WO2024007203A1 - New superstructure for high-piled wharf, and construction apparatus and construction method therefor - Google Patents

New superstructure for high-piled wharf, and construction apparatus and construction method therefor Download PDF

Info

Publication number
WO2024007203A1
WO2024007203A1 PCT/CN2022/104172 CN2022104172W WO2024007203A1 WO 2024007203 A1 WO2024007203 A1 WO 2024007203A1 CN 2022104172 W CN2022104172 W CN 2022104172W WO 2024007203 A1 WO2024007203 A1 WO 2024007203A1
Authority
WO
WIPO (PCT)
Prior art keywords
construction
pile
prefabricated
construction platform
beams
Prior art date
Application number
PCT/CN2022/104172
Other languages
French (fr)
Chinese (zh)
Inventor
张永涛
冯先导
林红星
刘聪聪
何聪
沈立龙
骆钊
杨汉彬
黄睿奕
赵东梁
王聪
仇正中
高宁波
韩鹏鹏
陈迪郁
巫兴发
施少治
程荣君
林绍锋
陈周俊
Original Assignee
中交第二航务工程局有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中交第二航务工程局有限公司 filed Critical 中交第二航务工程局有限公司
Priority to CN202280002361.2A priority Critical patent/CN115362292B/en
Priority to PCT/CN2022/104172 priority patent/WO2024007203A1/en
Priority to IL303559A priority patent/IL303559A/en
Publication of WO2024007203A1 publication Critical patent/WO2024007203A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/06Placing concrete under water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/16Foundations formed of separate piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/28Prefabricated piles made of steel or other metals
    • E02D5/285Prefabricated piles made of steel or other metals tubular, e.g. prefabricated from sheet pile elements
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Definitions

