JP2002188159A - Execution method for underwater structure - Google Patents
Execution method for underwater structureInfo
- Publication number
- JP2002188159A JP2002188159A JP2000385127A JP2000385127A JP2002188159A JP 2002188159 A JP2002188159 A JP 2002188159A JP 2000385127 A JP2000385127 A JP 2000385127A JP 2000385127 A JP2000385127 A JP 2000385127A JP 2002188159 A JP2002188159 A JP 2002188159A
- Authority
- JP
- Japan
- Prior art keywords
- well
- sheet pile
- steel pipe
- pipe sheet
- head
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Foundations (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、矢板基礎により水
中に構築される橋脚などの水中構造物の施工方法に関す
るものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing an underwater structure such as a pier constructed underwater with a sheet pile foundation.
【0002】[0002]
【従来の技術】鋼管矢板基礎は、鋼管矢板を現場で打設
して円形,小判形,長方形などの井筒状の閉鎖断面を形
成し、この井筒の頭部に頂版を設けて剛結することによ
り、鋼管矢板単独の剛性のみならず井筒全体としての剛
性を持たせ、所定の水平抵抗・鉛直支持力が得られるよ
うにした基礎構造物である。また、この鋼管矢板基礎
は、仮締切り兼用工法を採用することができ、鋼管矢板
を躯体コンクリート施工時の仮締切り壁と基礎本体とに
兼用できる利点がある。2. Description of the Related Art A steel pipe sheet pile foundation is formed by casting a steel pipe sheet pile on site to form a circular, oval, rectangular, or other well-shaped closed cross section, and a top plate is provided at the head of the well to form a rigid connection. This is a substructure in which not only the rigidity of the steel pipe sheet pile alone but also the rigidity of the entire well is provided, and a predetermined horizontal resistance and vertical supporting force can be obtained. In addition, this steel pipe sheet pile foundation can adopt a temporary closing method, and there is an advantage that the steel pipe sheet pile can be used as a temporary closing wall and a foundation body at the time of building concrete.
【0003】図2は、橋脚における従来の鋼管矢板基礎
の構造と標準的な施工方法の1例を示したものであり、
概略、次のような手順で施工が行われる。 (1) 橋脚の設置箇所に作業台・導材を設置し、鋼管矢板
1を導枠2を利用して打設する。外周の鋼管矢板1によ
り円形等の閉鎖断面の井筒3が形成される。井筒3の内
部には、必要に応じて、隔壁鋼管矢板や中打ち単独杭が
打設される。FIG. 2 shows an example of the structure of a conventional steel pipe sheet pile foundation on a pier and a standard construction method.
The construction is generally performed in the following procedure. (1) Install a workbench and guides at the location where the piers are to be installed, and cast steel pipe sheet piles 1 using the guide frames 2. The outer tubular steel sheet pile 1 forms a well 3 having a closed cross section such as a circle. A bulkhead steel pipe sheet pile and a single-story pile are driven into the inside of the well 3 as necessary.
【0004】(2) 井筒3の頭部に支保工を設置し、外周
鋼管矢板1の継手の止水工・外周鋼管矢板1の中詰めコ
ンクリート工を行った後、井筒3内を掘削し、底面の敷
砂(砂利)上に底盤コンクリート4を打設する。(2) A shoring is installed at the head of the well pipe 3, a waterproofing work of the joint of the outer steel pipe sheet pile 1 and a concrete filling work of the outer steel pipe sheet pile 1 are performed, and then the inside of the well pipe 3 is excavated. Pile concrete 4 on the bottom sand (gravel).
【0005】(3) 井筒3内に支保工(腹起し,切梁,火
打ち梁)5を設置しながら井筒3内の水を段階的に汲み
上げ、井筒3内をドライアップする。[0005] (3) While the support (belly, cut beam, fire beam) 5 is installed in the well 3, the water in the well 3 is pumped up gradually, and the inside of the well 3 is dried up.
