CN101956372B - 一种预应力混凝土梁式桥0号段快速施工方法 - Google Patents
一种预应力混凝土梁式桥0号段快速施工方法 Download PDFInfo
- Publication number
- CN101956372B CN101956372B CN2010102983235A CN201010298323A CN101956372B CN 101956372 B CN101956372 B CN 101956372B CN 2010102983235 A CN2010102983235 A CN 2010102983235A CN 201010298323 A CN201010298323 A CN 201010298323A CN 101956372 B CN101956372 B CN 101956372B
- Authority
- CN
- China
- Prior art keywords
- reinforcement
- cage
- bridge
- section
- prestressed concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000011513 prestressed concrete Substances 0.000 title claims abstract description 13
- 238000010276 construction Methods 0.000 title abstract description 14
- 238000000034 method Methods 0.000 claims abstract description 26
- 238000004519 manufacturing process Methods 0.000 claims abstract description 7
- 230000002787 reinforcement Effects 0.000 claims description 44
- 238000000465 moulding Methods 0.000 claims description 9
- 239000000725 suspension Substances 0.000 claims description 8
- 238000012423 maintenance Methods 0.000 claims description 4
- 238000011900 installation process Methods 0.000 claims description 2
- 239000004567 concrete Substances 0.000 abstract description 6
- 229910000831 Steel Inorganic materials 0.000 abstract description 5
- 239000010959 steel Substances 0.000 abstract description 5
- 238000010586 diagram Methods 0.000 description 5
- 230000032258 transport Effects 0.000 description 4
- 230000003014 reinforcing effect Effects 0.000 description 3
- 238000013461 design Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 238000012545 processing Methods 0.000 description 2
- 230000011218 segmentation Effects 0.000 description 2
- 238000010923 batch production Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009472 formulation Methods 0.000 description 1
- 238000003754 machining Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 238000003908 quality control method Methods 0.000 description 1
- 238000012882 sequential analysis Methods 0.000 description 1
- 238000003860 storage Methods 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Abstract
Description
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010102983235A CN101956372B (zh) | 2010-09-30 | 2010-09-30 | 一种预应力混凝土梁式桥0号段快速施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010102983235A CN101956372B (zh) | 2010-09-30 | 2010-09-30 | 一种预应力混凝土梁式桥0号段快速施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101956372A CN101956372A (zh) | 2011-01-26 |
CN101956372B true CN101956372B (zh) | 2011-12-07 |
Family
ID=43483944
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010102983235A Expired - Fee Related CN101956372B (zh) | 2010-09-30 | 2010-09-30 | 一种预应力混凝土梁式桥0号段快速施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101956372B (zh) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102505636B (zh) * | 2011-10-28 | 2014-09-10 | 中铁十六局集团有限公司 | 一种双薄壁墩连续刚构桥0号块施工方法 |
CN103184721B (zh) * | 2013-01-25 | 2015-02-18 | 中铁大桥局集团第一工程有限公司 | 预制节段拼装pc连续箱梁逐块悬挂、胶拼线形控制方法 |
CN108699851B (zh) * | 2018-03-30 | 2021-02-09 | 广东博智林机器人有限公司 | 钢筋预制加工系统 |
CN111139743A (zh) * | 2019-12-26 | 2020-05-12 | 中铁十七局集团第三工程有限公司 | 提高公路梁架梁速度的方法及龙门吊的安装方法 |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2247609C2 (de) * | 1972-09-28 | 1974-05-30 | Dyckerhoff & Widmann Ag, 8000 Muenchen | Verfahren zum Herstellen eines Brückenbauwerks aus Spannbeton im abschnittsweisen freien Vorbau |
CN101028726A (zh) * | 2006-09-21 | 2007-09-05 | 中铁大桥局股份有限公司 | 短线法预制pc箱梁工艺 |
CN101324055A (zh) * | 2008-08-06 | 2008-12-17 | 中铁大桥局股份有限公司 | 一种箱梁整体钢筋骨架的吊装设备及吊装方法 |
CN101824800B (zh) * | 2010-04-28 | 2011-06-22 | 中铁三局集团有限公司 | 一种桥位现浇预应力混凝土连续梁的施工方法 |
-
2010
- 2010-09-30 CN CN2010102983235A patent/CN101956372B/zh not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
CN101956372A (zh) | 2011-01-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108019076B (zh) | 大直径钢筋混凝土筒仓施工方法及用于锥壳施工的装置 | |
CN109968521A (zh) | 一种装配式桥梁预制构件生产方法及工业化生产线 | |
CN102587286A (zh) | 桥梁上部结构简支变连续施工方法 | |
CN101956372B (zh) | 一种预应力混凝土梁式桥0号段快速施工方法 | |
CN201933417U (zh) | 一种适用于高铁预制箱梁的钢筋整体绑扎胎具 | |
CN104695337A (zh) | 自提升滑翻施工系统及施工方法 | |
CN113752379B (zh) | 一种采用二次张拉工艺和移动台座的混凝土t梁预制工法 | |
CN107795122A (zh) | 混凝土筒身施工装置及施工方法 | |
CN108071124B (zh) | 预制装配式地铁车站预制构件施工方法 | |
CN202658529U (zh) | 一种高速铁路原位制梁预制钢筋整体吊装入模装置 | |
CN105196414A (zh) | 预制t梁腹板钢筋胎架及预应力t梁施工方法 | |
CN109055637B (zh) | 一种高炉大修中炉壳安装的液压提升工艺 | |
CN202164030U (zh) | 整体式箱梁吊架 | |
CN202064281U (zh) | 一种滑模模架 | |
CN102398305A (zh) | 一种预制混凝土桩的生产方法 | |
CN107447668A (zh) | 一种自动提升定位变截面桥墩模板 | |
CN111283860A (zh) | 一种高速铁路装配式空心盖梁流水线生产施工方法 | |
CN215920863U (zh) | 一种高速铁路预制箱梁生产线 | |
CN107338768B (zh) | 工厂式大型渡槽施工系统及方法 | |
CN204955097U (zh) | 预制t梁腹板钢筋胎架 | |
CN205521875U (zh) | 箱梁底腹板钢筋整体成型模架 | |
CN205170161U (zh) | 一种预制梁板钢筋骨架吊具 | |
CN113618874A (zh) | 一种预制墩柱新型生产工艺 | |
CN209890066U (zh) | 一种箱梁底腹板钢筋吊装工具 | |
CN210025766U (zh) | 一种箱梁钢筋骨架制作移动胎架装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
ASS | Succession or assignment of patent right |
Owner name: SHANXI SANJIANG ENGINEERING TEST CO., LTD. Free format text: FORMER OWNER: CHINA RAILWAY THIRD ENGINEERING CO., LTD. Effective date: 20130228 |
|
C41 | Transfer of patent application or patent right or utility model | ||
COR | Change of bibliographic data |
Free format text: CORRECT: ADDRESS; FROM: 030001 TAIYUAN, SHAANXI PROVINCE TO: 030006 TAIYUAN, SHAANXI PROVINCE |
|
TR01 | Transfer of patent right |
Effective date of registration: 20130228 Address after: 030006 No. 5 Xuefu street, Shanxi, Taiyuan Patentee after: SHANXI SANJIANG ENGINEERING DETECTION Co.,Ltd. Address before: 030001 Yingze street, Shanxi, No. 269, No. Patentee before: CHINA RAILWAY NO.3 ENGINEERING GROUP Co.,Ltd. |
|
TR01 | Transfer of patent right |
Effective date of registration: 20191223 Address after: 030073 Yingze Street 269, Yingze District, Taiyuan City, Shanxi Province Patentee after: SHANXI TIANSHENG PLOTTING DETECTION ENGINEERING Co.,Ltd. Address before: 030006 No. 5 Xuefu street, Shanxi, Taiyuan Patentee before: SHANXI SANJIANG ENGINEERING DETECTION Co.,Ltd. |
|
TR01 | Transfer of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20111207 |
|
CF01 | Termination of patent right due to non-payment of annual fee |