CN205061417U - What narrow regional building deep basal pit was under construction puies forward soil series all - Google Patents

What narrow regional building deep basal pit was under construction puies forward soil series all Download PDF

Info

Publication number
CN205061417U
CN205061417U CN201520807898.3U CN201520807898U CN205061417U CN 205061417 U CN205061417 U CN 205061417U CN 201520807898 U CN201520807898 U CN 201520807898U CN 205061417 U CN205061417 U CN 205061417U
Authority
CN
China
Prior art keywords
construction
shrouding
foundation pit
carrying
mound
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520807898.3U
Other languages
Chinese (zh)
Inventor
周予启
史春芳
廖刚林
李洪海
薛刚
魏健
刘卫未
任耀辉
詹必雄
付恩涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
Original Assignee
China Construction First Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN201520807898.3U priority Critical patent/CN205061417U/en
Application granted granted Critical
Publication of CN205061417U publication Critical patent/CN205061417U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a what narrow regional building deep basal pit was under construction puies forward soil series all which first concrete around the entrance to a cave supports and carries out big face shrouding, as being used for arranging first shrouding carrying indigenous equipment and mound platform, carry the indigenous equipment perpendicularly and adopt the steel derrick to carry native loop wheel machine, including erectting the steel derrick on the entrance to a cave and hanging the electric block on the steel derrick, the mound platform is established on first shrouding around the entrance to a cave, is the region that retaining wall and manger plate bank enclose. Support first concrete around the entrance to a cave and carry out big face shrouding, as first shrouding, for the transport vechicle provides transport corridor, for the construction of follow -up major structure provides the material store yard, provide the place for the installation of mound platform and steel derrick, set up the mound district on first shrouding, stack the earthwork that in time to transport outward temporarily, adopting the steel derrick to carry the indigenous equipment, not receiving the restriction in on -the -spot reinforced concrete ramp, increased unearthed route, greatly in advance the time limit for a project, the narrow and small deep basal pit in specially adapted place is under construction.