【0006】(4) 井筒3の内面の頂版部位置にコネクタ
6を取付け、頂版部の鉄筋を配置した後、頂版コンクリ
ート7を打設する。頂版コンクリート打設後、支保工5
を解体撤去すると共に、躯体外周に鋼製型枠と足場支保
工を組み、躯体コンクリート8を順次打設する。(4) A connector 6 is attached to the inner surface of the well tube 3 at the position of the top slab, and a reinforcing bar of the top slab is arranged. After placing concrete on top slab, support 5
Are dismantled and removed, and a steel formwork and a scaffolding support are assembled around the skeleton, and skeleton concrete 8 is sequentially poured.
【0007】(5) 頂版コンクリート7の上部を埋め戻
し、井筒3内に水を注入した後、水中切断機を外周の鋼
管矢板1内に挿入して鋼管矢板1を基礎本体部の上端で
切断し、鋼管矢板1の仮締切り部を引き抜く。(5) The upper part of the top slab concrete 7 is backfilled, water is injected into the well 3, and then an underwater cutting machine is inserted into the outer periphery of the steel pipe sheet pile 1 to put the steel pipe sheet pile 1 at the upper end of the foundation main body. Cut and pull out the temporary cutoff section of the steel pipe sheet pile 1.
【0008】(6) 仮設材を撤去することにより、鋼管矢
板基礎本体部の頭部に下部が一体的に剛結された上部躯
体(橋脚)が完成する。(6) By removing the temporary material, an upper frame (pier) in which the lower portion is rigidly connected integrally to the head of the steel pipe sheet pile foundation main body is completed.
【0009】[0009]
【発明が解決しようとする課題】しかし、前述のような
従来の鋼管矢板基礎の構造および施工方法の場合、次の
ような課題があった。However, the structure and construction method of the conventional steel pipe sheet pile foundation as described above has the following problems.
【0010】(1) 井筒基礎の上部を仮締切り部として利
用する構造のため、設計に際しては、施工時の土水圧等
により発生する鋼管矢板の残留応力度と、完成後の設計
外力により発生する応力度を合成して評価する必要があ
り、鋼管矢板等に完成後の基礎としての強度以上の強度
が必要となり、鋼管矢板等が大型化する。(1) Due to the structure in which the upper portion of the well base is used as a temporary cut-off portion, when designing, it is generated by the residual stress of the steel pipe sheet pile generated by soil water pressure and the like during construction and by the design external force after completion. It is necessary to synthesize and evaluate the stress levels, and the steel sheet piles and the like need to have a strength higher than the strength as a completed foundation, and the steel sheet piles and the like become large.
【0011】(2) 上部躯体の構築のため井筒内を掘削し
てドライアップするため、井筒内に支保工が必要とな
り、コストおよび工期が増加する。(2) Since the inside of the well is excavated and dried up for the construction of the upper frame, a support work is required in the well, which increases the cost and the construction period.
【0012】(3) 上部躯体を施工する際に型枠の足場を
井筒内に組む必要があり、この作業スペースを確保する
ため、井筒の径が必要以上に大きくなる。(3) When constructing the upper frame, it is necessary to assemble the scaffold of the formwork in the well, and in order to secure this work space, the diameter of the well becomes larger than necessary.
【0013】本発明は、前述のような従来の課題を解決
すべくなされたもので、その目的は、矢板基礎の上部を
仮締切り壁として使用することによる矢板の残留応力を
解消することができ、また井筒内の支保工や上部躯体の
型枠の足場を無くすことができ、橋脚等の矢板井筒基礎
の施工においてコストの低減および工期の短縮を図るこ
とのできる水中構造物の施工方法を提供することにあ
る。The present invention has been made to solve the above-mentioned conventional problems, and an object of the present invention is to eliminate the residual stress of a sheet pile by using the upper part of the sheet pile foundation as a temporary cutoff wall. In addition, it provides a method for constructing underwater structures that can reduce the cost and shorten the construction period in the construction of sheet pile foundations, such as bridge piers, by eliminating the support work inside the izutsu and the scaffolding of the upper frame form. Is to do.