  • the invention relates to the technical field of high pile wharf construction. More specifically, the present invention relates to a new superstructure of a high pile wharf and its construction equipment and construction methods.
  • the main structure of the "pile cap type" high pile wharf includes pile foundation, pile core, pile cap, prefabricated beams, prefabricated panels and other components. It is currently widely used because its structure is easy to assemble. However, the traditional superstructure and construction equipment, construction Problems caused by technology have become increasingly prominent. The structural type, construction equipment and construction technology of traditional high-pile wharfs have greatly affected the construction progress, quality, cost and safety of high-pile wharfs.
  • Pile cores and pile caps are usually located in areas where tide levels change. Traditional construction techniques are cast-in-place operations on the water. Pile core construction includes water pumping in steel pipe piles, lowering steel cages, concrete pouring, etc. Pile cap construction includes the erection of complex bottom form supports at the bottom. system, on-site lashing of steel bars, installation of formwork and larger amounts of concrete pouring. The above water construction is easily affected by wind, waves and tide levels, and the construction window is limited and the work efficiency is low; the steel bars located in the splash zone are prone to rust and the construction quality is poor; the water work volume is large and the safety risks are high.
  • the superstructure of the high pile wharf that is easy to assemble has many prefabricated components and requires frequent lifting operations.
  • traditional lifting equipment such as floating cranes, jacking platforms + lifting equipment, etc. are easily affected by waves and are constructed in harsh environments. The work efficiency is low and the operation window is small.
  • bridge erecting machines are used to convert water operations to land operations. However, for offshore wide platform terminals, the size of the bridge erecting machine is relatively large. If a floating crane or jacking platform + lifting equipment is used, the construction can only be completed first. The dock platform is half wide, and then switched to the other side to complete the construction of the remaining half. The construction period is long. If multiple pieces of equipment are used to operate at the same time, the construction cost is high and the economy is poor.
  • Another object of the present invention is to provide a new superstructure of a high-pile wharf and its construction equipment and construction methods, so as to solve the technical problems of difficult construction and low construction efficiency of the main structure of the high-pile wharf in the prior art.
  • a new superstructure of a high pile wharf is provided, which is arranged on the top of the pile foundation of the wharf, and each pile foundation includes two inclined piles or three inclined piles, The inner upper end of the steel pipe pile of each inclined pile is provided with a prefabricated pile core, including:
  • a hoop is placed close to the top of each inclined pile.
  • the upper surface of the hoop is connected to a bottom plate.
  • the bottom plate is set on the corresponding inclined pile.
  • the upper end of the prefabricated pile core is extended outward with a first steel bar;
  • the construction platform has a horizontal pile corresponding to each pile foundation and is connected to the upper surface of all bottom plates at the corresponding place.
  • Each inclined pile corresponding to the pile foundation on the construction platform is provided with a vertically connected and larger than steel pipe.
  • the holes of the piles are designed so that the tops of the steel pipe piles at the corresponding positions can penetrate, the top surface of the construction platform is flush with the top of the inclined piles, and node steel bars are provided on the construction platform;
  • the prefabricated beams are respectively arranged along the length direction of the pier or along the width direction of the pier.
  • a prefabricated beam is connected between the upper surfaces of each adjacent two construction platforms.
  • the two ends of the prefabricated beams are respectively extended outwards and provided with a second prefabricated beam.
  • the node is made of ultra-high performance concrete poured and set on the construction platform, and the first steel bar, the second steel bar, and the node steel bar are anchored and connected internally.
  • the pile foundations located on the outermost sides of the pier in the length direction each include three angled piles, and the remaining pile foundations each include two angled piles, corresponding to the pile foundations located on the pier.
  • Three of the holes are respectively provided on each of the construction platforms on the outermost two sides in the length direction, and two of the holes are respectively provided on the construction platforms at other positions.
  • the hoop includes a plurality of arc-shaped groove plates arranged around the outside of the inclined pile.
  • the inclined piles are connected with ear plates radially outward, and adjacent groove plates are fixedly connected by two ear plates on the same side.
  • Each ear plate is connected to the outside of the corresponding groove plate.
  • Stiffening plate, the bottom plate is assembled and connected by two connecting plates, and a semicircular arc-shaped groove is provided on the connecting plate corresponding to the steel pipe pile.
  • the node reinforcements include two sets of cross beam stirrup steel cages, two sets of longitudinal beam stirrup steel cages and one set of prefabricated node center area steel cages.
  • the cross beam stirrup steel cages are used to connect the cross beam stirrup steel cages arranged along the width direction of the wharf.
  • the prefabricated beams, the longitudinal beam stirrup steel cages are used to connect the prefabricated beams arranged along the length direction of the dock, the cross beam stirrup steel cages, and the longitudinal beam stirrup steel cages are all arranged with at least three layers of stirrups at intervals, each The layer stirrups are respectively connected to the second steel bars on the corresponding sides, and the first steel bars penetrate upward and are connected to the inside of the steel cage in the central area of the node.
  • the present invention provides a construction equipment for a new superstructure of a high pile wharf, including a support system, which includes a base structure, a rotary structure, a fixed support, a pair of main longitudinal beams, and a base structure connected upward in sequence.
  • the lower end is used to support multiple construction platforms.
  • the rotating structure can drive the fixed support to rotate freely in the horizontal direction relative to the base structure.
  • a pair of main longitudinal beams are opposite and parallel to each other.
  • the two ends of the fixed support are respectively connected with one main longitudinal beam.
  • the bottom of the beam is slidingly connected, and a pair of main longitudinal beams are slidingly connected to auxiliary beams between the tops of the two ends.
  • Each auxiliary beam is symmetrically provided with auxiliary legs that can be telescoped up and down for temporary support of the above-mentioned beams at corresponding positions.
  • one end of a pair of main longitudinal beams is equipped with a counterweight block;
  • Hoisting system which includes a main crossbeam slidably connected between the tops of a pair of main longitudinal beams, the main crossbeam being located between a fixed support and one of the auxiliary crossbeams and located on a different side of the fixed support from the counterweight block on the main crossbeam
  • a mobile crane is slidingly connected, and a spreader is installed on the mobile crane.
  • a moving space for the spreader is formed between a pair of main longitudinal beams, a fixed support, and an auxiliary beam on the side without a counterweight block, forming a lifting area. ;
  • the traveling system includes traveling mechanisms respectively arranged between the auxiliary beam and the main longitudinal beam, between the fixed support and the main longitudinal beam, and between the main beam and the main longitudinal beam.
  • the traveling mechanism is used to drive the corresponding connected auxiliary beams.
  • the crossbeam or fixed support or main crossbeam moves relative to the main longitudinal beam.
  • the base structure includes a horizontally arranged base bracket.
  • the top center of the base bracket is connected to the bottom of the rotary structure.
  • the bottom of the base bracket is arranged with adjustable supports along the four corners of the rectangle in the horizontal plane.
  • Position oil cylinder, the cylinder body of the position adjustment oil cylinder is fixed to the bottom of the base bracket, and the telescopic direction is set parallel to the diagonal direction of the rectangle.
  • the telescopic end of the position adjustment oil cylinder is fixed downward with a base leg, and the upper end of the base leg is in contact with the base bracket.
  • the bottom is slidingly connected, and the lower ends of the base legs are used to support and fix on the construction platform.
  • the present invention also provides a construction method of construction equipment for a new superstructure of a high pile wharf, which includes the following steps:
  • S1 Prefabricate the construction platform, the pile core, and the prefabricated beam.
  • the top of the pile core is connected to the first steel bar, and both ends of the prefabricated beam are connected to the second steel bar;
  • S4 Use grouting material to grout the gap between the steel pipe pile and the pile core underwater, and use fine stone concrete to grout the gap between the hole and the steel pipe pile;
  • the base structure is supported on the installed construction platform, and the rotating structure drives all the construction platforms.
  • the main longitudinal beam, the main beam, and the auxiliary beam are synchronously rotated above the prefabricated construction platform, the pile core, and the prefabricated beam, and the mobile crane is used to move the spreader for removal. material, and then use the rotary structure to rotate to the position to be installed for lowering and installation.
  • the walking mechanism drives the auxiliary beam to move to the installed position.
  • the walking mechanism drives the main longitudinal beam to move along the length direction, driving the base structure to move to the next construction platform, retracting the auxiliary legs, and re-supporting the base structure on all the lower parts.
  • the auxiliary beam is moved to the initial position through the walking structure of the auxiliary beam on the main longitudinal beam to complete the over-span forward movement of the base structure, and then the aforementioned operation is repeated.
  • the rotary structure drives the mobile crane and the spreader to retrieve materials and lower them for installation until all the construction platforms, pile cores, and prefabricated beams of the entire wharf are hoisted.
  • the distance between the counterweight block and the base structure covers one of the construction platforms in the length direction of the pier, and the The movement range of the main beam between the base structure and the corresponding end of the main longitudinal beam covers 2 of the construction platforms, and the base structure spans 2 to 3 adjacent construction platforms;
  • the mobile crane can move along the length direction of the main beams, and the base structure covers 2 ⁇ 3 adjacent construction platforms.
  • A1 Use one corner edge of the pier as the starting construction location, and set up a storage area or dock a transport ship according to the position of the pile foundation to store the prefabricated construction platform, pile core, prefabricated beams, and prefabricated panels.
  • the construction platform should be located at the pier.
  • the same length direction is one row, and the same width direction at the dock is one row.
  • A2 Use the rotary structure to drive the spreader to rotate to the adjacent storage area or dock the transport ship to retrieve materials, and then rotate the rotary structure to drive the spreader to the starting construction position, which is located in the length direction of the dock and is not yet under construction.
  • the main longitudinal beam is parallel to the length direction of the wharf, and then the construction platform, pile core and prefabricated beam located in the hoisting area are lowered and installed;
  • A3 Use the slewing structure to continue rotating 90° to drive the spreader to the starting construction position on the unconstruction side in the width direction of the pier. At this time, the main longitudinal beam is parallel to the width direction of the pier, and then lower it for installation. Construction platforms, pile cores, and prefabricated beams located in the hoisting area;
  • A4 Use the auxiliary beam, the auxiliary leg and the walking system to move the base structure forward by one unit of the length of the hoisting area along the width direction of the pier away from the starting construction position.
  • the above-mentioned revolving structure is rotated 180° so that the hoisting area is above the starting construction position, and all prefabricated beams at the starting construction position are supplementally installed;
  • A5 Use the slewing structure to rotate 90° so that the hoisting area is located on the non-construction side of the length of the pier. Hoist the construction platform, pile cores and prefabricated beams, and then move the base structure across the front span along the length of the pier. Move one unit of length of the hoisting area. At this point, the installation of all rows of construction platforms, pile cores, and prefabricated beams whose starting construction position is located in one unit of length of the hoisting area is completed;
  • A6 Hoist the construction platform, pile core and prefabricated beams on the pile foundation in the hoisting area after the span has been moved forward, rotate the rotary structure, and supplementary installation of the prefabricated beams located in the width direction of the base structure in the dock, at the same time , install the prefabricated panels located on the constructed side of the base structure in the width direction of the pier;
  • A7 Utilize the auxiliary beam, the auxiliary leg and the walking system to gradually move the base structure forward to the top along the width direction of the pier towards the starting construction position. At the same time, each span is Move forward and use the rotary structure to cooperate and install the construction platform, pile core, prefabricated beams and prefabricated panels on the constructed side of the base structure in the length direction of the wharf;
  • A8 Repeatedly drive the construction equipment to move along the width direction, length direction, and width direction of the pier on the unconstructed side, and cooperate with the rotation of the slewing structure and the lifting of the spreader to complete the construction platform of the entire pier. , pile cores, prefabricated beams, and prefabricated panels to complete the integrated installation of the new superstructure of the high-pile wharf.
  • the present invention replaces the traditional pile cap structure by sequentially arranging hoops, bottom plates, and construction platforms on top of piles, and pours nodes on the construction platform to connect the pile core at the bottom and the prefabricated beam structure in the horizontal direction, avoiding the need for steel Water-based cast-in-place operations such as pumping water inside pipe piles, tying pile cap steel bars, installing formwork, and concrete pouring of pile cores and pile caps reduce the impact of waves and tidal range on the construction window and the corrosion of steel bars by sea water. Under the condition of no pile cap , the first steel bar is reserved in the pile core to extend into the upper node to directly transfer the load, which improves the load-bearing performance of the pile top structure.
  • the construction platform set up in the present invention can be used as a platform for supporting and walking construction equipment, as well as an installation and resting platform for prefabricated pile cores and prefabricated beams.
  • the construction equipment is used to cycle the construction of the construction platform, pile cores, and prefabricated beams, and the newly installed
  • the construction platform serves as the support platform for the next step of construction, so that the construction equipment on the construction platform is not affected by waves and currents.
  • the operation window is increased, the positioning and installation accuracy is high, the construction quality is improved, and the traditional pile cap structure is avoided.
  • the interference of steel bars on the support and walking of construction equipment avoids the overall need to set up a complex steel support system on the water, improves construction efficiency and reduces safety risks.
  • the node steel bars of the present invention are tied and formed in advance in the precast factory, quickly assembled and constructed on site, and anchored and connected by ultra-high performance concrete.
  • the connection form of the pile top structure is optimized, which avoids welding operations in restricted spaces, reduces construction costs, and improves construction quality.
  • the construction equipment of the present invention realizes the main longitudinal beam to rotate 360° relative to the base structure through the rotation structure, so that the spreader can move along the length and width directions of the pier for all-round construction, which is flexible and convenient, with high operating efficiency and low construction cost. , especially for offshore wide-platform wharves, it can greatly reduce the cost of ship machinery and equipment and solve the construction problem of ship machinery and equipment being unable to cover the entire width of the wharf from one side.
  • the present invention forms a new fully assembled superstructure of a high-pile wharf through the design of prefabricated pile cores and construction platforms, componentized node steel bars, and ultra-high-performance concrete anchor connections. It is supported on the construction platform and equipped with a wharf. Hoisting equipment with horizontal and vertical self-propelled and rotary functions performs continuous operations, realizing the fully assembled design and construction of high pile wharf suitable for combined inclined piles.
  • Figure 1 is a schematic structural diagram of the top of a single inclined pile according to the present invention.
  • Figure 2 is a schematic structural diagram of the top of the pile foundation of the present invention.
  • Figure 3 is a schematic structural diagram of the node steel bar of the present invention.
  • Figure 3 is a structural schematic diagram of the new superstructure of the high pile wharf of the present invention.
  • Figure 4 is a front structural view of the construction equipment of the present invention.
  • Figure 5 is a side structural view of the construction equipment of the present invention.
  • Figure 6 is an enlarged side structural view of the main longitudinal beam of the present invention.
  • Figure 7 is a schematic plan view of the construction equipment of the present invention installed at the starting position of construction
  • Figure 8 is a schematic diagram of the planar structure corresponding to step A1 when constructing using construction equipment according to the present invention.
  • Figure 9 is a schematic diagram of the planar structure corresponding to step A2 when constructing using construction equipment according to the present invention.
  • Figure 10 is a schematic diagram of the planar structure corresponding to step A3 when constructing using construction equipment according to the present invention.
  • Figure 11 is a schematic diagram of the planar structure corresponding to step A4 when constructing using construction equipment according to the present invention.
  • Figure 12 is a schematic plan view corresponding to the first step of step A5 when constructing using construction equipment according to the present invention.
  • Figure 13 is a schematic diagram of the planar structure corresponding to the second step of step A5 when constructing using construction equipment according to the present invention
  • Figure 14 is a schematic diagram of the planar structure corresponding to step A6 when constructing using construction equipment according to the present invention.
  • Figure 15 is a schematic diagram of the planar structure corresponding to step A7 when constructing using construction equipment according to the present invention.
  • the present invention provides a new superstructure of a high pile wharf, which is arranged on the top of the pile foundation of the wharf.
  • the pile foundations are arranged in a rectangular array along the construction surface of the wharf.
  • Each pile foundation includes two inclined Pile or three inclined piles, each inclined pile is provided with a prefabricated pile core 2 at the inner upper end of the steel pipe pile 1, including:
  • a hoop 4 is tightly held near the top of each inclined pile.
  • the upper surface of the hoop 4 is connected to a bottom plate 3.
  • the bottom plate 3 is set on the corresponding inclined pile.
  • the upper end of the prefabricated pile core 2 extends outward. There is the first steel bar;
  • the construction platform 6 has a horizontal pile corresponding to each pile foundation and is connected to the upper surface of all bottom plates 3 at the corresponding place.
  • Each inclined pile corresponding to the pile foundation on the construction platform 6 is provided with a vertically connected and sized pile. It is larger than the hole 7 of the steel pipe pile 1, so that the top of the steel pipe pile 1 at the corresponding position can penetrate, the top surface of the construction platform 6 is flush with the top of the inclined pile, and the construction platform 6 is provided with node steel bars 11;
  • Prefabricated beams 8 and 9 are respectively arranged along the length direction of the dock head or along the width direction of the dock.
  • a prefabricated beam is connected between the upper surfaces of each two adjacent construction platforms 6, and the two ends of the prefabricated beams face outwards respectively.
  • the extension is provided with a second steel bar;
  • the node 10 is made of ultra-high performance concrete (UHPC) and is poured on the construction platform 6 and anchors the first steel bar, the second steel bar and the node steel bar 11 inside.
  • UHPC ultra-high performance concrete
  • the new connection structure on the top of the high-pile wharf piles is based on the combination of two inclined piles or three inclined piles on the pile foundation.
  • a simple hoop 4 and a bottom plate 3 are first installed on the top of the pile foundation, and then the connecting construction platform 6 is installed to provide prefabricated
  • the pile core 2 is installed and the prefabricated beam is installed to provide a resting platform.
  • the diameter of the hole 7 on the construction platform 6 is considered in conjunction with the slope of the steel pipe pile 1 and the maximum deflection of the steel pipe pile 1 of 150mm, so that the construction platform 6 can pass through the steel pipe pile 1 when installed.
  • the construction platform 6 serves as the construction site for the node 10, which can facilitate the erection of the formwork and node steel bars 11 at the node 10.
  • the node steel bars 11 can be tied and formed in the prefabricated factory in advance, and then quickly assembled on the construction platform 6 for construction. After setting the construction platform 6 in this way, it is generally avoided to pump water in the steel pipe pile 1, tie the pile cap steel bars, formwork installation, pile core 2, pile cap concrete pouring and other water cast-in-place operations, and reduce the impact of waves and tidal range. The influence of the construction window and the corrosion of steel bars by seawater.
  • the node 10 set by the pouring anchors the node steel bar 11, the first steel bar, and the second steel bar, optimizing the The connection form of the pile top structure avoids welding operations in a restricted space, reduces construction costs, and improves construction quality.
  • the first steel bar reserved at the upper end of the pile core 2 extends into the upper node 10 area, which can directly transfer the load and improve the construction quality. The load-bearing performance of the pile top structure.
  • the pile foundations located on the outermost two sides of the pier in the length direction each include three inclined piles, and the remaining pile foundations each include two
  • the inclined piles are respectively provided with three holes 7 on each of the construction platforms 6 located on the outermost sides of the length direction of the pier, and two holes 7 are respectively provided on the construction platforms 6 at other positions. Describe the hole 7.
  • the hoop 4 includes a plurality of arc-shaped groove plates arranged around the outside of the inclined pile, and the number of groove plates is at least four.
  • the two ends of each groove plate are respectively connected with ear plates outward along the radial direction of the inclined pile.
  • the adjacent groove plates are fixedly connected by two ear plates on the same side.
  • Each ear plate is connected to the corresponding ear plate.
  • Several stiffening plates 5 are connected between the outer sides of the groove plates.
  • the bottom plate 3 is assembled and connected by two connecting plates.
  • Semi-circular arc-shaped grooves are provided on the connecting plates corresponding to the steel pipe piles 1.
  • the length of the ear plate must be greater than the distance between the outside of the steel pipe pile 1 and the hole 7 of the reserved pile core 2 on the construction platform 6. Then the hoop 4 and the bottom plate 3 are fixedly connected, and rubber material is used to fill the bottom plate 3 and the steel pipe pile. 1, the hoop 4 is provided to support the bottom plate 3 and ensure the stability of the construction platform 6. The bottom plate 3 is provided to expand the resting area of the construction platform 6 and facilitate the installation of the construction platform 6. The stiffening plate 5 is provided to improve the ear plate. , the connection strength between grooved plates. By setting the bottom plate 3 as an assembled structure, the bottom plate 3 can be quickly assembled on the hoop 4, which facilitates prefabricated production and improves construction efficiency.
  • the node reinforcement 11 includes two sets of cross beam stirrup reinforcement cages 13, two sets of longitudinal beam stirrup reinforcement cages 14 and a set of node 10 center area reinforcement cages 12.
  • the cross beam The stirrup steel cage 13 is used to connect the prefabricated beams 8 arranged along the width direction of the pier
  • the longitudinal beam stirrup steel cage 14 is used to connect the prefabricated beams 9 arranged along the length direction of the pier
  • the cage 13 and the longitudinal beam stirrup steel cage 14 are arranged with at least three layers of stirrups at intervals. Each layer of stirrups is connected to the second steel bar on the corresponding side.
  • the first steel bar penetrates upward and is connected to the steel bar in the central area of the node 10.
  • the node steel bars 11 are set as multiple types of steel cages that can be prefabricated to facilitate rapid installation and construction.
  • the steel cages can be tied and formed in the prefabrication site and transported to the site by flatbed trucks. During installation, they are lifted as a whole.
  • the steel bars in the center area of node 10 Cage 12 serves as the main stress-bearing steel bar at node 10, including main bars and stirrups.
  • the first steel bar of pile core 2 extends into the main stress-bearing steel bar, and the cross-beam stirrup steel bar cage 13 and the longitudinal beam stirrup steel bars are provided.
  • the cage 14 is used to connect with the surrounding second steel bars of the prefabricated beams 8 and 9 arranged along the length direction of the pier and along the width direction of the pier, that is, a total of four directions.
  • the cross beam stirrup steel cage 13 and the longitudinal beam stirrup steel cage 14 The installation size is small, and at least 3 stirrups are arranged at intervals.
  • Anchor connection is used to realize the connection between the node 10, the prefabricated beams (8, 9) and the pile core 2.
  • the present invention also provides a new type of construction equipment for the superstructure of a high pile wharf, as shown in Figure 5-15, including:
  • the support system includes a base structure 21, a rotary structure 23, a fixed support 211, and a pair of main longitudinal beams 24 that are connected upward in sequence.
  • the lower end of the base structure 21 is used to support a plurality of the construction platforms 6.
  • the rotary structure 23 can drive the fixed support 211 to freely rotate in the horizontal direction relative to the base structure 21.
  • a pair of main longitudinal beams 24 are arranged opposite and parallel.
  • the two ends of the fixed support 211 are respectively slidingly connected to the bottom of one main longitudinal beam 24.
  • the longitudinal beams 24 are respectively slidably connected with auxiliary beams 27 between the tops of the two ends.
  • Each auxiliary beam 27 is symmetrically provided with auxiliary legs 28 that can telescope up and down for temporary support on the construction platform 6 at the corresponding position.
  • One end of a pair of main longitudinal beams 24 is provided with counterweights 29;
  • the hoisting system includes a main crossbeam 25 slidably connected between the tops of a pair of main longitudinal beams 24.
  • the main crossbeam 25 is located between a fixed support 211 and one of the auxiliary crossbeams 27 and is located on the fixed support 211 together with the counterweight 29.
  • a movable crane 26 is slidably connected, and a spreader 210 is provided on the movable crane 26.
  • the traveling system includes a traveling mechanism 212 respectively provided between the auxiliary cross beam 27 and the main longitudinal beam 24, between the fixed support 211 and the main longitudinal beam 24, and between the main cross beam 25 and the main longitudinal beam 24.
  • the traveling mechanism 212 is used to drive the corresponding connected auxiliary cross beam 27 or the fixed support 211 or the main cross beam 25 to move relative to the main longitudinal beam 24; the traveling mechanism 212 includes corresponding electrical and hydraulic systems, as well as a cooperating pulley structure.
  • the base structure 21 includes a horizontally arranged base bracket.
  • the top center of the base bracket is connected to the bottom of the rotating structure 23 .
  • the bottom of the base bracket is along the four corners of the rectangle in the horizontal plane.
  • the azimuth support is provided with an adjusting cylinder.
  • the cylinder body of the adjusting cylinder is fixed to the bottom of the base bracket and the telescopic direction is parallel to the diagonal direction of the rectangle.
  • the telescopic end of the adjusting cylinder is fixed with a base leg 22 downward.
  • the base The upper end of the support leg 22 is slidingly connected to the bottom of the base bracket, and the lower end of the base support leg 22 is used to support and be fixed on the construction platform 6 .
  • the position of the base leg 22 can be changed by telescopically adjusting the positioning cylinder, and can be adjusted according to the spacing between adjacent rows and columns of construction platforms 6/pile foundations, so that each base leg 22 can be stably supported on one construction platform 6, thereby improving Suitability of construction equipment.
  • the present invention also provides a construction method for the construction equipment of the new superstructure of the high pile wharf.
  • the steel pipe pile 1 is piled on the water.
  • the diameter of the pile foundation is 1200mm, specifically including the following steps:
  • S1 Prefabricate the construction platform 6, the pile core 2, and the prefabricated beams (8, 9).
  • the top of the pile core 2 is connected to the first steel bar, and the two sides of the prefabricated beams (8, 9) The end is connected to the second steel bar.
  • the diameter of the prefabricated pile core 2 is controlled according to the 80mm to 100mm gap between the pile core 2 and the inner wall of the steel pipe pile 1.
  • the construction platform 6 is divided into a combination of two inclined piles and a three inclined pile. The length, width and height of the prefabricated construction platform 6 of the two inclined pile combination are 6500mm respectively.
  • the prefabricated construction platform 6 of the three-incline pile combination is a profile structure, with a length, width and height of 7500mm ⁇ 5000mm ⁇ 800mm respectively.
  • the corresponding pile core 2 holes 7 are reserved in the middle of the construction platform 6, and the diameter of the holes 7 is according to the pile foundation. A maximum deviation of 150mm is considered.
  • S3 Install the construction platform 6 and the pile core 2, place the construction platform 6 on all the bottom plates 3 corresponding to the pile foundation, and penetrate the top of each steel pipe pile 1 upward. In one of the holes 7, control the deviation of the center of the circle so that the construction platform 6 is located at the center of the corresponding pile foundation, then set a bottom sealing plate 3 and a water-stop rubber ring at the bottom of the pile core 2, and lift the The pile core 2 is inserted into the corresponding steel pipe pile 1. After the installation of part of the construction platform is completed, the construction equipment is supported on the installed construction platform and the remaining construction is continued. Hoisting construction of platform and pile core.
  • the prefabricated pile core 2 can be fixed by anti-hanging the steel pipe pile 1 by setting circumferential pre-embedded hanging bars on the top.
  • the node steel bars 11 are manufactured into parts, and stirrups are provided for connecting the node steel bars 11 and the second steel bars of the prefabricated beams (8, 9).
  • the base structure 21 supports On the installed construction platform 6, the main longitudinal beam 24, the main cross beam 25 and the auxiliary cross beam 27 are driven to rotate synchronously through the rotating structure 23 to the prefabricated construction platform 6, the pile core 2, the prefabricated Above the beams (8, 9), the mobile crane 26 is used to move the spreader 210 to retrieve materials, and then the rotating structure 23 is used to rotate to the position to be installed for lowering and installation.
  • the auxiliary beam 27 is driven by the traveling mechanism 212 to move directly above the installed construction platform 6, and the auxiliary legs 28 are extended downward and supported on the corresponding construction platform 6, so that the bottom of the base structure 21 is detached.
  • the corresponding traveling mechanism 212 on the main longitudinal beam 24 drives the main longitudinal beam 24 to move along the length direction, driving the base structure 21 to move to the next construction platform 6, and retracting the auxiliary legs 28 , re-support the base structure 21 on the construction platform 6 below, and then move the auxiliary beam 27 on the main longitudinal beam 24 to the initial position through the walking structure of the auxiliary beam 27, completing the over-span forward movement of the base structure 21.
  • the rotating structure 23 can drive the fixed support 211 to rotate 360° relative to the base structure 21.
  • the base leg 22 is a component mainly supported on the construction platform 6, and the auxiliary leg 28 under the auxiliary beam 27 is a component temporarily supported on the construction platform 6.
  • the base structure 21 moves relative to the main longitudinal beam 24 together, or the auxiliary beam 27 and the auxiliary outrigger 28 move relative to the main longitudinal beam 24, so that the auxiliary beam 27 can adjust the auxiliary beam 27 or the auxiliary outrigger according to the setting interval of the construction platform 6
  • the position of 28 is convenient for the auxiliary leg 28 to be located directly above a construction platform 6, so that the base leg 22 and the auxiliary leg 28 are alternately supported on the construction platform 6 in the front and rear direction, realizing the over-span principle similar to that of a bridge erecting machine. By moving the span forward, the entire construction equipment can be moved along the length or width direction of the dock to carry out all-round construction.
  • the distance between a pair of main longitudinal beams 24 covers 2 to 3 construction platforms 6, and the mobile crane 26 can move along the length direction of the main beam 25.
  • the base structure 21 covers 2 to 3 adjacent construction platforms 6 .
  • the hoisting area is set to basically cover the length of 2-3 construction platforms 6 and cover at least 2-3 construction platforms.
  • the width of the platform 6 controls the overall frame size of the construction equipment within a reasonable range, which has both good economy and construction efficiency.
  • the base structure 21 and the base legs 22 provided at the bottom ensure that they can be symmetrically supported on four construction platforms. 6 is enough.
  • the hoisting area when constructing at each construction platform 6, the current hoisting area needs to be larger than the construction area required for a single construction platform 6. Therefore, when the hoisting area covers 2-3 construction platforms 6, It includes the width of the corresponding number of construction platforms 6 and the spacing between adjacent construction platforms 6 .
  • A1 As shown in Figure 8, take the top corner edge of the dock as the starting construction location, and set up a storage area or dock the transport ship according to the position of the pile foundation to store the prefabricated construction platform 6, pile core 2, prefabricated beams,
  • the prefabricated panels 15 and the construction platforms 6 are arranged in a row in the same length direction of the pier and in a row in the same width direction of the pier.
  • the base structure 21 is supported on four construction platforms 6, and is sequentially assembled upward to connect the remaining components of the support system, the hoisting system, and the walking system;
  • A2 As shown in Figure 9, use the rotating structure 23 to drive the spreader 210 to rotate to a nearby storage area or dock a transport ship to retrieve materials, and then rotate the rotating structure 23 to drive the spreader 210 to rotate to the lifting position.
  • the starting construction position is located on the non-construction side of the length direction of the pier.
  • the main longitudinal beam 24 is parallel to the length direction of the pier, and then the construction platform 6, pile core 2 and prefabricated beam located in the hoisting area are lowered and installed;
  • A3 As shown in Figure 10, use the rotating structure 23 to continue rotating 90° to drive the spreader 210 to move to the starting construction position on the unconstructed side in the width direction of the pier. At this time, the main longitudinal beam 24 and The width direction of the wharf is parallel, and then the construction platform 6, pile core 2 and prefabricated beam located in the hoisting area are lowered and installed;
  • the auxiliary beam 27, the auxiliary leg 28 and the walking system are used to move the base structure 21 forward along the width direction of the pier on the side away from the starting construction position.
  • the length unit of a hoisting area, and then the revolving structure 23 is rotated 180° so that the hoisting area is above the starting construction position, and all prefabricated beams at the starting construction position are supplemented and installed;
  • A5 As shown in Figure 12, use the slewing structure 23 to rotate 90° so that the hoisting area is located on the non-construction side of the length of the pier, and hoist the construction platform 6, pile core 2, and prefabricated beams, and then as shown in Figure 13 shows that the base structure 21 is moved forward by a unit of length of the hoisting area along the length direction of the pier. At this point, the construction platform 6, pile core 2, Installation of precast beams;
  • A6 As shown in Figure 14, hoist the construction platform 6, pile core 2, and prefabricated beams on the pile foundation in the hoisting area after the span has been moved forward, rotate the rotary structure 23, and additionally install the base structure 21 Precast beams in the width direction of the pier, and at the same time, install precast panels 15 on the side of the base structure 21 that has been constructed in the width direction of the pier;
  • the auxiliary beam 27, the auxiliary leg 28 and the walking system are used to gradually make the side of the base structure 21 toward the starting construction position along the width direction of the pier gradually pass the front of the span.
  • the rotating structure 23 is used to install the construction platform 6, the pile core 2, the prefabricated beam and the constructed one on the unconstructed side of the base structure 21 in the length direction of the pier each time the span is moved forward.
  • A8 Repeatedly drive the construction equipment to move along the width direction, length direction, and width direction of the pier on the non-construction side, and cooperate with the rotation of the rotating structure 23 and the lifting of the spreader 210 to complete the entire pier.
  • the construction of the construction platform 6, pile core 2, prefabricated beams, and prefabricated panels 15 completes the integrated installation of the new superstructure of the high pile wharf.
  • the left and right directions in Figure 8 are the length direction of the pier, and the up and down directions in Figure 5 are the width direction of the pier.
  • the main longitudinal beam 24 is The end where the counterweight 29 is located is the rear end, and the end where the hoisting area is located is the front end.
  • the construction platforms 6 are in one row vertically and in one row horizontally in Figure 5:
  • the base legs 22 are provided with Four, four base legs 22 are supported on these four construction platforms 6, spanning the 1 and 2 columns.
  • the main longitudinal beam 24 is parallel to the length direction of the pier.
  • the hoisting range is from the base structure 21 to the front end of the main longitudinal beam 24.
  • Covering 2 rows of construction platforms 6, the base structure 21 to the rear end of the main longitudinal beam 24 is the counterweight 29 range, covering 1 row of construction platforms 6, the distance between a pair of main longitudinal beams 24 covers 3 rows of construction platforms 6, and the auxiliary outriggers 28 are at Two auxiliary beams 27 are provided on each auxiliary beam 27, and the two auxiliary legs 28 are arranged at consistent intervals with the construction platforms 6 in rows 1 and 2 respectively.
  • the auxiliary legs 28 are relatively small in size and do not occupy too much space on the construction platform 6.
  • the spreader 210 takes the construction platform 6/pile core 2/prefabricated beam and rotates it to the position shown in Figure 9, and positions it on the hoop 4 and the top of the bottom plate 3 to ensure that the center of the hole 7 of the construction platform 6 is in line with the steel pipe pile 1 After the center of the circle is controlled within the deviation range, proceed to the lower level installation. As shown in Figure 11, complete the steps in columns 3 to 4. The row of construction platform 6, pile core 2, and prefabricated beams are lowered and installed.
  • the rotating structure 23 drives the construction equipment to rotate to the position shown in Figure 10, and installs the 1 and 2 columns.
  • the construction platform 6, the prefabricated pile core 2, and the prefabricated beam are arranged in a row; after the installation of the prefabricated beam is completed, the node reinforcement 11, formwork, and concrete process of the pile top are carried out on the corresponding construction platform 6 to form the node 10 by pouring.
  • the construction equipment moves downward, as shown in Figure 11, supported by the two auxiliary legs 28 at the front end in the 1 and 2 columns.
  • the two construction platforms 6 in the row are supported by the auxiliary legs 28 at the rear end in rows 1 and 2.
  • the two construction platforms 6 in the row push down the auxiliary legs 28 to make the base legs 22 empty, and then the walking mechanism 212 drives the main longitudinal beam 24 and the base structure 21 to move to the 1 and 2 rows.
  • Construction platform 6, then retract the auxiliary legs 28 to re-support the base legs 22 on the new construction platform 6, and then drive the auxiliary beam 27 back to the initial end position.
  • it can also be directly passed and fixed according to the span requirements.
  • the traveling mechanism 212 connected to the support 211 drives the fixed support 211 and the base structure 21 to adjust their relative positions and then restore them; adjust the orientation of the hoisting area through the rotating structure 23, and install the remaining columns 1 and 2 in sequence.
  • Construction platform 6 perform 5 and 6 Pile core 2, construction platform 6, prefabricated beam hoisting construction, rotating structure 23 rotating hoisting area, supplementary installation of columns 3 to 4 of prefabricated beams, and at the same time, install the 1 and 2 columns 15 prefabricated panels between them, see Figure 10.

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Revetment (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Tents Or Canopies (AREA)

Abstract

A new superstructure for a high-piled wharf, and a construction apparatus and construction method therefor. With respect to a combined form of two inclined piles or three inclined piles of a pile foundation, construction platforms (6) are jointly arranged at the top of the pile foundation, a traditional pile cap structure is eliminated, and multiple water cast-in-situ operations such as water pumping in a steel pipe pile (1), binding of pile-cap reinforced bars, formwork mounting, and concrete pouring of a pile core and a pile cap are avoided overall. By means of the designing of a prefabricated pile core (2), the construction platform (6), componentization of joint reinforced bars (11), ultra-high-performance concrete anchoring connection, etc., a new fully assembled superstructure for a high-piled wharf is formed; and the new superstructure for a high-piled wharf is continuously operated by means of a hoisting apparatus which is supported on the construction platforms (6) and has the functions of transverse and longitudinal self-traveling and swiveling on the wharf, thereby realizing the full-assembly design and construction of the high-piled wharf suitable for combined inclined piles overall.

