WO2021111690A1 - 建築物の基礎構造、及びその施工方法 - Google Patents

建築物の基礎構造、及びその施工方法 Download PDF

Info

Publication number
WO2021111690A1
WO2021111690A1 PCT/JP2020/033581 JP2020033581W WO2021111690A1 WO 2021111690 A1 WO2021111690 A1 WO 2021111690A1 JP 2020033581 W JP2020033581 W JP 2020033581W WO 2021111690 A1 WO2021111690 A1 WO 2021111690A1
Authority
WO
WIPO (PCT)
Prior art keywords
foundation
building
shaped portion
ground
horizontal direction
Prior art date
Application number
PCT/JP2020/033581
Other languages
English (en)
French (fr)
Inventor
謹治 竹内
Original Assignee
株式会社タケウチ建設
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社タケウチ建設 filed Critical 株式会社タケウチ建設
Priority to US17/309,777 priority Critical patent/US11566394B2/en
Publication of WO2021111690A1 publication Critical patent/WO2021111690A1/ja

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • E02D3/123Consolidating by placing solidifying or pore-filling substances in the soil and compacting the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • E02D27/08Reinforcements for flat foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/26Compacting soil locally before forming foundations; Construction of foundation structures by forcing binding substances into gravel fillings
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/28Stressing the soil or the foundation structure while forming foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete

Definitions

  • the present invention relates to a ground improvement body in which the surface layer ground is improved, a foundation structure of a building including a foundation concrete placed on the ground improvement body at the site, and a construction method thereof.
  • the foundation structure of such a building is a simple structure that can suppress construction costs, suppress uneven settlement and improve the bearing capacity of the entire foundation, and prevent liquefaction of earth and sand during an earthquake due to the effect of enclosing the ground. It has features such as being effective for.
  • the shape of the lower surface of the foundation concrete located below the pillars of the building is square, and the shape of the foundation concrete is a rectangular shape (regular square columnar) (Patent). See the engaging convex portion 7a of FIG. 5 of Document 1 and the foundation 3 of the building of FIG. 1 of Patent Document 2).
  • the bottom surface of the foundation concrete located below the pillars of the building is a polygon of a square or more smaller than the plane shape of the foundation concrete.
  • the lower surface of the foundation concrete other than the bottom surface is an inclined surface connecting the bottom surface and the plane shape, and the inclination angle of the inclined surface from the horizontal plane is set to 20 ° or more and 40 ° or less (Patent Document 3). See the foundation concrete 3 in FIG. 2).
  • the stress transmitted to the lower ground can be reduced by the shape of the foundation concrete.
  • the amount of foundation concrete placed can be reduced, the construction cost can be reduced.
  • the inventor of the present application intends to further improve the foundation structure of the building of Patent Document 3 which exerts the above effect, and further reviews the shape of the foundation concrete located below the pillars of the building. It was.
  • the problem to be solved by the present invention is to transmit to the lower ground in the foundation structure of the building including the ground improvement body in which the surface layer ground is improved and the foundation concrete placed on the ground improvement body in the field, and the construction method thereof. Further improvements are made for the purpose of reducing the stress to be applied and reducing the amount of foundation concrete placed to reduce the construction cost.
  • the present invention provides the following basic structure of a building and a construction method thereof in order to solve the above problems.
  • the gist of the present invention is as follows.
  • the foundation concrete has an upper part and a lower part having different shapes.
  • the lower part A cross-sectional shape cut by a vertical plane including the first horizontal direction orthogonal to the horizontal direction connecting adjacent columns of a building, or
  • the cross-sectional shape cut by the vertical plane including the second horizontal direction orthogonal to the wall of the building is an inverted trapezoidal shape.
  • the upper part is formed from the side edge of the upper end in the cross-sectional shape of the lower part.
  • the brim-shaped portion protruding in the first horizontal direction, or A foundation structure of a building, characterized by having a collar-shaped portion projecting in the second horizontal direction.
  • the thickness of the brim-shaped portion is 0.05 m or more and 0.3 m or less.
  • the protruding length of the brim-shaped portion is 0.1 m or more and 0.6 m or less.
  • the foundation concrete is an independent foundation
  • the bottom surface of the lower portion is a polygon having a square or more smaller than the planar shape of the outer peripheral edge of the upper end of the lower portion.
  • the foundation concrete has an upper part and a lower part having different shapes.
  • the lower part A cross-sectional shape cut by a vertical plane including the first horizontal direction orthogonal to the horizontal direction connecting adjacent columns of a building, or
  • the cross-sectional shape cut by the vertical plane including the second horizontal direction orthogonal to the wall of the building is an inverted trapezoidal shape.
  • the upper part is formed from the side edge of the upper end in the cross-sectional shape of the lower part.
  • the brim-shaped portion protruding in the first horizontal direction, or It has a brim-shaped portion that protrudes in the second horizontal direction, and has a brim-shaped portion.
  • the construction method of the foundation structure of the building includes a ground improvement process, a foundation excavation process, and a foundation placing process.
  • the ground improvement process is It is a process of backfilling the soil dug down in the surface layer ground, adding and mixing the solidifying material, mixing and stirring, and then compacting to construct the ground improvement body.
  • the foundation excavation process The process of excavating the upper part of the ground improvement body located below the pillars of the building or below the walls of the building into the shape of the upper part of the foundation concrete to form the upper excavation part, and It is a step of excavating the lower part of the upper excavation part into the shape of the lower part of the foundation concrete to form the lower excavation part.
  • the foundation placing process is A structure of a foundation structure of a building, which is a step of placing discarded concrete in the lower excavation part, arranging foundation reinforcement in the upper excavation part and the lower excavation part, and placing the foundation concrete in the lower excavation part. Construction method.
  • the thickness of the brim-shaped portion is 0.05 m or more and 0.3 m or less.
  • the protruding length of the brim-shaped portion is 0.1 m or more and 0.6 m or less.
  • the foundation concrete placed on the site on the ground improvement body in which the surface layer ground is improved has an upper part and a lower part having different shapes.
  • the lower portion has an inverted trapezoidal cross-sectional shape
  • the upper portion has a collar-shaped portion protruding in the horizontal direction.
  • the range in which stress propagates from the foundation concrete to the lower ground is widened, so that the stress transmitted to the lower ground can be reduced and the volume is reduced, so that the amount of foundation concrete placed can be reduced. Since it can be reduced, the construction cost can be reduced.
  • the foundation concrete has the flange-shaped portion, the ground pressure at the end portion of the foundation concrete is dispersed when a moment load is applied to the foundation concrete, so that the foundation concrete acts on one end under the foundation concrete.
  • the maximum ground pressure to be applied can be reduced.
  • FIG. 1A is a cross-sectional view taken along the line X1-X1 of FIG. 1A. It is an enlarged view of the main part of FIG. 1B. It is a top view which shows the state which formed the upper excavation part and the lower part excavation part in the foundation excavation process in the ground improvement body formed in the ground improvement process in the construction method of the foundation structure of the building which concerns on Embodiment 1.
  • FIG. 3A It is sectional drawing of FIG. 3A. It is a top view which shows the model for ground FEM analysis. It is sectional drawing which shows the model for ground FEM analysis. It is a top view which shows the model for ground FEM analysis of the comparative example 1.
  • FIG. 3A shows the model for ground FEM analysis.
  • FIG. 11A is a cross-sectional view taken along the line X2-X2 of FIG. 11A. It is an enlarged view of the main part of FIG. 11B. It is a top view which shows the state which formed the upper excavation part and the lower part excavation part in the foundation excavation process in the ground improvement body formed in the ground improvement process in the construction method of the foundation structure of the building which concerns on Embodiment 5.
  • FIG. 13A is a cross-sectional view taken along the line X3-X3 of FIG. 13A.
  • FIG. 1A The plan view of FIG. 1A and the cross-sectional views of FIGS. 1B and 2 show the foundation structure 1 of the building according to the first embodiment of the present invention.
  • the foundation structure 1 of the building includes a ground improvement body 2 in which the surface layer ground G is improved and a foundation concrete 3 cast on the ground improvement body 2 at the site.
  • the foundation concrete 3 is an independent foundation and has an upper part 3A and a lower part 3B having different shapes.
  • the lower 3B of the foundation concrete 3 has an inverted trapezoidal cross-sectional shape cut by a vertical plane including the first horizontal direction O1 orthogonal to the horizontal direction connecting the adjacent columns 4 and 4 of the building.
  • the shape of the lower portion 3B of the foundation concrete 3 is an inverted quadrangular frustum.
  • the plane shape of the outer peripheral edge U1 at the upper end of the lower portion 3B is square.
  • the planar shape of the bottom surface BS1 of the lower portion 3B is a square smaller than the planar shape of the outer peripheral edge U1 at the upper end of the lower portion 3B.
  • the side surface S1 of the lower portion 3B is an inclined surface connecting the outer peripheral edge U1 at the upper end of the lower portion 3B and the outer peripheral edge V1 of the bottom surface BS1. It is a preferable embodiment that the inclination angle ⁇ of the side surface (the side surface having the inverted truncated cone shape) S1 which is an inclined surface from the horizontal plane is 20 ° ⁇ ⁇ ⁇ 40 °.
  • the upper portion 3A of the foundation concrete 3 has a collar-shaped portion F1 protruding in the first horizontal direction O1 from the upper end side edge M (outer peripheral edge U1) in the cross-sectional shape of the lower portion 3B.
  • the lower surface T1 of the flange-shaped portion F1 is a substantially horizontal plane.
  • the lower excavation portion 2B is excavated in an inverted quadrangular frustum shape so that the bottom surface BS2 becomes a square from the inner peripheral edge U2 by the amount of the protrusion length E of the flange-shaped portion F1 from the outer peripheral edge P of the lower end portion.
  • the lower excavation portion 2B is excavated in a rectangular parallelepiped shape to a predetermined depth by a backhoe or the like, that is, to the outer peripheral edge V2 of the bottom surface BS2 within the range of the horizontal width B3 and the vertical width W3 of FIG. 3A, and then the inverted quadrangular pyramid shown in FIG. Excavate so as to form the side surface S2 which is a trapezoidal inclined surface.
  • the upper part 3A of the foundation concrete 3 (range of height H1 in FIG. 2) has a rectangular parallelepiped shape
  • the lower part 3B of the foundation concrete 3 range of height H2 in FIG. 2 has an inverted quadrangular pyramid shape.
  • Comparative Example 1 in which the foundation concrete has a rectangular parallelepiped shape
  • Comparative Example 2 in which the upper part of the foundation concrete has a rectangular parallelepiped shape and the lower part has an inverted quadrangular pyramid shape, and the foundation concrete has a flange-shaped portion.
