CN202658533U - Movable formwork of curved bridge with variable width - Google Patents

Movable formwork of curved bridge with variable width Download PDF

Info

Publication number
CN202658533U
CN202658533U CN2012202620931U CN201220262093U CN202658533U CN 202658533 U CN202658533 U CN 202658533U CN 2012202620931 U CN2012202620931 U CN 2012202620931U CN 201220262093 U CN201220262093 U CN 201220262093U CN 202658533 U CN202658533 U CN 202658533U
Authority
CN
China
Prior art keywords
girder
bridge
interim
hydraulic cylinder
bracket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2012202620931U
Other languages
Chinese (zh)
Inventor
吕彭民
王斌华
房义营
王恩东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changan University
Original Assignee
Changan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changan University filed Critical Changan University
Priority to CN2012202620931U priority Critical patent/CN202658533U/en
Application granted granted Critical
Publication of CN202658533U publication Critical patent/CN202658533U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a movable formwork of a curved bridge with a variable width. The movable formwork comprises bracket beams and pulling flatcars, wherein the bracket beams are fixed on a bridge pier through upright columns of brackets, a main beam is arranged at each of two sides of the top of each bracket beam, at least one temporary main beam is arranged between the two main beams, the temporary main beam and the main beams are all arranged on corresponding pulling flatcars through corresponding carriers, the pulling flatcars are arranged on the bracket beam, transversely moved hydraulic cylinders are arranged between the pulling flatcars and the bracket beams, vertically moved hydraulic cylinders are arranged between the pulling flatcars and the carriers, longitudinally moved hydraulic cylinders are arranged between the carriers and the temporary main beam and between the carriers and the main beams, cross beams are arranged at upper sides of the main beams and the temporary main beam, an external mold system is arranged at upper sides of the cross beams, and an internal mold is arranged at the inner part of the external mold system. According to the utility model, the number of temporary main beams can be adjusted conveniently based on the width of a bridge floor, so that the construction of varying the width of the bridge floor can be realized, and therefore the movable formwork has the advantages of high construction efficiency, saved labor cost, convenience for construction, high repeated utilization rate and no need of foundation treatment and the prefabrication of a beam field.

