JP6454674B2 - Construction method of water stop working space - Google Patents

Construction method of water stop working space Download PDF

Info

Publication number
JP6454674B2
JP6454674B2 JP2016252455A JP2016252455A JP6454674B2 JP 6454674 B2 JP6454674 B2 JP 6454674B2 JP 2016252455 A JP2016252455 A JP 2016252455A JP 2016252455 A JP2016252455 A JP 2016252455A JP 6454674 B2 JP6454674 B2 JP 6454674B2
Authority
JP
Japan
Prior art keywords
water
support
water stop
area
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2016252455A
Other languages
Japanese (ja)
Other versions
JP2018017111A (en
Inventor
秀一 上谷
秀一 上谷
泰憲 大木
泰憲 大木
務 榊原
務 榊原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toa Corp
Original Assignee
Toa Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toa Corp filed Critical Toa Corp
Priority to JP2016252455A priority Critical patent/JP6454674B2/en
Publication of JP2018017111A publication Critical patent/JP2018017111A/en
Application granted granted Critical
Publication of JP6454674B2 publication Critical patent/JP6454674B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

本発明は、止水作業空間の構築方法に関し、さらに詳しくは、橋脚等を水域に施工する際に、止水作業空間を効率よく構築することができ、かつ、水域を仕切る矢板の変形を抑制できる止水作業空間の構築方法に関するものである。   The present invention relates to a method for constructing a water stop working space, and more specifically, when a bridge pier or the like is constructed in a water area, the water stop work space can be efficiently constructed and deformation of a sheet pile that partitions the water area is suppressed. The present invention relates to a method for constructing a water stop working space.

海や河川等の水域に橋脚等の構造物を構築する場合には、まず、構造物を構築する領域に気中で作業を行なえる止水作業空間を構築し、その後に、止水作業空間内において構造物の施工を行う。従来、水域に止水作業空間を構築する場合には、まず、水底に矢板を打設して止水対象領域とその外側の領域とを水密に締切る。その後、止水対象領域内の水を所定の深さで複数段階で排出して止水対象領域内の水位を段階的に下げる。この水位を下げた段階ごとに順次下方の気中状態の現場で支保工の組み立てと設置を行い、支保工により矢板を支持する(例えば、特許文献1参照)。その後、止水対象領域内の水底を所望の深さまで掘削して、掘削した水底に水中コンクリートを打設して底盤を形成する。その後、止水対象領域内に残存している水を外部に排水することにより水域に止水作業空間を構築する。   When constructing structures such as bridge piers in water areas such as the sea and rivers, first build a water stop working space where you can work in the air in the area where the structure is to be built, and then stop the water stop working space The structure will be constructed inside. Conventionally, when constructing a water stop working space in a water area, first, a sheet pile is placed on the bottom of the water, and the water stop target area and the area outside thereof are tightly closed. Thereafter, the water in the water stop target area is discharged in a plurality of stages at a predetermined depth, and the water level in the water stop target area is lowered stepwise. At each stage where the water level is lowered, the support is assembled and installed at the site in the lower air state, and the sheet pile is supported by the support (for example, see Patent Document 1). Thereafter, the bottom of the water stop target area is excavated to a desired depth, and the bottom board is formed by placing underwater concrete on the excavated water bottom. Then, the water stop working space is constructed in the water area by draining the water remaining in the water stop target area to the outside.

しかしながら、上述した従来の構築方法では、排水作業、支保工の現場組立および設置作業を段階毎に行う必要があるため、作業が非常に煩雑になる。これに伴い、作業効率が低下し、工期の短縮化を妨げる一因になる。また、止水対象領域内の水位を段階的に下げながら気中状態になった現場で順次支保工の設置を行っていくので、水圧による矢板の累積変形量が大きくなるという問題もある。   However, in the conventional construction method described above, it is necessary to perform drainage work, on-site assembly and installation work of support works at each stage, and thus the work becomes very complicated. Along with this, work efficiency is lowered, which is one factor that hinders shortening of the construction period. In addition, since the support works are sequentially installed at the site that is in the air state while gradually lowering the water level in the water stop target region, there is also a problem that the accumulated deformation amount of the sheet pile due to water pressure increases.

特開2011−247050号公報JP 2011-247050 A

本発明の目的は、橋脚等を水域に施工する際に、止水作業空間を効率よく構築することができ、かつ、水域を仕切る矢板の変形を抑制できる止水作業空間の構築方法を提供することにある。   An object of the present invention is to provide a construction method of a water stop working space that can efficiently construct a water stop work space when constructing a pier or the like in a water region and can suppress deformation of a sheet pile that partitions the water region. There is.