  • Example 1-5 which is the shape of the first embodiment of the present invention.
  • An analysis is performed on Examples 6-8 in which the ratio of the protrusion length E of F1 (E / H1) is changed.
  • An analysis is performed on Examples 9-13 in which the ratio of the protrusion length E (E / H1) is changed.
  • the analysis model of the embodiment is shown in the plan view of FIG. 4A and the sectional view of FIG. 4B, and the analysis model of Comparative Example 1 is shown in the plan view of FIG. 5A and the sectional view of FIG. 5B.
  • the analysis model of Comparative Example 2 corresponding to the structure is shown in the plan view of FIG. 6A and the cross-sectional view of FIG. 6B.
  • the ratio of the protruding length E of the collar-shaped portion F1 to the thickness H1 of the flange-shaped portion F1 which is the height of the upper portion 3A of the foundation concrete 3 (E / Let H1) be 2.
  • H1, H2, B2, W2, and E are as follows.
  • seismic force and wind power also act as short-term loads on buildings. Since seismic force and wind force act to sway the building sideways, horizontal force also acts on the building. As a result, in addition to the long-term load, horizontal force and moment load due to the short-term load act on the foundation structure.
  • the load conditions of the numerical analysis are load condition 1, which corresponds to a long-term load, load condition 2, which corresponds to a state in which a medium earthquake (horizontal acceleration: about 200 gal) occurs, and a large earthquake (horizontal acceleration: about 400 gal).
  • the load condition 3 corresponding to the above-mentioned state is set.
  • the ground pressure (point D) under the improved body of Comparative Example 1-2 and Example 1-5 is shown in the graph of FIG. 7A, and the amount of concrete of Comparative Example 1-2 and Example 1-5 is shown in FIG. 7B. It is shown in the graph of.
  • Example 1-5 the ground pressure under the improved body is smaller in Example 1-5 than in Comparative Example 1.
  • the ground pressure under the improved body is generally smaller in Example 1-5 than in Comparative Example 2 (under load condition 3, Comparative Example 2 is 96.8 kN / m 2 and Example 4 is 97.1 kN / m 2).
  • Example 5 is 97.7 kN / m 2 , which is slightly larger in Examples 4 and 5 than in Comparative Example 2).
  • the ground pressure under the improved body (D point), the loading conditions 1, Example 1 (97.6kN / m 2) is about 91% of Comparative Example 1 (106.8kN / m 2), Comparative Example 2 ( It is about 97% of 100.4kN / m 2).
  • the ground pressure (point D) under the improved body was such that under load condition 2, Example 1 (99.1 kN / m 2 ) was about 93% of Comparative Example 1 (106.4 kN / m 2 ), and Comparative Example 2 ( It is about 98% of 101.6kN / m 2).
  • Example 1 (94.9 kN / m 2 ) was about 91% of Comparative Example 1 (104.0 kN / m 2 ), and Comparative Example 2 ( It is about 98% of 96.8kN / m 2).
  • the reason why the ground pressure under the improved body can be reduced in the embodiment is that the stress propagates from the foundation concrete 3 to the lower ground in a wide range due to the shape of the foundation concrete 3 in the embodiment (FIGS. 4A and 4B). Therefore, it is considered that the stress transmitted to the lower ground can be reduced.
  • Example 1-5 As compared with Comparative Example 1-2.
  • the reason is that the volume of the foundation concrete 3 is reduced due to the shape of the foundation concrete 3 of Example 1-5 (FIGS. 4A and 4B).
  • Example 1 concrete of Example 1 (6.0 m 3) is about 42% of Comparative Example 1 (14.4 m 3), is about 69% of Comparative Example 2 (8.7m 3).
  • Comparative Example 1 without a brim-shaped portion is 188.4 kN / m 2
  • Comparative Example 1 without a brim-shaped portion is 188.4 kN / m 2
  • Comparative Example 1 without a brim-shaped portion is 188.4 kN / m 2.
  • 2 is as small as 173.7kN / m 2
  • Comparative Example 1 without a flange-shaped portion is 281.0 N / m 2
  • Comparative Example 1 without a flange-shaped portion is 281.0 N / m 2.
  • 2 is 313.0 N / m 2, which is larger in Comparative Example 2.
  • Example 1-5 having a flange-shaped portion, it was 288.7kN / m 2 to 252.4kN / m 2 , and in Example 1 (288.7kN / m 2 ), it was Comparative Example 1 (281.0N / m). Although slightly larger than 2), Example 2 (271.7kN / m 2 ) to Example 5 (252.4kN / m 2 ) are found in Comparative Example 1 (281.0N / m 2 ) and Comparative Example 2 (313.0N / m 2). 2 ) is smaller. In particular, Examples 1-5 are significantly smaller than Comparative Example 2.
  • Example 1 (288.7kN / m 2 ) is about 92% of Comparative Example 2 (313.0N / m 2 ), and Example 5 (252.4kN / m 2 ) is Comparative Example 2 (313.0N / m 2). ) Is about 81%.
  • Example 1-5 having a flange-shaped portion, it is possible to reduce the maximum ground pressure acting on one end under the foundation concrete 3 when a moment load is applied to the foundation concrete 3. .. It is considered that the reason is that the ground pressure at the end portion (point C) of the foundation concrete 3 is dispersed by providing the flange-shaped portion (for example, F1 in FIG. 4B).
  • Load conditions and evaluation items The load conditions 1-3 and the evaluation items are the same as in the first analysis.
  • FIG. 8A shows a graph in which the horizontal axis is E / H1 and the vertical axis is the contact pressure (point D) under the improved body
  • FIG. 9A is a graph in which the horizontal axis is E / H1 and the vertical axis is the constant amount.
  • Load conditions and evaluation items The load conditions 1-3 and the evaluation items are the same as in the first analysis.
  • FIG. 8B shows a graph in which the horizontal axis is E / H1 and the vertical axis is the contact pressure (point D) under the improved body
  • FIG. 9B is a graph in which the horizontal axis is E / H1 and the vertical axis is the constant amount.
  • the contact pressure (point D) under the improved body decreases under load conditions 1 and 2 as the ratio (E / H1) increases, that is, as the protrusion length E of the flange-shaped portion F1 increases, and under load condition 3. It can be seen that there is a slight increase.
  • the allowable proof stress of the flange-shaped portion F1 (beared by the reinforcing bar and concrete) is reduced, and if the protruding length E of the flange-shaped portion F1 is increased, the flange-shaped portion F1 The bearing stress (bending moment and shearing force) increases.
  • the range of the value of the thickness H1 of the flange-shaped portion F1 and the range of the value of the protruding length E of the flange-shaped portion F1 are limited.
  • the thickness H1 of the brim-shaped portion F1 is 0.05 m (for example, Example 8) or more and 0.3 m (for example, Example 5) or less. Further, it is a preferable embodiment that the protruding length E of the brim-shaped portion F1 is 0.1 m (for example, Example 9) or more and 0.6 m (for example, Example 5) or less.
  • the ratio (E / H1) of the protruding length E of the brim-shaped portion F1 to the thickness H1 of the brim-shaped portion F1 is 1 or more and 4 or less (for example, FIGS. 9A and 9B). In that case, the protruding length E of the flange-shaped portion F1 is in the range of 1 to 4 times the thickness H1 of the flange-shaped portion F1.
  • the upper part 3A has a rectangular parallelepiped shape and the lower part 3B has an inverted quadrangular pyramid shape.
  • the foundation concrete in the present invention is not limited to such a shape.
  • the foundation concrete 3 which is an independent foundation has an inverted trapezoidal shape cut by a vertical plane including the first horizontal direction O1 which is orthogonal to the horizontal direction connecting the adjacent columns 4 and 4 of the building, and has an inverted trapezoidal shape. Any one having a flange-shaped portion F1 protruding from the upper end side edge M in the cross-sectional shape in the first horizontal direction O1 may be used.
  • FIG. 10A The foundation concrete 3 in the foundation structure of the building according to the second embodiment of the present invention is shown in the perspective view of FIG. 10A.
  • the upper part 3A has an octagonal columnar shape and the lower part 3B has an inverted octagonal frustum shape.
  • the upper portion 3A is an octagonal columnar shape
  • the outer peripheral edge U1 at the upper end of the lower portion 3B is a regular octagon
  • the outer peripheral edge V1 of the bottom surface BS1 is a square.
  • the upper portion 3A is a hexadecagonal columnar
  • the outer peripheral edge U1 at the upper end of the lower end 3B is a regular hexadecagon
  • the outer peripheral edge V1 of the bottom surface BS1 is a square.
  • FIG. 11A and the cross-sectional views of FIGS. 11B and 12 show the basic structure 1 of the building according to the fifth embodiment of the present invention.
  • the foundation structure 1 of the building includes a ground improvement body 2 in which the surface layer ground G is improved and a foundation concrete 7 cast on the ground improvement body 2 at the site.
  • the foundation concrete 7 is a cloth foundation and has an upper part 7A and a lower part 7B having different shapes.
  • the lower portion 7B of the foundation concrete 7 has an inverted trapezoidal cross-sectional shape cut by a vertical plane including the second horizontal direction O2 orthogonal to the wall 8 of the building.
  • the inclination angle ⁇ of the side surface S1 of the inverted trapezoidal cross-sectional shape from the horizontal plane is 20 ° ⁇ ⁇ ⁇ 40 °.
  • the upper portion 7A of the foundation concrete 7 has a collar-shaped portion F2 protruding in the second horizontal direction O2 from the side edge M of the upper end in the cross-sectional shape of the lower portion 7B.
  • the lower lower excavation portion 2B is excavated from the inner peripheral edges U3 and U4 by the amount of the protrusion length E of the flange-shaped portion F2 from the lower end outer peripheral edges P1 and P2.
  • the reinforcing bars for the wall 8 are discarded and the reinforcing bars are arranged on the concrete 10, the foundation reinforcement is arranged in the upper excavation part 2A and the lower excavation part 2B, and the foundation concrete 7 is placed.
  • the foundation concrete 7 and the wall 8 are connected by reinforcing bars and become one.
  • the foundation concretes 3 and 7 placed on the site on the ground improvement body 2 in which the surface layer ground G is improved have different shapes. It has 3A, 7A and lower parts 3B, 7B.
  • the lower portions 3B and 7B have an inverted trapezoidal cross-sectional shape, and the upper portions 3A and 7A have flange-shaped portions F1 and F2 protruding in the horizontal direction.
  • the range in which the stress propagates from the foundation concretes 3 and 7 to the lower ground is widened, so that the stress transmitted to the lower ground can be reduced and the volume is reduced. Since the amount of casting of, 7 can be reduced, the construction cost can be reduced.
  • the foundation concretes 3 and 7 have the flange-shaped portions F1 and F2, the ground pressure at the ends of the foundation concretes 3 and 7 is dispersed when a moment load is applied to the foundation concretes 3 and 7. , The maximum ground pressure acting on one end under the foundation concretes 3 and 7 can be reduced.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Foundations (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

