WO2015188694A1 - 一种地下核电站大件吊装运输方法 - Google Patents
一种地下核电站大件吊装运输方法 Download PDFInfo
- Publication number
- WO2015188694A1 WO2015188694A1 PCT/CN2015/079881 CN2015079881W WO2015188694A1 WO 2015188694 A1 WO2015188694 A1 WO 2015188694A1 CN 2015079881 W CN2015079881 W CN 2015079881W WO 2015188694 A1 WO2015188694 A1 WO 2015188694A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- combined
- nuclear power
- nuclear
- construction
- cavern
- Prior art date
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C19/00—Cranes comprising trolleys or crabs running on fixed or movable bridges or gantries
- B66C19/02—Cranes comprising trolleys or crabs running on fixed or movable bridges or gantries collapsible
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C17/00—Overhead travelling cranes comprising one or more substantially horizontal girders the ends of which are directly supported by wheels or rollers running on tracks carried by spaced supports
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C2700/00—Cranes
- B66C2700/01—General aspects of mobile cranes, overhead travelling cranes, gantry cranes, loading bridges, cranes for building ships on slipways, cranes for foundries or cranes for public works
-
- G—PHYSICS
- G21—NUCLEAR PHYSICS; NUCLEAR ENGINEERING
- G21C—NUCLEAR REACTORS
- G21C19/00—Arrangements for treating, for handling, or for facilitating the handling of, fuel or other materials which are used within the reactor, e.g. within its pressure vessel
- G21C19/02—Details of handling arrangements
Definitions
- the invention relates to the technical field of nuclear engineering, in particular to a method for hoisting and transporting large parts of underground nuclear power plants.
- the underground is mainly nuclear islands, including nuclear reactor building caverns, nuclear auxiliary building caverns, safe factory caverns, nuclear fuel plant caverns, etc.
- Large equipment such as ring crane girders, reactor pressure vessels, steam generators, voltage regulators and main coolant pumps, and containment dome linings are arranged in the room, which not only need to be transported in smaller underground passages, but also The hoisting is completed in a limited underground space. In this case, the conventional ground nuclear power plant bulk transport and hoisting methods cannot be implemented, and only new measures are taken to deal with them.
- the object of the present invention is to overcome the deficiencies of the above background art and to provide a method for hoisting and transporting large underground nuclear power plants, which satisfies the hoisting and transportation requirements of large-scale equipment of commercial underground nuclear power plants.
- the invention provides a method for hoisting and transporting large-scale underground nuclear power plants, comprising the following steps: Step 1: When the nuclear reactor building is built into the rock anchor beam layer, the concrete is poured, and after the concrete reaches the age to form the rock anchor beam, the concrete is passed. The hanging shaft at the top of the nuclear reactor building cavern is hoisted into the circular construction bridge machine, and the circular construction bridge machine is installed on the rock anchor beam through the car crane; Step 2: continue the construction of the nuclear reactor building cavern and complete the excavation work, using the ring The construction bridge machine carries out the installation of the safety shell cylinder and the endless crane rail beam until the installation is completed.
- the gantry crane hanging from one end of the end of the circular crane is hoisted into the hoisting crane shaft and sent into the nuclear reactor building cavern, and the ring construction bridge machine is used.
- Hanging the other end of the ring crane girders with the cooperation of the gantry crane and the ring-shaped construction bridge machine, make the ring crane big
- the beam is from vertical to horizontal and is mounted on the toroidal crane rail beam;
- Step 3 Using the ring crane rail beam and the ring crane girder as the support points for the mounting bracket of the safety shell dome steel lining, will be processed
- the safety shell dome steel lining piece is hoisted from the hanging shaft into the nuclear reactor building cavern, and is assembled and assembled on the mounting tire frame;
- Step 4: The equipment connected to the nuclear reactor building cavern is connected to each permanent large equipment in the nuclear reactor
- the transportation channel is transported to the safety shell, and then the ring crane girders are used to turn over and hoist to the working area.
- the construction of the combined cavern is carried out at the same time as the construction of the first step.
- the bridge crane is installed by the car crane to the upper leg of the combined cavern arranged along the length direction.
- the main traffic hole is used to transport the nuclear power auxiliary equipment to the installation platform on one side or one end of the combined cavern, and finally the nuclear power auxiliary equipment is hoisted to the working area through the plant bridge machine.
- the construction of the combined cavity is carried out simultaneously with the construction of the second step.
- the bridge crane is installed by the automobile crane to the upper leg of the combined cavity arranged along the length direction.
- the main traffic hole is used to transport the nuclear power auxiliary equipment to the installation platform on one side or one end of the combined cavern, and finally the nuclear power auxiliary equipment is hoisted to the working area through the plant bridge machine.
- the construction of the combined cavern is carried out at the same time as the construction of the third step.
- the bridge crane is installed by the car crane to the upper leg of the combined cavern arranged along the length direction.
- the main traffic hole is used to transport the nuclear power auxiliary equipment to the installation platform on one side or one end of the combined cavern, and finally the nuclear power auxiliary equipment is hoisted to the working area through the plant bridge machine.
- the construction of the combined cavern is carried out at the same time as the construction of the step 4.
- the bridge crane is installed by the car crane to the upper leg of the combined cavern arranged along the length direction.
- the main traffic hole is used to transport the nuclear power auxiliary equipment to the installation platform on one side or one end of the combined cavern, and finally the nuclear power auxiliary equipment is hoisted to the working area through the plant bridge machine.
- the construction of the combined cavern is carried out simultaneously with the construction of the first step to the fourth step.
- the bridge crane is installed by the automobile crane to the cattle arranged along the length direction in the upper part of the combined cavern.
- the nuclear power auxiliary equipment is then transported to the installation platform on one side or one end of the combined cavern by the main traffic hole, and finally the nuclear power auxiliary equipment is hoisted to the working area through the factory bridge machine.
- step 5 performing the construction of the combined cavern, and after the excavation of the combined cavern is completed, the bridge crane is installed by the automobile crane to the beef leg arranged along the length direction in the upper part of the combined cavity, and then utilized.
- the main traffic hole transports the nuclear power auxiliary equipment to the installation platform on one side or one end of the combined cavern, and finally the nuclear power through the plant bridge machine Auxiliary equipment is hoisted to the work area.
- the combined cavern comprises a nuclear auxiliary building cavern arranged in a "one" shape along the length direction, two safety building caverns and a nuclear fuel plant cavern, wherein the nuclear auxiliary building cavern, a safety The plant cavern, the nuclear fuel plant cavern and the other safe plant cavern are connected in sequence, and the nuclear auxiliary plant cavern, the two safe house caverns and the nuclear fuel plant cavern are respectively connected to the main traffic hole, and the nuclear auxiliary plant hole
- the outer end surface of the chamber and one side of the nuclear fuel plant cavern are respectively provided with mounting platforms connected to the main traffic hole.
- the large-sized hoisting and transporting method of the underground nuclear power plant of the invention has the following beneficial effects: the technical problem of lifting and transporting large-sized equipment in the underground cavern of the large underground nuclear power plant is solved reasonably and conveniently.
- Figure 1 is a schematic view showing the structure of a large-scale hoisting and transporting method of an underground nuclear power plant in a nuclear reactor building;
- Figure 2 is a schematic diagram showing the structure of a large-scale hoisting and transportation method for underground nuclear power plants required for the nuclear house of the nuclear reactor building, taking the nuclear fuel plant cavern as an example;
- FIG. 3 is a schematic structural view of a transportation arrangement mode of an underground nuclear power plant involved in a large-sized hoisting and transportation method for an underground nuclear power plant according to the present invention
- FIG. 4 is a schematic view showing the process flow of a large-sized hoisting and transporting method for an underground nuclear power plant according to the present invention.
- the method for hoisting and transporting large underground nuclear power plants of the present invention relates to a nuclear reactor building cavern 1, a hanging shaft 2, a nuclear reactor 3, a ring crane beam 4, a gantry crane (not shown), and a containment dome steel.
- Lining 5 ring-shaped construction bridge machine 6, automobile crane (not shown), safety shell cylinder 7, combined cavern, installation platform 11, factory bridge machine 12, main traffic tunnel 13, equipment transportation channel 14, rock Anchor beam 15 and toroidal crane track beam 18.
- the combined cavity is disposed along the depth direction of the mountain, and the nuclear reactor building chamber 1 and the main traffic hole 13 are respectively disposed on two sides of the combined cavity.
