CN102011596B - 盾构始发或接收端头洞门维护工艺 - Google Patents

盾构始发或接收端头洞门维护工艺 Download PDF

Info

Publication number
CN102011596B
CN102011596B CN 201010562717 CN201010562717A CN102011596B CN 102011596 B CN102011596 B CN 102011596B CN 201010562717 CN201010562717 CN 201010562717 CN 201010562717 A CN201010562717 A CN 201010562717A CN 102011596 B CN102011596 B CN 102011596B
Authority
CN
China
Prior art keywords
steel sheet
sheet pile
shield
portal
shield structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 201010562717
Other languages
English (en)
Other versions
CN102011596A (zh
Inventor
辛振省
常乃超
张宇宁
胡国伟
郑保才
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 3 Engineering Group Co Ltd
Original Assignee
China Railway No 3 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 3 Engineering Group Co Ltd filed Critical China Railway No 3 Engineering Group Co Ltd
Priority to CN 201010562717 priority Critical patent/CN102011596B/zh
Publication of CN102011596A publication Critical patent/CN102011596A/zh
Application granted granted Critical
Publication of CN102011596B publication Critical patent/CN102011596B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明属于地铁隧道工程的技术领域,具体是一种盾构端头洞门维护工艺,提供了一种经济、安全、快捷的方法,使盾构始发和接收时洞门维护结构既能防水又能起到维护土体作用且易于拔除。其步骤如下:在盾构端头洞门维护墙施工时,洞门位置插入钢板桩;在维护墙混凝土初凝前上下活动钢板桩;盾构始发或接收时,待盾构前端顶推到钢板桩时,起拔钢板桩,盾构推进,完成始发或接收。本发明简单易操作,造价低廉,而且钢板桩可以重复使用,在当今大力建设地下铁道交通工程时期,其经济效益和社会效益尤为突出,意义深远,有极高的推广价值。

