horizontal ram beam, horizontal ram beam lower part is provided with horizontal coupling beam and the two opposite can be slided, transverse adjusting oil cylinder is provided between horizontal coupling beam and horizontal ram beam.The lateral adjustment device of the present invention is arranged on the bottom of mould bases, it would be possible to cause the decentralization of stress change location so that mould bases whole stability under loading during lateral adjustments, while further enhance using counterweight the stability of mould bases.
Description
Technical field
The present invention relates to construction of cast-in-situ box-beam equipment technical fields, are specially a kind of whole landing mould bases of cast-in-situ box girder.
Background technology
Fast development with country's urban construction and the continuous input to infrastructure, overpass, railway light rail bridge
Largely show.Mobile formwork is progressively popularized in beam processed construction, due to mobile formwork beam need not both build it is huge prefabricated
Liang Chang, it is not required that the fortune beam setting up girder of large-tonnage, so as to reduce a large amount of costs for building Liang Chang;Meanwhile mobile formwork system
Beam can effectively ensure that construction speed and the passability in road under bridge face from the limitation in space.But what is had to take into account that is mobile mould
The making processing cost of frame is higher, and the construction personnel of each department is needed to have higher tacit degree and allotment in the construction process
Performance is high to the competency profiling of unit in charge of construction.
When in the wild or when blocked road carries out beam processed construction, running into road surface support force preferably and need not consider construction location
When passing through performance of bridge bottom can substantially reduce cost using frame body support.But during using raft support method construction, stent sets up week
Phase is long, safety of structure is poor, frame pipe consumption is big, and stent raw material are susceptible to corrosion, deformation, cracking in circular flow
The problems such as, influence structure safety;When using the construction of such frame body complete one across after, due to itself not possessing mobility, therefore need
Again frame body is set up, it is time-consuming and laborious.There is the supporting frame that portion of techniques personnel devise ground mobile, but study carefully its essence
For, essence is to realize moving horizontally for frame body, but die sinking, the conjunction of box beam external mold by installing fixing bracket body additional mobile device
The system that mold device is carried using template is realized that, since the matching degree of the two system is poor, frame body extremely topples, sternly
Construction safety is endangered again.
The content of the invention
The present invention in order to solve in road surface support force preferably and in the case of construction location bridge bottom need not be considered by performance,
It is time-consuming and laborious using conventional frame body, it is relatively low using mobile formwork sexual valence, while lack the problem of high safety performance lands mould bases again,
Provide a kind of cast-in-situ box girder integrally landing mould bases.
The present invention is achieved through the following technical solutions:A kind of whole landing mould bases of cast-in-situ box girder, is included in adjacent
The symmetrically arranged fore-stock in pier stud center line both ends and after-poppet, fore-stock is identical with after-poppet structure and top is elongated is provided with
Girder, fore-stock and after-poppet bottom are provided with the traveling wheel that can be moved along girder length direction, are arranged at intervals between girder
Perpendicular template cross member, template cross member pier stud position of center line be bolted separable structure, template bottom
The box beam external mold with support is connected on crossbeam, template cross member top is provided with counterweight, fore-stock away from pier stud center
Include frame body with after-poppet, hoisting frame is provided at the top of frame body, frame body bottom is provided with main lifting cylinder and lifting unit peace
Dismantling device, main lifting cylinder are fixed on horizontal ram beam, and horizontal ram beam lower part is provided with horizontal coupling beam and the two being capable of phase
To sliding, transverse adjusting oil cylinder is provided between horizontal coupling beam and horizontal ram beam.
Frame body is formed by multiple lifting unit composite assemblies, and most lower section lifting unit is connected with main lifting cylinder, each
Connecting hole A is provided in the middle part of lifting unit, inside connecting rod is provided between adjacent lifting unit, inside connecting rod includes setting in a word
The cross bar put and the bridging set in × word, cross bar and bridging are in interlaced arrangement.