Description

A kind of soil series of carrying of narrow zone deep foundation pit of construction construction is united
Technical field
The utility model relates to earth excavation technical field of construction, a kind of narrow zone deep foundation pit of construction construction of particularly applying in the narrow annulus building operation of construction space carry soil series system.
Background technology
At present, in the annulus deep foundation pit of construction engineering construction that construction space is narrow, two difficult problems are usually faced, on the one hand, due to narrow field, inner support area is large, between support, clear distance is little, supports bottom earth excavation difficulty, can not utilize in a conventional manner to put slope and complete earth excavation; On the other hand, owing to lacking material stockyard, earth moving vehicles need travel and transport the earthwork to foundation ditch, morning evening peak traffic and the rainy day can not transport outward, construction speed is obstructed, and greatly extends construction period, and the normal construction of critical circuits can not ensure.
Utility model content
The utility model object is that the soil series of carrying providing a kind of narrow zone deep foundation pit of construction to construct is united, to solve in prior art in narrow zone construction because narrow field, inner support area are large, support between clear distance little, support bottom earth excavation difficulty, path of being unearthed few, can not utilize in a conventional manner and put the technical barrier that slope completes earth excavation, and owing to lacking material stockyard, earth moving vehicles need travel to transport to foundation ditch the earthwork, morning evening peak traffic and the rainy day can not transport outward in construction speed to be obstructed, greatly to extend the technical barrier of construction period.
For realizing above-mentioned technical purpose, the utility model takes following technical scheme:
The construction of a kind of narrow zone deep foundation pit of construction carry soil series system, comprise foundation pit support system, vertically carry indigenous equipment and mound platform, described foundation pit support system comprises foundation pit enclosure stake, foundation ditch stand column pile and concrete support, it is characterized in that:
Described concrete support comprises some roads from top to bottom, and the first road concrete support around hole carries out large face shrouding, as arranging the first road shrouding carrying indigenous equipment and mound platform;
Described indigenous equipment of vertically carrying adopts steel headframe to carry native loop wheel machine, comprises and is erected at steel headframe on hole and the electric block of hanging on steel headframe;
Described steel headframe comprises the column of rectangle frame and the beneath support rectangle frame enclosed by crossbeam, described column symmetry is fixed on around hole, the centre of described rectangle frame is provided with for hanging electric block and as the track girder of its moving track, the suspension hook of electric block connects suspension bucket;
Described mound platform is located on the first road shrouding around hole, is the region that retaining wall and water-blocking bank surround.
As optimal technical scheme of the present utility model, the column of described steel headframe is shaped steel column, and described crossbeam comprises girder and secondary beam, and described girder comprises strength beam vertical with track girder in the middle of Vierendeel girder and framework, described secondary beam between strength beam and Vierendeel girder, also perpendicular to track girder.
Preferably, described first road shrouding is armoured concrete slab, and its thickness range is 200 ~ 350mm, and the support beam at described armoured concrete slab and foundation ditch stand column pile top is integrated moulding by casting, and the mutual colligation of reinforcing bar between the two connects.
Preferably, described mound platform is away from muck haulage car transport channel and retaining wall is established on the both sides in a bight at close hole, and remaining sides is along all establishing water-blocking bank, and the cross-sectional plane of described water-blocking bank is protruding semicircular arc, and its maximum height is 5 ~ 20cm.
Preferably, in mound platform outer, reinforcing knoll is set along retaining wall interval.
Preferably, near the upper edge of the retaining wall of side, hole, the position of respective carter beam has the suspension bucket preformed hole entering mound platform for suspension bucket.
Preferably, described steel headframe is also provided with inspection platform.
Compared with prior art, technical advantage of the present utility model is:
1, the first road concrete support around hole is carried out large face shrouding, as first road shrouding, for transport trolley provides transport channel, earth moving vehicles, without the need to travelling to foundation ditch, can complete earthwork shipment, greatly reduce vehicle cleaning on first road supports; Construction for succeeding body structure provides material stockyard, and avoid the Secondary Transport of material, save construction cost, speed shortens the construction period; For the installation of mound platform and steel headframe provides place, its structure is simple, and receives bracing members integrated construction, easy construction;
2, vertically carrying indigenous equipment adopts steel headframe to carry indigenous equipment, it is not by the restriction in on-the-spot ferro-concrete ramp, add unearthed path, about 1 month duration in advance, be specially adapted in the deep foundation pit construction of narrow field, solve because narrow field, inner support area are large, support between clear distance little, support bottom earth excavation difficulty, path of being unearthed few, can not utilize in a conventional manner and put the technical barrier that slope completes earth excavation;
