JPS62202125A - Underwater foundation work using steel plate shell - Google Patents
Underwater foundation work using steel plate shellInfo
- Publication number
- JPS62202125A JPS62202125A JP4130486A JP4130486A JPS62202125A JP S62202125 A JPS62202125 A JP S62202125A JP 4130486 A JP4130486 A JP 4130486A JP 4130486 A JP4130486 A JP 4130486A JP S62202125 A JPS62202125 A JP S62202125A
- Authority
- JP
- Japan
- Prior art keywords
- steel plate
- concrete
- plate cells
- piles
- footing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 53
- 239000010959 steel Substances 0.000 title claims abstract description 53
- 238000010276 construction Methods 0.000 claims abstract description 30
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 18
- 239000000945 filler Substances 0.000 claims description 11
- 238000000034 method Methods 0.000 abstract description 12
- 210000004027 cell Anatomy 0.000 description 43
- 238000009415 formwork Methods 0.000 description 3
- 210000002421 cell wall Anatomy 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 230000002787 reinforcement Effects 0.000 description 2
- 230000000630 rising effect Effects 0.000 description 2
- 229910001208 Crucible steel Inorganic materials 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 238000003911 water pollution Methods 0.000 description 1
Landscapes
- Foundations (AREA)
Abstract
Description
【発明の詳細な説明】
〔産業上の利用分野〕
この発明は鋼板セルを用いた水中基礎工法に関するもの
で、例えば橋脚の基礎等の施工に利用される。[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to an underwater foundation construction method using steel plate cells, and is used, for example, in construction of bridge pier foundations.
〔従来の技術および問題点」
近年、都市道路網の整備に伴なう湾岸道路の建設あるい
は沖合人工島建設に伴なう連絡橋架設等において海中も
しくは水中に橋脚を設ける事例が増加している。[Conventional technology and problems] In recent years, there has been an increase in the number of cases in which bridge piers are installed in or under the sea in the construction of coastal roads in conjunction with the development of urban road networks or in the construction of connecting bridges in conjunction with the construction of offshore artificial islands. .
このような水中構造物の基礎を施工するための工法には
特に次の点が要求される場合が多い。Construction methods for constructing foundations for such underwater structures often require the following points in particular:
■ 波浪、水流に対して、あまり影響されないこと
■ 現場施工期間が短いこと
■ 安全に施工できること
■ 大規模な仮設備を必要としないこと■ 水質汚濁を
起こさないこと
■ 経済的であること
従来の工法としては二重矢板による締切工法、ケーソン
工法、鋼管どうしを継手によって連結した井筒を使用す
る鋼管矢板井筒工法、水面上まで立上った多数の杭とそ
の頭部に設置されだフーチングよシなる多柱基礎工法、
その他鋼板セルと該セル内に施工した地中連続壁を組み
合わせた根入れ式鋼板セル・ケーソン工法(特開昭59
−8835号)や同心円状に打設した径の異なる鋼板セ
ルの内側の鋼板セル内部を中埋めするとともに内外の鋼
板セル間に立上りコンクリートを、中埋め部および立上
りコンクリートの上部に上部コンクリートを打設する海
中基礎工法(特開昭59−138621号)等があるが
、いずれも施工性経済性等で一長一短がある。例えば多
柱基礎工法ではフーチングコンクリートが水面上に施工
されいわゆるトップ・ヘビーの状態になるため、地震時
に杭に発生するモーメントが大きくなり、径の大きな杭
が必要となる。■ Not affected much by waves and water currents ■ Short on-site construction period ■ Safe construction ■ Does not require large-scale temporary equipment ■ Does not cause water pollution ■ Economical Construction methods include the cofferdam method using double sheet piles, the caisson method, the steel pipe sheet pile well method, which uses wells made by connecting steel pipes with joints, and the footings installed at the heads of many piles that rise above the water surface. Multi-column foundation construction method,
Other steel plate cell caisson construction methods (Japanese Unexamined Patent Publication No. 59/1989) that combine steel plate cells and underground continuous walls constructed within the cells.
-8835) or concentrically cast steel plate cells with different diameters, and then fill in the inside of the steel plate cells and place rising concrete between the inner and outer steel plate cells, and place upper concrete on the middle fill part and the top of the rising concrete. There are underwater foundation construction methods (Japanese Unexamined Patent Publication No. 59-138621), but all of them have advantages and disadvantages in terms of construction efficiency, etc. For example, in the multi-column foundation construction method, the footing concrete is constructed above the water surface, resulting in a so-called top-heavy condition, which increases the moment generated in the piles during an earthquake, necessitating the use of larger diameter piles.