【0014】[0014]
【課題を解決するための手段】本発明の請求項1は、矢
板基礎と上部躯体からなる水中構造物の施工方法であ
り、水中の基礎地盤内に矢板を打設して井筒を形成し、
この井筒の頭部の上に予め製作された上部躯体(橋脚
等)を沈設し、上部躯体の底部により井筒の上部開口を
止水可能に覆い、井筒頭部内の水位を低下させて上部躯
体を水圧で井筒頭部に固定した後、井筒頭部内で上部躯
体の底部と井筒頭部とを一体化することを特徴とする水
中構造物の施工方法である。上部躯体の底部と井筒頭部
の一体化は、コンクリートの打設やその他の方法で行
う。A first aspect of the present invention is a method for constructing an underwater structure comprising a sheet pile foundation and an upper body, wherein a sheet pile is cast in an underwater foundation ground to form a well.
A prefabricated upper skeleton (bridge pier, etc.) is laid down on the head of this well, and the upper opening of the well is covered by the bottom of the upper body so that the water can be stopped. Is fixed to the well head by hydraulic pressure, and then the bottom of the upper skeleton is integrated with the well head inside the well head. Integration of the bottom of the upper body with the head of the well is done by casting concrete or other methods.
【0015】本発明の請求項2は、請求項1の施工方法
において、上部躯体の底部は井筒頭部を覆う形状とさ
れ、これら上部躯体の底部と井筒頭部との間に止水材を
介在させることを特徴とする水中構造物の施工方法であ
る。即ち、上部躯体は、プレファブの鋼殻やプレキヤス
トのコンクリート等を使用し、下部には、井筒の頭部を
覆う蓋状のフーチングを設け、フーチングと井筒頭部の
間には止水材を介在させる。According to a second aspect of the present invention, in the construction method of the first aspect, the bottom of the upper skeleton is formed to cover the head of the well, and a waterproof material is provided between the bottom of the upper skeleton and the head of the well. It is a construction method of an underwater structure characterized by being interposed. That is, the upper frame is made of prefabricated steel shell or precast concrete, etc., the lower part is provided with a lid-shaped footing that covers the head of the well, and a waterproof material is interposed between the footing and the head of the well. Let it.
【0016】本発明の請求項3は、請求項1または2の
施工方法において、井筒が閉合されると、所定の位置を
切断し、井筒の上部を引抜いて除去することを特徴とす
る水中構造物の施工方法である。即ち、鋼管矢板等の矢
板は、通常どおり、上部が水面から突出するように打設
し、所定位置から上を切断除去することで、上部躯体を
沈設できるようにする。According to a third aspect of the present invention, in the construction method according to the first or second aspect, when the well is closed, a predetermined position is cut and the upper part of the well is removed by removal. The construction method of the object. That is, a sheet pile, such as a steel pipe sheet pile, is cast as usual, with the upper part protruding from the water surface, and the upper part is cut and removed from a predetermined position so that the upper skeleton can be laid down.
【0017】本発明の請求項4は、請求項1または2に
記載の施工方法において、井筒頭部が所定の位置に位置
するように矢板を打設することを特徴とする水中構造物
の施工方法である。即ち、矢板の最上端が前記切断位置
(上部躯体の据え付け位置)に位置するように矢板を打
設し、切断作業を省略するようにしてもよい。According to a fourth aspect of the present invention, in the construction method according to the first or second aspect, a sheet pile is driven so that a well head is located at a predetermined position. Is the way. That is, the sheet pile may be driven so that the uppermost end of the sheet pile is located at the cutting position (installation position of the upper frame), and the cutting operation may be omitted.
【0018】なお、上記の上部躯体は、構造体全体(発
電所の取水塔など)に限らず、構造体の一部(橋梁の下
部工など)も含むものとする。以上のような構成におい
て、井筒が形成されると、井筒頭部に上部躯体のフーチ
ング等の底部を被せ、ドライアップさせた底部内に気中
コンクリートを打設し、井筒基礎の頭部と上部躯体の下
部を一体的に剛結することから、従来のように矢板の上
部を仮締切り壁として使用する必要がなく、矢板には従
来のような残留応力が発生することがないため、井筒は
基礎としての強度だけを考慮すればよく、矢板等を小型
化できるなど、部材の最適化を図ることができる。The above upper frame is not limited to the entire structure (such as a water intake tower of a power plant), but also includes a part of the structure (such as a substructure of a bridge). In the above configuration, when the well is formed, the bottom of the upper body is footed with a footing or the like, and aerial concrete is poured into the dried bottom, and the head of the well and the upper part of the well are formed. Since the lower part of the skeleton is integrally rigidly connected, the upper part of the sheet pile does not need to be used as a temporary cutoff wall as in the past, and the sheet pile does not generate residual stress unlike the conventional case. Only the strength as a foundation needs to be considered, and the members can be optimized, for example, the size of the sheet pile can be reduced.
【0019】また、予め製作された上部躯体を井筒基礎
の頭部に容易に剛結することができるため、従来の支保
工が不要となる。さらに、上部躯体を構築するための作
業スペースを井筒内に確保する必要がなくなり、井筒基
礎は構造上必要な大きさのものとすることができる。Further, since the pre-fabricated upper frame can be easily and rigidly connected to the head of the well base, the conventional support work is not required. Further, it is not necessary to secure a work space for constructing the upper skeleton in the well, and the well base can be made to have a structurally necessary size.
【0020】[0020]
【発明の実施の形態】以下、本発明を図示する実施形態
に基づいて説明する。この実施形態は、水中に構築され
る橋脚の鋼管矢板基礎に本発明を適用した例である。図
1は、本発明の施工方法の1例を工程順に示したもので
ある。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below based on an embodiment shown in the drawings. This embodiment is an example in which the present invention is applied to a steel pipe sheet pile foundation of a pier constructed underwater. FIG. 1 shows an example of the construction method of the present invention in the order of steps.
【0021】図1に示すように、本発明で用いる上部躯
体としての橋脚11は、フーチング11aと躯体脚部1
1bと橋座部11cから構成され、これらをプレファブ
の鋼殻12で形成し、沈設した鋼殻12内にコンクリー
ト13を打設することで、鋼板とコンクリートの合成構
造の橋脚11が構築される。As shown in FIG. 1, a pier 11 as an upper skeleton used in the present invention includes a footing 11a and a skeleton leg 1a.
1b and a bridge seat portion 11c. These are formed of a prefabricated steel shell 12, and concrete 13 is cast into the sunk steel shell 12, whereby the pier 11 having a composite structure of a steel plate and concrete is constructed. .
【0022】フーチング11aは、鋼管矢板基礎(井
筒)10の平面形状より若干大きい形状の平板部14
と、この平板部14の外縁から一体的に垂下するスカー
ト部15からなり、鋼管矢板の井筒10の頭部を完全に
覆うことのできる形状とされている。さらに、平板部1
4の下面には、鋼管矢板の井筒10の頭部天端に当接す
るゴム製等の板状等の止水材16を周方向に連続して設
けておき、フーチング内に水が侵入しないようにする。The footing 11a has a flat plate portion 14 slightly larger than the plane shape of the steel sheet pile foundation (well cylinder) 10.
And a skirt portion 15 integrally hanging down from an outer edge of the flat plate portion 14, and has a shape capable of completely covering the head of the well 10 of the steel pipe sheet pile. Further, the flat plate portion 1
On the lower surface of the steel pipe sheet pile, a water-stopping material 16 made of rubber or the like abutting on the top end of the well 10 of the steel pipe sheet pile is provided continuously in the circumferential direction so that water does not enter the footing. To
【0023】なお、止水材16は、図示例に限らず、ス
カート部15の内面などに設け、この止水材がガイド
材、緩衝材、あるいは位置決め材として働くようにして
もよい。また、スカート部15は、長くして基礎地盤A
内に貫入できるようにし、止水性が向上するようにして
もよい。また、橋脚11は、プレファブの鋼殻12に限
らず、プレキャストコンクリートやこれらの合成構造等
でもよい。The water-stopping material 16 is not limited to the illustrated example, but may be provided on the inner surface of the skirt portion 15 or the like, and the water-stopping material may function as a guide material, a cushioning material, or a positioning material. In addition, the skirt portion 15 is made longer to make the foundation ground A
It may be made to be able to penetrate into the inside, and the water stopping performance may be improved. Further, the pier 11 is not limited to the prefabricated steel shell 12, but may be precast concrete or a composite structure thereof.