【課題】下部地盤へ伝達される応力を低減すること、及び基礎コンクリートの打設量を削減して施工コストを低減する。 【解決手段】表層地盤Gを改良した地盤改良体2及び地盤改良体2上に現場で打設した基礎コンクリート3を含む建築物の基礎構造1であって、建築物の柱4の下方に位置する基礎コンクート3は、形状の異なる上部3A及び下部3Bを有する。下部3Bは、建築物の隣り合う柱4,4間を結ぶ水平方向に直交する水平方向O1を含む鉛直面により切断した断面形状が逆台形状である。上部3Aは、下部3Bの前記断面形状における上端の側縁Mから第1水平方向O1へ突出する鍔状部F1を有する。

Description

建築物の基礎構造、及びその施工方法
 本発明は、表層地盤を改良した地盤改良体及び前記地盤改良体上に現場で打設した基礎コンクリートを含む建築物の基礎構造、及びその施工方法に関する。
 表層地盤を改良した地盤改良体及び前記地盤改良体上に現場で打設した基礎コンクリートを含む建築物の基礎構造がある(例えば、特許文献1ないし3参照)。このような建築物の基礎構造は、簡単な構造で施工コストが抑えられること、不同沈下を抑制できるとともに基礎全体の支持力を向上できること、及び地盤の囲い込み効果により地震時における土砂の液状化阻止に有効であること等の特徴を有する。
 特許文献1及び2の建築物の基礎構造は、建築物の柱の下方に位置する基礎コンクリートの下面の形状は正方形であり、前記基礎コンクリートの形状は直方体状(正四角柱状)である(特許文献1の図5の係合凸部7a、及び特許文献2の図1の建築物の基礎3参照)。
 特許文献3の建築物の基礎構造は、建築物の柱の下方に位置する基礎コンクリートの底面を、前記基礎コンクリートの平面形状よりも小さい四角以上の多角形としている。そして、前記基礎コンクリートの前記底面以外の下面を、前記底面と前記平面形状とを繋ぐ傾斜面とし、前記傾斜面の水平面からの傾斜角度を、20°以上40°以下にしている(特許文献3の図2の基礎コンクリート3参照)。
 特許文献3の建築物の基礎構造によれば、前記基礎コンクリートの形状により、下部地盤へ伝達される応力を低減できる。また、基礎コンクリートの打設量を削減できるので施工コストを低減できる。
特許第3608568号公報 特許第5494880号公報 特許第6436256号公報
 本願の発明者は、前記効果を奏する特許文献3の建築物の基礎構造に対して、より一層の改良を図ることを企図し、建築物の柱の下方に位置する基礎コンクリートの形状をさらに見直した。
 本発明が解決しようとする課題は、表層地盤を改良した地盤改良体及び前記地盤改良体上に現場で打設した基礎コンクリートを含む建築物の基礎構造、及びその施工方法において、下部地盤へ伝達される応力を低減すること、及び基礎コンクリートの打設量を削減して施工コストを低減することを目的として一層の改良を図ることである。
 本発明は、前記課題を解決するために、以下に示す建築物の基礎構造、及びその施工方法を提供する。
 本発明の要旨は以下のとおりである。
 〔1〕
 表層地盤を改良した地盤改良体及び前記地盤改良体上に現場で打設した基礎コンクリートを含む建築物の基礎構造であって、
 前記基礎コンクートは、形状の異なる上部及び下部を有し、
 前記下部は、
  建築物の隣り合う柱間を結ぶ水平方向に直交する第1水平方向を含む鉛直面により切断した断面形状、又は、
  建築物の壁に直交する第2水平方向を含む鉛直面により切断した断面形状
が逆台形状であり、
 前記上部は、前記下部の前記断面形状における上端の側縁から、
  前記第1水平方向へ突出する鍔状部、又は、
  前記第2水平方向へ突出する鍔状部
を有することを特徴とする、建築物の基礎構造。
 〔2〕
 前記鍔状部の厚みは、0.05m以上0.3m以下、
 前記鍔状部の突出長さは、0.1m以上0.6m以下であり、
 前記鍔状部の突出長さは、前記鍔状部の厚みに対して、1~4倍の範囲である、〔1〕に記載の建築物の基礎構造。
 〔3〕
 前記逆台形状の断面形状の側面の水平面からの傾斜角度は、20°以上40°以下である、〔1〕又は〔2〕に記載の建築物の基礎構造。
 〔4〕
 前記基礎コンクートは独立基礎であり、
 前記下部の底面は、前記下部の上端の外周縁の平面形状よりも小さい四角以上の多角形であり、
 前記下部の側面は、前記下部の上端の外周縁と前記底面の外周縁とを繋ぐ傾斜面である、〔1〕~〔3〕の何れかに記載の建築物の基礎構造。
 〔5〕
 表層地盤を改良した地盤改良体及び前記地盤改良体上に現場で打設した基礎コンクリートを含む建築物の基礎構造の施工方法であって、
 前記基礎コンクートは、形状の異なる上部及び下部を有し、
 前記下部は、
  建築物の隣り合う柱間を結ぶ水平方向に直交する第1水平方向を含む鉛直面により切断した断面形状、又は、
  建築物の壁に直交する第2水平方向を含む鉛直面により切断した断面形状
が逆台形状であり、
 前記上部は、前記下部の前記断面形状における上端の側縁から、
  前記第1水平方向へ突出する鍔状部、又は、
  前記第2水平方向へ突出する鍔状部
を有し、
 前記建築物の基礎構造の施工方法は、地盤改良工程と、基礎掘削工程と、基礎打設工程とを含み、
 前記地盤改良工程は、
  表層地盤を掘り下げた土を埋め戻し、固化材を添加混合しながら混合攪拌した後に締め固めて前記地盤改良体を構築する工程であり、
 前記基礎掘削工程は、
  建築物の柱の下方、又は建築物の壁の下方に位置する前記地盤改良体の上部を、前記基礎コンクートの上部の形状に掘削して上部掘削部を形成する工程、及び、
  前記上部掘削部の下方を、前記基礎コンクートの下部の形状に掘削して下部掘削部を形成する工程であり、
 前記基礎打設工程は、
  前記下部掘削部内に捨てコンクリートを打設し、前記上部掘削部及び前記下部掘削部内に基礎配筋を行って前記基礎コンクリートを打設する工程であることを特徴とする、建築物の基礎構造の施工方法。
 〔6〕
 前記鍔状部の厚みは、0.05m以上0.3m以下、
 前記鍔状部の突出長さは、0.1m以上0.6m以下であり、
 前記鍔状部の突出長さは、前記鍔状部の厚みに対して、1~4倍の範囲である、〔5〕に記載の建築物の基礎構造の施工方法。
 〔7〕
 前記逆台形状の断面形状の側面の水平面からの傾斜角度は、20°以上40°以下である、〔5〕又は〔6〕に記載の建築物の基礎構造の施工方法。
 以上における本発明に係る建築物の基礎構造、及びその施工方法によれば、表層地盤を改良した地盤改良体上に現場で打設した基礎コンクリートが、形状の異なる上部及び下部を有する。そして、前記下部は逆台形状の断面形状を有し、前記上部は水平方向へ突出する鍔状部を有する。
 前記基礎コンクリートの前記形状により、前記基礎コンクリートから下部地盤へ応力が伝搬する範囲が広くなるので、下部地盤へ伝達される応力を低減できるとともに、体積が小さくなることから基礎コンクリートの打設量を削減できるので施工コストを低減できる。
 その上、前記基礎コンクリートが前記鍔状部を有することから、前記基礎コンクリートにモーメント荷重が作用した際に前記基礎コンクリートの端部の接地圧が分散されるので、前記基礎コンクリート下の一端に作用する最大接地圧を小さくすることができる。
本発明の実施の形態1に係る建築物の基礎構造を示す平面図である。 図1Aの矢視X1-X1断面図である。 図1Bの要部拡大図である。 実施の形態1に係る建築物の基礎構造の施工方法において、地盤改良工程で形成した地盤改良体に基礎掘削工程で上部掘削部及び下部掘削部を形成した状態を示す平面図である。 図3Aの断面図である。 地盤FEM解析用モデルを示す平面図である。 地盤FEM解析用モデルを示す断面図である。 比較例1の地盤FEM解析用モデルを示す平面図である。 比較例1の地盤FEM解析用モデルを示す断面図である。 比較例2の地盤FEM解析用モデルを示す平面図である。 比較例2の地盤FEM解析用モデルを示す断面図である。 比較例1-2、実施例1-5の改良体下(D点)の接地圧を示すグラフである。 比較例1-2、実施例1-5のコンクリート量を示すグラフである。 E/H1(E=0.2m)による改良体下(D点)の接地圧の変化を示すグラフである。 E/H1(H1=0.1m)による改良体下(D点)の接地圧の変化を示すグラフである。 E/H1(E=0.2m)によるコンクリート量の変化を示すグラフである。 E/H1(H1=0.1m)によるコンクリート量の変化を示すグラフである。 本発明の実施の形態2に係る建築物の基礎構造における基礎コンクリートを下方から見た斜視図である。 本発明の実施の形態3に係る建築物の基礎構造における基礎コンクリートを下方から見た斜視図である。 本発明の実施の形態4に係る建築物の基礎構造における基礎コンクリートを下方から見た斜視図である。 本発明の実施の形態5に係る建築物の基礎構造を示す平面図である。 図11Aの矢視X2-X2断面図である。 図11Bの要部拡大図である。 実施の形態5に係る建築物の基礎構造の施工方法において、地盤改良工程で形成した地盤改良体に基礎掘削工程で上部掘削部及び下部掘削部を形成した状態を示す平面図である。 図13Aの矢視X3-X3断面図である。
 以下、本発明に係る実施の形態を図面に基づいて説明する。
[実施の形態1]
 図1Aの平面図、並びに図1B及び図2の断面図は、本発明の実施の形態1に係る建築物の基礎構造1を示している。
 建築物の基礎構造1は、表層地盤Gを改良した地盤改良体2及び地盤改良体2上に現場で打設した基礎コンクリート3を含む。
 基礎コンクート3は独立基礎であり、形状の異なる上部3A及び下部3Bを有する。
 基礎コンクート3の下部3Bは、建築物の隣り合う柱4,4間を結ぶ水平方向に直交する第1水平方向O1を含む鉛直面により切断した断面形状が逆台形状である。本実施の形態では、基礎コンクリート3の下部3Bの形状は、逆四角錐台状である。
 下部3Bの上端の外周縁U1の平面形状は正方形である。下部3Bの底面BS1の平面形状は、下部3Bの上端の外周縁U1の平面形状よりも小さい正方形である。下部3Bの側面S1は、下部3Bの上端の外周縁U1と底面BS1の外周縁V1とを繋ぐ傾斜面である。傾斜面である側面(前記逆円錐台状の断面形状の側面)S1の水平面からの傾斜角度αは、20°≦α≦40°とするのが好ましい実施態様である。
 基礎コンクート3の上部3Aは、下部3Bの前記断面形状における上端の側縁M(外周縁U1)から、第1水平方向O1へ突出する鍔状部F1を有する。鍔状部F1の下面T1は略水平面である。
 次に、建築物の基礎1の施工工程の一例を説明する。
<地盤改良工程>
(掘下げ工程)
 図1B及び図2に示す地表面GLから下側の表層地盤Gを、例えばバックホウによる鋤取り等により所要形状に掘り下げる。
(一次改良工程)
 次に、地盤改良体2の下部の形状である「口」字状に、アタッチメントとしてミキシングフォークを装着したバックホウ等により掘削し、セメント系固化材等の固化材を添加混合しながら混合攪拌し、重機及びローラー等により締め固めて地盤改良体2の下部を形成する一次改良工程を行う。
(二次改良工程)
 次に、前記掘下げ工程により掘り下げた土を、バックホウ等により地盤改良体2の下部の上側に埋め戻し、アタッチメントとしてミキシングフォークを装着したバックホウ等により、表層地盤Gを地表面GLから地盤改良体2上部の形状に掘削し、固化材を添加混合しながら混合攪拌し、重機及びローラー等により締め固めて地盤改良体2の上部を形成する二次改良工程を行う。
<基礎掘削工程>
(上部掘削部形成工程)
 次に、前記地盤改良工程で構築した地盤改良体2に対し、図3Aの平面図、及び図3Bの断面図に示すように、図1A及び図1B、並びに図2の鉄骨柱4の地上側部分の下方に位置する地盤改良体2の上部を、下端部外周縁Pの位置まで掘削して上部掘削部2Aを形成する。すなわち、図3Aの横幅B1、縦幅W1の範囲で、バックホウ等により所定深さである下面T2(図3B)の位置まで直方体状に掘削して上部掘削部2Aを形成する。
(下部掘削部形成工程)
 次に、下端部外周縁Pから鍔状部F1の突出長さEの分だけ内方の周縁U2から、底面BS2が正方形になるように逆四角錐台状に掘削して下部掘削部2Bを形成する。下部掘削部2Bは、例えば、図3Aの横幅B3、縦幅W3の範囲で、バックホウ等により所定深さまで、すなわち底面BS2の外周縁V2まで直方体状に掘削した後、図3Bに示す逆四角錐台状の傾斜面である側面S2を形成するように掘削する。
<基礎打設工程>
 次に、下部掘削部2B内に、図2に示す捨てコンクリート6を打設する。
 次に、鉄骨柱4固定用の柱脚アンカーボルトを捨てコンクリート6に固定し、上部掘削部2A及び下部掘削部2B内に基礎配筋を行って基礎コンクリート3を打設する。基礎コンクリート3の上部3A(図2の高さH1の範囲)は直方体状になり、基礎コンクリート3の下部3B(図2の高さH2の範囲)は逆四角錐台状になる。
 次に、鉄骨柱4を設置し、土間コンクリート5を打設する。
 以上の工程により、図1A及び図1Bに示す建築物の基礎(下部構造)1の施工が完了する。
<数値解析による効果確認>
 次に、効果確認のために行った数値解析について説明する。
(解析方法)
 地盤FEM(Finite Element Method)解析ソフトウェア(PLAXIS)を用いて数値解析を行う。
(1)第1の解析として、基礎コンクリートが直方体状である比較例1、基礎コンクリートの上部が直方体状で下部が逆四角錐台状である比較例2、及び基礎コンクリートが鍔状部を有する本発明の実施の形態1の形状である実施例1-5についての解析を行う。
(2)第2の解析として、本発明の実施の形態1の形状において、鍔状部F1の突出長さEを固定し(E=0.2m)、鍔状部F1の厚みH1に対する鍔状部F1の突出長さEの比(E/H1)を変化させた実施例6-8についての解析を行う。
(3)第3の解析として、本発明の実施の形態1の形状において、鍔状部F1の厚みH1を固定し(H1=0.1m)、鍔状部F1の厚みH1に対する鍔状部F1の突出長さEの比(E/H1)を変化させた実施例9-13についての解析を行う。
(実施例及び比較例の解析モデル)
 実施例の解析モデルを、図4Aの平面図及び図4Bの断面図に、比較例1の解析用モデルを、図5Aの平面図及び図5Bの断面図に、特許文献3の建築物の基礎構造に相当する比較例2の解析用モデルを、図6Aの平面図及び図6Bの断面図に示す。
<第1の解析>
(パラメータ)
(1)改良厚L=2.5m、二次改良厚J=1.0m、一次改良幅K=5.6mとする。
(2)基礎の高さH=0.9m、基礎の横幅B1=基礎の縦幅W1=4.0mとする。
(3)比較例2及び実施例1-5において、傾斜面S1(前記逆円錐台状の断面形状の側面)の水平面からの傾斜角度αを約30°とする。
(4)比較例2の基礎底面BS1の横幅B3=基礎底面BS1の縦幅W3=1.4mとする。
(5)実施例1-5の基礎底面BS1の横幅B3=基礎底面BS1の縦幅W3=0.8mとする。
(6)鍔状部F1を有する実施の形態1-5において、基礎コンクリート3の上部3Aの高さである鍔状部F1の厚みH1に対する鍔状部F1の突出長さEの比(E/H1)を2とする。
 H1、H2、B2、W2、Eを以下とする。
(1)比較例2:H1=0.2m、H2=0.7m
(2)実施例1:H1=0.1m、H2=0.8m、B2=W2=3.6m、E=0.2m
(3)実施例2:H1=0.15m、H2=0.75m、B2=W2=3.4m、E=0.3m
(4)実施例3:H1=0.2m、H2=0.7m、B2=W2=3.2m、E=0.4m
(5)実施例4:H1=0.25m、H2=0.65m、B2=W2=3.0m、E=0.5m
(6)実施例5:H1=0.3m、H2=0.6m、B2=W2=2.8m、E=0.6m
(荷重条件)
 特許文献3の建築物の基礎構造では、その効果を確認するために行った数値解析において、外力を、長期荷重である固定荷重及び積載荷重に相当する900kNの荷重のみとしている(特許文献3の[0025]参照)。
 建築物に対して、実際には、短期荷重として地震力や風力も作用する。地震力や風力は建築物を横に揺らすように作用するので、建築物には水平力も作用する。それにより、基礎構造には、長期荷重に加え、短期荷重による水平力及びモーメント荷重が作用する。
 そこで、当該数値解析の荷重条件は、長期荷重に相当する荷重条件1、中地震(水平加速度:200gal程度)が発生した状態に相当する荷重条件2、大地震(水平加速度:400gal程度)が発生した状態に相当する荷重条件3とする。
 すなわち、図4Aの平面図及び図4Bの断面図、図5Aの平面図及び図5Bの断面図、並びに図6Aの平面図及び図6Bの断面図に示す解析用モデルにおいて、基礎コンクリート3に作用する垂直荷重N及び水平荷重Qは、以下とする。
(1)荷重条件1:N=1100kN
(2)荷重条件2:N=1100kN、Q=220kN(I=3m)
(3)荷重条件3:N=1100kN、Q=440kN(I=3m)
(評価項目)
 図4B、図5B、及び図6Bに示す、基礎コンクリート3下のAないしC点の主応力(kN/m2)、及び地盤改良体2下のD点の接地圧(kN/m2)、並びに基礎コンクリート3の体積であるコンクリート量(m3)とする。
(解析結果)
 荷重条件1についての解析結果を表1に、荷重条件2についての解析結果を表2に、荷重条件3についての解析結果を表3に示す。
Figure JPOXMLDOC01-appb-T000001
Figure JPOXMLDOC01-appb-T000002
Figure JPOXMLDOC01-appb-T000003
 水平力及びモーメント荷重が作用しない荷重条件1の解析結果を示す表1において、荷重Nに対して対称である、基礎コンクリート下の主応力(B点)と基礎コンクリート下の主応力(C点)の値が異なっている。その理由は、地盤FEM解析ソフトウェアで解析領域のメッシュ分割を自動で作成した際に、B点まわりのメッシュとC点まわりにメッシュが対称になっていないことによる。B点の主応力とC点の主応力の差は1%以下であるので、問題のない解析精度であると考えられる。
 比較例1-2、及び実施例1-5の改良体下の接地圧(D点)を、図7Aのグラフに、比較例1-2、及び実施例1-5のコンクリート量を、図7Bのグラフに示す。
 図7Aのグラフから、改良体下の接地圧は、比較例1よりも実施例1-5の方が小さいことが分かる。また、改良体下の接地圧は、比較例2よりも実施例1-5の方が概ね小さい(荷重条件3では、比較例2は96.8kN/m2、実施例4は97.1kN/m2、実施例5は97.7kN/m2であり、比較例2よりも実施例4及び5の方が若干大きい)ことが分かる。
 例えば、改良体下の接地圧(D点)は、荷重条件1では、実施例1(97.6kN/m2)は、比較例1(106.8kN/m2)の約91%、比較例2(100.4kN/m2)の約97%である。また、改良体下の接地圧(D点)は、荷重条件2では、実施例1(99.1kN/m2)は、比較例1(106.4kN/m2)の約93%、比較例2(101.6kN/m2)の約98%である。さらに、改良体下の接地圧(D点)は、荷重条件3では、実施例1(94.9kN/m2)は、比較例1(104.0kN/m2)の約91%、比較例2(96.8kN/m2)の約98%である。
 このように実施例において、改良体下の接地圧を小さくできる理由は、実施例の基礎コンクリート3の形状(図4A及び図4B)により、基礎コンクリート3から下部地盤へ応力が伝搬する範囲が広くなるので、下部地盤へ伝達される応力を低減できるためであると考えられる。
 図7Bのグラフから、比較例1-2よりも実施例1-5の方がコンクリート量を少なくできることが分かる。その理由は、実施例1-5の基礎コンクリート3の形状(図4A及び図4B)により、基礎コンクリート3の体積が小さくなるためである。
 例えば、実施例1のコンクリート量(6.0m3)は、比較例1(14.4m3)の約42%、比較例2(8.7m3)の約69%である。
 荷重条件2及び3のように基礎コンクリート3に対して水平荷重Qが作用する場合、基礎コンクリート3にモーメント荷重が作用する。それにより、基礎コンクリート下の一端であるC点の主応力が大きくなり、C点に最大接地圧が作用する。
 例えば、荷重条件2である表2の基礎コンクリート下のC点の主応力について見ると、鍔状部が無い比較例1は188.4kN/m2であるのに対し、鍔状部が無い比較例2は173.7kN/m2と小さく、鍔状部がある実施例1-5では、172.5kN/m2ないし158.9kN/m2とさらに小さくなっている。
 また、荷重条件3である表3の基礎コンクリート下のC点の主応力について見ると、鍔状部が無い比較例1は281.0N/m2であるのに対し、鍔状部が無い比較例2は313.0N/m2と、比較例2の方が大きくなっている。
 それに対して、鍔状部が有る実施例1-5では、288.7kN/m2ないし252.4kN/m2であり、実施例1(288.7kN/m2)は、比較例1(281.0N/m2)よりも若干大きいが、実施例2(271.7kN/m2)ないし実施例5(252.4kN/m2)は、比較例1(281.0N/m2)及び比較例2(313.0N/m2)よりも小さい。特に、実施例1-5は、比較例2に対して大幅に小さくなっている。例えば、実施例1(288.7kN/m2)は、比較例2(313.0N/m2)の約92%、実施例5(252.4kN/m2)は、比較例2(313.0N/m2)の約81%である。
 以上のとおり、鍔状部が有る実施例1-5の基礎コンクリートによれば、基礎コンクリート3にモーメント荷重が作用した際に基礎コンクリート3下の一端に作用する最大接地圧を小さくすることができる。その理由は、鍔状部(例えば、図4BのF1)を設けることで、基礎コンクリート3の端部(C点)の接地圧が分散されるためであると考えられる。
<第2の解析>
(パラメータ)
(1)改良厚L=2.5m、二次改良厚J=1.0m、一次改良幅K=5.6mとする。
(2)基礎下部の高さH2=0.8m、基礎の横幅B1=基礎の縦幅W1=4.0mとする。
(3)B2=W2=3.6m、E=0.2mとする。
(4)傾斜面S1(前記逆円錐台状の断面形状の側面)の水平面からの傾斜角度αを約30°とする。
(5)基礎底面BS1の横幅B3=基礎底面BS1の縦幅W3=0.8mとする。
 H1、E/H1を以下とする。
(1)実施例6:H1=0.2m、E/H1=1
(2)実施例7:H1=0.15m、E/H1≒1.3
(3)実施例1:H1=0.1m、E/H1=2
(4)実施例8:H1=0.05m、E/H1=4
(荷重条件及び評価項目)
 荷重条件1-3、及び評価項目は、第1の解析と同じである。
(解析結果)
 解析結果を表4に示す。横軸をE/H1として縦軸を改良体下の接地圧(D点)としたグラフを図8Aに、横軸をE/H1として縦軸をコンリート量としたグラフを図9Aに示す。
Figure JPOXMLDOC01-appb-T000004
 鍔状部F1の突出長さEを固定し(E=0.2m)、鍔状部F1の厚みH1に対する鍔状部F1の突出長さEの比(E/H1)を変化させた場合、前記比(E/H1)が大きくなるほど、すなわち鍔状部F1の厚みH1が小さくなるほど、改良体下の接地圧(D点)及びコンクリート量が小さくなることが分かる。
<第3の解析>
(パラメータ)
(1)改良厚L=2.5m、二次改良厚J=1.0m、一次改良幅K=5.6mとする。
(2)基礎の高さH=0.9m、基礎上部の高さH1=0.1m、基礎下部の高さH2=0.8mとする。
(3)基礎の横幅B1=基礎の縦幅W1=4.0mとする。
(4)傾斜面S1(前記逆円錐台状の断面形状の側面)の水平面からの傾斜角度αを約30°とする。
 B2=W2、B3=W3、E、E/H1を以下とする。
(1)実施例9:B2=W2=3.8m、B3=W3=1.0m、E=0.1m、E/H1=1
(2)実施例10:B2=W2=3.7m、B3=W3=0.9m、E=0.15m、E/H1=1.5
(3)実施例1:B2=W2=3.6m、B3=W3=0.8m、E=0.2m、E/H1=2
(4)実施例11:B2=W2=3.5m、B3=W3=0.7m、E=0.25m、E/H1=2.5
(5)実施例12:B2=W2=3.4m、B3=W3=0.6m、E=0.3m、E/H1=3
(6)実施例13:B2=W2=3.2m、B3=W3=0.4m、E=0.4m、E/H1=4
(荷重条件及び評価項目)
 荷重条件1-3、及び評価項目は、第1の解析と同じである。
(解析結果)
 解析結果を表5に示す。横軸をE/H1として縦軸を改良体下の接地圧(D点)としたグラフを図8Bに、横軸をE/H1として縦軸をコンリート量としたグラフを図9Bに示す。
Figure JPOXMLDOC01-appb-T000005
 鍔状部F1の厚みH1を固定し(H1=0.1m)、鍔状部F1の厚みH1に対する鍔状部F1の突出長さEの比(E/H1)を変化させた場合、前記比(E/H1)が大きくなるほど、すなわち鍔状部F1の突出長さEが大きくなるほど、コンクリート量が小さくなることが分かる。
 改良体下の接地圧(D点)は、前記比(E/H1)が大きくなるほど、すなわち鍔状部F1の突出長さEが大きくなるほど、荷重条件1及び2では小さくなり、荷重条件3では若干増加する傾向であることが分かる。
<前記比(E/H1)についての考察>
 第2の解析、及び第3の解析により、鍔状部F1の厚みH1を小さくし、鍔状部F1の突出長さEを大きくすることにより、(E/H1)が大きくなり、それにより、改良体下の接地圧(D点)を小さくする効果、及びコンクリート量を小さくする効果があることが分かった。
 しかしながら、鍔状部F1の厚みH1を小さくすると、鍔状部F1の許容耐力(鉄筋とコンクリートが負担する)が小さくなり、鍔状部F1の突出長さEを大きくすると、鍔状部F1の負担応力(曲げモーメントとせん断力)が大きくなる。
 したがって、許容耐力よりも負担応力を小さくするために、鍔状部F1の厚みH1の値の範囲、及び鍔状部F1の突出長さEの値の範囲には制限がある。
 すなわち、鍔状部F1の厚みH1は、0.05m(例えば実施例8)以上0.3m(例えば実施例5)以下であるのが好ましい実施態様である。また、鍔状部F1の突出長さEは、0.1m(例えば実施例9)以上0.6m(例えば実施例5)以下であるのが好ましい実施態様である。
 鍔状部F1の厚みH1に対する鍔状部F1の突出長さEの比(E/H1)は、1以上4以下(例えば図9A及び図9B)にするのが好ましい実施態様である。その場合、鍔状部F1の突出長さEは、鍔状部F1の厚みH1に対して、1~4倍の範囲になる。
 実施の形態1における基礎コンクート3は、上部3Aが直方体状であり、下部3Bが逆四角錐台状である。本発明における基礎コンクリートは、このような形状に限定されない。
 独立基礎である基礎コンクリート3は、建築物の隣り合う柱4,4間を結ぶ水平方向に直交する第1水平方向O1を含む鉛直面により切断した断面形状が逆台形状であり、下部3Bの前記断面形状における上端の側縁Mから前記第1水平方向O1へ突出する鍔状部F1を有するものであればよい。
[実施の形態2]
 本発明の実施の形態2に係る建築物の基礎構造における基礎コンクリート3を、図10Aの斜視図に示す。
 図10Aの基礎コンクリート3は、上部3Aが八角柱状であり、下部3Bが逆八角錐台状である。
[実施の形態3]
 本発明の実施の形態3に係る建築物の基礎構造における基礎コンクリート3を、図10Bの斜視図に示す。
 図10Bの基礎コンクリート3は、上部3Aが八角柱状であり、下部3Bの上端の外周縁U1が正八角形であり、底面BS1の外周縁V1が正方形である。
[実施の形態4]
 本発明の実施の形態4に係る建築物の基礎構造における基礎コンクリート3を、図10Cの斜視図に示す。
 図10Cの基礎コンクリート3は、上部3Aが十六角柱状であり、下部3Bの上端の外周縁U1が正十六角形であり、底面BS1の外周縁V1が正方形である。
[実施の形態5]
 図11Aの平面図、並びに図11B及び図12の断面図は、本発明の実施の形態5に係る建築物の基礎構造1を示している。
 建築物の基礎構造1は、表層地盤Gを改良した地盤改良体2及び地盤改良体2上に現場で打設した基礎コンクリート7を含む。
 基礎コンクート7は布基礎であり、形状の異なる上部7A及び下部7Bを有する。
 基礎コンクート7の下部7Bは、建築物の壁8に直交する第2水平方向O2を含む鉛直面により切断した断面形状が逆台形状である。前記逆台形状の断面形状の側面S1の水平面からの傾斜角度αは、20°≦α≦40°とするのが好ましい実施態様である。
 基礎コンクート7の上部7Aは、下部7Bの前記断面形状における上端の側縁Mから、第2水平方向O2へ突出する鍔状部F2を有する。
 次に、建築物の基礎1の施工工程の一例を説明する。
<地盤改良工程>
(掘下げ工程)
 図11B及び図12に示す地表面GLから下側の表層地盤Gを、例えばバックホウによる鋤取り等により所要形状に掘り下げる。
(一次改良工程)
 次に、地盤改良体2の下部の形状である「口」字状に、アタッチメントとしてミキシングフォークを装着したバックホウ等により掘削し、セメント系固化材等の固化材を添加混合しながら混合攪拌し、重機及びローラー等により締め固めて地盤改良体2の下部を形成する一次改良工程を行う。
(二次改良工程)
 次に、前記掘下げ工程により掘り下げた土を、バックホウ等により地盤改良体2の下部の上側に埋め戻し、アタッチメントとしてミキシングフォークを装着したバックホウ等により、表層地盤Gを地表面GLから地盤改良体2上部の形状に掘削し、固化材を添加混合しながら混合攪拌し、重機及びローラー等により締め固めて地盤改良体2の上部を形成する二次改良工程を行う。
<基礎掘削工程>
(上部掘削部形成工程)
 次に、前記地盤改良工程で構築した地盤改良体2に対し、図13Aの平面図、及び図13Bの断面図に示すように、図11A及び図11B、並びに図12の壁8の下方に位置する地盤改良体2の上部を、下端部外周縁P1,P2の位置まで掘削して上部掘削部2Aを形成する。
(下部掘削部形成工程)
 次に、下端部外周縁P1,P2から鍔状部F2の突出長さEの分だけ内方の周縁U3,U4から、下方の下部掘削部2Bを掘削する。
<基礎打設工程>
 次に、下部掘削部2B内に、図12に示す捨てコンクリート10を打設する。
 次に、壁8用の鉄筋を捨てコンクリート10に配筋し、上部掘削部2A及び下部掘削部2B内に基礎配筋を行って基礎コンクリート7を打設する。
 次に、コンクリートである壁8を打設し、土間コンクリート9を打設する。基礎コンクート7と壁8とは鉄筋で接続されて一体になる。
 以上の工程により、図11A及び図11Bに示す建築物の基礎(下部構造)1の施工が完了する。
 以上のような本発明の実施の形態に係る建築物の基礎構造1によれば、表層地盤Gを改良した地盤改良体2上に現場で打設した基礎コンクリート3,7が、形状の異なる上部3A,7A及び下部3B,7Bを有する。そして、下部3B,7Bは逆台形状の断面形状を有し、上部3A,7Aは水平方向へ突出する鍔状部F1,F2を有する。
 基礎コンクリート3,7の前記形状により、基礎コンクリート3,7から下部地盤へ応力が伝搬する範囲が広くなるので、下部地盤へ伝達される応力を低減できるとともに、体積が小さくなることから基礎コンクリート3,7の打設量を削減できるので施工コストを低減できる。
 その上、基礎コンクリート3,7が前記鍔状部F1,F2を有することから、基礎コンクリート3,7にモーメント荷重が作用した際に基礎コンクリート3,7の端部の接地圧が分散されるので、基礎コンクリート3,7下の一端に作用する最大接地圧を小さくすることができる。
 以上の実施の形態の記載はすべて例示であり、これに制限されるものではない。本発明の範囲から逸脱することなく種々の改良及び変更を施すことができる。
1 建築物の基礎構造
2 地盤改良体
2A 上部掘削部
2B 下部掘削部
3 基礎コンクリート(独立基礎)
3A 上部
3B 下部
4 鉄骨柱
5 土間コンクリート
6 捨てコンクリート
7 基礎コンクリート(布基礎)
7A 上部
7B 下部
8 壁
9 土間コンクリート
10 捨てコンクリート
B1 基礎の横幅
B2 下部上端部の横幅
B3 基礎底面の横幅
BS1,BS2 底面
E 鍔状部の突出長さ
F1,F2 鍔状部
G 表層地盤
GL 地表面
H 基礎の高さ
H1 上部の高さ(鍔状部の厚み)
H2 下部の高さ
J 二次改良厚
K 一次改良幅
L 改良厚
M 下部の上端の側縁
O1 柱間を結ぶ水平方向に直交する水平方向
O2 壁に直交する水平方向
P,P1,P2 下端部外周縁
S1,S2 側面
T1,T2 下面
U1 下部の上端の外周縁(上部の下端部外周縁よりも内方の周縁)
U2 下部掘削部の上端縁(上部掘削部の下端部外周縁よりも内方の周縁)
U3,U4 周縁
V1 底面の外周縁
V2 下部掘削部の底面の外周縁
W1 基礎の縦幅
W2 下部上端部の縦幅
W3 基礎底面の縦幅
α 傾斜面である側面の水平面からの傾斜角度
 

