CN201857618U - Floating guide platform and steel casing supported drilling platform deepwater pile foundation - Google Patents
Floating guide platform and steel casing supported drilling platform deepwater pile foundation Download PDFInfo
- Publication number
- CN201857618U CN201857618U CN2010206020665U CN201020602066U CN201857618U CN 201857618 U CN201857618 U CN 201857618U CN 2010206020665 U CN2010206020665 U CN 2010206020665U CN 201020602066 U CN201020602066 U CN 201020602066U CN 201857618 U CN201857618 U CN 201857618U
- Authority
- CN
- China
- Prior art keywords
- platform
- steel
- steel casing
- construction
- crossbeam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Earth Drilling (AREA)
- Foundations (AREA)
Abstract
A floating guide platform and steel casing supported drilling platform deepwater pile foundation is characterized by comprising a floating guide platform and a steel casing supported drilling platform, wherein the steel casing supported drilling platform is installed by the aid of the floating guide construction platform, and during installation, steel wire ropes are used for anchoring and connection of the floating guide construction platform with the steel casing supported drilling platform. Construction of the deepwater pile foundation is not limited by site terrains and geological conditions, operability is high, ships are fully utilized for assembling the water floating construction platform, no large-sized water floating crane is utilized, construction is flexible and convenient, temporary steel pipe pile support is omitted from the steel casing supported drilling platform, and materials are economized. Simultaneously, the platform foundation is stabilized by the aid of concrete rafts at the bottom of the platform, stability of the drilling construction platform is ensured, the platform steel pipe piles and steel casings are supported and stabilized without bedrock covering, construction safety is guaranteed, application range is wide, and the deepwater pile foundation has certain economic benefit and social benefit.
Description
Technical field:
The utility model relates to the braced structures in the bridge construction, is applicable to bridge deep water pile foundation, specifically is that a kind of floating guide table and steel casing support drilling platform construction deep water pile foundation.
Background technology:
The bridge deepwater Pile Foundation Construction generally adopts steel pipe pile and steel casing to form the pile foundation construction platform, utilizes large-scale floating crane equipment to carry out the construction that underwater work is finished pile foundation.But in Upper Yangtze River or lake bridge construction, owing to be subjected to restrictions such as navigation channel, lack large-scale floating lifting appliance, cause material when subaqueous work, the lifting transportation of equipment is difficulty comparatively, simultaneously, bridge foundation position geological condition is comparatively complicated, bridge location often is in above the exposed basement rock, the basement rock angle of inclination is bigger, and covering layer is thinner, adopts conventional steel pipe pile very difficult as the drilling platform construction, and steel pipe pile and steel casing can't be stablized by build-in, therefore adopt floating guiding operation platform and steel casing to support drilling platform construction deep water pile foundation, well solved this difficult problem.
The utility model content:
The purpose of this utility model be overcome above-mentioned steel pipe pile and steel casing can't the stable constructional difficulties of build-in, a kind of new bridge deepwater Pile Foundation Construction is provided, has the floating guide table of certain economic benefits and social benefit and steel casing to support drilling platform deep water pile foundation.
The technical solution of the utility model is achieved in that a kind of floating guiding operation platform and steel casing support drilling platform deep water pile foundation, it is characterized in that supporting drilling platform by floating guiding operation platform and steel casing constitutes, carry out the steel casing by floating guiding operation platform and support the drilling platform installation, be connected by the steel cable anchoring therebetween, its floating guiding operation platform is by barge or cargo vessel, the hull section steel reinforcement supports, the shaped steel base for supporting, straddle truck universal rod body column, connect midship beam, straddle truck universal rod body crossbeam, the 2[16 distribution beam, the I20 distribution beam, track, the tripod crossbeam, flatcar, triangle frame end framework, tripod main longitudinal grider operating platform, following guide beam, last guide beam, mobile platform, preceding anchor line, back anchor line is formed, barge is welded on the support of hull section steel reinforcement hull is reinforced, welding shaped steel base for supporting on shaped steel, welding universal rod body column on the shaped steel base for supporting, the company's of employing midship beam connects between the column, column top assembly unit universal rod body crossbeam, on the universal rod body crossbeam, lay the 2[16 distribution beam, I20 distribution beam and track, flatcar and tripod crossbeam are installed, on crossbeam, establish track and flatcar as suspension centre, assembly unit triangle frame end framework on the shaped steel base for supporting, be connected with tripod main longitudinal grider operating platform by steel pin, adopt guide beam down between the operating platform, last guide beam is connected into integral body, guide beam is connected by bolt with operating platform, and on operating platform, lay shaped steel as mobile platform, the floating platform navigation system is by preceding anchor line, back anchor line is anchored on the concrete in water anchorage and positions, anchor line is connected with hoist engine on the ship, and hoist engine is weldingly fixed on the ship;
Its steel casing support drilling platform by joint cover under the diagonal brace, [16 diagonal braces, lower floor's steel corbel, the vertical connection of 2[32b, upper strata steel corbel, last bracket suspension rod, 2[32b horizontal-associate, I45b longeron, I45b crossbeam, I25b distribution beam, steel casing, caisson, plate raft, concrete gunnysack, panel are formed; The steel casing sets by vibrating hammer, joint cover under welding diagonal brace on the steel casing, [16 diagonal braces are installed, the diagonal brace lower end is connected by bolt with the diagonal brace lower connecting plate to be convenient to remove, diagonal brace upper end and the welding of steel casing, adopt the welding of 2[32b horizontal-associate to be linked to be integral body between the steel casing, establish caisson at floating guide platform suspension centre down to the position, riverbed, be provided with the concrete gunnysack in the caisson outside, build plate raft concrete, be fixedly connected into integral body with the steel casing, the firm bracket of welding lower floor on the steel casing, the firm bracket in upper strata, on the firm bracket of lower floor, lay the I45b longeron, by last bracket suspension rod longeron is hung on last bracket simultaneously, on longeron, lay the I45b crossbeam, the I25b distribution beam, longeron, crossbeam, adopt respectively between the distribution beam to be welded to connect, and on the I25b distribution beam, lay plank as panel.The erection construction pontoon bridge, assembly unit floating guide table, and in place, anchoring, utilize floating guiding operation platform that the steel casing is installed, flat connection is set between the steel casing, caisson is installed, build plate raft concrete stable platform basis, the casing top is provided with the flat joint group of shaped steel and becomes the drilling construction platform, carries out the pile foundation drilling construction.
The utility model adopts floating guide table and steel casing to support drilling platform construction deep water pile foundation, not only innovate and enriched the form of construction work of bridge of the same type, help simplifying and improving construction technology simultaneously, overcome on-the-spot unfavorable factor, accelerated progress, guarantee quality, safety and environmental protection, therefore obtained certain economic benefits and social benefit.Be specially construction and not limited by site contour and geological conditions, workable, make full use of ship, floating operation platform in the assembly unit water does not rely on crane barge equipment in the large-scale water, and is flexible; The steel casing supports drilling platform, cancellation temporary steel pile tube supports, save material, simultaneously by concrete plate raft stable platform basis, platform bottom, guarantee the stability of drilling construction platform, do not need to rely on the basement rock covering layer to support stable platform steel pipe pile and steel casing, guaranteed construction safety, applied widely.
Description of drawings:
Fig. 1 is that floating guide table and steel casing support drilling platform construction integral arrangement structural representation
Fig. 2-the 1st, floating guide table straddle truck structural representation
Fig. 2-the 2nd, floating guide table operating platform structural representation
Fig. 3-the 1st, floating guide table layout and flow implementation example 1 figure
Fig. 3-the 2nd, floating guide table layout and flow implementation example 2 figure
Fig. 3-the 3rd, floating guide table layout and flow implementation example 3 figure
Fig. 3-the 4th, floating guide table layout and flow implementation example 4 figure
Fig. 4-the 1st, steel casing support drilling construction platform direction across bridge and arrange schematic diagram
Fig. 4-the 2nd, steel casing support drilling construction platform bracket and arrange schematic diagram to flat connection in length and breadth
Fig. 4-the 3rd, steel casing support drilling construction platform longeron, crossbeam is arranged schematic diagram
Fig. 4-the 4th, steel casing support drilling construction deck roof distribution beam and arrange schematic diagram
Among the figure: 1-floating guiding operation platform; 2-steel casing supports the drilling construction platform; The 3-pile foundation; 2.1-barge or cargo vessel; 2.2-the hull section steel reinforcement supports; 2.3-shaped steel base for supporting; 2.4-connect midship beam; 2.5-omnipotent of column straddle truck; 2.6-universal rod body crossbeam straddle truck; 2.7-2[16 distribution beam; 2.8-I20 distribution beam; 2.9-track; 2.10-tripod crossbeam; 2.11-flatcar; 2.12-triangle frame end framework; 2.13-tripod main longitudinal grider operating platform; 2.14-following guide beam; 2.15-last guide beam; 2.16-mobile platform; 2.17-preceding anchor line; 2.18-back anchor line; 3.1-joint cover under the diagonal brace; 3.2-[16 diagonal brace; 3.3-lower floor's steel corbel; 3.4-2[32b vertical connection; 3.5-upper strata steel corbel; 3.6-last bracket suspension rod; 3.7-2[32b horizontal-associate; 3.8-I45b longeron; 3.9-I45b crossbeam; 3.10-I25b distribution beam; 3.11-steel casing; 3.12-caisson; 3.13-plate raft; 3.14-concrete gunnysack; 3.15-panel.
The specific embodiment:
Below in conjunction with accompanying drawing the utility model is further specified, the utility model is not limited to the following examples.
Fig. 1 is that floating guide table and steel casing support drilling platform construction general arrangement schematic, and 1 is the floating guide table among the figure, and 2 are steel casing support drilling platform.Elder generation's assembly unit floating guide table 1 during construction, and in place, anchoring utilize floating guide table 1 installation steel casing to support drilling platform 2 again, utilize floating guide table 1 and steel casing to support drilling platform 2 at last and carry out the pile foundation drilling construction.
Shown in Fig. 1-4: a kind of floating guide table and steel casing support drilling platform deep water pile foundation, supporting drilling platform 2 by floating guide table 1 and steel casing constitutes, carry out the steel casing by floating guiding operation platform and support the drilling platform installation, be connected by the steel cable anchoring therebetween, its floating guide table is by barge or cargo vessel 2.1, the hull section steel reinforcement supports 2.2, shaped steel base for supporting 2.3, universal rod body column 2.5, connect midship beam 2.4, universal rod body crossbeam 2.6,2[16 distribution beam 2.7, I20 distribution beam 2.8, track 2.9, tripod crossbeam 2.10, flatcar 2.11, triangle frame end framework 2.12, tripod main longitudinal grider operating platform 2.13, following guide beam 2.14, last guide beam 2.15, mobile platform 2.16, preceding anchor line 2.17, back anchor line 2.18 is formed, barge 2.1 is welded in the hull section steel reinforcement support 2.2 hull is reinforced, welding shaped steel base for supporting 2.3 on shaped steel, welding universal rod body column 2.5 on the shaped steel base for supporting 2.3, the company's of employing midship beam 2.4 connects between the column 2.5, column 2.5 top assembly unit universal rod body crossbeams 2.6, on universal rod body crossbeam 2.6, lay 2[16 distribution beam 2.7, I20 distribution beam and track 2.8, flatcar 11 and tripod crossbeam 2.10 are installed, on crossbeam 2.10, establish track 2.9 and 30t flatcar 11 assembly unit triangle frame end framework 2.12 on shaped steel base for supporting 2.3, be connected with tripod main longitudinal grider operating platform 2.13 by steel pin, adopt guide beam 2.14 down between the operating platform 2.13, last guide beam 2.15 is connected into integral body, guide beam 2.14,2.15 be connected by bolt with operating platform 2.13, and on operating platform 2.13, lay shaped steel as mobile platform 2.16, floating guide table 1 navigation system is by preceding anchor line 2.17, back anchor line 2.18 is anchored on the concrete in water anchorage and positions, anchor line is connected with hoist engine on the ship, and hoist engine is weldingly fixed on upper and lower integrator of ship.
Its steel casing support drilling platform 2 by joint cover under the diagonal brace 3.1, [16 diagonal braces 3.2, lower floor's steel corbel 3.3, the vertical connection 3.4 of 2[32b, upper strata steel corbel 3.5, go up bracket suspension rod 3.6,2[32b horizontal-associate 3.7, I45b longeron 3.8, I25b distribution beam 3.10, steel casing 3.11, caisson 3.12, plate raft 3.13, concrete gunnysack 3.14, panel 3.15 and form; Steel casing 3.11 sets by vibrating hammer, joint cover 3.1 under welding diagonal brace on the steel casing 3.11, [16 diagonal braces 3.2 are installed, joint cover 3.1 is connected by bolt under diagonal brace 3.2 lower ends and the diagonal brace, diagonal brace 3.2 upper ends and 3.11 welding of steel casing, adopt 3.7 welding of 2[32b horizontal-associate to be linked to be integral body between the steel casing 3.11, establish caisson 3.12 at floating guide platform 1 suspension centre down to the position, riverbed, be provided with concrete gunnysack 3.14 in caisson 3.12 outsides, build plate raft concrete 3.13, be fixedly connected into integral body with steel casing 3.11, the firm bracket 3.3 of welding lower floor on steel casing 3.11, the firm bracket 3.4 in upper strata, on the firm bracket 3.3 of lower floor, lay I45b longeron 3.9, by last bracket suspension rod 3.6 I45b longeron 3.8 is hung on upper strata steel corbel 3.5 simultaneously, on longeron 3.8, lay I45b crossbeam 3.9, I25b distribution beam 3.10, I45b longeron 3.8, I45b crossbeam 3.9, adopt respectively between the I25b distribution beam 3.10 to be welded to connect, and on I25b distribution beam 3.10, lay plank as panel 3.15.Adopt floating guide table 1 and steel casing to support drilling platform 2 deep water pile foundations, the erection construction pontoon bridge, assembly unit floating guide table, and in place, anchoring, adopt floating guide table 1 that steel casing 3.11 is installed, flat connection is set between the steel casing 3.11, caisson 3.12 is installed, build plate raft concrete 3.13 stable platform bases, the casing top is provided with the flat joint group of shaped steel and becomes the drilling construction platform, carries out the pile foundation drilling construction.
Claims (1)
1. floating guiding operation platform and steel casing support drilling platform deep water pile foundation, it is characterized in that supporting drilling platform (2) by floating guide table (1) and steel casing constitutes, carry out the steel casing by floating guiding operation platform and support the drilling platform installation, be connected by the steel cable anchoring therebetween, its floating guide table (1) is by barge (2.1), the hull section steel reinforcement supports (2.2), shaped steel base for supporting (2.3), universal rod body column (2.5), connect midship beam (2.4), universal rod body crossbeam (2.6), 2[16 distribution beam (2.7), I20 distribution beam (2.8), track (2.9), tripod crossbeam (2.10), flatcar (2.11), triangle frame end framework (2.12), tripod main longitudinal grider operating platform (2.13), following guide beam (2.14), last guide beam (2.15), mobile platform (2.16), preceding anchor line (2.17), back anchor line (2.18) is formed, barge (2.1) is welded on the hull section steel reinforcement and supports on (2.2), welding shaped steel base for supporting (2.3) on shaped steel, go up welding universal rod body column (2.5) at die base for supporting (2.3), the company's of employing midship beam (2.4) connects between the column (2.5), column (2.5) top assembly unit universal rod body crossbeam (2.6), on universal rod body crossbeam (2.6), lay 2[16 distribution beam (2.7), I20 distribution beam (2.8) and track (2.9), flatcar (11) and tripod crossbeam (2.10) are installed, on crossbeam (2.10), establish track (2.9) and flatcar (11), go up assembly unit triangle frame end framework (2.12) at shaped steel base for supporting (2.3), be connected with tripod main longitudinal grider operating platform (2.13) by steel pin, adopt guide beam (2.14) down between the tripod main longitudinal grider operating platform (2.13), last guide beam (2.15) is connected into integral body, guide beam (2.14,2.15) be connected by bolt with tripod main longitudinal grider operating platform (2.13), and on operating platform (2.13), lay shaped steel as mobile platform (2.16), floating guide table (1) navigation system is by preceding anchor line (2.17), back anchor line anchor (2.18) is solid locatees on the concrete in water anchorage, anchor line (2.17,2.18) be connected with hoist engine on the ship, hoist engine is weldingly fixed on the ship;
Its steel casing support drilling platform (2) by joint cover under the diagonal brace (3.1), [16 diagonal braces (3.2), lower floor's steel corbel (3.3), the vertical connection of 2[32b (3.4), upper strata steel corbel (3.5), go up bracket suspension rod (3.6), 2[32b horizontal-associate (3.7), I45b longeron (3.8), I25b distribution beam (3.10), steel casing (3.11), caisson (3.12), plate raft (3.13), concrete gunnysack (3.14), panel (3.15) and form; Steel casing (3.11) sets by vibrating hammer, go up joint cover (3.1) under the welding diagonal brace at steel casing (3.11), [16 diagonal braces (3.2) are installed, diagonal brace (3.2) lower end is connected by bolt with diagonal brace lower connecting plate (3.1), diagonal brace (3.2) upper end and steel casing (3.11) welding, adopt 2[32b horizontal-associate (3.7) welding to be linked to be integral body between the steel casing (3.11), establish caisson (3.12) down to the position, riverbed at floating guide platform (1) suspension centre, be provided with concrete gunnysack (3.14) in caisson (3.12) outside, build plate raft concrete (3.13), be fixedly connected into integral body with steel casing (3.11), go up welding lower floor's steel corbel (3.3) at steel casing (3.11), upper strata steel corbel (3.5), go up laying I45b longeron (3.9) at lower floor's steel corbel (3.3), by last bracket suspension rod (3.6) I45b longeron (3.8) is hung on upper strata steel corbel (3.5) simultaneously, go up laying I45b crossbeam (3.8) at longeron (3.8), I25b distribution beam (3.10), I45b longeron (3.8), I45b crossbeam (3.9), adopt respectively between the I25b distribution beam (3.10) to be welded to connect, and go up the laying plank as panel (3.15) in I25b distribution beam (3.10).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010206020665U CN201857618U (en) | 2010-11-11 | 2010-11-11 | Floating guide platform and steel casing supported drilling platform deepwater pile foundation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010206020665U CN201857618U (en) | 2010-11-11 | 2010-11-11 | Floating guide platform and steel casing supported drilling platform deepwater pile foundation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201857618U true CN201857618U (en) | 2011-06-08 |
Family
ID=44103428
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010206020665U Expired - Lifetime CN201857618U (en) | 2010-11-11 | 2010-11-11 | Floating guide platform and steel casing supported drilling platform deepwater pile foundation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201857618U (en) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102312442A (en) * | 2011-07-01 | 2012-01-11 | 中铁大桥局股份有限公司 | Construction method of trestle steel pipe pile foundation |
CN102409613A (en) * | 2011-08-17 | 2012-04-11 | 中国十七冶集团有限公司 | Construction method for installing steel beam of plank road built along mountain and near river |
CN102817342A (en) * | 2012-08-27 | 2012-12-12 | 中铁九桥工程有限公司 | Construction technology of in-situ assembly under pile foundation construction platform of double-wall steel cofferdam |
CN102828496A (en) * | 2012-08-23 | 2012-12-19 | 中交第二航务工程局有限公司 | Tool type pile foundation drilling platform based on HSE (Health, Safety and Environmental) management system |
CN104514219A (en) * | 2014-12-12 | 2015-04-15 | 中铁十九局集团有限公司 | Underwater drilled pile foundation construction system capable of recycling steel casing and construction method thereof |
CN105604061A (en) * | 2016-01-28 | 2016-05-25 | 中铁上海工程局集团第五工程有限公司 | Floating-type device for rock embedment mounting of steel pipe pile in water and construction method thereof |
CN106522211A (en) * | 2016-11-30 | 2017-03-22 | 中铁十六局集团第三工程有限公司 | Pile foundation construction device and pile foundation construction method for bridge pier tubular pile |
CN106610343A (en) * | 2015-10-27 | 2017-05-03 | 张志国 | A pier counterforce closing force system self-balance-type railway cast-in-situ beam static load test apparatus |
CN107313416A (en) * | 2017-07-07 | 2017-11-03 | 中交二航局第三工程有限公司 | Hydraulic element pin-connected panel prefabricated platform waterborne and method for prefabricating |
WO2018045772A1 (en) * | 2016-09-09 | 2018-03-15 | 中交第二航务工程局有限公司 | Construction method and construction system for overwater bored piles based on incremental launching movement platform |
CN108216506A (en) * | 2018-02-26 | 2018-06-29 | 中国葛洲坝集团第五工程有限公司 | A kind of floating drilling platform and construction method |
CN109371963A (en) * | 2018-11-16 | 2019-02-22 | 中铁上海工程局集团有限公司 | Back taper steel jacket box and its construction method in water in the prefabricated constructing tie beam of pier foundation |
-
2010
- 2010-11-11 CN CN2010206020665U patent/CN201857618U/en not_active Expired - Lifetime
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102312442A (en) * | 2011-07-01 | 2012-01-11 | 中铁大桥局股份有限公司 | Construction method of trestle steel pipe pile foundation |
CN102409613A (en) * | 2011-08-17 | 2012-04-11 | 中国十七冶集团有限公司 | Construction method for installing steel beam of plank road built along mountain and near river |
CN102409613B (en) * | 2011-08-17 | 2013-10-16 | 中国十七冶集团有限公司 | Construction method for installing steel beam of plank road built along mountain and near river |
CN102828496A (en) * | 2012-08-23 | 2012-12-19 | 中交第二航务工程局有限公司 | Tool type pile foundation drilling platform based on HSE (Health, Safety and Environmental) management system |
CN102817342A (en) * | 2012-08-27 | 2012-12-12 | 中铁九桥工程有限公司 | Construction technology of in-situ assembly under pile foundation construction platform of double-wall steel cofferdam |
CN104514219A (en) * | 2014-12-12 | 2015-04-15 | 中铁十九局集团有限公司 | Underwater drilled pile foundation construction system capable of recycling steel casing and construction method thereof |
CN106610343A (en) * | 2015-10-27 | 2017-05-03 | 张志国 | A pier counterforce closing force system self-balance-type railway cast-in-situ beam static load test apparatus |
CN105604061A (en) * | 2016-01-28 | 2016-05-25 | 中铁上海工程局集团第五工程有限公司 | Floating-type device for rock embedment mounting of steel pipe pile in water and construction method thereof |
CN105604061B (en) * | 2016-01-28 | 2018-12-28 | 中铁上海工程局集团第五工程有限公司 | A kind of surface unit and its construction method entering rock installation for steel-pipe pile in water |
WO2018045772A1 (en) * | 2016-09-09 | 2018-03-15 | 中交第二航务工程局有限公司 | Construction method and construction system for overwater bored piles based on incremental launching movement platform |
CN106522211A (en) * | 2016-11-30 | 2017-03-22 | 中铁十六局集团第三工程有限公司 | Pile foundation construction device and pile foundation construction method for bridge pier tubular pile |
CN107313416A (en) * | 2017-07-07 | 2017-11-03 | 中交二航局第三工程有限公司 | Hydraulic element pin-connected panel prefabricated platform waterborne and method for prefabricating |
CN108216506A (en) * | 2018-02-26 | 2018-06-29 | 中国葛洲坝集团第五工程有限公司 | A kind of floating drilling platform and construction method |
CN109371963A (en) * | 2018-11-16 | 2019-02-22 | 中铁上海工程局集团有限公司 | Back taper steel jacket box and its construction method in water in the prefabricated constructing tie beam of pier foundation |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201857618U (en) | Floating guide platform and steel casing supported drilling platform deepwater pile foundation | |
CN102720140B (en) | Large-span prestress concrete continuous beam deepwater pier construction process | |
CN101368389B (en) | Single and double-wall combined steel cofferdam construction method and its single and double-wall combined steel cofferdam | |
CN101775809B (en) | Construction method of marine self-floating type steel soleplate single-wall suspension box cofferdam and single-wall suspension box cofferdam | |
CN102251530B (en) | Construction process of double-wall steel cofferdam for construction of pier bearing platform in main river water of Yellow River | |
CN102116017B (en) | Foam platform for drilling on waterways | |
CN103741657A (en) | Construction method of large multifunctional over-water construction platform | |
CN108867672A (en) | A kind of Double-Wall Steel Boxed Cofferdam joining method | |
CN101538833A (en) | Vertical subsection double-wall steel cofferdam water stopping construction method | |
WO2023184679A1 (en) | Large-span space special-shaped arch rib flying-swallow type basket steel box arch bridge and rapid construction method | |
CN106223355A (en) | A kind of high bearing platform supported on piles in deep water Hold Hoop method has device and the construction method of end steel jacket box | |
KR20120012504A (en) | Cast in place concrete pile With precast type Caisson | |
CN202023182U (en) | Waterborne drilling foam platform | |
CN102936899A (en) | Method for installing steel cofferdam by the aid of pier supporting frame | |
CN214401781U (en) | Gripping mechanism suitable for large-tonnage underwater steel pipe pile clearing device | |
CN110670611A (en) | Inner support assembly type multilayer integral installation method for deep water foundation steel sheet pile cofferdam | |
CN115180101B (en) | Underwater local dry land overhauling method and system | |
CN103171976B (en) | Hoisting method for shipyard gantry crane | |
CN103498420B (en) | Large-scale steel box beam ashore construction method | |
CN108216506A (en) | A kind of floating drilling platform and construction method | |
CN214401783U (en) | Buoyancy tank platform suitable for large-tonnage underwater steel pipe pile clearing device | |
CN112609695B (en) | Large-tonnage underwater steel pipe pile removing device and construction method | |
CN104746476A (en) | Wharf additionally provided with batter pile on rear edge and method for reinforcing wharf rear edge by applying batter pile | |
TWI834746B (en) | Work platform vessel equipped with crane and method of using the crane | |
CN110984003B (en) | Method for removing pier and bearing platform at lower part of river-crossing bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CX01 | Expiry of patent term |
Granted publication date: 20110608 |
|
CX01 | Expiry of patent term |