WO2004020745A1 - Gründung für wasserbauwerke - Google Patents

Gründung für wasserbauwerke Download PDF

Info

Publication number
WO2004020745A1
WO2004020745A1 PCT/DE2003/002139 DE0302139W WO2004020745A1 WO 2004020745 A1 WO2004020745 A1 WO 2004020745A1 DE 0302139 W DE0302139 W DE 0302139W WO 2004020745 A1 WO2004020745 A1 WO 2004020745A1
Authority
WO
WIPO (PCT)
Prior art keywords
shaft element
foundation
caisson
shaft
channel
Prior art date
Application number
PCT/DE2003/002139
Other languages
German (de)
English (en)
French (fr)
Inventor
Helmut Schwarz
Klaus Dietz
Original Assignee
Stump Spezialtiefbau Gmbh
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Stump Spezialtiefbau Gmbh filed Critical Stump Spezialtiefbau Gmbh
Priority to AU2003257378A priority Critical patent/AU2003257378A1/en
Priority to EP03790630A priority patent/EP1530662A1/de
Publication of WO2004020745A1 publication Critical patent/WO2004020745A1/de

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/50Anchored foundations
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/20Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
    • F03D13/22Foundations specially adapted for wind motors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0091Offshore structures for wind turbines
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F05INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
    • F05BINDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
    • F05B2240/00Components
    • F05B2240/90Mounting on supporting structures or systems
    • F05B2240/95Mounting on supporting structures or systems offshore
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/727Offshore wind turbines
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P70/00Climate change mitigation technologies in the production process for final industrial or consumer products
    • Y02P70/50Manufacturing or production processes characterised by the final manufactured product