Claims (7)

  1.  表層地盤を改良した地盤改良体及び前記地盤改良体上に現場で打設した基礎コンクリートを含む建築物の基礎構造であって、
     前記基礎コンクートは、形状の異なる上部及び下部を有し、
     前記下部は、
      建築物の隣り合う柱間を結ぶ水平方向に直交する第1水平方向を含む鉛直面により切断した断面形状、又は、
      建築物の壁に直交する第2水平方向を含む鉛直面により切断した断面形状
    が逆台形状であり、
     前記上部は、
      前記下部の前記断面形状における上端の側縁から、
       前記第1水平方向へ突出する鍔状部、又は、
       前記第2水平方向へ突出する鍔状部
    を有することを特徴とする、
    建築物の基礎構造。
  2.  前記鍔状部の厚みは、0.05m以上0.3m以下、
     前記鍔状部の突出長さは、0.1m以上0.6m以下であり、
     前記鍔状部の突出長さは、前記鍔状部の厚みに対して、1~4倍の範囲である、
    請求項1に記載の建築物の基礎構造。
  3.  前記逆台形状の断面形状の側面の水平面からの傾斜角度は、20°以上40°以下である、
    請求項1又は2に記載の建築物の基礎構造。
  4.  前記基礎コンクートは独立基礎であり、
     前記下部の底面は、前記下部の上端の外周縁の平面形状よりも小さい四角以上の多角形であり、
     前記下部の側面は、前記下部の上端の外周縁と前記底面の外周縁とを繋ぐ傾斜面である、
    請求項1~3の何れか1項に記載の建築物の基礎構造。
  5.  表層地盤を改良した地盤改良体及び前記地盤改良体上に現場で打設した基礎コンクリートを含む建築物の基礎構造の施工方法であって、
     前記基礎コンクートは、形状の異なる上部及び下部を有し、
     前記下部は、
      建築物の隣り合う柱間を結ぶ水平方向に直交する第1水平方向を含む鉛直面により切断した断面形状、又は、
      建築物の壁に直交する第2水平方向を含む鉛直面により切断した断面形状
    が逆台形状であり、
     前記上部は、
      前記下部の前記断面形状における上端の側縁から、
       前記第1水平方向へ突出する鍔状部、又は、
       前記第2水平方向へ突出する鍔状部
    を有し、
     前記建築物の基礎構造の施工方法は、地盤改良工程と、基礎掘削工程と、基礎打設工程とを含み、
     前記地盤改良工程は、
      表層地盤を掘り下げた土を埋め戻し、固化材を添加混合しながら混合攪拌した後に締め固めて前記地盤改良体を構築する工程であり、
     前記基礎掘削工程は、
      建築物の柱の下方、又は建築物の壁の下方に位置する前記地盤改良体の上部を、前記基礎コンクートの上部の形状に掘削して上部掘削部を形成する工程、及び、
      前記上部掘削部の下方を、前記基礎コンクートの下部の形状に掘削して下部掘削部を形成する工程であり、
     前記基礎打設工程は、
      前記下部掘削部内に捨てコンクリートを打設し、前記上部掘削部及び前記下部掘削部内に基礎配筋を行って前記基礎コンクリートを打設する工程であることを特徴とする、
    建築物の基礎構造の施工方法。
  6.  前記鍔状部の厚みは、0.05m以上0.3m以下、
     前記鍔状部の突出長さは、0.1m以上0.6m以下であり、
     前記鍔状部の突出長さは、前記鍔状部の厚みに対して、1~4倍の範囲である、
    請求項5に記載の建築物の基礎構造の施工方法。
  7.  前記逆台形状の断面形状の側面の水平面からの傾斜角度は、20°以上40°以下である、
    請求項5又は6に記載の建築物の基礎構造の施工方法。
PCT/JP2020/033581 2019-12-02 2020-09-04 建築物の基礎構造、及びその施工方法 WO2021111690A1 (ja)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US17/309,777 US11566394B2 (en) 2019-12-02 2020-09-04 Building foundation structure, and construction method therefor

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2019218035A JP6868301B1 (ja) 2019-12-02 2019-12-02 建築物の基礎構造、及びその施工方法
JP2019-218035 2019-12-02

Publications (1)

Publication Number Publication Date
WO2021111690A1 true WO2021111690A1 (ja) 2021-06-10

Family

ID=75801818

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2020/033581 WO2021111690A1 (ja) 2019-12-02 2020-09-04 建築物の基礎構造、及びその施工方法

Country Status (3)

Country Link
US (1) US11566394B2 (ja)
JP (1) JP6868301B1 (ja)
WO (1) WO2021111690A1 (ja)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0270830A (ja) * 1988-09-02 1990-03-09 Kanegafuchi Chem Ind Co Ltd 建築物の基礎構造
JP2004060290A (ja) * 2002-07-30 2004-02-26 Konguro Engineering Kk 安定材付きベタ基礎工法
JP2008280828A (ja) * 2007-04-12 2008-11-20 Kinji Takeuchi 地盤改良体及びべた基礎からなる建築物の基礎の構造並びに地盤改良べた基礎工法
JP2009174181A (ja) * 2008-01-24 2009-08-06 Konguro Engineering Kk 基礎の施工方法
JP2018021418A (ja) * 2016-08-05 2018-02-08 鹿島建設株式会社 基礎構造物及び基礎構造物の施工方法
JP2018091047A (ja) * 2016-12-03 2018-06-14 糸井 元保 人工地盤及びその構築方法
JP6436256B1 (ja) * 2017-07-04 2018-12-12 株式会社タケウチ建設 建築物の基礎構造、及びその施工方法

Family Cites Families (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2215773A (en) * 1933-08-21 1940-09-24 Workman James Minor Building construction
US2374624A (en) * 1942-02-24 1945-04-24 Ethel F Schwendt Precast foundation
JPS608568B2 (ja) 1980-09-16 1985-03-04 株式会社明電舎 真空機器の製造方法
US4918891A (en) * 1987-05-12 1990-04-24 U.M.C., Inc. Precast concrete foundation elements and system and method of using same
GB9117337D0 (en) * 1991-08-10 1991-09-25 Roxbury Ltd Improvements in or relating to supports for building structures
US5746036A (en) * 1995-07-10 1998-05-05 Angelette; A. M. Railroad crossing signal foundation and spider and method of producing the same
US6431797B2 (en) * 1999-06-14 2002-08-13 Pyramid Retaining Walls, Llc Masonry retainer wall system and method
JP3608568B1 (ja) 2003-11-12 2005-01-12 謹治 竹内 地盤改良体及びべた基礎からなる建築物の基礎の構造並びに地盤改良べた基礎工法
US7302778B2 (en) * 2004-03-01 2007-12-04 Macmillan James Construction support assembly
KR100851837B1 (ko) * 2007-12-28 2008-08-13 문형록 수직 측면부를 갖는 팽이말뚝집합체용기를 이용한 지반보강공법
RU2379425C1 (ru) * 2008-08-14 2010-01-20 Федеральное государственное образовательное учреждение высшего профессионального образования Кубанский государственный аграрный университет Способ возведения свайно-плитного фундамента
EP2541059A2 (en) * 2011-06-28 2013-01-02 Gamesa Innovation & Technology, S.L. Footing for wind turbine towers
US8955276B2 (en) * 2012-01-25 2015-02-17 Steven James Wall Raised flooring apparatus and system
PT2886723T (pt) * 2012-06-06 2017-06-08 Gestamp Hybrid Towers S L Fundação nervurada para superestruturas e método para produção da fundação
JP5494880B1 (ja) 2013-09-26 2014-05-21 株式会社タケウチ建設 液状化対策基礎構造体及び液状化対策工法
US11085165B2 (en) * 2018-04-19 2021-08-10 RRC Power & Energy, LLC Post-tension tube foundation and method of assembling same
ES2701605A1 (es) * 2018-12-03 2019-02-25 Hws Concrete Towers S L Cimentacion para torres eolicas

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0270830A (ja) * 1988-09-02 1990-03-09 Kanegafuchi Chem Ind Co Ltd 建築物の基礎構造
JP2004060290A (ja) * 2002-07-30 2004-02-26 Konguro Engineering Kk 安定材付きベタ基礎工法
JP2008280828A (ja) * 2007-04-12 2008-11-20 Kinji Takeuchi 地盤改良体及びべた基礎からなる建築物の基礎の構造並びに地盤改良べた基礎工法
JP2009174181A (ja) * 2008-01-24 2009-08-06 Konguro Engineering Kk 基礎の施工方法
JP2018021418A (ja) * 2016-08-05 2018-02-08 鹿島建設株式会社 基礎構造物及び基礎構造物の施工方法
JP2018091047A (ja) * 2016-12-03 2018-06-14 糸井 元保 人工地盤及びその構築方法
JP6436256B1 (ja) * 2017-07-04 2018-12-12 株式会社タケウチ建設 建築物の基礎構造、及びその施工方法

Also Published As

Publication number Publication date
JP6868301B1 (ja) 2021-05-12
JP2021088817A (ja) 2021-06-10
US11566394B2 (en) 2023-01-31
US20220042271A1 (en) 2022-02-10

Similar Documents

Publication Publication Date Title
KR100722665B1 (ko) 지하연속벽 시공을 위한 스틸 가이드 월과 이를 이용한지하연속벽 시공방법
JP6343727B1 (ja) 自立式擁壁及び連結ブロック
JP2003064657A (ja) 軟弱地盤改良工法
JP2021063404A (ja) 既存岸壁の改良構造及び改良方法
JP2000352296A (ja) 地下構造物直下の通路の形成方法
WO2021111690A1 (ja) 建築物の基礎構造、及びその施工方法
JP2007009421A (ja) 構造物の基礎構造
JP2012026250A (ja) 既存擁壁の補強構造及び補強工法
CN112627249B (zh) 一种用于浅基础加固的施工方法
JP6436256B1 (ja) 建築物の基礎構造、及びその施工方法
JP5739051B1 (ja) 地盤改良ベタ基礎の液状化対策構造、及び液状化による不同沈下発生の修正方法
CN210797681U (zh) 一种钢筋混泥土基础承台加固结构
JP6017302B2 (ja) 構築物及びその構築方法
TW201741529A (zh) 連續壁施工前防止工地下陷的先行鋪面的施工方法
JP2008150859A (ja) 地盤段差部の補強構造
JP2009275358A (ja) 建物支持地盤の改良構造と施工方法
CN220908416U (zh) 一种基坑临时围护结构
JP2004132124A (ja) ニューマチックケーソン及びニューマチックケーソン工法
KR102443020B1 (ko) 겹침주열말뚝벽체를 이용한 교량 시공방법 및 겹침주열말뚝벽체를 이용한 교량
JP2017186760A (ja) 杭基礎構造
JP2010121372A (ja) 既存杭と既存基礎とを利用した新設構造物の構造および既存杭と既存基礎とを利用した新設構造物の構築方法
CN105604180B (zh) 一种地下建筑物的施工方法
JP2022108444A (ja) 既設護岸の補強方法
JP2023102736A (ja) 小断面の地中連続壁
JP6482207B2 (ja) 建物基礎構造

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 20895732

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 20895732

Country of ref document: EP

Kind code of ref document: A1