【0024】以上のような構成において、次のような手
順で施工を行う。 (1) 従来工法と同様に、作業台・導材を設置し(図示省
略)、鋼管矢板1を打設する。外周の鋼管矢板1により
円形等の閉鎖断面の井筒10が形成される。井筒10の
内部には、必要に応じて、隔壁鋼管矢板や中打ち単独杭
が打設される(図示省略)。次いで、外周鋼管矢板1の
継手の止水工・外周鋼管矢板1の中詰めコンクリート工
を行う。この止水工・中詰めコンクリート工は、次のス
テップの切断位置よりも下に施工する。In the above configuration, construction is performed in the following procedure. (1) In the same manner as the conventional method, a work table and a guide are installed (not shown), and a steel pipe sheet pile 1 is driven. A well 10 having a closed cross section such as a circle is formed by the steel pipe sheet pile 1 on the outer periphery. A bulkhead steel pipe sheet pile and a single-story pile are driven into the inside of the well 10 as necessary (not shown). Next, a waterproofing operation of the joint of the outer steel pipe sheet pile 1 and a concrete filling work of the outer steel pipe sheet pile 1 are performed. This waterproofing / filling concrete work is performed below the cutting position in the next step.
【0025】(2) 外周鋼管矢板1内に水中切断機を挿入
して外周鋼管矢板1の所定の位置を切断し、切断した外
周鋼管矢板1の上部を引き抜く。ここで、この切断は、
各外周鋼管矢板1の天端レベルが一致するように精度良
くを行う必要がある。これにより、鋼管矢板の井筒10
が形成される。なお、本発明では、外周鋼管矢板1の上
部を仮締切り壁として利用しないため、外周鋼管矢板1
の上端が前記切断位置となるように打設し、切断作業を
省略することもできる。(2) An underwater cutting machine is inserted into the outer steel pipe sheet pile 1 to cut a predetermined position of the outer steel pipe sheet pile 1, and the upper portion of the cut outer steel pipe sheet pile 1 is pulled out. Here, this disconnection
It is necessary to perform the operation with high accuracy so that the top level of each peripheral steel pipe sheet pile 1 matches. As a result, the well 10
Is formed. In the present invention, since the upper part of the outer steel pipe sheet pile 1 is not used as a temporary cutoff wall, the outer steel pipe sheet pile 1 is not used.
The cutting work can be omitted by driving the upper end to the cutting position.
【0026】(3) 起重機船等で曳航した橋脚11の鋼殻
12を鋼管矢板の井筒10の上に沈設する。フーチング
11aが鋼管矢板の井筒10の頭部を覆い、止水材16
により鋼管矢板の井筒10の頭部が密閉される。この状
態から鋼殻12内の水を排出してドライアップする。フ
ーチング11aは水圧により鋼管矢板の井筒10の頭部
と一体化し、完全な止水がなされる。さらに、次のステ
ップのコンクリート打設に際し、作業員の作業性を良く
するため、鋼管矢板の井筒10内の基礎地盤A内の内部
水を排出して水位を低下させる。(3) The steel shell 12 of the pier 11 towed by a hoist ship or the like is laid on the well 10 of the steel pipe sheet pile. The footing 11a covers the head of the well 10 made of steel sheet piles,
This seals the head of the well 10 of the steel pipe sheet pile. From this state, the water in the steel shell 12 is discharged and dried up. The footing 11a is integrated with the head of the well 10 of the steel pipe sheet pile by water pressure, and complete water blocking is performed. Furthermore, in the next step of placing concrete, in order to improve the workability of the worker, the internal water in the foundation ground A in the well 10 of the steel pipe sheet pile is discharged to lower the water level.
【0027】(4) フーチング11a内における外周鋼管
矢板1の上部内面にフーチング一体化用のスタッド筋1
7等を取付けた後、フーチング11a(鋼管矢板の井筒
10の頭部)内にコンクリート13を気中で打設する。
このコンクリート13は、躯体脚部11bの所定の位置
まで打設する。この躯体脚部11bの鋼殻内面には、一
体化用のリブ(図示省略)が予め取付けられている。以
上により、鋼管矢板の井筒10の頭部に一体的に剛結さ
れた鋼とコンクリートによる合成構造の橋脚11が完成
する。(4) A stud bar 1 for integrating the footing is formed on the inner surface of the upper portion of the outer steel sheet pile 1 in the footing 11a.
After the 7 and the like are attached, concrete 13 is poured into the footing 11a (the head of the well 10 of the steel pipe sheet pile) in the air.
The concrete 13 is cast to a predetermined position of the skeleton leg 11b. A rib (not shown) for integration is attached in advance to the inner surface of the steel shell of the body leg 11b. As described above, the pier 11 having a composite structure of steel and concrete rigidly connected to the head of the well 10 of the steel pipe sheet pile is completed.
【0028】なお、以上は、橋脚に適用した場合につい
て説明したが、これに限らず、発電所の海中放水塔など
の水中構造物にも本発明を適用することができる。Although the description has been given of the case where the present invention is applied to a pier, the present invention is not limited to this, and the present invention can be applied to an underwater structure such as an underwater discharge tower of a power plant.
【0029】[0029]
【発明の効果】本発明は、以上のような構成からなるの
で、次のような効果を奏する。 (1) 井筒が形成されると、井筒頭部に上部躯体のフーチ
ング等の底部を被せ、ドライアップさせた底部内に気中
コンクリートを打設し、井筒基礎の頭部と上部躯体の下
部を一体的に剛結することから、従来のように矢板の上
部を仮締切り壁として使用する必要がないため、矢板に
は従来のような残留応力が発生することがなく、井筒矢
板は完成後の基礎としての強度だけを考慮すればよく、
矢板等を小型化できるなど、部材の最適化を図ることが
でき、コストの低減を図ることができる。Since the present invention has the above-described structure, the following effects can be obtained. (1) When the well is formed, cover the bottom of the upper body with the footing or the like of the upper body, place the submerged concrete in the dried-up bottom, and connect the head of the well and the lower part of the upper body. Since it is integrally rigidly connected, there is no need to use the upper part of the sheet pile as a temporary cut-off wall as in the past, so there is no residual stress in the sheet pile as in the past, and the Izutsu sheet pile is completed after completion. You only have to consider the strength as a foundation,
The members can be optimized, for example, the size of the sheet pile can be reduced, and the cost can be reduced.
【0030】(2) 予め製作された上部躯体を井筒基礎の
頭部に容易に剛結することができるため、従来の支保工
が不要となり、コスト低減および工期の短縮を図ること
ができる。(2) Since the prefabricated upper frame can be easily and rigidly connected to the head of the well tube base, the conventional support work is not required, and the cost and the construction period can be reduced.
【0031】(3) さらに、従来の上部躯体を構築するた
めの作業スペースを井筒内に確保する必要がなくなり、
井筒基礎は構造上必要な大きさものとすることができ、
コスト低減および工期の短縮を図ることができる。(3) Further, it is not necessary to secure a work space for constructing the conventional upper frame in the well.
Izutsu foundations can be of the required size for the structure,
Cost reduction and shortening of the construction period can be achieved.
【図1】本発明の水中構造物の施工方法の1例を工程順
に示す断面図である。FIG. 1 is a sectional view showing an example of a method for constructing an underwater structure according to the present invention in the order of steps.
【図2】従来の橋脚の鋼管矢板基礎の施工方法を工程順
に示す断面図である。FIG. 2 is a cross-sectional view showing a conventional method of constructing a steel pipe sheet pile foundation for a pier in the order of steps.