Definitions

  • the invention relates to a method for producing a foundation for hydraulic structures, in particular an offshore foundation for a wind turbine, and a foundation produced by the method.
  • a complete foundation element can be prefabricated and lowered to the bottom of the water using a transport and lifting ship and assembled there.
  • a transport and lifting ship For anchoring wind turbines, it is known to lower a steel tube with a corresponding diameter and length vertically onto the ground and to ram into the ground by a sufficient length.
  • the tower for the wind turbine can then be mounted on the end reaching above the water level.
  • the invention is therefore based on the object of creating a method for producing a foundation for hydraulic structures, in particular offshore foundation for a wind turbine, with which such a foundation can be produced with reasonable economic outlay and sufficient stability. Furthermore, the invention is based on the object of creating a platform founded in a body of water which can be produced with economically justifiable outlay and which has a high degree of stability.
  • the invention is based on the knowledge that a foundation for a hydraulic structure can also be produced in great water depths with reasonable effort and high stability if a caisson with a vertically extending shaft is lowered to the bottom of the water and there by means of an anchor partially received in the shaft is biased.
  • the foundation element is anchored by drilling an anchor hole through a channel provided in the shaft, this channel and the interior of the caisson serving as an empty hole.
  • the anchor After the anchor hole has been drilled through the shaft in the subsurface, the anchor can be installed in the usual way.
  • the foundation element By biasing the at least an anchor tension member opposite an abutment in or at the upper end of the shaft, the foundation element is securely anchored and at the same time receives a stability through which high transverse forces can also be absorbed.
  • settlement processes of the foundation element generated by the tensioning of the anchor can be waited for and only then can the hydraulic engineering structure to be founded be placed on the foundation element or produced on it.
  • the length of the shaft is dimensioned such that its upper end extends to above the surface of the water even after the caisson or the entire foundation element has been lowered onto the subsoil of the water. This has the advantage that the anchor hole can be drilled from the water surface.
  • the shaft can have a tubular inner shaft element which is connected at its lower end to the caisson.
  • the caisson has a breakthrough in continuation of the interior of the tubular inner shaft element.
  • the tubular inner shaft element is preferably mounted in the form of shots when the caisson is lowered.
  • the first “shot” of the inner shaft element can be formed in one piece with the caisson.
  • the connection of the shots to one another can take place during the lowering, for example by welding or by means of releasable connecting means.
  • the inner shaft element or the wefts can be designed as a steel tube or corresponding tube sections.
  • the inner shaft preferably has a diameter such that it can serve as a man pipe and / or supply pipe for the further assembly of the foundation element.
  • a compressed air lock can be provided at the upper end of the inner shaft element.
  • prefabricated annular outer shaft elements are placed on the inner shaft element, preferably before the anchor hole is sunk into the subsurface through the channel of the shaft.
  • Outer shaft elements which are preferably made of concrete, are preferably dimensioned such that the inner shaft element has a force-centering effect.
  • the inner diameter of the outer shaft elements can also be made significantly larger than the outer diameter of the inner shaft element in order to make it easier to slide on the outer shaft elements.
  • forced centering can be provided by providing guide and centering aids on the outer wall of the inner shaft element and / or on the inner wall of the outer shaft elements.
  • each shot can be made in front of the Lowering the shot in question (or the entire base element previously produced) into the water, one or more prefabricated outer shaft elements are placed.
  • the outer shaft elements can be connected in the axial direction, for example by means of a positive fit on the joints and / or special plug-in connections and / or concrete composite.
  • the outer shaft elements serve to further stabilize the shaft or form the outer wall of the shaft when the inner shaft element is later removed again.
  • the outer shaft elements are preferably prestressed so that the finished shaft can also absorb high tensile or bending tensile and / or transverse forces.
  • the prestressing is preferably carried out using prestressing elements which are arranged on the inner wall of the outer shank elements or within the shank wall itself.
  • the free space between the inner walls of the outer shaft elements and the outer wall of the inner shaft element can be filled with hardenable building material, for example concrete.
  • the caissons preferably the caissons and the inner shaft element
  • a hardenable building material preferably concrete
  • the channel has a diameter such that it is possible to produce a borehole in the subsurface through the channel.
  • the inner shaft element can be removed again.
  • this can be composed of shots with detachable connections.
  • the channel can be produced by means of a tubular element, for example a steel or plastic tube, which is introduced into the area of the shaft and the caisson, which is filled with the hardening building material.
  • the annular space surrounding the tubular element is then filled with the hardening building material. This can be done by using the contractor procedure.
  • the concrete is here by means of a feed line in the lower region of the foundation element, i. H. inserted in the lower area of the caisson and pushes the water or residual water in it upwards.