この発明の工法ではこのような水中構造物の基礎を経済
的、かつ確実に施工できることを目的としている。The purpose of the construction method of the present invention is to economically and reliably construct the foundations of such underwater structures.
この発明の工法では、あらかじめ製作された大径筒状の
異なる径の鋼板セル1,2を水底地盤6に同心に根入れ
するとともに、この二重鋼板セルの内外の鋼板セル1,
2間に打設された複数の杭3の頭部を内外の鋼板セル1
,2間に間詰コンクリート4を充填することにより固定
する。なお二重鋼板セルは内外の鋼板セル1,2をあら
かじめ一体化しておいて打込む方法と内外それぞれの単
体鋼板セル1,2を個別に打込む方法とがある。In the construction method of this invention, prefabricated large-diameter cylindrical steel plate cells 1 and 2 of different diameters are concentrically rooted in the underwater ground 6, and the steel plate cells 1 and 2 inside and outside of this double steel plate cell,
The heads of the multiple piles 3 driven between the inner and outer steel plate cells 1
, 2 is fixed by filling the gap with filler concrete 4. Note that there are two methods for forming the double steel plate cells: one is to integrate the inner and outer steel plate cells 1 and 2 in advance and then drive them, and the other is to drive the inner and outer single steel plate cells 1 and 2 individually.
打込み方法としてはクレーン船および多数のバイブロハ
ンマーを連動させる装置による振動打込み方式が既に実
用化されている。As a driving method, a vibration driving method using a crane ship and a device that links multiple vibrohammers has already been put into practical use.
次に、内側の鋼板セル1内に水を残したまま、その水面
上に前記間詰コンクリート4をつなぐフーチングコンク
リート5を打設し、前記杭3と内外の鋼板セル1,2で
、囲まれた筒状部およびその上部のフーチング部をコン
クリートで一体化する。Next, while leaving water in the inner steel plate cells 1, a footing concrete 5 is placed on the water surface to connect the filler concrete 4, and the footing concrete 5 is surrounded by the piles 3 and the inner and outer steel plate cells 1 and 2. The cylindrical part and the footing part above it are integrated with concrete.
以上により、水中基礎が形成され、上部に橋脚等の上部
構造物を構築することができる。Through the above steps, an underwater foundation is formed, and a superstructure such as a bridge pier can be constructed on top of the underwater foundation.
なお、鋼板セル1,2は円筒状のものに限らず第2図に
示すような長円形断面のもの等でもよい。The steel plate cells 1 and 2 are not limited to cylindrical ones, but may have an oval cross section as shown in FIG. 2.
次に、この発明の実施例を図面に基づいて説明する。 Next, embodiments of the present invention will be described based on the drawings.
第1図(a) 、 (t))はこの発明の工法が水中橋
脚基礎に用いられる場合の構造概念図である。Figures 1(a) and 1(t) are structural conceptual diagrams when the construction method of the present invention is used for an underwater pier foundation.
水底地盤6に同心円状に打設された二重鋼板セル内外の
鋼板セル1,2間には所要の鉛直力および水平力に耐え
得るだけの杭3が打設されている。Piles 3 sufficient to withstand the required vertical force and horizontal force are driven between the inner and outer steel plate cells 1 and 2, which are concentrically driven into the underwater ground 6.
鋼板セル1,2間は間詰コンクリート4により充填され
ており、杭3頭部はこの間詰コンクリート4により固定
されている。The space between the steel plate cells 1 and 2 is filled with filler concrete 4, and the head of the pile 3 is fixed by this filler concrete 4.
間詰コンクリート4の上部には円形のフーチングコンク
リート5が内外の鋼板セル1.2に囲まれた円筒部に蓋
をするかたちで打設され、フーチングコンクリート5か
らは橋脚7が立上っている。A circular footing concrete 5 is placed on top of the filler concrete 4 to cover the cylindrical part surrounded by the inner and outer steel plate cells 1.2, and a pier 7 rises from the footing concrete 5. .
なお、この実施例では杭3は内外の鋼板セル1゜2間に
のみ打設されているが、基礎耐力を上げるため、第7図
に示すように内側の鋼板セル1内に杭頭をフーチングコ
ンクリート5に固定される追加の杭3′を打設してもよ
い。In this example, the piles 3 are driven only between the inner and outer steel plate cells 1°2, but in order to increase the foundation strength, a footing with a pile head is placed inside the inner steel plate cell 1 as shown in Fig. 7. Additional piles 3' fixed to the concrete 5 may be driven.
