CN101880994A - 特种道岔更换工艺 - Google Patents

特种道岔更换工艺 Download PDF

Info

Publication number
CN101880994A
CN101880994A CN2010101974262A CN201010197426A CN101880994A CN 101880994 A CN101880994 A CN 101880994A CN 2010101974262 A CN2010101974262 A CN 2010101974262A CN 201010197426 A CN201010197426 A CN 201010197426A CN 101880994 A CN101880994 A CN 101880994A
Authority
CN
China
Prior art keywords
track switch
track
switch
special
replacing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2010101974262A
Other languages
English (en)
Other versions
CN101880994B (zh
Inventor
孟瑞
付书锋
蔡忠泽
刘振华
张洪
潘付山
吴松
李士杰
梁添勇
沈永杰
齐伟广
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shijiazhuang Tiedao University
China Railway Sixth Group Co Ltd
Shijiazhuang Railway Construction Co Ltd of China Railway Sixth Group Co Ltd
Original Assignee
China Railway Sixth Group Co Ltd
Shijiazhuang Railway Construction Co Ltd of China Railway Sixth Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Sixth Group Co Ltd, Shijiazhuang Railway Construction Co Ltd of China Railway Sixth Group Co Ltd filed Critical China Railway Sixth Group Co Ltd
Priority to CN2010101974262A priority Critical patent/CN101880994B/zh
Publication of CN101880994A publication Critical patent/CN101880994A/zh
Application granted granted Critical
Publication of CN101880994B publication Critical patent/CN101880994B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Machines For Laying And Maintaining Railways (AREA)
  • Train Traffic Observation, Control, And Security (AREA)
  • Railway Tracks (AREA)

Abstract

本发明公开了一种特种道岔更换工艺,其步骤包括:1)测量放线;2)预铺道岔及中间轨排,在预铺地点预铺要更换的道岔及中间轨排;3)拆除菱形心;4)更换菱形心两侧的中间轨排;5)整体拆除道岔;6)安装道岔;7)组装菱形心;8)线路恢复,其关键改进在于:所述步骤1)中包括:以菱形心的两钝角辙岔为基准确定中轴线、以中轴线为基准确定更换道岔岔头岔尾位置。其优点在于:采用中轴控制法进行道岔施工,只需根据中轴线控制道岔位置,减少测量步骤,提高施工效率。