  • a work platform can be placed on the upper end of the shaft to produce the anchor. This enables the appropriate equipment, in particular a drilling platform, to be picked up in a simple manner.
  • the work platform can preferably be attached to the upper end of the shaft so that the upper end of the shaft is freely accessible. This way you can access the top
  • a head plate is placed on the shaft, which serves as an abutment for prestressing the armature or the at least one tension member of the armature.
  • an abutment can also be provided in the uppermost region of the shaft, against which the armature can be prestressed.
  • platform which is anchored to the water bottom by means of three such foundation elements.
  • Such a tripod creates an optimal compromise between the effort involved in the manufacture of such a platform and stability.
  • the platform itself can either be prefabricated and connected to the green by means of connecting structures on the underside of the platform. application elements that ensure a positive fit.
  • the platform can also be manufactured in the usual way on site and connected to the foundation elements, for example by concreting using appropriate formwork, if appropriate using suitable prefabricated parts.
  • Figure 1 is a schematic sectional view through a foundation element which is assembled and lowered in sections;
  • Figure 2 is a schematic sectional view of a lowered foundation element in the phase of processing the foundation horizon.
  • FIG. 3 shows a section along the line A-A in Fig. 2;
  • Figure 4 is a schematic sectional view of the fully assembled foundation element in the phase of drilling the anchor hole.
  • Fig. 5 is a section along the line B-B in Fig. 4;
  • Fig. 6 is a schematic sectional view of the foundation element in the phase of anchor installation
  • Fig. 7 is a section along the line C-C in Fig. 6;
  • Fig. 8 is a schematic partial sectional view of the finished hydraulic structure
  • Fig. 9 is a sectional view taken along the line DD in Fig. 8 and
  • Fig. 10 is a schematic partial sectional view of a further embodiment of a finished hydraulic structure.
  • Fig. 1 shows schematically in section or in side view a jack 1, with which a foundation element 3 for a hydraulic structure 5 ( Figures 8 and 9) can be manufactured or assembled.
  • the foundation element 3 comprises a caisson 7, which can have a pot-shaped structure, for example.
  • the underside of the cylindrical wall can be designed in a cutting-like manner in order to allow the caisson to easily penetrate into a soft surface 9 of the water.
  • the subsoil can consist of a rocky subsoil 9a, the upper edge of which forms the foundation horizon for the foundation element 3.
  • a sandy layer 9b and above it a silt layer 9c can be present on the rocky ground 9a.
  • the jack-up platform can be temporarily anchored to the subsurface by means of several stilts 11 and projects above the water level W.
  • the lifting island 1 has a crane device 13 with a mobile crane truck 15 on which a lifting plate 17 which can be raised and lowered vertically is arranged.
  • a lifting plate 17 which can be raised and lowered vertically is arranged.
  • mounting parts (not shown) mounted on the lifting island 1 for producing the foundation element can be moved from a storage position into the mounting position shown in FIG. 1.
  • the lifting plate 17 is used for floating mounting and for lowering the part of the foundation element 3 that has already been assembled.
  • the foundation element 3 can be composed of individual wefts for an inner shaft element 19 and an outer shaft element 21.
  • Fig. 1 shows that the caisson 7 has an opening in its upper, horizontally running wall for receiving a first shot of the inner shaft element 19.
  • This first part of the inner shaft element 19 can also be preassembled due to the required sealing between the inner shaft element and the caisson.
  • the shots of the outer shaft element 21 can be assembled by means of a concrete composite and additionally connected by means of corresponding prestressing elements 23.
  • the prestressing elements 23 simultaneously serve for the floating mounting of the respectively prefabricated part of the foundation element 3 on the lifting plate 17 of the crane device 13.
  • the lifting island 1 also has a clamping device 25, with which the uppermost shot of the foundation element 3 which has been preassembled until then can be held in a clamping manner on the lifting island 1.
  • the lifting plate 17 can be detached from the foundation element 3 and a new shot can be put on for the inner shaft element 19 or the outer shaft element 21.
  • the weft for the inner shaft element 19 is preferably first placed and then the additional weft for the outer shaft element 21 is placed.
  • Each outer shaft element 21 can have radially inwardly extending projections 27 in the region of the upper end, which act as abutments for tensioning serve the biasing elements 23.
  • the uppermost shot for the outer shaft element 21 should have such projections 27 in order to ensure a continuous bracing in the final state. to enable all shots for the outer shaft element 21.
  • the lower abutment for the prestressing elements 23 is formed by the horizontally running wall of the caisson 7, as can be seen in FIG. 1.
  • guide and centering projections 29 extending radially outward can be formed on the outer wall of the shots for the inner shaft element 19.
  • the upper edges of the guide and centering projections 29 are designed to run obliquely downwards, so that when the first shot is placed for the outer shaft element 21, centering takes place first and then guidance is carried out over the vertical regions of the guide and centering projections 29.
  • an airlock 31 can be connected to the upper end of the inner shaft element 19. In this way, it is possible to apply compressed air to the entire interior of the inner shaft element 19 and the caisson 7 in such a way that all the water is pressed out of this interior. In this way it is possible to let assembly personnel descend via the airlock 31 via the interior of the inner shaft element 19 into the interior of the caisson 7.
  • the caisson then sits on the final foundation horizon, for example on the rocky subsoil 9a shown in FIG. 1, this can be examined by the ground staff for its nature and load-bearing capacity. If the floor does not meet the requirements for the load-bearing capacity, appropriate processing can be carried out, as shown in FIG. 2.
  • a device for the manufacture of ground seams was placed over the inner shaft element (still pressurized with compressed air).
  • the pegs can be introduced, for example, along an imaginary circle at equidistant intervals, as shown in FIG. 3.
  • FIG. 2 shows a further possibility for producing the foundation element, wherein a pontoon 35 is used which can carry a crane device 13 'floating on the water surface.
  • the pontoon can also be designed as a stilt pontoon. With such stilts pontons can be installed up to a water depth of approx. 30 meters.
  • Fig. 4 shows an assembly phase in which the foundation element 3 has already been manufactured except for its anchoring in the underground.
  • the inner shaft element 19 was first removed. This can be done by loosening the lower end of the inner shaft element 19 at the point of connection with the caisson and dismounting and pulling upwards in shots.
  • Inner shaft element 19 take place.
  • a shuttering tube 35 was introduced into the inner space of the outer shaft element 21.
  • the shutter pipe 35 can be made of plastic, for example.
  • the shuttering pipe 35 extends to the foundation horizon.
  • the cavity surrounding the shuttering tube 35 within the outer shaft element 21 or the caisson 7 was then filled with a hardening building material 37, for example concrete.
  • the tensioning elements 23 were prestressed with respect to the top of the hardened building material 37.
  • the tensioning elements 23 can be designed in the usual way, for example as
  • Prestressing strands that run in plastic pipes that are filled with corrosion protection Prestressing strands that run in plastic pipes that are filled with corrosion protection.
  • FIG. 4 based on the finished building to be produced in FIGS. 8 and 9, in which a tripod consists of three foundation elements 3 and a platform 41 placed thereon.
  • an anchor hole 45 can be drilled into the subsurface below the foundation horizon through the channel within the shutdown tube 35 by means of a drilling device 43 located on the platform.
  • the channel within the foundation element 3 serves as an empty hole.
  • the anchor can also be installed, likewise from the work platform 39, using an appropriate device, for example a crane.
  • an appropriate device for example a crane.
  • the tension element can be pulled off a drum with a correspondingly large radius.
  • the tension element 47 can be a steel anchor strand, for example. This is in the borehole 45th
  • FIGS. 8 and 9 The platform 41 can either be placed on the tripod of the foundation elements 3 as a prefabricated component, for example in a form-fitting manner, or else can be produced in a conventional manner, if appropriate using prefabricated components, on the upper ends of the foundation elements 3.
  • the tensioning of the tension elements 47 of the anchors can take place at the upper end relative to the platform 41 as an abutment.
  • the actual hydraulic structure for example the tower 49 of a wind turbine, can be mounted on the platform 41.
  • the tower 49 of the wind power plant is mounted on a platform which is analogous to that by means of foundation elements 3 in the form of a tripod
  • Figures 8 and 9 is anchored to the ground.
  • the platform 41 is however not above the water level W, but rather just above the subsurface in the water.
  • the foundation elements can largely be produced as described above.
  • a pressure lock can also be used under water during the manufacture or assembly of the foundation elements 3.
  • the platform 41 is preferably largely prefabricated in order to avoid the more complex production under water.
  • This embodiment has the advantage of significantly shorter foundation elements, and the anchors can be correspondingly shorter. Due to their lower height or length, the foundation elements can also be largely prefabricated without the problem of transporting the foundation elements to the installation site.
  • the foundation elements can be prefabricated except for the filling with the hardening building material 37, possibly together with the inner shaft element 19. If the subsoil is not processed from the caisson, the entire foundation element can also be prefabricated, apart from the installation of the anchor. In this case, only the caisson or part of it cannot yet be filled with hardenable building material. After the foundation element has been placed on the prepared foundation horizon, this part can be filled with hardenable building material via the channel or the shuttering tube 35, and the connection to the foundation horizon can thus be established. Prefabrication and assembly of an entire tripod with platform is also possible in this way.
  • the method according to the invention for producing a foundation element enables the simple and inexpensive construction or assembly of a foundation element even in great water depths, while at the same time ensuring sufficient stability for absorbing high transverse forces.
  • the invention is not limited to the exemplary embodiments presented above. It is of course readily possible for a person skilled in the art to create further embodiments which have other combinations of features which have been described above in connection with the two embodiments shown in the drawing.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • Mining & Mineral Resources (AREA)
  • Sustainable Energy (AREA)
  • Mechanical Engineering (AREA)
  • Combustion & Propulsion (AREA)
  • Chemical & Material Sciences (AREA)
  • Sustainable Development (AREA)
  • Foundations (AREA)
PCT/DE2003/002139 2002-08-22 2003-06-26 Gründung für wasserbauwerke WO2004020745A1 (de)

Priority Applications (2)

Application Number Priority Date Filing Date Title
AU2003257378A AU2003257378A1 (en) 2002-08-22 2003-06-26 Foundation for water structures
EP03790630A EP1530662A1 (de) 2002-08-22 2003-06-26 Gründung für wasserbauwerke

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DE10239278.1 2002-08-22
DE10239278A DE10239278B4 (de) 2002-08-22 2002-08-22 Gründung für Wasserbauwerke

Publications (1)

Publication Number Publication Date
WO2004020745A1 true WO2004020745A1 (de) 2004-03-11

Family

ID=31197432

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/DE2003/002139 WO2004020745A1 (de) 2002-08-22 2003-06-26 Gründung für wasserbauwerke

Country Status (5)

Country Link
EP (1) EP1530662A1 (xx)
AU (1) AU2003257378A1 (xx)
DE (1) DE10239278B4 (xx)
PL (1) PL374482A1 (xx)
WO (1) WO2004020745A1 (xx)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106320187A (zh) * 2016-10-27 2017-01-11 朱育盼 用于特殊地层中的桥梁施工方法和装置
CN109137958A (zh) * 2018-10-24 2019-01-04 北京天杉高科风电科技有限责任公司 预应力海上单桩基础及其安装方法

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1429024A3 (de) * 2002-12-11 2010-09-29 Ed. Züblin Ag Caisson auf Pfählen als off-shore-Gründung für Windkraftanlagen
DE102004013017B4 (de) * 2004-03-16 2006-01-19 Deutsche Gleis- Und Tiefbau Gmbh Verfahren zur Herstellung von Ortbetonfundamenten mittels vorgefertigter Schalungsbauteile
DE202007009474U1 (de) * 2007-07-05 2008-11-13 F & Z Baugesellschaft Mbh Offshore-Plattform
CN101148890B (zh) * 2007-11-08 2010-05-19 中交公路规划设计院有限公司 桥梁沉箱复合桩基础及其逆作建造方法
DE102009023466B4 (de) * 2009-06-02 2012-09-13 Herrenknecht Ag Verfahren und Vorrichtung zum Erstellen eines Unterwasserfundaments eines Bauwerks
NL2003012C2 (en) * 2009-06-12 2010-12-15 D E M E N V Hybrid offshore large pile - gravity foundation for constructions, and installation method therefor.
DE102009051425A1 (de) 2009-10-30 2011-05-05 Voith Patent Gmbh Strömungskraftwerk und Verfahren für dessen Erstellung
DE102010024469A1 (de) * 2010-06-21 2011-12-22 Franki Grundbau Gmbh & Co.Kg Gründungssystem
CN106854873B (zh) * 2017-02-22 2022-11-11 中铁科建工程有限公司 一种预制拼接的沉井式停车库的工程方法及停车库

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3054268A (en) * 1959-04-06 1962-09-18 Muller Ludwig Structure with underwater foundation
US3256694A (en) * 1962-10-29 1966-06-21 Bremische Spannbetonwerke Hill Structural piles and methods of preparing pipe foundations
WO2001040581A1 (en) * 1999-11-30 2001-06-07 Kvaerner Oil & Gas Ltd Substructure for offshore platform
DE10061916A1 (de) * 2000-12-18 2002-07-11 Conrad Hansen Gründung für eine Offshore-Windkraftanlage

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB208620A (en) * 1922-10-28 1923-12-27 Francis Gascoigne Lynde Improvements in and relating to caissons, coffer dams, platforms and the like
DE20109981U1 (de) * 2001-06-16 2001-10-04 Hansen, Conrad, 24340 Eckernförde Gründung für eine Offshore-Windkraftanlage

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3054268A (en) * 1959-04-06 1962-09-18 Muller Ludwig Structure with underwater foundation
US3256694A (en) * 1962-10-29 1966-06-21 Bremische Spannbetonwerke Hill Structural piles and methods of preparing pipe foundations
WO2001040581A1 (en) * 1999-11-30 2001-06-07 Kvaerner Oil & Gas Ltd Substructure for offshore platform
DE10061916A1 (de) * 2000-12-18 2002-07-11 Conrad Hansen Gründung für eine Offshore-Windkraftanlage

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106320187A (zh) * 2016-10-27 2017-01-11 朱育盼 用于特殊地层中的桥梁施工方法和装置
CN109137958A (zh) * 2018-10-24 2019-01-04 北京天杉高科风电科技有限责任公司 预应力海上单桩基础及其安装方法

Also Published As

Publication number Publication date
AU2003257378A1 (en) 2004-03-19
DE10239278A1 (de) 2004-03-04
EP1530662A1 (de) 2005-05-18
PL374482A1 (en) 2005-10-31
DE10239278B4 (de) 2004-07-29