この構造では多柱基礎工法によるものと同様フーチング
コンクリート5が水面付近に施工されることとなり、い
わゆるトップ・ヘビーの状態となる。多柱基礎では、こ
のため地震時に杭に発生するモーメントが大きくなシ、
径の大きな杭が必要となるが、この発明による構造では
杭頭が水底地盤面付近で固定されているため、杭3に発
生するモーメントは大きくならず、従って杭径も比較的
小さくできる。In this structure, the footing concrete 5 is constructed near the water surface, similar to the multi-column foundation construction method, resulting in a so-called top-heavy condition. For this reason, in multi-column foundations, the moment generated in the piles during an earthquake is large.
Although a pile with a large diameter is required, in the structure according to the present invention, since the pile head is fixed near the underwater ground surface, the moment generated on the pile 3 does not become large, and therefore the pile diameter can be made relatively small.
第2図は内外の鋼板セル1,2の断面を長円形とした場
合を示しだものである。すなわち、内側の鋼板1′内に
土砂等の中詰材を充填すると、直線部のセル殻に大きな
モーメントが生じるが、この発明では中詰めを行なわず
、内外の鋼板セル1’、2’ 間に間詰コンクリート4
を打設した構造であるため長円形も可能であり、特に流
れ方向に立設すれば基礎に加わる流体 や水流に与える
影響も少なく、また荷重条件に対応した経済的な机配置
も可能となり、効果が犬である。FIG. 2 shows the case where the inner and outer steel plate cells 1 and 2 have an oval cross section. That is, when the inner steel plate 1' is filled with filler material such as earth and sand, a large moment is generated in the cell shell in the straight section, but in this invention, filling is not performed and the space between the inner and outer steel plate cells 1' and 2' is Interfill concrete 4
Because it is a concrete structure, an oval shape is also possible.Especially if it is installed upright in the flow direction, there is less impact on the fluid and water flow applied to the foundation, and it is also possible to arrange the desk economically according to the load conditions. The effect is a dog.
第3図〜第6図はこの発明の工法による施工手順を示し
たもので、次のような手順で作業を行なう。3 to 6 show the construction procedure according to the construction method of the present invention, and the work is carried out in the following steps.
■ あらかじめ製作された鋼板セル1,2は打設場所に
運搬され、位置決めの後、水底地盤6中に所要深さだけ
打設される(第3図参照)。外側の鋼板セル2の天端高
さは、後に施工される間詰コンクリート4の外周型枠を
兼ねることおよび施工中波浪の影響を受けないことを目
的として水面より高いレベルとする。■ The steel plate cells 1 and 2 manufactured in advance are transported to the pouring site, and after positioning, are poured into the underwater ground 6 to the required depth (see Fig. 3). The height of the top of the outer steel plate cell 2 is set at a level higher than the water surface in order to serve as the outer peripheral formwork of the filler concrete 4 to be constructed later and to avoid being affected by waves during construction.
■ 内外の鋼板セル1,2が打設された後、鋼板セル1
,2間に複数本の杭3を打設する(第4図参照)。この
とき、内外の鋼板セル1,2は杭3のガイドとなり得る
。また、杭3の打設は鋼板セル1,2の打設に先立って
実施してもよい0
■ 次に内外の鋼板セル1,2間に所要の配筋を行なっ
た後、間詰コンクリート4を打設する(第5図参照)。■ After the inner and outer steel plate cells 1 and 2 are poured, steel plate cell 1
, drive multiple piles 3 between the two (see Figure 4). At this time, the inner and outer steel plate cells 1 and 2 can serve as guides for the pile 3. Furthermore, the driving of the piles 3 may be carried out prior to the driving of the steel plate cells 1 and 2. Next, after the required reinforcement is placed between the inner and outer steel plate cells 1 and 2, the filling concrete 4 is placed. (See Figure 5).
この施工は水中施工となる。なお、フーチング下面レベ
ルが水面以下の場合は鋼板セル1,2内の水位がフーチ
ング下面レベル以下になるまで水を排出する。このとき
、必要があればセル壁を補強するための支保工を設ける
。This construction will be carried out underwater. In addition, when the level of the bottom surface of the footing is below the water surface, water is drained until the water level in the steel plate cells 1 and 2 becomes below the level of the bottom surface of the footing. At this time, if necessary, provide support to reinforce the cell walls.