3, mound platform is located on first road shrouding, and at the morning of evening peak traffic and in the rainy day can not transport outward, the position that can support shrouding in first road arrange mound district, and stack the earthwork that can not transport outward in time, the foundation ditch deadline shifts to an earlier date temporarily;
4, construction equipment simple, flexibly, pollute little, noise is low, do not disturb residents.
When the utility model design openings position and inner support absolute altitude, by pattern foundation pit supporting structure vertical member as stand column pile etc. avoids the engineering pile of agent structure, pillar and well, pattern foundation pit supporting structure horizontal struts system avoids the position of formal structure horizontal force component; Agent structure pillar position reserves hole in first road inner support, the earth excavation stage, as unearthed passage, the subsequent structural construction stage, can ensure that agent structure does not affect by supporting removal, normal construction.Meanwhile, the utility model is according to each construction stage, and different parts preloading requirement, has also carried out Force Calculation to whole support system, ensures that support system can meet each construction stage operating needs.
Accompanying drawing explanation
Fig. 1 is the integral structure schematic diagram carrying soil series system of the narrow zone deep foundation pit of construction construction that the utility model relates to;
Fig. 2 is the perspective view of the steel headframe 4 that the utility model relates to;
Fig. 3 is the front elevation of the steel headframe 4 that the utility model relates to;
Fig. 4 is the birds-eye view of the steel headframe 4 that the utility model relates to;
Fig. 5 is the set-up mode schematic diagram of the mound platform 6 that the utility model relates to.
Reference numeral: the stake of 1-foundation pit enclosure, 2-foundation ditch stand column pile, 3-concrete support, 31-first road concrete support, 32-first road shrouding, 4-steel headframe, 41-column, 42-crossbeam, 43-track girder, 5-electric block, 6-mound platform, 7-retaining wall, 8-water-blocking bank, 9-reinforce knoll, 10-hole, 11-muck haulage car, 12-suspension bucket, 13-inspection platform, 14-suspension bucket preformed hole.
Detailed description of the invention
Be described principle of the present utility model and feature below in conjunction with accompanying drawing, example, only for explaining the utility model, is not intended to limit scope of the present utility model.
As Fig. 1, a kind of soil series of carrying of narrow zone deep foundation pit of construction construction is united, and comprise foundation pit support system, vertically carry indigenous equipment and mound platform, described foundation pit support system comprises foundation pit enclosure stake 1, foundation ditch stand column pile 2 and concrete support 3, it is characterized in that:
Described concrete support 3 comprises some roads from top to bottom, and the first road concrete support 31 around hole 10 carries out large face shrouding, as arranging the first road shrouding 32 carrying indigenous equipment and mound platform; Described first road shrouding 32 is armoured concrete slabs, and its thickness range is 200 ~ 350mm, and the support beam at described armoured concrete slab and foundation ditch stand column pile 2 top is integrated moulding by casting, and the mutual colligation of reinforcing bar between the two connects.Described indigenous equipment of vertically carrying adopts steel headframe to carry native loop wheel machine, comprises and is erected at steel headframe on hole 10 4 and the electric block 5 of hanging on steel headframe 4; As Fig. 2 ~ 4, described steel headframe 4 comprises the column 41 of rectangle frame and the beneath support rectangle frame enclosed by crossbeam 42, described column 41 symmetry is fixed on around hole 10, the centre of described rectangle frame is provided with for hanging electric block 5 and as the track girder 43 of its moving track, the suspension hook of electric block connects suspension bucket 12; The column 41 of described steel headframe 4 is shaped steel column, and described crossbeam 42 comprises girder and secondary beam, and described girder comprises strength beam vertical with track girder 43 in the middle of Vierendeel girder and framework, described secondary beam between strength beam and Vierendeel girder, also perpendicular to track girder 43.Described steel headframe 4 is also provided with inspection platform 13.
As Fig. 5, described mound platform 6 is located on the first road shrouding around hole 10, is the region that retaining wall 7 and water-blocking bank 8 surround.Described mound platform 6 is away from muck haulage car transport channel and retaining wall 7 is established on the both sides in a bight at close hole 10, and remaining sides is along all establishing water-blocking bank 8, and the cross-sectional plane of described water-blocking bank 8 is protruding semicircular arc, and its maximum height is 5 ~ 20cm.In mound platform 6 outer, arrange along retaining wall 7 interval and reinforce knoll 9.Near the upper edge of the retaining wall 7 of side, hole, the position of respective carter beam 43 has the suspension bucket preformed hole 14 entering mound platform 6 for suspension bucket 12.
What utilize above-mentioned a kind of narrow zone deep foundation pit of construction construction carries the soil series system when carrying out proposing soil construction, and adopt crossed construction to carry indigenous method, concrete refer step is as follows:
Step one, determine the position at hole 10: the design paper of combining main body structure, foundation ditch stand column pile 2 is avoided the engineering pile of agent structure, pillar and well, determine number and the position at hole 10;
Step 2, the thickness of slab determining first road shrouding 32 and laying area: the specification of foundation transportation device and windrow require thickness of slab and the laying area of determining first road shrouding 32, first road shrouding 32 is located on the first road concrete support 31 around hole 10, as arranging the first road shrouding 32 carrying indigenous equipment and mound platform;
Step 3, earth excavation are to absolute altitude at the bottom of first road inner support: after foundation ditch periphery fender post and hole inner column pile driving construction, absolute altitude at the bottom of earth excavation to first road inner support is carried out in large face;
The integrated construction of step 4, first road inner support 31 and first road shrouding 32: comprise formwork erection, reinforcing bar binding and concreting, and carry out maintenance, the concrete grammar of construction is:
In step 1, first road inner support casting process, steel headframe 4 column embedded part is imbedded in first road inner support beam;
After step 2, Dai Shou road inner support beam concrete strength reach designing requirement, according to order, steel headframe column 41, crossbeam 42 and track girder 43 are installed; Column and embedded part adopt and are welded to connect, column 41, with bolts between crossbeam 42 and track girder 43.
Step 3, installation bridging and diagonal brace, ensure the safety of the stable of whole support body and unit member stress;
Step 4, installation and repairing platform 13, in order to ensure the normal operation of electric block, need arrange inspection platform on portal frame;
Step 5, installation electric block 5, and carry out trail run.
Step 5, installation vertically carry indigenous equipment: the concrete strength of Dai Shou road inner support 31 and first road shrouding 32 reaches after 75%, first road shrouding 32 is installed around hole steel headframe and carries native loop wheel machine, comprise the installation of steel headframe 4 and electric block 5; During making, according to inner support dimension of opening, determine that the spacing of steel frame column is 6m × 7m, according to height and the load requirement in Foundation Pit Support Design stage in early stage of earth moving vehicles, determine that the height of steel frame column is 6.9m, take into full account cubic metre of earth handling load and inspection platform position and load requirement simultaneously, carry out the design of raising legs.Adopt finite element software, in conjunction with construction actual loading operating mode, Force Calculation is carried out to lifting steel headframe, comprise the contents such as main stressed member, reaction at basement, pre-buried dowel, electric hoist to check, through Force Calculation, and consider installation requirements, column adopts HW300mm × 300mm × 10mm × 15mm, horizontal girder steel adopts HW400mm × 200mm × 8mm × 13mm, HW400mm × 150mm × 8mm × 13mm, and carries out Deepen Design to connecting joint;
The construction of step 6, mound platform 6: the construction first road shrouding 32 around hole carrying out retaining wall 7 and water-blocking bank 4, forms mound platform 6; Complete the construction of retaining wall 4 and water-blocking bank 4 at the openings position of first road inner support, form mound platform 6, the first floor shrouding position of each bont is all designed with mound district, when the earthwork cannot be transported outward in time, to stack the earthwork temporarily.Interim mound height is no more than 2m, to meet the restriction requirement of floor plan load.Mound district need arrange concrete retaining wall height 1500mm, thick 200mm, two-layer two-way reinforcement, need arrange water-blocking bank, trickle to prevent rainwater everywhere in other side in mound district.Water-blocking bank is curved, vertex height 150mm, is convenient to muck haulage garage and walks;
Step 7, utilize completed indigenous equipment of carrying to carry out carrying soil: to start electric block 5, make, bottom suspension bucket 12 vertical landing to hole, to rise after filling the earthwork, enter mound platform 6 and carry out discharging, repeat until be excavated to absolute altitude at the bottom of second inner support; If earth excavation is night work, then suspension bucket 12 is utilized the earthwork directly to be had bad luck on muck haulage car 11; If operation on daytime, does not allow earthwork transportation, then by the earthwork that suspension bucket 12 is had bad luck up, stack in the mound platform 6 within the scope of first floor retaining wall;
Step 8, while earth excavation, repeat step 7 and carry out proposing soil construction, until be excavated to absolute altitude at the bottom of foundation ditch.The concrete strength of Dai Shou road inner support reaches after 100%, adopts excavating machine excavation to support the downside earthwork, and utilizes and vertically carry indigenous equipment and complete a cubic metre of earth vertical transport operation, until be excavated to absolute altitude at the bottom of second inner support; If earth excavation is night work, then suspension bucket 12 is utilized the earthwork directly to be had bad luck on muck haulage car; If operation on daytime, does not allow earthwork transportation, then by the earthwork that suspension bucket 12 is had bad luck up, stack in the mound platform within the scope of first floor retaining wall.Construction second inner support: same to step 3; According to different foundation depth and inner support number of channels, complete follow-up work, until be excavated to absolute altitude at the bottom of foundation ditch.Construction and the vertical transport in clear groove stage of successive projects stake all can adopt this vertical transport equipment.
The present embodiment can excavate the earthwork that first road, southern side supports downside under first road supports not closed operating mode, earth excavation time advance about 1.5 months, for subsequent construction carries out providing condition smoothly, if traditionally carry indigenous method to construct, carry out support downside earth excavation after needing maintenance to structural strength to reach 90% after inner support construction, construction period is longer.
The foregoing is only preferred embodiment of the present utility model, not in order to limit the utility model, all within spirit of the present utility model and principle, any amendment done, equivalent replacement, improvement etc., all should be included within protection domain of the present utility model.

Claims (6)

1. the soil series of carrying of a narrow zone deep foundation pit of construction construction is united, comprise foundation pit support system, vertically carry indigenous equipment and mound platform, described foundation pit support system comprises foundation pit enclosure stake (1), foundation ditch stand column pile (2) and concrete support (3), it is characterized in that:
Described concrete support (3) comprises some roads from top to bottom, and hole (10) first road concrete support (31) around carries out large face shrouding, as arranging first road shrouding (32) carrying indigenous equipment and mound platform;
Described indigenous equipment of vertically carrying adopts steel headframe to carry native loop wheel machine, comprises and is erected at steel headframe (4) on hole (10) and hangs the electric block (5) on steel headframe (4);
Described steel headframe (4) comprises the column (41) of rectangle frame and the beneath support rectangle frame enclosed by crossbeam (42), described column (41) symmetry is fixed on hole (10) around, the centre of described rectangle frame is provided with for hanging electric block (5) and as the track girder (43) of its moving track, the suspension hook of electric block connects suspension bucket (12);
Described mound platform (6) is located on the first road shrouding around of hole (10), is the region that retaining wall (7) and water-blocking bank (8) surround.
2. the soil series of carrying of a kind of narrow zone deep foundation pit of construction construction according to claim 1 is united, it is characterized in that: the column (41) of described steel headframe (4) is shaped steel column, described crossbeam (42) comprises girder and secondary beam, described girder comprises strength beam vertical with track girder (43) in the middle of Vierendeel girder and framework, described secondary beam between strength beam and Vierendeel girder, also perpendicular to track girder (43).
3. the soil series of carrying of a kind of narrow zone deep foundation pit of construction construction according to claim 1 is united, it is characterized in that: described first road shrouding (32) is armoured concrete slab, the support beam at described armoured concrete slab and foundation ditch stand column pile (2) top is integrated moulding by casting, and the mutual colligation of reinforcing bar between the two connects.
4. the soil series of carrying of a kind of narrow zone deep foundation pit of construction construction according to claim 1 is united, it is characterized in that: described mound platform (6) is away from muck haulage car transport channel and retaining wall (7) is established on the both sides in a bight at close hole (10), remaining sides is along all establishing water-blocking bank (8), the cross-sectional plane of described water-blocking bank (8) is protruding semicircular arc, and its maximum height is 5 ~ 20cm.
5. the soil series of carrying of a kind of narrow zone deep foundation pit of construction construction according to claim 1 is united, and it is characterized in that: in mound platform (6) outer, arranges reinforce knoll (9) along retaining wall (7) interval; Near the upper edge of the retaining wall (7) of side, hole, the position of respective carter beam (43) has the suspension bucket preformed hole (14) entering mound platform (6) for suspension bucket (12).
6. the soil series of carrying of a kind of narrow zone deep foundation pit of construction construction according to Claims 1 to 5 any one is united, and it is characterized in that: described steel headframe (4) is also provided with inspection platform (13).
CN201520807898.3U 2015-10-19 2015-10-19 What narrow regional building deep basal pit was under construction puies forward soil series all Expired - Fee Related CN205061417U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520807898.3U CN205061417U (en) 2015-10-19 2015-10-19 What narrow regional building deep basal pit was under construction puies forward soil series all

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520807898.3U CN205061417U (en) 2015-10-19 2015-10-19 What narrow regional building deep basal pit was under construction puies forward soil series all

Publications (1)

Publication Number Publication Date
CN205061417U true CN205061417U (en) 2016-03-02

Family

ID=55387998

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520807898.3U Expired - Fee Related CN205061417U (en) 2015-10-19 2015-10-19 What narrow regional building deep basal pit was under construction puies forward soil series all

Country Status (1)

Country Link
CN (1) CN205061417U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105236275A (en) * 2015-10-19 2016-01-13 中建一局集团建设发展有限公司 Soil lifting system and soil lifting method for building deep foundation pit construction in narrow zone
CN110552519A (en) * 2019-08-30 2019-12-10 中国一冶集团有限公司 Deep foundation pit assembled type safe passage construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105236275A (en) * 2015-10-19 2016-01-13 中建一局集团建设发展有限公司 Soil lifting system and soil lifting method for building deep foundation pit construction in narrow zone
CN110552519A (en) * 2019-08-30 2019-12-10 中国一冶集团有限公司 Deep foundation pit assembled type safe passage construction method

Similar Documents

Publication Publication Date Title
CN105236275A (en) Soil lifting system and soil lifting method for building deep foundation pit construction in narrow zone
CN106907161B (en) A kind of tunnel slope caunches special construction method
CN106758841B (en) A kind of whole construction process of the double rope face low-pylon cable-stayed bridges of double tower
CN103485288B (en) A kind ofly pass through both wired double-deck jacking culvert construction technology
CN109235499A (en) A kind of open cut hypogee Standard formula construction method
CN107795749A (en) A kind of precast spliced pipe fitting jacking system and its construction method
CN105201516A (en) Subway station body structure and four-joint-arch PBA underground excavation construction method thereof
CN111851509A (en) Temporary channel construction method based on deep foundation pit inner support structure
CN110439590A (en) Method for tunnel construction
CN104831635A (en) Combined H-shaped steel cast-in-situ box beam support adjoining to and overpassing existing lines
CN206495233U (en) Door shape assembled armored concrete box culvert
CN205061417U (en) What narrow regional building deep basal pit was under construction puies forward soil series all
CN205036380U (en) Block of four encircles PBA and secretly digs subway station major structure
CN108589568B (en) Rapid construction method for shed tunnel T-shaped beam crossing business line in narrow space
JP2020002778A (en) Bridge pier construction method
CN205188981U (en) Assembled foundation ditch is gone along with sb. to guard him steel pipe concrete and is supported
KR101011805B1 (en) Method of constructing underground structure crossing pile bases in a pile-based ground and underground structure constructed using the same
CN109594581A (en) Cross a river segment pipe structure and its installation method
CN108978673A (en) A kind of foundation pit supporting construction and construction method of viaduct pile foundation underpinning
CN108708290A (en) The case crane span structure hollow structure and cast-in-situ construction method of minor radius railway curve unit
CN105298147A (en) Ultra-deep foundation pit spiral descending quick material transportation passage and construction method thereof
CN111608429B (en) Assembled ultra-deep foundation pit ramp system and construction method thereof
CN204151662U (en) A kind of one across the temporary trestle bridge crossing over river valley
CN212270945U (en) Existing railway line foundation pit supporting system
CN107090772A (en) A kind of construction method of the especially big cast-in-place boom support of cable-stayed bridge end bay

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160302