Description

The wide curved bridge mobile formwork of a kind of luffing
Technical field
The utility model belongs to technical field of bridge construction, relates to a kind of mobile formwork, is specifically related to the wide curved bridge mobile formwork of a kind of luffing for the wide curve bridge construction of luffing.
Background technology
Mobile formwork is a kind of template that carries, and utilizes cushion cap or pier stud as supporting, bridge is carried out the construction equipment of cast in situs.Construction equipment as a kind of advanced person, owing to have good, the easy and simple to handle and efficient advantages of higher of construction quality, mobile formwork has been widely used in the Construction of continuous beam of speedway, road bridge and railway bridge, but mobile formwork is owing to be subjected to the restriction of structure, and generally its construction object is the uniform section bridge.
At present, along with expanding economy, bridge is widely used in track traffic and the urban construction, because its application purpose is different with the building physical condition, bridge type is diversified development trend, such as the appearance of ring road in the urban viaduct, so that the object of constructing becomes the curvilinear structures bridge by general uniform section linear structure bridge, even be the wide structural bridge of luffing, this just has higher requirement to the use of mobile formwork system.The General Mobile mould bases that routine is applied to the laying of uniform section bridge can not satisfy the construction that the wide bridge concrete of luffing is built.Therefore need a kind of novel bridge construction equipment for this type of bridge, both possessed the advantage of General Mobile mould bases, can satisfy again the construction requirement of the wide curve bridge of luffing.
The utility model content
The purpose of this utility model is to overcome above-mentioned deficiency of the prior art, provide a kind of luffing wide curved bridge mobile formwork, this mobile formwork can be according to the number of the interim girder of bridge deck width adjustment, adopt this mobile formwork not only can realize becoming the construction of bridge deck width, also can satisfy the topology requirement of span and pier stud number of variations; Efficiency of construction is high, and the labor savings cost need not ground and processes, and need not the precast beam field, easy construction and protection of the environment, and recycling rate of waterused is high.
For achieving the above object, the technical solution adopted in the utility model is: the wide curved bridge mobile formwork of a kind of luffing, comprise bracket beam and advance flatcar, it is characterized in that: described bracket beam is fixed on the bridge pier by the bracket column, both sides, described bracket beam top respectively are provided with a girder, be provided with at least one interim girder between the two described girders, described interim girder and girder all are arranged on the corresponding propelling flatcar by corresponding carriage, described propelling flatcar is arranged on the bracket beam, be provided with the transverse shifting hydraulic cylinder between described propelling flatcar and the bracket beam, be provided with vertical mobile hydraulic cylinder between described propelling flatcar and the carriage, between described carriage and the interim girder and be provided with between carriage and the girder and vertically move hydraulic cylinder, described transverse shifting hydraulic cylinder, vertical mobile hydraulic cylinder be connected hydraulic cylinder and all be connected with hydraulic power unit by oil pipe, the upside of described girder and interim girder is provided with crossbeam, described crossbeam upside is furnished be used to the outer modular system of constructing pontic, described external mold internal system is provided with the internal mold for moulding pontic internal cavities, is provided with the internal mold that prevents the internal mold distortion in the described internal mold and supports.
The wide curved bridge mobile formwork of above-mentioned a kind of luffing is characterized in that: described outer modular system is mutually assembled by bed die, side form and wing mould, is provided with the mechanical spiral adjusting rod between described side form and the girder and between wing mould and the girder.
The wide curved bridge mobile formwork of above-mentioned a kind of luffing, it is characterized in that: described interim girder agent structure adopts trussed construction assembled, it is box-structure that described interim girder is positioned at the bracket support position, and described trussed construction is connected with described box structure by bearing pin.
The wide curved bridge mobile formwork of above-mentioned a kind of luffing is characterized in that: all be bolted between described crossbeam and interim girder and crossbeam and the girder.
The wide curved bridge mobile formwork of above-mentioned a kind of luffing is characterized in that: described girder front end is provided with front launching nose, and described main beam rear end is provided with back launching nose.
The utility model compared with prior art has the following advantages:
(1) the wide curved bridge mobile formwork of this luffing can be according to the number of the interim girder of bridge deck width adjustment, not only can realize becoming the construction of bridge deck width, also can satisfy the topology requirement of span and pier stud number of variations, during to the wide curved bridge construction of luffing, need not the integral replacing mobile formwork, improve efficiency of construction, reduced engineering cost.
