WO2017088117A1 - 桥梁上部结构施工使用的升降式施工系统及其施工方法 - Google Patents

桥梁上部结构施工使用的升降式施工系统及其施工方法 Download PDF

Info

Publication number
WO2017088117A1
WO2017088117A1 PCT/CN2015/095505 CN2015095505W WO2017088117A1 WO 2017088117 A1 WO2017088117 A1 WO 2017088117A1 CN 2015095505 W CN2015095505 W CN 2015095505W WO 2017088117 A1 WO2017088117 A1 WO 2017088117A1
Authority
WO
WIPO (PCT)
Prior art keywords
steel
truss
shelf
trolley
construction
Prior art date
Application number
PCT/CN2015/095505
Other languages
English (en)
French (fr)
Inventor
陈修缘
Original Assignee
陈修缘
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 陈修缘 filed Critical 陈修缘
Priority to PCT/CN2015/095505 priority Critical patent/WO2017088117A1/zh
Publication of WO2017088117A1 publication Critical patent/WO2017088117A1/zh

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Definitions

  • the invention relates to a civil construction method used for construction of a bridge upper structure, in particular to a support lifting construction system used for construction of a bridge upper structure and a construction method thereof.
  • the conventional bridge construction method is that the space under the bridge is covered with a support frame under the bridge upper structure, and the support frame needs to be assembled from the ground up to the height, in the disassembly and assembly of the support frame and the formwork.
  • the mobile crane At each stage of the equipment, it is necessary to rely on the mobile crane to disassemble and assemble.
  • the construction personnel need to be located at a high place to disassemble the assembly work, and the same is true when dismantling.
  • a conventional bridge construction method for the superstructure of the bridge is provided by pre-laying the brackets of the bridge piers or the cap beams, and then using the mobile crane or the loading device to drive the main beam work vehicle. Completed and dismantled. When propelling, the mounting bracket must be installed before the next pier or cap beam. The installation must rely on the mobile crane to assemble and assemble. The construction personnel should be located at a high place to disassemble the assembly work, and the same when dismantling.
  • the conventional two-building bridge superstructure civil construction method has the following disadvantages:
  • the construction workers need to be exposed to the high-altitude operation.
  • the mobile crane is required to cooperate with the construction, and the same is also carried out when dismantling.
  • brackets for each pier column when installing the brackets for each pier column, the construction personnel should be exposed to high-altitude operations, and the mobile cranes should be used in conjunction with the construction.
  • the present inventors have developed and designed the present invention in view of the many shortcomings and inconveniences caused by the unfinished design of the existing bridge superstructure construction system.
  • the object of the present invention is to provide a lifting type construction system and a construction method thereof, which can reduce the use of the support frame and eliminate the need for a closed road, and can improve the safety of the bridge upper structure construction.
  • the solution of the present invention is:
  • a supporting lifting type construction system used for bridge superstructure construction comprising a plurality of inner mold working trolleys, two flexing and extending steel templates, two main beam supporting truss working vehicles, two steel frame supporting frames, four hydraulic lifting devices,
  • the plurality of inner mold work trolleys are located above the bottom plate of the superposed bridge upper structure, and comprise an upper and lower moving steel formwork and a laterally moving steel formwork;
  • the hydraulic lifting device is assembled and fixed around the bridge pier and is disposed on the steel
  • the hydraulic lifting device drives the steel frame support frame to support the main beam support truss work vehicle ascending and descending, and the two steel frame support frame is arranged around the bridge pier pillars to be constructed before and after, steel
  • the steel frame support frame is lowered and constructed by cyclic construction.
  • the inner mold working table is provided with a telescopic oil pressure rod driving steel template; the inner mold working trolley is provided with a moving roller for moving the inner mold working trolley to the positioning; a hydraulic jack is arranged under the inner mold working trolley; The inner mold work trolley is used for forming the upper structure web and the roof concrete of the bridge.
  • the two-push-out steel formwork and the two-main beam support truss work vehicle are steel formwork devices for the upper structure of the bridge, and the fixed-type trolley and the mobile trolley under the work of the flex-extension steel formwork and the main beam support truss work vehicle;
  • the hydraulic telescopic rod controls the upward flexion and the downward extension to be flattened above the main beam support truss;
  • the main beam support truss work vehicle uses the hydraulic telescopic rod to control the inward propulsion and outward push movement, and when moving to the positioning, the bolt is used. Positioning.
  • the steel frame support frame is divided into a trolley frame, a channel shelf and a pedestal shelf, and each shelf is divided into an A unit and a B unit, and the A and B units are corresponding modularized frames.
  • the joint joints of the A and B unit steel beams are provided with joint substrates and bolted and joined.
  • the channel pedals, the platform and the upper and lower stairs of the steel frame support frame are joined by bolts and bolts, and the steel frame support frame and the pier are provided with rollers. Keep the spacing.
  • the four hydraulic lifting device is disposed between the steel frame support frame and the pier column, and each hydraulic lifting device provides a power source for lifting and lowering the steel frame support frame, and the hydraulic pressure lifting device is supported by four or more array hydraulic presses, A lifting control box, four or more lifting supports, four or a plurality of anti-slip brake devices; when the steel frame support frame is lifted, four or more hydraulic presses are controlled by the lifting control box to simultaneously act.
  • the utility model relates to a construction method of a supporting lifting type construction system used for construction of a bridge superstructure.
  • the construction system is located at the ground part during assembly, and the hydraulic pressure lifting device is first assembled to connect the fixing rod to the periphery of the completed concrete pier column.
  • the A and B units of the car frame are pushed by the corresponding horizontal sides to be bolted, and the mobile trolley and the fixed trolley are assembled above the shelf.
  • the flexural and extension steel formwork equipment and the main beam support truss work vehicle are on the ground.
  • the assembly is completed, and the hoisting is combined with the mobile trolley.
  • the invention When the invention rises, it is located at the ground part, first raises the lifting support of the hydraulic lifting device to a certain height, and is connected and fixed with the steel frame support frame, and the hydraulic frame lifting frame is raised by the lifting control box operating the hydraulic lifting device To positioning.
  • the channel shelf A unit and the B unit are pushed into the channel shelf by the mobile device by the corresponding sides of the ground level and are bolted.
  • the trolley frame is lowered and combined with the channel shelf to be bolted.
  • the grounding portion is operated, and the lifting support of the hydraulic lifting device is first raised to a certain height, and is connected and fixed to the steel frame support frame, and the bolts for connecting the upper and lower shelves and the left and right shelves are removed, and the oil pressure is raised and lowered.
  • the equipment operation is lifted up by 5 cm to separate the upper and lower shelves, and the shelf is pulled out and removed by using the mobile device.
  • the hydraulic lifting device system starts to descend to the falling frame support frame to the ground.
  • the pedestal shelf is removed, and the descending steel frame support frame is moved to the highest position of the main beam support truss work vehicle and the cap beam without interference height, and the front truss is extended forward to a certain length.
  • a lifting construction method used for construction of a bridge superstructure comprising:
  • the above step A includes:
  • Step a1 the oil pressure lifting device is assembled and fixed around the pier column by connecting the fixing rod;
  • Step a2 moving into the A unit and the B unit of the trolley shelf at corresponding positions, and the corresponding joint substrate is bolted;
  • Step a3 hoisting the fixed trolley and the mobile trolley above the trolley shelf on the trolley guide rail;
  • Step a4 hoisting the support truss to the corresponding mobile trolley, and connecting the adjacent pitch telescopic hydraulic pressure rod;
  • Step a5 lifting the main beam supporting the truss work trolley to the corresponding mobile trolley, connecting the main beam supporting the truss telescopic hydraulic pressure rod;
  • Step a6 installing a template beam on the support truss and the main beam support gantry workbench;
  • Step a7 lifting the bent steel form to the top of the formwork beam, connecting the center support;
  • Step a8 test drive
  • Step a9 raising the lifting support of the hydraulic lifting device to a certain height, connecting and fixing with the steel beam of the trolley frame;
  • Step a10 The hydraulic lifting device raises and positions the trolley shelf from bottom to top, and the A unit and the B unit pushed into the channel shelf by the simple moving equipment on both sides of the ground level are bolted and bonded to the substrate.
  • the falling trolley shelf is combined with the channel shelf to lock the substrate by bolts;
  • Step a11 the operation contents of the steps a9 and a10 are cycled until the pedestal shelf is installed to raise the main beam supporting truss working vehicle to the construction positioning;
  • Step a12 measurement and elevation adjustment
  • Step a13 using the hydraulic jack below the pedestal shelf to adjust the elevation.
  • the above step B includes:
  • Step b1 tying the upper structural floor steel bar and the web reinforcement bar above the upper structural steel formwork;
  • Step b2 pouring the concrete of the upper structure floor and the concrete of the web to a height of 30 cm;
  • Step b3 concrete curing
  • Step b4 hoisting and installing the positioning inner mold working trolley
  • Step b5 measurement and elevation adjustment
  • Step b6 adjusting the elevation by using the hydraulic jack under the inner mold working trolley;
  • Step b7 tying the top plate steel of the upper structure and installing the necessary application components
  • Step b8 pouring the upper structure web concrete and the roof concrete
  • Step b9 concrete curing
  • Step b10 demoulding the hydraulic jack under the descending pedestal shelf