Description

特种道岔更换工艺
技术领域
本发明涉及了一种道岔施工工艺,特别涉及了一种特种道岔更换工艺。
背景技术
道岔是一种使机车车辆从一股道转入另一股道的线路连接设备,通常在车站、编组站大量铺设。有了道岔,可以充分发挥线路的通过能力,即使是单线铁路,铺设道岔,并修筑一段大于列车长度的叉线,就可以对开列车。
由于道岔具有数量多、构造复杂、使用寿命短、限制列车速度、行车安全性低、养护维修投入大等特点,与曲线、接头并称为轨道的三大薄弱环节。它的基本形式有三种:即线路的连接、交叉、连接与交叉的组合,常用的线路连接有各种类型的单式道岔和复式道岔;交叉有直交叉和菱形交叉;连接与交叉的组合有交分道岔和交叉渡线等。
当前,铁路建设正进入跨越式发展时期,未来几年铁路提速范围将进一步扩大,现有铁路既有设备已不能满足铁路运输的要求,道岔作为铁路运输设备重要组成部分,对列车通过速度影响很大,它也逐步向高速、重载的应用方向发展。钢筋混凝土岔枕可动心高速道岔与跨区间无缝线路组合的新型轨道结构,有效地满足了高速列车对基础结构的要求。为不断适应高速列车对铁路线路的要求,我国铁路每年需更换的既有线道岔高达3000多组。
而道岔更换就必须封锁所在区间线路,对行车造成一定的影响,而且道岔施工精度要求高,所以道岔更换施工效率是施工质量和安全控制之外的又一大关键点,现有的道岔施工工艺包括:特种道岔更换工艺,其步骤包括:1)测量放线;2)预铺道岔及中间轨排,在预铺地点预铺要更换的道岔及中间轨排;3)拆除菱形心;4)更换菱形心两侧的中间轨排;5)体拆除道岔;6)更换道岔;7)组装菱形心;8)线路恢复。其中道岔拆除、滑移过程中虽然使用了机械设备,在一定程度上提高道岔施工效率,但是其整个施工过程中测量放线是贯穿始终的,现有的一些交分道岔或者交叉渡线拆除更换过程中就要根据设计资料对岔头岔尾进行控制,道岔安装精度要求较高,标准轨缝为8mm,如果只控制一个道岔的位置继而控制其他道岔位置,就很难保证与其他道岔之间的轨缝能够满足要求,降低安装精度,同时测量放线较繁琐,道岔更换效率低。
发明内容
本发明提供一种特种道岔更换工艺,以提高道岔更换施工精度和施工效率,缩短封锁点要点时间,保证道岔更换施工质量。
为解决上述技术问题,本发明所采用的技术方案是:特种道岔更换工艺,其步骤包括:1)测量放线;2)预铺道岔及中间轨排,在预铺地点预铺要更换的道岔及中间轨排;3)拆除菱形心;4)更换菱形心两侧的中间轨排;5)整体拆除道岔;6)安装道岔;7)组装菱形心;8)线路恢复,其关键改进在于:所述步骤1)中包括:以菱形心的两钝角辙岔为基准确定中轴线、以中轴线为基准确定更换道岔岔头岔尾的位置。
采用上述技术方案所产生的有益效果是:采用中轴控制法进行道岔更换施工,在施工之前确定中轴线位置,并设置控制桩,以便在施工过程中对中轴线及道岔位置进行复核,更换道岔时以中轴线为基准分别更换两侧的道岔,能够保证道岔与两端基本轨之间的轨缝,且只需根据中轴线控制道岔位置,减少测量步骤,提高施工效率。
具体实施方式
为使本发明的上述目的,特征和有益效果能够更加明显易懂,下面将结合本发明实施例中的附图和具体实施方式,对本发明实施例中的技术方案进行清楚、完整地描述。
实施例1:特种道岔更换工艺,以最基本的交叉渡线为例,一般的交叉渡线分解开以后实际是由四个单开道岔和一个菱形心以及用于连接道岔的轨排构成,在更换过程中可以根据封锁点的长短、机具设备和劳动力的情况选择一次更换、分步更换单开道岔或者一次更换对角的单开道岔等几种作业方式,其步骤包括:1)测量放线,按照设计资料以菱形心的两钝角辙岔为基准确定中轴线、以中轴线为基准确定计划拆除的单开道岔岔头和岔尾的位置、并在限界外设置控制桩;2)预铺道岔,在预铺地点预铺要更换的单开道岔,包括预铺单开道岔的转辙器、连接部分和辙叉及护轨,预铺地点即满足施工需要及施工现场允许的铺设场地;3)拆除菱形心,拆除既有菱形心,并将长岔枕锯为标准枕木,以便整体拆除;4)更换菱形心两侧的中间轨排,包括拆除连接单开道岔的轨排、以中轴线为基准安装新轨排和在轨排上标记中轴线位置;5)采用滑移法整体拆除单开道岔,根据封锁点长短以及现场施工机具和施工人员情况,分步拆除单开道岔,步骤中包括起道钉、用打压机将单开道岔抬起、在底部穿设横向滑轨及设置滑车、将道岔横移出线界、道岔底部穿设纵向滑轨及设置滑车和将道岔纵向移动至开阔地后解体;6)安装道岔,包括将单开道岔纵向移动至线外正对安装位置、道岔底部穿设横向滑轨及设置滑车、将道岔横移至安装位置并落岔、人工拨移道岔对位、联接道岔,人工拨移道岔对位步骤中以更换好的轨排两端为基准进行对位,且预留标准轨缝8mm;7)组装菱形心;8)线路恢复,包括拨改道及上道碴、起落道、道碴捣固和线路检查。
实施例2:特种道岔更换工艺,以三渡三交道岔为例,三渡三交道岔可以看作是三组复式交分道岔和七组单开道岔构成,但其在两平行线路之间所形成的交叉渡线是相对于菱形心两钝角相对应的中轴线对称的,所以也可以采用中轴控制法施工,其具体步骤包括:1)测量放线,按照设计资料确定岔头、岔尾位置,以菱形心的两钝角辙岔为基准确定中轴线、以中轴线为基准确定复式交分道岔以及单开道岔岔头和岔尾的位置、并在限界外设置控制桩;2)预铺要更换的单开道岔或者复式交分道岔,包括预铺道岔的转辙器、连接部分和辙叉及护轨,预铺地点即满足施工需要及施工现场允许的铺设场地;3)拆除菱形心,拆除既有菱形心,将长岔枕锯为标准枕木;4)更换菱形心两侧的轨排,包括拆除连接道岔的轨排、以中轴线为基准安装新轨排和在轨排上标记中轴线位置;5)采用滑移法整体拆除单开道岔或者复式交分道岔,根据封锁点长短以及现场施工机具和施工人员情况,可以分步拆除复式交分道岔和单开道岔,步骤中包括起道钉、用打压机将道岔抬起、道岔底部穿设横向滑轨及设置滑车、将道岔横移出线界、道岔底部穿设纵向滑轨及设置滑车和将道岔纵向移动至开阔地后解体;6)安装道岔,包括将道岔纵向移动至线外正对安装位置、道岔底部穿设横向滑轨及设置滑车、将道岔横移至安装位置并落岔、人工拨移道岔对位、联接道岔,人工拨移道岔对位步骤中以更换好的轨排两端为基准进行对位,且预留标准轨缝8mm;可以一次拆除一个单开道岔或者一个复式交分道岔,也可以一次连续拆除多个单开道岔或者复式交分道岔;7)组装菱形心;8)线路恢复,包括拨改道及上道碴、起落道、道碴捣固和线路检查。
具体施工过程中仍然可以根据铁路线运输情况、施工机具和人力情况选择一次更换一组交叉渡线或者每次只更换一组单开道岔或者复式交分道岔,由于构成交叉渡线的单开道岔相对于菱形心两钝角相对应的中轴线左右对称的,所以只要控制好中轴线的位置,以中轴线为基准向两侧铺设道岔,完全可以保证道岔与轨排之间、道岔与基本轨之间的轨矩,而且经过现场施工验证,采用中轴控制法进行道岔施工可以提高施工效率,缩短封锁点时间,最大程度上降低施工对铁路营运线的影响。