Description

一种高桩码头新型上部结构及其施工装备和施工方法A new type of superstructure of high pile wharf and its construction equipment and construction methods 技术领域Technical field
本发明涉及高桩码头建造技术领域。更具体地说,本发明涉及一种高桩码头新型上部结构及其施工装备和施工方法。The invention relates to the technical field of high pile wharf construction. More specifically, the present invention relates to a new superstructure of a high pile wharf and its construction equipment and construction methods.
背景技术Background technique
“桩帽型式”的高桩码头主体结构包括桩基、桩芯、桩帽、预制梁、预制板等构件,因其结构易于装配化目前被广泛应用,而传统的上部结构及施工装备、施工工艺带来的问题日益突出,传统高桩码头结构型式、施工装备及施工工艺均极大地影响了高桩码头的施工进度、质量、成本和安全。The main structure of the "pile cap type" high pile wharf includes pile foundation, pile core, pile cap, prefabricated beams, prefabricated panels and other components. It is currently widely used because its structure is easy to assemble. However, the traditional superstructure and construction equipment, construction Problems caused by technology have become increasingly prominent. The structural type, construction equipment and construction technology of traditional high-pile wharfs have greatly affected the construction progress, quality, cost and safety of high-pile wharfs.
桩芯、桩帽通常位于潮位变动区,传统施工工艺均为水上现浇作业,桩芯施工包括钢管桩内抽水、钢筋笼下放、混凝土浇筑等,桩帽施工包括底部搭设复杂的底模支撑体系、钢筋现场绑扎、模板安装以及较大方量的混凝土浇筑。以上水上施工易受风浪、潮位影响,施工窗口受限,工效低;钢筋位于浪溅区易锈蚀,施工质量差;水上作业量大,安全风险高。Pile cores and pile caps are usually located in areas where tide levels change. Traditional construction techniques are cast-in-place operations on the water. Pile core construction includes water pumping in steel pipe piles, lowering steel cages, concrete pouring, etc. Pile cap construction includes the erection of complex bottom form supports at the bottom. system, on-site lashing of steel bars, installation of formwork and larger amounts of concrete pouring. The above water construction is easily affected by wind, waves and tide levels, and the construction window is limited and the work efficiency is low; the steel bars located in the splash zone are prone to rust and the construction quality is poor; the water work volume is large and the safety risks are high.
预制横、纵梁节点处,传统节点结构型式钢筋密布,纵横交错,碰撞问题突出,作业空间小,现场焊接复杂,施工质量控制难度大。At the joints of prefabricated transverse and longitudinal beams, traditional joint structural steel bars are densely covered and criss-crossed, causing prominent collision problems, small working space, complicated on-site welding, and difficult construction quality control.
此外,易于装配化的高桩码头上部结构的预制构件较多,需要频繁进行起重吊装作业,而传统吊装设备如浮吊、顶升平台+起重设备等易受波浪影响,恶劣环境下施工工效低且作业窗口少。少数项目中使用架桥机将水上作业转为陆上作业,但针对离岸式宽平台码头,架桥机尺寸较为庞大,如采用浮吊或顶升平台+起重设备则只能先施工完成码头平台半幅,然后转换到另一侧完成剩下半幅的施工,施工工期长,如果采用多台装备同时作业,施工成本较高,经济性差。In addition, the superstructure of the high pile wharf that is easy to assemble has many prefabricated components and requires frequent lifting operations. However, traditional lifting equipment such as floating cranes, jacking platforms + lifting equipment, etc. are easily affected by waves and are constructed in harsh environments. The work efficiency is low and the operation window is small. In a few projects, bridge erecting machines are used to convert water operations to land operations. However, for offshore wide platform terminals, the size of the bridge erecting machine is relatively large. If a floating crane or jacking platform + lifting equipment is used, the construction can only be completed first. The dock platform is half wide, and then switched to the other side to complete the construction of the remaining half. The construction period is long. If multiple pieces of equipment are used to operate at the same time, the construction cost is high and the economy is poor.
发明内容Contents of the invention
本发明的一个目的是解决至少上述问题,并提供至少后面将说明的优点。It is an object of the present invention to solve at least the above-mentioned problems and to provide at least the advantages to be explained later.
本发明还有一个目的是提供一种高桩码头新型上部结构及其施工装备和施工方法,以解决现有技术中高桩码头主体结构施工困难、施工效率低的技术问题。Another object of the present invention is to provide a new superstructure of a high-pile wharf and its construction equipment and construction methods, so as to solve the technical problems of difficult construction and low construction efficiency of the main structure of the high-pile wharf in the prior art.
为了实现根据本发明的这些目的和其它优点,一方面,提供了一种高桩码头新型上部结构,设置在码头的桩基的顶部,每处桩基包括两个斜桩或三个斜桩,每个斜桩的钢管桩内侧上端设置有预制桩芯,包括:In order to achieve these objects and other advantages according to the present invention, on the one hand, a new superstructure of a high pile wharf is provided, which is arranged on the top of the pile foundation of the wharf, and each pile foundation includes two inclined piles or three inclined piles, The inner upper end of the steel pipe pile of each inclined pile is provided with a prefabricated pile core, including:
在每个斜桩上靠近顶部的位置抱紧设置的抱箍,抱箍的上表面连接有底板,底板套设在对应的斜桩上,预制桩芯的上端向外延伸设置有第一钢筋;A hoop is placed close to the top of each inclined pile. The upper surface of the hoop is connected to a bottom plate. The bottom plate is set on the corresponding inclined pile. The upper end of the prefabricated pile core is extended outward with a first steel bar;
施工平台,其对应每处的桩基分别水平设置一个且连接在对应处的所有底板的上表面,施工平台上对应桩基的每个斜桩分别开设有一个沿竖向贯通且尺寸大于钢管桩的孔洞,以使对应位置的钢管桩的顶部穿入,施工平台的顶面与斜桩的顶部齐平,施工平台上设置有节点钢筋;The construction platform has a horizontal pile corresponding to each pile foundation and is connected to the upper surface of all bottom plates at the corresponding place. Each inclined pile corresponding to the pile foundation on the construction platform is provided with a vertically connected and larger than steel pipe. The holes of the piles are designed so that the tops of the steel pipe piles at the corresponding positions can penetrate, the top surface of the construction platform is flush with the top of the inclined piles, and node steel bars are provided on the construction platform;
预制梁,其沿码头的长度方向或沿码头的宽度方向分别设置,每相邻的两个施工平台的上表面之间共同连接一个预制梁,预制梁的两端分别向外延伸设置有第二钢筋;The prefabricated beams are respectively arranged along the length direction of the pier or along the width direction of the pier. A prefabricated beam is connected between the upper surfaces of each adjacent two construction platforms. The two ends of the prefabricated beams are respectively extended outwards and provided with a second prefabricated beam. steel bars;
节点,其由超高性能混凝土浇筑设置在施工平台上且将第一钢筋、第二钢筋、节点钢筋锚固连接在内部。The node is made of ultra-high performance concrete poured and set on the construction platform, and the first steel bar, the second steel bar, and the node steel bar are anchored and connected internally.
优选的是,位于所述码头的长度方向的最外两侧的所述桩基均包括三个所述斜桩,其余的所述桩基分别包括两个所述斜桩,对应位于所述码头的长度方向的最外两侧的每个所述施工平台上分别开设三个所述孔洞,其余位置的所述施工平台上分别开设两个所述孔洞。Preferably, the pile foundations located on the outermost sides of the pier in the length direction each include three angled piles, and the remaining pile foundations each include two angled piles, corresponding to the pile foundations located on the pier. Three of the holes are respectively provided on each of the construction platforms on the outermost two sides in the length direction, and two of the holes are respectively provided on the construction platforms at other positions.
优选的是,所述抱箍包括环绕所述斜桩的外侧设置的多个圆弧形的凹槽板,凹槽板的数量至少设置有四个,每个凹槽板的两端分别沿所述斜桩的径向向外连接有耳板,相邻的凹槽板之间通过同侧的两个耳板固定连接,每个耳板与对应的凹槽板的外侧之间连接有若干个加劲板,所述底板由两块连接板拼装连接而成,连接板上对应所述钢管桩开设有半圆弧形的凹槽。Preferably, the hoop includes a plurality of arc-shaped groove plates arranged around the outside of the inclined pile. There are at least four groove plates, and the two ends of each groove plate are respectively along the The inclined piles are connected with ear plates radially outward, and adjacent groove plates are fixedly connected by two ear plates on the same side. Each ear plate is connected to the outside of the corresponding groove plate. Stiffening plate, the bottom plate is assembled and connected by two connecting plates, and a semicircular arc-shaped groove is provided on the connecting plate corresponding to the steel pipe pile.
优选的是,所述节点钢筋包括两套横梁箍筋钢筋笼、两套纵梁箍筋钢筋笼和一套预制节点中心区钢筋笼,横梁箍筋钢筋笼用于连接沿所述码头宽度方向设置的所述预制梁,纵梁箍筋钢筋笼用于连接沿所述码头长度方向设置的所述预制梁,横梁箍筋钢筋笼、纵梁箍筋钢筋笼均至少间隔布置三层箍筋,每层箍筋分别与对应侧的所述第二钢筋连接,所述第一钢筋向上穿入连接至节点中心区钢筋笼的内部。Preferably, the node reinforcements include two sets of cross beam stirrup steel cages, two sets of longitudinal beam stirrup steel cages and one set of prefabricated node center area steel cages. The cross beam stirrup steel cages are used to connect the cross beam stirrup steel cages arranged along the width direction of the wharf. The prefabricated beams, the longitudinal beam stirrup steel cages are used to connect the prefabricated beams arranged along the length direction of the dock, the cross beam stirrup steel cages, and the longitudinal beam stirrup steel cages are all arranged with at least three layers of stirrups at intervals, each The layer stirrups are respectively connected to the second steel bars on the corresponding sides, and the first steel bars penetrate upward and are connected to the inside of the steel cage in the central area of the node.
另一方面,本发明提供了一种高桩码头新型上部结构的施工装备,包括支撑系统,其包括依次向上连接设置的底座结构、回转结构、固定支座、一对主纵梁,底座结构的下端用于支撑于多个所述施工平台上,回转结构能带动固定支座相对底座结构沿水平方向自由旋转,一对主纵梁相对且平行设置,固定支座的两端分别与一个主纵梁的底部滑动连接,一对主纵梁在两端的顶部之间分别滑动连接有辅助横梁,每个辅助横梁上对称设置有可上下伸缩的辅助支腿,用于临时支撑在对应位置的所述施工平台上,一对主纵梁的其中一端设置有配重块;On the other hand, the present invention provides a construction equipment for a new superstructure of a high pile wharf, including a support system, which includes a base structure, a rotary structure, a fixed support, a pair of main longitudinal beams, and a base structure connected upward in sequence. The lower end is used to support multiple construction platforms. The rotating structure can drive the fixed support to rotate freely in the horizontal direction relative to the base structure. A pair of main longitudinal beams are opposite and parallel to each other. The two ends of the fixed support are respectively connected with one main longitudinal beam. The bottom of the beam is slidingly connected, and a pair of main longitudinal beams are slidingly connected to auxiliary beams between the tops of the two ends. Each auxiliary beam is symmetrically provided with auxiliary legs that can be telescoped up and down for temporary support of the above-mentioned beams at corresponding positions. On the construction platform, one end of a pair of main longitudinal beams is equipped with a counterweight block;
吊装系统,其包括滑动连接在一对主纵梁的顶部之间的主横梁,主横梁位于固定支座与其中一个辅助横梁之间且与配重块位于固定支座的不同侧,主横梁上滑动连接有移动天车,移动天车上设置有吊具,在一对主纵梁与固定支座、未设置配重块一侧的辅助横梁之间围成吊具的移动空间,形成吊装区域;Hoisting system, which includes a main crossbeam slidably connected between the tops of a pair of main longitudinal beams, the main crossbeam being located between a fixed support and one of the auxiliary crossbeams and located on a different side of the fixed support from the counterweight block on the main crossbeam A mobile crane is slidingly connected, and a spreader is installed on the mobile crane. A moving space for the spreader is formed between a pair of main longitudinal beams, a fixed support, and an auxiliary beam on the side without a counterweight block, forming a lifting area. ;
行走系统,其包括分别设置在辅助横梁与主纵梁之间、设置在固定支座与主纵梁之间、主横梁与主纵梁之间的行走机构,行走机构用于驱动对应连接的辅助横梁或固定支座或主横梁相对主纵梁发生移动。The traveling system includes traveling mechanisms respectively arranged between the auxiliary beam and the main longitudinal beam, between the fixed support and the main longitudinal beam, and between the main beam and the main longitudinal beam. The traveling mechanism is used to drive the corresponding connected auxiliary beams. The crossbeam or fixed support or main crossbeam moves relative to the main longitudinal beam.
优选的是,所述底座结构包括水平设置的底座支架,底座支架的顶部中心处与所述回转结构的底部连接,底座支架的底部在水平面内沿矩形的四个顶角方位对撑布置有调位油缸,调位油缸的缸体与底座支架的底部固定且伸缩方向平行于矩形的对角线方向设置,调位油缸的伸缩端向下固定有底座支腿,底座支腿的上端与底座支架的底部滑动连接、底座支腿的下端用于支撑固定在所述施工平台上。Preferably, the base structure includes a horizontally arranged base bracket. The top center of the base bracket is connected to the bottom of the rotary structure. The bottom of the base bracket is arranged with adjustable supports along the four corners of the rectangle in the horizontal plane. Position oil cylinder, the cylinder body of the position adjustment oil cylinder is fixed to the bottom of the base bracket, and the telescopic direction is set parallel to the diagonal direction of the rectangle. The telescopic end of the position adjustment oil cylinder is fixed downward with a base leg, and the upper end of the base leg is in contact with the base bracket. The bottom is slidingly connected, and the lower ends of the base legs are used to support and fix on the construction platform.
再一方面,本发明还提供了一种高桩码头新型上部结构的施工装备的施工方法,包括如下步骤:On the other hand, the present invention also provides a construction method of construction equipment for a new superstructure of a high pile wharf, which includes the following steps:
S1:预制所述施工平台、所述桩芯、所述预制梁,所述桩芯的顶部连接所述第一钢筋,所述预制梁的两端连接所述第二钢筋;S1: Prefabricate the construction platform, the pile core, and the prefabricated beam. The top of the pile core is connected to the first steel bar, and both ends of the prefabricated beam are connected to the second steel bar;
S2:分别对每处所述桩基的单个所述斜桩对应安装所述抱箍及所述底板,所述底板的内侧孔的面积略大于所述孔洞的面积;S2: Install the hoop and the bottom plate correspondingly to each of the inclined piles of the pile foundation, and the area of the inner hole of the bottom plate is slightly larger than the area of the hole;
S3:安装所述施工平台、所述桩芯,将所述施工平台搁置于对应所述桩基的所有所述底板上,每个所述钢管桩的顶部分别向上穿入一个所述孔洞内,控制圆心偏差,使所述施工平台位于对应的所述桩基的中心位置,然后在所述桩芯的底部设置封底板及止水橡胶圈,起吊所述桩芯并插入至对应的所述钢管桩内,在部分所述施工平台安装完成后,将所述施工装备支撑在已安装的所述施工平台上,继续进行剩下的所述施工平台、所述桩芯的吊装施工;S3: Install the construction platform and pile core, place the construction platform on all the bottom plates corresponding to the pile foundation, and penetrate the top of each steel pipe pile upward into one of the holes. , control the center deviation of the circle so that the construction platform is located at the center of the corresponding pile foundation, then set a bottom sealing plate and a water-stop rubber ring at the bottom of the pile core, lift the pile core and insert it into the corresponding pile foundation In the steel pipe pile, after the installation of part of the construction platform is completed, the construction equipment is supported on the installed construction platform, and the hoisting construction of the remaining construction platform and pile core is continued;
S4:采用灌浆材料对所述钢管桩与所述桩芯之间的空隙进行水下灌浆,采用细石混凝土对所述孔洞与所述钢管桩之间的空隙进行灌注;S4: Use grouting material to grout the gap between the steel pipe pile and the pile core underwater, and use fine stone concrete to grout the gap between the hole and the steel pipe pile;
S5:在所有位于所述码头的宽度方向或长度方向上相邻的两个所述施工平台之间利用所述施工装备吊装所述预制梁,此时所述第一钢筋、所述第二钢筋均位于对应的所述施工平台上;S5: Use the construction equipment to hoist the prefabricated beam between all two adjacent construction platforms located in the width direction or length direction of the dock. At this time, the first steel bar and the second steel bar are All are located on the corresponding construction platform;
S6:进行所述节点钢筋部品化制作,并设置箍筋,用于连接所述节点钢筋与所述预制梁的所述第二钢筋;S6: Make the node steel bars into parts, and set stirrups for connecting the node steel bars and the second steel bars of the prefabricated beam;
S7:在所述施工平台上吊装所述节点钢筋部品,连接所述施工平台上的所述第一钢筋、所述第二钢筋,然后在所述施工平台上安装所述节点的模板,之后采用超高性能混凝土浇筑所述节点,将位于同一所述施工平台上的所述预制梁、所述桩芯锚固连接;S7: Hoist the node steel bar components on the construction platform, connect the first steel bar and the second steel bar on the construction platform, and then install the node template on the construction platform, and then use The nodes are poured with ultra-high performance concrete, and the prefabricated beams and pile cores located on the same construction platform are anchored and connected;
S8:利用所述施工装备在已安装好的所述预制梁上吊装预制面板。S8: Use the construction equipment to hoist the prefabricated panels on the installed prefabricated beams.
优选的是,利用所述施工装备在吊装所述施工平台、所述桩芯、所述预制梁时,所述底座结构支撑在已安装好的所述施工平台上,通过所述回转结构带动所述主纵梁、所述主横梁、所述辅助横梁同步旋转至预制好的所述施工平台、所述桩芯、所述预制梁的上方,利用所述移动天车移动所述吊具进行取料,然后利用所述回转结构旋转至待安装位置进行下放安装,当需要将所述施工装备整体移动至下一个施工位置时,通过所述行走机构驱动所述辅助横梁移动到已安装好的所述施工平台的正上方,向下伸长所述辅助支腿并支撑在对应的所述施工平台上,使所述底座结构的底部脱离对应的所述施工平台,然后所述主纵梁上对应的所述行走机构驱动所述主纵梁沿长度方向移动,带动所述底座结构移动到下一个所述施工平台上,缩回所述辅助支腿,重新使所述底座结构支撑在下方的所述施工平台上,再通过所述辅助横梁的所述行走结构在所述主纵梁上移动所述辅助横梁到初始位置,完成一次所述底座结构的过跨前移,之后重复前述操作,通过所述回转结构带动所述移动天车及所述吊具进行取料、下放安装,直至整个码头的所有所述施工平台、所述桩芯、所述预制梁完成吊装。Preferably, when using the construction equipment to hoist the construction platform, the pile core, and the prefabricated beam, the base structure is supported on the installed construction platform, and the rotating structure drives all the construction platforms. The main longitudinal beam, the main beam, and the auxiliary beam are synchronously rotated above the prefabricated construction platform, the pile core, and the prefabricated beam, and the mobile crane is used to move the spreader for removal. material, and then use the rotary structure to rotate to the position to be installed for lowering and installation. When it is necessary to move the construction equipment as a whole to the next construction position, the walking mechanism drives the auxiliary beam to move to the installed position. Directly above the construction platform, extend the auxiliary legs downward and support them on the corresponding construction platform, so that the bottom of the base structure is separated from the corresponding construction platform, and then the corresponding main longitudinal beam is The walking mechanism drives the main longitudinal beam to move along the length direction, driving the base structure to move to the next construction platform, retracting the auxiliary legs, and re-supporting the base structure on all the lower parts. On the construction platform, the auxiliary beam is moved to the initial position through the walking structure of the auxiliary beam on the main longitudinal beam to complete the over-span forward movement of the base structure, and then the aforementioned operation is repeated. The rotary structure drives the mobile crane and the spreader to retrieve materials and lower them for installation until all the construction platforms, pile cores, and prefabricated beams of the entire wharf are hoisted.
优选的是,所述主纵梁沿所述码头的长度方向设置时,在所述码头的长度方向上,所述配重块与所述底座结构的间距覆盖1个所述施工平台,所述主横梁在所述底座结构与所述主纵梁的对应端之间的移动范围覆盖2个所述施工平台,所述底座结构横跨在相邻的2~3个所述施工平台上;Preferably, when the main longitudinal beam is arranged along the length direction of the pier, the distance between the counterweight block and the base structure covers one of the construction platforms in the length direction of the pier, and the The movement range of the main beam between the base structure and the corresponding end of the main longitudinal beam covers 2 of the construction platforms, and the base structure spans 2 to 3 adjacent construction platforms;
在所述码头的宽度方向上,一对所述主纵梁的间距覆盖2~3个所述施工平台,所述移动天车能沿所述主横梁的长度方向移动,所述底座结构覆盖2~3个相邻的所述施工平台。In the width direction of the pier, the distance between a pair of main longitudinal beams covers 2 to 3 construction platforms, the mobile crane can move along the length direction of the main beams, and the base structure covers 2 ~3 adjacent construction platforms.
