JP7319887B2 - Bridge pier construction method - Google Patents

Bridge pier construction method Download PDF

Info

Publication number
JP7319887B2
JP7319887B2 JP2019186695A JP2019186695A JP7319887B2 JP 7319887 B2 JP7319887 B2 JP 7319887B2 JP 2019186695 A JP2019186695 A JP 2019186695A JP 2019186695 A JP2019186695 A JP 2019186695A JP 7319887 B2 JP7319887 B2 JP 7319887B2
Authority
JP
Japan
Prior art keywords
girder
pier
erection
cofferdam
constructing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2019186695A
Other languages
Japanese (ja)
Other versions
JP2020002778A (en
Inventor
恵太 桝本
俊彦 鎌田
統央 山口
浩 十河
悠 村井
公生 齋藤
与博 中島
寛 白浜
優介 佐々木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2019186695A priority Critical patent/JP7319887B2/en
Publication of JP2020002778A publication Critical patent/JP2020002778A/en
Application granted granted Critical
Publication of JP7319887B2 publication Critical patent/JP7319887B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、橋脚構築方法に関するものである。 The present invention relates to a bridge pier construction method.

従来、河川の水域を締切って橋梁の橋脚を施工する方法が知られている(例えば、特許文献1参照。)。また、この種の橋梁の施工において、浚渫量を削減して環境への影響を軽減しながらも渇水期を含めた通年施工を可能にして施工期間の短縮を図るために、橋脚を主に上空から施工する方法が従来から知られている(例えば、非特許文献1,2参照。)。この施工方法は次のように実行される。まず、渇水期に河川内の浚渫が行われ、杭打ち台船を用いて図9及び図10(a)に示されるような鋼管矢板井筒201が構築される。鋼管矢板井筒201は、水域を締切るように水面73上に突出し平面視円環状をなす。 BACKGROUND ART Conventionally, a method of constructing a bridge pier by closing off a water area of a river is known (see, for example, Patent Document 1). In addition, in the construction of this type of bridge, the bridge piers are mainly constructed in the sky in order to reduce the amount of dredging and reduce the impact on the environment while enabling construction throughout the year including the dry season and shortening the construction period. A method of constructing from the ground is conventionally known (see, for example, Non-Patent Documents 1 and 2). This construction method is executed as follows. First, the river is dredged during the dry season, and a steel pipe sheet pile well 201 as shown in FIGS. 9 and 10(a) is constructed using a pile-driving barge. The steel pipe sheet pile well 201 protrudes above the water surface 73 so as to close off the water area and forms an annular shape in plan view.

鋼管矢板井筒201のうち、橋軸直角方向(図10(a)の紙面直交方向)に対面する一対の部位207,207は、他の部位よりも更に上方に突出するように設けられている。例えば、当該部位207(以下、「突出部位207」という)を構成する複数の鋼管203aが、他の鋼管203bよりも高く上方に延び出すことにより、上記のような構造が実現されている。なお、他の鋼管203bは、一般的な鋼管矢板井筒における鋼管と同程度の高さで水面から突出している。このような突出部位207を補強する補強構造部(図示せず)が適宜構築されてもよい。 Of the steel pipe sheet pile well 201, a pair of portions 207, 207 facing in the direction perpendicular to the bridge axis (perpendicular to the paper surface of FIG. 10(a)) are provided so as to protrude further upward than the other portions. For example, the structure described above is realized by the plurality of steel pipes 203a forming the portion 207 (hereinafter referred to as "protruding portion 207") extending upward higher than the other steel pipes 203b. The other steel pipe 203b protrudes from the water surface at a height similar to that of a steel pipe in a general steel pipe sheet pile well. A reinforcing structure (not shown) that reinforces such a projecting portion 207 may be appropriately constructed.

2つの突出部位207,207の上端には、橋軸直角方向に延びる受梁211が架け渡される。そして、受梁211上には、橋軸方向に延びる架設桁205の先端部が載置される。例えば、架設桁205は、鋼管矢板井筒201に隣接する他の鋼管矢板井筒(図示せず)から送り出されて、その先端部が鋼管矢板井筒201上に到達する。また受梁211と架設桁205との間には、サンドル、ジャッキ、駆動シンクロジャッキ、エンドレスローラー等を含む嵩上装置212が挟み込まれ、架設桁205の嵩上げが適宜行われる。これにより、受梁211及び架設桁205の荷重が鋼管矢板井筒201によって支持される。 A support beam 211 extending in the direction perpendicular to the bridge axis is bridged over the upper ends of the two projecting portions 207 , 207 . Then, on the receiving beam 211, the tip part of the erection girder 205 extending in the bridge axis direction is placed. For example, the erection girder 205 is sent out from another steel pipe sheet pile well (not shown) adjacent to the steel pipe sheet pile well 201 , and its tip reaches the steel pipe sheet pile well 201 . A raising device 212 including sandals, jacks, drive synchronous jacks, endless rollers, etc. is sandwiched between the receiving beams 211 and the construction girder 205, and the construction girder 205 is appropriately raised. Thereby, the load of the receiving beam 211 and the erection girder 205 is supported by the steel pipe sheet pile well 201 .

架設桁205の上面には、橋軸方向に移動可能な揚重設備221及び運搬台車223が設置されている。この揚重設備221が鋼管矢板井筒201の上方の位置(例えば、受梁211の直上の位置)に配置される。 On the upper surface of the erection girder 205, a lifting equipment 221 and a carriage 223 that can move in the direction of the bridge axis are installed. This lifting equipment 221 is arranged at a position above the steel pipe sheet pile well 201 (for example, a position directly above the receiving beam 211).

架設桁205の設置後、図10(b)に示されるように、鋼管矢板井筒201の内部では、必要に応じて内部補強をしながら河底の水中掘削が実行され、敷石層227及び底盤コンクリート229が構築された後、鋼管矢板井筒201の内部がドライアップされ、底盤コンクリート229上に頂版コンクリート231が構築される。更に、頂版コンクリート231の上方に橋脚233が構築される。 After installation of the erection girder 205, as shown in FIG. 10(b), inside the steel pipe sheet pile well 201, underwater excavation of the riverbed is performed while internal reinforcement is carried out as necessary, and the paving stone layer 227 and the bottom concrete are formed. 229 is constructed, the inside of the steel pipe sheet pile well 201 is dried up, and the top slab concrete 231 is constructed on the bottom concrete 229 . Furthermore, a pier 233 is constructed above the top concrete 231 .

更に、図11(a)に示されるように、一対の突出部位207同士の間の位置で、橋脚233の上方に、場所打ちコンクリートによる柱頭部241が構築される。その後、図11(b)に示されるように、完成した柱頭部241上にベント243が設置され、このベント243に受梁211及び架設桁205の荷重が盛り替えられる。その後、上記荷重から解放された受梁211の両端部が除去される。これにより、受梁211及び架設桁205の荷重は、柱頭部241及び橋脚233に盛り替えられ、支持される。 Furthermore, as shown in FIG. 11(a), a column head 241 made of cast-in-place concrete is constructed above the bridge pier 233 between the pair of projecting portions 207. As shown in FIG. After that, as shown in FIG. 11(b), a vent 243 is installed on the completed column head 241, and the load of the support beam 211 and the erection girder 205 is transferred to the vent 243. After that, both ends of the support beam 211 released from the load are removed. Thereby, the load of the receiving beam 211 and the erection girder 205 is transferred to the column head 241 and the bridge pier 233 and supported.

その後、図12(a)に示されるように、鋼管矢板井筒201の上部が頂版コンクリート231上端の位置で切除される。そして、図12(b)に示されるように、柱頭部241が橋軸方向の両方に張出すように延長される。その後、延長された柱頭部241の両側にそれぞれワーゲン245が設置され、張出架設工法によって橋桁が順次構築されていく。一方、架設桁205は、隣の鋼管矢板井筒に向けて送り出され、当該隣の鋼管矢板井筒において上述の工程が実行される。以上を鋼管矢板井筒ごとに実行することで、橋梁が建造される。 After that, as shown in FIG. 12( a ), the upper part of the steel pipe sheet pile well 201 is cut off at the position of the upper end of the top slab concrete 231 . Then, as shown in FIG. 12(b), the column head 241 is extended in both directions of the bridge axis. After that, wagons 245 are installed on both sides of the extended column head 241, and bridge girders are sequentially constructed by the overhang erection method. On the other hand, the erection girder 205 is sent out toward the adjacent steel pipe sheet pile well, and the above-described process is executed in the adjacent steel pipe sheet pile well. A bridge is constructed by executing the above for each steel pipe sheet pile well.

上述のような水中掘削、敷石層227の構築、底盤コンクリート229の構築、ドライアップ、頂版コンクリート231の構築、及び橋脚233の構築に用いられる資機材は、架設桁205を通じて鋼管矢板井筒201の内部に搬送される。すなわち、鋼管矢板井筒201は、完成済みの既設の橋桁と、架設桁205とを介して河岸に接続されている。そして、上記の資機材は、河岸から既設橋桁及び架設桁205を通じて鋼管矢板井筒201の内部に搬送される。例えば、コンクリート打設に使用される生コンクリートは、既設の橋桁及び架設桁205上に設けられた配管(図示せず)を通じて河岸から打設現場に供給される。このとき、運搬台車223は、資機材を治部クレーン221の近傍に搬送し、揚重設備221は、当該資機材を鋼管矢板井筒201の内部に吊下ろす。なお、上記のような柱頭部241の構築、及び張出架設工法による橋桁の構築に使用される資機材も、河岸から既設橋桁及び架設桁205を通じて必要な場所に搬送される。 Materials and equipment used for underwater excavation, construction of the pavement layer 227, construction of the base concrete 229, dry-up, construction of the top concrete 231, and construction of the piers 233 as described above are used to construct the steel pipe sheet pile well 201 through the erection girder 205. transported inside. That is, the steel pipe sheet pile well 201 is connected to the river bank via the existing completed bridge girder and the erection girder 205 . Then, the materials and equipment are transported from the river bank into the steel pipe sheet pile well 201 through the existing bridge girders and the erected girders 205 . For example, ready-mixed concrete used for pouring concrete is supplied from the river bank to the pouring site through pipes (not shown) provided on the existing bridge girders and erected girders 205 . At this time, the carriage 223 transports the materials and equipment to the vicinity of the jig crane 221 , and the lifting equipment 221 suspends the materials and equipment inside the steel pipe sheet pile well 201 . Materials and equipment used for constructing the column head 241 as described above and constructing bridge girders by the cantilever erection method are also transported from the river bank to the required locations through the existing bridge girders and erection girders 205 .

特開2017-210840号公報Japanese Patent Application Laid-Open No. 2017-210840

「はまゆう大橋頭上の“桁”で資材搬入」、橋梁&都市PROJECT、橋梁編纂委員会、平成15年12月10日、VOL.39 No.12、2003年12月号、pp.4~7"Materials Carrying in with Girder on Hamayu Bridge", Bridge & City Project, Bridge Compilation Committee, December 10, 2003, VOL.39 No.12, December 2003, pp.4-7

「吉野川渡河部の環境保全に配慮した構造及び施工」、第6頁~第8頁(資料(1)-4-2,資料(1)-5,資料(1)-6)、[online]、第5回四国横断自動車道 吉野川渡河部の環境保全に関する検討会(平成27年4月27日開催)、[令和1年9月20日検索]、インターネット(URL:https://corp.w-nexco.co.jp/newly/h27/0427/pdfs/1-02.pdf)"Structure and Construction Considering Environmental Conservation at Crossing the Yoshino River", Pages 6 to 8 (Document (1)-4-2, Document (1)-5, Document (1)-6), [online] , The 5th Study Group on Environmental Conservation of the Yoshino River Crossing on the Shikoku Odan Expressway (held on April 27, 2015), [Searched on September 20, 2019], Internet (URL: https://corp. w-nexco.co.jp/newly/h27/0427/pdfs/1-02.pdf)

しかしながら、上述のような方法よりも更に効率がよい橋脚構築方法が求められていた。本発明は、効率がよい橋脚構築方法を提供することを目的とする。 However, there has been a need for a method of constructing piers that is more efficient than the methods described above. An object of the present invention is to provide an efficient bridge pier construction method.

本発明の橋脚構築方法は、水域に橋脚を構築する橋脚構築方法であって、水域に橋脚の基礎を構築するための前段構造物を構築する前段構造物構築工程と、前段構造物に設けられた仮支柱を介して前段構造物に支持されるように、架設桁を前段構造物に架け渡す桁架設工程と、架設桁を通じて搬送される資機材を用いて前段構造物に橋脚を構築する橋脚構築工程と、を備え、仮支柱は、桁架設工程に先立って、前段構造物の近傍まで片持ちで延伸された架設桁を通じて搬送される資機材を用いて前段構造物に設けられる。 A bridge pier construction method of the present invention is a bridge pier construction method for constructing a bridge pier in a water area, comprising: a front structure construction step of constructing a front structure for constructing a foundation of the bridge pier in a water area; A girder erection process in which the erection girders are laid over the preceding structure so that they are supported by the preceding structure via temporary pillars. and a construction step, wherein the temporary pillars are installed on the front structure prior to the girder erection step using materials and equipment that are transported through an erection girder that is cantilevered to the vicinity of the front structure.

本発明の橋脚構築方法は、水域に橋脚を構築する橋脚構築方法であって、水域に橋脚の基礎を構築するための前段構造物を構築する前段構造物構築工程と、前段構造物の近傍の水域に仮支柱を構築する仮支柱構築工程と、仮支柱に架設桁を架け渡す桁架設工程と、架設桁を通じて搬送される資機材を用いて前段構造物に橋脚を構築する橋脚構築工程と、を備える。 A bridge pier construction method of the present invention is a bridge pier construction method for constructing a bridge pier in a water area, comprising: a front structure construction step of constructing a front structure for constructing a foundation of the bridge pier in a water area; A temporary pillar building process for building temporary pillars in a water area, a girder erecting process for spanning the temporary pillars with erection girders, and a pier building process for building piers on the front stage structure using materials and equipment transported through the erection girders, Prepare.

前段構造物は、水域を締切る締切工を有し、橋脚構築工程では、締切工の内部に橋脚が構築されることとしてもよい。 The front-stage structure may have a cofferdam that closes off the water area, and the piers may be constructed inside the cofferdam in the pier construction process.

橋脚構築工程は、橋脚の構築に用いる資機材を仮置きするための、締切工に支持され締切工から外側に張出した張出ステージを設けるステージ設置工程を有することとしてもよい。 The pier construction process may include a stage installation process of providing an overhang stage that is supported by the cofferdam and projects outward from the cofferdam for temporarily placing the materials and equipment used in constructing the pier.

橋脚構築工程は、資機材同士が組み立てられて構成される資機材ユニットを締切工の内部に吊下ろすユニット吊下工程を有することとしてもよい。 The pier construction process may include a unit suspension process of suspending a material/equipment unit configured by assembling materials/equipment together inside the cofferdam.

本発明の橋脚構築方法は、水域に橋脚を構築する橋脚構築方法であって、水域を締切る締切工を構築する締切工程と、橋脚の構築に用いる資機材を仮置きするための、締切工に支持され締切工から外側に張出した張出ステージを設けるステージ設置工程と、を備える。 The bridge pier construction method of the present invention is a bridge pier construction method for constructing a bridge pier in a water area. a stage installation step of providing an overhang stage supported by the cofferdam and overhanging to the outside.

本発明の橋脚構築方法は、水域に橋脚を構築する橋脚構築方法であって、水域を締切る締切工を構築する締切工程と、締切工に設けられた仮支柱を介して締切工に支持されるように、架設桁を締切工に架け渡す桁架設工程と、架設桁を通じて搬送される資機材を用いて締切工の内部に橋脚を構築する橋脚構築工程と、を備え、仮支柱は、桁架設工程に先立って、締切工の近傍まで片持ちで延伸された架設桁を通じて搬送される資機材を用いて締切工に設けられる、ものであってもよい。 The bridge pier construction method of the present invention is a bridge pier construction method for constructing a bridge pier in a water area. As shown in the figure, a girder erection process for connecting the erection girder to the cofferdam, and a pier construction process for constructing the pier inside the cofferdam using materials and equipment transported through the erection girder. It may be installed in the cofferdam prior to the erection process using materials and equipment that are transported through an erection girder that is cantilevered to the vicinity of the cofferdam.

本発明の橋脚構築方法は、水域に橋脚を構築する橋脚構築方法であって、水域を締切る締切工を構築する締切工程と、締切工の近傍の水域に仮支柱を構築する仮支柱構築工程と、仮支柱に架設桁を架け渡す桁架設工程と、架設桁を通じて搬送される資機材を用いて締切工の内部に橋脚を構築する橋脚構築工程と、を備える、ものであってもよい。 The bridge pier construction method of the present invention is a bridge pier construction method for constructing bridge piers in a water area, comprising a cofferdam construction process for constructing a cofferdam for coffering a water area, and a temporary support construction process for constructing a temporary support in a water area near the cofferdam. and a girder erection step of bridging the temporary struts with the girder, and a pier construction step of constructing the pier inside the cofferdam using materials and equipment transported through the erection girder.

本発明によれば、効率がよい橋脚構築方法を提供することができる。 According to the present invention, it is possible to provide an efficient bridge pier construction method.

第1実施形態に係る橋脚構築方法を順次示す側面図(橋軸直角方向の視線で見た図)である。It is a side view (view seen in the line of sight in the direction perpendicular to the bridge axis) sequentially showing the bridge pier construction method according to the first embodiment. 第1実施形態に係る橋脚構築方法を順次示す側面図である。It is a side view which shows sequentially the bridge pier construction method which concerns on 1st Embodiment. 第1実施形態に係る橋脚構築方法を順次示す側面図である。It is a side view which shows sequentially the bridge pier construction method which concerns on 1st Embodiment. 第1実施形態に係る橋脚構築方法を順次示す斜視図である。It is a perspective view which shows sequentially the bridge pier construction method which concerns on 1st Embodiment. 第1実施形態に係る橋脚構築方法を順次示す側面図である。It is a side view which shows sequentially the bridge pier construction method which concerns on 1st Embodiment. 第2実施形態に係る橋脚構築方法を順次示す側面図である。It is a side view which shows sequentially the pier construction method which concerns on 2nd Embodiment. 第2実施形態に係る橋脚構築方法を順次示す側面図である。It is a side view which shows sequentially the pier construction method which concerns on 2nd Embodiment. 第2実施形態に係る橋脚構築方法を順次示す側面図である。It is a side view which shows sequentially the pier construction method which concerns on 2nd Embodiment. 従来の橋脚構築方法を順次示す斜視図である。It is a perspective view which shows the conventional bridge pier construction method one by one. (a),(b)は、従来の橋脚構築方法を順次示す側面図(橋軸直角方向の視線で見た図)である。(a) and (b) are side views (viewed in the direction perpendicular to the bridge axis) sequentially showing a conventional bridge pier construction method. (a),(b)は、従来の橋脚構築方法を順次示す側面図である。(a) and (b) are side views sequentially showing a conventional bridge pier construction method. (a),(b)は、従来の橋脚構築方法を順次示す側面図である。(a) and (b) are side views sequentially showing a conventional bridge pier construction method.

以下、図面を参照しつつ本発明に係る橋脚構築方法の実施形態について詳細に説明する。 An embodiment of a bridge pier construction method according to the present invention will be described in detail below with reference to the drawings.

(第1実施形態)
本実施形態の橋脚構築方法は、河川に建造される橋梁の橋脚を主に上空から施工する方法であり、次に説明する締切工程と、桁架設工程と、橋脚構築工程と、を備える。以下では、各側面図の左側を左岸側とし、右側を右岸側とする。また、以下では、左岸側から橋脚が順次構築される場合を例として、そのうちの1つの橋脚に注目して構築方法を説明する。また、各図面は特徴的な部分を誇張して図示する場合があるため、図面上の各要素の寸法比は必ずしも正確ではない。
(First embodiment)
The bridge pier construction method of this embodiment is a method of constructing bridge piers of a bridge constructed over a river mainly from the air, and includes a cofferdam process, a girder construction process, and a pier construction process, which will be described below. Hereinafter, the left side of each side view is the left bank side, and the right side is the right bank side. In the following, the construction method will be described by focusing on one of the piers, taking as an example the case where the piers are constructed sequentially from the left bank side. In addition, since each drawing may exaggerate characteristic parts, the dimensional ratio of each element on the drawing is not necessarily accurate.

〔締切工程〕
締切工程は、例えば、渇水期に河川内の浚渫が行われた上で実行される。図1に示されるように、締切工程(前段構造物構築工程)では、橋脚の構築予定の位置において、橋脚の基礎を形成するための前段構造物として、河川の水域を締切る締切工が構築される。本実施形態における締切工は、複数の鋼管3を井筒状に配置して水域を締切る鋼管矢板井筒1である。鋼管矢板井筒1は、杭打ち台船等を用いて河底71に打設され水面73から上方に突出した複数の鋼管3を備えている。鋼管3同士は所定の継手構造によって互いに接続され、平面視で環状(例えば、円環状)に配列されている。
[Deadline process]
The closing process is executed, for example, after the river is dredged during the dry season. As shown in Fig. 1, in the cofferdam process (pre-stage structure construction process), cofferdams are constructed to coffer off the water area of the river as the pre-stage structures for forming the foundations of the piers at the positions where the piers are planned to be constructed. be done. The cofferdam in this embodiment is a steel pipe sheet pile well 1 that closes off a water area by arranging a plurality of steel pipes 3 in a well shape. The steel pipe sheet pile well 1 includes a plurality of steel pipes 3 driven into a river bed 71 using a pile driving barge or the like and protruding upward from a water surface 73 . The steel pipes 3 are connected to each other by a predetermined joint structure, and are arranged in an annular shape (for example, an annular shape) in plan view.

〔桁架設工程〕
桁架設工程では、鋼管矢板井筒1に対して、左岸側に隣接する既設の鋼管矢板井筒91から架設桁5を架け渡す。この桁架設工程の前の段階では、図2に示されるように、鋼管矢板井筒91の上部に仮支柱97が設けられており、破線で示されるように架設桁5は仮支柱97を介して鋼管矢板井筒91に支持されている。或いは、鋼管矢板井筒91と、その更に左岸側に位置する既設の鋼管矢板井筒(図示せず)と、を含めた複数の既設の鋼管矢板井筒で架設桁5が支持されていてもよい。架設桁5の上面には、橋軸方向に走行可能な揚重設備21及び運搬台車23(図4参照)が設置されている。
[Girder erection process]
In the girder erection process, the erection girder 5 is bridged over the steel pipe sheet pile well 1 from the existing steel pipe sheet pile well 91 adjacent to the left bank side. At the stage before this girder erection process, as shown in FIG. It is supported by a steel pipe sheet pile well 91 . Alternatively, the erection girder 5 may be supported by a plurality of existing steel pipe sheet pile wells, including the steel pipe sheet pile well 91 and an existing steel pipe sheet pile well (not shown) located further on the left bank side. A lifting equipment 21 and a carrier 23 (see FIG. 4) that can travel in the direction of the bridge axis are installed on the upper surface of the erection girder 5 .

この状態から、図2に示されるように、鋼管矢板井筒91から右岸側に向けて架設桁5が送り出され、鋼管矢板井筒1の近傍まで片持ちで延伸される。その後、鋼管矢板井筒1の上部に、前述の仮支柱97と同様の構造の仮支柱7が設けられる。この仮支柱7の構築は、左岸から架設桁5を通じて搬送される資機材9を用いて行われる。なお、本明細書における「資機材」には、例えば、鉄筋、鉄骨、PC鋼材、生コンクリート等の建設材料や、型枠、仮設足場等の建設資材が含まれる。例えば、左岸から延びる完成済みの既設の橋桁(図示せず)が存在する場合には、当該既設橋桁と架設桁5とを通じて上記のような資機材9が搬送される。例えば、生コンクリートは、既設橋桁及び架設桁5に設けられた配管(図示せず)を通じて、左岸から打設現場に供給される。 From this state, as shown in FIG. 2 , the erection girder 5 is sent out from the steel pipe sheet pile well 91 toward the right bank side and extended to the vicinity of the steel pipe sheet pile well 1 in a cantilever manner. Thereafter, a temporary support 7 having the same structure as the temporary support 97 described above is provided on the upper portion of the steel pipe sheet pile well 1 . Construction of this temporary support 7 is carried out using materials and equipment 9 transported from the left bank through the erection girder 5 . In addition, the "materials and equipment" in this specification includes, for example, construction materials such as reinforcing bars, steel frames, PC steel materials, ready-mixed concrete, and construction materials such as formwork and temporary scaffolding. For example, if there is a completed existing bridge girder (not shown) extending from the left bank, the materials and equipment 9 as described above are transported through the existing bridge girder and the construction girder 5 . For example, ready-mixed concrete is supplied from the left bank to the casting site through a pipe (not shown) provided on the existing bridge girder and the erected girder 5 .

図4にも示されるように、仮支柱7は、鋼管矢板井筒1の上端部のうち、橋軸直角方向に対面する箇所に1つずつ形成される。そして、一対の仮支柱7の上端に、橋軸直角方向に延びる受梁11が架け渡される。一対の仮支柱7は、後述する柱頭部41に干渉しない位置及び大きさで設けられる。また、仮支柱7は、上記受梁11が上記柱頭部41に干渉しないような高さに設けられる。仮支柱7は、鋼管矢板井筒1を構成する複数の鋼管3の上端部に接合される。この接合方法は、例えば,溶接、ボルト締結等の種々の接合方法が採用され得る。 As also shown in FIG. 4 , the temporary supports 7 are formed one by one at the upper ends of the steel pipe sheet pile wells 1 facing each other in the direction perpendicular to the bridge axis. A support beam 11 extending in the direction perpendicular to the bridge axis is bridged over the upper ends of the pair of temporary supports 7 . The pair of temporary pillars 7 are provided at positions and sizes that do not interfere with the stigmas 41 to be described later. Further, the temporary support 7 is provided at a height such that the support beam 11 does not interfere with the column head 41 . The temporary support 7 is joined to the upper ends of the plurality of steel pipes 3 that constitute the steel pipe sheet pile well 1 . For this joining method, various joining methods such as welding and bolting can be adopted.

その後、図3及び図4に示されるように、架設桁5の先端部を受梁11及び仮支柱7に支持させるようにして、鋼管矢板井筒91から右岸側に向けて更に架設桁5が送り出される。最終的には、送り出された架設桁5の先端部が鋼管矢板井筒1の鉛直上方を横切る位置まで送り出される。そして、架設桁5と受梁11との間に、サンドル、ジャッキ、駆動シンクロジャッキ、エンドレスローラー等を含む嵩上装置12が挿入されることで、架設桁5の上下位置が調整される。架設桁5は、仮支柱7を介して鋼管矢板井筒1で支持されると共に、仮支柱97を介して鋼管矢板井筒91で支持された状態となる。すなわち、鋼管矢板井筒91から鋼管矢板井筒1に対して架設桁5が架け渡された状態となり、架設桁5は、少なくとも鋼管矢板井筒1及び鋼管矢板井筒91によって支持される。このとき例えば、架設桁5の長さが少なくとも2スパン分であり、鋼管矢板井筒91の更に左岸側に隣接する鋼管矢板井筒(図示せず)を含め3本の鋼管矢板井筒で架設桁5が支持されてもよい。 After that, as shown in FIGS. 3 and 4, the tip of the erection girder 5 is supported by the receiving beam 11 and the temporary support 7, and the erection girder 5 is further sent out from the steel pipe sheet pile well 91 toward the right bank side. be Finally, the tip of the erection girder 5 that has been sent out is sent out to a position that crosses the vertical upper part of the steel pipe sheet pile well 1 . A lifting device 12 including a sander, a jack, a drive synchronous jack, an endless roller, etc. is inserted between the erection girder 5 and the support beam 11 to adjust the vertical position of the construction girder 5 . The erection girder 5 is supported by the steel pipe sheet pile well 1 via the temporary support 7 and supported by the steel pipe sheet pile well 91 via the temporary support 97 . That is, the erection girder 5 is bridged from the steel pipe sheet pile well 91 to the steel pipe sheet pile well 1 , and the construction girder 5 is supported by at least the steel pipe sheet pile well 1 and the steel pipe sheet pile well 91 . At this time, for example, the length of the erection girder 5 is at least two spans, and the erection girder 5 is formed by three steel pipe sheet pile wells including a steel pipe sheet pile well (not shown) adjacent to the steel pipe sheet pile well 91 on the left bank side. may be supported.

〔橋脚構築工程〕
橋脚構築工程では、図4に示されるように、水面73の上方において鋼管矢板井筒1の外縁部から水平に張出した張出ステージ13が設けられる(ステージ設置工程)。張出ステージ13は、例えば鋼管矢板井筒1を中心とする円環板状をなし、鋼管矢板井筒1に支持され当該鋼管矢板井筒1の全周に亘って存在している。また、張出ステージ13上には、当該張出ステージ13上を走行可能な運搬台車15と、当該運搬台車15に資機材9を積み降ろしする揚重設備17と、が設置される。また、受梁11の下面には、鋼管矢板井筒1の内部と運搬台車15との間で資機材9を上下に搬送する天井クレーン19が設置される。またここでは、架設桁5上の揚重設備21は、鋼管矢板井筒1の上方の位置(例えば、受梁11の直上の位置)に配置される。
[Bridge construction process]
In the pier construction process, as shown in FIG. 4, an overhang stage 13 horizontally overhanging from the outer edge of the steel pipe sheet pile well 1 above the water surface 73 is provided (stage installation process). The overhang stage 13 has, for example, an annular plate shape centered on the steel pipe sheet pile well 1 , is supported by the steel pipe sheet pile well 1 , and exists over the entire circumference of the steel pipe sheet pile well 1 . Further, on the projecting stage 13, a carriage 15 capable of running on the projecting stage 13 and a lifting equipment 17 for loading and unloading the materials and equipment 9 on the carriage 15 are installed. An overhead crane 19 is installed on the lower surface of the support beam 11 for vertically transporting the materials and equipment 9 between the inside of the steel pipe sheet pile well 1 and the carriage 15 . Further, here, the lifting equipment 21 on the construction girder 5 is arranged at a position above the steel pipe sheet pile well 1 (for example, a position directly above the receiving beam 11).

平面視において、張出ステージ13は、架設桁5から橋軸直角方向にはみ出すサイズに設けられる。この構造により、揚重設備21は、架設桁5上の資機材9を鉛直に吊下ろして張出ステージ13上に仮置きしたり、張出ステージ13上の資機材9を鉛直に吊上げて架設桁5上に運搬したりすることができる。ここで仮に、張出ステージ13が存在せず、架設桁5から鋼管矢板井筒1内部まで揚重設備21で資機材9を搬送するとすれば、揚重設備21から吊下げられた資機材9を当該揚重設備21の鉛直下方の位置に向けて内側に引き込む作業が発生し、作業の安全性が低下する虞がある。これに対し、張出ステージ13が存在することにより、揚重設備21による資機材9の搬送を鉛直方向にすることができ、作業の安全性を高めることができる。 In plan view, the overhang stage 13 is provided in a size that protrudes from the erection girder 5 in the direction perpendicular to the bridge axis. With this structure, the lifting equipment 21 vertically suspends the materials and equipment 9 on the erection girder 5 and temporarily places them on the overhanging stage 13, or vertically lifts the materials and equipment 9 on the overhanging stage 13 for erection. It can be transported on the girder 5. Here, if the overhang stage 13 does not exist and the materials and equipment 9 are transported from the erection girder 5 to the inside of the steel pipe sheet pile well 1 by the lifting equipment 21, the materials and equipment 9 suspended from the lifting equipment 21 There is a possibility that the lifting equipment 21 will need to be pulled inward toward a vertically downward position, and the safety of the work will be reduced. On the other hand, due to the existence of the projecting stage 13, the equipment 9 can be transported vertically by the lifting equipment 21, and the safety of the work can be enhanced.

揚重設備17は、張出ステージ13上に仮置きされた資機材9を運搬台車15上に積載することに用いられる。運搬台車15は、張出ステージ13の内縁から内側にはみ出すようにして天井クレーン19の鉛直下方の位置にも移動可能である。この構造により、天井クレーン19は、運搬台車15上の資機材9を鉛直に吊上げ及び吊下ろしし鋼管矢板井筒1内部まで運搬することができる。上記のような運搬台車15の移動を可能とするために、例えば図4に示されるように、運搬台車15を案内する案内レール14が張出ステージ13に設けられてもよい。案内レール14は、張出ステージ13の上面を含む平面に沿って設けられ、例えば、橋軸直角方向に延びるレール14aと、天井クレーン19の下方で橋軸方向に延びるレール14bとを有している。レール14bの両端は張出ステージ13の内縁で両持ち支持されてもよい。運搬台車15は、このような案内レール14で案内されて、橋軸直角方向の移動が可能であり、また天井クレーン19の鉛直下方(鋼管矢板井筒1内部の鉛直上方)を通過するような橋軸方向の移動が可能である。 The lifting equipment 17 is used to load the materials and equipment 9 temporarily placed on the overhanging stage 13 onto the carriage 15 . The carriage 15 can also move to a position vertically below the overhead crane 19 so as to protrude inward from the inner edge of the overhang stage 13 . With this structure, the overhead crane 19 can vertically lift and lower the materials and equipment 9 on the carriage 15 and transport them to the inside of the steel pipe sheet pile well 1 . In order to enable the movement of the carriage 15 as described above, a guide rail 14 for guiding the carriage 15 may be provided on the overhang stage 13 as shown in FIG. 4, for example. The guide rail 14 is provided along a plane including the upper surface of the overhang stage 13, and includes, for example, a rail 14a extending in the direction perpendicular to the bridge axis and a rail 14b extending in the bridge axis direction below the overhead crane 19. there is Both ends of the rail 14b may be supported by the inner edges of the overhanging stage 13. FIG. The carriage 15 is guided by such a guide rail 14 and can move in the direction perpendicular to the bridge axis. Axial movement is possible.

図5に示されるように、張出ステージ13の設置後、鋼管矢板井筒1の内部において、必要に応じて内部補強をしながら河底の水中掘削が実行され、敷石層27及び底盤コンクリート29が構築された後、鋼管矢板井筒1の内部がドライアップされ、底盤コンクリート29上に頂版コンクリート31が構築される。更に、頂版コンクリート31の上方に鉄筋コンクリート製の橋脚33が構築される。 As shown in FIG. 5, after the overhang stage 13 is installed, underwater excavation of the riverbed is performed inside the steel pipe sheet pile well 1 while reinforcing the inside as necessary, and the paving stone layer 27 and the bottom concrete 29 are formed. After construction, the inside of the steel pipe sheet pile well 1 is dried up, and the top slab concrete 31 is constructed on the bottom concrete 29 . Furthermore, a pier 33 made of reinforced concrete is constructed above the top slab concrete 31 .

その後、一対の仮支柱7同士の間の位置で、橋脚33の上方に、場所打ちコンクリートによる柱頭部41が構築される。そして、柱頭部41が完成した後、受梁11及び架設桁5の荷重が柱頭部41に盛り替えられ、鋼管矢板井筒1の上部が頂版コンクリート31の上端の位置で切除される。受梁11及び架設桁5の荷重の盛り替え方法は、図11(b)で説明した方法と同様であるので、詳細な説明を省略する。 After that, a column head 41 made of cast-in-place concrete is constructed above the bridge pier 33 at a position between the pair of temporary pillars 7 . After the column head 41 is completed, the load of the supporting beam 11 and the erection girder 5 is transferred to the column head 41, and the upper part of the steel pipe sheet pile well 1 is cut off at the position of the upper end of the top concrete 31. Since the method of changing the load of the receiving beam 11 and the erection girder 5 is the same as the method described in FIG. 11(b), detailed description thereof will be omitted.

以上のようにして橋脚33が完成する。上部が切除されて残存する鋼管矢板井筒1と、当該鋼管矢板井筒1内部に構築された敷石層27、底盤コンクリート29、及び頂版コンクリート31と、によって橋脚33の基礎が構成される。 The bridge pier 33 is completed as described above. The foundation of the bridge pier 33 is composed of the steel pipe sheet pile well 1 remaining after the upper part is excised, and the paving stone layer 27, the bottom concrete 29, and the top concrete 31 constructed inside the steel pipe sheet pile well 1.

なお、このように橋脚33が完成した後は、柱頭部41が橋軸方向の両方に張出すように延長される。その後、延長された柱頭部41の両側にそれぞれワーゲン(図示せず)が設置され、張出架設工法によって橋桁が順次構築されていく。その後、架設桁5は、隣の鋼管矢板井筒に向けて送り出され、当該隣の鋼管矢板井筒において上述の工程が実行される。以上を鋼管矢板井筒ごとに実行することで、橋梁が建造される。 After the bridge pier 33 is completed in this way, the column head 41 is extended so as to protrude in both directions of the bridge axis. After that, wagons (not shown) are installed on both sides of the extended column head 41, and bridge girders are sequentially constructed by the overhang erection method. After that, the erection girder 5 is sent out toward the adjacent steel pipe sheet pile well, and the above-described steps are performed in the adjacent steel pipe sheet pile well. A bridge is constructed by executing the above for each steel pipe sheet pile well.

上記のような水中掘削、敷石層27の構築、底盤コンクリート29の構築、ドライアップ、頂版コンクリート31の構築、橋脚33の構築、柱頭部41の構築、及び張出架設工法による橋桁の構築の方法としては、公知の方法を採用すればよく、更なる詳細な説明は省略する。 Underwater excavation as described above, construction of paving stone layer 27, construction of base concrete 29, dry-up, construction of top slab concrete 31, construction of bridge piers 33, construction of column heads 41, and construction of bridge girders by the overhang erection method. As a method, a known method may be adopted, and further detailed description is omitted.

上記のような水中掘削、敷石層27の構築、底盤コンクリート29の構築、ドライアップ、頂版コンクリート31の構築、及び橋脚33の構築に用いられる資機材9は、左岸から架設桁5を通じて鋼管矢板井筒1の内部に搬送される。すなわち、鋼管矢板井筒1は、完成済みの既設の橋桁と、架設桁5とを介して左岸に接続されている。そして、上記の資機材は、河岸から既設橋桁及び架設桁5を通じて鋼管矢板井筒1の内部に搬送される。例えば、コンクリート打設に使用される生コンクリートは、既設の橋桁及び架設桁5上に設けられた配管(図示せず)を通じて左岸から打設現場に供給される。なお、上記のような柱頭部41の構築、及び張出架設工法による橋桁の構築に使用される資機材9も、左岸から既設橋桁及び架設桁5を通じて必要な場所に搬送される。また、水中掘削による掘削土は架設桁5上にベルコン等の搬送装置を設置して運搬する。 The materials and equipment 9 used for underwater excavation, construction of the pavement layer 27, construction of the bottom concrete 29, dry-up, construction of the top slab concrete 31, and construction of the bridge piers 33 are carried from the left bank through the installation girder 5 to the steel pipe sheet piles. It is transported inside the well 1 . That is, the steel pipe sheet pile well 1 is connected to the left bank via the completed existing bridge girder and the erection girder 5 . The materials and equipment are transported from the river bank into the steel pipe sheet pile well 1 through the existing bridge girders and the erected girders 5 . For example, ready-mixed concrete used for concrete casting is supplied from the left bank to the casting site through a pipe (not shown) provided on the existing bridge girder and erection girder 5 . The materials and equipment 9 used for constructing the column head 41 as described above and constructing the bridge girder by the overhang erection method are also transported from the left bank through the existing bridge girder and the erection girder 5 to the required location. Further, excavated soil by underwater excavation is transported by installing a conveying device such as a belcon on the construction girder 5 .

特に、架設桁5上から鋼管矢板井筒1内部までの資機材9の搬送は、前述の運搬台車23、揚重設備21、揚重設備17、運搬台車15、及び天井クレーン19を用いて実行される。このとき、架設桁5上を運搬台車23によって揚重設備21近傍まで搬送された資機材9は、揚重設備21によって鉛直に吊下ろされて、張出ステージ13上に仮置きされる(仮置き工程)。そして、仮置きされた資機材9は、揚重設備17によって運搬台車15に積載され、運搬台車15は天井クレーン19の鉛直下方の位置まで水平移動する。そして、運搬台車15上の資機材9が天井クレーン19で吊上げられ、運搬台車15が張出ステージ13上に退避した後、資機材9は天井クレーン19によって鉛直下方に吊下ろされ、鋼管矢板井筒1内部に搬送される。 In particular, the transportation of the materials and equipment 9 from the erection girder 5 to the inside of the steel pipe sheet pile well 1 is carried out using the above-described transport truck 23, lifting equipment 21, lifting equipment 17, transport truck 15, and overhead crane 19. be. At this time, the materials and equipment 9 transported to the vicinity of the lifting equipment 21 by the carriage 23 on the erection girder 5 are vertically suspended by the lifting equipment 21 and temporarily placed on the overhang stage 13 (temporary placement process). The materials and equipment 9 that have been temporarily placed are then loaded onto the carriage 15 by the lifting equipment 17 , and the carriage 15 moves horizontally to a position vertically below the overhead crane 19 . Then, the materials and equipment 9 on the carriage 15 are lifted by the overhead crane 19, and after the carriage 15 is evacuated onto the overhanging stage 13, the materials and equipment 9 are hung vertically downward by the overhead crane 19, and the steel pipe sheet pile well is 1 inside.

なお、鋼管矢板井筒1内部への資機材9の搬送に関して、張出ステージ13上に仮置きされた資機材9同士が張出ステージ13上で組み立てられユニット化されて、当該資機材ユニットが鋼管矢板井筒1の内部に吊下ろされてもよい(ユニット吊下工程)。具体例として、資機材9の一例である足場材が張出ステージ13上で地組みされて足場ユニットが形成され、この足場ユニットが揚重設備17、運搬台車15、及び天井クレーン19を用いて鋼管矢板井筒1内部へ搬送されてもよい。 Regarding the transportation of the materials and equipment 9 to the inside of the steel pipe sheet pile well 1, the materials and equipment 9 temporarily placed on the overhanging stage 13 are assembled on the overhanging stage 13 to form a unit, and the material and equipment unit is a steel pipe It may be suspended inside the sheet pile well 1 (unit suspension process). As a specific example, a scaffolding material, which is an example of the materials and equipment 9, is assembled on the overhanging stage 13 to form a scaffolding unit, and this scaffolding unit is lifted using the lifting equipment 17, the carrier 15, and the overhead crane 19. It may be transported inside the steel pipe sheet pile well 1 .

橋脚33の構築に用いられる足場は、橋脚33の構築予定位置と鋼管矢板井筒1の内壁面との間の狭隘スペースに設置する必要がある。また、足場を組立てる際には、橋脚33の高さに対応する高所での作業が必要になる。これに対し、上記のように、比較的安全な張出ステージ13上で予めユニット化された足場ユニットが鋼管矢板井筒1内部に搬送されることで、上記のような狭隘スペース且つ高所における作業が削減され工事の危険が低減される。また、資機材の揚重回数が削減される。このような資機材ユニットとしては、上記のように地組された足場ユニットの他、鉄筋同士(帯鉄筋及び中間帯鉄筋など)を組立ててなる鉄筋ユニットや、外型枠、内型枠及び大判型枠を組立ててなる型枠ユニット、等が考えられる。なお、上記のような資機材ユニットは、架設桁5上、又は左岸において既に組立てられていてもよい。 The scaffolding used for constructing the pier 33 needs to be installed in a narrow space between the planned construction position of the pier 33 and the inner wall surface of the steel pipe sheet pile well 1 . Moreover, when assembling the scaffolding, it is necessary to work at a high place corresponding to the height of the bridge pier 33 . On the other hand, as described above, the scaffolding unit unitized in advance on the relatively safe overhanging stage 13 is conveyed inside the steel pipe sheet pile well 1, so that work in a narrow space and high place as described above can be performed. is reduced and construction hazards are reduced. In addition, the number of lifting times of materials and equipment is reduced. Such material and equipment units include scaffolding units that are assembled as described above, reinforcing bar units that are made by assembling reinforcing bars (band reinforcing bars, intermediate band reinforcing bars, etc.), outer formwork, inner formwork, and large format. A formwork unit formed by assembling formwork, and the like are conceivable. Incidentally, the material and equipment unit as described above may already be assembled on the erection girder 5 or on the left bank.

以上説明したような橋脚構築方法が繰返し実行されることで、右岸側に向かって各橋脚33が順次完成していく。なお、完成後の各橋脚33においては、それぞれ、柱頭部が構築され各柱頭部から張出架設工法によって橋桁が構築されるようにしてもよい。このような本実施形態の橋脚構築方法では、橋脚33が主に上空から施工されることで浚渫量が削減されて環境への影響が軽減されると共に渇水期を含めた通年施工を可能になり施工期間の短縮が図られる。そして、本実施形態の橋脚構築方法によれば、鋼管矢板井筒1の近傍まで片持ちで架設桁5を延伸して鋼管矢板井筒1に仮支柱7を構築するので、主に上空からの橋脚33の施工を効率良く行うことができる。 By repeatedly executing the pier construction method as described above, each pier 33 is sequentially completed toward the right bank side. In addition, on each bridge pier 33 after completion, a column head may be constructed and a bridge girder may be constructed from each column head by an overhang erection method. In the bridge pier construction method of this embodiment, the amount of dredging is reduced by constructing the piers 33 mainly from above, which reduces the impact on the environment and enables year-round construction including the dry season. The construction period will be shortened. According to the bridge pier construction method of the present embodiment, the erection girder 5 is cantilevered to the vicinity of the steel pipe sheet pile well 1 and the temporary support 7 is constructed on the steel pipe sheet pile well 1. construction can be done efficiently.

(第2実施形態)
続いて、第2実施形態に係る橋脚構築方法について説明する。本実施形態の説明において、第1実施形態と同一又は同等の構成要素には同一の符号を付して重複する説明を省略する。前述の第1実施形態では、架設桁5が仮支柱7を介して鋼管矢板井筒1で支持されるのに対し、本実施形態は、架設桁5が河底71に打設された仮支柱37で支持される点において異なっている。本実施形態の橋脚構築方法は、次に説明する締切工程と、仮支柱構築工程と、桁架設工程と、橋脚構築工程と、を備える。
(Second embodiment)
Next, a bridge pier construction method according to the second embodiment will be described. In the description of this embodiment, the same reference numerals are given to the same or equivalent components as in the first embodiment, and duplicate descriptions are omitted. In the above-described first embodiment, the erection girder 5 is supported by the steel pipe sheet pile well 1 via the temporary support 7, whereas in this embodiment, the erection girder 5 is supported by the temporary support 37 driven into the riverbed 71. It is different in that it is supported by The bridge pier construction method of this embodiment includes a cofferdam construction process, a temporary support construction process, a girder erection process, and a pier construction process, which will be described below.

〔締切工程〕
図6に示されるように、本実施形態の締切工程では、第1実施形態の締切工程と同様に、鋼管矢板井筒1が構築される。
[Deadline process]
As shown in FIG. 6, in the closing process of the present embodiment, a steel pipe sheet pile well 1 is constructed in the same manner as in the closing process of the first embodiment.

〔仮支柱構築工程〕
図6に示されるように、仮支柱構築工程では、鋼管矢板井筒1の近傍の水域に仮支柱37が構築される。具体的には、例えば杭打ち台船を用いて、鋼管矢板井筒1の近傍で左岸側及び右岸側それぞれに1本ずつの仮支柱37が河底71に打設される。仮支柱37は、鋼管矢板井筒1よりも高い位置まで、水面73から上方に突出する。仮支柱37としては、鋼管矢板井筒1を構成する鋼管3と同様の鋼管が採用されてもよい。この場合、前述の締切工程で使用された鋼管3の打設装置(例えば杭打ち台船)を、当該仮支柱構築工程における仮支柱37の打設装置としてそのまま使用することができる。
[Temporary post construction process]
As shown in FIG. 6 , in the temporary support construction step, a temporary support 37 is constructed in a water area near the steel pipe sheet pile well 1 . Specifically, for example, using a pile-driving barge, the temporary supports 37 are driven into the riverbed 71 in the vicinity of the steel pipe sheet pile well 1, one each on the left bank side and the right bank side. The temporary support 37 protrudes upward from the water surface 73 to a position higher than the steel pipe sheet pile well 1 . A steel pipe similar to the steel pipe 3 constituting the steel pipe sheet pile well 1 may be employed as the temporary support 37 . In this case, the device for driving the steel pipes 3 (for example, a pile-driving barge) used in the coffering process can be used as it is as the device for driving the temporary pillars 37 in the temporary pillar construction process.

〔桁架設工程〕
桁架設工程の前の段階では、図7に示されるように、鋼管矢板井筒91の近傍で左岸側及び右岸側それぞれに1本ずつ仮支柱98が設けられており、破線で示されるように架設桁5は仮支柱98で支持されている。或いは、仮支柱98と、更に左岸側に配列された既設の鋼管矢板井筒(図示せず)近傍の仮支柱と、を含めた複数の仮支柱で架設桁5が支持されていてもよい。
[Girder erection process]
At the stage before the girder erection process, as shown in FIG. 7, temporary struts 98 are provided on each of the left bank side and the right bank side in the vicinity of the steel pipe sheet pile well 91. The girder 5 is supported by temporary struts 98 . Alternatively, the erection girder 5 may be supported by a plurality of temporary pillars including the temporary pillar 98 and a temporary pillar near an existing steel pipe sheet pile well (not shown) arranged on the left bank side.

桁架設工程では、この状態から、図7に示されるように、仮支柱98から右岸側に向けて架設桁5が送り出され、最終的には、架設桁5の先端部が鋼管矢板井筒1の鉛直上方を横切る位置まで送り出され、架設桁5の先端部が仮支柱37に支持される。すなわち、仮支柱98から仮支柱37に対して架設桁5が架け渡された状態となり、架設桁5は少なくとも仮支柱98及び仮支柱37によって支持される。また、第1実施形態と同様に、架設桁5と仮支柱37,98との間には、適宜、サンドル、ジャッキ、駆動シンクロジャッキ、エンドレスローラー等を含む嵩上装置39が挟み込まれる。このように架け渡された架設桁5と、鋼管矢板井筒1と、の位置関係は第1実施形態と同様である。従って、架設桁5上の揚重設備21を用いて、架設桁5上と張出ステージ13上との間での資機材9の搬送が可能である。 In the girder erection process, as shown in FIG. 7, the erection girder 5 is sent out from the temporary support 98 toward the right bank, and finally, the tip of the erection girder 5 reaches the steel pipe sheet pile well 1. It is sent out to a position crossing vertically upward, and the tip of the construction girder 5 is supported by the temporary support 37 . That is, the construction girder 5 is bridged from the temporary support 98 to the temporary support 37 , and the construction girder 5 is supported by at least the temporary support 98 and the temporary support 37 . Further, similarly to the first embodiment, between the erection girder 5 and the temporary struts 37, 98, a lifting device 39 including sandals, jacks, drive synchronous jacks, endless rollers, etc. is interposed as appropriate. The positional relationship between the erection girder 5 bridged in this manner and the steel pipe sheet pile well 1 is the same as in the first embodiment. Therefore, using the lifting equipment 21 on the erection girder 5 , it is possible to transport the materials and equipment 9 between the construction girder 5 and the overhang stage 13 .

〔橋脚構築工程〕
図8に示されるように、橋脚構築工程では、第1実施形態と同様に、張出ステージ13が構築される。更に、第1実施形態と同様に、水中掘削、敷石層27の構築、底盤コンクリート29の構築、ドライアップ、頂版コンクリート31の構築、橋脚33の構築が実行されて、橋脚33が完成する。また、第1実施形態と同様に、柱頭部41の構築、及び張出架設工法による橋桁の構築が実行されて、橋桁が構築される。
[Bridge construction process]
As shown in FIG. 8, in the bridge pier construction process, the projecting stage 13 is constructed as in the first embodiment. Furthermore, as in the first embodiment, underwater excavation, construction of paving stone layer 27, construction of base concrete 29, dry-up, construction of top concrete 31, and construction of pier 33 are executed to complete pier 33. Further, similarly to the first embodiment, the construction of the column head 41 and the construction of the bridge girder by the overhang construction method are executed to construct the bridge girder.

以上、本発明の第1及び第2実施形態について説明したが、本発明は、上記実施形態に限られるものではなく、各請求項に記載した要旨を変更しない範囲で変形したものであってもよい。各実施形態の構成を適宜組み合わせて使用してもよい。 As described above, the first and second embodiments of the present invention have been described, but the present invention is not limited to the above embodiments, and may be modified within the scope of not changing the gist described in each claim. good. You may use it, combining the structure of each embodiment suitably.

例えば、各実施形態における鋼管矢板井筒1代えて、鋼殻ケーソン又はニューマチックケーソンが、橋脚の基礎を構築するための前段構造物として採用されてもよい。この場合、各実施形態における締切工程に代えて、水域にケーソンを沈設するケーソン沈設工程が前段構造物構築工程として実行される。この種の鋼殻ケーソン又はニューマチックケーソンの設置方法については公知の方法を採用すればよく、更なる詳細な説明は省略する。 For example, instead of the steel pipe sheet pile well 1 in each embodiment, a steel shell caisson or a pneumatic caisson may be adopted as the front structure for constructing the foundation of the pier. In this case, instead of the closing process in each embodiment, a caisson sinking process of sinking a caisson in a water area is executed as the pre-stage structure construction process. As for the installation method of this kind of steel-shelled caisson or pneumatic caisson, a well-known method can be adopted, and further detailed explanation is omitted.

また、鋼管矢板井筒1は平面視円環状のものに限られず、例えば、いわゆる小判形の鋼管矢板井筒であってもよく、平面視矩形の鋼管矢板井筒であってもよい。また、各実施形態における鋼管矢板井筒1代えて、複数の鋼矢板を井筒状に配置して水域を締切る締切工が採用されてもよい。第2実施形態においては、1つの鋼管矢板井筒に対して2本の仮支柱37が設けられているが、1つの鋼管矢板井筒に対して設けられる仮支柱37の本数はこれには限定されず、必要に応じて適宜設計すればよい。また、第1実施形態において、仮支柱7及び嵩上装置12は、鋼管矢板井筒1に向けて送り出される架設桁5の先端部下面に予め設けられていてもよい。 Further, the steel pipe sheet pile well 1 is not limited to an annular one in plan view, and may be, for example, a so-called oval steel pipe sheet pile well or a steel pipe sheet pile well rectangular in plan view. Further, instead of the steel pipe sheet pile well 1 in each embodiment, a cofferdam that closes off a water area by arranging a plurality of steel sheet piles in a well may be employed. In the second embodiment, two temporary supports 37 are provided for one steel pipe sheet pile well, but the number of temporary supports 37 provided for one steel pipe sheet pile well is not limited to this. , may be appropriately designed as necessary. Further, in the first embodiment, the temporary support 7 and the lifting device 12 may be provided in advance on the lower surface of the tip portion of the erection girder 5 sent out toward the steel pipe sheet pile well 1 .

さらに、張出ステージ13は鋼管矢板井筒1を中心とする円環板状をなすものに限られず、例えば、矩形状のものでもよく、鋼管矢板井筒1を中心としたとしたものでなく一部が突出したような形状でもよい。 Furthermore, the overhanging stage 13 is not limited to having the shape of an annular plate centered on the steel pipe sheet pile well 1. For example, it may have a rectangular shape. It may be shaped like a protruding .

1…鋼管矢板井筒(前段構造物、締切工)、5…架設桁、7,37…仮支柱、9…資機材、13…張出ステージ、33…橋脚。 DESCRIPTION OF SYMBOLS 1... Steel pipe sheet pile well (former stage structure, cofferdam), 5... Erection girder, 7, 37... Temporary support, 9... Material and equipment, 13... Overhang stage, 33... Bridge pier.

Claims (6)

水域に橋脚を構築する橋脚構築方法であって、
前記水域に前記橋脚の基礎を構築するための前段構造物を構築する前段構造物構築工程と、
前記前段構造物に設けられた仮支柱を介して前記前段構造物に支持されるように、架設桁を前記前段構造物に架け渡す桁架設工程と、
前記架設桁を通じて搬送される資機材を用いて前記前段構造物に前記橋脚を構築する橋脚構築工程と、を備え、
前記仮支柱は、前記桁架設工程に先立って、前記前段構造物の近傍まで片持ちで延伸された前記架設桁を通じて搬送される資機材を用いて前記前段構造物に設けられる、橋脚構築方法。
A pier construction method for constructing a pier in a body of water,
a front-stage structure building step of building a front-stage structure for building a foundation of the bridge pier in the water area;
A girder erecting step of constructing an erection girder over the front-stage structure so as to be supported by the front-stage structure via temporary supports provided on the front-stage structure;
a pier construction step of constructing the pier on the front structure using materials and equipment transported through the erection girder;
The bridge pier construction method, wherein, prior to the girder erection step, the temporary pillars are provided on the front structure using materials and equipment transported through the erection girder that is cantilevered to the vicinity of the front structure.
水域に橋脚を構築する橋脚構築方法であって、
前記水域に前記橋脚の基礎を構築するための前段構造物を構築する前段構造物構築工程と、
前記前段構造物の近傍の水域に仮支柱を構築する仮支柱構築工程と、
前記仮支柱に架設桁を架け渡す桁架設工程と、
前記架設桁を通じて搬送される資機材を用いて前記前段構造物に前記橋脚を構築する橋脚構築工程と、を備え、
前記前段構造物は、前記水域を締切る締切工を有し、
前記橋脚構築工程では、前記締切工の内部に前記橋脚が構築される、橋脚構築方法。
A pier construction method for constructing a pier in a body of water,
a front-stage structure building step of building a front-stage structure for building a foundation of the bridge pier in the water area;
A temporary support building step of constructing a temporary support in a water area near the front stage structure;
A girder erecting step of building an erection girder over the temporary support;
a pier construction step of constructing the pier on the front structure using materials and equipment transported through the erection girder;
The front stage structure has a cofferdam that closes off the water area,
The pier construction method, wherein in the pier construction step, the pier is constructed inside the cofferdam.
前記前段構造物は、前記水域を締切る締切工を有し、
前記橋脚構築工程では、前記締切工の内部に前記橋脚が構築される、請求項1に記載の橋脚構築方法。
The front stage structure has a cofferdam that closes off the water area,
2. The bridge pier construction method according to claim 1, wherein, in said bridge pier construction step, said pier is constructed inside said cofferdam.
前記橋脚構築工程は、
前記橋脚の構築に用いる資機材を仮置きするための、前記締切工に支持され前記締切工から外側に張出した張出ステージを設けるステージ設置工程を有する、請求項2又は3に記載の橋脚構築方法。
The pier construction step includes:
4. The bridge pier construction according to claim 2 or 3, comprising a stage installation step of providing an overhanging stage supported by said cofferdam and projecting outward from said cofferdam for temporarily placing materials and equipment used for constructing said bridge pier. Method.
前記橋脚構築工程は、
前記資機材同士が組み立てられて構成される資機材ユニットを前記締切工の内部に吊下ろすユニット吊下工程を有する、請求項~4の何れか1項に記載の橋脚構築方法。
The pier construction step includes:
The bridge pier construction method according to any one of claims 2 to 4, further comprising a unit suspension step of suspending a material/equipment unit constructed by assembling said materials/equipment together inside said cofferdam.
水域に橋脚を構築する橋脚構築方法であって、
前記水域を締切る締切工を構築する締切工程と、
前記締切工の鉛直上方を通過する架設桁を設置する桁架設工程と、
前記橋脚の構築に用いる資機材を仮置きするための、前記締切工に支持され前記締切工から外側に張出し前記架設桁からはみ出すサイズの張出ステージを設けるステージ設置工程と、
前記資機材を前記架設桁を通じて搬送し、前記張出ステージに吊下ろして仮置きし、前記締切工の内部に吊下ろす吊下工程と、
を備える、橋脚構築方法。
A pier construction method for constructing a pier in a body of water,
a coffering step of constructing cofferdams closing off the water area;
A girder erection step of installing an erection girder passing vertically above the cofferdam;
A stage installation step of providing an overhang stage of a size that is supported by the cofferdam, extends outward from the cofferdam, and protrudes from the erection girder for temporarily placing materials and equipment used for constructing the bridge pier;
A suspension step of transporting the materials and equipment through the erection girder, suspending them on the overhang stage for temporary placement, and suspending them inside the cofferdam;
A bridge pier construction method comprising:
JP2019186695A 2019-10-10 2019-10-10 Bridge pier construction method Active JP7319887B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2019186695A JP7319887B2 (en) 2019-10-10 2019-10-10 Bridge pier construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2019186695A JP7319887B2 (en) 2019-10-10 2019-10-10 Bridge pier construction method

Publications (2)

Publication Number Publication Date
JP2020002778A JP2020002778A (en) 2020-01-09
JP7319887B2 true JP7319887B2 (en) 2023-08-02

Family

ID=69099094

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2019186695A Active JP7319887B2 (en) 2019-10-10 2019-10-10 Bridge pier construction method

Country Status (1)

Country Link
JP (1) JP7319887B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112813848A (en) * 2021-02-18 2021-05-18 中交第二公路工程局有限公司 Supporting structure for platform erection based on steel pile foundation and construction method
CN114370004B (en) * 2022-01-14 2024-01-30 中国电建集团市政规划设计研究院有限公司 Island-shaped viewing platform and bridge construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002188159A (en) 2000-12-19 2002-07-05 Kajima Corp Execution method for underwater structure
JP2003082603A (en) 2001-09-12 2003-03-19 East Japan Railway Co Construction method for structure under rail track
JP2008214940A (en) 2007-03-02 2008-09-18 Sumitomo Mitsui Construction Co Ltd Movable suspension timbering
JP2017057615A (en) 2015-09-16 2017-03-23 五洋建設株式会社 Temporary scaffolding of pile-type aquatic structure and its installation method
JP2017210840A (en) 2016-05-27 2017-11-30 鹿島建設株式会社 Temporary cut-off method, temporary cut-off structure

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6462518A (en) * 1987-09-01 1989-03-09 Morinaga Gumi Kk Continuous placement of concrete underwater

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002188159A (en) 2000-12-19 2002-07-05 Kajima Corp Execution method for underwater structure
JP2003082603A (en) 2001-09-12 2003-03-19 East Japan Railway Co Construction method for structure under rail track
JP2008214940A (en) 2007-03-02 2008-09-18 Sumitomo Mitsui Construction Co Ltd Movable suspension timbering
JP2017057615A (en) 2015-09-16 2017-03-23 五洋建設株式会社 Temporary scaffolding of pile-type aquatic structure and its installation method
JP2017210840A (en) 2016-05-27 2017-11-30 鹿島建設株式会社 Temporary cut-off method, temporary cut-off structure

Also Published As

Publication number Publication date
JP2020002778A (en) 2020-01-09

Similar Documents

Publication Publication Date Title
JP4722783B2 (en) Foundation reinforcement method for existing buildings
JP4853429B2 (en) Support structure of lining board, method of supporting lining board
JP7319887B2 (en) Bridge pier construction method
CN105236275A (en) Soil lifting system and soil lifting method for building deep foundation pit construction in narrow zone
WO2023184679A1 (en) Large-span space special-shaped arch rib flying-swallow type basket steel box arch bridge and rapid construction method
CN104736465B (en) Harbour constructing device and the method for construction using same apparatus
KR101011805B1 (en) Method of constructing underground structure crossing pile bases in a pile-based ground and underground structure constructed using the same
JP2003213708A (en) Construction method for underground structure and elevated traffic roadway
CN112813969A (en) Steel pipe pile foundation and construction method thereof
JP2004285735A (en) Method of constructing temporary landing bridge by using truss frame
CN110820519A (en) Tunnel arch bridge convenient for rapid construction and construction method thereof
KR20100118482A (en) To use reclamation steel perimeter beam and slab diaphragm effect in order for one side of the basement outer wall continuous construct was possible ,which the basement infrastructure construction method
CN205061417U (en) What narrow regional building deep basal pit was under construction puies forward soil series all
JP2005002671A (en) Underpinning method and viaduct
CN105155867A (en) Underpinning device for tunnel to pass through existing large-diameter pile building
JP2004176434A (en) Method for constructing structure and underground skeleton
JP6938198B2 (en) Construction method
JP3940587B2 (en) Construction method of divided bridge type traffic route
CN204960366U (en) Tunnel passes through device that underpins of existing large diameter pile building
CN112982200B (en) Underpinning method of existing continuous bridge
CN218713281U (en) Near-track foundation pit external construction platform
WO2024007203A1 (en) New superstructure for high-piled wharf, and construction apparatus and construction method therefor
JP7419169B2 (en) How to build underground structures
JPH0711620A (en) Construction method of artificial ground
JP2003213698A (en) Bridge and construction method thereof

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20220414

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20230126

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230131

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230221

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230509

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230525

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20230718

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20230721

R150 Certificate of patent or registration of utility model

Ref document number: 7319887

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150