第8図のように内側の鋼板セル1の天端を外側の鋼板セ
ル2の天端と同一とした場合、間詰コンクリート4を鋼
板セル1,2の天端高さまで打設することによりセル内
の水を排出する際のセル壁の補強は不要となる。If the top of the inner steel plate cell 1 is the same as the top of the outer steel plate cell 2 as shown in Figure 8, by pouring filler concrete 4 up to the height of the top of the steel plate cells 1 and 2, the cell There is no need to reinforce the cell walls when draining the water inside.
■ 次に、フーチングコンクリート用の支保工、底型枠
を施工した上、フーチング用の配筋を行ない、フーチン
グコンクリート5の打設を行なう。■Next, after constructing the support for the footing concrete and the bottom formwork, the reinforcement for the footing is arranged, and the footing concrete 5 is placed.
第7図は前述の内側の鋼板セル1内に追加の杭3′を施
工した場合、第8図は内側の鋼板セル1の天端を外側の
鋼板セル2の天端と同一とした場合の実施例を示したも
のである。Figure 7 shows the case where an additional pile 3' is constructed inside the aforementioned inner steel plate cell 1, and Figure 8 shows the case where the top of the inner steel plate cell 1 is made the same as the top of the outer steel plate cell 2. This shows an example.
内外の鋼板セルが杭頭部固定用の間詰コンクリート打設
のだめの型枠となり、大規模な仮設備を必要とせず、施
工工程も簡略化されているため工期も短縮され経済的で
ある。The inner and outer steel plate cells serve as a formwork for pouring concrete to fix the pile head, and because large-scale temporary equipment is not required and the construction process is simplified, the construction period is shortened and economical.
また、杭頭部は間詰コンクリートに固定され、一体化し
ているため、杭に作用する曲げモーメントはそれほど大
きくならず、多柱基礎工法に比べ杭径を小さくすること
ができる。In addition, since the pile head is fixed and integrated with the filler concrete, the bending moment acting on the pile is not so large, and the pile diameter can be made smaller than in the multi-column foundation method.
さらに、内側の鋼板セル内への中詰めがないだめ、荷重
条件に対応して長円形その他任意の経済的な断面形状と
することができる。また断面形状により、水流に与える
影響等を小さくすることも可能である。Furthermore, as long as there is no filling in the inner steel plate cells, the cross-sectional shape can be oval or any other economical cross-sectional shape depending on the load conditions. Also, depending on the cross-sectional shape, it is possible to reduce the influence on water flow.
第1図(a)はこの発明の工法によって施工される水中
基礎の構造を示す正面図(右半分は断面図)第1図(b
)はそのI−I断面図、第2図は変形例を示す水中基礎
の横断面図、第3図〜第6図は施工手順を示す断面図、
第7図および第8図はそれぞれ他の実施例における断面
図である。
1.2・・鋼板セル、3・・杭
4・・間詰コンクリート、5・・フーチングコンクリー
ト、6・・水底地盤、7・・橋脚第1図
(a)
第2g
第3図 第4図
第5図 第6図
第 7 図
第 8 ス
手続補正書
11訃061年 3月 4日
特許庁長官 宇賀道部殿 、1
、 事件の表示
昭和61年2月26日提出の特許願(3)3、 補正を
する者
事件との関係 特許出願人
4、代理人
住 所 ■107東j諸都区赤坂6丁目5番21号
シャド−赤坂電話(586) 8741Figure 1 (a) is a front view (the right half is a sectional view) showing the structure of an underwater foundation constructed by the construction method of this invention.
) is an I-I cross-sectional view, Figure 2 is a cross-sectional view of an underwater foundation showing a modified example, Figures 3 to 6 are cross-sectional views showing the construction procedure,
FIG. 7 and FIG. 8 are sectional views of other embodiments, respectively. 1.2... Steel plate cell, 3... Pile 4... Filling concrete, 5... Footing concrete, 6... Underwater ground, 7... Pier Figure 1 (a) Figure 2g Figure 3 Figure 4 Figure 5 Figure 6 Figure 7 Figure 8 Written Amendment to Procedures 11 March 4, 20061 Mr. Michibu Uga, Commissioner of the Patent Office, 1
, Indication of the case Patent application filed on February 26, 1986 (3) 3. Person making the amendment Relationship to the case Patent applicant 4, agent address ■ 107 Higashij Shiroto-ku Akasaka 6-5-21 No. Shadow - Akasaka Telephone (586) 8741
Claims (2)
の鋼板セル間に打設された複数本の杭の頭部を前記内外
の鋼板セル間に間詰コンクリートを充填することにより
固定し、内側の鋼板セル内に水を残したまま、その水面
上に前記間詰コンクリートをつなぐフーチングコンクリ
ートを打設することにより、前記杭と内外の鋼板セルで
囲まれた筒状部およびその上部のフーチング部をコンク
リートで一体化することを特徴とする鋼板セルを用いた
水中基礎工法。(1) The heads of multiple piles driven between the inner and outer steel plate cells of a double steel plate cell concentrically rooted in the underwater ground are fixed by filling the space between the inner and outer steel plate cells with filler concrete. Then, while leaving water in the inner steel plate cell, footing concrete is placed on the water surface to connect the filler concrete, thereby forming a cylindrical part surrounded by the pile and the inner and outer steel plate cells and its upper part. An underwater foundation construction method using steel plate cells, which is characterized by integrating the footings with concrete.