优选的是,利用所述施工装备对施工平台、桩芯、预制梁、预制面板进行吊装施工时,采用如下步骤进行:Preferably, when using the construction equipment to hoist the construction platform, pile cores, prefabricated beams, and prefabricated panels, the following steps are used:
A1:将码头的一顶角边缘处作为起始施工位置,并根据桩基位置设置存放区或停靠运输船,存放预制好的施工平台、桩芯、预制梁、预制面板,施工平台以位于码头的同一长度方向为一排、以位于码头的同一宽度方向为一列,完成起始施工位置的4个施工平台及对应的桩芯施工,将所述底座结构支撑在4个施工平台上,并向上依次拼装连接所述支撑系统的其余部件及所述吊装系统、所述行走系统;A1: Use one corner edge of the pier as the starting construction location, and set up a storage area or dock a transport ship according to the position of the pile foundation to store the prefabricated construction platform, pile core, prefabricated beams, and prefabricated panels. The construction platform should be located at the pier. The same length direction is one row, and the same width direction at the dock is one row. Complete the construction of the 4 construction platforms and the corresponding pile cores at the starting construction position. Support the base structure on the 4 construction platforms and upwards. Assemble and connect the remaining components of the support system, the hoisting system, and the walking system in sequence;
A2:利用所述回转结构带动所述吊具旋转至临近的存放区或停靠运输船取料,随后旋转所述回转结构,带动所述吊具旋转至起始施工位置位于码头长度方向的未施工一侧,此时所述主纵梁与码头的长度方向平行,然后下放安装位于吊装区域内的施工平台、桩芯、预制梁;A2: Use the rotary structure to drive the spreader to rotate to the adjacent storage area or dock the transport ship to retrieve materials, and then rotate the rotary structure to drive the spreader to the starting construction position, which is located in the length direction of the dock and is not yet under construction. On one side, the main longitudinal beam is parallel to the length direction of the wharf, and then the construction platform, pile core and prefabricated beam located in the hoisting area are lowered and installed;
A3:利用所述回转结构继续旋转90°,带动所述吊具移动至起始施工位置位于码头宽度方向的未施工一侧,此时所述主纵梁与码头的宽度方向平行,然后下放安装位于吊装区域内的施工平台、桩芯、预制梁;A3: Use the slewing structure to continue rotating 90° to drive the spreader to the starting construction position on the unconstruction side in the width direction of the pier. At this time, the main longitudinal beam is parallel to the width direction of the pier, and then lower it for installation. Construction platforms, pile cores, and prefabricated beams located in the hoisting area;
A4:利用所述辅助横梁、所述辅助支腿及所述行走系统,使所述底座结构沿码头宽度方向的远离起始施工位置的一侧过跨前移一个吊装区域的长度单位,随后所述回转结构旋转180°,使吊装区域位于起始施工位置上方,补充安装起始施工位置的所有预制梁;A4: Use the auxiliary beam, the auxiliary leg and the walking system to move the base structure forward by one unit of the length of the hoisting area along the width direction of the pier away from the starting construction position. The above-mentioned revolving structure is rotated 180° so that the hoisting area is above the starting construction position, and all prefabricated beams at the starting construction position are supplementally installed;
A5:利用所述回转结构旋转90°,使吊装区域位于码头长度方向的未施工一侧,进行施工平台、桩芯、预制梁的吊装,之后使所述底座结构沿码头的长度方向过跨前移一个吊装区域的长度单位,至此,完成起始施工位置位于一个吊装区域的长度单位的所有列的施工平台、桩芯、预制梁的安装;A5: Use the slewing structure to rotate 90° so that the hoisting area is located on the non-construction side of the length of the pier. Hoist the construction platform, pile cores and prefabricated beams, and then move the base structure across the front span along the length of the pier. Move one unit of length of the hoisting area. At this point, the installation of all rows of construction platforms, pile cores, and prefabricated beams whose starting construction position is located in one unit of length of the hoisting area is completed;
A6:对位于过跨前移后的吊装区域内桩基进行施工平台、桩芯、预制梁的吊装,旋转所述回转结构,补充安装位于所述底座结构在码头的宽度方向的预制梁,同期,安装位于所述底座结构在码头的宽度方向上已施工一侧的预制面板;A6: Hoist the construction platform, pile core and prefabricated beams on the pile foundation in the hoisting area after the span has been moved forward, rotate the rotary structure, and supplementary installation of the prefabricated beams located in the width direction of the base structure in the dock, at the same time , install the prefabricated panels located on the constructed side of the base structure in the width direction of the pier;
A7:利用所述辅助横梁、所述辅助支腿及所述行走系统,使所述底座结构沿码头宽度方向的朝向起始施工位置的一侧逐步过跨前移到顶,同时,每次过跨前移利用所述回转结构配合安装位于所述底座结构在 码头的长度方向的未施工一侧的施工平台、桩芯、预制梁和已施工一侧的预制面板;A7: Utilize the auxiliary beam, the auxiliary leg and the walking system to gradually move the base structure forward to the top along the width direction of the pier towards the starting construction position. At the same time, each span is Move forward and use the rotary structure to cooperate and install the construction platform, pile core, prefabricated beams and prefabricated panels on the constructed side of the base structure in the length direction of the wharf;
A8:重复驱动所述施工装备依次沿未施工一侧的码头的宽度方向、长度方向、宽度方向移动,配合旋转所述回转结构及所述吊具的取料、吊装,完成整个码头的施工平台、桩芯、预制梁、预制面板的施工,从而完成高桩码头新型上部结构的一体化安装。A8: Repeatedly drive the construction equipment to move along the width direction, length direction, and width direction of the pier on the unconstructed side, and cooperate with the rotation of the slewing structure and the lifting of the spreader to complete the construction platform of the entire pier. , pile cores, prefabricated beams, and prefabricated panels to complete the integrated installation of the new superstructure of the high-pile wharf.
本发明至少包括以下有益效果:The present invention at least includes the following beneficial effects:
(1)本发明通过在桩顶依次设置抱箍、底板、施工平台替代传统的桩帽结构,在施工平台上浇筑节点,以连接底部的桩芯与水平方向上的预制梁结构,避免了钢管桩内抽水、桩帽钢筋绑扎、模板安装及桩芯、桩帽混凝土浇筑等水上现浇作业,减小了波浪、潮差对施工窗口的影响以及海水对钢筋的锈蚀,无桩帽条件下,桩芯预留第一钢筋伸入上部节点直接传递荷载,提升了桩顶结构承载性能。(1) The present invention replaces the traditional pile cap structure by sequentially arranging hoops, bottom plates, and construction platforms on top of piles, and pours nodes on the construction platform to connect the pile core at the bottom and the prefabricated beam structure in the horizontal direction, avoiding the need for steel Water-based cast-in-place operations such as pumping water inside pipe piles, tying pile cap steel bars, installing formwork, and concrete pouring of pile cores and pile caps reduce the impact of waves and tidal range on the construction window and the corrosion of steel bars by sea water. Under the condition of no pile cap , the first steel bar is reserved in the pile core to extend into the upper node to directly transfer the load, which improves the load-bearing performance of the pile top structure.
(2)本发明设置的施工平台能够作为施工装备支撑与行走的平台以及预制桩芯、预制梁的安装搁置平台,利用施工装备循环进行施工平台、桩芯、预制梁的施工,并将新安装的施工平台作为下一步施工时的支撑平台,使得施工装备在施工平台上的施工不受波浪、潮流影响,作业窗口增加,定位安装精度高,施工质量提升,也避免了传统桩帽结构预留钢筋对施工装备支撑与行走时的干扰,整体避免了水上搭设复杂的型钢支撑体系,提高了施工工效,降低了安全风险。(2) The construction platform set up in the present invention can be used as a platform for supporting and walking construction equipment, as well as an installation and resting platform for prefabricated pile cores and prefabricated beams. The construction equipment is used to cycle the construction of the construction platform, pile cores, and prefabricated beams, and the newly installed The construction platform serves as the support platform for the next step of construction, so that the construction equipment on the construction platform is not affected by waves and currents. The operation window is increased, the positioning and installation accuracy is high, the construction quality is improved, and the traditional pile cap structure is avoided. The interference of steel bars on the support and walking of construction equipment avoids the overall need to set up a complex steel support system on the water, improves construction efficiency and reduces safety risks.
(3)本发明的节点钢筋提前在预制厂内绑扎成型,现场快速装配施工,并采用超高性能混凝土锚固连接。优化了桩顶结构的连接形式,避免了受限空间内焊接作业,降低了施工成本,提高了施工质量。(3) The node steel bars of the present invention are tied and formed in advance in the precast factory, quickly assembled and constructed on site, and anchored and connected by ultra-high performance concrete. The connection form of the pile top structure is optimized, which avoids welding operations in restricted spaces, reduces construction costs, and improves construction quality.
(4)本发明的施工装备通过回转结构实现主纵梁相对底座结构回转360°,从而使吊具可沿码头长度方向、宽度方向移动进行全方位施工,灵活便捷,作业效率高,施工成本小,尤其对于离岸式宽平台码头,可大幅度减少船机设备成本,解决船机设备无法从一侧覆盖码头整体宽度施工问题。(4) The construction equipment of the present invention realizes the main longitudinal beam to rotate 360° relative to the base structure through the rotation structure, so that the spreader can move along the length and width directions of the pier for all-round construction, which is flexible and convenient, with high operating efficiency and low construction cost. , especially for offshore wide-platform wharves, it can greatly reduce the cost of ship machinery and equipment and solve the construction problem of ship machinery and equipment being unable to cover the entire width of the wharf from one side.
(5)本发明通过预制桩芯及施工平台、节点钢筋部品化及超高性能混凝土锚固连接等设计,形成了一种高桩码头新型全装配式上部结构,并通过支撑于施工平台且具备码头横纵向自行走和回转功能的吊装装备进行连续作业,实现了适用组合斜桩的高桩码头全装配化设计与施工。(5) The present invention forms a new fully assembled superstructure of a high-pile wharf through the design of prefabricated pile cores and construction platforms, componentized node steel bars, and ultra-high-performance concrete anchor connections. It is supported on the construction platform and equipped with a wharf. Hoisting equipment with horizontal and vertical self-propelled and rotary functions performs continuous operations, realizing the fully assembled design and construction of high pile wharf suitable for combined inclined piles.
本发明的其它优点、目标和特征将部分通过下面的说明体现,部分还将通过对本发明的研究和实践而为本领域的技术人员所理解。Other advantages, objects, and features of the present invention will be apparent in part from the description below, and in part will be understood by those skilled in the art through study and practice of the present invention.
附图说明Description of the drawings
图1为本发明的单个斜桩顶部的结构示意图;Figure 1 is a schematic structural diagram of the top of a single inclined pile according to the present invention;
图2为本发明的桩基顶部的结构示意图;Figure 2 is a schematic structural diagram of the top of the pile foundation of the present invention;
图3为本发明的节点钢筋的结构示意图;Figure 3 is a schematic structural diagram of the node steel bar of the present invention;
图3为本发明的高桩码头新型上部结构的结构示意图;Figure 3 is a structural schematic diagram of the new superstructure of the high pile wharf of the present invention;
图4为本发明的施工装备的主视结构图;Figure 4 is a front structural view of the construction equipment of the present invention;
图5为本发明的施工装备的侧式结构图;Figure 5 is a side structural view of the construction equipment of the present invention;
图6为本发明的主纵梁的侧视放大结构图;Figure 6 is an enlarged side structural view of the main longitudinal beam of the present invention;
图7为本发明的施工装备的安装在施工起始位置的平面结构示意图;Figure 7 is a schematic plan view of the construction equipment of the present invention installed at the starting position of construction;
图8为本发明在利用施工装备施工时步骤A1对应的平面结构示意图;Figure 8 is a schematic diagram of the planar structure corresponding to step A1 when constructing using construction equipment according to the present invention;
图9为本发明在利用施工装备施工时步骤A2对应的平面结构示意图;Figure 9 is a schematic diagram of the planar structure corresponding to step A2 when constructing using construction equipment according to the present invention;
图10为本发明在利用施工装备施工时步骤A3对应的平面结构示意图;Figure 10 is a schematic diagram of the planar structure corresponding to step A3 when constructing using construction equipment according to the present invention;
图11为本发明在利用施工装备施工时步骤A4对应的平面结构示意图;Figure 11 is a schematic diagram of the planar structure corresponding to step A4 when constructing using construction equipment according to the present invention;
图12为本发明在利用施工装备施工时步骤A5的第一步对应的平面结构示意图;Figure 12 is a schematic plan view corresponding to the first step of step A5 when constructing using construction equipment according to the present invention;
图13为本发明在利用施工装备施工时步骤A5的第二步对应的平面结构示意图;Figure 13 is a schematic diagram of the planar structure corresponding to the second step of step A5 when constructing using construction equipment according to the present invention;
图14为本发明在利用施工装备施工时步骤A6对应的平面结构示意图;Figure 14 is a schematic diagram of the planar structure corresponding to step A6 when constructing using construction equipment according to the present invention;
图15为本发明在利用施工装备施工时步骤A7对应的平面结构示意图。Figure 15 is a schematic diagram of the planar structure corresponding to step A7 when constructing using construction equipment according to the present invention.
附图标记:1—钢管桩,2—桩芯,3—底板,4—抱箍,5—加劲板,6—施工平台,7—孔洞,8—沿码头的宽度方向设置的预制梁,9—沿码头的长度方向设置的预制梁,10—节点,11—节点钢筋,12—节点中心区钢筋笼,13—横梁箍筋钢筋笼,14—纵梁箍筋钢筋笼,15—预制面板,21—底座结构,22—底座支腿,23—回转结构,24—主纵梁,25—主横梁,26—移动天车,27—辅助横梁,28—辅助支腿,29—配重,210—吊具,211—固定支座,212—行走机构。Reference signs: 1—steel pipe pile, 2—pile core, 3—bottom plate, 4—hoop, 5—stiffening plate, 6—construction platform, 7—hole, 8—prefabricated beam set along the width of the pier, 9—Prefabricated beams set along the length of the dock, 10—nodes, 11—node steel bars, 12—node center area steel cages, 13—beam stirrup steel cages, 14—longitudinal beam stirrup steel cages, 15—prefabricated panels , 21—base structure, 22—base legs, 23—slewing structure, 24—main longitudinal beam, 25—main beam, 26—mobile crane, 27—auxiliary beam, 28—auxiliary leg, 29—counterweight, 210—spreader, 211—fixed support, 212—traveling mechanism.
具体实施方式Detailed ways
下面结合附图对本发明做进一步的详细说明,以令本领域技术人员参照说明书文字能够据以实施。The present invention will be further described in detail below with reference to the accompanying drawings, so that those skilled in the art can implement it with reference to the text of the description.
需要说明的是,下述实施方案中所述实验方法,如无特殊说明,均为常规方法,所述试剂和材料,如无特殊说明,均可从商业途径获得;在本发明的描述中,术语“横向”、“纵向”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,并不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。It should be noted that the experimental methods described in the following embodiments, unless otherwise specified, are all conventional methods, and the reagents and materials, unless otherwise specified, can be obtained from commercial sources; in the description of the present invention, The terms "horizontal", "vertical", "top", "bottom", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", The orientations or positional relationships indicated by "inner", "outer", etc. are based on the orientations or positional relationships shown in the drawings. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have Specific orientations, construction and operation in specific orientations and therefore are not to be construed as limitations of the invention.
如图1‐4所示,本发明提供一种高桩码头新型上部结构,设置在码头的桩基的顶部,桩基在沿码头施工面呈矩形阵列排列设置,每处桩基包括两个斜桩或三个斜桩,每个斜桩的钢管桩1内侧上端设置有预制桩芯2,包括:As shown in Figures 1-4, the present invention provides a new superstructure of a high pile wharf, which is arranged on the top of the pile foundation of the wharf. The pile foundations are arranged in a rectangular array along the construction surface of the wharf. Each pile foundation includes two inclined Pile or three inclined piles, each inclined pile is provided with a prefabricated pile core 2 at the inner upper end of the steel pipe pile 1, including:
在每个斜桩上靠近顶部的位置抱紧设置的抱箍4,抱箍4的上表面连接有底板3,底板3套设在对应的斜桩上,预制桩芯2的上端向外延伸设置有第一钢筋;A hoop 4 is tightly held near the top of each inclined pile. The upper surface of the hoop 4 is connected to a bottom plate 3. The bottom plate 3 is set on the corresponding inclined pile. The upper end of the prefabricated pile core 2 extends outward. There is the first steel bar;
施工平台6,其对应每处的桩基分别水平设置一个且连接在对应处的所有底板3的上表面,施工平台6上对应桩基的每个斜桩分别开设有一个沿竖向贯通且尺寸大于钢管桩1的孔洞7,以使对应位置的钢管桩1的顶部穿入,施工平台6的顶面与斜桩的顶部齐平,施工平台6上设置有节点钢筋11;The construction platform 6 has a horizontal pile corresponding to each pile foundation and is connected to the upper surface of all bottom plates 3 at the corresponding place. Each inclined pile corresponding to the pile foundation on the construction platform 6 is provided with a vertically connected and sized pile. It is larger than the hole 7 of the steel pipe pile 1, so that the top of the steel pipe pile 1 at the corresponding position can penetrate, the top surface of the construction platform 6 is flush with the top of the inclined pile, and the construction platform 6 is provided with node steel bars 11;
预制梁8、9,其沿码的头长度方向或沿码头的宽度方向分别设置,每相邻的两个施工平台6的上表面之间共同连接一个预制梁,预制梁的两端分别向外延伸设置有第二钢筋; Prefabricated beams 8 and 9 are respectively arranged along the length direction of the dock head or along the width direction of the dock. A prefabricated beam is connected between the upper surfaces of each two adjacent construction platforms 6, and the two ends of the prefabricated beams face outwards respectively. The extension is provided with a second steel bar;
节点10,其由超高性能混凝土(UHPC)浇筑设置在施工平台6上且将第一钢筋、第二钢筋、节点钢筋11锚固连接在内部。The node 10 is made of ultra-high performance concrete (UHPC) and is poured on the construction platform 6 and anchors the first steel bar, the second steel bar and the node steel bar 11 inside.
高桩码头桩顶上部新型连接结构,针对桩基两斜桩或三斜桩的组合形式,共同在桩基顶部首先安装简易的抱箍4及底板3,然后安装连接施工平台6,给预制的桩芯2安装及预制梁安装提供搁置平台,施工平台6上孔洞7的直径结合钢管桩1斜率以及钢管桩1最大偏位150mm考虑,以便使施工平台6安装时穿过钢管桩1,同时,在施工平台6上作为节点10的施工场地,可便于架设节点10处模板、节点钢筋11,节点钢筋11可提前在预制厂内绑扎成型,现场再快速装配至施工平台6上进行施工,如此设置施工平台6后整体上避免了钢管桩1内抽水、桩帽钢筋绑扎、模板安装及桩芯2、桩帽混凝土浇筑等多项水上现浇作业,减小了波浪、潮差对施工窗口的影响以及海水对钢筋的锈蚀,另外,在取消传统桩芯2上端现浇桩帽结构后,浇筑设置的节点10将节点钢筋11、第一钢筋、第二钢筋锚固连接起来,优化了桩顶结构的连接形式,避免了受限空间内焊接作业,降低了施工成本,提高了施工质量,且桩芯2上端预留的第一钢筋伸入上部节点10区域,能够直接传递荷载,提升了桩顶结构的承载性能。The new connection structure on the top of the high-pile wharf piles is based on the combination of two inclined piles or three inclined piles on the pile foundation. A simple hoop 4 and a bottom plate 3 are first installed on the top of the pile foundation, and then the connecting construction platform 6 is installed to provide prefabricated The pile core 2 is installed and the prefabricated beam is installed to provide a resting platform. The diameter of the hole 7 on the construction platform 6 is considered in conjunction with the slope of the steel pipe pile 1 and the maximum deflection of the steel pipe pile 1 of 150mm, so that the construction platform 6 can pass through the steel pipe pile 1 when installed. , at the same time, the construction platform 6 serves as the construction site for the node 10, which can facilitate the erection of the formwork and node steel bars 11 at the node 10. The node steel bars 11 can be tied and formed in the prefabricated factory in advance, and then quickly assembled on the construction platform 6 for construction. After setting the construction platform 6 in this way, it is generally avoided to pump water in the steel pipe pile 1, tie the pile cap steel bars, formwork installation, pile core 2, pile cap concrete pouring and other water cast-in-place operations, and reduce the impact of waves and tidal range. The influence of the construction window and the corrosion of steel bars by seawater. In addition, after canceling the cast-in-place pile cap structure at the upper end of the traditional pile core 2, the node 10 set by the pouring anchors the node steel bar 11, the first steel bar, and the second steel bar, optimizing the The connection form of the pile top structure avoids welding operations in a restricted space, reduces construction costs, and improves construction quality. Moreover, the first steel bar reserved at the upper end of the pile core 2 extends into the upper node 10 area, which can directly transfer the load and improve the construction quality. The load-bearing performance of the pile top structure.