Description

盾构始发或接收端头洞门维护工艺
技术领域
本发明属于地铁隧道工程中盾构始发或接收的技术领域,具体涉及一种盾构始发或接收端头洞门维护工艺。
背景技术
  地下铁道交通用于解决城市交通问题的优越性十分明显,近年来地铁建设在全国范围内大面积铺开,地铁建设工程中盾构作为隧道施工的智能化施工机械被广泛应用,盾构工程施工过程中,盾构的始发和接收为当今普遍认为的难点重点工程,也是盾构工程中重要的风险源之一,多数的盾构始发和接收工程事故发生在洞门的破除阶段,所以洞门及洞门后土体的维护措施十分重要。
目前,盾构始发和接收洞门后土体维护有以下几种:
1、单纯注浆加固,即在洞门后土体一定范围的土体内注浆加固,使得破除洞门后,土体能抵抗后方土体压力和防止地下水喷涌,这种方法由于工艺简单被广泛应用,但这种方法在盾构接收时的弊端很大,破除洞门后,加固土体在后方盾构强大推力下极容易向洞门发生坍塌,且洞门内层钢筋不宜破除太早。待盾构将要到达前,加固土体由于盾构推力挤压作用发生破裂,地下水喷涌事故极易发生,此时由于洞门钢筋没有破除而盾构不能强行推出而极易发生灾难性事故。
2、维护桩式洞门加固措施,即在洞门圈后打灌注桩等桩体来维护洞门土体的稳定,这种加固方式在盾构始发和接收的过程中桩体的破除时机难以把握,而且这种桩体式加固方法对防水极为不利,所以一般用于水位较低的无水地层,适用范围极为有限。
发明内容
本发明的发明目的:用经济、安全、快捷的方法实现盾构始发或接收端头洞门的维护措施,使盾构始发和接收时洞门维护结构既能防水又能起到维护土体作用且易于拔除。
本发明采用如下的技术方案实现:
盾构始发或接收端头洞门维护工艺,其步骤如下:
1)、在盾构始发或接收端头洞门维护墙施工时,洞门位置插入钢板桩;
2)、在维护墙混凝土初凝前上下活动钢板桩,维护墙后方采用注浆加固方式加固设计范围;
3)、盾构始发或接收时,待盾构前端顶推到钢板桩时,起拔钢板桩,盾构推进,完成始发或接收。
盾构接收时,待盾构前端顶推到钢板桩时,开始补充注浆或注聚氨酯加固管片隧道周围过水通道空隙,然后缓慢抽拔钢板桩,如果抽拔过程中洞门处有大量水喷涌,马上回插钢板桩,直到抽拔钢板桩时无水喷冒时拔出洞门处的全部钢板桩,盾构迅速推进,盾构推出洞门后,洞门用防水帘布封闭,完成盾构接收。
本发明具有如下有益效果:本发明利用钢板桩替代洞门维护结构中的钢筋或灌注桩,既能起到防水和稳固后方土体的作用,同时钢板桩插拔工艺简单易操作,避免了传统方法中洞门钢筋破除时事故的发生,从理论上及实践中保证了恶劣地层中盾构始发和接收的万无一失,避免不良地层中盾构始发和接收工程的灾难性事故。本方法简单易操作,造价低廉,而且钢板桩可以重复使用,在当今大力建设地下铁道交通工程时期,其经济效益和社会效益尤为突出,意义深远,有极高的推广价值。
附图说明
图1为盾构隧道端头洞门处插入钢板桩的示意图
图2为盾构始发顶到钢板桩时的示意图
图3为起拔钢板桩后盾构始发推进的示意图
图4为盾构接收时盾构顶推到钢板桩后注浆封堵空隙的示意图
图5为起拔钢板桩盾构接收进站的示意图
图中:1-预开挖隧道,2-端头加固区,3-维护墙,4-结构墙,5-钢板桩,6-盾构始发或接收井,7-盾构机,8-盾构始发或接收托架,9-车站底板,10-注浆封堵空隙,11-管片隧道。
具体实施方式
    结合附图对本发明的具体实施方式作进一步说明。
在洞门维护墙施工时洞门位置插入钢板桩代替该位置处的钢筋,所述的钢板桩本领域技术人员可从现有技术中获知。如图1所示,在维护墙混凝土初凝前上下活动钢板桩,以免钢板桩与墙体混凝土粘结力过大而不宜拔出;在围护结构做好后、盾构到达前,维护墙后方采用注浆加固方式加固设计范围;如图2所示,盾构始发时,待盾构推进直至刀盘顶到洞门钢板桩时;如图3所示,起拔钢板桩,盾构始发推进即可。如图4所示,盾构接收时,待盾构顶推到洞门钢板桩时,开始补充注浆或注聚氨酯加固周围过水通道空隙,然后试着拔出钢板桩,如果拔出钢板桩后洞门有大量水喷涌,说明还存在较大过水通道,马上回插钢板桩,直到拔出钢板桩后基本无水喷冒,此时拔出洞门处的全部钢板桩,盾构迅速推进,如图5所示,推出洞门后洞门防水帘布封闭,完成盾构接收。

Claims (1)

1.一种盾构始发或接收端头洞门维护工艺,其特征在于步骤如下:
1)、在盾构始发或接收端头洞门维护墙施工时,洞门位置插入钢板桩;
2)、在维护墙混凝土初凝前上下活动钢板桩,维护墙后方采用注浆加固方式加固设计范围;
3)、盾构始发时,待盾构前端顶推到钢板桩时,起拔钢板桩,盾构推进,完成始发;盾构接收时,待盾构前端顶推到钢板桩时,开始补充注浆或注聚氨酯加固管片隧道周围过水通道空隙,然后缓慢抽拔钢板桩,如果抽拔过程中洞门处有大量水喷涌,马上回插钢板桩,直到抽拔钢板桩时无水喷冒时拔出洞门处的全部钢板桩,盾构迅速推进,盾构推出洞门后,洞门用防水帘布封闭,完成盾构接收。
CN 201010562717 2010-11-29 2010-11-29 盾构始发或接收端头洞门维护工艺 Active CN102011596B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010562717 CN102011596B (zh) 2010-11-29 2010-11-29 盾构始发或接收端头洞门维护工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010562717 CN102011596B (zh) 2010-11-29 2010-11-29 盾构始发或接收端头洞门维护工艺

Publications (2)

Publication Number Publication Date
CN102011596A CN102011596A (zh) 2011-04-13
CN102011596B true CN102011596B (zh) 2012-07-11

Family

ID=43841906

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010562717 Active CN102011596B (zh) 2010-11-29 2010-11-29 盾构始发或接收端头洞门维护工艺

Country Status (1)

Country Link
CN (1) CN102011596B (zh)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102787851B (zh) * 2011-05-20 2015-03-18 上海市电力公司 对电力电缆隧道管片接缝进行堵漏的方法
CN102808630B (zh) * 2011-06-03 2015-06-17 上海市电力公司 对电力电缆隧道管片螺栓孔进行堵漏的方法
CN102352753B (zh) * 2011-06-29 2014-08-27 中铁第四勘察设计院集团有限公司 采用冻结加固和堆土灌水的盾构到达接收方法
CN103397892A (zh) * 2013-07-15 2013-11-20 中铁十三局集团有限公司 盾构始发洞门延伸钢环
CN103643961A (zh) * 2013-12-04 2014-03-19 中国水电顾问集团华东勘测设计研究院有限公司 无端头加固盾构接收结构及接收方法
CN105421310A (zh) * 2015-12-28 2016-03-23 中国电建集团贵阳勘测设计研究院有限公司 一种导流洞闸室下闸后渗漏的处理方法及结构
CN105649637A (zh) * 2016-04-06 2016-06-08 北京市政建设集团有限责任公司 一种盾构横通道平移接收施工工法
CN107386273A (zh) * 2017-08-11 2017-11-24 山东大学 一种盾构始发接收用新型组合h型桩及其施工工艺
CN108915706A (zh) * 2018-08-14 2018-11-30 中国铁建大桥工程局集团有限公司 高水压力盾构始发洞门水平注浆与静态破除施工方法
CN110700842A (zh) * 2019-11-11 2020-01-17 山东大学 一种适用于盾构端头富水砂层段的超前注浆加固方法

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201193027Y (zh) * 2008-04-06 2009-02-11 马兴华 与地面道路相结合的地下无轨电车通道
CN101608551B (zh) * 2009-06-15 2011-06-22 广东华隧建设股份有限公司 一种盾构机密闭始发及到达的施工方法
CN101749026B (zh) * 2010-02-10 2012-10-03 中铁三局集团有限公司 盾构接收或始发端头网格式加固方法及盾构接收方法
CN101781991B (zh) * 2010-02-10 2012-05-30 中铁三局集团有限公司 盾构接收或始发端头的双井式加固方法及双井式盾构接收方法

Also Published As

Publication number Publication date
CN102011596A (zh) 2011-04-13

Similar Documents

Publication Publication Date Title
CN102011596B (zh) 盾构始发或接收端头洞门维护工艺
CN104196546B (zh) 一种隧道施工过程中断层破碎带塌方治理方法
CN102287198B (zh) 一种过江盾构隧道破碎地层联络通道的施工方法
CN204738817U (zh) 一种隧道柔性支护结构型式
CN104047623B (zh) 一种大跨洞室开挖施工方法
CN103306680B (zh) 既有单线隧道扩建为多线隧道的施工方法
CN103899323B (zh) 一种盾构穿越铁路站场的施工方法
CN102606168B (zh) 防止浅埋暗挖隧道开挖时沉降变形的施工方法
CN106869969A (zh) 一种软岩超大断面隧道的开挖支护施工方法
CN106761778A (zh) 一种适用于上软下硬地层的地铁车站暗挖施工工艺
CN104314585A (zh) 隧道全断面预加固方法及结构
CN103790592A (zh) 一种端头土体加固系统和方法
CN103953366B (zh) 单洞隧道改为连拱时中隔墙顶部原衬砌空腔回填施工方法
CN103195467A (zh) 一种水力压裂与注浆固化相结合的石门揭煤方法
CN110259449A (zh) 一种依托钢模台车的特厚煤层条带式充填开采方法
CN103089277A (zh) 砂层巷道的空间加固施工工艺
CN104612722B (zh) 一种环形盾构或环形顶管始发及到达的洞门加固方法
CN111594199A (zh) 一种双护盾tbm的壁后回填的施工方法
CN109209443A (zh) 一种破碎围岩隧道结构的修建方法
CN104533431A (zh) 一种无中墙连拱隧道的施工工法
CN204186394U (zh) 隧道全断面预加固结构
CN204716253U (zh) 圆形大直径引水隧洞结构
CN103352701A (zh) 一种盾构机的推盾施工工法
CN101358529A (zh) 短导管及短导管固砂剂加固施工工艺
CN203499698U (zh) 一种应用于地下工程施工的超前帷幕注浆系统

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant