CN101538897B - 钢筋混凝土建筑物的主体工程施工方法 - Google Patents

钢筋混凝土建筑物的主体工程施工方法 Download PDF

Info

Publication number
CN101538897B
CN101538897B CN 200910116509 CN200910116509A CN101538897B CN 101538897 B CN101538897 B CN 101538897B CN 200910116509 CN200910116509 CN 200910116509 CN 200910116509 A CN200910116509 A CN 200910116509A CN 101538897 B CN101538897 B CN 101538897B
Authority
CN
China
Prior art keywords
construction
layer
lifting platform
lifting
vertical member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 200910116509
Other languages
English (en)
Other versions
CN101538897A (zh
Inventor
袁斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Kaiyuan Highway and Bridge Co., Ltd.
Original Assignee
袁斌
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 袁斌 filed Critical 袁斌
Priority to CN 200910116509 priority Critical patent/CN101538897B/zh
Publication of CN101538897A publication Critical patent/CN101538897A/zh
Priority to PCT/CN2010/000473 priority patent/WO2010115350A1/zh
Priority to US13/263,740 priority patent/US8863474B2/en
Application granted granted Critical
Publication of CN101538897B publication Critical patent/CN101538897B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66FHOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F7/00Lifting frames, e.g. for lifting vehicles; Platform lifts
    • B66F7/10Lifting frames, e.g. for lifting vehicles; Platform lifts with platforms supported directly by jacks
    • B66F7/16Lifting frames, e.g. for lifting vehicles; Platform lifts with platforms supported directly by jacks by one or more hydraulic or pneumatic jacks
    • B66F7/20Lifting frames, e.g. for lifting vehicles; Platform lifts with platforms supported directly by jacks by one or more hydraulic or pneumatic jacks by several jacks with means for maintaining the platforms horizontal during movement
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

一种钢筋混凝土建筑物的主体工程施工方法,其特征是在已完工的永久基础上设置顶升机构及项升平台,首先在顶升机构及顶升平台上施工顶层框架,然后依靠顶升机构对顶层框架实施顶升,再在原有位置的顶升机构及顶升平台上施工次高层框架,同时完成顶层框架与次高层框架之间的永久连接;随后,再依靠顶升机构对顶层框架及次高层框架实施顶升,如此重复施工,直至地面一层,完成从最高层到地面一层的逆向逐层施工。本发明方法是先施工顶层,再逐层向下至第一层,克服作业面上设备、周转材料每层都要组装、拆卸再组装、拆卸的弊病,使作业面始终保持在第一层面上,使标准层的施工连续作业成为可能。

Description

钢筋混凝土建筑物的主体工程施工方法
技术领域
本发明涉及建筑物的施工方法,特别是建筑物主体含现浇钢筋混凝土及预制构件的施工方法。
背景技术
钢筋混凝土建筑物施工一般有现场浇注和预制装配两种施工方法。预制装配施工近年来发展了很多的先进技术,虽然预制装配比现场浇注机械化程度高,工业生产特征明显,但由于目前装配式钢筋混凝土结构的干式节点连接可靠性较差等缺点,使预制装配式的整体性(如抗震性能)受影响,应用受到限制。现今绝大部分钢筋混凝土建筑物为现场浇注施工方法。提高现场浇注施工方法的工业化程度又有一个很大的瓶颈,现有现场浇注施工均是从第一层开始到最高层的顺层施工,顺层施工由于施工作业的设备和周转材料在本层完成后进入下一层作业面时必将面对已经完工的楼板障碍——所以作业面上的设备、周转材料每层都要组装、拆卸,再组装、拆卸,而且是越来越往高空延伸,难度越来越大。所以在作业面上采用更高的机械化装备就变得不经济而且不可行。建筑施工行业作业手段的原始性、作业环境恶劣性、生产作坊性等弊病长期以来得不到根本的克服,使现场浇注建筑的工业化水平难以提高。
发明内容
本发明是为避免上述现有技术所存在的不足之处,提供一种钢筋混凝土建筑物的主体工程施工方法,结合现场浇注和预制装配的优点,使得可以在建筑工地形成工业化生产的流水线作业,以解决预制装配干式节点连接和现场浇注施工的机械化水平低、劳动力消耗大、劳动条件恶劣、手工劳动产品质量波动大等弊病。
本发明为解决技术问题提供如下技术方案
本发明钢筋混凝土建筑物的主体工程施工方法的特点是在已完工的永久基础上设置顶升机构及项升平台,首先在所述顶升机构及顶升平台上施工顶层框架,然后依靠顶升机构对所述顶层框架实施顶升,再在原有位置的顶升机构及顶升平台上施工次高层框架,同时完成顶层框架与次高层框架之间的永久连接;随后,再依靠顶升机构对所述顶层框架及次高层框架实施顶升,如此重复施工,直至地面一层,完成从最高层到地面一层的逆向逐层施工。
本发明钢筋混凝土建筑物的主体工程施工方法的特点也在于所述逆向逐层施工的顺序为:
a、在已完工的永久基础上设置顶升机构及顶升平台;
b、在顶升机构和顶升平台之间施工顶层竖向构件,在顶升平台上施工屋面板,形成顶层构架;
c、顶升机构以顶升平台为支承,将已经形成的顶层构架顶升一个层高,空出次高层的施工位置;
d、在顶升机构之间施工次高层竖向构件,在次高层竖向构件与顶层竖向构件之间形成固定连接;
e、顶升平台下降复位,在顶升平台上施工顶层楼板,形成次高层构架;
f、循环以上步骤c、d、e,直到在第一层竖向构件上完成第一层构架;
g、将第一层竖向构件与永久基础进行锚固。
本发明方法是将主体结构混凝土施工的顺序与传统方法颠倒后,先施工顶层,再逐层向下至第一层,克服了作业面上的设备、周转材料每层都要组装、拆卸再组装、拆卸的弊病,使作业面始终保持在第一层面上,从而能够在第一层空间中利用现场组装的机械设备形成工厂化组装车间,使标准层的施工连续作业成为可能,施工流水线能够形成。
与已有技术相比,本发明有益效果体现在:
1、本发明在永久基础以上的各标准层均是在地表层设置的组装车间的顶升平台上采用逐层施工、流水作业完成,形成流水线作业,极大地提高了施工作业的机械化程度和作业的标准化程度。
2、本发明中施工作业的设备不需要反复拆装,始终保持在地表层上,极大地简化了施工过程、减少施工成本、提高了施工速度。
3、本发明使用现浇施工结合预制装配,使建筑物质量稳定性更好。
4、本发明能够使建筑生产像流水线一样真正实现工业化生产,解决了建筑工业化在施工环节的难题,使提高建筑施工机械装备水平和经济性矛盾得以解决,使得将建筑物按其内在规律,把结构、功能、装饰等各类要求系统考虑,分解成各种总成,而各种总成在各个专业工厂提供的系统集成产品在现场整合装配的设计思路的具体实施能够获得实质性进展。
附图说明
图1、图2、图3、图4、图5、图6直至图7为本发明顶层和次高层施工过程示意图。
以下通过具体实施方式,并结合附图对本发明作进一步说明。
具体实施方式
参见图1,在已经完工的永久基础1的地表层平整场地,设置组装车间;要求组装车间含有必须能够承受整个建筑物施工荷载的顶升平台22和具有往复运动的顶升机构21。
施工顺序为:
1、图1所示,在已完工的永久基础上设置组装车间,包括顶升机构21及顶升平台22;
2、图2所示,在顶升机构21和顶升平台22之间施工顶层竖向构件3,顶层竖向构件3与顶升平台22临时加强连接,竖向构件3可能是立柱或剪力墙;
3、图3所示,在顶升平台22上施工屋面板4,形成顶层构架;
4、图4所示,在顶升机构21以顶升平台22为支承,将已经形成的顶层构架顶升一个层高,空出层高层的施工位置;
5、图5所示,在顶升机构21之间施工次高层竖向构件5;
6、图6所示,用型钢6在次高层竖向构件5与顶层竖向构件3之间进行竖向加固连接,使之成为一个受力的整体,以便承受建筑物的竖向荷载;解除顶层竖向构件3与顶升平台22之间的连接,使顶层竖向构件3和次高层竖向构件5独立承受荷载;顶升机构21反向工作,使顶升平台22下降复位,将顶升平台22与次高层竖向构件5临时加强连接,随后,在顶升平台22上施工顶层楼板7,形成次高层构架;
7、图7所示,在以上步骤4到步骤6之间循环,直到在第一层竖向构件上完成第一层构架;
8、将第一层竖向构件与永久基础进行锚固。
具体实施中,利用现有的计算机监控软硬件系统以及大吨位的液压顶升设备,例如专利号为200410011228的一种大负载任意位置机械锁定液压顶升机构,液压顶升机构的运动感应、监测和控制实施计算机控制,并设置误操作安全锁紧机制。
本发明方法是在地面层形成生产车间,实施流水作业,使建筑施工能够按照流水作业进行工业化生产,可以进一步将建筑物按其内在规律,将结构、功能、装饰等各类要求系统考虑,分别整合在各种部件中,部件在工厂完成预制,直接运输到现场组装车间进行组合。比如把有外装饰、防水保温、隔音、维护等功能整合到外墙部件;具有供水、供电、防水、橱柜等功能整合到厨房卫生间部件;隔断、隔音布线等功能整合到内墙部件,各部件在工厂内精确、高品质预制,运到现场组装车间内在固定位置组合到建筑物中。
具体实施中,相应的设置也包括:
1、顶升平台具有安全性和经济性。顶升平台的整体性及刚度的要求是方案安全顺利实施的保证;由于解决了作业面上的设备、周转材料每层都要组装、拆卸再组装、拆卸的难题,顶升平台一次性装配,多次使用,所投入的成本经多次摊销具有很好的经济性。
2、顶升平台的运动可控性。设置顶升平台在上升过程中只能往向上的一个方向运动,获得单向锁定;当局部出现问题时,通过局部锁定使整体不能提升;各液压顶升机构的速度和行程需要保持一致,实施行程锁定。
3、预制竖向构件。竖向构件是施工期间承受建筑荷载的构件,按照永久和临时相结合的原则设计,考虑临时支撑的强度和刚度,并考虑永久连接的整体性。
5、顶升平台与竖向构件的连接。由于在施工期间,建筑物的荷载由顶升平台和竖向构件传递至建筑物的永久基础,永久基础上要预留设施用以承接顶升平台和竖向构件传递来的荷载;同时顶升平台和竖向构件设置有方便连接和解除连接的设施用以方便荷载的传递和共同受力,以保证整体升降的稳定性。
6、预制装配和现场浇注。本发明中所有预制的结构构件均使用现浇连接组合成整体。

Claims (1)

1.一种钢筋混凝土建筑物的主体工程施工方法,是从最高层到地面一层的逆向逐层施工;其特征是所述逆向逐层施工的顺序为:
a、在已完工的永久基础(1)上设置顶升机构(21)及顶升平台(22);
b、在所述顶升机构(21)和顶升平台(22)之间施工顶层竖向构件(3),在所述顶升平台(22)上施工屋面板(4),形成顶层构架;
c、顶升机构(21)以顶升平台(22)为支承,将已经形成的顶层构架顶升一个层高,空出次高层的施工位置;
d、在所述顶升机构(21)之间施工次高层竖向构件(5),在所述次高层竖向构件(5)与顶层竖向构件(3)之间形成固定连接;
e、顶升平台(22)下降复位,在顶升平台(22)上施工顶层楼板(7),形成次高层构架;
f、循环以上步骤c、d、e,直到在第一层竖向构件上完成第一层构架;
g、将第一层竖向构件与永久基础进行锚固。
CN 200910116509 2009-04-10 2009-04-10 钢筋混凝土建筑物的主体工程施工方法 Active CN101538897B (zh)

Priority Applications (3)

Application Number Priority Date Filing Date Title
CN 200910116509 CN101538897B (zh) 2009-04-10 2009-04-10 钢筋混凝土建筑物的主体工程施工方法
PCT/CN2010/000473 WO2010115350A1 (zh) 2009-04-10 2010-04-09 钢筋混凝土建筑物的主体工程施工方法及房屋建造机
US13/263,740 US8863474B2 (en) 2009-04-10 2010-04-09 Main work construction method for reinforced concrete building and building construction machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200910116509 CN101538897B (zh) 2009-04-10 2009-04-10 钢筋混凝土建筑物的主体工程施工方法

Publications (2)

Publication Number Publication Date
CN101538897A CN101538897A (zh) 2009-09-23
CN101538897B true CN101538897B (zh) 2011-03-30

Family

ID=41122272

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200910116509 Active CN101538897B (zh) 2009-04-10 2009-04-10 钢筋混凝土建筑物的主体工程施工方法

Country Status (3)

Country Link
US (1) US8863474B2 (zh)
CN (1) CN101538897B (zh)
WO (1) WO2010115350A1 (zh)

Families Citing this family (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101538897B (zh) 2009-04-10 2011-03-30 袁斌 钢筋混凝土建筑物的主体工程施工方法
US8919058B2 (en) 2009-06-22 2014-12-30 Barnet L. Liberman Modular building system for constructing multi-story buildings
IT1406581B1 (it) * 2010-06-14 2014-02-28 Inco Srl Metodo per la costruzione di un edificio multipiano ed attrezzatura atta a realizzare tale metodo
CN102092642B (zh) * 2010-12-09 2012-09-05 中建二局第三建筑工程有限公司 筒体混合结构群塔附臂、顶升装置及其施工方法
US8590259B2 (en) * 2011-02-14 2013-11-26 Thomas Trinko Method of straightening foundational walls
AU2013204839B2 (en) * 2013-03-08 2015-07-09 Up First Construction Systems Pty Ltd Building System
US9556636B2 (en) 2014-06-27 2017-01-31 Tindall Corporation Method and apparatus for erecting tower with hydraulic cylinders
CN105275207A (zh) * 2015-02-11 2016-01-27 中建四局第三建筑工程有限公司 一种高层建筑外立面上下循环穿插施工方法
DE102015112974A1 (de) * 2015-08-06 2017-02-09 Sherpa Autodiagnostik Gmbh Antrieb für eine elektrohydraulische betriebene Hebeeinrichtung, insbesondere Hebebühne
JP7101077B2 (ja) * 2018-08-09 2022-07-14 大成建設株式会社 柱梁架構の構築方法
CN109779007A (zh) * 2019-03-11 2019-05-21 中建钢构有限公司 连廊安装方法及连廊
US10753080B1 (en) 2019-03-29 2020-08-25 Big Time Investment, Llc Method of constructing a building, and a building construction system therefor
US10829928B2 (en) * 2019-03-29 2020-11-10 Big Time Investment, Llc Floor plate assembly system and method of constructing a building therewith
CN110203857A (zh) * 2019-04-25 2019-09-06 东莞市华楠骏业机械制造有限公司 一种空中造楼机的平台升降装置
CN112112283A (zh) * 2019-06-19 2020-12-22 高继良 一种与装配式建筑物顶升施工方法相匹配的分层流水结构安装方法
CN111894276B (zh) * 2020-08-13 2021-05-04 通号建设集团第一工程有限公司 一种房屋建筑装配式楼板定点安装施工方法
CN113699890A (zh) * 2021-08-27 2021-11-26 上海市基础工程集团有限公司 桥梁预制拼装构件用临时支架标高自动补偿方法
CN113685042A (zh) * 2021-09-08 2021-11-23 中国建筑第八工程局有限公司 抽屉式自动卸料平台及其施工方法

Family Cites Families (46)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3017723A (en) * 1958-03-17 1962-01-23 Heidenstam Erik Johan Von Lift-slab construction of buildings
DE1138208B (de) * 1959-04-02 1962-10-18 Paul Plueckebaum Verfahren und Vorrichtung zum Einrichten von mehrgeschossigen, unterkellerten Gebaeuden
NL278769A (zh) * 1959-05-08
AT242325B (de) * 1960-05-07 1965-09-10 Erik Goesta Vilhelm Herolf Verfahren zur Errichtung von Gebäuden aus vorgefertigten Bauelementen
CH381408A (de) * 1960-05-17 1964-08-31 Waelli Ernst Verfahren und Einrichtung zum Erstellen eines mehrstöckigen Bauwerks
US3260028A (en) * 1963-07-22 1966-07-12 Fraser R Lee Method of constructing a building
US3275719A (en) * 1963-08-07 1966-09-27 Brian H Dudson Method of building in situ construction using sequential molding techniques
US3363393A (en) * 1963-11-08 1968-01-16 Heidenstam Erik Johan Von Method and equipment for erecting multi-storey building structures
US3362126A (en) * 1963-11-25 1968-01-09 Herolf Erik Gosta Vilhelm Method for guiding floors during their lifting
US3355853A (en) * 1965-02-23 1967-12-05 Intermountain Lift Slab Corp Method of building construction
GB1257705A (zh) * 1968-01-25 1971-12-22
US3579935A (en) * 1968-06-14 1971-05-25 James L Regan System for erecting multistorey buildings
US3594965A (en) * 1968-10-01 1971-07-27 Kolbjorn Saether Precast building construction
US3631648A (en) * 1970-01-23 1972-01-04 Stirling Homex Corp Method of erection of high-rise building structure formed of modular units
US3726053A (en) * 1970-07-13 1973-04-10 Stirling Homex Corp Method and apparatus for erecting modular high-rise building
US3722169A (en) * 1971-01-04 1973-03-27 R Boehmig Method of building construction
US3892055A (en) * 1971-01-27 1975-07-01 Torsten Nickolaus Ljung Method for manufacturing multi-story housing with floor-slabs, bearing walls and partitions cast on the ground level
US3692446A (en) 1971-02-11 1972-09-19 Research Corp Apparatus for forming and lifting multi-story columns in one story increments
US3831902A (en) * 1971-02-11 1974-08-27 Research Corp Method of erecting a multi-story building and apparatus therefor
US3828513A (en) * 1971-02-11 1974-08-13 Research Corp Method of erecting a multi-story building and apparatus therefor
SE338582B (zh) * 1971-04-29 1971-09-13 N Ahlgren
US3920780A (en) * 1972-08-09 1975-11-18 Research Corp Method of erecting a multi-story building and apparatus
US3921362A (en) * 1974-03-18 1975-11-25 Pablo Cortina Ortega Method of and means for multi-story building construction
US4251974A (en) * 1979-04-25 1981-02-24 Peter M. Vanderklaauw Sensing and control apparatus for lifting heavy construction elements
MX147576A (es) * 1980-12-03 1982-12-14 Innovaciones Tecnologicas Naci Mejoras en procedimiento de construccion de casas muros o similares
US5022199A (en) * 1988-09-05 1991-06-11 Ohbayashi Corporation Construction apparatus and construction method
US5319895A (en) * 1993-03-05 1994-06-14 Ray William W Activity floor changing system for multi-activity complex
US5575591A (en) * 1995-04-24 1996-11-19 Vanderklaauw; Peter M. Apparatus and method for a modular support and lifting system
JP2884402B2 (ja) * 1996-03-08 1999-04-19 鹿島建設株式会社 建物構造体の建築工法
US5839239A (en) * 1996-04-04 1998-11-24 Jang; Byung K. Apparatus and method for building construction
TW294749B (en) * 1996-06-28 1997-01-01 Vanguard Int Semiconduct Corp Method for setting supporting frame for elevated floor
CN1080801C (zh) * 1996-10-07 2002-03-13 邓庚厚 一种由上往下建造建筑物的顶升式建筑法
JPH11131811A (ja) 1997-11-04 1999-05-18 Sekisui House Ltd 建物の建築方法
US5970680A (en) * 1997-12-10 1999-10-26 Powers; James M. Air-lifted slab structure
US6260311B1 (en) * 1999-02-11 2001-07-17 Peter Vladikovic Concrete form suspension system and method
US20030079436A1 (en) * 2001-10-30 2003-05-01 Manfre Mark Thomas Lifting frame
CN1423020A (zh) 2001-12-06 2003-06-11 于君 多层建筑的施工方法及其专用的起重设备
CN100478813C (zh) 2005-12-22 2009-04-15 柳州欧维姆机械股份有限公司 一种液压提升监控系统及其在液压提升控制上的运用
US20080016805A1 (en) * 2006-07-19 2008-01-24 Richard Walter Truss lock floor systems and related methods and apparatus
JP5059357B2 (ja) * 2006-08-03 2012-10-24 株式会社日立プラントテクノロジー ボイラケージ部フロアの構築方法
CN1903698B (zh) * 2006-08-04 2011-07-20 长江三峡通航管理局 多点同步升降装置及其升降方法
BRPI1008509B1 (pt) * 2009-02-09 2019-10-15 3L-Innogénie Inc. Sistema de construção de edifícios de vários andares para construir progressivamente andares
CN101538897B (zh) 2009-04-10 2011-03-30 袁斌 钢筋混凝土建筑物的主体工程施工方法
WO2011155992A1 (en) * 2010-06-08 2011-12-15 Collins Arlan E Lift-slab construction system and method for constructing multi-story buildings using pre-manufactured structures
US8590259B2 (en) * 2011-02-14 2013-11-26 Thomas Trinko Method of straightening foundational walls
CN102733615B (zh) * 2012-07-12 2014-10-15 广州建筑股份有限公司 非对称整体提升施工方法

Also Published As

Publication number Publication date
US8863474B2 (en) 2014-10-21
CN101538897A (zh) 2009-09-23
US20120023840A1 (en) 2012-02-02
WO2010115350A1 (zh) 2010-10-14

Similar Documents

Publication Publication Date Title
CN101538897B (zh) 钢筋混凝土建筑物的主体工程施工方法
Banks et al. Enhancing high-rise residential construction through design for manufacture and assembly–a UK case study
CN101769008B (zh) 利用预制构造柱圈梁建造抗震砌体房屋的方法
CN203866966U (zh) 一种新型装配式框架核心筒钢结构住宅建筑体系
CN105863067A (zh) 一种模块化低层装配式异形柱钢结构房屋体系
CN103243838A (zh) 一种装配整体式混凝土框架-剪力墙连接结构
CN203213346U (zh) 一种装配整体式混凝土框架-剪力墙连接结构
CN105839784B (zh) 拼装顶升式建筑施工方法
CN106149868A (zh) 装配式房屋建筑结构体系及其装配方法
CN106351445A (zh) 一种劲性混凝土斜墙模板组合支撑加固系统及安装施工方法
CN102888894B (zh) 内筒外框式回形钢框架建筑的结构及施工方法
CN203394027U (zh) 半装配式框架剪力墙筒体结构施工体系
CN116145857A (zh) 钢-混凝土组合剪力墙结构的模块单元、建筑及建造方法
CN107818223A (zh) 地下车库屋盖上安装升降机承载力验算与施工方法
CN106869328A (zh) 一种吊挂式模块化建筑结构及其施工方法
CN205875520U (zh) 预制梁钢筋笼构件和钢筋混凝土梁
CN103334492A (zh) 一种预制装配式框架结构
CN203361332U (zh) 预制装配式框架结构
CN111021532A (zh) 一种装配式组合结构体系及其实施方法
CN106759933A (zh) 装配式rc框‑剪结构中预制柱‑叠合梁中间层中节点连接方法
CN106760139A (zh) 一种外贴式模块化建筑结构及其施工方法
CN1020645C (zh) 超高建筑模具外脚手整体升降系统
CN206554265U (zh) 一种吊挂式模块化建筑结构
CN106759882A (zh) 装配式rc框‑剪结构中预制柱‑叠合梁顶层边节点连接方法
CN106836473A (zh) 装配式rc框‑剪结构中预制柱‑叠合梁中间层边节点连接方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Yuan Bin

Inventor after: Niu Dianzhou

Inventor after: Zhang Xinning

Inventor after: Huang Huibin

Inventor after: Zhang Zhongyue

Inventor before: Yuan Bin

COR Change of bibliographic data
TR01 Transfer of patent right

Effective date of registration: 20160504

Address after: High tech Zone Hefei city Anhui province 230088 Tianzhi Road No. 17

Patentee after: Anhui Kaiyuan Highway and Bridge Co., Ltd.

Address before: 234000 Anhui province Suzhou City Yongqiao district near the River Road No. 27 in three to build thirty-three

Patentee before: Yuan Bin