  • Step b11 raising the lifting support of the hydraulic lifting device to a certain height, connecting and fixing with the channel beam steel beam;
  • Step b12 removing the joint substrate bolt between the upper channel shelf and the pedestal shelf, and the base layer frame A unit and the B unit bonding substrate bolt, and the hydraulic lifting device rises by 5 cm;
  • Step b13 using a simple mobile device to pull out the A unit and the B unit of the pedestal shelf in the opposite direction of the ground level;
  • Step b14 descending the channel shelf to contact with the ground
  • Step b15 separating the lifting beam and the steel beam connection of the channel shelf, and pushing the space between the bridge piers at a horizontal angle of 90 degrees.
  • the above step C includes:
  • Step c1 The supporting truss is connected with the pitch telescopic oil pressure rod to the main beam supporting truss working vehicle to connect with the bolt, and the flexing and extending steel template is supported by the steel mold to flex the telescopic oil pressure rod upward, and the pitch expansion and contraction oil rod is matched. The action causes the steel form to bend upwards;
  • Step c2 the main beam supporting the truss working vehicle and the supporting truss to connect the main beam supporting truss telescopic hydraulic rod of the mobile trolley below the main beam supporting truss working vehicle to the outside to the position, and all the moving trolleys are fixed by the bolt;
  • Step c3 removing the moving latches of the front and rear leading trusses, and the rear leading truss and the positioning rod are fixed by bolts;
  • Step c4 The front truss front hydraulic pressure device pushes the leading truss forward to the position and is fixed by the bolt;
  • Step c5 propelling the main beam supporting truss working vehicle and the supporting truss with the main beam supporting truss front hydraulic pressure device, and moving to the positioning by the longitudinal propulsion roller on the mobile trolley and the fixed trolley;
  • Step c6 After the current guide truss and the next span steel frame support frame are connected, the front truss and the positioning rod are fixed by a pin connection, and the plug connection of the rear front guide truss and the positioning rod is removed;
  • Step c7 continuing to advance the main beam supporting truss working vehicle and the supporting truss to the positioning by the main beam supporting truss front hydraulic pressure device, and after the main beam supporting the truss working vehicle and the supporting truss and the next straddle mobile trolley are engaged and positioned, Fixed with a pin;
  • Step c8 The front truss front hydraulic pressure device gathers the leading truss downwards in a direction, and fixes the moving pin;
  • Step c9 removing the fixed latches of all the mobile trolleys
  • Step c10 the support trusses on both sides protrude forward with the pitch telescopic oil pressure rod, and the flex-extension steel template is retracted by the steel mold to flex the telescopic oil pressure rod to flatten the steel template;
  • Step c11 the main beam support truss work vehicle equipment is connected to the main beam support truss telescopic oil pressure rod of the lower mobile trolley to push the inner retracting position, and all the mobile trolleys are fixed by bolts, thereby completing the superstructure steel template combination;
  • Step c12 raising the lifting support of the hydraulic lifting device to a certain height, connecting and fixing with the channel beam steel beam;
  • Step c13 The hydraulic lifting device raises the channel shelf from bottom to top; the A and B units pushed into the pedestal shelf by the simple moving devices on both sides of the ground level are bolted to the substrate, The descending channel shelf is combined with the pedestal shelf, and the substrate is bonded by bolts;
  • Step c14 separating the lifting beam and the steel beam connection of the channel shelf, pushing the space between the pier and the column horizontally to the positioning, and descending to the positioning, thereby completing the upper structural steel formwork and the main beam supporting the truss working vehicle to the construction positioning;
  • Step c15 measurement and elevation adjustment
  • Step c16 using an oil pressure jack under the pedestal shelf to adjust the elevation
  • Step c17 tying the upper structure floor steel bar, the web reinforcement bar and installing the necessary application components above the upper structural steel formwork;
  • Step c18 pouring the upper structure floor concrete and the web concrete to a height of 30 cm;
  • Step c19 concrete curing
  • Step c20 lowering the hydraulic jack below the steel template of the inner mold working trolley to position, so that the telescopic oil pressure rod is retracted to retract the lateral moving steel template to the positioning, and the demoulding is completed;
  • Step c21 lowering the hydraulic jack under the inner mold working trolley to make the roller contact the concrete surface
  • Step c22 sequentially moving the internal mold work vehicle to the next span positioning
  • Step c23 measurement and elevation adjustment
  • Step c24 adjusting the elevation using the hydraulic jack under the inner mold working trolley
  • Step c25 tying the top plate steel of the upper structure
  • Step c26 pouring the upper structure web concrete and the roof concrete
  • Step c27 concrete curing.
  • the above step D includes:
  • Step d1 demolishing the hydraulic jack below the pedestal shelf
  • Step d2 raising the lifting support of the hydraulic lifting device to a certain height, connecting and fixing with the channel beam steel beam;
  • Step d3 removing the joint substrate bolt between the upper channel shelf and the pedestal shelf and the A unit and the B unit of the pedestal shelf to bond the substrate bolt, and the hydraulic lifting device rises by 5 cm;
  • Step d4 using a mobile device to pull out the A unit and the B unit of the pedestal shelf in the opposite direction of the ground level;
  • Step d5 descending the channel shelf to contact with the ground
  • Step d6 raising the lifting support of the hydraulic lifting device to be connected and fixed to the channel beam steel beam;
  • Step d7 disassembling the joint substrate bolt between the upper trolley shelf and the channel shelf and the A and B units of the channel shelf to bond the substrate bolt, and the hydraulic lifting device rises by 5 cm;
  • step d8 the A unit and the B unit of the channel shelf are pulled out in the opposite direction of the ground level using a simple mobile device.
  • Step d9 descending the trolley shelf until it is in contact with the ground;
  • Step d10 sequentially removing the flex-extension steel formwork, formwork beam, support truss, main beam support truss work vehicle, mobile trolley and fixed trolley, trolley shelf, hydraulic lifting equipment.
  • the lifting type construction system used in the construction of the bridge superstructure of the present invention and the construction method thereof have at least the following advantages:
  • the steel frame support frame is located on the ground when it is assembled and assembled, which greatly reduces the number and time of construction workers exposed to high altitude.
  • the steel formwork is designed for automation, eliminating the need for personnel to work in high places and mobile cranes.
  • Figure 1 is a conventional construction system of a bridge superstructure
  • Figure 2 is a conventional construction system of another bridge superstructure
  • Figure 3 is a perspective view of the present invention
  • Figure 4 is a front view of the present invention.
  • Figure 5 is a left side view of the present invention.
  • Figure 6 is a cross-sectional view of the present invention.
  • Figure 7 is a perspective view of the hydraulic lifting device of the present invention.
  • Figure 8 is a perspective view of the invention of the trolley shelf
  • Figure 9 is a perspective view of the channel shelf of the present invention.
  • Figure 10 is a perspective view of a susceptor shelf of the present invention.
  • Figure 11 is a schematic view showing the flexing of the steel formwork apparatus of the present invention.
  • Figure 12 is a perspective view of the inner mold work vehicle of the present invention.
  • Figure 13 is a flow chart showing the flow of the main beam supporting truss work vehicle of the present invention.
  • the present invention provides a support lifting construction system for the construction of a bridge superstructure, which comprises an inner mold working trolley 38, a flexing and extension steel formwork 11, a main beam supporting truss working machine 15, and a steel.
  • the inner mold workbench 38 of the present invention is used when the concrete is placed on the roof and the web of the bridge superstructure, and includes the upper and lower moving steel formwork 49 and the laterally moving steel formwork 48, and the upper and lower moving steel formwork 49 is connected to the hydraulic jack 18
  • the laterally moving steel template 48 is connected to the telescopic oil pressure rod 37 for horizontal support and demoulding action
  • the inner mold work cart 38 is provided with a roller 35 below, the roller 35 has a moving function, the hydraulic jack 18 has support and adjust the elevation function.
  • the main beam support truss work vehicle 15 of the present invention is composed of an upper structural steel formwork 10, a flex-extension steel formwork 11, a support truss 46, and a formwork beam 45.
  • the support truss work cart 15 is controlled to be closed and pushed out by the main beam support truss telescopic oil pressure rod 47, and the support truss 46 is controlled to be closed and retracted by the pitch telescopic oil pressure rod 34; when the flexural and extension steel formwork 11 is flexed, the steel mold bends the telescopic oil
  • the pressing rod 33 is propped up, and the steel formwork is centered on the center support 36, and the formwork beam 45 is moved in the horizontal direction.
  • the steel frame support frame 19 of the present invention is disposed around the bridge pier 31 to be constructed before and after, and the steel frame support frame 19 is divided into a trolley shelf 21, a channel shelf 22 and a pedestal shelf 23, and the trolley shelf 21 is composed of A unit 21a and B unit 21b; channel shelf 22A is composed of A unit 22a and B unit 22b; pedestal shelf 23 is composed of A unit 23a and B unit 23b and hydraulic jack 18 below;
  • the A and B units are corresponding modularized frames.
  • the joint joints of the A and B unit steel beams are provided with the joint substrate 25 and bolted and joined; the steel frame support frame 19 and the bridge pier 31 are provided with rollers. 35, and maintain the spacing to facilitate the lifting operation and avoid frame and pier wear.
  • the trolley shelf 21 is provided with a trolley guide 41 for the mobile trolley 13 to move horizontally by the trolley moving roller 43; the stationary trolley 16 is located above the trolley shelf 21 with a longitudinal propulsion roller 42 for supporting the main beam
  • the truss work cart 15 is propelled as it moves downward; the mobile cart 13 carries the main beam support truss work cart 15 and the support truss 46.
  • the trolley shelf 21 is provided with a service access 17 for maintenance.
  • the hydraulic lifting device 28 of the present invention provides a power source for driving the steel frame support frame 19 to support the main beam supporting truss work vehicle 15 to rise and fall.
  • the hydraulic lifting device 28 includes an lifting support 27, a hydraulic press 29 for driving the ascending and descending, and The shuttle device 39.
  • the lifting support 27 can be rotated 90 degrees horizontally.
  • the hydraulic lifting device 28 is connected and fixed to the periphery of the bridge pier 31 by a connecting fixing rod 32.
  • the supporting lifting construction system used in the construction of the superstructure of the bridge of the present invention is as follows:
  • Pre-operation The components of the supporting lifting construction system used in the construction of the superstructure of the bridge are prefabricated in the factory and then transported to the construction site for assembly; the piers of the bridge at the construction site shall be completed to the cap beam or the predetermined elevation.
  • Step a1 the hydraulic lifting device 28 is assembled and fixed around the bridge pier 31 by the connecting fixing rod 32;
  • Step a2 moving into the A unit 21a and the B unit 21b of the trolley shelf 21 at corresponding positions, and the corresponding bonding substrate 25 is bolted;
  • Step a3 lifting the stationary trolley 16 and the mobile trolley 13 above the trolley shelf 21 are placed on the trolley guide 41;
  • Step a4 lifting the support truss 46 to the corresponding mobile trolley 13, connecting the adjacent pitch telescopic oil pressure lever 34;
  • Step a5 lifting the main beam support truss work trolley 15 to the corresponding mobile trolley 13, connected to the main beam support truss telescopic oil pressure rod 47;
  • Step a6 installing the template beam 45 above the support truss 46 and the main beam support gantry workbench 15;
  • Step a7 lifting the bent steel form 11 to the top of the formwork beam 45, connecting the center support 36;
  • Step a8 test drive
  • Step a9 raising the lifting support 27 of the hydraulic lifting device 28 to a certain height, connecting and fixing with the steel beam of the trolley shelf 21;
  • Step a10 the hydraulic lifting device 28 raises and positions the trolley shelf 21 from bottom to top, and pushes the A unit 22a and the B unit 22b of the channel shelf 22 with the simple moving devices from the two sides of the ground level. Locking the bonding substrate 25, the falling carriage shelf 21 is combined with the channel shelf 22, and bolting the bonding substrate 25;
  • Step a11 the operation contents of the cycle steps 9 and 10, until the installation base shelf 23 raises the main beam support truss work vehicle 15 to the construction positioning;
  • Step a12 measurement and elevation adjustment
  • step a13 the elevation jack is adjusted using the hydraulic jack 18 below the pedestal shelf 23.
  • Step b1 tying the upper structure floor steel bar, the web reinforcement bar and installing the necessary application components on the upper structural steel formwork 10;
  • Step b2 pouring the concrete of the upper structure floor and the concrete of the web to a height of 30 cm;
  • Step b3 concrete curing
  • Step b4 hoisting and positioning the positioning inner mold work trolley 38;
  • Step b5 measurement and elevation adjustment
  • Step b6 adjusting the elevation using the hydraulic jack 18 under the inner mold working trolley 38;
  • Step b7 tying the top plate steel of the upper structure and installing the necessary application components
  • Step b8 pouring the upper structure web concrete and the roof concrete
  • Step b9 concrete curing
  • Step b10 the hydraulic jack 18 under the descending pedestal shelf 23 is demoulded
  • Step b11 raising the lifting support 27 of the hydraulic lifting device 28 to a certain height, connecting and fixing with the steel beam of the channel shelf 22;
  • Step b12 removing the bonding substrate 25 between the upper channel shelf 22 and the pedestal shelf 23, and the pedestal shelf 23A unit 23a and the B unit 23b bonding the substrate 25 bolts, and the hydraulic lifting device 28 is raised by 5 cm;
  • Step b13 using the simple mobile device to pull out the A unit 23a and the B unit 23b of the pedestal shelf 23 in the opposite direction of the ground level;
  • Step b14 descending the channel shelf 22 until it is in contact with the ground;
  • step b15 the separation lifting support 27 is connected with the steel beam of the channel shelf 22, and is pushed horizontally by 90 degrees toward the space between the bridge piers 31.
  • Step c1 the supporting truss 46 is connected to the main beam supporting truss working vehicle 15 by a pitch telescopic hydraulic rod 34 to be connected by a pin, and the flexing and extending steel template 11 is supported by a steel mold to flex the telescopic hydraulic rod 33 upward, and the spacing is matched.
  • the action of the telescopic oil pressure rod 34 causes the steel formwork to bend upward;
  • Step c2 the main beam supporting truss working vehicle 15 and the supporting truss 46 are connected to the main beam supporting truss telescopic hydraulic rod 47 of the mobile trolley 13 connected under the main beam supporting truss working vehicle 15 to push outward to the position, all the mobile stations
  • the car 13 is fixed by a pin;
  • Step c3 removing the moving latches of the front and rear front truss 14 , and the rear leading truss 14 and the positioning rod 40 are connected and fixed by a pin;
  • Step c4 the front truss front hydraulic pressure device 12 pushes the leading truss 14 forward to the position and is fixed by the bolt;
  • Step c5 propelling the main beam supporting truss working vehicle 15 and the supporting truss 46 with the main beam supporting truss front hydraulic pressure device 30, and moving by the moving trolley 13 and the longitudinal propulsion roller 42 on the stationary trolley 16 to Positioning
  • Step c6 after the current guide truss 14 is connected to the next slab frame support frame 19, the front truss 14 and the positioning rod 40 are fixed by a pin connection, and the rear front truss 14 is removed from the pin connection of the positioning rod 40;
  • Step c7 continuing to advance the main beam supporting truss working vehicle 15 and the supporting truss 46 to the positioning by the main beam supporting truss front hydraulic pressure device 30, the main beam supporting the truss working vehicle 15 and the supporting truss 46 and the next straddle mobile platform After the car 13 is engaged and positioned, the pin is fixed;
  • Step c8 The front guide truss front hydraulic pressure device 12 gathers the leading truss 14 downwardly and vertically to fix the moving latch;
  • Step c9 removing the fixed latches of all the mobile trolleys 13;
  • Step c10 the support trusses 46 on both sides protrude forward with the pitch telescopic oil pressure rod 34, and the flex-extension steel formwork 11 is retracted downward by the steel mold flexing and retracting hydraulic pressure rod 33 to flatten the steel formwork;
  • Step c11 the main beam supporting truss working vehicle device 15 is pushed inwardly retracted by the main beam supporting truss telescopic oil pressure rod 47 connected to the lower moving type trolley 13 , and all the moving trolleys 13 are fixed by bolts;
  • Step c12 raising the lifting support 27 of the hydraulic lifting device 28 to a certain height, connecting and fixing with the steel beam of the channel shelf 22;
  • step c13 the hydraulic lifting device 28 raises the channel shelf 22 from the bottom to the top.
  • the A unit 23a and the B unit 23b pushed into the pedestal shelf 23 by the simple moving equipment on both sides of the ground level are bolted to the bonding substrate 25, and the descending channel shelf 22 is combined with the pedestal shelf 23 to be bolted. Bonding the substrate 25;
  • Step c14 the separation lifting support 27 is connected with the steel beam of the channel shelf 22, and is pushed horizontally by 90 degrees toward the space between the bridge piers 31, and is lowered to the positioning;
  • Step c15 measurement and elevation adjustment
  • Step c16 using the hydraulic jack 18 under the pedestal shelf 23 to adjust the elevation
  • Step c17 tying the upper structure floor steel bar, the web reinforcement bar and installing the necessary application components on the upper structural steel formwork 10;
  • Step c18 pouring the upper structure floor concrete and the web concrete to a height of 30 cm;
  • Step c19 concrete curing
  • Step c20 the lowering of the inner mold working trolley 38 moves the hydraulic jack 18 below the steel template 49 to the positioning, so that the telescopic oil pressing rod 37 is retracted to retract the laterally moving steel template 48 to the positioning, and the demoulding is completed;
  • Step c21 the oil pressure jack 18 below the lower inner mold work trolley 38 causes the roller 35 to contact the concrete surface;
  • Step c22 sequentially moving the inner mold work cart 38 to the next span positioning
  • Step c23 measurement and elevation adjustment
  • Step c24 adjusting the elevation using the hydraulic jack 18 under the inner mold working trolley 38;
  • Step c25 tying the top plate steel of the upper structure and installing necessary application components
  • Step c26 pouring the upper structure web concrete and the roof concrete
  • Step c27 concrete curing.
  • Step d1 the hydraulic jack 18 under the descending pedestal shelf 23 is demoulded
  • Step d2 raising the lifting support 27 of the hydraulic lifting device 28 to a certain height, connecting and fixing with the steel beam of the channel shelf 22;
  • Step d3 removing the bonding substrate 25 between the upper channel shelf 22 and the pedestal shelf 23, and the A unit 23a and the B unit 23b of the pedestal shelf 23 are bonded to the substrate 25 bolt, and the hydraulic lifting device 28 is raised by 5 cm;
  • Step d4 using the simple mobile device to pull out the A unit 23a and the B unit 23b of the pedestal shelf 23 in the opposite direction of the ground level;
  • Step d5 descending the channel shelf 22 until it is in contact with the ground;
  • Step d6 raising the lifting support 27 of the hydraulic lifting device 28 to a certain height, connecting and fixing with the steel beam of the channel shelf 22;
  • Step d7 removing the bonding substrate 25 between the upper trolley shelf 21 and the channel shelf 22, and the A unit 22a and the B unit 22b of the channel shelf 22 are joined to the substrate 25 bolt, and the hydraulic lifting device 28 is raised by 5 cm;
  • Step d8 using the simple mobile device to pull out the A unit 22a and the B unit 22b of the channel shelf 22 in the opposite direction of the ground level;
  • Step d9 descending the trolley shelf 21 until it is in contact with the ground;
  • Step d10 removing the flex-extension steel template 11;
  • Step d11 removing the template beam 45;
  • Step d12 removing the support truss 46;
  • Step d13 removing the main beam support truss work vehicle 15;
  • Step d14 removing the mobile trolley 13 and the stationary trolley 16;
  • Step d15 removing the trolley shelf 21;
  • Step d16 removing the hydraulic lifting device 28;
  • step d17 the removed device components are transported away from the work area.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

一种用于桥梁上部结构施工的升降式施工系统及其施工方法。升降式施工系统包括内模工作台车(38)、屈伸式钢模板(110、主梁支撑桁架工作车(15)、钢框支撑架(19)及油压升降设备(28);其中,内模工作台车(38)包括上下移动钢模板(49)及侧向移动钢模板(48),油压升降设备(28)驱动钢框支撑架(19)承载主梁支撑桁架工作车(15)上升及下降。施工时,钢框支撑架(19)设置在桥梁墩柱(31)四周,钢框支撑架(19)在地面组装及拆卸,推进主梁支撑桁架工作车(15)时,下降钢框支撑架(19),采取循环施工的方式施工。该升降式施工系统及其施工方法减少了人员高处作业的次数从而提高了施工安全。

Description

桥梁上部结构施工使用的升降式施工系统及其施工方法 技术领域
本发明涉及一种桥梁上部结构施工使用的土木施工法,特别是指一种桥梁上部结构施工使用的支撑升降式施工系统及其施工方法。
背景技术
如图1所示,习知的桥梁上部结构土木施工法是于桥梁上部结构下方桥下空间布满支撑架,支撑架需由地面依序向上于高处组装,在拆卸、组装支撑架及模板设备的每一阶段,均需依赖移动式吊车配合拆组装,施工人员需位于高处拆组装作业,拆除时亦同。
如图2所示,一种习知的桥梁上部结构土木施工法,该施工法为预先于桥梁墩柱或帽梁设置托架,再使用移动式吊车或上车设备将主梁工作车上车完成,拆除亦同。推进时必须先于下一墩柱或帽梁设置安装托架,安装时须依靠移动式吊车配合组装,施工人员需位于高处拆组装作业,拆除时亦同。
综上所述,习知两代表性桥梁上部结构土木施工法技术,分别具有下列缺点:
首先,必须使用大量的支撑架,无桥下空间可供施工利用,工程进行时桥梁下方的道路需封闭施工。
其次,支撑架及模板组装时,施工人员需暴露于高空作业,每一阶段皆需移动式吊车配合施工,拆除时亦同。
再者,每一桥墩柱安装托架时,施工人员需暴露于高空作业,需移动式吊车配合施工,拆除时亦同。
另外,上述两习知桥梁上部结构土木施工系统皆需另行搭设供施工人员上下的设备。
有鉴于此,本设计人针对现有桥梁上部结构施工使用系统设计上未臻完善所导致的诸多缺失及不便,而深入构思,且积极研究改良试做而开发设计出本发明。
发明内容
本发明的目的在于提供一种可减少支撑架的使用,无需封闭道路,可提高使用安全度的桥梁上部结构施工使用的升降式施工系统及其施工方法。
为了达成上述目的,本发明的解决方案是:
一种桥梁上部结构施工使用的支撑升降式施工系统,包含多数个内模工作台车、二屈伸式钢模板、二主梁支撑桁架工作车、二钢框支撑架、四油压升降设备,所述多数个内模工作台车位于浇置完成的桥梁上部结构的底板上方,其包含上下移动钢模板及侧向移动钢模板;所述油压升降设备组装固定于桥梁墩柱四周且设置于钢框支撑架与墩柱之间,油压升降设备驱动钢框支撑架承载主梁支撑桁架工作车上升及下降,所述二钢框支撑架设置于前后已完成欲施工的桥梁墩柱四周,钢框支撑架位于地面组装及拆卸,推进主梁支撑桁架工作车时,下降钢框支撑架,以循环施工的方式施工。
所述内模工作台设有伸缩油压杆驱动钢模板;内模工作台车下方设有为移动内模工作台车至定位使用的移动滚轮;内模工作台车下方设有油压千斤顶;内模工作台车为浇置桥梁上部结构腹板及顶板混凝土成形使用。
所述二屈伸式钢模板及二主梁支撑桁架工作车为桥梁上部结构的钢模板设备,屈伸式钢模板及主梁支撑桁架工作车下方具有固定台车与移动台车;屈伸式钢模板使用油压伸缩杆控制向上屈起与向下伸出展平于主梁支撑桁架上方;主梁支撑桁架工作车使用油压伸缩杆控制向内推进接合与向外推出移动,移动至定位时,使用插销定位。
所述钢框支撑架区分为台车层架、通道层架及基座层架,每一层架均分为A单元与B单元,A、B单元为相对应的模组化制作的框架,A、B单元钢梁相应接合处设有接合基板并使用螺栓锁固接合,钢框支撑架的通道踏板、平台及上下楼梯使用螺栓及插销接合,钢框支撑架与墩柱间设有滚轮且保持间距。
所述四油压升降设备设置于钢框支撑架与墩柱之间,各油压升降设备提供钢框支撑架升降时的动力来源,所述油压升降设备由四或多数组油压机升降支承、一个升降控制箱、四或多数个升降支承、四或多数个止滑煞车装置所组成;钢框支撑架升降时由升降控制箱控制四组或多数个油压机升降支承同时动作。
一种桥梁上部结构施工使用的支撑升降式施工系统的施工方法,该施工系统于组装时,位于地面部作业,先组装油压升降设备以连接固定杆固定于完成的混凝土墩柱的四周,台车层架A单元与B单元由相应的水平两侧推入以螺栓固接,组装移动式台车与固定式台车于层架上方,屈伸式钢模板设备与主梁支撑桁架工作车于地面上组装完成,续吊装与移动式台车组合。
本发明于上升时,位于地面部作业,先升起油压升降设备的升降支承至一定高度,与钢框支撑架连接且固定,由升降控制箱操作油压升降设备将钢框支撑架升高至定位。由地面水平相应两侧以移动设备推入通道层架A单元与B单元并以螺栓锁固。下降台车层架,并与通道层架组合,以螺栓固接。
进一步,该施工系统下降时,位于地面部作业,先升起油压升降设备的升降支承至一定高度,与钢框支撑架连接且固定,拆卸上下及左右层架接合基板的螺栓,油压升降设备操作向上举起5公分使上下层架分离,使用移动设备将层架向外侧拉出移除,油压升降设备系统始操作向下降落钢框支撑架至地面。
进一步,该施工系统于推进时,需拆除基座层架,向下降落钢框支撑架至主梁支撑桁架工作车最高处与帽梁无干涉推进高度,向前伸出前导桁架至一定长度,卸除后方前导桁架移动插销并将后前导桁架与定位杆连接固定,使用设置于主梁支撑桁架工作车下方的油压推进设备,推进主梁支撑桁架工作车;当前导桁架与下一跨支撑架接续定位后,将前导桁架与定位杆连接固定,卸除后方前导桁架与定位杆连接,续推进主梁支撑桁架工作车至下一跨钢框支撑架定位,以插销固定工作车与移动式台车的连接,收回后前导桁架至定位并固定移动插销。
一种桥梁上部结构施工使用的升降式施工方法,包括:
A:组装上车阶段施工步骤;
B:桥梁上部结构施工循环阶段施工步骤;
C:主梁支撑桁架工作车推进循环阶段施工步骤;
D:拆除下车阶段施工步骤。
上述步骤A包括:
步骤a1、油压升降设备以连接固定杆组装固定于桥梁墩柱四周;
步骤a2、以相对应的位置移入台车层架的A单元与B单元,相对应的接合基板以螺栓锁固;
步骤a3、于台车层架上方吊装固定式台车与移动式台车置于台车导轨上;
步骤a4、吊装支撑桁架至相对应的移动式台车上方,连接相邻的间距伸缩油压杆;
步骤a5、吊装主梁支撑桁架工作台车至相对应的移动式台车上方,连接主梁支撑桁架伸缩油压杆;
步骤a6、安装模板横梁于支撑桁架及主梁支撑行架工作台车上方;
步骤a7、吊装屈伸式钢模板至模板横梁上方,连接圆心支承;
步骤a8、试车;
步骤a9、升起油压升降设备的升降支承至一定高度,与台车层架钢梁连接且固定;
步骤a10、油压升降设备由下往上将台车层架升高并定位,由地面水平相应的两侧以简易移动设备推入通道层架的A单元与B单元以螺栓锁固接合基板,下降台车层架与通道层架组合,以螺栓锁固接合基板;
步骤a11、循环步骤a9及a10的操作内容,直至安装基座层架将主梁支撑桁架工作车升高至施工定位;
步骤a12、测量及高程调整;
步骤a13、使用基座层架下方的油压千斤顶调整高程。
上述步骤B包括:
步骤b1、于上部结构钢模板上方绑扎上部结构底板钢筋、腹板钢筋;
步骤b2、浇置上部结构底板混凝土及腹板混凝土至30公分高;
步骤b3、混凝土养护;
步骤b4、吊放安装定位内模工作台车;
步骤b5、测量及高程调整;
步骤b6、使用内模工作台车下方的油压千斤顶调整高程;
步骤b7、绑扎上部结构顶板钢筋及安装必要的施作组件;
步骤b8、浇置上部结构腹板混凝土及顶板混凝土;
步骤b9、混凝土养护;
步骤b10、下降基座层架下方的油压千斤顶脱模;
步骤b11、升起油压升降设备的升降支承至一定高度,与通道层架钢梁连接且固定;
步骤b12、拆除上方通道层架与基座层架间的接合基板螺栓及基座层架A单元与B单元接合基板螺栓,油压升降设备上升5公分;
步骤b13、使用简易移动设备将基座层架的A单元与B单元在地面水平反方向拉出移除;
步骤b14、下降通道层架至与地面接触为止;
步骤b15、分离升降支承与通道层架的钢梁连接,以水平90度推向桥梁墩柱间的空间收合。
上述步骤C包括:
步骤c1、支撑桁架以间距伸缩油压杆向主梁支撑桁架工作车靠拢以插销连接,屈伸式钢模板以钢模屈起伸缩油压杆向上将钢模板撑起,配合间距伸缩油压杆的动作使钢模板向上屈起;
步骤c2、主梁支撑桁架工作车及支撑桁架以连接在主梁支撑桁架工作车下方的移动式台车的主梁支撑桁架伸缩油压杆推向外侧至定位,所有移动台车以插销固定;
步骤c3、卸除前、后前导桁架的移动插销,后方前导桁架与定位杆以插销连接固定;
步骤c4、以前导桁架前驱油压设备将前导桁架向前推出至定位并以插销固定;
步骤c5、以主梁支撑桁架前驱油压设备将主梁支撑桁架工作车及支撑桁架向前推进,借由移动式台车与固定式台车上的纵向推进滚轮移动至定位;
步骤c6、当前导桁架与下一跨钢框支撑架接续后,前导桁架与定位杆以插销连接固定,卸除后方前导桁架与定位杆的插销连接;
步骤c7、续以主梁支撑桁架前驱油压设备将主梁支撑桁架工作车及支撑桁架向前推进至定位,主梁支撑桁架工作车及支撑桁架与下一跨移动式台车接合定位后,以插销固定;
步骤c8、以前导桁架前驱油压设备将前导桁架向下一跨方向收拢,固定移动插销;
步骤c9、卸除所有移动式台车的固定插销;
步骤c10、两侧的支撑桁架以间距伸缩油压杆向前伸出,屈伸式钢模板以钢模屈起伸缩油压杆向下缩回将钢模板展平;
步骤c11、主梁支撑桁架工作车设备以连接在下方移动式台车的主梁支撑桁架伸缩油压杆推向内缩回定位,所有移动台车以插销固定,至此完成上部结构钢模板组合;
步骤c12、升起油压升降设备的升降支承至一定高度,与通道层架钢梁连接且固定;
步骤c13、油压升降设备由下往上将通道层架升高至定位;由地面水平相应的两侧以简易移动设备推入基座层架的A单元与B单元以螺栓锁固接合基板,下降通道层架与基座层架组合,以螺栓固结接合基板;
步骤c14、分离升降支承与通道层架的钢梁连接,以水平度推向桥梁墩柱间的空间收合,下降至定位,至此完成上部结构钢模板与主梁支撑桁架工作车至施工定位;
步骤c15、测量及高程调整;
步骤c16、使用基座层架下方的油压千斤顶调整高程;
步骤c17、于上部结构钢模板上方绑扎上部结构底板钢筋、腹板钢筋及安装必要的施作组件;
步骤c18、浇置上部结构底板混凝土及腹板混凝土至30公分高;
步骤c19、混凝土养护;
步骤c20、下降内模工作台车的上下移动钢模板下方的油压千斤顶至定位,使伸缩油压杆缩回将侧向移动钢模板收回至定位,完成脱模;
步骤c21、下降内模工作台车下方的油压千斤顶使滚轮与混凝土面接触;
步骤c22、依序移动内模工作台车至下一跨定位;
步骤c23、测量及高程调整;
步骤c24、使用内模工作台车下方的油压千斤顶调整高程;
步骤c25、绑扎上部结构顶板钢筋;
步骤c26、浇置上部结构腹板混凝土及顶板混凝土;
步骤c27、混凝土养护。
上述步骤D包括:
步骤d1、下降基座层架下方的油压千斤顶脱模;
步骤d2、升起油压升降设备的升降支承至一定高度,与通道层架钢梁连接且固定;
步骤d3、拆除上方通道层架与基座层架间的接合基板螺栓及基座层架的A单元与B单元接合基板螺栓,油压升降设备上升5公分;
步骤d4、使用移动设备将基座层架的A单元与B单元在地面水平反方向拉出移除;
步骤d5、下降通道层架至与地面接触为止;
步骤d6、升起油压升降设备的升降支承至与通道层架钢梁连接且固定;
步骤d7、拆除上方台车层架与通道层架间的接合基板螺栓及通道层架的A单元与B单元接合基板螺栓,油压升降设备上升5公分;
步骤d8、使用简易移动设备将通道层架的A单元与B单元在地面水平反方向拉出移除。
步骤d9、下降台车层架至与地面接触为止;
步骤d10、依序拆除屈伸式钢模板、模板横梁、支撑桁架、主梁支撑桁架工作车、移动式台车与固定式台车、台车层架、油压升降设备。
采用上述方案后,本发明桥梁上部结构施工使用的升降式施工系统及其施工方法至少具有以下优点:
1、各组件均于地面部组装完成,除初次组装与拆除时需移动式吊车配合作业,其余均为自动化的操作或简易移动设备配合施工。
2、经结构计算后,仅使用所需的支撑架及钢材,大幅减少支撑架及钢材的使用。
3、工程进行时,施工位置桥梁下方的道路无须封闭。
4、钢框支撑架上升组装时位于地面部操作,大幅减少施工人员曝露于高空处作业的次数及时间。
5、钢模板组装时为自动化设计,免除人员于高处作业及移动式吊车作业。
6、人员上下设备已规划于钢框支撑架内部或外部附挂组合,无须另行搭设。
7、钢框支撑架先行至下一跨墩柱设置时,施工人员无需位于高空处组装支撑托架。
附图说明
图1为习知一种桥梁上部结构的施工系统;
图2为习知另一种桥梁上部结构的施工系统;
图3为本发明的立体图;
图4为本发明的前视图;
图5为本发明的左视图;
图6为本发明的剖视图;
图7为本发明油压升降设备的立体图;
图8为本能发明台车层架的立体图;
图9为本发明通道层架的立体图;
图10为本发明基座层架的立体图;
图11为本发明钢模板设备的屈展示意图;
图12为本发明内模工作台车的立体图;
图13为本发明推进主梁支撑桁架工作车的流程顺序示意图。
其中:
10 上部结构钢模板11 屈伸式钢模板
12前导桁架前驱油压设备13 移动式台车
14 前导桁架15 主梁支撑桁架工作车
16 固定式台车17 维修通道
18 油压千斤顶19钢框支撑架
20 平台栏杆21 台车层架
21a台车层架A单元21b台车层架B单元
22 通道层架22a通道层架A单元
22b通道层架B单元23 基座层架
23a基座层架A单元23b基座层架B单元
24 楼梯25 接合基板
26 桥墩帽梁27 升降支承
28 油压升降设备29 油压机
30 主梁支撑桁架前驱油压设备31 桥梁墩柱
32 连接固定杆33 钢模屈起伸缩油压杆
34 间距伸缩油压杆35 滚轮
36 圆心支承37 伸缩油压杆
38 内模工作台车39 止滑煞车装置
40 定位杆41 台车导轨
42 纵向推进滚轮43 台车移动滚轮
44 连杆45 模板横梁
46 支撑桁架47 主梁支撑桁架伸缩油压杆
48 侧向移动钢模板49 上下移动钢模板。
具体实施方式
为了进一步解释本发明的技术方案,下面通过具体实施例来对本发明进行详细阐述。
请参阅图3至图13,本发明提供一种桥梁上部结构施工使用的支撑升降式施工系统,其包含了内模工作台车38、屈伸式钢模板11、主梁支撑桁架工作车15、钢框支撑架19及油压升降设备28。
本发明的内模工作台车38是使用于桥梁上部结构混凝土浇置顶板及腹板时使用,其包含上下移动钢模板49及侧向移动钢模板48,上下移动钢模板49连接油压千斤顶18作上下支撑及脱模动作,侧向移动钢模板48连接伸缩油压杆37做水平方向支撑及脱模动作,内模工作台车38下方设有滚轮35,滚轮35具有移动功能,油压千斤顶18具有支撑及调整高程功能。
本发明的主梁支撑桁架工作车15是由上部结构钢模板10、屈伸式钢模板11、支撑桁架46、模板横梁45所组成,主梁支撑桁架工作车15向柱中心收合时,主梁支撑桁架工作车15由主梁支撑桁架伸缩油压杆47控制闭合与推出,支撑桁架46由间距伸缩油压杆34控制闭合与收回;屈伸式钢模板11屈展时由钢模屈起伸缩油压杆33向上撑起,钢模板以圆心支承36为中心动作收展,同时模板横梁45一同水平方向移动。
本发明的钢框支撑架19设置于前后已完成欲施工的桥梁墩柱31四周,钢框支撑架19区分为台车层架21、通道层架22及基座层架23,台车层架21由A单元21a与B单元21b所组成;通道层架22A由A单元22a与B单元22b所组成;基座层架23由A单元23a与B单元23b及下方的油压千斤顶18所组成;A、B单元为相对应的模组化制作的框架,A、B单元钢梁相应接合处设有接合基板25并使用螺栓锁固接合;钢框支撑架19与桥梁墩柱31间设有滚轮35,并保持间距以利升降作业的进行及避免框架与墩柱磨损。台车层架21设有台车导轨41供移动式台车13以台车移动滚轮43做水平方向移动;固定式台车16位于台车层架21上方设有纵向推进滚轮42供主梁支撑桁架工作车15向下一跨移动时推进;移动式台车13上方承载主梁支撑桁架工作车15及支撑桁架46。台车层架21设有维修通道17供维修时使用。
本发明的油压升降设备28是提供驱动钢框支撑架19承载主梁支撑桁架工作车15上升下降的动力来源,其中油压升降设备28包含升降支承27、驱动上升及下降的油压机29以及止滑煞车装置39。升降支承27可作90度的水平推移。油压升降设备28以连接固定杆32连接固定于桥梁墩柱31四周。
本发明桥梁上部结构施工使用的支撑升降式施工系统,其施工组装操作实施方式顺序说明如下:
先期作业:桥梁上部结构施工使用的支撑升降式施工系统各部件皆于工厂内预制完成,再运载至施工现场组装;施工现场桥梁墩柱须完成至帽梁或预定高程。
A、组装上车阶段施工步骤:
步骤a1、油压升降设备28以连接固定杆32组装固定于桥梁墩柱31四周;
步骤a2、以相对应的位置移入台车层架21的A单元21a与B单元21b,相对应的接合基板25以螺栓锁固;
步骤a3、于台车层架21上方吊装固定式台车16与移动式台车13置于台车导轨41上;
步骤a4、吊装支撑桁架46至相对应的移动式台车13上方,连接相邻的间距伸缩油压杆34;
步骤a5、吊装主梁支撑桁架工作台车15至相对应的移动式台车13上方,连接主梁支撑桁架伸缩油压杆47;
步骤a6、安装模板横梁45于支撑桁架46及主梁支撑行架工作台车15上方;
步骤a7、吊装屈伸式钢模板11至模板横梁45上方,连接圆心支承36;
步骤a8、试车;
步骤a9、升起油压升降设备28的升降支承27至一定高度,与台车层架21钢梁连接且固定;
步骤a10、油压升降设备28由下往上将台车层架21升高并定位,由地面水平相应的两侧以简易移动设备推入通道层架22的A单元22a与B单元22b以螺栓锁固接合基板25,下降台车层架21与通道层架22组合,以螺栓锁固接合基板25;
步骤a11、循环步骤9及10的操作内容,直至安装基座层架23将主梁支撑桁架工作车15升高至施工定位;
步骤a12、测量及高程调整;
步骤a13、使用基座层架23下方的油压千斤顶18调整高程。
B、桥梁上部结构施工循环阶段施工步骤:
步骤b1、于上部结构钢模板10上方绑扎上部结构底板钢筋、腹板钢筋及安装必要的施作组件;
步骤b2、浇置上部结构底板混凝土及腹板混凝土至30公分高;
步骤b3、混凝土养护;
步骤b4、吊放安装定位内模工作台车38;
步骤b5、测量及高程调整;
步骤b6、使用内模工作台车38下方的油压千斤顶18调整高程;
步骤b7、绑扎上部结构顶板钢筋及安装必要的施作组件;
步骤b8、浇置上部结构腹板混凝土及顶板混凝土;
步骤b9、混凝土养护;
步骤b10、下降基座层架23下方的油压千斤顶18脱模;
步骤b11、升起油压升降设备28的升降支承27至一定高度,与通道层架22钢梁连接且固定;
步骤b12、拆除上方通道层架22与基座层架23间的接合基板25螺栓及基座层架23A单元23a与B单元23b接合基板25螺栓,油压升降设备28上升5公分;
步骤b13、使用简易移动设备将基座层架23的A单元23a与B单元23b在地面水平反方向拉出移除;
步骤b14、下降通道层架22至与地面接触为止;
步骤b15、分离升降支承27与通道层架22的钢梁连接,以水平90度推向桥梁墩柱31间的空间收合。
C、主梁支撑桁架工作车15推进循环阶段施工步骤:
步骤c1、支撑桁架46以间距伸缩油压杆34向主梁支撑桁架工作车15靠拢以插销连接,屈伸式钢模板11以钢模屈起伸缩油压杆33向上将钢模板撑起,配合间距伸缩油压杆34的动作使钢模板向上屈起;
步骤c2、主梁支撑桁架工作车15及支撑桁架46以连接在主梁支撑桁架工作车15下方的移动式台车13的主梁支撑桁架伸缩油压杆47推向外侧至定位,所有移动台车13以插销固定;
步骤c3、卸除前、后前导桁架14的移动插销,后方前导桁架14与定位杆40以插销连接固定;
步骤c4、以前导桁架前驱油压设备12将前导桁架14向前推出至定位并以插销固定;
步骤c5、以主梁支撑桁架前驱油压设备30将主梁支撑桁架工作车15及支撑桁架46向前推进,借由移动式台车13与固定式台车16上的纵向推进滚轮42移动至定位;
步骤c6、当前导桁架14与下一跨钢框支撑架19接续后,前导桁架14与定位杆40以插销连接固定,卸除后方前导桁架14与定位杆40的插销连接;
步骤c7、续以主梁支撑桁架前驱油压设备30将主梁支撑桁架工作车15及支撑桁架46向前推进至定位,主梁支撑桁架工作车15及支撑桁架46与下一跨移动式台车13接合定位后,以插销固定;
步骤c8、以前导桁架前驱油压设备12将前导桁架14向下一跨方向收拢,固定移动插销;
步骤c9、卸除所有移动式台车13的固定插销;
步骤c10、两侧的支撑桁架46以间距伸缩油压杆34向前伸出,屈伸式钢模板11以钢模屈起伸缩油压杆33向下缩回将钢模板展平;
步骤c11、主梁支撑桁架工作车设备15以连接在下方移动式台车13的主梁支撑桁架伸缩油压杆47推向内缩回定位,所有移动台车13以插销固定;
至此完成上部结构钢模板10组合;
步骤c12、升起油压升降设备28的升降支承27至一定高度,与通道层架22钢梁连接且固定;
步骤c13、油压升降设备28由下往上将通道层架22升高至定位。由地面水平相应的两侧以简易移动设备推入基座层架23的A单元23a与B单元23b以螺栓锁固接合基板25,下降通道层架22与基座层架23组合,以螺栓固结接合基板25;
步骤c14、分离升降支承27与通道层架22的钢梁连接,以水平90度推向桥梁墩柱31间的空间收合,下降至定位;
至此完成上部结构钢模板10与主梁支撑桁架工作车15至施工定位;
步骤c15、测量及高程调整;
步骤c16、使用基座层架23下方的油压千斤顶18调整高程;
步骤c17、于上部结构钢模板10上方绑扎上部结构底板钢筋、腹板钢筋及安装必要的施作组件;
步骤c18、浇置上部结构底板混凝土及腹板混凝土至30公分高;
步骤c19、混凝土养护;
步骤c20、下降内模工作台车38的上下移动钢模板49下方的油压千斤顶18至定位,使伸缩油压杆37缩回将侧向移动钢模板48收回至定位,完成脱模;
步骤c21、下降内模工作台车38下方的油压千斤顶18使滚轮35与混凝土面接触;
步骤c22、依序移动内模工作台车38至下一跨定位;
步骤c23、测量及高程调整;
步骤c24、使用内模工作台车38下方的油压千斤顶18调整高程;
步骤c25、绑扎上部结构顶板钢筋及安装必要的施作组件;
步骤c26、浇置上部结构腹板混凝土及顶板混凝土;
步骤c27、混凝土养护。
接续桥梁上部结构施工循环阶段施工步骤10至步骤15,续回复本阶段主梁支撑桁架工作车15推进循环阶段步骤1,至此为循环施工方式至工程完成。
D、拆除下车阶段施工步骤:
步骤d1、下降基座层架23下方的油压千斤顶18脱模;
步骤d2、升起油压升降设备28的升降支承27至一定高度,与通道层架22钢梁连接且固定;
步骤d3、拆除上方通道层架22与基座层架23间的接合基板25螺栓及基座层架23的A单元23a与B单元23b接合基板25螺栓,油压升降设备28上升5公分;
步骤d4、使用简易移动设备将基座层架23的A单元23a与B单元23b在地面水平反方向拉出移除;
步骤d5、下降通道层架22至与地面接触为止;
步骤d6、升起油压升降设备28的升降支承27至一定高度,与通道层架22钢梁连接且固定;
步骤d7、拆除上方台车层架21与通道层架22间的接合基板25螺栓及通道层架22的A单元22a与B单元22b接合基板25螺栓,油压升降设备28上升5公分;
步骤d8、使用简易移动设备将通道层架22的A单元22a与B单元22b在地面水平反方向拉出移除;
步骤d9、下降台车层架21至与地面接触为止;
步骤d10、拆除屈伸式钢模板11;
步骤d11、拆除模板横梁45;
步骤d12、拆除支撑桁架46;
步骤d13、拆除主梁支撑桁架工作车15;
步骤d14、拆除移动式台车13与固定式台车16;
步骤d15、拆除台车层架21;
步骤d16、拆除油压升降设备28;
步骤d17、将拆除的各设备组件运离工区。
上述实施例和图式并非限定本发明的产品形态和式样,任何所属技术领域的普通技术人员对其所做的适当变化或修饰,皆应视为不脱离本发明的专利范畴。

Claims (10)

1、一种桥梁上部结构施工使用的升降式施工系统,其特征在于:包含多数个内模工作台车、二屈伸式钢模板、二主梁支撑桁架工作车、二钢框支撑架、四油压升降设备,所述多数个内模工作台车位于浇置完成的桥梁上部结构的底板上方,其包含上下移动钢模板及侧向移动钢模板;所述油压升降设备组装固定于桥梁墩柱四周且设置于钢框支撑架与墩柱之间,油压升降设备驱动钢框支撑架承载主梁支撑桁架工作车上升及下降,所述二钢框支撑架设置于前后已完成欲施工的桥梁墩柱四周,钢框支撑架位于地面组装及拆卸,推进主梁支撑桁架工作车时,下降钢框支撑架,以循环施工的方式施工。
2、依据权利要求1所述的桥梁上部结构施工使用的升降式施工系统,其特征在于:所述内模工作台设有伸缩油压杆驱动钢模板;内模工作台车下方设有为移动内模工作台车至定位使用的移动滚轮;内模工作台车下方设有油压千斤顶;内模工作台车为浇置桥梁上部结构腹板及顶板混凝土成形使用。
3、依据权利要求1所述的桥梁上部结构施工使用的升降式施工系统,其特征在于:所述二屈伸式钢模板及二主梁支撑桁架工作车为桥梁上部结构的钢模板设备,屈伸式钢模板及主梁支撑桁架工作车下方具有固定台车与移动台车;屈伸式钢模板使用油压伸缩杆控制向上屈起与向下伸出展平于主梁支撑桁架上方;主梁支撑桁架工作车使用油压伸缩杆控制向内推进接合与向外推出移动,移动至定位时,使用插销定位。
4、依据权利要求1所述的桥梁上部结构施工使用的升降式施工系统,其特征在于:所述钢框支撑架区分为台车层架、通道层架及基座层架,每一层架均分为A单元与B单元,A、B单元为相对应的模组化制作的框架,A、B单元钢梁相应接合处设有接合基板并使用螺栓锁固接合,钢框支撑架的通道踏板、平台及上下楼梯使用螺栓及插销接合,钢框支撑架与墩柱间设有滚轮且保持间距。
5、依据权利要求1所述的桥梁上部结构施工使用的升降式施工系统,其特征在于:所述四油压升降设备设置于钢框支撑架与墩柱之间,各油压升降设备提供钢框支撑架升降时的动力来源,所述油压升降设备由四或多数组油压机升降支承、一个升降控制箱、四或多数个升降支承、四或多数个止滑煞车装置所组成;钢框支撑架升降时由升降控制箱控制四组或多数个油压机升降支承同时动作。
6、一种桥梁上部结构施工使用的升降式施工方法,包括以下步骤:
A:组装上车阶段施工步骤;
B:桥梁上部结构施工循环阶段施工步骤;
C:主梁支撑桁架工作车推进循环阶段施工步骤;
D:拆除下车阶段施工步骤。
7、如权利要求6所述的桥梁上部结构施工使用的升降式施工方法,其特征在于:步骤A包括:
步骤a1、油压升降设备以连接固定杆组装固定于桥梁墩柱四周;
步骤a2、以相对应的位置移入台车层架的A单元与B单元,相对应的接合基板以螺栓锁固;
步骤a3、于台车层架上方吊装固定式台车与移动式台车置于台车导轨上;
步骤a4、吊装支撑桁架至相对应的移动式台车上方,连接相邻的间距伸缩油压杆;
步骤a5、吊装主梁支撑桁架工作台车至相对应的移动式台车上方,连接主梁支撑桁架伸缩油压杆;
步骤a6、安装模板横梁于支撑桁架及主梁支撑行架工作台车上方;
步骤a7、吊装屈伸式钢模板至模板横梁上方,连接圆心支承;
步骤a8、试车;
步骤a9、升起油压升降设备的升降支承至一定高度,与台车层架钢梁连接且固定;
步骤a10、油压升降设备由下往上将台车层架升高并定位,由地面水平相应的两侧以简易移动设备推入通道层架的A单元与B单元以螺栓锁固接合基板,下降台车层架与通道层架组合,以螺栓锁固接合基板;
步骤a11、循环步骤a9及a10的操作内容,直至安装基座层架将主梁支撑桁架工作车升高至施工定位;
步骤a12、测量及高程调整;
步骤a13、使用基座层架下方的油压千斤顶调整高程。
8、如权利要求6所述的桥梁上部结构施工使用的升降式施工方法,其特征在于:步骤B包括:
步骤b1、于上部结构钢模板上方绑扎上部结构底板钢筋、腹板钢筋;
步骤b2、浇置上部结构底板混凝土及腹板混凝土至30公分高;
步骤b3、混凝土养护;
步骤b4、吊放安装定位内模工作台车;
步骤b5、测量及高程调整;
步骤b6、使用内模工作台车下方的油压千斤顶调整高程;
步骤b7、绑扎上部结构顶板钢筋及安装必要的施作组件;
步骤b8、浇置上部结构腹板混凝土及顶板混凝土;
步骤b9、混凝土养护;
步骤b10、下降基座层架下方的油压千斤顶脱模;
步骤b11、升起油压升降设备的升降支承至一定高度,与通道层架钢梁连接且固定;
步骤b12、拆除上方通道层架与基座层架间的接合基板螺栓及基座层架A单元与B单元接合基板螺栓,油压升降设备上升5公分;
步骤b13、使用简易移动设备将基座层架的A单元与B单元在地面水平反方向拉出移除;
步骤b14、下降通道层架至与地面接触为止;
步骤b15、分离升降支承与通道层架的钢梁连接,以水平90度推向桥梁墩柱间的空间收合。
9、如权利要求6所述的桥梁上部结构施工使用的升降式施工方法,其特征在于:步骤C包括:
步骤c1、支撑桁架以间距伸缩油压杆向主梁支撑桁架工作车靠拢以插销连接,屈伸式钢模板以钢模屈起伸缩油压杆向上将钢模板撑起,配合间距伸缩油压杆的动作使钢模板向上屈起;
步骤c2、主梁支撑桁架工作车及支撑桁架以连接在主梁支撑桁架工作车下方的移动式台车的主梁支撑桁架伸缩油压杆推向外侧至定位,所有移动台车以插销固定;
步骤c3、卸除前、后前导桁架的移动插销,后方前导桁架与定位杆以插销连接固定;
步骤c4、以前导桁架前驱油压设备将前导桁架向前推出至定位并以插销固定;
步骤c5、以主梁支撑桁架前驱油压设备将主梁支撑桁架工作车及支撑桁架向前推进,借由移动式台车与固定式台车上的纵向推进滚轮移动至定位;
步骤c6、当前导桁架与下一跨钢框支撑架接续后,前导桁架与定位杆以插销连接固定,卸除后方前导桁架与定位杆的插销连接;
步骤c7、续以主梁支撑桁架前驱油压设备将主梁支撑桁架工作车及支撑桁架向前推进至定位,主梁支撑桁架工作车及支撑桁架与下一跨移动式台车接合定位后,以插销固定;
步骤c8、以前导桁架前驱油压设备将前导桁架向下一跨方向收拢,固定移动插销;
步骤c9、卸除所有移动式台车的固定插销;
步骤c10、两侧的支撑桁架以间距伸缩油压杆向前伸出,屈伸式钢模板以钢模屈起伸缩油压杆向下缩回将钢模板展平;
步骤c11、主梁支撑桁架工作车设备以连接在下方移动式台车的主梁支撑桁架伸缩油压杆推向内缩回定位,所有移动台车以插销固定,至此完成上部结构钢模板组合;
步骤c12、升起油压升降设备的升降支承至一定高度,与通道层架钢梁连接且固定;
步骤c13、油压升降设备由下往上将通道层架升高至定位;由地面水平相应的两侧以简易移动设备推入基座层架的A单元与B单元以螺栓锁固接合基板,下降通道层架与基座层架组合,以螺栓固结接合基板;
步骤c14、分离升降支承与通道层架的钢梁连接,以水平度推向桥梁墩柱间的空间收合,下降至定位,至此完成上部结构钢模板与主梁支撑桁架工作车至施工定位;
步骤c15、测量及高程调整;
步骤c16、使用基座层架下方的油压千斤顶调整高程;
步骤c17、于上部结构钢模板上方绑扎上部结构底板钢筋、腹板钢筋及安装必要的施作组件;
步骤c18、浇置上部结构底板混凝土及腹板混凝土至30公分高;
步骤c19、混凝土养护;
步骤c20、下降内模工作台车的上下移动钢模板下方的油压千斤顶至定位,使伸缩油压杆缩回将侧向移动钢模板收回至定位,完成脱模;
步骤c21、下降内模工作台车下方的油压千斤顶使滚轮与混凝土面接触;
步骤c22、依序移动内模工作台车至下一跨定位;
步骤c23、测量及高程调整;
步骤c24、使用内模工作台车下方的油压千斤顶调整高程;
步骤c25、绑扎上部结构顶板钢筋;
步骤c26、浇置上部结构腹板混凝土及顶板混凝土;
步骤c27、混凝土养护。
10、如权利要求6所述的桥梁上部结构施工使用的升降式施工方法,其特征在于:步骤D包括:
步骤d1、下降基座层架下方的油压千斤顶脱模;
步骤d2、升起油压升降设备的升降支承至一定高度,与通道层架钢梁连接且固定;
步骤d3、拆除上方通道层架与基座层架间的接合基板螺栓及基座层架的A单元与B单元接合基板螺栓,油压升降设备上升5公分;
步骤d4、使用移动设备将基座层架的A单元与B单元在地面水平反方向拉出移除;
步骤d5、下降通道层架至与地面接触为止;
步骤d6、升起油压升降设备的升降支承至与通道层架钢梁连接且固定;
步骤d7、拆除上方台车层架与通道层架间的接合基板螺栓及通道层架的A单元与B单元接合基板螺栓,油压升降设备上升5公分;
步骤d8、使用简易移动设备将通道层架的A单元与B单元在地面水平反方向拉出移除。
步骤d9、下降台车层架至与地面接触为止;
步骤d10、依序拆除屈伸式钢模板、模板横梁、支撑桁架、主梁支撑桁架工作车、移动式台车与固定式台车、台车层架、油压升降设备。
PCT/CN2015/095505 2015-11-25 2015-11-25 桥梁上部结构施工使用的升降式施工系统及其施工方法 WO2017088117A1 (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
PCT/CN2015/095505 WO2017088117A1 (zh) 2015-11-25 2015-11-25 桥梁上部结构施工使用的升降式施工系统及其施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/CN2015/095505 WO2017088117A1 (zh) 2015-11-25 2015-11-25 桥梁上部结构施工使用的升降式施工系统及其施工方法

Publications (1)

Publication Number Publication Date
WO2017088117A1 true WO2017088117A1 (zh) 2017-06-01

Family

ID=58762854

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2015/095505 WO2017088117A1 (zh) 2015-11-25 2015-11-25 桥梁上部结构施工使用的升降式施工系统及其施工方法

Country Status (1)

Country Link
WO (1) WO2017088117A1 (zh)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107254847A (zh) * 2017-06-15 2017-10-17 上海颖川路桥科技有限公司 一种城市环形立交同步顶升钢支撑结构
CN107268452A (zh) * 2017-08-11 2017-10-20 山东省路桥集团有限公司 移动模架底模工作车及过孔施工方法
CN108004932A (zh) * 2017-12-14 2018-05-08 河南省交通规划设计研究院股份有限公司 利用梁下运梁方式施工钢混组合梁的方法
CN108118620A (zh) * 2017-12-30 2018-06-05 中建三局集团有限公司 用于桥塔施工的整体自爬式集成平台及其施工方法
CN109267487A (zh) * 2018-10-15 2019-01-25 中建三局第二建设工程有限责任公司 一种长悬挑大截面盖梁托架体系
CN109403220A (zh) * 2018-12-27 2019-03-01 中冶天工集团天津有限公司 一种悬索桥梁高墩钢模架拆除装置及其施工方法
CN109775551A (zh) * 2019-03-21 2019-05-21 广东省水利水电第三工程局有限公司 一种用于贝雷桥整体运输的吊装系统及其施工方法
CN110080116A (zh) * 2019-05-30 2019-08-02 甘肃路桥建设集团有限公司 一种大跨度预应力盖梁临时支撑装置及其施工方法
CN110863438A (zh) * 2019-12-27 2020-03-06 中铁宝桥集团有限公司 一种全方位桥梁安装调整设备及桥梁安装方法
CN113202027A (zh) * 2021-04-07 2021-08-03 中交路桥建设有限公司 一种现浇梁钢管桩支架快速拆除方法
CN114016413A (zh) * 2021-11-04 2022-02-08 中交二航局第四工程有限公司安徽混凝土装配化构件分公司 一种用于桥面板湿接缝的快速拆装模板装置及工艺
CN114622482A (zh) * 2022-04-11 2022-06-14 北京工业大学 分层式波纹管连接预制装配盖梁结构、施工方法及设计方法
WO2022252607A1 (zh) * 2021-05-31 2022-12-08 中铁十一局集团有限公司 一种桥梁用非标准预制构件快速对位系统及方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100814388B1 (ko) * 2007-08-28 2008-03-18 노윤근 차량통행중 교량 인상방법
CN101144259A (zh) * 2007-09-20 2008-03-19 中铁二局股份有限公司 大吨位整孔箱梁运输及架设施工方法
CN201704630U (zh) * 2010-05-25 2011-01-12 中铁十八局集团第三工程有限公司 混凝土现浇连续梁滑移模架
CN102251475A (zh) * 2010-05-19 2011-11-23 北京万桥兴业机械有限公司 变位平台运架一体机及桥梁架设方法
KR20150070578A (ko) * 2013-12-17 2015-06-25 남해이엔씨 주식회사 불규칙 경간을 갖는 구간의 거더 연속 시공방법
KR20150108625A (ko) * 2014-03-18 2015-09-30 컨텍이앤씨 주식회사 비자주식 빔 런처를 이용한 교량시공방법

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100814388B1 (ko) * 2007-08-28 2008-03-18 노윤근 차량통행중 교량 인상방법
CN101144259A (zh) * 2007-09-20 2008-03-19 中铁二局股份有限公司 大吨位整孔箱梁运输及架设施工方法
CN102251475A (zh) * 2010-05-19 2011-11-23 北京万桥兴业机械有限公司 变位平台运架一体机及桥梁架设方法
CN201704630U (zh) * 2010-05-25 2011-01-12 中铁十八局集团第三工程有限公司 混凝土现浇连续梁滑移模架
KR20150070578A (ko) * 2013-12-17 2015-06-25 남해이엔씨 주식회사 불규칙 경간을 갖는 구간의 거더 연속 시공방법
KR20150108625A (ko) * 2014-03-18 2015-09-30 컨텍이앤씨 주식회사 비자주식 빔 런처를 이용한 교량시공방법

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107254847A (zh) * 2017-06-15 2017-10-17 上海颖川路桥科技有限公司 一种城市环形立交同步顶升钢支撑结构
CN107268452B (zh) * 2017-08-11 2023-05-12 山东省路桥集团有限公司 移动模架底模工作车及过孔施工方法
CN107268452A (zh) * 2017-08-11 2017-10-20 山东省路桥集团有限公司 移动模架底模工作车及过孔施工方法
CN108004932A (zh) * 2017-12-14 2018-05-08 河南省交通规划设计研究院股份有限公司 利用梁下运梁方式施工钢混组合梁的方法
CN108004932B (zh) * 2017-12-14 2023-10-03 河南省交通规划设计研究院股份有限公司 利用梁下运梁方式施工钢混组合梁的方法
CN108118620A (zh) * 2017-12-30 2018-06-05 中建三局集团有限公司 用于桥塔施工的整体自爬式集成平台及其施工方法
CN108118620B (zh) * 2017-12-30 2023-07-18 中建三局集团有限公司 用于桥塔施工的整体自爬式集成平台及其施工方法
CN109267487A (zh) * 2018-10-15 2019-01-25 中建三局第二建设工程有限责任公司 一种长悬挑大截面盖梁托架体系
CN109403220A (zh) * 2018-12-27 2019-03-01 中冶天工集团天津有限公司 一种悬索桥梁高墩钢模架拆除装置及其施工方法
CN109403220B (zh) * 2018-12-27 2024-03-26 中冶天工集团天津有限公司 一种悬索桥梁高墩钢模架拆除装置及其施工方法
CN109775551A (zh) * 2019-03-21 2019-05-21 广东省水利水电第三工程局有限公司 一种用于贝雷桥整体运输的吊装系统及其施工方法
CN109775551B (zh) * 2019-03-21 2024-03-08 广东省水利水电第三工程局有限公司 一种用于贝雷桥整体运输的吊装系统及其施工方法
CN110080116A (zh) * 2019-05-30 2019-08-02 甘肃路桥建设集团有限公司 一种大跨度预应力盖梁临时支撑装置及其施工方法
CN110863438A (zh) * 2019-12-27 2020-03-06 中铁宝桥集团有限公司 一种全方位桥梁安装调整设备及桥梁安装方法
CN113202027A (zh) * 2021-04-07 2021-08-03 中交路桥建设有限公司 一种现浇梁钢管桩支架快速拆除方法
WO2022252607A1 (zh) * 2021-05-31 2022-12-08 中铁十一局集团有限公司 一种桥梁用非标准预制构件快速对位系统及方法
CN114016413A (zh) * 2021-11-04 2022-02-08 中交二航局第四工程有限公司安徽混凝土装配化构件分公司 一种用于桥面板湿接缝的快速拆装模板装置及工艺
CN114016413B (zh) * 2021-11-04 2024-01-26 中交二航局第四工程有限公司安徽混凝土装配化构件分公司 一种用于桥面板湿接缝的快速拆装模板装置及工艺
CN114622482A (zh) * 2022-04-11 2022-06-14 北京工业大学 分层式波纹管连接预制装配盖梁结构、施工方法及设计方法
CN114622482B (zh) * 2022-04-11 2024-05-10 北京工业大学 分层式波纹管连接预制装配盖梁结构、施工方法及设计方法

Similar Documents

Publication Publication Date Title
WO2017088117A1 (zh) 桥梁上部结构施工使用的升降式施工系统及其施工方法
WO2020013473A1 (ko) 배전선로용 간접활선 인상장치 및 이를 이용한 간접활선 무정전공법
WO2021025256A1 (ko) 축조물 시공 장치
WO2011102595A2 (ko) 아칭효과를 이용한 보강형 자립식 흙막이 구조체 및 이를 이용한 지중굴착 시공방법
WO2014035169A1 (ko) 농업용 방제로봇 및 농업용 방제 로봇 시스템
WO2019177260A1 (ko) 동작 모드에 따라 자세가 제어되는 근력 보조 장치
WO2019177276A1 (ko) 절연인상기능 케이블클램프 접속장치 및 그 장치를 이용한 간접활선 무정전 배전공법
WO2011037304A1 (ko) 슬라브 패널 및 그의 설치 시스템, 슬라브 패널의 조립 및 해체 방법
WO2019132140A1 (ko) 필터 프레스
CN101522334A (zh) 冲压加工方法及冲压加工装置
WO2018088622A1 (ko) 가변기능을 갖는 종이판재용 접이 시스템 및 가변방법
WO2015026019A1 (ko) 이물처리시스템 및 이를 이용한 이물처리방법
JP5394334B2 (ja) 高所作業用作業床の施工方法
WO2011055947A9 (ko) 이동식 다기능 테이블 리프트
WO2016076625A1 (ko) 염전 소금채집장치
WO2017084113A1 (zh) 墩柱施工使用的组装升降式施工平台及其施工法
WO2011155726A2 (ko) 대형 프레스의 소재 이송장치
WO2015190812A1 (ko) 배전설비 활선작업 방법
WO2019066126A1 (en) CURVED DISPLAY PANEL CONNECTING APPARATUS
WO2013006009A2 (ko) 화물창용 고소작업대
WO2018093007A1 (ko) 리프트 테이블용 승강 장치
WO2019225855A1 (ko) 트러스를 구비한 경사부 적층형 시스템 데크
WO2016105096A1 (ko) 차량의 필러부재 및, 롤포밍부재
WO2020242084A1 (ko) 벤딩 머신
WO2019013506A1 (ko) 이에프이엠 및 이에프이엠 시스템

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 15909029

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 15909029

Country of ref document: EP

Kind code of ref document: A1