CN102080555A - 适于煤炭综采大采高工作面过渡支架的双级侧护装置 - Google Patents

适于煤炭综采大采高工作面过渡支架的双级侧护装置 Download PDF

Info

Publication number
CN102080555A
CN102080555A CN 201110028057 CN201110028057A CN102080555A CN 102080555 A CN102080555 A CN 102080555A CN 201110028057 CN201110028057 CN 201110028057 CN 201110028057 A CN201110028057 A CN 201110028057A CN 102080555 A CN102080555 A CN 102080555A
Authority
CN
China
Prior art keywords
side plate
back timber
shield
top beam
movable side
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201110028057
Other languages
English (en)
Inventor
郭昊峰
刘付营
龚宇
史朝军
边彦胜
张跃东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Coal Mining Machinery Group Co Ltd
Original Assignee
Zhengzhou Coal Mining Machinery Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou Coal Mining Machinery Group Co Ltd filed Critical Zhengzhou Coal Mining Machinery Group Co Ltd
Priority to CN 201110028057 priority Critical patent/CN102080555A/zh
Publication of CN102080555A publication Critical patent/CN102080555A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明公开了一种适于煤炭综采大采高工作面过渡支架的双级侧护装置,包括焊接于液压支架顶梁、掩护梁同一侧的箱型结构的顶梁大侧板、掩护梁大侧板,和铰接于所述液压支架顶梁、掩护梁另一侧的顶梁活动侧板、掩护梁活动侧板,在所述顶梁活动侧板、掩护梁活动侧板上分别设置有用于与液压支架顶梁、掩护梁相铰接的侧推千斤顶;在所述箱型结构的顶梁大侧板下边沿通过连接耳水平铰接有整体结构的下侧板,在所述下侧板上设置有与顶梁大侧板相铰接的支撑千斤顶。本发明优点在于实现工作面中间支架和端头支架支护高度落差较大区域的安全防护,达到有效回收大采高工作面两侧巷顶三角煤、提高煤炭回收率之目的。

Description

适于煤炭综采大采高工作面过渡支架的双级侧护装置
技术领域
 本发明涉及煤矿综采工作面大采高的支护装置,尤其是涉及适于煤炭综采大采高工作面过渡支架的双级侧护装置。
背景技术
煤矿已使用的综采设备一次开采高度在七米左右非常之多,并随着综采技术的发展开采高度不断提高。工作面巷道高度受到掘进、支护设备的限制,高度一般在四米左右,再高将急剧增加劳动强度并存在一定的安全隐患。因此,巷道和工作面就有一个比较大的高度差。现有的过渡方式是通过几架甚至十几架液压支架逐渐降低高度实现缓慢过渡,这就使得在工作面两端顶部留有三角形顶煤区,造成了一定的资源浪费,并随着开采高度的提高浪费越来越严重。
发明内容
本发明目的在于提供一种适于煤炭综采大采高工作面过渡支架的双级侧护装置,以解决过渡支架与端头支架大高差防护问题。
为实现上述目的,本发明可采取下述技术方案:
本发明所述适于煤炭综采大采高工作面过渡支架的双级侧护装置,包括焊接于液压支架顶梁、掩护梁同一侧的箱型结构的顶梁大侧板、掩护梁大侧板,和铰接于所述液压支架顶梁、掩护梁另一侧的顶梁活动侧板、掩护梁活动侧板,在所述顶梁活动侧板、掩护梁活动侧板上分别设置有用于与液压支架顶梁、掩护梁相铰接的侧推千斤顶;在所述箱型结构的顶梁大侧板下边沿通过连接耳水平铰接有整体结构的下侧板,在所述下侧板上设置有与顶梁大侧板相铰接的支撑千斤顶。
本发明优点在于实现工作面中间支架和端头支架支护高度落差较大区域的安全防护,达到有效回收大采高工作面两侧巷顶三角煤、提高煤炭回收率之目的。在工作面布置液压支架时,将所述箱型结构的顶梁大侧板与端头支架侧护板搭接,根据采高不同可单独使用顶梁大侧板或与整体结构的下侧板组合使用,以利于大采高工作面刚出切眼采高较低时避让运输机和采煤机,然后将所述箱型结构的顶梁活动侧板与中间支架搭接即可。
附图说明
图1是本发明的结构示意图。
图2是图1的左视结构示意图。
具体实施方式
如图1、2所示,本发明所述适于煤炭综采大采高工作面过渡支架的双级侧护装置,包括焊接于液压支架顶梁、掩护梁同一侧的箱型结构的顶梁大侧板1、掩护梁大侧板2,和铰接于所述液压支架顶梁、掩护梁另一侧的顶梁活动侧板3、掩护梁活动侧板4,在所述顶梁活动侧板3、掩护梁活动侧板4上分别设置有用于与液压支架顶梁、掩护梁相铰接的侧推千斤顶;在所述箱型结构的顶梁大侧板1下边沿通过连接耳水平铰接有整体结构的下侧板5,在所述下侧板5上设置有与顶梁大侧板1相铰接的支撑千斤顶6。

Claims (1)

1.一种适于煤炭综采大采高工作面过渡支架的双级侧护装置,其特征在于:包括焊接于液压支架顶梁、掩护梁同一侧的箱型结构的顶梁大侧板(1)、掩护梁大侧板(2),和铰接于所述液压支架顶梁、掩护梁另一侧的顶梁活动侧板(3)、掩护梁活动侧板(4),在所述顶梁活动侧板(3)、掩护梁活动侧板(4)上分别设置有用于与液压支架顶梁、掩护梁相铰接的侧推千斤顶;在所述箱型结构的顶梁大侧板(1)下边沿通过连接耳水平铰接有整体结构的下侧板(5),在所述下侧板(5)上设置有与顶梁大侧板(1)相铰接的支撑千斤顶(6)。
CN 201110028057 2011-01-26 2011-01-26 适于煤炭综采大采高工作面过渡支架的双级侧护装置 Pending CN102080555A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110028057 CN102080555A (zh) 2011-01-26 2011-01-26 适于煤炭综采大采高工作面过渡支架的双级侧护装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110028057 CN102080555A (zh) 2011-01-26 2011-01-26 适于煤炭综采大采高工作面过渡支架的双级侧护装置

Publications (1)

Publication Number Publication Date
CN102080555A true CN102080555A (zh) 2011-06-01

Family

ID=44086720

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110028057 Pending CN102080555A (zh) 2011-01-26 2011-01-26 适于煤炭综采大采高工作面过渡支架的双级侧护装置

Country Status (1)

Country Link
CN (1) CN102080555A (zh)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3726562A (en) * 1971-04-07 1973-04-10 G Wharton Mining machine including means for utilizing vacuum at working face and methods of operation thereof
CN1763351A (zh) * 2003-12-12 2006-04-26 肖自立 “四控”式全面采煤方法
CN1865657A (zh) * 2005-05-19 2006-11-22 兖矿集团有限公司 长壁采煤法综采工艺
CN101372891A (zh) * 2008-06-10 2009-02-25 沈阳市华祥矿山机械厂 条带充填整体回采采煤方法
CN101906982A (zh) * 2010-09-02 2010-12-08 郑州煤矿机械集团股份有限公司 大采高工作面两级侧护过渡支架
CN101915107A (zh) * 2010-09-02 2010-12-15 郑州煤矿机械集团股份有限公司 煤矿大采高工作面设备布置方法
CN201943730U (zh) * 2011-01-26 2011-08-24 郑州煤矿机械集团股份有限公司 适于煤炭综采大采高工作面过渡支架的双级侧护装置

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3726562A (en) * 1971-04-07 1973-04-10 G Wharton Mining machine including means for utilizing vacuum at working face and methods of operation thereof
CN1763351A (zh) * 2003-12-12 2006-04-26 肖自立 “四控”式全面采煤方法
CN1865657A (zh) * 2005-05-19 2006-11-22 兖矿集团有限公司 长壁采煤法综采工艺
AU2005203458A1 (en) * 2005-05-19 2006-12-07 Yankuang Group Corporation Limited Fully mechanized mining technique of longwall mining method
CN101372891A (zh) * 2008-06-10 2009-02-25 沈阳市华祥矿山机械厂 条带充填整体回采采煤方法
CN101906982A (zh) * 2010-09-02 2010-12-08 郑州煤矿机械集团股份有限公司 大采高工作面两级侧护过渡支架
CN101915107A (zh) * 2010-09-02 2010-12-15 郑州煤矿机械集团股份有限公司 煤矿大采高工作面设备布置方法
CN201943730U (zh) * 2011-01-26 2011-08-24 郑州煤矿机械集团股份有限公司 适于煤炭综采大采高工作面过渡支架的双级侧护装置

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
20100228 王继明 世界首个7m大采高综采面投产 第15页 , 第2期 2 *
20100330 李根威等 大采高整层综采面开采技术研究 第5-7页 , 第1期 2 *
20100830 张书敬 厚煤层中小煤矿改造技术途径 第12-14页 第15卷, 第4期 2 *

Similar Documents

Publication Publication Date Title
CN101906982B (zh) 大采高工作面两级侧护过渡支架
CN203066995U (zh) 急倾斜煤层工作面两巷超前支护液压支架侧护装置
CN102410017B (zh) 支护式综合掘锚机
CN202946177U (zh) 一种改进的煤矿用液压支架
CN201083130Y (zh) 煤矿用掘进机机载超前支护装置
CN203879530U (zh) 一种履带式巷道超前支护液压支架
CN102080557A (zh) 适于煤炭综采大采高工作面过渡支架的分体侧护装置
CN203362199U (zh) 综采工作面端头液压支架
CN201747391U (zh) 大采高工作面两级侧护过渡支架
CN203547736U (zh) 新型连续采煤机
CN110925005B (zh) 一种挡矸液压支架
CN201943730U (zh) 适于煤炭综采大采高工作面过渡支架的双级侧护装置
CN102080556A (zh) 用于煤炭综采大采高工作面的过渡支架
CN202596763U (zh) 一种用于急倾斜采煤工作面过断层的综采液压支架
CN201943729U (zh) 适于煤炭综采大采高工作面过渡支架的单级侧护装置
CN201908671U (zh) 适于煤炭综采大采高工作面过渡支架的分体侧护装置
CN104100287A (zh) 一种新型自移式采煤巷道超前支护支架
CN103485775A (zh) 新型连续采煤机
CN102108875A (zh) 适于煤炭综采大采高工作面过渡支架的单级侧护装置
CN103670475A (zh) 液压支架用柔性护帮辅助防护装置
CN202659267U (zh) 整体分级跨越式步移支架
CN103195458A (zh) 煤矿井下大通道端头悬移液压支架
CN102080555A (zh) 适于煤炭综采大采高工作面过渡支架的双级侧护装置
CN201915981U (zh) 用于煤炭综采大采高工作面的过渡支架
CN203130131U (zh) 煤矿井下大通道端头悬移液压支架

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20110601