Claims (10)

1.特种道岔更换工艺,其步骤包括:1)测量放线;2)预铺道岔及中间轨排,在预铺地点预铺要更换的道岔及中间轨排;3)拆除菱形心;4)更换菱形心两侧的中间轨排;5)整体拆除道岔;6)安装道岔;7)组装菱形心;8)线路恢复,其特征在于:所述步骤1)中包括:以菱形心的两钝角辙岔为基准确定中轴线、以中轴线为基准确定更换道岔岔头岔尾的位置。
2.根据权利要求1所述的特种道岔更换工艺,其特征在于:所述步骤2)中包括预铺道岔的转辙器、连接部分和辙叉及护轨。
3.根据权利要求2所述的特种道岔更换工艺,其特征在于:所述步骤3)中包括拆除既有菱形心,并将长岔枕锯为标准枕木。
4.根据权利要求3所述的特种道岔更换工艺,其特征在于:所述步骤4)包括拆除连接道岔的轨排、以中轴线为基准安装新轨排和在轨排上标记中轴线位置。
5.根据权利要求4所述的特种道岔更换工艺,其特征在于:所述步骤5)包括起道钉、用打压机将道岔抬起、道岔底部穿设横向滑轨并设置滑车、将道岔横移出线界、道岔底部穿设纵向滑轨及设置滑车和将道岔纵向移动至开阔地后解体。
6.根据权利要求5所述的特种道岔更换工艺,其特征在于:所述步骤6)包括将道岔纵向移动至线外正对安装位置、道岔底部穿设横向滑轨并设置滑车、将道岔横移至安装位置并落岔、人工拨移道岔对位、联接道岔。
7.根据权利要求6所述的特种道岔更换工艺,其特征在于:所述人工拨移道岔对位步骤中以更换好的轨排两端为基准进行对位,且预留标准轨缝8mm。
8.根据权利要求1至7中任一项权利所述的特种道岔更换工艺,其特征在于:所述步骤5)中包括拆除一个单开道岔,步骤6)中只包括更换步骤5)中拆除的一个单开道岔。
9.根据权利要求1至7中任一项权利所述的特种道岔更换工艺,其特征在于:所述步骤5)中包括采用滑移法拆除整体复式交分道岔,步骤6)中包括更换步骤5)中拆除的整体复式交分道岔。
10.根据权利要求1所述的特种道岔更换工艺,其特征在于:所述步骤8)包括拨改道及上道碴、起落道、道碴捣固和线路检查。
CN2010101974262A 2010-06-11 2010-06-11 三渡三交道岔更换工艺 Active CN101880994B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010101974262A CN101880994B (zh) 2010-06-11 2010-06-11 三渡三交道岔更换工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010101974262A CN101880994B (zh) 2010-06-11 2010-06-11 三渡三交道岔更换工艺

Publications (2)

Publication Number Publication Date
CN101880994A true CN101880994A (zh) 2010-11-10
CN101880994B CN101880994B (zh) 2012-08-22

Family

ID=43053121

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010101974262A Active CN101880994B (zh) 2010-06-11 2010-06-11 三渡三交道岔更换工艺

Country Status (1)

Country Link
CN (1) CN101880994B (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102828451A (zh) * 2012-09-28 2012-12-19 中铁五局(集团)有限公司 一种将整条铁道曲线采用滑轮和钢轨滑道拨移的方法
CN103510440A (zh) * 2013-10-18 2014-01-15 中铁上海设计院集团有限公司 一种铁路站场的过渡改造方法
CN110205875A (zh) * 2019-06-18 2019-09-06 中铁二十一局集团第四工程有限公司 铁路既有线交叉渡线整体插铺施工方法
CN113919021A (zh) * 2021-12-13 2022-01-11 中铁第五勘察设计院集团有限公司 一种既有铁路车站股道线位重构方法及系统

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005009118A (ja) * 2003-06-17 2005-01-13 Sekisui Chem Co Ltd 分岐部用まくら木
CN1598147A (zh) * 2004-09-15 2005-03-23 中铁二十五局集团第三工程有限公司 更换铁路道岔施工工艺及道岔换铺设备
CN2730917Y (zh) * 2004-08-24 2005-10-05 鞍钢集团铁路修建公司 60kg/m钢轨小号码单开道岔及交叉渡线道岔

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005009118A (ja) * 2003-06-17 2005-01-13 Sekisui Chem Co Ltd 分岐部用まくら木
CN2730917Y (zh) * 2004-08-24 2005-10-05 鞍钢集团铁路修建公司 60kg/m钢轨小号码单开道岔及交叉渡线道岔
CN1598147A (zh) * 2004-09-15 2005-03-23 中铁二十五局集团第三工程有限公司 更换铁路道岔施工工艺及道岔换铺设备

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
《上海铁道科技》 20030930 吕宏辉等 提速型交叉渡线的铺设 33-34 1-10 , 第3期 2 *
《铁道建筑》 20060831 孙健 铁路干线交汇处整组更换交叉渡线和复式交分道岔群的施工组织 104-105 1-10 , 第8期 2 *
《铁道建筑》 20070930 贾秋,张玉明 整组更换道岔的前期测量 73-75 1-4,8-10 , 第9期 2 *
《铁道建筑技术》 20030228 孙季平等 点上更换交叉渡线施工技术 28-29 1-4,8-10 , 第1期 2 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102828451A (zh) * 2012-09-28 2012-12-19 中铁五局(集团)有限公司 一种将整条铁道曲线采用滑轮和钢轨滑道拨移的方法
CN103510440A (zh) * 2013-10-18 2014-01-15 中铁上海设计院集团有限公司 一种铁路站场的过渡改造方法
CN103510440B (zh) * 2013-10-18 2016-04-20 中铁上海设计院集团有限公司 一种铁路站场的过渡改造方法
CN110205875A (zh) * 2019-06-18 2019-09-06 中铁二十一局集团第四工程有限公司 铁路既有线交叉渡线整体插铺施工方法
CN113919021A (zh) * 2021-12-13 2022-01-11 中铁第五勘察设计院集团有限公司 一种既有铁路车站股道线位重构方法及系统
CN113919021B (zh) * 2021-12-13 2022-04-05 中铁第五勘察设计院集团有限公司 一种既有铁路车站股道线位重构方法及系统

Also Published As

Publication number Publication date
CN101880994B (zh) 2012-08-22

Similar Documents

Publication Publication Date Title
CN102979041B (zh) 下穿铁路道岔群顶进大跨度箱桥施工的软架空加固顶进法
CN103437254B (zh) 框架桥顶进铁路岔区线路加固装置
CN101880994B (zh) 三渡三交道岔更换工艺
CN102322000A (zh) 城市轨道交通工程线路轨道对称三开道岔
CN108842526A (zh) 一种槽型轨复式交分道岔
CN202131563U (zh) 钢横梁一次吊装就位组合门式桥墩
CN108486965A (zh) 轨道线路道岔区辙叉结构
CN202208869U (zh) 城市轨道交通工程线路轨道对称三开道岔
CN109098102B (zh) 用于道岔区段的便梁加固结构
CN203821172U (zh) 交叉渡线道岔
CN2758310Y (zh) 双块式轨枕
CN201614526U (zh) 狭窄空间交叉渡线形式窄轨道岔
CN102304882B (zh) 城市轨道交通工程中线路轨道4.5号对称道岔
CN210134294U (zh) 轨道线路道岔区转辙器结构
CN217324965U (zh) 一种永临结合的铺轨基地桥梁
CN105926381A (zh) 不中断行车条件下将隧道有砟道床更换为无砟轨道的方法
CN212000396U (zh) 新西兰钢轨、轨距7.5号复式交分道岔
CN203440720U (zh) 框架桥顶进铁路岔区线路加固装置
CN202347369U (zh) 铁路道岔活动心轨组装辙叉
CN205152818U (zh) 一种桥梁整体横移换梁系统
CN208830066U (zh) 一种槽型轨复式交分道岔
CN203021922U (zh) 滑动支点组件
CN110205875A (zh) 铁路既有线交叉渡线整体插铺施工方法
CN208151775U (zh) 一种悬吊式过轨人行天桥
CN213447888U (zh) 一种60kg/m钢轨6号交分道岔

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: CHINA RAILWAY SIXTH GROUP CO., LTD. SHIJIAZHUANG T

Free format text: FORMER OWNER: SHIJIAZHUANG RAILWAY CONSTRUCTION CO., LTD. OF THE SIXTH ENGINEERING BUREAU, CREC

Effective date: 20120615

Owner name: SHIJIAZHUANG RAILWAY CONSTRUCTION CO., LTD. OF THE

Free format text: FORMER OWNER: CHINA RAILWAY SIXTH GROUP CO., LTD.

Effective date: 20120615

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Meng Rui

Inventor after: Liang Tianyong

Inventor after: Shen Yongjie

Inventor after: Qi Weiguang

Inventor after: Dong Huichuan

Inventor after: Yao Shaokang

Inventor after: Wang Guoan

Inventor after: Cai Zhongze

Inventor after: Fu Shufeng

Inventor after: Liu Zhenhua

Inventor after: Zhang Hong

Inventor after: Pan Fushan

Inventor after: Wu Song

Inventor after: Li Shijie

Inventor before: Meng Rui

Inventor before: Shen Yongjie

Inventor before: Qi Weiguang

Inventor before: Fu Shufeng

Inventor before: Cai Zhongze

Inventor before: Liu Zhenhua

Inventor before: Zhang Hong

Inventor before: Pan Fushan

Inventor before: Wu Song

Inventor before: Li Shijie

Inventor before: Liang Tianyong

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: MENG RUI FU SHUFENG CAI ZHONGZE LIU ZHENHUA ZHANG HONG PAN FUSHAN WU SONG LI SHIJIE LIANG TIANYONG SHEN YONGJIE QI WEIGUANG TO: MENG RUI WANG GUOAN CAI ZHONGZE FU SHUFENG LIU ZHENHUA ZHANG HONG PAN FUSHAN WU SONG LI SHIJIE LIANG TIANYONG SHEN YONGJIE QI WEIGUANG DONG HUICHUAN YAO SHAOKANG

Free format text: CORRECT: ADDRESS; FROM: 100036 HAIDIAN, BEIJING TO: 050010 SHIJIAZHUANG, HEBEI PROVINCE

TA01 Transfer of patent application right

Effective date of registration: 20120615

Address after: 050010, No. 18, Ping'an North Street, Hebei, Shijiazhuang

Applicant after: Shijiazhuang Railway Construction Co., Ltd. Of The Sixth Engineering Bureau, CREC

Co-applicant after: The Sixth Engineering Bureau Group Co., Ltd., China Railway

Co-applicant after: Shijiazhuang Tiedao University

Address before: 100036 Haidian District, Wanshou Road, No. 2,

Applicant before: The Sixth Engineering Bureau Group Co., Ltd., China Railway

Co-applicant before: Shijiazhuang Railway Construction Co., Ltd. Of The Sixth Engineering Bureau, CREC

C14 Grant of patent or utility model
GR01 Patent grant