上記目的を達成するため本発明の止水作業空間の構築方法は、隣接して水底に打設した複数の矢板によって止水対象水域と非対象水域とに仕切る仕切り工程と、前記止水対象水域に支保工を設置して前記矢板を前記支保工により支持する支保工設置工程と、前記支保工を設置した前記止水対象水域の水を外部に排出することにより前記止水対象水域を気中状態の止水作業空間にする排水工程とを有する止水作業空間の構築方法において、前記仕切り工程と前記支保工設置工程との間で、前記止水対象水域および前記非対象水域の水位が前記矢板の上端部に位置する状態で、前記止水対象水域の水底を所定深さまで掘削する掘削工程と、この掘削した後の水底に複数の中間杭を打設してから、この水底の上に水中コンクリートを打設して底盤を形成する底板形成工程とを有し、前記支保工設置工程では、前記支保工として予め組み立てられている大組支保工を使用して、この大組支保工を気中から前記止水対象水域に沈設して、前記中間杭が前記大組支保工の内周縁に沿う位置に配置された状態で、前記大組支保工を前記矢板および前記中間杭のそれぞれに取付けられているブラケットに載置して設置することを特徴とする。
上記目的を達成するため本発明の別の止水作業空間の構築方法は、隣接して水底に打設した複数の矢板によって止水対象水域と非対象水域とに仕切る仕切り工程と、前記止水対象水域に支保工を設置して前記矢板を前記支保工により支持する支保工設置工程と、前記支保工を設置した前記止水対象水域の水を外部に排出することにより前記止水対象水域を気中状態の止水作業空間にする排水工程とを有する止水作業空間の構築方法において、前記仕切り工程と前記支保工設置工程との間で、前記止水対象水域および前記非対象水域の水位が前記矢板の上端部に位置する状態で、前記止水対象水域の水底を所定深さまで掘削する掘削工程と、この掘削した後の水底の上に水中コンクリートを打設して底盤を形成する底盤形成工程とを有し、前記支保工設置工程では、前記支保工として予め組み立てられている複数の大組支保工を使用して、これらの大組支保工を下段から上段にかけて、気中から前記止水対象水域に順次沈設して、複数段の前記大組支保工を設置することを特徴とする。
In order to achieve the above object, the construction method of the water stop working space of the present invention includes a partitioning step of partitioning into a water stop target water area and a non-target water area by a plurality of sheet piles placed adjacent to the bottom of the water, and the water stop target water area A support work installation process in which a support work is installed and the sheet pile is supported by the support work, and the water in the water stop target water area in which the support work is installed is discharged to the outside. In the construction method of the water stop working space having a drainage process to make the water stop working space in a state, the water level of the water stop target water area and the non-target water area is between the partitioning process and the support construction setting process. The excavation process of excavating the bottom of the water-stop target water area to a predetermined depth in a state where it is located at the upper end of the sheet pile, and after placing a plurality of intermediate piles on the bottom of the excavated water, Placing underwater concrete A bottom plate forming step, and in the support installation step, a large set support constructed in advance as the support is used, and the large set support is transferred from the atmosphere to the water stop target water area. In the state where the intermediate pile is placed at a position along the inner peripheral edge of the large support structure, the large support structure is placed on the bracket attached to each of the sheet pile and the intermediate pile. It is characterized by being installed .
In order to achieve the above object, another method for constructing a water stop working space according to the present invention includes a partitioning step of partitioning into a water stop target water area and a non-target water area by a plurality of sheet piles placed adjacent to the bottom of the water, and the water stop A support work installation process in which a support work is installed in the target water area and the sheet pile is supported by the support work, and the water in the water stop target water area in which the support work is installed is discharged to the outside. In the construction method of a water stop working space having a draining step for making the water stop working space in an air state, between the partitioning step and the support installation setting step, the water level of the water stop target water area and the non-target water area Excavation step of excavating the bottom of the water-stop target water area to a predetermined depth in a state where the bottom plate is positioned at the upper end of the sheet pile, and a bottom plate that forms a bottom plate by placing underwater concrete on the bottom of the excavated water Forming step, and In the pre-installation process, a plurality of large support works assembled in advance as the support works are used, and these large support works are sequentially set from the air to the water-stop target water area from the bottom to the top. A plurality of stages of the large group support works are installed.

本発明によれば、掘削工程と底盤形成工程を両水域の水位が概ね同じ高さ位置の状態で行なうので、矢板に作用する両水域からの水圧がバランスして矢板の変形を抑えることができる。しかも、支保工として予め組み立てられている大組支保工を気中から止水対象水域に沈設することで、従来のような段階毎に行う排水作業、支保工の現場組立および設置作業が不要になる。これにより、工期の短縮を図ることができる。さらに、底盤と全段の大組支保工がすべて機能する状態で排水を行うので、従来の工法に比して水圧による矢板の累積変形量を小さくすることができる。   According to the present invention, since the excavation step and the bottom plate formation step are performed in a state where the water levels in both water areas are substantially the same, the water pressure acting on the sheet piles is balanced, and deformation of the sheet pile can be suppressed. . In addition, by substituting large supporters that have been pre-assembled as supporters into the water-stopping target water area from the air, there is no need for conventional drainage work, support work on-site assembly and installation work. Become. Thereby, shortening of a construction period can be aimed at. Furthermore, since the drainage is performed in a state where the bottom plate and all the large support works of all stages function, the accumulated deformation amount of the sheet pile due to water pressure can be reduced as compared with the conventional method.

前記大組支保工としては例えば、大火打ち式の支保工を用いる。大火打ち式の支保工では中央部分に大きな開口部を確保できるので大きな作業空間を得ることができる。そのため、止水作業空間内に橋脚等の構造物を構築する際の施工効率の向上を図るには有利になる。   As the large support structure, for example, a large fire-type support structure is used. In the large fire-type support work, a large opening can be secured in the central portion, so that a large working space can be obtained. Therefore, it is advantageous to improve the construction efficiency when constructing a structure such as a pier in the water stop working space.

例えば、前記止水対象水域の水底に打設した中間杭および前記矢板に、上下方向に間隔をあけた複数の所定高さ位置にブラケットを取付け、それぞれの所定高さ位置に取付けられた前記ブラケットにより前記大組支保工を支持することにより、複数の前記大組支保工を上下に間隔をあけて設置する。この場合には、予め取付けたブラケットに大組支保工を設置することで大組支保工の位置決めおよび固定を行うことができる。   For example, brackets are attached to a plurality of predetermined height positions spaced apart in the vertical direction on the intermediate pile and the sheet pile placed on the bottom of the water stop target water area, and the brackets are attached to the respective predetermined height positions. By supporting the large group supporting work by the above, a plurality of large group supporting works are installed at intervals in the vertical direction. In this case, it is possible to position and fix the large group support work by installing the large structure support work on the bracket attached in advance.

本発明の仕切り工程により仕切られた水域を縦断面視で例示する説明図である。It is explanatory drawing which illustrates the water area partitioned off by the partition process of this invention by a longitudinal cross-sectional view. 図1の水域を平面視で例示する説明図である。It is explanatory drawing which illustrates the water area of FIG. 1 by planar view. 本発明の掘削工程により掘削された水域を縦断面視で例示する説明図である。It is explanatory drawing which illustrates the water area excavated by the excavation process of this invention by a longitudinal cross-sectional view. 図2の水域を平面視で例示する説明図である。It is explanatory drawing which illustrates the water area of FIG. 2 by planar view. 本発明の底盤形成工程により底盤が形成された水域を縦断面視で例示する説明図である。It is explanatory drawing which illustrates the water area by which the bottom board was formed by the bottom board formation process of this invention by a longitudinal cross-sectional view. 本発明の支保工設置工程によりブラケットが設置された水域を平面視で例示する説明図である。It is explanatory drawing which illustrates the water area where the bracket was installed by the support installation process of this invention by planar view. 本発明の支保工設置工程により大組支保工を設置している状況を縦断面視で例示する説明図である。It is explanatory drawing which illustrates the condition which has installed the large group support work by the support work installation process of this invention by a longitudinal cross-sectional view. 本発明の支保工設置工程により最下段の大組支保工が設置された水域を平面視で例示する説明図である。It is explanatory drawing which illustrates the water area by which the lowermost large support work was installed by the support work installation process of this invention by planar view. 本発明の支保工設置工程により全段の大組支保工が設置された水域を縦断面視で例示する説明図である。It is explanatory drawing which illustrates the water area where the large group support work of all the stages was installed by the support work installation process of this invention by a longitudinal cross-sectional view. 本発明の排水工程を経て構築した止水作業空間を縦断面視で例示する説明図である。It is explanatory drawing which illustrates the water stop working space constructed | assembled through the drainage process of this invention by a longitudinal cross-sectional view. 図10の止水作業空間に橋脚を構築している状態を縦断面視で例示する説明図である。It is explanatory drawing which illustrates the state which has constructed the pier in the water stop work space of FIG. 10 by a longitudinal cross-sectional view. 図11の橋脚の施工が完了した状態を縦断面視で例示する説明図である。It is explanatory drawing which illustrates the state which construction of the pier of FIG. 11 was completed by a longitudinal cross-sectional view.

以下、本発明の止水作業空間の構築方法を図に示した実施形態に基づいて説明する。本発明は、図1〜10に例示する仕切り工程、掘削工程、底盤形成工程、支保工設置工程、排水工程の5つの工程を順次行って止水対象水域に止水作業空間を構築する。構築された止水作業空間には図12に示すような橋脚16が施工される。   Hereinafter, the construction method of the water stop working space of the present invention will be described based on the embodiments shown in the drawings. In the present invention, the water stop working space is constructed in the water stop target water area by sequentially performing the five steps of the partitioning process, the excavation process, the bottom plate forming process, the support installation process, and the drainage process illustrated in FIGS. In the constructed water stop working space, a pier 16 as shown in FIG. 12 is constructed.

図1、2に例示する仕切り工程では、止水対象水域WA1を区画する矢板1を水底Gに打設する。矢板1の上端部は、水上に突出した状態にする。打設した矢板1の上端部には水平方向に延在する定規材2を設置する。定規材2に沿わせるように水底Gに矢板1を打設して、隣り合う矢板1どうしの継手を連結する。定規材2を用いることで矢板1の位置決めをするとともに矢板1の打設時のぶれを抑制することができる。定規材2としては、例えば、H形鋼を用いる。   In the partitioning process illustrated in FIGS. 1 and 2, a sheet pile 1 that partitions the water stop target water area WA <b> 1 is placed on the bottom G. The upper end of the sheet pile 1 is in a state of protruding above the water. A ruler material 2 extending in the horizontal direction is installed at the upper end of the sheet pile 1 that has been placed. A sheet pile 1 is driven on the bottom G so as to follow the ruler material 2, and joints between adjacent sheet piles 1 are connected. By using the ruler material 2, the sheet pile 1 can be positioned and shake during the placement of the sheet pile 1 can be suppressed. As the ruler material 2, for example, H-shaped steel is used.

隣接して水底に打設した複数の矢板1によって、水域を止水対象水域WA1とその外側の非対象水域WA2とに仕切る。この実施形態では、矢板1として鋼管矢板を使用し、平面視で四角形状の止水対象水域WA1(止水作業空間DA)を形成している。矢板1としては他にも、例えば、ハット型の鋼矢板や直線型の鋼矢板等を使用することができる。止水対象水域WA1は、平面視で円形など任意の形状にすることができる。   The water area is partitioned into a water-stopping target water area WA1 and an outer non-target water area WA2 by a plurality of sheet piles 1 placed adjacent to the bottom of the water. In this embodiment, a steel pipe sheet pile is used as the sheet pile 1, and the water-stop target water area WA1 (water stop working space DA) having a quadrangular shape in plan view is formed. In addition, as the sheet pile 1, for example, a hat-type steel sheet pile, a linear steel sheet pile, or the like can be used. The water-stop target water area WA1 can have an arbitrary shape such as a circle in plan view.

次いで、図3、4に例示する掘削工程では、止水対象水域WA1における矢板1の上端部に仮支保工3を設置し、仮支保工3により矢板1を水平方向に支持した状態にする。この実施形態では、仮支保工3として切梁式の仮支保工を用いている。切梁式の仮支保工は、矢板1の止水対象水域WA1側の面に沿って水平方向に延在する腹起し7と、対向する腹起し7どうしを連結して支持する切梁8とを有している。それぞれの切梁8には伸縮可能なジャッキ10が介在されている。この仮支保工3には、さらに、腹起し7および切梁8を補強する火打ち梁9も設けられている。仮支保工3として例えば、腹起し7と、隣り合う腹起し7どうしを連結して支持する火打ち梁9とを有する大火打ち式の仮支保工を用いることもできる。   Next, in the excavation process illustrated in FIGS. 3 and 4, the temporary support work 3 is installed at the upper end of the sheet pile 1 in the water stop target water area WA <b> 1, and the temporary support work 3 supports the sheet pile 1 in the horizontal direction. In this embodiment, the temporary support work 3 is a cut beam type temporary support work. Cut beam-type temporary support work is a cut beam that connects and supports the bulge 7 extending horizontally along the surface of the sheet pile 1 on the water stop target water area WA1 side and the bulge 7 facing each other. 8. Each cut beam 8 is provided with an extendable jack 10. The temporary support 3 is further provided with a fire beam 9 that reinforces the erection 7 and the cut beam 8. As the temporary support 3, for example, a large fire-type temporary support having a belly ridge 7 and a fire beam 9 that connects and supports the adjacent belly ridges 7 can be used.

仮支保工3を設置する手順は例えば、矢板1の所定高さ位置にブラケット5を取り付ける。そして、腹起し7をブラケット5上に設置し、腹起し7を矢板1に固定する。次いで、起重機船20等を使用して切梁8を対向する腹起し7と腹起し7との間の所定位置に配置した状態で、ジャッキ10を伸長させて切梁8を腹起し7どうしの間で突っ張った状態にする。そして、切梁8を腹起し7に連結する。次いで、腹起し7どうしの交差周辺、腹起し7と切梁8との交差周辺に火打ち梁9を設置して補強する。以上により、矢板1に対して仮支保工3を固定する。   The procedure for installing the temporary support 3 is, for example, attaching the bracket 5 to a predetermined height position of the sheet pile 1. Then, the erection 7 is installed on the bracket 5, and the erection 7 is fixed to the sheet pile 1. Next, using the hoist ship 20 or the like, with the cut beam 8 disposed at a predetermined position between the opposed bulge 7 and the bulge 7, the jack 10 is extended to erection the cut beam 8. Keep it stretched between the two. Then, the cut beam 8 is erected and connected to 7. Next, a fire beam 9 is installed and reinforced around the intersection of the bulges 7 and around the intersection of the bulges 7 and the cut beam 8. As described above, the temporary support 3 is fixed to the sheet pile 1.

次いで、止水対象水域WA1の水位WL1と非対象水域WA2の水位WL2とが概ね同じ高さ位置(例えば、上下差が1m以内)の状態で止水対象水域WA1を所定深さの水底G1まで掘削する。水底G1の掘削は例えば、グラブ浚渫船やクラムシェル等によって行う。   Next, in the state where the water level WL1 of the water stop target water area WA1 and the water level WL2 of the non-target water area WA2 are substantially the same height position (for example, within 1 m or less), the water stop target water area WA1 is moved to the bottom G1 having a predetermined depth. Excavate. The bottom G1 is excavated by, for example, a grab dredger or a clamshell.

この実施形態では、矢板1の上端部に連通孔11が形成されている。連通孔11を通じて止水対象水域WA1と非対象水域WA2との間を水が流通する。そのため、止水対象水域WA1の水位WL1と非対象水域WA2の水位WL2とが矢板1の上端部で概ね同じ高さ位置に維持される。ポンプ等を使用して止水対象水域WA1の水位WL1と非対象水域WA2の水位WL2とを概ね同じ高さ位置になるように調整することもできる。   In this embodiment, a communication hole 11 is formed at the upper end of the sheet pile 1. Water flows between the water-stopping target water area WA1 and the non-target water area WA2 through the communication hole 11. Therefore, the water level WL1 of the water stop target water area WA1 and the water level WL2 of the non-target water area WA2 are maintained at substantially the same height position at the upper end portion of the sheet pile 1. It is also possible to adjust the water level WL1 of the water-stop target water area WA1 and the water level WL2 of the non-target water area WA2 to be approximately the same height position using a pump or the like.

このように、本発明では、掘削工程を止水対象水域WA1の水位WL1および非対象水域WA2の水位WL2が概ね同じ高さ位置の状態で行なうので、矢板1に作用する両水域からの水圧がバランスして矢板1の変形を抑えることができる。この実施形態では、さらに、矢板1の上端部に仮支保工3を設置しているので、止水対象水域WA1を水底G1まで掘削することで、止水対象水域WA1の水位WL1が非対象水域WA2の水位WL2に比べて若干低くなった場合おいても、仮支保工3により水圧による矢板1の変形を抑えるには有利になっている。したがって、矢板1の変形が大きくなりそうな現場では仮支保工3を設置する。   Thus, in the present invention, the excavation process is performed in a state where the water level WL1 of the water-stopping target water area WA1 and the water level WL2 of the non-target water area WA2 are substantially at the same height position, so that the water pressure from both water areas acting on the sheet pile 1 is reduced. The deformation of the sheet pile 1 can be suppressed by balancing. In this embodiment, since the temporary support 3 is installed in the upper end part of the sheet pile 1, the water level WL1 of the water stop target water area WA1 is set to the non-target water area by excavating the water stop target water area WA1 to the bottom G1. Even when it is slightly lower than the water level WL2 of WA2, it is advantageous for the temporary support 3 to suppress the deformation of the sheet pile 1 due to water pressure. Therefore, the temporary support 3 is installed at the site where the deformation of the sheet pile 1 is likely to increase.

次いで、図5に例示する底盤形成工程においても、掘削工程に引き続いて、止水対象水域WA1の水位WL1と非対象水域WA2の水位WL2とを概ね同じ高さ位置とする。底盤形成工程では、まず、止水対象水域WA1の水底G1に複数の中間杭4を打設する。中間杭4としては、例えば、H形鋼を用いる。中間杭4は、後に設置する大組支保工6の内周縁に沿う位置に配置する。水底G1の地盤強度が不十分な場合には、公知の地盤改良工法によって水底G1の地盤強度を向上させる。   Next, also in the bottom plate forming process illustrated in FIG. 5, following the excavation process, the water level WL1 of the water-stop target water area WA1 and the water level WL2 of the non-target water area WA2 are set to approximately the same height position. In the bottom plate forming step, first, a plurality of intermediate piles 4 are placed on the bottom G1 of the water stop target water area WA1. As the intermediate pile 4, for example, an H-section steel is used. The intermediate pile 4 is arrange | positioned in the position along the inner periphery of the large group support work 6 installed later. When the ground strength of the bottom G1 is insufficient, the ground strength of the bottom G1 is improved by a known ground improvement method.

次いで、止水対象水域WA1の水底G1の上に敷砂13を敷き詰めて均す。そして、均した敷砂13の上に水中コンクリートを打設して底盤14を形成し、その後、仮支保工3を矢板1から取り外して撤去する。水中コンクリートは、水中での材料分離を防ぐために、例えば、水中不分離性混和剤や流動化剤等の混和剤が添加された水中不分離性コンクリートを使用する。   Next, the sand 13 is spread on the water bottom G1 of the water stop target water area WA1 and leveled. And underwater concrete is laid on the leveled sand 13 to form the bottom board 14, and then the temporary support 3 is removed from the sheet pile 1 and removed. In order to prevent material separation in water, underwater concrete uses, for example, underwater inseparable concrete to which an admixture such as an underwater inseparable admixture or a fluidizing agent is added.

止水対象水域WA1の水底G1の上に水中コンクリートが固化した底盤14を形成することで、底盤14により矢板1を水平方向に支持することができる。これにより、矢板1の変形をより抑えることができる。中間杭4の下端部は底盤14により強固に支持される。   By forming the bottom board 14 in which the underwater concrete is solidified on the water bottom G1 of the water stop target water area WA1, the sheet pile 1 can be supported by the bottom board 14 in the horizontal direction. Thereby, a deformation | transformation of the sheet pile 1 can be suppressed more. The lower end of the intermediate pile 4 is firmly supported by the bottom board 14.

次いで、図6〜9に例示する支保工設置工程では、複数の大組支保工6を上下に間隔をあけて設置する。まず、図6に示すように、中間杭4と矢板1の最下段の大組支保工6を設置する所定高さ位置にそれぞれブラケット5を取り付ける。そして、図7に示すように、予め組み立てられた大組支保工6を起重機船20等を使用して気中から止水対象水域WA1に沈めて、ブラケット5上に設置する。水中における作業は主に潜水士によって行う。   Next, in the support work installation process illustrated in FIGS. 6 to 9, a plurality of large group support works 6 are installed at intervals in the vertical direction. First, as shown in FIG. 6, the brackets 5 are respectively attached to predetermined height positions where the intermediate pile 4 and the lowermost large support 6 of the sheet pile 1 are installed. Then, as shown in FIG. 7, the large assembly support 6 assembled in advance is submerged in the water-stopping target water area WA <b> 1 using the hoist ship 20 or the like and installed on the bracket 5. Underwater work is mainly performed by divers.

図8に示すように、この実施形態では、大組支保工6として腹起し7と火打ち梁9とを有する大火打ち式の支保工を用いている。火打ち梁9は腹起し7で形成された隅に斜めに架け渡された梁部材である。大組支保工6には、腹起し7および火打ち梁9を補強する切梁8も設けられている。大組支保工6の平面視の中央部分には、これから構築される橋脚16が収まる大きさの開口部が形成されている。矢板1に取り付けたブラケット5上に腹起し7を載置するとともに、中間杭4に取り付けたブラケット5上に火打ち梁9と切梁8を載置することで大組支保工6を仮設置する。   As shown in FIG. 8, in this embodiment, a large fire-type support structure having a belly rise 7 and a fire beam 9 is used as the large group support structure 6. The fire beam 9 is a beam member that is slanted over the corner formed by the bulge 7. The large group support 6 is also provided with a beam 8 for reinforcing the erection 7 and the fire beam 9. An opening having a size that can accommodate a bridge pier 16 to be constructed in the future is formed in the central portion of the large support 6 in plan view. While placing the belly 7 on the bracket 5 attached to the sheet pile 1 and placing the fire beam 9 and the cutting beam 8 on the bracket 5 attached to the intermediate pile 4, a large support 6 is temporarily installed. To do.

次いで、図8に示すように、腹起し7と矢板1の間に水中コンクリート等の間詰材12を充填して、間詰材12を固化させることにより矢板1に対して大組支保工6を固定する。これにより、1段の大組支保工6の設置が完了する。同様に、ブラケット5の取り付け作業、大組支保工6の沈設作業、間詰材12の充填作業を繰り返し行うことで、図9に例示するように下段から上段にかけて上下方向に間隔をあけて複数段の大組支保工6を設置する。   Next, as shown in FIG. 8, a large support for the sheet pile 1 is made by filling a filler 12 such as underwater concrete between the uplift 7 and the sheet pile 1 and solidifying the filler 12. 6 is fixed. This completes the installation of the one-stage large support structure 6. Similarly, by repeatedly performing the mounting work of the bracket 5, the setting work of the large structure supporter 6, and the filling work of the interstitial material 12, a plurality of pieces are spaced apart in the vertical direction from the lower stage to the upper stage as illustrated in FIG. 9. Set up a large support structure 6 of steps.

次いで、図10に例示する排水工程では、止水対象水域WA1の水をポンプ等を使用して外部に排出することにより止水対象水域WA1を気中状態の止水作業空間DAにする。この実施形態では、矢板1に連通孔11が形成されているので、排水工程を行う際には連通孔11は塞いでおく。以上により、止水作業空間DAの構築が完了する。   Next, in the drainage process illustrated in FIG. 10, the water in the water-stopping target water area WA1 is made into a water-stopping working space DA in the air by discharging the water in the water-stopping target water area WA1 to the outside using a pump or the like. In this embodiment, since the communication hole 11 is formed in the sheet pile 1, the communication hole 11 is closed when performing a drainage process. Thus, the construction of the water stop working space DA is completed.

その後、図11に例示する橋脚構築工程では、底盤14の上に鉄筋を組み上げてコンクリートを打設することにより、橋脚16の土台となる頂版15を形成する。そして、頂版15の上に橋脚16を構築するための足場を構築する。次いで、橋脚16の最下段を構成する鉄筋を組み上げて、鉄筋の外側に型枠を設置する。そして、型枠内にコンクリートを打設することにより、橋脚16の最下段を構築する。同様に、鉄筋の組み上げ、型枠の設置、コンクリート打設を繰り返し行うことで、橋脚16を下段から上段にかけて順次構築する。   After that, in the pier construction process illustrated in FIG. 11, the top plate 15 that forms the foundation of the pier 16 is formed by assembling the reinforcing bars on the bottom plate 14 and placing concrete. Then, a scaffold for constructing the pier 16 is constructed on the top plate 15. Next, the reinforcing bars constituting the lowermost stage of the pier 16 are assembled, and the formwork is installed outside the reinforcing bars. And the lowest stage of the pier 16 is constructed | assembled by placing concrete in a formwork. Similarly, the pier 16 is constructed sequentially from the lower stage to the upper stage by repeatedly assembling the reinforcing bars, installing the formwork, and placing the concrete.

橋脚16の構築が完了した後は、止水作業空間DAに水を注水して止水対象水域WA1(止水作業空間DA)の水位W1を非対象水域WA2との水位WL2とを概ね同じ高さにする。そして、矢板1に作用する両水域からの水圧がバランスした状態で大組支保工6を撤去する。次いで、矢板1の水底Gに埋設されている部分を残した状態で切断し、その上方の不要な部分は撤去する。中間杭4の頂版15よりも上側に突出する部分も切断して撤去する。最後に適宜土砂の埋め戻しを行うことにより図12に例示するように橋脚16の施工が完了する。   After the construction of the pier 16 is completed, water is poured into the water stop working space DA so that the water level W1 of the water stop target water area WA1 (water stop work space DA) is substantially the same as the water level WL2 with the non-target water area WA2. Say it. And the large group support work 6 is removed in the state which the water pressure from both water areas which act on the sheet pile 1 balanced. Subsequently, it cut | disconnects in the state which left the part embed | buried under the bottom G of the sheet pile 1, and removes the unnecessary part above it. The portion protruding above the top plate 15 of the intermediate pile 4 is also cut and removed. Finally, the construction of the pier 16 is completed as illustrated in FIG.

本発明では上述したとおり、支保工として予め組み立てられている大組支保工6を気中から止水対象水域WA1に沈設するので、従来のような段階毎に行う排水作業、支保工の現場組立および設置作業が不要になる。これにより、従来に比して工期の大幅な短縮を図ることができる。また、従来では支保工を上段から下段にかけて設置していたため、下段の支保工を設置する際には、上段の支保工を避けながら設置作業を行なう必要があったが、本発明では大組支保工6を下段から上段にかけて設置することができるので、比較的広い作業空間を確保した状態で大組支保工6の設置作業を行なうことができる。   In the present invention, as described above, since the large support 6 that has been assembled in advance as a support is submerged in the water-stopping target water area WA1 from the air, the conventional drainage work performed at each stage, assembling of the support in the field And installation work becomes unnecessary. As a result, the construction period can be greatly shortened as compared with the prior art. Conventionally, since the support work was installed from the upper stage to the lower stage, it was necessary to perform the installation work while avoiding the upper support work when installing the lower support work. Since the work 6 can be installed from the lower stage to the upper stage, the installation work of the large support structure 6 can be performed in a state in which a relatively wide work space is secured.

しかも、この実施形態では、大組支保工6を大火打ち式の支保工で構成し、大組支保工6の中央部分に大きな開口部を形成しているので、橋脚16を構築する際に、工事の進行に合わせて支保工や足場を移設する盛り替えが不要となる。それ故、切梁式の支保工を設置する従来の工法に比して、橋脚16の施工に要する工期の大幅な短縮を図ることができる。   In addition, in this embodiment, the large group support work 6 is configured by a large fire-type support work, and a large opening is formed in the central portion of the large structure support work 6, so when the pier 16 is constructed, As the construction progresses, it will not be necessary to relocate support works or scaffolds. Therefore, the construction period required for the construction of the pier 16 can be greatly shortened as compared with the conventional construction method in which a beam-type support is installed.

さらに、本発明では、底盤14と支保工(全段の大組支保工6)がすべて機能する状態で排水を行うので、従来の工法に比して水圧による矢板1の累積変形量を小さくすることができる。矢板1の累積変形量を小さくできることで、従来に比して支保工の段数や部材数を減らすことも可能になる。   Furthermore, in the present invention, since drainage is performed in a state where the bottom plate 14 and the support work (all-stage large support work 6) are functioning, the accumulated deformation amount of the sheet pile 1 due to water pressure is reduced as compared with the conventional method. be able to. Since the amount of accumulated deformation of the sheet pile 1 can be reduced, it is possible to reduce the number of stages of supporting works and the number of members as compared with the conventional case.

中間杭4および矢板1の所定高さ位置にブラケット5を取付け、その後に大組支保工6を気中から止水対象水域WA1に沈設して、ブラケット5上に設置する構成にすると、ブラケット5により大組支保工6の位置決めを精度よく行うことができる。   When the bracket 5 is attached to the intermediate pile 4 and the sheet pile 1 at a predetermined height position, and then the large support structure 6 is submerged from the air into the water-stopping target water area WA1 and installed on the bracket 5, the bracket 5 As a result, positioning of the large support structure 6 can be performed with high accuracy.

実施形態では、支保工設置工程において、予め組み立てられている1つの大組支保工6を順次沈設する方法を例示したが、例えば、複数段あるいは全段の大組支保工6を予め連結して組み立てておき、これを沈設することもできる。また、大組支保工6は切梁式の支保工等で構成することもできる。   In the embodiment, the method of sequentially sinking one large group supporting work 6 assembled in advance in the supporting work installation step is exemplified. For example, a plurality of or all stages of large structure supporting works 6 are connected in advance. You can assemble it and sink it. Moreover, the large group support work 6 can also be comprised by a cut beam type support work etc.

本発明は、平面視で四角形や円形、小判型等の任意形状の止水作業空間DAを構築することも可能である。仮支保工3の構成や大組支保工6の構成、中間杭4の位置、中間杭4を打設するタイミング等も上記で示した実施形態に限定されず、適宜様々な構成にすることができる。また、本発明は、橋脚16を施工する場合に限らず、例えば、風力発電の支柱を施工する場合等に採用することもできる。   The present invention can also construct a water stop working space DA having an arbitrary shape such as a quadrangle, a circle, or an oval shape in a plan view. The configuration of the temporary support 3, the configuration of the large support 6, the position of the intermediate pile 4, the timing for placing the intermediate pile 4, and the like are not limited to the embodiment described above, and various configurations can be appropriately made. it can. In addition, the present invention is not limited to the case where the pier 16 is constructed, and may be employed, for example, when a column for wind power generation is constructed.

1 矢板
2 定規材
3 仮支保工
4 中間杭
5 ブラケット
6 大組支保工
7 腹起し
8 切梁
9 火打ち梁
10 ジャッキ
11 連通孔
12 間詰材
13 敷砂
14 底盤
15 頂版
16 橋脚
20 起重機船
WA1 止水対象水域
WA2 非対象水域
DA 止水作業空間
G 水底
G1 止水対象水域の水底
WL1 止水対象水域の水位
WL2 非対象水域の水位
DESCRIPTION OF SYMBOLS 1 Sheet pile 2 Ruler material 3 Temporary support 4 Intermediate pile 5 Bracket 6 Large group support 7 Raise 8 Cut beam 9 Fire beam 10 Jack 11 Communication hole 12 Filling material 13 Laying sand 14 Bottom board 15 Top plate 16 Pier 20 Hoist Ship WA1 Water stop target water area WA2 Non-target water area DA Water stop working space G Water bottom G1 Water bottom WL1 Water stop target water level WL2 Water non-target water level

Claims (3)

隣接して水底に打設した複数の矢板によって止水対象水域と非対象水域とに仕切る仕切り工程と、前記止水対象水域に支保工を設置して前記矢板を前記支保工により支持する支保工設置工程と、前記支保工を設置した前記止水対象水域の水を外部に排出することにより前記止水対象水域を気中状態の止水作業空間にする排水工程とを有する止水作業空間の構築方法において、
前記仕切り工程と前記支保工設置工程との間で、前記止水対象水域および前記非対象水域の水位が前記矢板の上端部に位置する状態で、前記止水対象水域の水底を所定深さまで掘削する掘削工程と、この掘削した後の水底に複数の中間杭を打設してから、この水底の上に水中コンクリートを打設して底盤を形成する底板形成工程とを有し、前記支保工設置工程では、前記支保工として予め組み立てられている大組支保工を使用して、この大組支保工を気中から前記止水対象水域に沈設して、前記中間杭が前記大組支保工の内周縁に沿う位置に配置された状態で、前記大組支保工を前記矢板および前記中間杭のそれぞれに取付けられているブラケットに載置して設置することを特徴とする止水作業空間の構築方法。
A partitioning process of partitioning into a water stop target water area and a non-target water area by a plurality of sheet piles placed adjacent to the bottom of the water, and a support work in which a support is installed in the water stop target water area and the sheet pile is supported by the support work A water stop working space having an installation step and a draining step of making the water stop target water region into an air stop water work space by discharging the water in the water stop target water region where the support is installed to the outside. In the construction method,
Between the partitioning step and the support installation step, the bottom of the water stop target water area is excavated to a predetermined depth with the water levels of the water stop target water area and the non-target water area located at the upper end of the sheet pile. And a bottom plate forming step in which a plurality of intermediate piles are placed on the bottom of the water after the excavation, and then a bottom plate is formed by placing underwater concrete on the bottom of the water. In the installation process, using a large group supporting work assembled in advance as the supporting structure, the large structure supporting structure is submerged from the air into the water-stopping target water area, and the intermediate pile is supported by the large structure supporting structure. In the state of being arranged at a position along the inner peripheral edge of the water stop working space, the large support structure is placed and installed on a bracket attached to each of the sheet pile and the intermediate pile . Construction method.
隣接して水底に打設した複数の矢板によって止水対象水域と非対象水域とに仕切る仕切り工程と、前記止水対象水域に支保工を設置して前記矢板を前記支保工により支持する支保工設置工程と、前記支保工を設置した前記止水対象水域の水を外部に排出することにより前記止水対象水域を気中状態の止水作業空間にする排水工程とを有する止水作業空間の構築方法において、
前記仕切り工程と前記支保工設置工程との間で、前記止水対象水域および前記非対象水域の水位が前記矢板の上端部に位置する状態で、前記止水対象水域の水底を所定深さまで掘削する掘削工程と、この掘削した後の水底の上に水中コンクリートを打設して底盤を形成する底盤形成工程とを有し、前記支保工設置工程では、前記支保工として予め組み立てられている複数の大組支保工を使用して、これらの大組支保工を下段から上段にかけて、気中から前記止水対象水域に順次沈設して、複数段の前記大組支保工を設置することを特徴とする止水作業空間の構築方法。
A partitioning process of partitioning into a water stop target water area and a non-target water area by a plurality of sheet piles placed adjacent to the bottom of the water, and a support work in which a support is installed in the water stop target water area and the sheet pile is supported by the support work A water stop working space having an installation step and a draining step of making the water stop target water region into an air stop water work space by discharging the water in the water stop target water region where the support is installed to the outside. In the construction method,
Between the partitioning step and the support installation step, the bottom of the water stop target water area is excavated to a predetermined depth with the water levels of the water stop target water area and the non-target water area located at the upper end of the sheet pile. multiple drilling and step, and a bottom plate forming a bottom plate and Da設underwater concrete over the bottom of the water after the drilling, in the shoring setting step, which are assembled in advance as the shoring that using a large set支保Engineering, features that subjected upper these large set支保Engineering from the lower, are sequentially sinking from in the air to the water stop target water area, placing the large set支保Engineering plurality of stages The construction method of the water stop working space.
前記大組支保工が、大火打ち式の支保工である請求項1または2に記載の止水作業空間の構築方法。 The construction method of the water stop working space according to claim 1 or 2 , wherein the large group support work is a large fire-type support work.
JP2016252455A 2016-12-27 2016-12-27 Construction method of water stop working space Active JP6454674B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016252455A JP6454674B2 (en) 2016-12-27 2016-12-27 Construction method of water stop working space

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016252455A JP6454674B2 (en) 2016-12-27 2016-12-27 Construction method of water stop working space

Publications (2)

Publication Number Publication Date
JP2018017111A JP2018017111A (en) 2018-02-01
JP6454674B2 true JP6454674B2 (en) 2019-01-16

Family

ID=61081217

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016252455A Active JP6454674B2 (en) 2016-12-27 2016-12-27 Construction method of water stop working space

Country Status (1)

Country Link
JP (1) JP6454674B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109371996A (en) * 2018-12-04 2019-02-22 中铁大桥局集团有限公司 A kind of cofferdam and its lifting decentralization construction method
JP7079726B2 (en) * 2018-12-28 2022-06-02 鹿島建設株式会社 How to dismantle the support
JP7296311B2 (en) * 2019-12-13 2023-06-22 大成建設株式会社 Construction method of underground structure
JP7437336B2 (en) * 2021-02-24 2024-02-22 鹿島建設株式会社 Temporary cofferdam method, temporary cofferdam structure
CN115492141B (en) * 2022-10-21 2024-01-30 中铁二院工程集团有限责任公司 Steel suspended box cofferdam structure, bottom plate thereof and construction method

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10168915A (en) * 1996-12-13 1998-06-23 Hazama Gumi Ltd Method of ground excavation construction in coffering sheet pile
JP2000352026A (en) * 1999-06-09 2000-12-19 Fudo Constr Co Ltd Method for installation of supporting material for cofferdam construction
JP3794682B2 (en) * 2002-01-15 2006-07-05 鹿島建設株式会社 Construction method of multistage underwater support
JP6317122B2 (en) * 2014-02-07 2018-04-25 鹿島建設株式会社 Yamazushi support work
JP2016205126A (en) * 2015-04-23 2016-12-08 清水建設株式会社 Earth-retaining support method, and earth-retaining support structure
JP6200550B1 (en) * 2016-05-27 2017-09-20 鹿島建設株式会社 Temporary deadline method, temporary deadline structure

Also Published As

Publication number Publication date
JP2018017111A (en) 2018-02-01

Similar Documents

Publication Publication Date Title
JP6454674B2 (en) Construction method of water stop working space
US9567720B2 (en) Offshore platform for a marine environment
JP6010070B2 (en) Temporary closing method for existing underwater structures
KR100936161B1 (en) Nature friendly polygon cell type coffering method for harbor, river and dam construction
JP2007205077A (en) Temporary coffering method
JP6274688B1 (en) Temporary deadline construction method
CN110359476B (en) Construction method of construction platform for mounting steel sheet pile cofferdam inner support and bored pile steel casing
AU2012313196B2 (en) Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method
KR101296856B1 (en) Reinforcement structure for wall of underground structure and construction method of underground structure using the same
KR102168165B1 (en) Reinforcement method of Pile­Support Intake Tower using Earthquake­Resistant Pile and Slab
AU2020100004A4 (en) A Method Of Constructing A Column, A Subterranean Structure, And A Structure Made From The Method
JPH10168915A (en) Method of ground excavation construction in coffering sheet pile
JP2001348888A (en) Method and device for constructing underwater foundation structure
JP2007291770A (en) Pit excavation method
JP4475116B2 (en) Vertical shaft structure and its construction method
JP7437336B2 (en) Temporary cofferdam method, temporary cofferdam structure
CN115262568B (en) Deepening support and excavation construction method based on zero-field deep foundation pit
KR101381276B1 (en) Construction method of split type pc house and split type pc house
CN210262915U (en) Integrated configuration of revetment pipe groove plank road
CN106836247B (en) Combined cofferdam and construction method thereof
JP2002188159A (en) Execution method for underwater structure
KR102016972B1 (en) Construction Method of Underwater Civil Engineering Structure Foundation
JPH10227194A (en) Construction method of shaft
JP6851180B2 (en) How to rebuild the building
CN117569563A (en) Method for safely and stably fixing basement exterior wall template of large building in coastal beach area

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20171218

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20180808

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20180814

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20180928

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20181204

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20181217

R150 Certificate of patent or registration of utility model

Ref document number: 6454674

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250