CN101550829B - 盾构整体自行过站施工方法 - Google Patents

盾构整体自行过站施工方法 Download PDF

Info

Publication number
CN101550829B
CN101550829B CN2009100743751A CN200910074375A CN101550829B CN 101550829 B CN101550829 B CN 101550829B CN 2009100743751 A CN2009100743751 A CN 2009100743751A CN 200910074375 A CN200910074375 A CN 200910074375A CN 101550829 B CN101550829 B CN 101550829B
Authority
CN
China
Prior art keywords
shield
station
reaction
semi
reaction holes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2009100743751A
Other languages
English (en)
Other versions
CN101550829A (zh
Inventor
辛振省
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 3 Engineering Group Co Ltd
Original Assignee
China Railway No 3 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 3 Engineering Group Co Ltd filed Critical China Railway No 3 Engineering Group Co Ltd
Priority to CN2009100743751A priority Critical patent/CN101550829B/zh
Publication of CN101550829A publication Critical patent/CN101550829A/zh
Application granted granted Critical
Publication of CN101550829B publication Critical patent/CN101550829B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

本发明属于盾构过站的技术领域,具体涉及一种地铁隧道工程中盾构整体自行过站施工方法,解决了现有盾构机过站施工方法存在的问题。盾构整体自行过站施工方法,步骤如下:过站导台设置若干组反力孔洞;盾构机接收完毕推上过站导台后,在第一组反力孔洞和盾构机盾尾之间放置半环管片;在反力孔洞内插入反力柱;盾构千斤顶推半环管片,前进,待盾构千斤顶推出一段距离后,缩回盾构千斤顶,吊出半环管片,拔出反力柱,把反力柱插入相邻下一组的反力孔洞中,继续以上的过程;循环前进直到把盾构机顶推到预定位置。本发明综合考虑了盾构自身优势和导台反力孔柱便捷优势,循环工艺简单易懂易操作,适合大面积推广,经济效益和社会效益十分可观。