範囲第1項記載の鋼板セルを用いた水中基礎工法。(2) An underwater foundation construction method using steel plate cells according to claim 1, wherein the inner and outer steel plate cells have an oval cross section.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4130486A JPS62202125A (en) | 1986-02-26 | 1986-02-26 | Underwater foundation work using steel plate shell |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4130486A JPS62202125A (en) | 1986-02-26 | 1986-02-26 | Underwater foundation work using steel plate shell |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS62202125A true JPS62202125A (en) | 1987-09-05 |
Family
ID=12604744
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP4130486A Pending JPS62202125A (en) | 1986-02-26 | 1986-02-26 | Underwater foundation work using steel plate shell |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS62202125A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002188159A (en) * | 2000-12-19 | 2002-07-05 | Kajima Corp | Execution method for underwater structure |
JP2010229747A (en) * | 2009-03-27 | 2010-10-14 | Penta Ocean Construction Co Ltd | Bottom foundation structure for ocean structure and method of constructing the same |
JP2010248734A (en) * | 2009-04-13 | 2010-11-04 | Jfe Steel Corp | Bridge pier foundation structure |
-
1986
- 1986-02-26 JP JP4130486A patent/JPS62202125A/en active Pending
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002188159A (en) * | 2000-12-19 | 2002-07-05 | Kajima Corp | Execution method for underwater structure |
JP4626052B2 (en) * | 2000-12-19 | 2011-02-02 | 鹿島建設株式会社 | Construction method for underwater structures |
JP2010229747A (en) * | 2009-03-27 | 2010-10-14 | Penta Ocean Construction Co Ltd | Bottom foundation structure for ocean structure and method of constructing the same |
JP2010248734A (en) * | 2009-04-13 | 2010-11-04 | Jfe Steel Corp | Bridge pier foundation structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP2837554A1 (en) | Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method | |
JP3423394B2 (en) | Underwater frame structure | |
AU2012313196B2 (en) | Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method | |
CN201588209U (en) | Self-balancing sinking tubular pile with large diameter | |
JPH06146305A (en) | Underwater foundation and installation method thereof | |
CN217517602U (en) | Nearly river dike underground structure | |
JPS62202125A (en) | Underwater foundation work using steel plate shell | |
CN211368726U (en) | Self-balancing support system for underwater excavation foundation pit | |
CN115467361A (en) | Offshore overhead transmission line foundation structure and construction method thereof | |
JPH056601B2 (en) | ||
JP3790451B2 (en) | Underwater foundation and installation method of underwater foundation | |
JPS59150810A (en) | Coastal structure with caisson and its construction | |
JPH09296427A (en) | Structure in water area and construction method thereof | |
JPS603308A (en) | Pile driving and connecting block work | |
JP2566414Y2 (en) | Breakwater structure | |
CN109356187A (en) | Analysis of Suspension Bridges ' Anchorage composite foundation and its construction method suitable for deep water soft clay area | |
CN217810967U (en) | Supporting structure adopting prefabricated section steel concrete square pile as stand column | |
JPS62202124A (en) | Underwater foundation work using steel plate shell | |
JP4231194B2 (en) | Revetment structure | |
KR102535841B1 (en) | Construction method of pier foundation using floating PC houses | |
CN212128811U (en) | Main tower artificial island structure of deep open sea suspension bridge | |
JP2764447B2 (en) | Ground structure such as pier support | |
JP3776751B2 (en) | Jacket structure | |
JP2953823B2 (en) | Construction method of offshore substructure | |
CN106836247B (en) | Combined cofferdam and construction method thereof |