Similar Documents

Publication Publication Date Title
EP2360373B1 (de) Off-Shore-Anlage, Fundament einer Off-Shore-Anlage und Verfahren zum Errichten einer Off-Shore-Anlage
EP1288122B1 (de) Schwimmfundament für ein über die Wasseroberfläche aufragendes Bauwerk
EP2753765B1 (de) Geräuscharm zu installierende gründungskonstruktion einer offshore-anlage, insbesondere einer offshore-windenergieanlage und montageverfahren hierfür
EP2420624A2 (de) Gründungsstruktur für eine Offshore-Windenergieanlage, sowie Verfahren zum Errichten dieser
WO2005005752A1 (de) Gründung für bauwerke
EP2500473B1 (de) Verfahren zur Herstellung einer Gründung für eine Offshore-Anlage
EP3428345A1 (de) Gründung für eine offshore-windenergieanlage
DE10239278B4 (de) Gründung für Wasserbauwerke
DE2559498A1 (de) Verfahren zum herstellen einer turmkonstruktion
DE102019217692A1 (de) Fundament für einen Turm einer Windkraftanlage
EP2417305A2 (de) Verfahren zum errichten einer off-shore-anlage und off-shore-anlage
DE102011012450A1 (de) Verfahren zum Einbau eines Schwergewichtsgründungssystems für eine Offshore-Windenergieanlage (WEA)
EP1033446A1 (de) Verfahren zum Herstellen eines Tiefbauwerkes in einer mit Grundwasser gefüllten Tiefbaugrube
DE2240935C3 (de) Verfahren zur Herstellung einer gegen Auftrieb gesicherten Unterwasserbetonsohle und Vorrichtung zum Durchführen des Verfahrens
DE102010035025A1 (de) Gündungsstruktur für ein Wasserbauwerk und Verfahren zum Errichten einer Gründungsstruktur
EP3555390B1 (de) Verfahren zum aufstellen eines windenergieanlagenturms aus spannbeton sowie entsprechender windenergieanlagenturm
DE1963852A1 (de) Verfahren zum Errichten eines wenigstens teilweise in einem Gewaesser untergetauchten Bauwerks
DE102012214338B4 (de) Verfahren zum Herstellen eines Verpresspfahls unterhalb einer Wasseroberfläche
EP2674532B1 (de) Verfahren und System für die Gründung eines Offshorebauwerkes
DE202010011625U1 (de) Gründung für eine Windenergieanlage
DE102021119100A1 (de) Anordnung zur Gründung eines Hochbauwerks in einem wasserbedeckten Grund, insbesondere zur Monopile-Gründung einer Offshore-Windenergieanlage, und Montageverfahren hierfür
DE2942428A1 (de) Verfahren zum ausbau von hafenanlagen o.dgl.
DE1409606C (de) Verfahren zur Gründung eines Schwimmkastens mit Rammpfählen
DE102012016692A1 (de) Verfahren zum Einbau eines Schwergewichtsgründungssystems für eine Offshore-Windenergienanlage (WEA)
EP0096650A1 (de) Tragsäule für eine Überwasserplattform und Verfahren zu ihrer Herstellung

Legal Events

Date Code Title Description
AK Designated states

Kind code of ref document: A1

Designated state(s): AE AG AL AM AT AU AZ BA BB BG BR BY BZ CA CH CN CO CR CU CZ DK DM DZ EC EE ES FI GB GD GE GH GM HR HU ID IL IN IS JP KE KG KP KR KZ LC LK LR LS LT LU LV MA MD MG MK MN MW MX MZ NO NZ OM PH PL PT RO RU SC SD SE SG SK SL TJ TM TN TR TT TZ UA UG US UZ VC VN YU ZA ZM ZW

AL Designated countries for regional patents

Kind code of ref document: A1

Designated state(s): GH GM KE LS MW MZ SD SL SZ TZ UG ZM ZW AM AZ BY KG KZ MD RU TJ TM AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IT LU MC NL PT RO SE SI SK TR BF BJ CF CG CI CM GA GN GQ GW ML MR NE SN TD TG

121 Ep: the epo has been informed by wipo that ep was designated in this application
WWE Wipo information: entry into national phase

Ref document number: 374482

Country of ref document: PL

WWE Wipo information: entry into national phase

Ref document number: 2003790630

Country of ref document: EP

WWP Wipo information: published in national office

Ref document number: 2003790630

Country of ref document: EP

NENP Non-entry into the national phase

Ref country code: JP

WWW Wipo information: withdrawn in national office

Country of ref document: JP

WWW Wipo information: withdrawn in national office

Ref document number: 2003790630

Country of ref document: EP