- the nuclear reactor building chamber 1 is respectively disposed on two sides perpendicular to the depth direction of the mountain body, and is respectively provided with an electrical house cavity 16 and a pressure relief hole chamber 17, and the electrical house cavity 16 is vertically arranged in the depth direction of the mountain body.
- the combined cavity includes a nuclear auxiliary building chamber 8 arranged in a "one" shape along the length direction, and two safety building holes a chamber 9 and a nuclear fuel plant cavern 10, wherein a nuclear auxiliary plant cavern 8, a safety plant cavern 9, a nuclear fuel plant cavern 10 and another safe plant cavern 9 are connected in sequence, and the nuclear auxiliary plant cavern 8, Two safety plant chambers 9 and nuclear fuel plant chambers 10 are respectively connected to the main traffic hole 13, and the outer end surface of the nuclear auxiliary plant chamber 8 and one side of the nuclear fuel plant chamber 10 are respectively connected to the main traffic hole 13 Installation platform 11.
- the method for hoisting and transporting large parts of an underground nuclear power plant of the present invention comprises the following steps:
- step one When the nuclear reactor building cavern 1 is applied to the rock anchor beam layer, the concrete is poured. After the concrete reaches the age to form the rock anchor beam 15, the crane shaft 2 is suspended from the top of the nuclear reactor building. The ring-shaped construction bridge machine 6 is installed, and the ring-shaped construction bridge machine 6 is installed on the rock anchor beam 15 by the automobile crane. This is because the nuclear reactor building cavern 1 has a high elevation, and if the nuclear reactor building cavern 1 is completely constructed, the installation is completed. The circular construction bridge machine 6 requires a long length of the car suspension boom, and it is difficult to reach this length in general car cranes.
- the nuclear reactor building chamber 1 is also easy to operate in a relatively confined space, and the installation of the lifting shaft 2 not only makes full use of the hoisting equipment on the ground, but also does not occupy the underground space too much. ;
- Step 2 Continue the construction of the nuclear reactor building chamber 1 and complete the excavation work, and install the safety casing cylinder 7 and the annular crane rail beam 18 by the annular construction bridge machine 6 until the installation is completed, the safety casing cylinder 7 and the ring shape
- the transportation of the crane rail beam 18 is completed by the equipment transport passage 14.
- the gantry crane hanging from the end of the end of the ring crane beam 4 is hoisted into the hoisting crane shaft 2 and sent into the nuclear reactor building cavern 1 and used to form a circular construction bridge.
- the machine 6 suspends the other end of the ring crane beam 4, and with the cooperation of the gantry crane and the ring-shaped construction bridge machine 6, the ring crane girder 4 is placed from the vertical state to the horizontal position, and is mounted on the ring crane rail beam 18, due to the safety shell
- the body 7 has been installed, so it is difficult to complete the construction of the ring crane beam 4 through the equipment transport passage 14.
- the safety shell dome steel lining 5 is not capped, and the ring crane beam 4 is hoisted through the hanging shaft 2 Entering the nuclear reactor building cavern 1 not only makes full use of the relatively open nuclear reactor building cavern 1 upper space, but also directly utilizes the newly installed ring construction 6 machine to avoid additional costs of construction equipment and time to speed up the progress of the project, reducing the cost of production;
- Step 3 Using the ring crane rail beam 18 and the ring crane beam 4 as the supporting support points of the mounting bracket of the safety shell dome steel lining 5, the processed safety shell dome steel lining 5 pieces from the lifting shaft 2 Hanging into a nuclear reactor plant In the chamber 1 and on the mounting frame, the pieces are welded and assembled. Because the space inside the nuclear reactor building 1 is limited, it is impossible to guarantee the construction site as well as the ground nuclear power plant. Only the existing components and space are used as the Force support point, and on this basis, the split welding assembly of the safety shell dome steel liner 5;
- Step 4 transporting each permanent large equipment in the nuclear reactor 3 to the containment vessel 7 through the equipment transport passage 14 connected to the nuclear reactor building chamber 1 by passing these permanent large equipment through the large flatbed (not shown in the figure) And transported to the equipment gate of the containment cylinder 7 (not shown) along the rails disposed on the equipment transport passage 14, and then transported into the containment cylinder 7 through the equipment gate and placed into the containment cylinder 7
- the ring crane girders 4 are used to turn over and hoist to the working position. Since each permanent large equipment in the nuclear reactor 3 must wait until the containment steel lining 5 is capped, it can be installed. It is possible to continue lifting with the hanging shaft 2, so that only the equipment transport passage 14 can be fully utilized for lifting and transporting through the equipment gate and the working platform in the containment cylinder 7;
- the fuel plant cavern 10 is taken as an example to illustrate the fifth step: the construction of the combined cavern, the electrical building cavern 16 and the pressure relief cavern 17 is performed, and the combined cavern, the electrical building cavern 16 and the pressure relief cavern are used.
- the plant bridge machine 12 is installed on the cattle legs arranged along the length direction in the upper part of the combined cavern by the automobile crane, and then the nuclear power auxiliary equipment is transported to the side or end of the combined cavern by the main traffic hole 13 On the installation platform 11, finally, the nuclear power auxiliary equipment is hoisted to the working area through the factory bridge machine 12. Since the length of the combined cavity is long, the crane hoist can fully utilize this feature to install and construct the factory bridge machine 12. It is not subject to the space limitation of the nuclear reactor building 1 in the pre-order step.
- step 5 can also be carried out simultaneously with the construction of step 1, step two, step three or step four, or simultaneously with the construction of step one, step two, step three and step four.
- the invention fully utilizes the existing equipment in the large underground nuclear power plant, combines the characteristics of the underground space and the underground construction, and solves the technical problem of hoisting transportation of the large-scale equipment in the underground cavern of the large underground nuclear power plant reasonably and conveniently, and provides the construction of the underground space. A new idea.
Abstract
Description
Claims (8)
- 一种地下核电站大件吊装运输方法,其特征在于:包括如下步骤:步骤一:当核反应堆厂房洞室(1)施工到岩锚梁层时进行混凝土的浇筑,待混凝土达到龄期形成岩锚梁(15)后,通过核反应堆厂房洞室(1)顶部的吊物竖井(2)吊入环形施工桥机(6),并通过汽车吊将环形施工桥机(6)安装到岩锚梁(15)上;步骤二:继续核反应堆厂房洞室(1)的施工并完成开挖工作,利用环形施工桥机(6)进行安全壳筒体(7)和环形吊车轨道梁(18)的安装直至完成安装,通过吊住环形吊车大梁(4)一端的龙门吊向吊物竖井(2)吊入环形吊车大梁(4)并送入核反应堆厂房洞室(1)内,利用环形施工桥机(6)吊住环形吊车大梁(4)的另一端,在龙门吊和环形施工桥机(6)的配合下,使环形吊车大梁(4)由竖直状态直至水平,并安装到环形吊车轨道梁(18)上;步骤三:利用环形吊车轨道梁(18)和环形吊车大梁(4)作为安全壳穹顶钢里衬(5)的安装胎架的受力支撑点,将加工好的安全壳穹顶钢里衬(5)分片从吊物竖井(2)吊入核反应堆厂房洞室(1)内,并在安装胎架上分片焊接拼装;步骤四:将核反应堆(3)内的各个永久大型设备通过与核反应堆厂房洞室(1)相连的设备运输通道(14)运至安全壳筒体(7)内,再利用环形吊车大梁(4)进行翻身以及吊装到工作区位。
- 根据权利要求1所述的地下核电站大件吊装运输方法,其特征在于:按步骤一施工的同时进行组合洞室的施工,当组合洞室的开挖完成后,利用汽车吊将厂房桥机(12)安装到组合洞室上部沿长度方向布置的牛腿上,随后利用主交通洞(13)将核电辅助设备运到位于组合洞室一侧或一端的安装平台(11)上,最后通过厂房桥机(12)将核电辅助设备吊装到工作区位。
- 根据权利要求1所述的地下核电站大件吊装运输方法,其特征在于:按步骤二施工的同时进行组合洞室的施工,当组合洞室的开挖完成后,利用汽车吊将厂房桥机(12)安装到组合洞室上部沿长度方向布置的牛腿上,随后利用主交通洞(13)将核电辅助设 备运到位于组合洞室一侧或一端的安装平台(11)上,最后通过厂房桥机(12)将核电辅助设备吊装到工作区位。
- 根据权利要求1所述的地下核电站大件吊装运输方法,其特征在于:按步骤三施工的同时进行组合洞室的施工,当组合洞室的开挖完成后,利用汽车吊将厂房桥机(12)安装到组合洞室上部沿长度方向布置的牛腿上,随后利用主交通洞(13)将核电辅助设备运到位于组合洞室一侧或一端的安装平台(11)上,最后通过厂房桥机(12)将核电辅助设备吊装到工作区位。
- 根据权利要求1所述的地下核电站大件吊装运输方法,其特征在于:按步骤四施工的同时进行组合洞室的施工,当组合洞室的开挖完成后,利用汽车吊将厂房桥机(12)安装到组合洞室上部沿长度方向布置的牛腿上,随后利用主交通洞(13)将核电辅助设备运到位于组合洞室一侧或一端的安装平台(11)上,最后通过厂房桥机(12)将核电辅助设备吊装到工作区位。
- 根据权利要求1所述的地下核电站大件吊装运输方法,其特征在于:按步骤一至步骤四施工的同时进行组合洞室的施工,当组合洞室的开挖完成后,利用汽车吊将厂房桥机(12)安装到组合洞室上部沿长度方向布置的牛腿上,随后利用主交通洞(13)将核电辅助设备运到位于组合洞室一侧或一端的安装平台(11)上,最后通过厂房桥机(12)将核电辅助设备吊装到工作区位。
- 根据权利要求1所述的地下核电站大件吊装运输方法,其特征在于:步骤五:进行组合洞室的施工,当组合洞室的开挖完成后,利用汽车吊将厂房桥机(12)安装到组合洞室上部沿长度方向布置的牛腿上,随后利用主交通洞(13)将核电辅助设备运到位于组合洞室一侧或一端的安装平台(11)上,最后通过厂房桥机(12)将核电辅助设备吊装到工作区位。
- 根据权利要求2至7中任一项所述的地下核电站大件吊装运输方法,其特征在于: 所述组合洞室包括沿长度方向呈“一”字布置的核辅助厂房洞室(8)、两个安全厂房洞室(9)和核燃料厂房洞室(10),其中,核辅助厂房洞室(8)、一个安全厂房洞室(9)、核燃料厂房洞室(10)和另一个安全厂房洞室(9)依次相连,所述核辅助厂房洞室(8)、两个安全厂房洞室(9)和核燃料厂房洞室(10)分别与主交通洞(13)相连,所述核辅助厂房洞室(8)的外端面和核燃料厂房洞室(10)的一侧分别设有与主交通洞(13)相连的安装平台(11)。
Priority Applications (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
RU2017100926A RU2655088C1 (ru) | 2014-06-13 | 2015-05-27 | Способ подъема и транспортировки крупных частей подземной атомной электростанции |
JP2017517167A JP6431601B2 (ja) | 2014-06-13 | 2015-05-27 | 地下原子力発電所の大物吊上げ搬送方法 |
US15/376,586 US10544014B2 (en) | 2014-06-13 | 2016-12-12 | Method for hoisting and transporting assemblies in underground nuclear power plant |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410264483.6 | 2014-06-13 | ||
CN201410264483.6A CN104060830B (zh) | 2014-06-13 | 2014-06-13 | 一种地下核电站大件吊装运输方法 |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US15/376,586 Continuation-In-Part US10544014B2 (en) | 2014-06-13 | 2016-12-12 | Method for hoisting and transporting assemblies in underground nuclear power plant |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2015188694A1 true WO2015188694A1 (zh) | 2015-12-17 |
Family
ID=51548743
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/CN2015/079881 WO2015188694A1 (zh) | 2014-06-13 | 2015-05-27 | 一种地下核电站大件吊装运输方法 |
Country Status (5)
Country | Link |
---|---|
US (1) | US10544014B2 (zh) |
JP (1) | JP6431601B2 (zh) |
CN (1) | CN104060830B (zh) |
RU (1) | RU2655088C1 (zh) |
WO (1) | WO2015188694A1 (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107587722A (zh) * | 2017-09-26 | 2018-01-16 | 中国水利水电第七工程局有限公司 | 一种地下厂房岩壁吊车梁钢筋超前安装工艺及其钢筋自稳结构 |
CN112589347A (zh) * | 2020-12-03 | 2021-04-02 | 中国核工业二四建设有限公司 | 一种应用于核电站钢衬里模块整体拼装的调整工装及系统 |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104060830B (zh) * | 2014-06-13 | 2015-05-06 | 长江勘测规划设计研究有限责任公司 | 一种地下核电站大件吊装运输方法 |
CN109019468B (zh) * | 2018-07-13 | 2021-08-17 | 中国核工业二三建设有限公司 | Acp1000核电站重型设备引入方法 |
CN109530388B (zh) * | 2018-10-31 | 2021-07-09 | 东华理工大学 | 一种基于盐穴的放射性核废物回收装置 |
CN113086841B (zh) * | 2021-04-13 | 2022-10-21 | 索通发展股份有限公司 | 一种用于焙烧炉墙修复的吊篮装置 |
CN114348891A (zh) * | 2022-01-07 | 2022-04-15 | 中国电建集团华东勘测设计研究院有限公司 | 用于地下厂房桥机拆装的起吊设备及桥机拆装施工方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09202587A (ja) * | 1996-01-22 | 1997-08-05 | Mitsubishi Heavy Ind Ltd | 長尺重量物の吊下移送装置 |
CN103015715A (zh) * | 2012-11-19 | 2013-04-03 | 中国核工业华兴建设有限公司 | 核电站外壳双屋面板施工方法 |
CN103291075A (zh) * | 2013-06-27 | 2013-09-11 | 中广核工程有限公司 | 核电厂大型模块制造方法 |
CN103342321A (zh) * | 2013-06-28 | 2013-10-09 | 中广核工程有限公司 | 在役核电站蒸汽发生器的整体更换吊装方法 |
CN104060830A (zh) * | 2014-06-13 | 2014-09-24 | 长江勘测规划设计研究有限责任公司 | 一种地下核电站大件吊装运输方法 |
Family Cites Families (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4181231A (en) * | 1977-08-22 | 1980-01-01 | Paceco Division of Fruehauf Corporation | Polar wye crane |
JPS57156900U (zh) * | 1981-03-27 | 1982-10-02 | ||
JPS6184588A (ja) * | 1984-10-03 | 1986-04-30 | 株式会社日立製作所 | 地下式原子力発電所 |
DE69018644T2 (de) * | 1990-08-14 | 1995-09-07 | Moritaka Ishimaru | Atomkraftwerk und bauverfahren dafür. |
RU2072961C1 (ru) * | 1993-05-26 | 1997-02-10 | Отверченко Анатолий Алексеевич | Консольный передвижной кран |
US6017181A (en) * | 1994-05-27 | 2000-01-25 | J&R Engineering Co., Inc. | Cask transporter |
JP3888564B2 (ja) * | 1997-08-28 | 2007-03-07 | 株式会社大林組 | 地中構造物の構築方法 |
JP2000338278A (ja) * | 1999-05-28 | 2000-12-08 | Toshiba Corp | 原子力コジェネプラント |
JP2007232420A (ja) * | 2006-02-28 | 2007-09-13 | Hitachi Ltd | 原子炉格納容器 |
JP4150063B1 (ja) * | 2007-07-18 | 2008-09-17 | 芳人 小林 | 地下構造体の施工方法及び該方法によって得られる地下構造体並びに地下立地式原子力発電所 |
JP2012126482A (ja) * | 2010-12-14 | 2012-07-05 | Hitachi-Ge Nuclear Energy Ltd | 天井クレーン |
CH705099A2 (de) * | 2011-06-07 | 2012-12-14 | Bjoern Sigurd Rump | Kernreaktor, unterirdisch in einer Kaverne angelegt. |
CN102518311B (zh) * | 2011-12-20 | 2014-12-03 | 中国核工业二三建设有限公司 | 安装核电站核岛端梁的方法 |
JP6066164B2 (ja) * | 2012-06-07 | 2017-01-25 | 三菱重工業株式会社 | 重量機器の据付工法 |
CN202899128U (zh) * | 2012-08-20 | 2013-04-24 | 长江勘测规划设计研究有限责任公司 | 主承载锚杆应力可全过程调节的岩锚吊车梁 |
-
2014
- 2014-06-13 CN CN201410264483.6A patent/CN104060830B/zh active Active
-
2015
- 2015-05-27 RU RU2017100926A patent/RU2655088C1/ru active
- 2015-05-27 WO PCT/CN2015/079881 patent/WO2015188694A1/zh active Application Filing
- 2015-05-27 JP JP2017517167A patent/JP6431601B2/ja active Active
-
2016
- 2016-12-12 US US15/376,586 patent/US10544014B2/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09202587A (ja) * | 1996-01-22 | 1997-08-05 | Mitsubishi Heavy Ind Ltd | 長尺重量物の吊下移送装置 |
CN103015715A (zh) * | 2012-11-19 | 2013-04-03 | 中国核工业华兴建设有限公司 | 核电站外壳双屋面板施工方法 |
CN103291075A (zh) * | 2013-06-27 | 2013-09-11 | 中广核工程有限公司 | 核电厂大型模块制造方法 |
CN103342321A (zh) * | 2013-06-28 | 2013-10-09 | 中广核工程有限公司 | 在役核电站蒸汽发生器的整体更换吊装方法 |
CN104060830A (zh) * | 2014-06-13 | 2014-09-24 | 长江勘测规划设计研究有限责任公司 | 一种地下核电站大件吊装运输方法 |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107587722A (zh) * | 2017-09-26 | 2018-01-16 | 中国水利水电第七工程局有限公司 | 一种地下厂房岩壁吊车梁钢筋超前安装工艺及其钢筋自稳结构 |
CN112589347A (zh) * | 2020-12-03 | 2021-04-02 | 中国核工业二四建设有限公司 | 一种应用于核电站钢衬里模块整体拼装的调整工装及系统 |
Also Published As
Publication number | Publication date |
---|---|
RU2655088C1 (ru) | 2018-05-23 |
JP6431601B2 (ja) | 2018-11-28 |
JP2017524845A (ja) | 2017-08-31 |
US10544014B2 (en) | 2020-01-28 |
CN104060830B (zh) | 2015-05-06 |
CN104060830A (zh) | 2014-09-24 |
US20180002144A1 (en) | 2018-01-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2015188694A1 (zh) | 一种地下核电站大件吊装运输方法 | |
CN103510529B (zh) | 用于水下高桩承台施工的钢吊箱系统及施工工艺 | |
CN108019076A (zh) | 大直径钢筋混凝土筒仓施工方法及用于锥壳施工的装置 | |
CN103410094B (zh) | 桥梁刚性铰的安装施工方法 | |
CN102235107B (zh) | 烟囱钢内筒的液压提升施工方法 | |
US20210231014A1 (en) | Full-circle secondary lining inverted arch construction formwork system for long-distance tunnel and formwork transporting method | |
CN103510541B (zh) | 一种吊装架洞内吊装安装钢管柱的装置 | |
CN103938875A (zh) | 单层弦支穹顶地面单体张拉提升施工方法 | |
JP2017524845A5 (zh) | ||
CN108867672A (zh) | 一种双壁钢围堰拼接方法 | |
CN103967284B (zh) | 预留柱头对接的钢柱安装方法 | |
CN105908843A (zh) | 一种双层拱顶储罐同步倒装施工方法 | |
CN104016260B (zh) | 小格漏斗滑移安装方法及滑移安装机构 | |
CN202139255U (zh) | 转炉本体设备安装的工装平台 | |
CN106836829A (zh) | 一种环吊牛腿的安装结构及其安装方法 | |
CN212503680U (zh) | 一种大型桥机重大件的起吊系统 | |
CN107675792A (zh) | 钢结构悬挑连廊结构及施工方法 | |
CN104058333B (zh) | 一种地下核电站反应堆厂房环形吊车大梁吊装方法 | |
CN104060838B (zh) | 一种通廊分组空中组对安装法 | |
CN203007965U (zh) | 用于水下高桩承台施工的钢吊箱系统 | |
CN207062916U (zh) | 一种分体安装式升压站 | |
CN102392550A (zh) | 烟气脱硫吸收塔倒序安装方法 | |
CN104627849A (zh) | 一种用于内天井管道吊装的吊装设备及吊装方法 | |
CN107975148B (zh) | 主系统设备预引入方法 | |
CN203638979U (zh) | 用于低温储罐内罐底板安装的装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 15806043 Country of ref document: EP Kind code of ref document: A1 |
|
ENP | Entry into the national phase |
Ref document number: 2017517167 Country of ref document: JP Kind code of ref document: A |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
ENP | Entry into the national phase |
Ref document number: 2017100926 Country of ref document: RU Kind code of ref document: A |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 15806043 Country of ref document: EP Kind code of ref document: A1 |