Description

盾构整体自行过站施工方法
技术领域
本发明属于盾构过站的技术领域,具体涉及一种地铁隧道工程中盾构整体自行过站施工方法。
背景技术
在城市地铁建设过程中,盾构机以其安全快捷、机械化和自动化程度高等优点越来越被广泛应用。城市地铁建设中,为方便日后旅客出行,车站距离一般较短,车站数量较多,而且目前国内施工方法中绝大部分是先施工地铁车站,然后再施工隧道部分,为保证施工的连续性和质量,一般每个标段都含有几个车站。这种情况下,盾构施工完一个区间后,必须通过建成的车站进入下一个区间。
盾构机过站施工是多区间标段土建施工中的必经阶段,也是重点和难点,目前盾构机过站方法有四种方法,分别为:①盾构机和后配套台车解体后过站,即盾构机与后配套台车分开,然后分别用额外千斤顶或牵引设备推动或拉动盾构主机和台车。②盾构完全解体过站,由于车站受限盾构机要完全解体后再吊出,在井外进行维修,而后下井再拼装。以上这种方法施工工期长,施工费用高,工序复杂,施工作业面较大,安全性低。③盾构机整体牵引过站,即盾构机不做任何拆卸,由于盾构推进车站将不再拼装管片,自行没有推力,只能在外力的牵引作用下在盾构导台上滑动过站。这种方法虽然为整体过站,但是其需要较大的牵引设备,而且由于外拉力的不均匀很容易造成盾构的滚动和侧移,安全程度低,需要拉力设备较大,预先还要设立卷扬机固定台等施工,没有充分发挥盾构机自身的优点。④盾构机拼装管片过站,这种方法是盾构机到达车站后继续照常推进和拼装管片,在管片拼装的同时,在管片的外部设立支护管片的支撑,待盾构推进到预定位置后,停下盾构机,一边维修盾构一边拆除车站内的多余管片。这种方法虽然发挥了盾构机自身的优点,不需要外来设备,但是进站后拼装每环管片都要做外部支撑,而且还要过站后还要拆除导台上的多余管片,不经施工工期长,而且费用较高。
发明内容
本发明为了解决现有盾构机过站施工方法存在的上述问题,提供了一种盾构整体自行过站施工方法。
本发明采用如下的技术方案实现:一种盾构整体自行过站施工方法,其步骤如下:
1)、过站导台的导台凹槽内设置若干组反力孔洞,各组反力孔洞设置在导台凹槽的同一圆周上;
2)、盾构机接收完毕推上过站导台后,在第一组反力孔洞和盾构机盾尾之间放置半环管片,反力孔洞的宽度+半环管片的宽度≤盾构机千斤顶的行程;
3)、在反力孔洞内插入反力柱;
4)、盾构千斤顶推半环管片,盾构机前进,待盾构千斤顶推出一段距离后,缩回盾构千斤顶,吊出半环管片,拔出第一组反力孔洞中的反力柱,把反力柱插入相邻下一组的反力孔洞中,继续以上的过程;
5)、循环前进直到把盾构机顶推到预定位置。
相邻的反力孔洞之间的距离≥半环管片的宽度。每组反力孔洞包括3~4个孔洞。
本发明的有益效果:充分利用了盾构机机械化自动化的优点,以其自身的千斤顶推力来提供动力,节省了外部顶推设备或牵引设备,而且盾构自身的千斤顶推力可以数值化控制;循环利用半环管片,不需要拼装连续管片,节约费用在1/3以上;此外,本发明连续快捷循环施工,盾构整体前行,不用解体和重新安装,大大缩短工期,一般可节约工期一半甚至更多。
本发明综合考虑了盾构自身优势和导台反力孔柱便捷优势,循环工艺简单易懂易操作,适合大面积推广,经济效益和社会效益十分可观。
附图说明
图1为本发明导台凹槽内预留反力孔洞的示意图
图2为本发明盾构、管片及反力柱的关系示意图
图中:1-过站导台,2-导台凹槽,3-反力孔洞,4-盾构机,5-反力柱,6-半环管片,7-盾构千斤顶,d-反力孔洞的宽度,D-半环管片的宽度,L-相邻的反力孔洞之间的距离。
具体实施方式
结合附图对本发明的具体实施方式作进一步说明。
本发明是针对盾构机通过车站,其具体的实施方法为:在过站导台1建设的过程中预留若干组反力孔洞3,各组反力孔洞设置在导台凹槽的同一圆周截面上,每一组根据需要预留3~5个孔洞,如图1所示。待盾构机4接收完毕推上过站导台1后,在盾构机1盾尾与反力柱5之间放入半环管片6(一般由3片管片连接而成),在预留的反力孔洞内插入反柱力5,如图2所示。然后盾构千斤顶7推半环管片6,盾构机4前进,待推出一段距离,盾构机前进使下一组反力孔洞露出后,缩回盾构千斤顶7,吊出临时半环管片6,拔出反力孔洞中的反力柱5,把反力柱5插入下一组中的反力孔洞3中,继续以上的过程。这样循环前进直到把盾构顶推到预定位置。

Claims (3)

1.一种盾构整体自行过站施工方法,其特征在于步骤如下:
1)、过站导台(1)的导台凹槽(2)内设置若干组反力孔洞(3),各组反力孔洞(3)设置在导台凹槽(2)的同一圆周上,
2)、盾构机(4)接收完毕推上过站导台(1)后,在第一组反力孔洞(3)和盾构机(4)盾尾之间放置半环管片(6),反力孔洞(3)的宽度+半环管片(6)的宽度≤盾构千斤顶(7)的行程;
3)、在反力孔洞(3)内插入反力柱(5);
4)、盾构千斤顶(7)推半环管片(6),盾构机(4)前进,待盾构千斤顶(7)推出一段距离后,缩回盾构千斤顶(7),吊出半环管片(6),拔出第一组反力孔洞(3)中的反力柱(5),把反力柱(5)插入相邻下一组的反力孔洞中,继续以上的过程;
5)、循环前进直到把盾构机(4)顶推到预定位置。
2.根据权利要求1所述的盾构整体自行过站施工方法,其特征在于相邻的反力孔洞(3)之间的距离≥半环管片(6)的宽度。
3.根据权利要求1或2所述的盾构整体自行过站施工方法,其特征在于每组反力孔洞包括3~5个孔洞。
CN2009100743751A 2009-05-14 2009-05-14 盾构整体自行过站施工方法 Active CN101550829B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009100743751A CN101550829B (zh) 2009-05-14 2009-05-14 盾构整体自行过站施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009100743751A CN101550829B (zh) 2009-05-14 2009-05-14 盾构整体自行过站施工方法

Publications (2)

Publication Number Publication Date
CN101550829A CN101550829A (zh) 2009-10-07
CN101550829B true CN101550829B (zh) 2011-03-16

Family

ID=41155289

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009100743751A Active CN101550829B (zh) 2009-05-14 2009-05-14 盾构整体自行过站施工方法

Country Status (1)

Country Link
CN (1) CN101550829B (zh)

Families Citing this family (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101922298B (zh) * 2010-08-20 2012-10-10 上海市第一市政工程有限公司 自行走式盾构平移过站系统
CN101922295A (zh) * 2010-08-23 2010-12-22 上海市第一市政工程有限公司 盾构平移过站反力系统
CN102155236B (zh) * 2011-02-16 2013-07-03 长江水利委员会长江勘测规划设计研究院 盾构出发反力座
CN102285616B (zh) * 2011-07-12 2013-04-24 广州轨道交通建设监理有限公司 步履式盾构机侧移系统及侧移方法
CN102337900A (zh) * 2011-09-16 2012-02-01 中铁三局集团有限公司 一种循环铺垫式盾构空推方法
CN102418530B (zh) * 2011-12-14 2013-07-31 中铁十二局集团第二工程有限公司 一种盾构整机滚轮导轨过站施工方法
CN104653229B (zh) * 2015-01-27 2017-01-25 粤水电轨道交通建设有限公司 盾构滑靴曲线上推过洞施工方法
CN105221153A (zh) * 2015-09-16 2016-01-06 中铁十局集团第三建设有限公司 盾构机整体过站施工方法
CN106437730A (zh) * 2016-10-09 2017-02-22 上海市基础工程集团有限公司 盾构机倒拔装置
CN106640185A (zh) * 2016-12-26 2017-05-10 中铁二局集团有限公司 一种盾构机过站装置及方法
CN109026036B (zh) * 2018-09-21 2019-11-29 中南大学 一种盾构机空推步进装置
CN110094209B (zh) * 2019-06-10 2021-08-17 中交二公局第四工程有限公司 一种盾构机推进方法
CN110159279B (zh) * 2019-06-10 2021-02-19 上海弥涅科技有限公司 一种盾构机推进装置
CN110374614B (zh) * 2019-07-09 2020-11-03 中国铁建大桥工程局集团有限公司 一种洞室内盾构机快速接收平移施工方法
NL2023905B1 (en) * 2019-09-25 2020-09-04 Shanghai Minie Tech Co Ltd Plane sliding advancing device for shield machine
CN112049651B (zh) * 2020-08-12 2023-02-03 中国铁建投资集团有限公司 在轨平移空推过站的方法

Also Published As

Publication number Publication date
CN101550829A (zh) 2009-10-07

Similar Documents

Publication Publication Date Title
CN101550829B (zh) 盾构整体自行过站施工方法
CN103046933B (zh) 一种盾构过站掘进与车站平行施工方法
CN102337900A (zh) 一种循环铺垫式盾构空推方法
CN101713292B (zh) 一种用于土压平衡式盾构的全时推进系统结构
CN105971628A (zh) 掘进巷道临时支护方法
CN109057810B (zh) 一种盾构空推通过矿山法隧道的施工方法及辅助装置
CN102011596B (zh) 盾构始发或接收端头洞门维护工艺
CN104653229A (zh) 盾构滑靴曲线上推过洞施工方法
CN204402559U (zh) 一种大顶推力盾构机空推过洞用桁架式反力支座组
CN203684234U (zh) 轨排施工吊装预留井支护结构
CN112523760B (zh) 一种大断面隧道双侧壁导坑法向cd法转换的施工方法
CN103291317A (zh) 旧隧道管片拆除与隧道扩径的施工方法及隧道扩径机
CN108222953B (zh) U型敞口盾构机通过管廊非标准段的施工方法
CN111594199A (zh) 一种双护盾tbm的壁后回填的施工方法
CN202250095U (zh) 盾构前移推进装置
CN202560321U (zh) 盾构分体始发管线同步移动装置
CN103742155A (zh) 一种大跨度管片拆除方法
CN104832202A (zh) 一次性衬砌的液压可伸缩移动衬车
CN205677652U (zh) 一种沿空留巷超前支护装置
CN205025492U (zh) 综采工作面管线自移小车装置
CN210483734U (zh) 盾构始发负环
CN102094665A (zh) 盾构法多孔隧道近接施工附加荷载的辅助支撑方法
CN104879166B (zh) 一种大采高综采工作面台阶式自掘回撤通道方法
CN109339798B (zh) 一种用于改进隧道双侧壁导坑法施工中核心土解除方法
CN209539363U (zh) 盾构隧道用管片环氧树脂堵漏系统

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant