CN100587165C - 装配式支架原位现浇制梁施工方法 - Google Patents

装配式支架原位现浇制梁施工方法 Download PDF

Info

Publication number
CN100587165C
CN100587165C CN200710057735A CN200710057735A CN100587165C CN 100587165 C CN100587165 C CN 100587165C CN 200710057735 A CN200710057735 A CN 200710057735A CN 200710057735 A CN200710057735 A CN 200710057735A CN 100587165 C CN100587165 C CN 100587165C
Authority
CN
China
Prior art keywords
adopts
military
construction method
mold
internal mold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN200710057735A
Other languages
English (en)
Other versions
CN101333801A (zh
Inventor
任少强
丁大有
马西章
颜健
褚红艳
周金红
李科
寥太昌
郭晓鹏
杨万仁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
the Electrification Engineering Co., Ltd. of CR 20 G
XI'AN ENGINEERING MACHINERY CO., LTD. OF CR20G
China Railway 20th Bureau Group Corp
Fifth Engineering Co Ltd of China Railway 20th Bureau Group Co Ltd
Firts Engineering Co Ltd of China Railway 20th Bureau Group Co Ltd
Original Assignee
China Railway 20th Bureau Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 20th Bureau Group Corp filed Critical China Railway 20th Bureau Group Corp
Priority to CN200710057735A priority Critical patent/CN100587165C/zh
Publication of CN101333801A publication Critical patent/CN101333801A/zh
Application granted granted Critical
Publication of CN100587165C publication Critical patent/CN100587165C/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

一种装配式支架原位现浇制梁施工方法,其特征是:地基用水泥挤密桩处理成复合式地基;支撑体系中的支墩采用贝雷架,纵向承载梁采用军用梁;箱梁模板由底模、外侧模、内模三大部分组合拼装组成;其中,底模采用大块平面钢模板组拼而成;外侧模采用轻型焊接钢结构,内模采用丝杠机械式收缩钢结构,分节段组拼而成,外侧模和内模均可沿设置在军用梁上的轨道滑移。本发明具有的优点是:1、复合地基承载力可达239KPa,满足中间支墩承载要求。2、装配式支架一套仅需370万左右,构件为常备品,安装方便。且侧模移动不受箱梁龄期限制,强度满足后,即可过孔。施工完后,装配式支架可作为龙门吊、架桥机、便桥等施工装备,可重复使用。

Description

装配式支架原位现浇制梁施工方法
技术领域:
本发明涉及一种大桥大吨位箱梁现浇法施工方法,特别涉及一种装配式支架原位现浇制梁施工方法。
背景技术:
铁路客运专线箱梁现浇法施工,主要的施工方法有移动模架法、支架法两种。移动模架投入大,一套需要600万左右,构件需要专门加工,运输拼装需大吨位吊机配合,同时受工况限制,不能任意调整孔跨。使用完后,设备重复利用率极低。
发明内容:
本发明的目的就在于提供一种装配式支架原位现浇制梁施工方法,该方法的施工成本低、安装方便、施工完毕后设备可重复使用使用。
本发明的技术方案是:一种装配式支架原位现浇制梁施工方法,包括地基处理、建造支撑体系、堆载预压、制造箱梁模板、绑扎钢筋、浇注混凝土工艺,其特征在于:地基用水泥挤密桩处理成复合式地基;支撑体系中的支墩采用贝雷架,纵向承载梁采用军用梁;箱梁模板由底模、外侧模、内模三大部分组合拼装组成;其中,底模采用大块平面钢模板组拼而成;外侧模采用轻型焊接钢结构,内模采用丝杠机械式收缩钢结构,分节段组拼而成,外侧模和内模均可沿设置在军用梁上的轨道滑移。
本发明还可以采用如下的技术措施:
上述军用梁采用加强型64式军用梁,贝雷架采用321钢桥(贝雷架)。
上述复合式地基采用夯扩挤密水泥土桩,其上浇筑顶面为10cm砂夹碎石垫层和50cm厚的C30钢筋砼形成复合式基础。
本发明具有如下的优点和积极效果:
1、由于地基处理采用夯扩挤密水泥土桩,其上浇筑顶面为10cm砂夹碎石垫层和50cm厚的C30钢筋砼形成复合式基础,因此,复合地基承载力239KPa,满足中间支墩承载要求。
2、装配式支架一套仅需370万左右,构件为常备品,安装方便。且侧模移动不受箱梁龄期限制,强度满足后,即可过孔。施工完后,装配式支架可作为龙门吊、架桥机、便桥等施工装备,可重复使用。
附图说明:
图1是模板的结构示意图。
图2是内模过孔流程图。
具体实施方式:
本发明在虎头村特大桥上的应用。
虎头村特大桥全长627.20m,为19-32m双线简支箱梁桥。基础为明扩大基础、挖井、桩基础三种型式;墩身全为等截面尺寸,有6×2m和6×2.6m两种,最高墩墩高为17.5m。梁结构尺寸为32.6×13×3.0m,底宽5.68m,截面形式为单箱单室等高简支箱梁,梁端腹板、底板局部向内侧加厚,在结构外侧的腹板与顶板相交处均采用圆弧倒角过度。地面表层为新黄土,具有湿陷性承载力为160Kpa;下层为老黄土,承载力为300Kpa。
1、地基处理
表层为新黄土和老黄土,下部岩层为角砾石和石灰岩,新黄土具有湿陷性承载力较低,老黄土承载力达到300Kpa。
根据计算,跨中支墩基础承受的荷载为6210KN,其承载力须达到123KPa以上。
为提高中间支墩基础承载力,控制沉降变形,跨中支墩基础采用夯扩挤密水泥土桩,采用直径40cm,间距80cm,梅花型布置,复合地基承载力239KPa,满足中间支墩承载要求。
挤密桩顶面为10cm厚碎石垫层和50cm厚钢筋混凝土;承台四周,底部用砂夹碎石回填夯实,其上浇筑30cm厚混凝土。
2、构建支撑体系:
根据本桥桥址的地形条件和箱梁的结构特点及荷载分布情况,每孔采用16m、12m跨度各10榀军用梁和贝雷梁作为现浇箱梁的支撑体系,梁为加强型六四式军用梁,支墩为贝雷梁。本桥军用梁布置参数如下:主箱下采用6榀,两侧翼缘下各用2榀搭设;每孔梁支架中间加设一个贝雷梁支墩,军用梁均采用简支形式。其安装均用吊车吊装,人工配合。
基础处理施工完毕后,首先安装贝雷梁底座板,将底层基础预埋螺栓与底座板锚固,然后安装底层贝雷梁,并及时安装水平拉撑,安装斜拉撑,完成后安装上一层贝雷梁,继续安装斜拉撑,依次顺序直至完成整个支墩,最后安装顶层垫梁及砂箱。安装时,中间支墩每隔3m用[10联结槽钢在水平方向联结成一个整体;墩柱处利用墩柱拉模筋将贝雷梁支墩固定,墩柱外侧贝雷梁采用10号槽钢联接成为整体,增加支墩的稳定性。
主梁安装采用一台25吨吊车吊装,单片依次安装。安装顺序为先从内向外,每安装好一片主桁立即临时锚固主桁,待全部主桁吊装到位后立即用联结系槽钢将主桁连接成整体。
3、堆载预压:
军用梁和贝雷架搭设完毕后为验证地基承载力、沉降、稳定性是否符合地基设计计算,同时检查支架系统的稳定性。消除支架系统的非弹性变形,观测出变形值,作为施工预留沉降量的一部分,对首孔整套支架系统进行堆载预压。
采用等载预压重量,同时考虑一定的安全储备:堆载总重量1025.6t。
4、制造箱梁模板:
箱梁模板采用自行设计的定型钢模。分为:底模1、外侧模2、内模3三大部分。底模采用大块平面钢模板组拼而成;侧模采用轻型焊接钢结构,分块沿轨道滑移式前行,每块长2.4米,可人工快速滑移;内模采用丝杠机械式收缩钢结构,分节段组拼而成,人工操作安装滑移。整套模板在支架上人工滑移过孔,技术先进,操作灵活方便,无需大型吊装设备。
模板的安装过程如下:(如图1所示)
1、底模安装:
底模分段运输进场,吊车吊装在军用梁4钢枕上,并用螺栓使之联结牢固,与底模钢枕处用楔块嵌紧,并固定牢固。底模拼接时注意保证各段的中心线放在同一直线上。底模根据预压观测结果设置反拱,在放置钢筋骨架之前,必须对底模进行调整,使之符合要求。
2、外侧模安装:
安装外侧模时,通过吊车将外侧模运送到与底模相对应的地方,利用千斤顶和砂箱调整外侧模高度,用滚杠和千斤顶调整模板横向位置,用螺栓将外侧模与底模连接成一个整体。
3、内模安装:
先把内模各部分组装成一体。在现浇梁外场地将内模支承桁架和顶模、侧模分节段组装,各部件均用销轴和螺栓联结牢固,并涂刷脱模剂。底腹板钢筋和模板组装完毕后,用25吨吊车把内模吊装于预设轨道上,再检查整体外形尺寸和模板相对位置是否正确,各支承丝杠是否松动,确保支承牢靠,最后将各节段之间采用螺栓连接。内模安装利用300×300mm的混凝土预制柱支撑并固定在底模上。
模板的拆卸过程如下:
梁体混凝土浇筑完毕后,在混凝土强度达到设计强度的85%时,可卸落内模、外侧模及拆除端模。
(1)端头模拆卸:
端头模板拆除先用4个脱模器将模板同步地向外拉开约50mm,然后用吊车将其吊出。严禁用倒链或其它动力将模板不同步地强行拉开,以防损坏梁体混凝土边角。
(2)外模过孔:
外侧模拆除时,松开螺栓,千斤顶预顶,退掉楔木,松落千斤顶,侧模至于横移装置上,外侧模横移至滑移轨道(设置在军用梁上的纵向工字钢)上时,千斤顶顶起外模,去掉横移装置,落外模至轨道上向前移动至下一孔就位。
(3)内模过孔依照下列步骤进行:(如图2所示)
①拆去所有的横向支撑;
②铺设枕木和轨道;
③引导小车调整千斤顶;
④拆去下角模与侧板;
⑤旋转调节支撑螺杆;
⑥拆去调节支撑螺杆;
⑦旋空调节支撑螺杆;
⑧拆去顶板立柱;
⑨最后人工将模板通移动小车移出梁体,移至下一跨就位。
(4)底模拆除
砂箱回落,军用梁和底模一起回落,同梁体分开,将底模依次拉出,吊车吊放在平板车上,运至下一跨吊车吊放就位。
5、绑扎钢筋:
在钢筋绑扎场地内的定型模具上分节段绑扎底板及腹板钢筋,再在模架上绑扎翼缘板钢筋,用简易运输板车将钢筋骨架运至箱梁现场用吊车及人工配合,将其吊放在箱梁模板的即定位置进行连接成整体。并按照要求安装好波纹管、锚垫板、螺旋筋和其他预埋钢筋等。
6、浇筑混凝土:
箱梁混凝土采用2台HZS120型强制式拌合机集中拌制,混凝土输送车运输,输送泵泵送至梁,两端各一台布料机均匀分料入模,一次成型,以插入式振捣器振捣。
混凝土浇注顺序为先腹板后再底板最后顶板。
7、预应力张拉及孔道压浆:
张拉设备采用特制250T和400T千斤顶,千斤顶外形长度28cm,能满足梁端窄小作业空间的要求。孔道压浆采用真空压浆工艺。