(2) all be furnished with the propelling flatcar between every interim girder of the wide curved bridge mobile formwork of this luffing and bracket beam and girder and the bracket beam, can realize vertical, the transverse shifting of every girder or interim girder and vertically move the requirement of striding.
Need not ground when (3) the wide curved bridge mobile formwork of this luffing uses and process, need not the precast beam field, the integral bridge performance of cast is good, easy construction and protection of the environment, and recycling rate of waterused is high.
Below by drawings and Examples, the utility model is described in further detail.
Description of drawings
Fig. 1 is the matched moulds state overall structure schematic diagram of the utility model cast bridge Standard Beam section.
Fig. 2 is the die opening state overall structure schematic diagram of the utility model cast bridge Standard Beam section.
Fig. 3 is the A-A sectional view of Fig. 2.
Fig. 4 is the B-B sectional view of Fig. 2.
Fig. 5 is the matched moulds state overall structure schematic diagram of the utility model cast bridge widening beam section.
Fig. 6 is the die opening state overall structure schematic diagram of the utility model cast bridge widening beam section.
Fig. 7 is the I partial enlarged drawing of Fig. 1.
Fig. 8 is the II partial enlarged drawing of Fig. 3.
Fig. 9 is the C-C sectional view of Fig. 7.
Description of reference numerals:
Figure BDA0000172968531
The specific embodiment
Such as Fig. 1 to the wide curved bridge mobile formwork of a kind of luffing shown in Figure 9, comprise bracket beam 11 and advance flatcar 10, described bracket beam 11 is fixed on the bridge pier 19 by bracket column 20, both sides, described bracket beam 11 top respectively are provided with a girder 9, be provided with the interim girder 1 of right quantity between the two described girders 9, the number of described interim girder 1 can be according to the bridge deck width adjustment; Described interim girder 1 and girder 9 all are arranged on the corresponding propelling flatcar 10 by corresponding carriage 18, described propelling flatcar 10 is arranged on the bracket beam 11, be provided with transverse shifting hydraulic cylinder 13 between described propelling flatcar 10 and the bracket beam 11, described transverse shifting hydraulic cylinder 13 1 ends are hinged with propelling flatcar 10, and described transverse shifting hydraulic cylinder 13 other ends and bracket beam 11 are hinged; Be provided with vertical mobile hydraulic cylinder 12 between described propelling flatcar 10 and the carriage 18, described vertical mobile hydraulic cylinder 12 lower ends are installed in the bottom that advances flatcar 10, and described vertical mobile hydraulic cylinder 12 upper ends link to each other with carriage 18 bottoms; Between described carriage 18 and the interim girder 1 and be provided with between carriage 18 and the girder 9 and vertically move hydraulic cylinder 15, described hydraulic cylinder 15 1 ends that vertically move are articulated on interim girder 1 or the girder 9, and described hydraulic cylinder 15 other ends that vertically move are articulated on the carriage 18.Described vertical mobile hydraulic cylinder 12, transverse shifting hydraulic cylinder 13 and be connected hydraulic cylinder 15 and all be connected with the hydraulic power unit 14 that is arranged on bracket beam 11 upsides by oil pipe, the upside of described girder 9 and interim girder 1 is provided with crossbeam 2, all be bolted between described crossbeam 2 and interim girder 1 and crossbeam 2 and the girder 9, bolt connects easy accessibility, easy access, and can increase pretightning force and prevent from becoming flexible; Described crossbeam 2 upsides are furnished be used to the outer modular system of constructing pontic, and described external mold internal system is provided with the internal mold 3 for moulding pontic internal cavities, are provided with the internal mold that prevents the internal mold distortion in the described internal mold 3 and support 4.
Such as Fig. 1, Fig. 2, Fig. 5 and shown in Figure 6, described outer modular system is spliced mutually by bed die 5, side form 6 and wing mould 7, and this splicing construction is convenient to be adjusted according to the external modular system of bridge deck width.Be provided with mechanical spiral adjusting rod 8 between described side form 6 and the girder 9 and between wing mould 7 and the girder 9, mechanical spiral adjusting rod 8 can be advantageously used in the supporting and location of side form 6 and wing mould 7.
As shown in Figure 4, described interim girder 1 agent structure adopts trussed construction assembled, and it is simple in structure, lightweight and assemble fast advantage that trussed construction has; Described interim girder 1 is positioned at place, carriage 18 Support Positions and is box-structure, and box-structure can improve the structural strength at place, Support Position, increases and supports contact area and connective stability; Described trussed construction is connected with described box-structure by bearing pin, and the bearing pin connection is convenient to the dismounting of interim girder 1 and is transported; As shown in Figure 3, described girder 9 one ends are provided with front launching nose 17, and described girder 9 other ends are provided with back launching nose 16.
With the example that is cast for of the bridge Standard Beam section that is connected and bridge widening beam section, the course of work of the wide curved bridge mobile formwork of the utility model luffing is as follows:
At first pour into a mould bridge Standard Beam section, to be installed on the good bridge pier 19 of cast such as Fig. 1, Fig. 3 and the wide curved bridge mobile formwork of this luffing shown in Figure 4, two interim girders 1 are set, girder 9 and interim girder 1 common supporting traverse 2 and outer modular system between two girders 9.Start hydraulic power unit 14, transverse shifting hydraulic cylinder 13 drives and advances flatcar 10 transverse shiftings, advances flatcar 10 to drive carriage 18, interim girder 1 and girder 9 transverse shiftings, thereby the bed die 5 of crossbeam 2 and outer modular system is closed up.Crossbeam 2 after will closing up and close up after bed die 5 usefulness bolts be linked as integral body, thereby realize the matched moulds of outer modular system.Adjust vertical mobile hydraulic cylinder 12, raise carriage 18, interim girder 1, girder 9, crossbeam 2 and outer modular system, carriage 18, interim girder 1, girder 9, crossbeam 2 and outer modular system are raised to the bridge casting position after, assembly unit internal mold 3 and internal mold support 4.Internal mold 3 and internal mold support 4 assembly units finish after, at internal mold 3 and finish between the outer modular system of matched moulds and build an amount of concrete, thereby finish building of bridge standard bridge section.
In conjunction with Fig. 2, through concrete curing and after reaching the stretch-draw requirement of strength, remove internal mold support 4 and internal mold 3, adjust vertical mobile hydraulic cylinder 12, thereby carriage 18, interim girder 1 and girder 9 are moved down, and carriage 18, interim girder 1 drives crossbeam 2 when moving down with girder 9 and outer modular system separates with in type pontic.After removing part crossbeam 2 and bed die 5, adjust transverse shifting hydraulic cylinder 13 and make propelling flatcar 10 transverse shiftings, advance flatcar 10 to drive carriages 18, interim girder 1 and girder 9 transverse shifting certain distances, thereby avoid interim girder 1 and girder 9 when vertical shift and bridge pier bumps.Fig. 2 be the utility model build bridge Standard Beam section finish and die sinking after the structural entity schematic diagram.
In conjunction with Fig. 2 and Fig. 5, after the moulding of bridge Standard Beam section, can descend the cast of two bridge beam widening beam sections.At first be arranged between interim girder 1 and the carriage 18 and between girder 9 and the carriage 18 vertically move hydraulic cylinder 15 drive interim girder 1, girder 9 and split after outer modular system vertically move, finish mobile formwork two and stride vertical shift.According to the Specific construction situation, for every girder 9 or interim girder 1, also can adjust simultaneously the transverse shifting hydraulic cylinder 13 of 10 in each bridge pier 19 place's bracket beam 11 and propelling flatcar, realize that carriage 18 is around vertical mobile hydraulic cylinder 12 deflections, carriage 18 drives girder 9 or interim girder 1 deflection of supporting, and makes things convenient for the luffing via hole.Because Bridge Beam section to be cast is widened, its bridge pier 19 central post quantity increase, corresponding bracket beam 11 needs to increase corresponding length, crossbeam 2 and bed die 5 also need increase respective width, do not changing in the integrally-built situation of mobile formwork, below bracket beam 11, increasing bracket column 20 according to the pier column quantity that increases and support so that the bracket beam 11 that lengthens is formed reliably; Two interim girders 1 of other increase between two girders 9 make the number of interim girder 1 increase to four with crossbeam 2 and reliably support of bed die 5 formation to widening, thus the construction quality of the moulding of the wide bridge of realization luffing and assurance different in width Bridge Beam section.Above-mentioned basis bridge width to be built is adjusted flexibly the job practices of interim girder 1 and bracket column 20 quantity and has been avoided integral replacing mobile formwork when building the wide bridge of luffing, has greatly improved efficiency of construction, has reduced cost.Adjust transverse shifting hydraulic cylinder 13, it is driven advance flatcar 10 transverse shiftings, advance flatcar 10 to drive carriage 18, interim girder 1 and girder 9 and move, realize the matched moulds of outer modular system.Adjust vertical mobile hydraulic cylinder 12, raise carriage 18, interim girder 1, girder 9, crossbeam 2 and outer modular system, carriage 18, interim girder 1, crossbeam 2, girder 9 and outer modular system are raised to the bridge casting position after, assembly unit internal mold 3 and internal mold support 4.Internal mold 3 and internal mold support 4 assembly units finish after, at internal mold 3 and finish between the outer modular system of matched moulds and build an amount of concrete, obtain the matched moulds state overall structure schematic diagram of the utility model cast bridge widening beam section as shown in Figure 5.
In conjunction with Fig. 6, through concrete curing and after reaching the stretch-draw requirement of strength, remove internal mold support 4 and internal mold 3, adjust vertical mobile hydraulic cylinder 12, thereby carriage 18, interim girder 1 and girder 9 are moved down, and carriage 18, interim girder 1 drives crossbeam 2 when moving down with girder 9 and outer modular system separates with in type pontic.After removing part crossbeam 2 and bed die 5, adjust transverse shifting hydraulic cylinder 13 and make propelling flatcar 10 transverse shiftings, advance flatcar 10 to drive carriage 18, interim girder 1 and girder 9 transverse shifting certain distances, thereby avoid interim girder 1 and girder 9 when vertical shift and bridge pier bumps, Fig. 6 be that the utility model builds that bridge widening beam section is finished and die sinking after the structural entity schematic diagram.
The above; it only is preferred embodiment of the present utility model; be not that the utility model is imposed any restrictions; every according to the utility model technical spirit to any simple modification, change and equivalent structure transformation that above embodiment does, all still belong in the protection domain of technical solutions of the utility model.

Claims (5)

1. wide curved bridge mobile formwork of luffing, comprise bracket beam (11) and advance flatcar (10), it is characterized in that: described bracket beam (11) is fixed on the bridge pier (19) by bracket column (20), described bracket beam (11) both sides, top respectively are provided with a girder (9), be provided with at least one interim girder (1) between the two described girders (9), described interim girder (1) and girder (9) all are arranged on the corresponding propelling flatcar (10) by corresponding carriage (18), described propelling flatcar (10) is arranged on the bracket beam (11), be provided with transverse shifting hydraulic cylinder (13) between described propelling flatcar (10) and the bracket beam (11), be provided with vertical mobile hydraulic cylinder (12) between described propelling flatcar (10) and the carriage (18), between described carriage (18) and the interim girder (1) and be provided with between carriage (18) and the girder (9) and vertically move hydraulic cylinder (15), described transverse shifting hydraulic cylinder (13), vertical mobile hydraulic cylinder (12) with vertically move hydraulic cylinder (15) and all link to each other with the hydraulic power unit (14) that is arranged on bracket beam (11) upside by oil pipe, the upside of described girder (9) and interim girder (1) is provided with crossbeam (2), described crossbeam (2) upside is furnished be used to the outer modular system of constructing pontic, described external mold internal system is provided with the internal mold (3) for moulding pontic internal cavities, is provided with the internal mold that prevents the internal mold distortion in the described internal mold (3) and supports (4).
2. the wide curved bridge mobile formwork of a kind of luffing according to claim 1, it is characterized in that: described outer modular system is mutually assembled by bed die (5), side form (6) and wing mould (7), is provided with mechanical spiral adjusting rod (8) between described side form (6) and the girder (9) and between wing mould (7) and the girder (9).
3. the wide curved bridge mobile formwork of a kind of luffing according to claim 1, it is characterized in that: described interim girder (1) agent structure adopts trussed construction assembled, described interim girder (1) is positioned at place, carriage (18) Support Position and is box-structure, and described trussed construction is connected with described box-structure by bearing pin.
4. the wide curved bridge mobile formwork of a kind of luffing according to claim 1 is characterized in that: all be bolted between described crossbeam (2) and interim girder (1) and crossbeam (2) and the girder (9).
5. the wide curved bridge mobile formwork of a kind of luffing according to claim 1, it is characterized in that: described girder (9) one ends are provided with front launching nose (17), and described girder (9) other end is provided with back launching nose (16).
CN2012202620931U 2012-06-06 2012-06-06 Movable formwork of curved bridge with variable width Expired - Fee Related CN202658533U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012202620931U CN202658533U (en) 2012-06-06 2012-06-06 Movable formwork of curved bridge with variable width

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012202620931U CN202658533U (en) 2012-06-06 2012-06-06 Movable formwork of curved bridge with variable width

Publications (1)

Publication Number Publication Date
CN202658533U true CN202658533U (en) 2013-01-09

Family

ID=47453450

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012202620931U Expired - Fee Related CN202658533U (en) 2012-06-06 2012-06-06 Movable formwork of curved bridge with variable width

Country Status (1)

Country Link
CN (1) CN202658533U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102660925A (en) * 2012-06-06 2012-09-12 长安大学 Moveable formwork for variable-width curved bridge
CN104179125A (en) * 2014-08-29 2014-12-03 长安大学 Balance beam device for supporting movable formwork main beam
CN105064220A (en) * 2015-09-14 2015-11-18 山东恒堃机械有限公司 Anti-skid device for moving formwork
CN106012842A (en) * 2016-05-20 2016-10-12 中建三局基础设施工程有限公司 Standardized movable formwork
CN108103945A (en) * 2017-12-21 2018-06-01 中国电建集团铁路建设有限公司 A kind of whole landing mould bases of cast-in-situ box girder
CN110053152A (en) * 2018-12-27 2019-07-26 中铁十一局集团汉江重工有限公司 A kind of adjustable end bed die of prefabricated PC track girder
CN110804958A (en) * 2019-11-26 2020-02-18 中铁第五勘察设计院集团有限公司 Whole hole beam frame changing method

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102660925A (en) * 2012-06-06 2012-09-12 长安大学 Moveable formwork for variable-width curved bridge
CN102660925B (en) * 2012-06-06 2014-01-15 长安大学 Moveable formwork for variable-width curved bridge
CN104179125A (en) * 2014-08-29 2014-12-03 长安大学 Balance beam device for supporting movable formwork main beam
CN104179125B (en) * 2014-08-29 2015-12-09 长安大学 A kind of mobile formwork girder supports uses equalizer bar device
CN105064220A (en) * 2015-09-14 2015-11-18 山东恒堃机械有限公司 Anti-skid device for moving formwork
CN105064220B (en) * 2015-09-14 2016-09-07 山东恒堃机械有限公司 Mobile formwork shoe
CN106012842A (en) * 2016-05-20 2016-10-12 中建三局基础设施工程有限公司 Standardized movable formwork
CN108103945A (en) * 2017-12-21 2018-06-01 中国电建集团铁路建设有限公司 A kind of whole landing mould bases of cast-in-situ box girder
CN108103945B (en) * 2017-12-21 2019-10-22 中国电建集团铁路建设有限公司 A kind of whole landing mould bases of cast-in-situ box girder
CN110053152A (en) * 2018-12-27 2019-07-26 中铁十一局集团汉江重工有限公司 A kind of adjustable end bed die of prefabricated PC track girder
CN110053152B (en) * 2018-12-27 2024-06-25 中铁十一局集团汉江重工有限公司 Adjustable end bottom die of prefabricated PC track beam
CN110804958A (en) * 2019-11-26 2020-02-18 中铁第五勘察设计院集团有限公司 Whole hole beam frame changing method
CN110804958B (en) * 2019-11-26 2021-06-25 中铁第五勘察设计院集团有限公司 Whole hole beam frame changing method

Similar Documents

Publication Publication Date Title
CN202658533U (en) Movable formwork of curved bridge with variable width
CN102660925B (en) Moveable formwork for variable-width curved bridge
CN108442255B (en) Movable formwork bridge fabrication machine and construction method for cast-in-situ bridge fabrication
CN105155423A (en) Upward moving type movable formwork for continuous box girder construction
CN206092022U (en) Be used for lining cutting rectangular -section or radiation gradual change rectangular -section formula operation car of crawling
CN108374677B (en) Combined mechanical trolley device for coagulation construction of tunnel side ditch and bridge guardrail
CN103498421B (en) A kind of mobile formwork of constructing for U-shaped water conservancy aqueduct
CN108103945B (en) A kind of whole landing mould bases of cast-in-situ box girder
CN207315404U (en) Municipal tunnel big cross section culvert and piping lane trolley
CN201244857Y (en) Prestress concrete box girder hydraulic internal mold vehicle and hydraulic internal mold system
CN216640216U (en) Sliding die mechanism for cast-in-place simply supported beam construction
CN102198693A (en) Sectional box beam hydraulic internal mold
CN109505271B (en) Mobile hydraulic trolley arch culvert complete construction method
CN102191751B (en) Hydraulic internal mold for asymmetric box girder
CN109371851B (en) Groove making machine with multiple bottom die head cover supporting frames
CN208430437U (en) Movable formwork bridge fabrication machine
CN102001127A (en) Combined box girder hydraulic internal mould
CN217072831U (en) Self-positioning and walking template moving trolley for prefabricating hollow pier stud
CN217327341U (en) Self-propelled long-span variable cross-section hydraulic formwork trolley
CN201998308U (en) Hydraulic internal mold of single-line box girder
CN203514205U (en) Mobile framework for construction of U-shaped water conservancy flume
CN210031563U (en) Quick construction equipment of mobilizable modularization box culvert
CN210317334U (en) A template platform truck for tunnel thin wall mid-board concrete placement
CN201952740U (en) Hydraulic inner die of asymmetric box girder
CN201816126U (en) Hydraulic internal model for combined box beam

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130109

Termination date: 20150606

EXPY Termination of patent right or utility model