在另一种技术方案中,如图4所示,位于所述码头的长度方向的最外两侧的所述桩基均包括三个所述斜桩,其余的所述桩基分别包括两个所述斜桩,对应位于所述码头的长度方向的最外两侧的每个所述施工平台6上分别开设三个所述孔洞7,其余位置的所述施工平台6上分别开设两个所述孔洞7。通过在码头的外侧的桩基设置三个斜桩,提高桩基的承载能力及对外侧水流冲击的抵抗能力。In another technical solution, as shown in Figure 4, the pile foundations located on the outermost two sides of the pier in the length direction each include three inclined piles, and the remaining pile foundations each include two The inclined piles are respectively provided with three holes 7 on each of the construction platforms 6 located on the outermost sides of the length direction of the pier, and two holes 7 are respectively provided on the construction platforms 6 at other positions. Describe the hole 7. By setting three inclined piles on the outer pile foundation of the pier, the bearing capacity of the pile foundation and its resistance to the impact of outer water flow are improved.
在另一种技术方案中,如图1所示,所述抱箍4包括环绕所述斜桩的外侧设置的多个圆弧形的凹槽板,凹槽板的数量至少设置有四个,每个凹槽板的两端分别沿所述斜桩的径向向外连接有耳板,相邻的凹槽板 之间通过同侧的两个耳板固定连接,每个耳板与对应的凹槽板的外侧之间连接有若干个加劲板5,所述底板3由两块连接板拼装连接而成,连接板上对应所述钢管桩1开设有半圆弧形的凹槽。In another technical solution, as shown in Figure 1, the hoop 4 includes a plurality of arc-shaped groove plates arranged around the outside of the inclined pile, and the number of groove plates is at least four. The two ends of each groove plate are respectively connected with ear plates outward along the radial direction of the inclined pile. The adjacent groove plates are fixedly connected by two ear plates on the same side. Each ear plate is connected to the corresponding ear plate. Several stiffening plates 5 are connected between the outer sides of the groove plates. The bottom plate 3 is assembled and connected by two connecting plates. Semi-circular arc-shaped grooves are provided on the connecting plates corresponding to the steel pipe piles 1.
耳板设置的长度保证大于钢管桩1外侧与施工平台6预留桩芯2的孔洞7间距,其后将抱箍4与底板3之间固定连接,使用橡胶材料填充底板3与钢管桩1之间的缝隙,通过设置抱箍4提供支撑底板3和保障施工平台6稳定性的作用,设置底板3扩大施工平台6的搁置面积,便于安装施工平台6,设置加劲板5以提高耳板、凹槽板之间的连接强度。通过将底板3设置为拼装结构便于底板3在抱箍4上快速组装,便于预制化生产,提高施工效率。The length of the ear plate must be greater than the distance between the outside of the steel pipe pile 1 and the hole 7 of the reserved pile core 2 on the construction platform 6. Then the hoop 4 and the bottom plate 3 are fixedly connected, and rubber material is used to fill the bottom plate 3 and the steel pipe pile. 1, the hoop 4 is provided to support the bottom plate 3 and ensure the stability of the construction platform 6. The bottom plate 3 is provided to expand the resting area of the construction platform 6 and facilitate the installation of the construction platform 6. The stiffening plate 5 is provided to improve the ear plate. , the connection strength between grooved plates. By setting the bottom plate 3 as an assembled structure, the bottom plate 3 can be quickly assembled on the hoop 4, which facilitates prefabricated production and improves construction efficiency.
在另一种技术方案中,如图3所示,所述节点钢筋11包括两套横梁箍筋钢筋笼13、两套纵梁箍筋钢筋笼14和一套节点10中心区钢筋笼12,横梁箍筋钢筋笼13用于连接沿所述码头宽度方向设置的所述预制梁8,纵梁箍筋钢筋笼14用于连接沿所述码头长度方向设置的所述预制梁9,横梁箍筋钢筋笼13、纵梁箍筋钢筋笼14均至少间隔布置三层箍筋,每层箍筋分别与对应侧的所述第二钢筋连接,所述第一钢筋向上穿入连接至节点10中心区钢筋笼12的内部。In another technical solution, as shown in Figure 3, the node reinforcement 11 includes two sets of cross beam stirrup reinforcement cages 13, two sets of longitudinal beam stirrup reinforcement cages 14 and a set of node 10 center area reinforcement cages 12. The cross beam The stirrup steel cage 13 is used to connect the prefabricated beams 8 arranged along the width direction of the pier, the longitudinal beam stirrup steel cage 14 is used to connect the prefabricated beams 9 arranged along the length direction of the pier, and the stirrup steel bars of the cross beams The cage 13 and the longitudinal beam stirrup steel cage 14 are arranged with at least three layers of stirrups at intervals. Each layer of stirrups is connected to the second steel bar on the corresponding side. The first steel bar penetrates upward and is connected to the steel bar in the central area of the node 10. The interior of cage 12.
将节点钢筋11设置为可预制化的多种类型的钢筋笼,便于实现快速安装施工,钢筋笼可在预制场内绑扎成型后,通过平板车运输至现场,安装时整体起吊,节点10中心区钢筋笼12作为节点10处的主要受力钢筋,包含主筋及箍筋等,桩芯2的第一钢筋伸入在主要受力钢筋内,而设置的横梁箍筋钢筋笼13、纵梁箍筋钢筋笼14分别用于与周围的沿码头长度方向及沿码头宽度方向,即共四个方向设置的预制梁8、9的第二钢筋连接,横梁箍筋钢筋笼13、纵梁箍筋钢筋笼14设置尺寸较小,至少间隔布置3根箍筋,在浇筑节点10后,将第一钢筋、第二钢筋与横梁箍筋钢筋笼13、纵梁箍筋钢筋笼14、节点10中心区钢筋笼12锚固连接,由此实现节点10与预制梁(8、9)、桩芯2的连接。The node steel bars 11 are set as multiple types of steel cages that can be prefabricated to facilitate rapid installation and construction. The steel cages can be tied and formed in the prefabrication site and transported to the site by flatbed trucks. During installation, they are lifted as a whole. The steel bars in the center area of node 10 Cage 12 serves as the main stress-bearing steel bar at node 10, including main bars and stirrups. The first steel bar of pile core 2 extends into the main stress-bearing steel bar, and the cross-beam stirrup steel bar cage 13 and the longitudinal beam stirrup steel bars are provided. The cage 14 is used to connect with the surrounding second steel bars of the prefabricated beams 8 and 9 arranged along the length direction of the pier and along the width direction of the pier, that is, a total of four directions. The cross beam stirrup steel cage 13 and the longitudinal beam stirrup steel cage 14 The installation size is small, and at least 3 stirrups are arranged at intervals. After pouring node 10, connect the first steel bar, the second steel bar and the cross beam stirrup steel cage 13, the longitudinal beam stirrup steel cage 14, and the node 10 central area steel cage 12 Anchor connection is used to realize the connection between the node 10, the prefabricated beams (8, 9) and the pile core 2.
本发明还提供一种高桩码头新型上部结构的施工装备,如图5‐15所示,包括:The present invention also provides a new type of construction equipment for the superstructure of a high pile wharf, as shown in Figure 5-15, including:
支撑系统,其包括依次向上连接设置的底座结构21、回转结构23、固定支座211、一对主纵梁24,底座结构21的下端用于支撑于多个所述施工平台6上,回转结构23能带动固定支座211相对底座结构21沿水平方向自由旋转,一对主纵梁24相对且平行设置,固定支座211的两端分别与一个主纵梁24的底部滑动连接,一对主纵梁24在两端的顶部之间分别滑动连接有辅助横梁27,每个辅助横梁27上对称设置有可上下伸缩的辅助支腿28,用于临时支撑在对应位置的所述施工平台6上,一对主纵梁24的其中一端设置有配重29块;The support system includes a base structure 21, a rotary structure 23, a fixed support 211, and a pair of main longitudinal beams 24 that are connected upward in sequence. The lower end of the base structure 21 is used to support a plurality of the construction platforms 6. The rotary structure 23 can drive the fixed support 211 to freely rotate in the horizontal direction relative to the base structure 21. A pair of main longitudinal beams 24 are arranged opposite and parallel. The two ends of the fixed support 211 are respectively slidingly connected to the bottom of one main longitudinal beam 24. The longitudinal beams 24 are respectively slidably connected with auxiliary beams 27 between the tops of the two ends. Each auxiliary beam 27 is symmetrically provided with auxiliary legs 28 that can telescope up and down for temporary support on the construction platform 6 at the corresponding position. One end of a pair of main longitudinal beams 24 is provided with counterweights 29;
吊装系统,其包括滑动连接在一对主纵梁24的顶部之间的主横梁25,主横梁25位于固定支座211与其中一个辅助横梁27之间且与配重29块位于固定支座211的不同侧,主横梁25上滑动连接有移动天车26,移动天车26上设置有吊具210,在一对主纵梁24与固定支座211、未设置配重29块一侧的辅助横梁27之间围成吊具210的移动空间,形成吊装区域;The hoisting system includes a main crossbeam 25 slidably connected between the tops of a pair of main longitudinal beams 24. The main crossbeam 25 is located between a fixed support 211 and one of the auxiliary crossbeams 27 and is located on the fixed support 211 together with the counterweight 29. On different sides of the main beam 25, a movable crane 26 is slidably connected, and a spreader 210 is provided on the movable crane 26. On the pair of main longitudinal beams 24 and fixed supports 211, there is no auxiliary counterweight 29 on one side. The movement space of the spreader 210 is enclosed between the beams 27 to form a lifting area;
行走系统,其包括分别设置在辅助横梁27与主纵梁24之间、设置在固定支座211与主纵梁24之间、主横梁25与主纵梁24之间的行走机构212,行走机构212用于驱动对应连接的辅助横梁27或固定支座211或主横梁25相对主纵梁24发生移动;行走机构212包括对应设置的电气及液压系统,以及配合设置的滑轮结构。The traveling system includes a traveling mechanism 212 respectively provided between the auxiliary cross beam 27 and the main longitudinal beam 24, between the fixed support 211 and the main longitudinal beam 24, and between the main cross beam 25 and the main longitudinal beam 24. The traveling mechanism 212 is used to drive the corresponding connected auxiliary cross beam 27 or the fixed support 211 or the main cross beam 25 to move relative to the main longitudinal beam 24; the traveling mechanism 212 includes corresponding electrical and hydraulic systems, as well as a cooperating pulley structure.
在另一种技术方案中,所述底座结构21包括水平设置的底座支架,底座支架的顶部中心处与所述回转结构23的底部连接,底座支架的底部在水平面内沿矩形的四个顶角方位对撑布置有调位油缸,调位油缸的缸体与底座支架的底部固定且伸缩方向平行于矩形的对角线方向设置,调位油缸的伸缩端向下固定有底座支腿22,底座支腿22的上端与底座支架的底部滑动连接、底座支腿22的下端用于支撑固定在所述施工平台6上。In another technical solution, the base structure 21 includes a horizontally arranged base bracket. The top center of the base bracket is connected to the bottom of the rotating structure 23 . The bottom of the base bracket is along the four corners of the rectangle in the horizontal plane. The azimuth support is provided with an adjusting cylinder. The cylinder body of the adjusting cylinder is fixed to the bottom of the base bracket and the telescopic direction is parallel to the diagonal direction of the rectangle. The telescopic end of the adjusting cylinder is fixed with a base leg 22 downward. The base The upper end of the support leg 22 is slidingly connected to the bottom of the base bracket, and the lower end of the base support leg 22 is used to support and be fixed on the construction platform 6 .
通过调位油缸伸缩改变底座支腿22的位置,可根据相邻排及相邻列的施工平台6/桩基的间距调整,使每个底座支腿22平稳支撑在一个施工平台6上,提高施工装备的适用性。The position of the base leg 22 can be changed by telescopically adjusting the positioning cylinder, and can be adjusted according to the spacing between adjacent rows and columns of construction platforms 6/pile foundations, so that each base leg 22 can be stably supported on one construction platform 6, thereby improving Suitability of construction equipment.
本发明还提供一种高桩码头新型上部结构的施工装备的施工方法,如图5‐15所示,以离岸式宽平台码头为例,进行钢管桩1水上沉桩,桩基直径为1200mm,具体包括如下步骤:The present invention also provides a construction method for the construction equipment of the new superstructure of the high pile wharf. As shown in Figure 5-15, taking the offshore wide platform wharf as an example, the steel pipe pile 1 is piled on the water. The diameter of the pile foundation is 1200mm, specifically including the following steps:
S1:预制所述施工平台6、所述桩芯2、所述预制梁(8、9),所述桩芯2的顶部连接所述第一钢筋,所述预制梁(8、9)的两端连接所述第二钢筋。预制桩芯2直径按桩芯2与钢管桩1内壁80mm~100mm空隙控制,施工平台6分为两斜桩和三斜桩组合,两斜桩组合的预制施工平台6长宽高分别为6500mm×4000mm×800mm,三斜桩组合的预制施工平台6为品形结构,长宽高分别为7500mm×5000mm×800mm,施工平台6中间预留相应的桩芯2孔洞7,孔洞7直径按桩基偏位最大150mm考虑。S1: Prefabricate the construction platform 6, the pile core 2, and the prefabricated beams (8, 9). The top of the pile core 2 is connected to the first steel bar, and the two sides of the prefabricated beams (8, 9) The end is connected to the second steel bar. The diameter of the prefabricated pile core 2 is controlled according to the 80mm to 100mm gap between the pile core 2 and the inner wall of the steel pipe pile 1. The construction platform 6 is divided into a combination of two inclined piles and a three inclined pile. The length, width and height of the prefabricated construction platform 6 of the two inclined pile combination are 6500mm respectively. ×4000mm×800mm, the prefabricated construction platform 6 of the three-incline pile combination is a profile structure, with a length, width and height of 7500mm×5000mm×800mm respectively. The corresponding pile core 2 holes 7 are reserved in the middle of the construction platform 6, and the diameter of the holes 7 is according to the pile foundation. A maximum deviation of 150mm is considered.
S2:分别对每处所述桩基的单个所述斜桩对应安装所述抱箍4及所述底板3,所述底板3的内侧孔的面积略大于所述孔洞7的面积。耳板长度为500mm。S2: Install the hoop 4 and the bottom plate 3 correspondingly to each of the inclined piles of the pile foundation. The area of the inner hole of the bottom plate 3 is slightly larger than the area of the hole 7. The ear plate length is 500mm.
S3:安装所述施工平台6、所述桩芯2,将所述施工平台6搁置于对应所述桩基的所有所述底板3上,每个所述钢管桩1的顶部分别向上穿入一个所述孔洞7内,控制圆心偏差,使所述施工平台6位于对应的所述桩基的中心位置,然后在所述桩芯2的底部设置封底板3及止水橡胶圈,起吊所述桩芯2并插入至对应的所述钢管桩1内,在部分所述施工平台安装完成后,将所述施工装备支撑在已安装的所述施工平台上,继续进行剩下的所述施工平台、所述桩芯的吊装施工。预制桩芯2可通过在顶部设置环向预埋吊筋与钢管桩1反吊固定。S3: Install the construction platform 6 and the pile core 2, place the construction platform 6 on all the bottom plates 3 corresponding to the pile foundation, and penetrate the top of each steel pipe pile 1 upward. In one of the holes 7, control the deviation of the center of the circle so that the construction platform 6 is located at the center of the corresponding pile foundation, then set a bottom sealing plate 3 and a water-stop rubber ring at the bottom of the pile core 2, and lift the The pile core 2 is inserted into the corresponding steel pipe pile 1. After the installation of part of the construction platform is completed, the construction equipment is supported on the installed construction platform and the remaining construction is continued. Hoisting construction of platform and pile core. The prefabricated pile core 2 can be fixed by anti-hanging the steel pipe pile 1 by setting circumferential pre-embedded hanging bars on the top.
S4:桩芯2插入对应的钢管桩1内,采用灌浆材料对所述钢管桩1与所述桩芯2之间的空隙进行水下灌浆,以此代替传统的桩芯2混凝土浇筑工序,同时采用细石混凝土对所述孔洞7与所述钢管桩1之间的空隙进行灌注。S4: The pile core 2 is inserted into the corresponding steel pipe pile 1, and grouting material is used to grout the gap between the steel pipe pile 1 and the pile core 2 underwater, thereby replacing the traditional concrete pouring process of the pile core 2. , and at the same time, the gap between the hole 7 and the steel pipe pile 1 is filled with fine stone concrete.
S5:在所有位于所述码头的宽度方向或长度方向上相邻的两个所述施工平台6之间利用所述施工装备吊装所述预制梁(8、9),此时所述第一钢筋、所述第二钢筋均位于对应的所述施工平台6上。S5: Use the construction equipment to hoist the prefabricated beams (8, 9) between all two adjacent construction platforms 6 located in the width direction or length direction of the dock. At this time, the first steel bar , the second steel bars are located on the corresponding construction platform 6.
S6:进行所述节点钢筋11部品化制作,并设置箍筋,用于连接所述节点钢筋11与所述预制梁(8、9)的所述第二钢筋。S6: The node steel bars 11 are manufactured into parts, and stirrups are provided for connecting the node steel bars 11 and the second steel bars of the prefabricated beams (8, 9).
S7:在所述施工平台6上吊装所述节点钢筋11部品,连接所述施工平台6上的所述第一钢筋、所述第二钢筋,然后在所述施工平台6上安装所述节点10的模板,之后采用超高性能混凝土浇筑所述节点10,将位于同一所述施工平台6上的所述预制梁(8、9)、所述桩芯2锚固连接。S7: Hoist the node steel bar 11 components on the construction platform 6, connect the first steel bar and the second steel bar on the construction platform 6, and then install the node 10 on the construction platform 6 formwork, and then use ultra-high performance concrete to pour the nodes 10, and anchor the prefabricated beams (8, 9) and the pile core 2 located on the same construction platform 6.
S8:利用所述施工装备在已安装好的所述预制梁(8、9)上吊装预制面板15。S8: Use the construction equipment to hoist the prefabricated panels 15 on the installed prefabricated beams (8, 9).
在另一种技术方案中,如图5‐15所示,利用所述施工装备在吊装所述施工平台6、所述桩芯2、所述预制梁(8、9)时,底座结构21支撑在已安装好的所述施工平台6上,通过回转结构23带动主纵梁24、主横梁25、辅助横梁27同步旋转至预制好的所述施工平台6、所述桩芯2、所述预制梁(8、9)的上方,利用移动天车26移动吊具210进行取料,然后利用回转结构23旋转至待安装位置进行下放安装,当需要将施工装备整体移动至下一个施工位置时,通过行走机构212驱动辅助横梁27移动到已安装好的所述施工平台6的正上方,向下伸长辅助支腿28并支撑在对应的所述施工平台6上,使底座结构21的底部脱离对应的所述施工平台6,然后主纵梁24上对应的行走机构212驱动主纵梁24沿长度方向移动,带动底座结构21移动到下一个所述施工平台6上,缩回辅助支腿28,重新使底座结构21支撑在下方的所述施工平台6上,再通过辅助横梁27的行走结构在主纵梁24上移动辅助横梁27到初始位置,完成一次底座结构21的过跨前移,之后重复前述操作,通过回转结构23带动移动天车26及吊具210进行取料、下放安装,直至整个码头的所有所述施工平台6、所述桩芯2、所述预制梁(8、9)完成吊装。In another technical solution, as shown in Figure 5-15, when the construction equipment is used to hoist the construction platform 6, the pile core 2, and the prefabricated beams (8, 9), the base structure 21 supports On the installed construction platform 6, the main longitudinal beam 24, the main cross beam 25 and the auxiliary cross beam 27 are driven to rotate synchronously through the rotating structure 23 to the prefabricated construction platform 6, the pile core 2, the prefabricated Above the beams (8, 9), the mobile crane 26 is used to move the spreader 210 to retrieve materials, and then the rotating structure 23 is used to rotate to the position to be installed for lowering and installation. When the entire construction equipment needs to be moved to the next construction position, The auxiliary beam 27 is driven by the traveling mechanism 212 to move directly above the installed construction platform 6, and the auxiliary legs 28 are extended downward and supported on the corresponding construction platform 6, so that the bottom of the base structure 21 is detached. Corresponding to the construction platform 6, the corresponding traveling mechanism 212 on the main longitudinal beam 24 drives the main longitudinal beam 24 to move along the length direction, driving the base structure 21 to move to the next construction platform 6, and retracting the auxiliary legs 28 , re-support the base structure 21 on the construction platform 6 below, and then move the auxiliary beam 27 on the main longitudinal beam 24 to the initial position through the walking structure of the auxiliary beam 27, completing the over-span forward movement of the base structure 21. After that, the aforementioned operations are repeated, and the rotating structure 23 drives the mobile crane 26 and the spreader 210 to retrieve materials and lower them for installation until all the construction platforms 6, pile cores 2, and prefabricated beams (8, 9) of the entire wharf are installed. ) to complete the hoisting.
通过设置施工装备,施工装备支撑于桩顶的施工平台6,不受波浪、潮流影响,作业窗口增加,其中回转结构23可带动固定支座211相对底座结构21回转360°,底座结构21下的底座支腿22为主要支撑在施工平台6上的部件,辅助横梁27下的辅助支腿28作为临时支撑在施工平台6上的部件,在行走结构的驱动下使固定支座211、回转结构23、底座结构21一起相对主纵梁24发生移动或使辅助横梁27及辅助支腿28相对主纵梁24发生移动,使得辅助横梁27能够根据施工平台6的设置间隔调整辅助横梁27即辅助支腿28的位置,便于辅助支腿28位于一个施工平台6的正上方,从而使得底座支腿22与辅助支腿28交替支撑在前后方向上的施工平台6上,实现类似架桥机的过跨原理进行过跨前移,使施工装备整体沿码头长度方向或宽度方向移动,进行全方位施工,灵活便捷,作业效率高,施工成本小,尤其对于离岸式宽平台码头,可大幅度减少船机设备成本,解决船机设备无法从一侧覆盖码头整体宽度施工问题,且定位 安装精度高,施工质量得到显著提升。By setting up construction equipment, the construction equipment is supported on the construction platform 6 on top of the pile, which is not affected by waves and tidal currents, and the operating window is increased. The rotating structure 23 can drive the fixed support 211 to rotate 360° relative to the base structure 21. The base leg 22 is a component mainly supported on the construction platform 6, and the auxiliary leg 28 under the auxiliary beam 27 is a component temporarily supported on the construction platform 6. Driven by the walking structure, the fixed support 211 and the rotating structure 23 , the base structure 21 moves relative to the main longitudinal beam 24 together, or the auxiliary beam 27 and the auxiliary outrigger 28 move relative to the main longitudinal beam 24, so that the auxiliary beam 27 can adjust the auxiliary beam 27 or the auxiliary outrigger according to the setting interval of the construction platform 6 The position of 28 is convenient for the auxiliary leg 28 to be located directly above a construction platform 6, so that the base leg 22 and the auxiliary leg 28 are alternately supported on the construction platform 6 in the front and rear direction, realizing the over-span principle similar to that of a bridge erecting machine. By moving the span forward, the entire construction equipment can be moved along the length or width direction of the dock to carry out all-round construction. It is flexible and convenient, with high operating efficiency and low construction cost. Especially for offshore wide-platform docks, it can significantly reduce the number of ship machines. The equipment cost is reduced, and the problem of ship machinery equipment being unable to cover the entire width of the dock from one side is solved. The positioning and installation accuracy is high, and the construction quality is significantly improved.
在另一种技术方案中,如图8‐15所示,所述主纵梁24沿所述码头的长度方向设置时,在所述码头的长度方向上,所述配重29块与所述底座结构21的间距覆盖1个所述施工平台6,所述主横梁25在所述底座结构21与所述主纵梁24的对应端之间的移动范围覆盖2个所述施工平台6,所述底座结构21横跨在相邻的2~3个所述施工平台6上;In another technical solution, as shown in Figure 8-15, when the main longitudinal beam 24 is arranged along the length direction of the pier, in the length direction of the pier, the counterweight 29 and the The distance between the base structure 21 covers one of the construction platforms 6, and the movement range of the main beam 25 between the base structure 21 and the corresponding end of the main longitudinal beam 24 covers two of the construction platforms 6, so The base structure 21 spans two to three adjacent construction platforms 6;
在所述码头的宽度方向上,一对所述主纵梁24的间距覆盖2~3个所述施工平台6,所述移动天车26能沿所述主横梁25的长度方向移动,所述底座结构21覆盖2~3个相邻的所述施工平台6。In the width direction of the pier, the distance between a pair of main longitudinal beams 24 covers 2 to 3 construction platforms 6, and the mobile crane 26 can move along the length direction of the main beam 25. The base structure 21 covers 2 to 3 adjacent construction platforms 6 .
针对一般的码头桩基布置数量及施工装备在施工过程中吊装要求及配重29块的考虑,将吊装区域设置为基本覆盖2‐3个施工平台6的长度、且覆盖至少2‐3个施工平台6的宽度,控制施工装备整体框架尺寸在较为合理的范围内,兼具良好的经济性及施工工效,其中,底座结构21及底部设置的底座支腿22保证能对称支撑在4个施工平台6上即可,为保证吊装操作,在每个施工平台6处施工时,需当前的吊装区域大于单个施工平台6所需的施工区域,因此在吊装区域覆盖2‐3个施工平台6时,包含了对应数量的施工平台6的宽度及相邻的施工平台6之间的间距。In view of the general layout quantity of dock pile foundations and the hoisting requirements and counterweight of construction equipment during the construction process, the hoisting area is set to basically cover the length of 2-3 construction platforms 6 and cover at least 2-3 construction platforms. The width of the platform 6 controls the overall frame size of the construction equipment within a reasonable range, which has both good economy and construction efficiency. Among them, the base structure 21 and the base legs 22 provided at the bottom ensure that they can be symmetrically supported on four construction platforms. 6 is enough. In order to ensure the hoisting operation, when constructing at each construction platform 6, the current hoisting area needs to be larger than the construction area required for a single construction platform 6. Therefore, when the hoisting area covers 2-3 construction platforms 6, It includes the width of the corresponding number of construction platforms 6 and the spacing between adjacent construction platforms 6 .
在另一种技术方案中,如图8‐15所示,利用所述施工装备对施工平台6、桩芯2、预制梁(8、9)、预制面板15进行吊装施工时,采用如下步骤进行:In another technical solution, as shown in Figure 8-15, when using the construction equipment to hoist the construction platform 6, pile core 2, prefabricated beams (8, 9), and prefabricated panels 15, the following steps are used. :
A1:如图8所示,将码头的一顶角边缘处作为起始施工位置,并根据桩基位置设置存放区或停靠运输船,存放预制好的施工平台6、桩芯2、预制梁、预制面板15,施工平台6以位于码头的同一长度方向为一排、以位于码头的同一宽度方向为一列,完成起始施工位置的4个施工平台6及对应的桩芯2施工,将所述底座结构21支撑在4个施工平台6上,并向上依次拼装连接所述支撑系统的其余部件及所述吊装系统、所述行走系统;A1: As shown in Figure 8, take the top corner edge of the dock as the starting construction location, and set up a storage area or dock the transport ship according to the position of the pile foundation to store the prefabricated construction platform 6, pile core 2, prefabricated beams, The prefabricated panels 15 and the construction platforms 6 are arranged in a row in the same length direction of the pier and in a row in the same width direction of the pier. Complete the construction of the four construction platforms 6 and the corresponding pile cores 2 at the starting construction position. The base structure 21 is supported on four construction platforms 6, and is sequentially assembled upward to connect the remaining components of the support system, the hoisting system, and the walking system;
A2:如图9所示,利用所述回转结构23带动所述吊具210旋转至临近的存放区或停靠运输船取料,随后旋转所述回转结构23,带动所述吊具210旋转至起始施工位置位于码头长度方向的未施工一侧,此时所述主纵梁24与码头的长度方向平行,然后下放安装位于吊装区域内的施工平台6、桩芯2、预制梁;A2: As shown in Figure 9, use the rotating structure 23 to drive the spreader 210 to rotate to a nearby storage area or dock a transport ship to retrieve materials, and then rotate the rotating structure 23 to drive the spreader 210 to rotate to the lifting position. The starting construction position is located on the non-construction side of the length direction of the pier. At this time, the main longitudinal beam 24 is parallel to the length direction of the pier, and then the construction platform 6, pile core 2 and prefabricated beam located in the hoisting area are lowered and installed;
A3:如图10所示,利用所述回转结构23继续旋转90°,带动所述吊具210移动至起始施工位置位于码头宽度方向的未施工一侧,此时所述主纵梁24与码头的宽度方向平行,然后下放安装位于吊装区域内的施工平台6、桩芯2、预制梁;A3: As shown in Figure 10, use the rotating structure 23 to continue rotating 90° to drive the spreader 210 to move to the starting construction position on the unconstructed side in the width direction of the pier. At this time, the main longitudinal beam 24 and The width direction of the wharf is parallel, and then the construction platform 6, pile core 2 and prefabricated beam located in the hoisting area are lowered and installed;
A4:如图11所示,利用所述辅助横梁27、所述辅助支腿28及所述行走系统,使所述底座结构21沿码头宽度方向的远离起始施工位置的一侧过跨前移一个吊装区域的长度单位,随后所述回转结构23旋转180°,使吊装区域位于起始施工位置上方,补充安装起始施工位置的所有预制梁;A4: As shown in Figure 11, the auxiliary beam 27, the auxiliary leg 28 and the walking system are used to move the base structure 21 forward along the width direction of the pier on the side away from the starting construction position. The length unit of a hoisting area, and then the revolving structure 23 is rotated 180° so that the hoisting area is above the starting construction position, and all prefabricated beams at the starting construction position are supplemented and installed;
A5:如图12所示,利用所述回转结构23旋转90°,使吊装区域位于码头长度方向的未施工一侧,进行施工平台6、桩芯2、预制梁的吊装,之后如图13所示,使所述底座结构21沿码头的长度方向过跨前移一个吊装区域的长度单位,至此,完成起始施工位置位于一个吊装区域的长度单位的所有列的施工平台6、桩芯2、预制梁的安装;A5: As shown in Figure 12, use the slewing structure 23 to rotate 90° so that the hoisting area is located on the non-construction side of the length of the pier, and hoist the construction platform 6, pile core 2, and prefabricated beams, and then as shown in Figure 13 shows that the base structure 21 is moved forward by a unit of length of the hoisting area along the length direction of the pier. At this point, the construction platform 6, pile core 2, Installation of precast beams;
A6:如图14所示,对位于过跨前移后的吊装区域内桩基进行施工平台6、桩芯2、预制梁的吊装,旋转所述回转结构23,补充安装位于所述底座结构21在码头的宽度方向的预制梁,同期,安装位于所述底座结构21在码头的宽度方向上已施工一侧的预制面板15;A6: As shown in Figure 14, hoist the construction platform 6, pile core 2, and prefabricated beams on the pile foundation in the hoisting area after the span has been moved forward, rotate the rotary structure 23, and additionally install the base structure 21 Precast beams in the width direction of the pier, and at the same time, install precast panels 15 on the side of the base structure 21 that has been constructed in the width direction of the pier;
A7:如图15所示,利用所述辅助横梁27、所述辅助支腿28及所述行走系统,使所述底座结构21沿码头宽度方向的朝向起始施工位置的一侧逐步过跨前移到顶,同时,每次过跨前移利用所述回转结构23配合安装位于所述底座结构21在码头的长度方向的未施工一侧的施工平台6、桩芯2、预制梁和已施工一侧的预制面板15;A7: As shown in Figure 15, the auxiliary beam 27, the auxiliary leg 28 and the walking system are used to gradually make the side of the base structure 21 toward the starting construction position along the width direction of the pier gradually pass the front of the span. At the same time, the rotating structure 23 is used to install the construction platform 6, the pile core 2, the prefabricated beam and the constructed one on the unconstructed side of the base structure 21 in the length direction of the pier each time the span is moved forward. Side prefabricated panels 15;
A8:重复驱动所述施工装备依次沿未施工一侧的码头的宽度方向、长度方向、宽度方向移动,配合旋转所述回转结构23及所述吊具210的取料、吊装,完成整个码头的施工平台6、桩芯2、预制梁、预制面板15的施工,从而完成高桩码头新型上部结构的一体化安装。A8: Repeatedly drive the construction equipment to move along the width direction, length direction, and width direction of the pier on the non-construction side, and cooperate with the rotation of the rotating structure 23 and the lifting of the spreader 210 to complete the entire pier. The construction of the construction platform 6, pile core 2, prefabricated beams, and prefabricated panels 15 completes the integrated installation of the new superstructure of the high pile wharf.
具体的,结合图8‐图15所示,给出如下实施步骤,为方便说明,以图8的左右方向为码头的长度方向、图5的上下方向为码头的宽度方向,主纵梁24以配重29块所在一端为后端,以吊装区域所在一端为前端,施工平台6在图5的竖向为一列、横向为一排:Specifically, as shown in Figures 8 to 15, the following implementation steps are given. For the convenience of explanation, the left and right directions in Figure 8 are the length direction of the pier, and the up and down directions in Figure 5 are the width direction of the pier. The main longitudinal beam 24 is The end where the counterweight 29 is located is the rear end, and the end where the hoisting area is located is the front end. The construction platforms 6 are in one row vertically and in one row horizontally in Figure 5:
(1)如图8所示,完成起始施工位置为①、②列的E、F排共四个施工平台6及桩芯2施工,然后由下至上拼装施工装备,底座支腿22设置有四个,四个底座支腿22支撑在这四个施工平台6上,横跨①、②列,主纵梁24平行于码头长度方向,从底座结构21至主纵梁24前端为吊装范围,覆盖2列施工平台6,底座结构21至主纵梁24后端为配重29范围,覆盖1列施工平台6,一对主纵梁24的间距覆盖3列施工平台6,辅助支腿28在每个辅助横梁27上设置两个,两个辅助支腿28分别与①、②列的施工平台6的位置间隔设置一致,辅助支腿28相对尺寸较小,不占用施工平台6过多空间。(1) As shown in Figure 8, complete the construction of a total of four construction platforms 6 and pile cores 2 in rows E and F at the starting construction positions of ① and ②, and then assemble the construction equipment from bottom to top. The base legs 22 are provided with Four, four base legs 22 are supported on these four construction platforms 6, spanning the ① and ② columns. The main longitudinal beam 24 is parallel to the length direction of the pier. The hoisting range is from the base structure 21 to the front end of the main longitudinal beam 24. Covering 2 rows of construction platforms 6, the base structure 21 to the rear end of the main longitudinal beam 24 is the counterweight 29 range, covering 1 row of construction platforms 6, the distance between a pair of main longitudinal beams 24 covers 3 rows of construction platforms 6, and the auxiliary outriggers 28 are at Two auxiliary beams 27 are provided on each auxiliary beam 27, and the two auxiliary legs 28 are arranged at consistent intervals with the construction platforms 6 in rows ① and ② respectively. The auxiliary legs 28 are relatively small in size and do not occupy too much space on the construction platform 6.
(2)吊具210取施工平台6/桩芯2/预制梁后旋转至图9所示位置,定位于抱箍4、底板3顶部,确保施工平台6的孔洞7中心与钢管桩1的圆心控制在偏差范围内后进行下放安装,如图11所示,完成③~④列的
Figure PCTCN2022104172-appb-000001
排的施工平台6、桩芯2、预制梁下放安装。
(2) The spreader 210 takes the construction platform 6/pile core 2/prefabricated beam and rotates it to the position shown in Figure 9, and positions it on the hoop 4 and the top of the bottom plate 3 to ensure that the center of the hole 7 of the construction platform 6 is in line with the steel pipe pile 1 After the center of the circle is controlled within the deviation range, proceed to the lower level installation. As shown in Figure 11, complete the steps in columns 3 to 4.
Figure PCTCN2022104172-appb-000001
The row of construction platform 6, pile core 2, and prefabricated beams are lowered and installed.
(3)回转结构23驱动施工装备旋转至图10位置,安装①、②列
Figure PCTCN2022104172-appb-000002
列施工平台6、预制桩芯2、预制梁;待预制梁安装完成后,在对应的施工平台6上进行桩顶的节点钢筋11、模板、混凝土工序施工,以浇筑形成节点10。
(3) The rotating structure 23 drives the construction equipment to rotate to the position shown in Figure 10, and installs the ① and ② columns.
Figure PCTCN2022104172-appb-000002
The construction platform 6, the prefabricated pile core 2, and the prefabricated beam are arranged in a row; after the installation of the prefabricated beam is completed, the node reinforcement 11, formwork, and concrete process of the pile top are carried out on the corresponding construction platform 6 to form the node 10 by pouring.
(4)施工装备向下移动,如图11所示,由前端的两个辅助支腿28支撑在①、②列的
Figure PCTCN2022104172-appb-000003
排的两个施工平台6,后端的辅助支腿28支撑在①、②列的
Figure PCTCN2022104172-appb-000004
排的两个施工平台6,向下撑开辅助支腿28,使底座支腿22腾空,然后行走机构212驱动主纵梁24及底座结构21移动至①、②列的
Figure PCTCN2022104172-appb-000005
施工平台6,然后收回辅助支腿28使底座支腿22重新支撑在新的施工平台6上,再驱动辅助横梁27回到初始的端部位置,当然也可根据过跨需要,直接通过与固定支座211连接的行走机构212驱动固定支座211、底座结构21调整相对位置,之后再还原;通过回转结构23调整吊装区域的朝向,依次安装剩下的①、②列的
Figure PCTCN2022104172-appb-000006
的施工平台6、桩芯2、预制梁。
(4) The construction equipment moves downward, as shown in Figure 11, supported by the two auxiliary legs 28 at the front end in the ① and ② columns.
Figure PCTCN2022104172-appb-000003
The two construction platforms 6 in the row are supported by the auxiliary legs 28 at the rear end in rows ① and ②.
Figure PCTCN2022104172-appb-000004
The two construction platforms 6 in the row push down the auxiliary legs 28 to make the base legs 22 empty, and then the walking mechanism 212 drives the main longitudinal beam 24 and the base structure 21 to move to the ① and ② rows.
Figure PCTCN2022104172-appb-000005
Construction platform 6, then retract the auxiliary legs 28 to re-support the base legs 22 on the new construction platform 6, and then drive the auxiliary beam 27 back to the initial end position. Of course, it can also be directly passed and fixed according to the span requirements. The traveling mechanism 212 connected to the support 211 drives the fixed support 211 and the base structure 21 to adjust their relative positions and then restore them; adjust the orientation of the hoisting area through the rotating structure 23, and install the remaining columns ① and ② in sequence.
Figure PCTCN2022104172-appb-000006
Construction platform 6, pile core 2, prefabricated beam.
(5)通过回转结构23调整吊装区域的朝向,安装③~④列的
Figure PCTCN2022104172-appb-000007
施工平台6、桩芯2、预制梁,见图12,至此,完成了①、②列所有施工平台6、桩芯2、预制梁施工。同时针对①、②列的所有节点10浇筑施工。
(5) Adjust the direction of the hoisting area through the rotating structure 23, and install the ③~④ rows
Figure PCTCN2022104172-appb-000007
Construction platform 6, pile core 2, and prefabricated beams are shown in Figure 12. At this point, the construction of all construction platforms 6, pile core 2, and prefabricated beams in columns 1 and 2 has been completed. At the same time, pouring construction is carried out for all nodes 10 in columns ① and ②.
(6)如图13所示,施工装备向右过跨前移,底座结构21、底座支腿22支撑于③~④列的
Figure PCTCN2022104172-appb-000008
施工平台6,进行⑤、⑥的
Figure PCTCN2022104172-appb-000009
桩芯2、施工平台6、预制梁吊装施工,回转结构23旋转吊装区域,补充安装③~④列的
Figure PCTCN2022104172-appb-000010
的预制梁,同时,安装①、②列的
Figure PCTCN2022104172-appb-000011
之间的预制面板15,见图10。
(6) As shown in Figure 13, the construction equipment moves forward across the span to the right, and the base structure 21 and base legs 22 are supported on the ③~④ rows.
Figure PCTCN2022104172-appb-000008
Construction platform 6, perform ⑤ and ⑥
Figure PCTCN2022104172-appb-000009
Pile core 2, construction platform 6, prefabricated beam hoisting construction, rotating structure 23 rotating hoisting area, supplementary installation of columns 3 to 4
Figure PCTCN2022104172-appb-000010
of prefabricated beams, and at the same time, install the ① and ② columns
Figure PCTCN2022104172-appb-000011
15 prefabricated panels between them, see Figure 10.
(7)施工装备整体向上行走,底座支腿22支撑于③~④列的
Figure PCTCN2022104172-appb-000012
桩顶的施工平台6,进行⑤、⑥列的
Figure PCTCN2022104172-appb-000013
预制桩芯2、预制施工平台6、预制梁吊装施工,同时,安装①、②列的
Figure PCTCN2022104172-appb-000014
Figure PCTCN2022104172-appb-000015
之间的预制面板15,见图14,施工装备继续上行,底座支腿22支撑于③~④列的
Figure PCTCN2022104172-appb-000016
施工平台6,对⑤、⑥列的
Figure PCTCN2022104172-appb-000017
预制桩芯2、预制施工平台6、预制梁吊装施工,同时,安装①、②列的
Figure PCTCN2022104172-appb-000018
Figure PCTCN2022104172-appb-000019
之间的预制面板15,见图15。
(7) The construction equipment moves upward as a whole, and the base legs 22 are supported on the ③~④ rows.
Figure PCTCN2022104172-appb-000012
On the construction platform 6 on top of the pile, perform the steps ⑤ and ⑥.
Figure PCTCN2022104172-appb-000013
Prefabricated pile core 2, prefabricated construction platform 6, prefabricated beam hoisting construction, at the same time, install the ① and ② columns
Figure PCTCN2022104172-appb-000014
Figure PCTCN2022104172-appb-000015
The prefabricated panels 15 between them are shown in Figure 14. The construction equipment continues to move upward, and the base legs 22 are supported on the ③~④ columns.
Figure PCTCN2022104172-appb-000016
Construction platform 6, for columns ⑤ and ⑥
Figure PCTCN2022104172-appb-000017
Prefabricated pile core 2, prefabricated construction platform 6, prefabricated beam hoisting construction, at the same time, install the ① and ② columns
Figure PCTCN2022104172-appb-000018
Figure PCTCN2022104172-appb-000019
15 prefabricated panels between them, see Figure 15.
(8)以此形成流水作业,逐步向前推进,直至桩顶预制桩芯2、预制施工平台6、预制梁、预制面板15施工完成。(8) This forms a flow operation and gradually advances until the prefabricated pile core 2 on the pile top, the prefabricated construction platform 6, the prefabricated beams, and the prefabricated panels 15 are completed.
尽管本发明的实施方案已公开如上,但其并不仅仅限于说明书和实施方式中所列运用,它完全可以被适用于各种适合本发明的领域,对于熟悉本领域的人员而言,可容易地实现另外的修改,因此在不背离权利要求及等同范围所限定的一般概念下,本发明并不限于特定的细节和这里示出与描述的图例。Although the embodiments of the present invention have been disclosed above, they are not limited to the applications listed in the description and embodiments. They can be applied to various fields suitable for the present invention. For those familiar with the art, they can easily Additional modifications may be made, and the invention is therefore not limited to the specific details and illustrations shown and described herein without departing from the general concept defined by the claims and equivalent scope.

Claims (10)

  1. 一种高桩码头新型上部结构,设置在码头的桩基的顶部,每处桩基包括两个斜桩或三个斜桩,每个斜桩的钢管桩内侧上端设置有预制桩芯,其特征在于,包括:A new type of superstructure for a high-pile wharf, which is set on the top of the pile foundation of the wharf. Each pile foundation includes two inclined piles or three inclined piles. The upper end of the inner side of the steel pipe pile of each inclined pile is provided with a prefabricated pile core. Characteristics include:
    在每个斜桩上靠近顶部的位置抱紧设置的抱箍,抱箍的上表面连接有底板,底板套设在对应的斜桩上,预制桩芯的上端向外延伸设置有第一钢筋;A hoop is placed close to the top of each inclined pile. The upper surface of the hoop is connected to a bottom plate. The bottom plate is set on the corresponding inclined pile. The upper end of the prefabricated pile core is extended outward with a first steel bar;
    施工平台,其对应每处的桩基分别水平设置一个且连接在对应处的所有底板的上表面,施工平台上对应桩基的每个斜桩分别开设有一个沿竖向贯通且尺寸大于钢管桩的孔洞,以使对应位置的钢管桩的顶部穿入,施工平台的顶面与斜桩的顶部齐平,施工平台上设置有节点钢筋;The construction platform has a horizontal pile corresponding to each pile foundation and is connected to the upper surface of all bottom plates at the corresponding place. Each inclined pile corresponding to the pile foundation on the construction platform is provided with a vertically connected and larger than steel pipe. The holes of the piles are designed so that the tops of the steel pipe piles at the corresponding positions can penetrate, the top surface of the construction platform is flush with the top of the inclined piles, and node steel bars are provided on the construction platform;
    预制梁,其沿码头的长度方向或沿码头的宽度方向分别设置,每相邻的两个施工平台的上表面之间共同连接一个预制梁,预制梁的两端分别向外延伸设置有第二钢筋;The prefabricated beams are respectively arranged along the length direction of the pier or along the width direction of the pier. A prefabricated beam is connected between the upper surfaces of each adjacent two construction platforms. The two ends of the prefabricated beams are respectively extended outwards and provided with a second prefabricated beam. steel bars;
    节点,其由超高性能混凝土浇筑设置在施工平台上且将第一钢筋、第二钢筋、节点钢筋锚固连接在内部。The node is made of ultra-high performance concrete poured and set on the construction platform, and the first steel bar, the second steel bar, and the node steel bar are anchored and connected internally.
  2. 如权利要求1所述的高桩码头新型上部结构,其特征在于,位于所述码头的长度方向的最外两侧的所述桩基均包括三个所述斜桩,其余的所述桩基分别包括两个所述斜桩,对应位于所述码头的长度方向的最外两侧的每个所述施工平台上分别开设三个所述孔洞,其余位置的所述施工平台上分别开设两个所述孔洞。The new superstructure of a high pile wharf according to claim 1, characterized in that the pile foundations located on the outermost two sides of the length direction of the wharf each include three inclined piles, and the remaining pile foundations Each includes two inclined piles, three holes are respectively provided on each construction platform located on the outermost sides of the length direction of the pier, and two holes are respectively provided on the construction platforms at other positions. The hole.
  3. 如权利要求1所述的高桩码头新型上部结构,其特征在于,所述抱箍包括环绕所述斜桩的外侧设置的多个圆弧形的凹槽板,凹槽板的数量至少设置有四个,每个凹槽板的两端分别沿所述斜桩的径向向外连接有耳板,相邻的凹槽板之间通过同侧的两个耳板固定连接,每个耳板与对应的凹槽板的外侧之间连接有若干个加劲板,所述底板由两块连接板拼装连接而成,连接板上对应所述钢管桩开设有半圆弧形的凹槽。The new superstructure of a high pile wharf according to claim 1, wherein the hoop includes a plurality of arc-shaped groove plates arranged around the outside of the inclined pile, and the number of groove plates is at least Four, the two ends of each groove plate are respectively connected with ear plates outward along the radial direction of the inclined pile. The adjacent groove plates are fixedly connected by two ear plates on the same side. Each ear plate Several stiffening plates are connected to the outside of the corresponding groove plate. The bottom plate is assembled and connected by two connecting plates. Semi-circular arc-shaped grooves are provided on the connecting plates corresponding to the steel pipe piles.
  4. 如权利要求1所述的高桩码头新型上部结构,其特征在于,所述节点钢筋包括两套横梁箍筋钢筋笼、两套纵梁箍筋钢筋笼和一套节点中心区钢筋笼,横梁箍筋钢筋笼用于连接沿所述码头宽度方向设置的所述预制梁,纵梁箍筋钢筋笼用于连接沿所述码头长度方向设置的所述预制梁,横梁箍筋钢筋笼、纵梁箍筋钢筋笼均至少间隔布置三层箍筋,每层箍筋分别与对应侧的所述第二钢筋连接,所述第一钢筋向上穿入连接至节点中心区钢筋笼的内部。The new superstructure of a high pile wharf according to claim 1, characterized in that the node steel bars include two sets of cross beam stirrup steel cages, two sets of longitudinal beam stirrup steel cages and a set of node center area steel cages. The cross beam stirrup cages Reinforcement cages are used to connect the prefabricated beams arranged along the width direction of the dock, longitudinal beam stirrup reinforcement cages are used to connect the prefabricated beams arranged along the length direction of the dock, cross beam stirrup reinforcement cages, longitudinal beam hoops The steel cages are arranged with at least three layers of stirrups at intervals, and each layer of stirrups is connected to the second steel bar on the corresponding side. The first steel bar penetrates upward and is connected to the inside of the steel cage in the center area of the node.
  5. 如权利要求1所述的高桩码头新型上部结构的施工装备,其特征在于,包括:The construction equipment for the new superstructure of the high pile wharf according to claim 1, characterized in that it includes:
    支撑系统,其包括依次向上连接设置的底座结构、回转结构、固定支座、一对主纵梁,底座结构的下端用于支撑于多个所述施工平台上,回转结构能带动固定支座相对底座结构沿水平方向自由旋转,一对主纵梁相对且平行设置,固定支座的两端分别与一个主纵梁的底部滑动连接,一对主纵梁在两端的顶部之间分别滑动连接有辅助横梁,每个辅助横梁上对称设置有可上下伸缩的辅助支腿,用于临时支撑在对应位置的所述施工平台上,一对主纵梁的其中一端设置有配重块;The support system includes a base structure, a rotary structure, a fixed support and a pair of main longitudinal beams connected upward in sequence. The lower end of the base structure is used to support multiple construction platforms. The rotary structure can drive the fixed supports to face each other. The base structure rotates freely in the horizontal direction. A pair of main longitudinal beams are arranged opposite and parallel. The two ends of the fixed support are slidingly connected to the bottom of one main longitudinal beam. A pair of main longitudinal beams are slidingly connected between the tops of the two ends. Auxiliary beams. Each auxiliary beam is symmetrically provided with auxiliary legs that can be telescopic up and down for temporary support on the construction platform at the corresponding position. One end of a pair of main longitudinal beams is provided with a counterweight block;
    吊装系统,其包括滑动连接在一对主纵梁的顶部之间的主横梁,主横梁位于固定支座与其中一个辅助横梁之间且与配重块位于固定支座的不同侧,主横梁上滑动连接有移动天车,移动天车上设置有吊具,在一对主纵梁与固定支座、未设置配重块一侧的辅助横梁之间围成吊具的移动空间,形成吊装区域;Hoisting system, which includes a main crossbeam slidably connected between the tops of a pair of main longitudinal beams, the main crossbeam being located between a fixed support and one of the auxiliary crossbeams and located on a different side of the fixed support from the counterweight block on the main crossbeam A mobile crane is slidingly connected, and a spreader is installed on the mobile crane. A moving space for the spreader is formed between a pair of main longitudinal beams, a fixed support, and an auxiliary beam on the side without a counterweight block, forming a lifting area. ;
    行走系统,其包括分别设置在辅助横梁与主纵梁之间、设置在固定支座与主纵梁之间、主横梁与主纵梁之间的行走机构,行走机构用于驱动对应连接的辅助横梁或固定支座或主横梁相对主纵梁发生移动。The traveling system includes traveling mechanisms respectively arranged between the auxiliary beam and the main longitudinal beam, between the fixed support and the main longitudinal beam, and between the main beam and the main longitudinal beam. The traveling mechanism is used to drive the corresponding connected auxiliary beams. The crossbeam or fixed support or main crossbeam moves relative to the main longitudinal beam.
  6. 如权利要求5所述的高桩码头新型上部结构的施工装备,其特征在于,所述底座结构包括水平设置的底座支架,底座支架的顶部中心处与所述回转结构的底部连接,底座支架的底部在水平面内沿矩形的四个顶角方位对撑布置有调位油缸,调位油缸的缸体与底座支架的底部固定且伸缩方向平行于矩形的对角线方向设置,调位油缸的伸缩端向下固定有底座支腿,底座支腿的上端与底座支架的底部滑动连接、底座支腿的下端用于支撑固定在所述施工平台上。The construction equipment for the new superstructure of the high pile wharf according to claim 5, characterized in that the base structure includes a horizontally arranged base bracket, the top center of the base bracket is connected to the bottom of the rotary structure, and the base bracket is The bottom is arranged with an adjusting cylinder in the horizontal plane along the four top corners of the rectangle. The cylinder of the adjusting cylinder is fixed to the bottom of the base bracket and the telescopic direction is parallel to the diagonal direction of the rectangle. The telescopic cylinder A base leg is fixed downward at the end, the upper end of the base leg is slidingly connected to the bottom of the base bracket, and the lower end of the base leg is used to support and be fixed on the construction platform.
  7. 如权利要求5所述的高桩码头新型上部结构的施工装备的施工方法,其特征在于,包括如下步骤:The construction method of the construction equipment of the new superstructure of the high pile wharf according to claim 5, characterized in that it includes the following steps:
    S1:预制所述施工平台、所述桩芯、所述预制梁,所述桩芯的顶部连接所述第一钢筋,所述预制梁的两端连接所述第二钢筋;S1: Prefabricate the construction platform, the pile core, and the prefabricated beam. The top of the pile core is connected to the first steel bar, and both ends of the prefabricated beam are connected to the second steel bar;
    S2:分别对每处所述桩基的单个所述斜桩对应安装所述抱箍及所述底板,所述底板的内侧孔的面积略大于所述孔洞的面积;S2: Install the hoop and the bottom plate correspondingly to each of the inclined piles of the pile foundation, and the area of the inner hole of the bottom plate is slightly larger than the area of the hole;
    S3:安装所述施工平台、所述桩芯,将所述施工平台搁置于对应所述桩基的所有所述底板上,每个所述钢管桩的顶部分别向上穿入一个所述孔洞内,控制圆心偏差,使所述施工平台位于对应的所述桩基的中心位置,然后在所述桩芯的底部设置封底板及止水橡胶圈,起吊所述桩芯并插入至对应的所述钢管桩内,在部分所述施工平台安装完成后,将所述施工装备支撑在已安装的所述施工平台上,继续进行剩下的所述施工平台、所述桩芯的吊装施工;S3: Install the construction platform and pile core, place the construction platform on all the bottom plates corresponding to the pile foundation, and penetrate the top of each steel pipe pile upward into one of the holes. , control the center deviation of the circle so that the construction platform is located at the center of the corresponding pile foundation, then set a bottom sealing plate and a water-stop rubber ring at the bottom of the pile core, lift the pile core and insert it into the corresponding pile foundation In the steel pipe pile, after the installation of part of the construction platform is completed, the construction equipment is supported on the installed construction platform, and the hoisting construction of the remaining construction platform and pile core is continued;
    S4:采用灌浆材料对所述钢管桩与所述桩芯之间的空隙进行水下灌浆,采用细石混凝土对所述孔洞与所述钢管桩之间的空隙进行灌注;S4: Use grouting material to grout the gap between the steel pipe pile and the pile core underwater, and use fine stone concrete to grout the gap between the hole and the steel pipe pile;
    S5:在所有位于所述码头的宽度方向或长度方向上相邻的两个所述施工平台之间利用所述施工装备吊装所述预制梁,此时所述第一钢筋、所述第二钢筋均位于对应的所述施工平台上;S5: Use the construction equipment to hoist the prefabricated beam between all two adjacent construction platforms located in the width direction or length direction of the dock. At this time, the first steel bar and the second steel bar are All are located on the corresponding construction platform;
    S6:进行所述节点钢筋部品化制作,并设置箍筋,用于连接所述节点钢筋与所述预制梁的所述第二钢筋;S6: Make the node steel bars into parts, and set stirrups for connecting the node steel bars and the second steel bars of the prefabricated beam;
    S7:在所述施工平台上吊装所述节点钢筋部品,连接所述施工平台上的所述第一钢筋、所述第二钢筋,然后在所述施工平台上安装所述节点的模板,之后采用超高性能混凝土浇筑所述节点,将位于同一所述施工平台上的所述预制梁、所述桩芯锚固连接;S7: Hoist the node steel bar components on the construction platform, connect the first steel bar and the second steel bar on the construction platform, and then install the node template on the construction platform, and then use The nodes are poured with ultra-high performance concrete, and the prefabricated beams and pile cores located on the same construction platform are anchored and connected;
    S8:利用所述施工装备在已安装好的所述预制梁上吊装预制面板。S8: Use the construction equipment to hoist the prefabricated panels on the installed prefabricated beams.
  8. 如权利要求6所述的高桩码头新型上部结构的施工装备的施工方法,其特征在于,利用所述施工装备在吊装所述施工平台、所述桩芯、所述预制梁时,所述底座结构支撑在已安装好的所述施工平台上,通过所述回转结构带动所述主纵梁、所述主横梁、所述辅助横梁同步旋转至预制好的所述施工平台、所述桩芯、所述预制梁的上方,利用所述移动天车移动所述吊具进行取料,然后利用所述回转结构旋转至待安装位置进行下放安装,当需要将所述施工装备整体移动至下一个施工位置时,通过所述行走机构驱动所述辅助横梁移动到已安装好的所述施工平台的正上方,向下伸长所述辅助支腿并支撑在对应的所述施工平台上,使所述底座结构的底部脱离对应的所述施工平台,然后所述主纵梁上对应的所述行走机构驱动所述主纵梁沿长度方向移动,带动所述底座结构移动到下一个所述施工平台上,缩回所述辅助支腿,重新使所述底座结构支撑在下方的所述施工平台上,再通过所述辅助横梁的所述行走结构在所述主纵梁上移动所述辅助横梁到初始位置,完成一次所述底座结构的过跨前移,之后重复前述操作,通过所述回转结构带动所述移动天车及所述吊具进行取料、下放安装,直至整个码头的所有所述施工平台、所述桩芯、所述预制梁完成吊装。The construction method of the construction equipment of the new superstructure of the high pile wharf according to claim 6, characterized in that when the construction equipment is used to hoist the construction platform, the pile core and the prefabricated beam, the base The structure is supported on the installed construction platform, and the rotating structure drives the main longitudinal beam, the main beam, and the auxiliary beam to rotate synchronously to the prefabricated construction platform, pile core, Above the prefabricated beam, the mobile crane is used to move the spreader to retrieve materials, and then the rotating structure is used to rotate to the position to be installed for lowering and installation. When it is necessary to move the entire construction equipment to the next construction position, the walking mechanism drives the auxiliary beam to move directly above the installed construction platform, extends the auxiliary leg downward and supports it on the corresponding construction platform, so that the The bottom of the base structure breaks away from the corresponding construction platform, and then the corresponding walking mechanism on the main longitudinal beam drives the main longitudinal beam to move along the length direction, driving the base structure to move to the next construction platform. , retract the auxiliary legs, re-support the base structure on the construction platform below, and then move the auxiliary beam on the main longitudinal beam to the initial position through the walking structure of the auxiliary beam. Position, complete the over-span forward movement of the base structure once, and then repeat the aforementioned operation, driving the mobile crane and the spreader through the rotating structure to retrieve materials, lower them for installation, until all the construction of the entire wharf The platform, the pile core and the prefabricated beam are hoisted.
  9. 如权利要求8所述的高桩码头新型上部结构的施工装备的施工方法,其特征在于,所述主纵梁沿所述码头的长度方向设置时,在所述码头的长度方向上,所述配重块与所述底座结构的间距覆盖1个所述施工平台,所述主横梁在所述底座结构与所述主纵梁的对应端之间的移动范围覆盖2个所述施工平台,所述底座结构横跨在相邻的2~3个所述施工平台上;The construction method of the construction equipment of the new superstructure of the high pile wharf according to claim 8, characterized in that when the main longitudinal beam is arranged along the length direction of the wharf, in the length direction of the wharf, the The distance between the counterweight block and the base structure covers one of the construction platforms, and the movement range of the main beam between the base structure and the corresponding end of the main longitudinal beam covers two of the construction platforms, so The base structure spans 2 to 3 adjacent construction platforms;
    在所述码头的宽度方向上,一对所述主纵梁的间距覆盖2~3个所述施工平台,所述移动天车能沿所述主横梁的长度方向移动,所述底座结构覆盖2~3个相邻的所述施工平台。In the width direction of the pier, the distance between a pair of main longitudinal beams covers 2 to 3 construction platforms, the mobile crane can move along the length direction of the main beams, and the base structure covers 2 ~3 adjacent construction platforms.
  10. 如权利要求8所述的高桩码头新型上部结构的施工装备的施工方法,其特征在于,利用所述施工装备对施工平台、桩芯、预制梁、预制面板进行吊装施工时,采用如下步骤进行:The construction method of the construction equipment of the new superstructure of the high pile wharf according to claim 8, characterized in that when using the construction equipment to hoist the construction platform, pile core, prefabricated beams and prefabricated panels, the following steps are used. :
    A1:将码头的一顶角边缘处作为起始施工位置,并根据桩基位置设置存放区或停靠运输船,存放预制好的施工平台、桩芯、预制梁、预制面板,施工平台以位于码头的同一长度方向为一排、以位于码头的同一宽度方向为一列,完成起始施工位置的4个施工平台及对应的桩芯施工,将所述底座结构支撑在4个施工平台上,并向上依次拼装连接所述支撑系统的其余部件及所述吊装系统、所述行走系统;A1: Use one corner edge of the pier as the starting construction location, and set up a storage area or dock a transport ship according to the position of the pile foundation to store the prefabricated construction platform, pile core, prefabricated beams, and prefabricated panels. The construction platform should be located at the pier. The same length direction is one row, and the same width direction at the dock is one row. Complete the construction of the 4 construction platforms and the corresponding pile cores at the starting construction position. Support the base structure on the 4 construction platforms and upwards. Assemble and connect the remaining components of the support system, the hoisting system, and the walking system in sequence;
    A2:利用所述回转结构带动所述吊具旋转至临近的存放区或停靠运输船取料,随后旋转所述回转结构,带动所述吊具旋转至起始施工位置位于码头长度方向的未施工一侧,此时所述主纵梁与码头的长度方向平行,然后下放安装位于吊装区域内的施工平台、桩芯、预制梁;A2: Use the rotary structure to drive the spreader to rotate to the adjacent storage area or dock the transport ship to retrieve materials, and then rotate the rotary structure to drive the spreader to the starting construction position, which is located in the length direction of the dock and is not yet under construction. On one side, the main longitudinal beam is parallel to the length direction of the wharf, and then the construction platform, pile core and prefabricated beam located in the hoisting area are lowered and installed;
    A3:利用所述回转结构继续旋转90°,带动所述吊具移动至起始施工位置位于码头宽度方向的未施工一侧,此时所述主纵梁与码头的宽度方向平行,然后下放安装位于吊装区域内的施工平台、桩芯、预制梁;A3: Use the slewing structure to continue rotating 90° to drive the spreader to the starting construction position on the unconstruction side in the width direction of the pier. At this time, the main longitudinal beam is parallel to the width direction of the pier, and then lower it for installation. Construction platforms, pile cores, and prefabricated beams located in the hoisting area;
    A4:利用所述辅助横梁、所述辅助支腿及所述行走系统,使所述底座结构沿码头宽度方向的远离起始施工位置的一侧过跨前移一个吊装区域的长度单位,随后所述回转结构旋转180°,使吊装区域位于起始施工位置上方,补充安装起始施工位置的所有预制梁;A4: Use the auxiliary beam, the auxiliary leg and the walking system to move the base structure forward by one unit of the length of the hoisting area along the width direction of the pier away from the starting construction position. The above-mentioned revolving structure is rotated 180° so that the hoisting area is above the starting construction position, and all prefabricated beams at the starting construction position are supplementally installed;
    A5:利用所述回转结构旋转90°,使吊装区域位于码头长度方向的未施工一侧,进行施工平台、桩芯、预制梁的吊装,之后使所述底座结构沿码头的长度方向过跨前移一个吊装区域的长度单位,至此,完成起始施工位置位于一个吊装区域的长度单位的所有列的施工平台、桩芯、预制梁的安装;A5: Use the slewing structure to rotate 90° so that the hoisting area is located on the non-construction side of the length of the pier. Hoist the construction platform, pile cores and prefabricated beams, and then move the base structure across the front span along the length of the pier. Move one unit of length of the hoisting area. At this point, the installation of all rows of construction platforms, pile cores, and prefabricated beams whose starting construction position is located in one unit of length of the hoisting area is completed;
    A6:对位于过跨前移后的吊装区域内桩基进行施工平台、桩芯、预制梁的吊装,旋转所述回转结构,补充安装位于所述底座结构在码头的宽度方向的预制梁,同期,安装位于所述底座结构在码头的宽度方向上已施工一侧的预制面板;A6: Hoist the construction platform, pile core and prefabricated beams on the pile foundation in the hoisting area after the span has been moved forward, rotate the rotary structure, and supplementary installation of the prefabricated beams located in the width direction of the base structure in the dock, at the same time , install the prefabricated panels located on the constructed side of the base structure in the width direction of the pier;
    A7:利用所述辅助横梁、所述辅助支腿及所述行走系统,使所述底座结构沿码头宽度方向的朝向起始施工位置的一侧逐步过跨前移到顶,同时,每次过跨前移利用所述回转结构配合安装位于所述底座结构在码头的长度方向的未施工一侧的施工平台、桩芯、预制梁和已施工一侧的预制面板;A7: Utilize the auxiliary beam, the auxiliary leg and the walking system to gradually move the base structure forward to the top along the width direction of the pier towards the starting construction position. At the same time, each span is Move forward and use the rotary structure to cooperate and install the construction platform, pile core, prefabricated beams and prefabricated panels on the constructed side of the base structure in the length direction of the wharf;
    A8:重复驱动所述施工装备依次沿未施工一侧的码头的宽度方向、长度方向、宽度方向移动,配合旋转所述回转结构及所述吊具的取料、吊装,完成整个码头的施工平台、桩芯、预制梁、预制面板的施工,从而完成高桩码头新型上部结构的一体化安装。A8: Repeatedly drive the construction equipment to move along the width direction, length direction, and width direction of the pier on the unconstructed side, and cooperate with the rotation of the slewing structure and the lifting of the spreader to complete the construction platform of the entire pier. , pile cores, prefabricated beams, and prefabricated panels to complete the integrated installation of the new superstructure of the high-pile wharf.
PCT/CN2022/104172 2022-07-06 2022-07-06 New superstructure for high-piled wharf, and construction apparatus and construction method therefor WO2024007203A1 (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
CN202280002361.2A CN115362292B (en) 2022-07-06 2022-07-06 High pile wharf superstructure and construction equipment and construction method thereof
PCT/CN2022/104172 WO2024007203A1 (en) 2022-07-06 2022-07-06 New superstructure for high-piled wharf, and construction apparatus and construction method therefor
IL303559A IL303559A (en) 2022-07-06 2023-06-08 Construction equipment and method for fully assembled superstructure of high piled wharf

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/CN2022/104172 WO2024007203A1 (en) 2022-07-06 2022-07-06 New superstructure for high-piled wharf, and construction apparatus and construction method therefor

Publications (1)

Publication Number Publication Date
WO2024007203A1 true WO2024007203A1 (en) 2024-01-11

Family

ID=84008541

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2022/104172 WO2024007203A1 (en) 2022-07-06 2022-07-06 New superstructure for high-piled wharf, and construction apparatus and construction method therefor

Country Status (3)

Country Link
CN (1) CN115362292B (en)
IL (1) IL303559A (en)
WO (1) WO2024007203A1 (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10152822A (en) * 1996-11-22 1998-06-09 Saeki Kensetsu Kogyo Kk Precast landing bridge structure and wharf construction method using the structure
JP2005264514A (en) * 2004-03-17 2005-09-29 Nishimatsu Constr Co Ltd Foundation slab structure of sea berth structure, and its construction method
CN104386586A (en) * 2014-11-06 2015-03-04 中铁港航局集团有限公司 Land installation method and installation equipment of hydraulic prefabricated component
CN110747805A (en) * 2019-10-25 2020-02-04 中交第三航务工程勘察设计院有限公司 Prefabricated high-pile wharf node structure and construction method
CN211571598U (en) * 2019-10-31 2020-09-25 中交上海航道勘察设计研究院有限公司 Novel high-pile wharf panel
CN112695696A (en) * 2021-01-05 2021-04-23 中交第二航务工程局有限公司 Integrated construction equipment for superstructure of high-pile wharf and construction method thereof
CN113481931A (en) * 2021-07-07 2021-10-08 中交第三航务工程勘察设计院有限公司 Modular assembly type high-pile wharf structure and construction method thereof
CN113832907A (en) * 2021-09-30 2021-12-24 中交第二航务工程局有限公司 Pile top connecting structure of high-pile wharf and construction method of pile top connecting structure
CN216474790U (en) * 2021-10-22 2022-05-10 中交(福州)建设有限公司 Steel-concrete composite straight pile assembled high pile wharf structure

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB600129A (en) * 1945-09-27 1948-04-01 Richard Pavry Improvements in or relating to the construction of bridges, piers and other structures over water
KR200363059Y1 (en) * 2004-07-05 2004-09-23 휘선건설(주) Upper bridge structure construcion system with precast segment deck or box using a lifting traveller
KR101297127B1 (en) * 2011-07-07 2013-08-14 주식회사 장헌산업 Landing pier structure construction method
JP2013174075A (en) * 2012-02-24 2013-09-05 Nippon Steel Topy Bridge Co Ltd Reconstruction technique for bridge girder
CN104775446B (en) * 2014-01-15 2021-06-15 广东海上城建控股发展有限公司 Barrel pier for fixing water structure and installation and construction method thereof
CN106320332B (en) * 2016-09-09 2018-08-31 中交第二航务工程局有限公司 The construction method and construction system of over-water bored pile are carried out based on pushing tow mobile platform
CN207919582U (en) * 2018-01-12 2018-09-28 中交第三航务工程勘察设计院有限公司 A kind of assembled pile foundation wharfs structure
CN211849244U (en) * 2019-11-07 2020-11-03 中交天津港湾工程设计院有限公司 Novel assembled high-pile beam-slab wharf structure
CN113106918A (en) * 2021-03-23 2021-07-13 中交第二航务工程局有限公司 Prefabricated assembly component erecting equipment capable of walking by means of front and rear inverted rails and construction method
CN114481844B (en) * 2022-01-21 2024-04-30 中铁十一局集团有限公司 Bridge girder erection machine is pieced together to festival

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10152822A (en) * 1996-11-22 1998-06-09 Saeki Kensetsu Kogyo Kk Precast landing bridge structure and wharf construction method using the structure
JP2005264514A (en) * 2004-03-17 2005-09-29 Nishimatsu Constr Co Ltd Foundation slab structure of sea berth structure, and its construction method
CN104386586A (en) * 2014-11-06 2015-03-04 中铁港航局集团有限公司 Land installation method and installation equipment of hydraulic prefabricated component
CN110747805A (en) * 2019-10-25 2020-02-04 中交第三航务工程勘察设计院有限公司 Prefabricated high-pile wharf node structure and construction method
CN211571598U (en) * 2019-10-31 2020-09-25 中交上海航道勘察设计研究院有限公司 Novel high-pile wharf panel
CN112695696A (en) * 2021-01-05 2021-04-23 中交第二航务工程局有限公司 Integrated construction equipment for superstructure of high-pile wharf and construction method thereof
CN113481931A (en) * 2021-07-07 2021-10-08 中交第三航务工程勘察设计院有限公司 Modular assembly type high-pile wharf structure and construction method thereof
CN113832907A (en) * 2021-09-30 2021-12-24 中交第二航务工程局有限公司 Pile top connecting structure of high-pile wharf and construction method of pile top connecting structure
CN216474790U (en) * 2021-10-22 2022-05-10 中交(福州)建设有限公司 Steel-concrete composite straight pile assembled high pile wharf structure

Also Published As

Publication number Publication date
IL303559A (en) 2023-08-01
CN115362292B (en) 2023-08-18
CN115362292A (en) 2022-11-18

Similar Documents

Publication Publication Date Title
CN201857618U (en) Floating guide platform and steel casing supported drilling platform deepwater pile foundation
CN106012960A (en) Assembly type long piled wharf upper structure system and construction method thereof
CN211815986U (en) High-pile beamless plate wharf structure
CN112695696A (en) Integrated construction equipment for superstructure of high-pile wharf and construction method thereof
CN106088120B (en) A kind of cofferdam decentralization construction method
CN106869032A (en) Bridge bearing platform beam tying construction method
CN104736465B (en) Harbour constructing device and the method for construction using same apparatus
JP7319887B2 (en) Bridge pier construction method
CN114000459B (en) Method for erecting platform for high-pile wharf cast-in-place pile construction
CN113502828B (en) Processing method for early warning of deep foundation pit
CN114575589A (en) Construction method for lifting template of electric hoist of steel reinforced concrete structural column
CN215165629U (en) Structure for lowering steel cofferdam by utilizing steel pipe pile of drilling platform
WO2024007203A1 (en) New superstructure for high-piled wharf, and construction apparatus and construction method therefor
CN113863736B (en) Construction process of continuous-span common-column C-shaped stock yard
CN215329670U (en) Integrated construction equipment for superstructure of high-pile wharf
CN216194899U (en) Bearing platform prefabricated structure and bearing platform foundation
CN213013857U (en) Height-adjustable simple cable-stayed diversion trench temporary bridge
CN212611890U (en) Steel-concrete combined arch bridge crossing karst cave in tunnel
CN212452552U (en) Deposit and beat integrative low wave influence offshore construction platform
CN211769949U (en) Movable arm type tower crane underframe ballast type foundation
CN211849445U (en) Construction system of river levee dam concrete bed course
CN113818477A (en) Bearing platform prefabricated structure, bearing platform foundation and construction method thereof
CN114000514A (en) Construction method of deep foundation pit angle support pile column component
CN116084421B (en) Construction method of permeable anti-collision pier
GB2518356A (en) Method of suspension bridge construction

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 22949790

Country of ref document: EP

Kind code of ref document: A1