Lifting unit peace dismantling device is arranged on main lifting cylinder both sides, including lifting beam position-limited rack, lifting unit dismounting oil
Cylinder and lifting beam, the rectangular frame structure of lifting beam position-limited rack and bottom centre position are fixed with lifting unit dismounting oil cylinder to be connected
It connects, the hydraulic stem of lifting unit dismounting oil cylinder is connected with lifting beam, and lifting beam can move vertically along lifting beam position-limited rack, carry
The one end for rising beam towards frame body is provided with lengthening block, lengthens and is provided with the connection that can be matched with the connecting hole of lifting unit on block
Hole B.
Girder is the combining structure of hollow rectangle beam, triangle-frame and Filled Rectangle beam, and triangle-frame is arranged on hollow square
The middle part of ellbeam and Filled Rectangle beam.
The height modulus of lifting unit is one kind in 0.5~2 meter, preferably 0.5 meter or 1 meter or 1.5 meters.
The pedestal of transverse adjusting oil cylinder is connected with horizontal coupling beam, and the hydraulic stem of transverse adjusting oil cylinder connects with horizontal ram beam
It connects.
The stroke of lifting unit dismounting oil cylinder is more than the height modulus of selected lifting unit.
Traveling wheel is arranged on the outside of horizontal coupling beam and the length of the rotation direction of traveling wheel and horizontal coupling beam is to vertical, walking
Wheel is set in orbit, and rail inferior portion is lined with sleeper.
Hydraulic station is additionally provided on mould bases, hydraulic station is fixed in horizontal coupling beam, and hydraulic station is connected to by oil pipe
Lifting unit dismounting oil cylinder, main lifting cylinder and transverse adjusting oil cylinder.
The longitudinal direction that the present invention realizes whole landing mould bases by traveling wheel is walked, and band is realized by transverse adjusting oil cylinder
Support box beam external mold moves horizontally, and demoulds or cross pier stud transposition construction in the case where not removing convenient for mould bases.Due to normal
The device of rule folding template is arranged at the bed die position of template so that landing mould bases stress in demoulding or replacing work progress
It easily changes, mould bases is caused to topple, jeopardize the life security of construction personnel.The lateral adjustment device of the present invention is arranged on mould bases
Bottom, it would be possible to cause the decentralization of stress change location so that mould bases whole stability under loading during lateral adjustments,
The stability of mould bases is further enhanced using counterweight simultaneously.The present invention is higher for ground bearing pressure and height is no more than 15 meters
Construction of cast-in-place box girders construction have high cost performance and security, be worth promoting the use of a large area.
Description of the drawings
Fig. 1 is the structural representation front view of the present invention;
Fig. 2 is the structural representation side view of present invention support higher position;
Fig. 3 is the structural representation side view of present invention support lower position;
Fig. 4 is the structure diagram of the box beam external mold with support in Fig. 2 or Fig. 3;
Fig. 5 is the decomposition texture schematic diagram of fore-stock and after-poppet in Fig. 2;
Fig. 6 is the structure diagram of lifting unit lifting means;
Fig. 7 is the structural representation side view of lifting unit peace dismantling device;
Fig. 8 is the structure diagram of girder.
In figure:1- fore-stocks, 2- after-poppets, 3- girders, 4- template cross members, box beam external molds of the 5- with support, 6- box beams
Internal model, 7- frame bodies, 8- lifting units dismounting oil cylinder, the main lifting cylinders of 9-, 10- transverse direction coupling beams, 11- hydraulic stations, 12- pier studs, 13-
Counterweight, 14- transverse adjusting oil cylinders, 15- traveling wheels, 16- lifting beams, 17- inside connecting rods, 18- lifting units, 19- hoisting frames,
20- lifting beam position-limited racks, 21- sleepers, 22- transverse direction ram beams, 23- lengthen block, 24- hollow rectangle beams, 25- triangle-frames, 26-
Filled Rectangle beam, 27- tracks.
Specific embodiment
With reference to Fig. 1~Fig. 8, the present invention will be further described, and a kind of whole landing mould bases of cast-in-situ box girder is included in phase
The symmetrically arranged fore-stock 1 in adjacent 12 center line both ends of pier stud and after-poppet 2, fore-stock 1 is identical with 2 structure of after-poppet and top leads to
Length is provided with girder 3, and fore-stock 1 and 2 bottom of after-poppet are provided with the traveling wheel 15 that can be moved along 3 length direction of girder, main
Perpendicular template cross member 4 is arranged at intervals between beam 3, template cross member 4 is to be bolted in 12 position of center line of pier stud
Separable structure, the box beam external mold 5 with support is connected on template cross member 4,4 top of template cross member is away from pier stud 12
Heart position is provided with counterweight 13, and fore-stock 1 and after-poppet 2 include frame body 7, and 7 top of frame body is provided with hoisting frame 19, frame body 7
Bottom is provided with main lifting cylinder 9 and lifting unit peace dismantling device, and main lifting cylinder 9 is fixed on horizontal ram beam 22, laterally
22 lower part of ram beam is provided with horizontal coupling beam 10 and the two opposite can be slided, and is set between horizontal coupling beam 10 and horizontal ram beam 22
There is transverse adjusting oil cylinder 14.
The stroke of lifting unit dismounting oil cylinder 8 is more than the height modulus of selected lifting unit 18.
Traveling wheel 15 be arranged on the rotation direction of the outside of horizontal coupling beam 10 and traveling wheel 15 and the length of horizontal coupling beam 10 to
Vertically, traveling wheel 15 is set in orbit, and rail inferior portion is lined with sleeper 21.
Hydraulic station 11 is additionally provided on mould bases, hydraulic station 11 is fixed in horizontal coupling beam 10, and hydraulic station 11 passes through oil pipe point
Lifting unit dismounting oil cylinder 8, main lifting cylinder 9 and transverse adjusting oil cylinder 14 are not connected with.
Before use, needing to assemble present invention landing mould bases, carry out smooth to ground before assembling and lay railway sleepers 21,
21 top trapped orbit of sleeper simultaneously ensures stabilized structure;Specifically assembling process is:Laterally connect in 15 over-assemble of traveling wheel first
Beam 10, be connected in horizontal coupling beam 10 horizontal ram beam 22, and the pedestal of transverse adjusting oil cylinder 14 is connected with horizontal coupling beam 10, horizontal stroke
It is connected to the hydraulic stem for adjusting oil cylinder 14 with horizontal ram beam 22.
Further traveling wheel 15 is positioned on track, main lifting cylinder 9, main lifting are fixed on horizontal 22 top of ram beam
Frame body 7 is fixed on oil cylinder 9, frame body 7 is formed by multiple 18 composite assemblies of lifting unit, and most lower section lifting unit 18 is connected with
Main lifting cylinder 9, each 18 middle part of lifting unit are provided with connecting hole A, inside connecting rod are provided between adjacent lifting unit 18
17, inside connecting rod 17 includes the cross bar set in a word and the bridging set in × word, cross bar and bridging in staggeredly cloth
It puts.The height modulus selectable range of specific lifting unit 18 is 0.5~2 meter, can pour highly to be changed according to box beam
It calculates, any one of preferable 0.5 meter or 1 meter or 1.5 meters after conversion, two kinds of combination can also be carried out.In fore-stock 1 with after
Girder 3 is installed respectively on stent 2, girder 3 is the combining structure of hollow rectangle beam 24, triangle-frame 25 and Filled Rectangle beam 26,
Triangle-frame 25 is arranged on the middle part of hollow rectangle beam 24 and Filled Rectangle beam 26.
The length direction of girder 3 is identical with the erection direction of box beam;Further, the installation form cross member on girder 3
4, template cross member 4 is bolted separable structure in 12 position of center line of pier stud, and band branch is connected on template cross member 4
The box beam external mold 5 of support, 4 top of template cross member are provided with counterweight 13 away from 12 center of pier stud.
The installation of lifting unit peace dismantling device is further carried out, lifting unit peace dismantling device is arranged on main 9 liang of lifting cylinder
Side, including lifting beam position-limited rack 20, lifting unit dismounting oil cylinder 8 and lifting beam 16,20 rectangular framework knot of lifting beam position-limited rack
Structure and bottom centre position dismount oil cylinder 8 with lifting unit and are fixedly connected, and the hydraulic stem of lifting unit dismounting oil cylinder 8, which is connected with, to be carried
Beam 16 is risen, lifting beam 16 can move vertically along lifting beam position-limited rack 20, and one end of lifting beam 16 towards frame body 7, which is provided with, to be added
Long block 23 lengthens and is provided with the connecting hole B that can be matched with the connecting hole A of lifting unit 18 on block 23, in connecting hole A and connection
Pin is passed in the B of hole and realizes that the connection of the two is fixed.
During installation, need first to be attached hydraulic station 11 and lifting unit dismounting oil cylinder 8, the oil cylinder of lifting unit dismounting at this time
8 is in running order, and the connecting hole B that the connecting hole A of most lower section lifting unit 18 is lengthened to block 23 with lifting beam 16 is connected, and is started
Lifting unit dismounting oil cylinder 8 makes it extend upwards, and most lower section lifting unit 18 rises together with lifting unit dismounting oil cylinder 8 at this time
More than the distance of 18 height of lifting unit, further, can continue to place lifting unit 18 on main lifting cylinder 9, repeat with
Upper step, until 7 height of frame body after the combination of lifting unit 18 reaches required setting height.7 height of frame body with
During lifting unit 18 constantly increases, inside connecting rod 17 will be installed synchronously.
After installation is complete, by operating main lifting cylinder 9, the hydraulic stem of main lifting cylinder 9 is made to extend upwards, passes through frame body
7 rise is further driven to girder 3 and moves up, until the box beam external mold 5 with support reaches the specified elevation location of design;By
After unwrapping wire determines that position is accurate, template cross member 4 can be attached fixation in 12 midline position of pier stud with bolt.
Further, the construction of box beam can be carried out, box girder construction can be in the box beam external mold 5 with support and box girder inner formwork 6
Cooperation is lower to carry out the binding of reinforcing bar and pouring for concrete.Wherein, box girder inner formwork 6 selects inflatable internal model or wooden model.
After box beam concrete pours completion and reaches design strength, the demoulding of box beam can be carried out.During the demoulding, behaviour is first passed through
It decides lifting cylinder 9, the hydraulic stem of main lifting cylinder 9 is made to bounce back downwards, until 5 bottom of box beam external mold with support and cast-in-place case
Leave 150~200mm in the bottom of beam concrete;Further, it can extend hydraulic stem by operating transverse adjusting oil cylinder 14, liquid
Compression bar elongation drives horizontal ram beam 22 to be moved horizontally to the direction away from pier stud 12, until the box beam external mold 5 with support is with pouring
Until the box beam concrete built completely disengages.
After the demoulding, by track spreading so that the whole landing mould bases of the present invention can move forward, and mobile transposition is by row
It walks wheel 15 to realize, traveling wheel 15 is both needed to realize linkage from translator and motor.When before mould bases progress, need to block with pier stud 12
10 partial demolition of horizontal coupling beam of position after mould bases is moved to appropriate location, is reconnected horizontal coupling beam 10 using bolt
It is fixed, mould bases is made to become firm whole.Lateral adjustment device is arranged on the bottom of mould bases in the present invention, it would be possible to stress be caused to become
Change the decentralization of position so that mould bases whole stability under loading during lateral adjustments, while further strengthened using counterweight
The stability of mould bases.
Claims (9)
1. a kind of whole landing mould bases of cast-in-situ box girder, it is characterised in that:It is included in adjacent pier stud(12)Center line both ends are symmetrical
The fore-stock of setting(1)And after-poppet(2), fore-stock(1)And after-poppet(2)Structure is identical and top is elongated is provided with girder
(3), fore-stock(1)And after-poppet(2)Bottom is provided with can be along girder(3)The traveling wheel of length direction movement(15), girder
(3)Between be arranged at intervals with perpendicular template cross member(4), template cross member(4)In pier stud(12)Position of center line is spiral shell
Tether the separable structure connect, template cross member(4)On be connected with support box beam external mold(5), template cross member(4)Top
Away from pier stud(12)Center is provided with counterweight(13), fore-stock(1)And after-poppet(2)Include frame body(7), frame body(7)
Top is provided with hoisting frame(19), frame body(7)Bottom is provided with main lifting cylinder(9)Pacify dismantling device, main lifting with lifting unit
Oil cylinder(9)It is fixed on horizontal ram beam(22)On, horizontal ram beam(22)Lower part is provided with horizontal coupling beam(10)And the two can
It is opposite to slide, horizontal coupling beam(10)With horizontal ram beam(22)Between be provided with transverse adjusting oil cylinder(14).
2. a kind of whole landing mould bases of cast-in-situ box girder according to claim 1, it is characterised in that:Frame body(7)By more
A lifting unit(18)Composite assembly forms, and most descends section lifting unit(18)It is connected with main lifting cylinder(9), each lifting unit
(18)Middle part is provided with connecting hole A, adjacent lifting unit(18)Between be provided with inside connecting rod(17), inside connecting rod(17)Including
The cross bar set in a word and the bridging set in × word, cross bar and bridging are in interlaced arrangement.
3. a kind of move integrally according to claim 1 lands mould bases, it is characterised in that:Lifting unit peace dismantling device is set
In main lifting cylinder(9)Both sides, including lifting beam position-limited rack(20), lifting unit dismounting oil cylinder(8)And lifting beam(16), promoted
Beam position-limited rack(20)Rectangular frame structure and bottom centre position and lifting unit dismounting oil cylinder(8)It is fixedly connected, lifting is single
Member dismounting oil cylinder(8)Hydraulic stem be connected with lifting beam(16), lifting beam(16)It can be along lifting beam position-limited rack(20)It does vertical
Movement, lifting beam(16)Towards frame body(7)One end be provided with lengthening block(23), lengthen block(23)On be provided with can be single with lifting
Member(18)The connecting hole B that match of connecting hole A.
4. a kind of whole landing mould bases of cast-in-situ box girder according to claim 1, it is characterised in that:Girder(3)It is hollow
Rectangular beam(24), triangle-frame(25)With Filled Rectangle beam(26)Combining structure, triangle-frame(25)It is arranged on hollow rectangle
Beam(24)With Filled Rectangle beam(26)Middle part.
5. a kind of whole landing mould bases of cast-in-situ box girder according to claim 2, it is characterised in that:Lifting unit(18)'s
Height modulus is one kind in 0.5~2 meter, preferably 0.5 meter or 1 meter or 1.5 meters.
6. a kind of whole landing mould bases of cast-in-situ box girder according to claim 1, it is characterised in that:Transverse adjusting oil cylinder
(14)Pedestal and horizontal coupling beam(10)Connection, transverse adjusting oil cylinder(14)Hydraulic stem and horizontal ram beam(22)Connection.
7. a kind of whole landing mould bases of cast-in-situ box girder according to claim 3, it is characterised in that:Lifting unit dismounting oil
Cylinder(8)Stroke be more than selected lifting unit(18)Height modulus.
8. a kind of whole landing mould bases of cast-in-situ box girder according to claim 1, it is characterised in that:Traveling wheel(15)It sets
In horizontal coupling beam(10)Outside and traveling wheel(15)Rotation direction and horizontal coupling beam(10)Length to vertical, traveling wheel(15)
It sets in orbit, rail inferior portion is lined with sleeper(21).
9. a kind of cast-in-situ box girder according to any one in claim 1~8 lands mould bases with whole, it is characterised in that:
Hydraulic station is additionally provided on mould bases(11), hydraulic station(11)It is fixed on horizontal coupling beam(10)On, hydraulic station(11)Pass through oil pipe point
Lifting unit dismounting oil cylinder is not connected with(8), main lifting cylinder(9)And transverse adjusting oil cylinder(14).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711389770.XA CN108103945B (en) | 2017-12-21 | 2017-12-21 | A kind of whole landing mould bases of cast-in-situ box girder |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711389770.XA CN108103945B (en) | 2017-12-21 | 2017-12-21 | A kind of whole landing mould bases of cast-in-situ box girder |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108103945A true CN108103945A (en) | 2018-06-01 |
CN108103945B CN108103945B (en) | 2019-10-22 |
Family
ID=62211572
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711389770.XA Active CN108103945B (en) | 2017-12-21 | 2017-12-21 | A kind of whole landing mould bases of cast-in-situ box girder |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108103945B (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108999085A (en) * | 2018-07-20 | 2018-12-14 | 浙江交工宏途交通建设有限公司 | Sea area construction of cast-in-situ box-beam bracket and sea area construction of cast-in-situ box-beam method |
CN109881588A (en) * | 2019-04-10 | 2019-06-14 | 北方工业大学 | Pier adjusting device and pier adjusting system |
CN112482226A (en) * | 2020-11-19 | 2021-03-12 | 中铁大桥局集团有限公司 | Overhead variable-span length construction method for upstroke movable formwork |
CN113529586A (en) * | 2021-08-25 | 2021-10-22 | 南通路桥工程有限公司 | Box girder supporting system and construction method |
CN114277693A (en) * | 2022-01-07 | 2022-04-05 | 山东高速尼罗投资发展有限公司 | Walking type large-bearing combined steel pipe support and using method |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1337498A (en) * | 2000-08-03 | 2002-02-27 | 章启光 | In-situ support system and its construction method |
JP2007044956A (en) * | 2005-08-09 | 2007-02-22 | Oriental Construction Co Ltd | Mold device for curved line beam |
CN201704630U (en) * | 2010-05-25 | 2011-01-12 | 中铁十八局集团第三工程有限公司 | Slippage die carrier of concrete cast-in-situ continuous beam |
CN102660925A (en) * | 2012-06-06 | 2012-09-12 | 长安大学 | Moveable formwork for variable-width curved bridge |
CN202658533U (en) * | 2012-06-06 | 2013-01-09 | 长安大学 | Movable formwork of curved bridge with variable width |
CN206368328U (en) * | 2016-12-08 | 2017-08-01 | 济南城建集团有限公司 | A kind of box beam four moves integrally die carrier structure across one-piece casting |
-
2017
- 2017-12-21 CN CN201711389770.XA patent/CN108103945B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1337498A (en) * | 2000-08-03 | 2002-02-27 | 章启光 | In-situ support system and its construction method |
JP2007044956A (en) * | 2005-08-09 | 2007-02-22 | Oriental Construction Co Ltd | Mold device for curved line beam |
CN201704630U (en) * | 2010-05-25 | 2011-01-12 | 中铁十八局集团第三工程有限公司 | Slippage die carrier of concrete cast-in-situ continuous beam |
CN102660925A (en) * | 2012-06-06 | 2012-09-12 | 长安大学 | Moveable formwork for variable-width curved bridge |
CN202658533U (en) * | 2012-06-06 | 2013-01-09 | 长安大学 | Movable formwork of curved bridge with variable width |
CN206368328U (en) * | 2016-12-08 | 2017-08-01 | 济南城建集团有限公司 | A kind of box beam four moves integrally die carrier structure across one-piece casting |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108999085A (en) * | 2018-07-20 | 2018-12-14 | 浙江交工宏途交通建设有限公司 | Sea area construction of cast-in-situ box-beam bracket and sea area construction of cast-in-situ box-beam method |
CN109881588A (en) * | 2019-04-10 | 2019-06-14 | 北方工业大学 | Pier adjusting device and pier adjusting system |
CN109881588B (en) * | 2019-04-10 | 2023-11-21 | 北方工业大学 | Pier adjusting device and pier adjusting system |
CN112482226A (en) * | 2020-11-19 | 2021-03-12 | 中铁大桥局集团有限公司 | Overhead variable-span length construction method for upstroke movable formwork |
CN113529586A (en) * | 2021-08-25 | 2021-10-22 | 南通路桥工程有限公司 | Box girder supporting system and construction method |
CN113529586B (en) * | 2021-08-25 | 2022-11-18 | 南通路桥工程有限公司 | Box girder supporting system and construction method |
CN114277693A (en) * | 2022-01-07 | 2022-04-05 | 山东高速尼罗投资发展有限公司 | Walking type large-bearing combined steel pipe support and using method |
Also Published As
Publication number | Publication date |
---|---|
CN108103945B (en) | 2019-10-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108103945B (en) | A kind of whole landing mould bases of cast-in-situ box girder | |
CN103074854B (en) | Rear supporting point triangular bracket hanging basket and bridge construction method using same | |
CN106089253B (en) | A kind of all-hydraulic template system poured for culvert | |
CN102094392B (en) | Lower supported hanging basket in bridge construction and application thereof | |
CN110528402B (en) | Construction method of ultra-wide box girder multi-truss-piece combined hanging basket | |
CN102660925B (en) | Moveable formwork for variable-width curved bridge | |
KR20140084107A (en) | Self-Launching Movable Scaffolding System | |
CN207608836U (en) | A kind of Successive interference cancellation cantilever pouring construction Diamond-Shape Form Traveler | |
CN205348004U (en) | Moving die carrier | |
CN105568870B (en) | For the triangle hanging basket method cantilever device and its construction method of cross-line bridge construction | |
CN113235472A (en) | Concrete placement platform truck is contained to apron | |
CN209408814U (en) | A kind of PC track beam form system | |
CN102953337B (en) | Bridge construction method | |
CN102704406A (en) | Roadbed slab non-tensile stress construction method based on combined channel girder | |
CN110593114A (en) | Box girder construction method based on large-span box girder multi-hoop truss support bailey bracket | |
CN202658533U (en) | Movable formwork of curved bridge with variable width | |
CN103526697A (en) | Self-propelled movable formwork for construction of double-rectangle water conservancy aqueduct | |
CN106150525A (en) | A kind of rock anchorage beam construction trolley and construction method thereof | |
WO2022142193A1 (en) | Construction method for large-span thin-wall concrete sound barrier pouring trolley | |
CN109505271A (en) | A kind of complete construction of mobile hydraulic trolley arch culvert | |
CN105735142A (en) | Bridge girder erection machine for prestressed concrete bridge precast section span-by-span splicing construction | |
CN206035507U (en) | Rectangle box culvert and for tunnel construction platform truck | |
CN211815595U (en) | Lower tower column tension and compression structure for cable tower | |
CN207295476U (en) | One kind moves integrally landing mould bases | |
CN205711767U (en) | Bridge Erector for Prestressed Concrete Bridges prefabricated subsection construction of splicing span by span |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP03 | Change of name, title or address |
Address after: 100160 701, 7th floor, building 3, yard 10, Automobile Museum East Road, Fengtai District, Beijing Patentee after: China Power Construction Railway Construction Investment Group Co.,Ltd. Address before: 100044 1001, 10th floor, building 2, yard 22, Chegongzhuang West Road, Haidian District, Beijing Patentee before: POWERCHINA RAILWAY CONSTRUCTION Co.,Ltd. |
|
CP03 | Change of name, title or address |