Claims (3)

1、一种装配式支架原位现浇制梁施工方法,包括地基处理、建造支撑体系、堆载预压、制造箱梁模板、绑扎钢筋、浇注混凝土工艺,其特征在于:地基用水泥挤密桩处理成复合式地基;支撑体系中的支墩采用贝雷架,纵向承载梁采用军用梁;箱梁模板由底模、外侧模、内模三大部分组合拼装组成;其中,底模采用大块平面钢模板组拼而成;外侧模采用轻型焊接钢结构,内模采用丝杠机械式收缩钢结构,分节段组拼而成,外侧模和内模均可沿设置在军用梁上的轨道滑移。
2、根据权利要求1所述的装配式支架原位现浇制梁施工方法,其特征在于:上述军用梁采用加强型64式军用梁,贝雷架采用321钢桥贝雷架。
3、根据权利要求1所述的装配式支架原位现浇制梁施工方法,上述复合式地基采用夯扩挤密水泥土桩,其上浇筑顶面为10cm砂夹碎石垫层和50cm厚的C30钢筋砼形成复合式基础。
CN200710057735A 2007-06-25 2007-06-25 装配式支架原位现浇制梁施工方法 Active CN100587165C (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200710057735A CN100587165C (zh) 2007-06-25 2007-06-25 装配式支架原位现浇制梁施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200710057735A CN100587165C (zh) 2007-06-25 2007-06-25 装配式支架原位现浇制梁施工方法

Publications (2)

Publication Number Publication Date
CN101333801A CN101333801A (zh) 2008-12-31
CN100587165C true CN100587165C (zh) 2010-02-03

Family

ID=40196653

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200710057735A Active CN100587165C (zh) 2007-06-25 2007-06-25 装配式支架原位现浇制梁施工方法

Country Status (1)

Country Link
CN (1) CN100587165C (zh)

Families Citing this family (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101672014B (zh) * 2009-08-27 2011-12-28 孙广喜 挂篮内模起落梁式滑移系统
CN101793006B (zh) * 2009-12-23 2011-06-22 中铁大桥局集团第一工程有限公司 一种支架现浇连续梁快速施工的施工方法
CN101974885B (zh) * 2010-10-26 2011-10-19 中交一航局第四工程有限公司 铁路连续箱梁多坡面加高平台混凝土一次成型的施工方法
CN102031756A (zh) * 2010-12-01 2011-04-27 中建五局土木工程有限公司 现浇箱梁的支撑组件及现浇箱梁的施工方法
CN102134833B (zh) * 2011-02-21 2012-09-05 中国一冶集团有限公司 贝雷架吊装拆除的施工方法
CN102229196B (zh) * 2011-04-19 2012-10-10 中铁二十四局集团有限公司 用于桥梁施工的整体钢筋预绑胎模施工方法
CN102198695B (zh) * 2011-04-19 2012-11-14 中铁二十四局集团有限公司 箱梁外模之外侧模的纵向移动方法
CN102121233A (zh) * 2011-04-20 2011-07-13 天津第三市政公路工程有限公司 一种桥梁现浇箱梁施工方法
US10195764B2 (en) * 2012-03-09 2019-02-05 Halliburton Energy Services, Inc. Set-delayed cement compositions comprising pumice and associated methods
CN102587283B (zh) * 2012-03-14 2014-11-26 中国十九冶集团有限公司 一种现浇混凝土桥梁的现浇施工方法
CN103382702B (zh) * 2013-07-11 2016-03-30 中国建筑第六工程局有限公司 一种现浇箱梁的支架及其搭建方法
CN103485284A (zh) * 2013-09-30 2014-01-01 上海建工七建集团有限公司 一种用于桥梁支架预压的高空注水堆载系统
CN103696440A (zh) * 2013-11-29 2014-04-02 中交第二航务工程局有限公司 可移动式钢筋笼绑扎胎架
CN103692550B (zh) * 2013-11-29 2016-06-29 中交第四航务工程局有限公司 一种海底隧道沉管的浇筑方法
CN106120563B (zh) * 2016-07-14 2017-09-08 德州市公路工程总公司 基于复合式移动模架现浇箱梁的施工方法
CN106884437A (zh) * 2017-02-28 2017-06-23 中国十七冶集团有限公司 用于地下管廊的自动收缩移动式内模板系统及使用方法
CN106978860A (zh) * 2017-05-26 2017-07-25 河南鑫型建筑科技有限公司 一种抗震房屋施工方法
CN107053437A (zh) * 2017-06-23 2017-08-18 安徽奥发高铁桥梁模板有限公司 一种智能转轴式高铁箱梁外侧模板
CN107558351A (zh) * 2017-09-30 2018-01-09 深圳市市政设计研究院有限公司 腹包底梯形(波形)钢板组合箱梁及其施工方法
CN107794845B (zh) * 2017-11-28 2024-03-15 中铁建大桥工程局集团第六工程有限公司 一种现浇梁用钢结构支架整体横移装置及方法
CN108660930B (zh) * 2018-04-28 2020-06-23 中交一航局第一工程有限公司 一种底模板整体吊装方法
CN109629437A (zh) * 2019-01-11 2019-04-16 中国铁建大桥工程局集团有限公司 一种箱梁移动式整孔现浇设备及其使用方法
CN110847052B (zh) * 2019-11-28 2021-09-14 湖北省路桥集团有限公司 多孔大断面现浇箱梁及施工方法
CN113529586B (zh) * 2021-08-25 2022-11-18 南通路桥工程有限公司 一种箱梁支撑体系及施工方法
CN114645515B (zh) * 2022-03-24 2024-04-12 中国建筑土木建设有限公司 混凝土节段箱梁的浇筑设备及其浇筑方法
CN114775450B (zh) * 2022-06-20 2022-09-09 山西临汾市政工程集团股份有限公司 用于钢箱梁的建筑辅助模板

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
斜拉钢桁架高支模施工技术. 童敏杰,郭正兴.中国建筑金属结构,第35卷第2期. 2005
斜拉钢桁架高支模施工技术. 童敏杰,郭正兴.中国建筑金属结构,第35卷第2期. 2005 *
软土地基上大跨度预应力混凝土现浇连续箱梁的设计与施工. 唐国胜,金峰.地下工程与隧道,第3期. 2006
软土地基上大跨度预应力混凝土现浇连续箱梁的设计与施工. 唐国胜,金峰.地下工程与隧道,第3期. 2006 *

Also Published As

Publication number Publication date
CN101333801A (zh) 2008-12-31

Similar Documents

Publication Publication Date Title
CN100587165C (zh) 装配式支架原位现浇制梁施工方法
CN101230785B (zh) 大断面、多断面隧道衬砌施工方法
CN103485288B (zh) 一种穿越既有线的双层顶进涵施工工艺
CN101701439B (zh) 钢弹簧浮置板轨道钢筋笼轨排法施工工艺
CN104533456B (zh) 一种超大断面硐室钢筋混凝土模筑施工的方法
CN104878766B (zh) 一种长边坡护坡混凝土连续快速浇筑拉模体系及施工方法
CN106702910A (zh) 一种双塔双索面矮塔斜拉桥的主梁施工工艺
CN102704949A (zh) 地下隧道无拉杆侧墙施工方法及施工用模板台车
CN101125441A (zh) 后张法预应力混凝土箱梁整孔预制施工方法
CN100464026C (zh) 铁路既有线桥梁连续顶推框架法换梁施工方法
CN205025086U (zh) 一种劲性骨架混凝土梁施工的悬吊模板
CN202596743U (zh) 地下隧道无拉杆侧墙施工用模板台车
CN102031756A (zh) 现浇箱梁的支撑组件及现浇箱梁的施工方法
CN107905114A (zh) 一种特大跨径连续刚构拱桥的施工方法
CN104532754B (zh) 一种预应力混凝土箱梁封端模板施工方法
CN113152306B (zh) 小半径大坡度预制t梁架设施工方法
KR100891961B1 (ko) 가설구조물을 이용하여 도로 또는 철도의 노후된 교량이나 무도상 교량을 유도상화 하기 위한 교량 교체공법 및 그 장치
CN106930315B (zh) 一种移动塔吊基础结构及施工方法
CN110904969A (zh) 一种高陡边坡板廊结构混凝土浇筑滑模系统
CN102797223B (zh) 海塘区客运专线膺架法现浇道岔连续梁施工方法
CN102286932B (zh) 移动模架桥台后方拼装自行上桥施工方法
CN106988339A (zh) 砂砾层管廊施工工艺
CN204690763U (zh) 长边坡护坡混凝土连续快速浇筑拉模体系
CN103382702B (zh) 一种现浇箱梁的支架及其搭建方法
CN106480826B (zh) 单线箱梁墩顶现浇横移施工工法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: CHINA RAILWAY 20TH BUREAU GROUP CONSTRUCTION MACHI

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20100531

Address after: 710016 Shaanxi province Xi'an City Taihua Road No. 89

Co-patentee after: XI'AN ENGINEERING MACHINERY CO., LTD. OF CR20G

Patentee after: China Railway 20th Bureau Group Co., Ltd.

Co-patentee after: the Electrification Engineering Co., Ltd. of CR 20 G

Co-patentee after: CR20BG No.1 Engineering Co., Ltd.

Co-patentee after: China Railway 20th Group Co., Ltd.

Co-patentee after: China Railway 20th Bureau Group Co., Ltd.

Co-patentee after: China Railway 20 Bureau Group Co., Ltd.

Co-patentee after: No.5 Engineering Co., Ltd. of China Railway Construction 20 Bureau Group

Co-patentee after: CR20BG No.1 Engineering Co., Ltd.

Address before: 710016 Shaanxi province Xi'an City Taihua Road No. 89

Patentee before: China Railway 20th Bureau Group Co., Ltd.