1…鋼管矢板 2…導枠 3…井筒 4…底盤コンクリート 5…支保工 6…コネクタ 7…頂版コンクリート 8…躯体コンクリート 10…鋼管矢板の井筒 11…橋脚 11a…フーチング 11b…躯体脚部 11c…橋座部 12…鋼殻 13…コンクリート 14…平板部 15…スカート部 16…止水材 17…スタッド筋 DESCRIPTION OF SYMBOLS 1 ... Steel sheet pile 2 ... Conductor frame 3 ... Well cylinder 4 ... Bottom concrete 5 ... Shoring 6 ... Connector 7 ... Top slab concrete 8 ... Body concrete 10 ... Steel pipe sheet pile well 11 ... Bridge pier 11a ... Footing 11b ... Body leg 11c ... Bridge seat 12 ... Shell 13 ... Concrete 14 ... Plate 15 ... Skirt 16 ... Water stop material 17 ... Stud streak
Claims (4)
の施工方法であり、水中の基礎地盤内に矢板を打設して
井筒を形成し、この井筒の頭部の上に予め製作された上
部躯体を沈設し、上部躯体の底部により井筒の上部開口
を止水可能に覆い、井筒頭部内の水位を低下させて上部
躯体を水圧で井筒頭部に固定した後、井筒頭部内で上部
躯体の底部と井筒頭部とを一体化することを特徴とする
水中構造物の施工方法。1. A method for constructing an underwater structure comprising a sheet pile foundation and an upper body, wherein a sheet pile is cast into a submerged foundation ground to form a well, which is manufactured in advance on the head of the well. The upper body is submerged, the upper opening of the well is covered with the bottom of the upper body so that water can be stopped, the water level in the head of the well is lowered, and the upper body is fixed to the head of the well by water pressure. A method for constructing an underwater structure, comprising integrating a bottom portion of an upper frame with a head of a well.
部躯体の底部は井筒頭部を覆う形状とされ、これら上部
躯体の底部と井筒頭部との間に止水材を介在させること
を特徴とする水中構造物の施工方法。2. The construction method according to claim 1, wherein the bottom of the upper skeleton is shaped to cover the head of the well, and a water blocking material is interposed between the bottom of the upper skeleton and the head of the well. Characteristic construction method of underwater structures.
いて、井筒が閉合されると、所定の位置を切断し、井筒
の上部を引抜いて除去することを特徴とする水中構造物
の施工方法。3. The construction method according to claim 1, wherein when the well is closed, a predetermined position is cut, and the upper part of the well is removed by removal. .
いて、井筒頭部が所定の位置に位置するように矢板を打
設することを特徴とする水中構造物の施工方法。4. The construction method according to claim 1, wherein the sheet pile is driven so that the well head is located at a predetermined position.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000385127A JP4626052B2 (en) | 2000-12-19 | 2000-12-19 | Construction method for underwater structures |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000385127A JP4626052B2 (en) | 2000-12-19 | 2000-12-19 | Construction method for underwater structures |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2002188159A true JP2002188159A (en) | 2002-07-05 |
JP4626052B2 JP4626052B2 (en) | 2011-02-02 |
Family
ID=18852451
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2000385127A Expired - Fee Related JP4626052B2 (en) | 2000-12-19 | 2000-12-19 | Construction method for underwater structures |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4626052B2 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101129250B1 (en) | 2011-08-31 | 2012-03-26 | 김순민 | The intake tower construction method that use a mold of intake tower that can do function of cofferdam and an outer wall of intake tower at the same time |
JP2019148108A (en) * | 2018-02-27 | 2019-09-05 | 三井住友建設株式会社 | Bridge pier construction method |
JP2020002778A (en) * | 2019-10-10 | 2020-01-09 | 鹿島建設株式会社 | Bridge pier construction method |
CN118422704A (en) * | 2024-07-04 | 2024-08-02 | 中铁三局集团有限公司 | Scour prevention bridge pier pile foundation structure and construction device thereof |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6092518A (en) * | 1983-10-26 | 1985-05-24 | Taisei Corp | Connection of pile heads under water |
JPS61158528A (en) * | 1984-12-28 | 1986-07-18 | Sumitomo Metal Ind Ltd | Foundation structure in soft ground and building thereof |
JPS62202125A (en) * | 1986-02-26 | 1987-09-05 | Sumitomo Metal Ind Ltd | Underwater foundation work using steel plate shell |
JPS63534A (en) * | 1986-06-18 | 1988-01-05 | Kajima Corp | Artificial islet construction work |
JP2000170182A (en) * | 1998-12-09 | 2000-06-20 | Ohbayashi Corp | Construction method of underwater foundation |
JP2000290936A (en) * | 1999-04-12 | 2000-10-17 | Shimizu Corp | Method and caisson for constructing bridge pier footing |
-
2000
- 2000-12-19 JP JP2000385127A patent/JP4626052B2/en not_active Expired - Fee Related
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6092518A (en) * | 1983-10-26 | 1985-05-24 | Taisei Corp | Connection of pile heads under water |
JPS61158528A (en) * | 1984-12-28 | 1986-07-18 | Sumitomo Metal Ind Ltd | Foundation structure in soft ground and building thereof |
JPS62202125A (en) * | 1986-02-26 | 1987-09-05 | Sumitomo Metal Ind Ltd | Underwater foundation work using steel plate shell |
JPS63534A (en) * | 1986-06-18 | 1988-01-05 | Kajima Corp | Artificial islet construction work |
JP2000170182A (en) * | 1998-12-09 | 2000-06-20 | Ohbayashi Corp | Construction method of underwater foundation |
JP2000290936A (en) * | 1999-04-12 | 2000-10-17 | Shimizu Corp | Method and caisson for constructing bridge pier footing |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101129250B1 (en) | 2011-08-31 | 2012-03-26 | 김순민 | The intake tower construction method that use a mold of intake tower that can do function of cofferdam and an outer wall of intake tower at the same time |
JP2019148108A (en) * | 2018-02-27 | 2019-09-05 | 三井住友建設株式会社 | Bridge pier construction method |
JP2020002778A (en) * | 2019-10-10 | 2020-01-09 | 鹿島建設株式会社 | Bridge pier construction method |
JP7319887B2 (en) | 2019-10-10 | 2023-08-02 | 鹿島建設株式会社 | Bridge pier construction method |
CN118422704A (en) * | 2024-07-04 | 2024-08-02 | 中铁三局集团有限公司 | Scour prevention bridge pier pile foundation structure and construction device thereof |
CN118422704B (en) * | 2024-07-04 | 2024-10-18 | 中铁三局集团有限公司 | Scour prevention bridge pier pile foundation structure and construction device thereof |
Also Published As
Publication number | Publication date |
---|---|
JP4626052B2 (en) | 2011-02-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2007205077A (en) | Temporary coffering method | |
CN113550317B (en) | Permanent-temporary combined supporting structure and construction method for open excavation reverse construction foundation pit of large shield starting well | |
JP2007327244A (en) | Method and structure for temporarily coffering underwater structure | |
JP6454674B2 (en) | Construction method of water stop working space | |
JP3054635B2 (en) | Construction method of attached structure | |
KR20160000702A (en) | Fastening member used in concrete filled steel tube and its using concrete filled steel tube mounting structure and method and its includes build underground structure and method | |
JP4206165B2 (en) | Temporary deadline construction method | |
JP3888174B2 (en) | Temporary deadline construction method | |
JP2002188159A (en) | Execution method for underwater structure | |
JPH10168915A (en) | Method of ground excavation construction in coffering sheet pile | |
JP2001348888A (en) | Method and device for constructing underwater foundation structure | |
JP4475116B2 (en) | Vertical shaft structure and its construction method | |
KR101129250B1 (en) | The intake tower construction method that use a mold of intake tower that can do function of cofferdam and an outer wall of intake tower at the same time | |
JPH11117316A (en) | Temporary cofferdam structure | |
JP2004108078A (en) | Construction method for underwater shaft, underwater shaft, connection method for shaft and adit, and pit structure | |
KR100999410B1 (en) | Assembled wale beam and construction method of underground structure using the same | |
JPS6335923A (en) | Basement and its construction | |
KR100609732B1 (en) | Watertight Caisson for Underwater Pier Construction Work and Dry Construction Method of Underwater Pier Foundation Work Using Thereof | |
JP2949341B1 (en) | Underwater girder construction method | |
KR100525355B1 (en) | Caisson for constructing pier | |
CN218813822U (en) | Hydrophobic drainage device of bottom plate construction and hydrophobic well structure | |
JPH084033A (en) | Structure method of building underground outer periphery pressure bulkhead | |
JPH116164A (en) | Construction method for underground structure | |
JPH101957A (en) | Underground construction method for building | |
JP2006118152A (en) | Method for constructing circular closed conduit by open excavation system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20070413 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20090908 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20100427 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20100623 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20101012 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20101025 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131119 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 4626052 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |