US3843988A - Method for excavating an underpass beneath an existing roadway - Google Patents

Method for excavating an underpass beneath an existing roadway Download PDF

Info

Publication number
US3843988A
US3843988A US00272031A US27203172A US3843988A US 3843988 A US3843988 A US 3843988A US 00272031 A US00272031 A US 00272031A US 27203172 A US27203172 A US 27203172A US 3843988 A US3843988 A US 3843988A
Authority
US
United States
Prior art keywords
pillars
superstructure
roadway
underpass
excavations
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US00272031A
Other languages
English (en)
Inventor
E Hirsch
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Application granted granted Critical
Publication of US3843988A publication Critical patent/US3843988A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G04HOROLOGY
    • G04DAPPARATUS OR TOOLS SPECIALLY DESIGNED FOR MAKING OR MAINTAINING CLOCKS OR WATCHES
    • G04D3/00Watchmakers' or watch-repairers' machines or tools for working materials
    • G04D3/0069Watchmakers' or watch-repairers' machines or tools for working materials for working with non-mechanical means, e.g. chemical, electrochemical, metallising, vapourising; with electron beams, laser beams
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/005Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by forcing prefabricated elements through the ground, e.g. by pushing lining from an access pit
    • GPHYSICS
    • G04HOROLOGY
    • G04DAPPARATUS OR TOOLS SPECIALLY DESIGNED FOR MAKING OR MAINTAINING CLOCKS OR WATCHES
    • G04D7/00Measuring, counting, calibrating, testing or regulating apparatus
    • G04D7/12Timing devices for clocks or watches for comparing the rate of the oscillating member with a standard
    • G04D7/1257Timing devices for clocks or watches for comparing the rate of the oscillating member with a standard wherein further adjustment devices are present
    • G04D7/1271Timing devices for clocks or watches for comparing the rate of the oscillating member with a standard wherein further adjustment devices are present for the control mechanism only (from outside the clockwork)
    • G04D7/1285Timing devices for clocks or watches for comparing the rate of the oscillating member with a standard wherein further adjustment devices are present for the control mechanism only (from outside the clockwork) whereby the adjustment device works on the mainspring
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2/00General structure of permanent way

Definitions

  • ABSTRACT The invention relates to a procedure whereby an un- [52] US. Cl. 14/77 [51] E01d 19/02 73, 23; 52/742,
  • I t Cl derpass may be dug out from a section of earth over which there already is a roadway. Pillars are constructed into the ground alongside the existing roadway and a superstructure is supported therefrom spanning the existing roadway. This superstructure is then utilized to support the load normally borne by the ex- [58] Field of Search........ 14/77, 75
  • This invention relates to a method for constructing an underpass beneath an existing overhead roadway.
  • This invention is directed to a method whereby an underpass may be constructed while maintaining traffic on the overhead roadway at less cost than permitted according to construction techniques.
  • An object of the present invention is a procedure for constructing a passageway underneath a pre-existant traffic roadway and is characterized in that pillars are sunk into the ground and that at least part of the upper roadway load is supported by said pillars before the excavation for the lower pathway is undertaken.
  • the superstructure of the upper roadway will rest on longitudinal springer structures which are placed on the pillars. As seen further below, the superstructure can be constructed rapidly.
  • the main excavations will be made following the erection of the superstructure, and they will be easy to carry out, without hampering the upper roadway traffic.
  • the pillars will facilitate the shoring operations.
  • FIG. 1 is a top view of a railroad embankment that is to be crossed by an underpass.
  • the first work stage is shown, that is, the construction of the foundations and pillars;
  • FIG. 2 is a section view taken along line lI-II of FIG. 1, showing the foundations and pillars of the first stage and also the longitudinal springers of the second stage;
  • FIG. 3 is a fragmentary view of FIG. 2, and enlarged, showing same at a further work stage;
  • FIG. 4 is a fragmentary longitudinal section showing other stages in the procedure (section along line lVlV of FIG. 1);
  • FIG. 5 is the same section as in FIG. 4, however after completion of construction.
  • FIG. 6 is a section similar to that of FIG. 3, showing a variation in procedure application.
  • the underpass may be intended, for instance, for a road sloping along line 3 of FIG. 2.
  • the roads width corresponds to the distance between the two straight lines (dashed) in FIG. 1.
  • 2 pits may be replaced by other excavation methods such as three-sided ones if the location is an embankment for instance.
  • the foundations are poured into these pits and then pillars 4 are constructed, for instance of reinforced concrete.
  • These pillars may be made of other materials, for example, metal.
  • the pillars may be replaced by sunk or driven piles; in that case the wood-shored excavations and the foundations are omitted.
  • two longitudinal springer structures 7 are constructed (FIGS. 2 and 3), which may be of reinforced concrete; metallic construction also is applicable.
  • each springer structure will be supported by at least three pillars. If the upper pathway is big and comprises several tracks, the number of longitudinal springer structures shall be increased.
  • the next stage namely, laying the superstructure, must be carried out quickly and preferably during nights, because its requires the temporary removal of the railroad track. It consists in removal of track 2 removal of ballast 8 and of terrain between springer structures 7,
  • the duration of traffic stoppage may be reduced by carrying out in steps the operations above and over several periods when the trains are not scheduled to run.
  • the procedures flexibility allows many combinations in this sense.
  • manufacture of the emplacement bed for the prefabricated components on the springer structures It may be made by means of rapid-setting synthetic resin mortar. A special device will be used to pour this bed when components 9 shall already have been emplaced; joining components 9 to each other, for instance by means of a rapid-setting synthetic resin mortar. Depending on circumstances, the bonding between prefabricated components may be reinforced by tie-rods, pre-stressed or not. water-proofing the upperside of the superstructure and the inner sides of the springer structures, the water-proofing material being protected by an appropriate sheating; removal of the supporting blocks, emplacement of ballast; and emplacement of protection barriers.
  • FIG. 4 shows one may progress in stages, emplacing planks 13 from top to bottom, lines 14 and 15 showing the successive clearing stages for the lower passageway.
  • ground consolidation by injection may be appropriate before excavating laterally.
  • lateral excavation methods may be used, for instance by vertical in lieu of horizontal sections, or by making use of vertically emplaced earth sustaining means, etc.
  • shoring means 13 one may directly undertake pouring concrete in successive sections. After the pillars have been cleared, they may eventually be covered, even reinforced. This would be especially the case if they have been made initially of metal or are in the form of concrete piles.
  • a draining jacket 16 will be placed together with a wall 17 against the lateral sides.
  • the construction will be finished by preparing the ground of the lower passageway either for a highway or for one or more railroad tracks, etc.
  • the pillars 4 and springer structures 7 are constructed in the same manner as for the first execution of the procedure.
  • the ballast 8 is removed from track 2 so as to allow inserting temporary metallic springer structures 19, which are 2-3 m apart and the ends of which rest on springer structures 7, underneath the sleepers.
  • the track must be reinforced by bundles of rails 11 or by shaped-profile iron bars. This operation may be undertaken in stages and betwen train passages.
  • the excavation proceeds fully underneath the bridge.
  • the superstructure will be a solid slab.
  • a prefabricated one may also be considered.
  • the coffering may be erected after excavation, and the concrete may be poured between metal beams l9.
  • the procedue may also be used when the overpass is still without traffic.
  • the supports and the superstructure as for a traditional bridge, it will be often preferable to make use of the initial presence of the terrain in order to construct the bridge framework.
  • the described procedure therefore may be applied fairly generally. It simplifies work when a bridge superstructure must be made at a site where the terrain, initially filled up, must be dug up for setting up a lower pathway.
  • the upper part of the bridge no longer is necessarily constituted by longitudinal springer structures that are connected by a superstructure.
  • This upper part may be made up of reinforced concrete (solid slab, caisson slab, semi-solid slab etc.) which makes use of the raised earth platform as a work area. As in the preceding cases, this upper part will rest on previously built pillars buried in the ground.
  • springers parallel to the upper roadway and resting on the upper end of said pillars, said springers being outwardly of a predetermined traffic gauge necessary for said upper roadway, placing a superstructure on said springers, said superstructure comprising transverse beams arranged side by side and having their ends resting on the springers, then completing the roadway portion on said superstructure, said superstructure emplacement and roadway portion completion being carried out step by step,
  • said lateral excavations being carried out step by step with pro gressively strengthening the side faces of the underpass from the level of said springers down to the level of a lower platform of said underpass, and completing said lower platform.
  • a procedure according to claim 1, comprising sinking said pillars in the ground and finishing said pillars after completion of said excavations in order to constitute the constructions final pillars.
  • a procedure according to claim 1, comprising driving said pillars in the ground and finishing said pillars after completion of said excavations, in order to constitute the constructions final pillars.
  • a procedure according to claim 1, comprising constructing said pillars of metal components and finishing said components after completion of said excavations in order to constitute the final construction pillars.
  • a procedure according to claim 1, comprising constructing said, pillars of metal components and modifying said components after completion of said excavations in order to constitute the final construction pillars.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Physics & Mathematics (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Paleontology (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Optics & Photonics (AREA)
  • Plasma & Fusion (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Bridges Or Land Bridges (AREA)
  • Road Signs Or Road Markings (AREA)
US00272031A 1971-07-19 1972-07-14 Method for excavating an underpass beneath an existing roadway Expired - Lifetime US3843988A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CH1060871A CH544191A (fr) 1971-07-19 1971-07-19 Procédé de construction d'un passage sous une voie de communication, notamment sous une voie existante

Publications (1)

Publication Number Publication Date
US3843988A true US3843988A (en) 1974-10-29

Family

ID=4365003

Family Applications (1)

Application Number Title Priority Date Filing Date
US00272031A Expired - Lifetime US3843988A (en) 1971-07-19 1972-07-14 Method for excavating an underpass beneath an existing roadway

Country Status (9)

Country Link
US (1) US3843988A (es)
AT (1) AT329623B (es)
BE (1) BE785735A (es)
CH (1) CH544191A (es)
DE (1) DE2233263A1 (es)
ES (1) ES404629A1 (es)
FR (1) FR2146731A5 (es)
IT (1) IT962964B (es)
SE (1) SE380312B (es)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0990768A1 (de) * 1998-09-30 2000-04-05 Bilfinger + Berger Bauaktiengesellschaft Verfahren zum Erstellen eines Tunnelbauwerks unter einer bestehenden Gleisanlage
ES2151364A1 (es) * 1997-10-27 2000-12-16 Alicantina De Construcciones I Apeo de via ferrea para ejecucion de pasos inferiores.
US6795992B2 (en) 2002-10-03 2004-09-28 Paul H. Markelz Bridge construction method
WO2006074992A1 (en) * 2005-01-11 2006-07-20 Salvatore Matarrese Spa Method to construct underpasses in an artificial tunnel
WO2017136918A1 (en) * 2016-02-12 2017-08-17 Grade Separation Systems Inc. Construction methods and systems for grade separation structures

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3733246A1 (de) * 1987-10-01 1989-04-13 Kunz Alfred & Co Verfahren zur herstellung eines tunnels mit geringer ueberdeckung unter gleisanlagen o. dgl.
FR2650848B1 (fr) * 1989-08-10 1993-09-24 Travaux Publics Entr Indle Methode de realisation d'ouvrages d'art sous voie de chemin de fer en service sans utilisation de tabliers metalliques auxiliaires
FR2698114B1 (fr) * 1992-11-18 1995-03-10 Beauthier Jean Marie Procédé pour la réalisation d'une assise de camarteaux destinés à l'appui d'un tablier auxiliaire de grande longueur pour le support d'une voie ferrée.

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US48530A (en) * 1865-07-04 Improved trestle-bridge
US189020A (en) * 1877-04-03 Improvement in bridge-piers
US534032A (en) * 1895-02-12 Bridge
US1558430A (en) * 1918-10-31 1925-10-20 John B Goldsborough Underpinning
US1880290A (en) * 1931-01-09 1932-10-04 Roeblings John A Sons Co Method of transferring load in making bridges and the like
US2282452A (en) * 1938-10-28 1942-05-12 Brown Horatio Whittemore Method of constructing the foundations of cellarless houses
US2602321A (en) * 1947-03-21 1952-07-08 John E Blair Method of constructing a prefabricated bridge structure
US2686421A (en) * 1947-01-07 1954-08-17 Barron Maurice Bridge
US3184893A (en) * 1960-04-11 1965-05-25 Contact Foundation Inc Contact foundation method
US3295276A (en) * 1964-02-10 1967-01-03 Stanley Rene Inc J Bridge
US3457690A (en) * 1967-01-26 1969-07-29 Pierre Le Clercq Method for constructing a building simultaneously below and above ground level
US3706125A (en) * 1970-08-10 1972-12-19 John P Hopkins Co Pipe line construction method

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US48530A (en) * 1865-07-04 Improved trestle-bridge
US189020A (en) * 1877-04-03 Improvement in bridge-piers
US534032A (en) * 1895-02-12 Bridge
US1558430A (en) * 1918-10-31 1925-10-20 John B Goldsborough Underpinning
US1880290A (en) * 1931-01-09 1932-10-04 Roeblings John A Sons Co Method of transferring load in making bridges and the like
US2282452A (en) * 1938-10-28 1942-05-12 Brown Horatio Whittemore Method of constructing the foundations of cellarless houses
US2686421A (en) * 1947-01-07 1954-08-17 Barron Maurice Bridge
US2602321A (en) * 1947-03-21 1952-07-08 John E Blair Method of constructing a prefabricated bridge structure
US3184893A (en) * 1960-04-11 1965-05-25 Contact Foundation Inc Contact foundation method
US3295276A (en) * 1964-02-10 1967-01-03 Stanley Rene Inc J Bridge
US3457690A (en) * 1967-01-26 1969-07-29 Pierre Le Clercq Method for constructing a building simultaneously below and above ground level
US3706125A (en) * 1970-08-10 1972-12-19 John P Hopkins Co Pipe line construction method

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ES2151364A1 (es) * 1997-10-27 2000-12-16 Alicantina De Construcciones I Apeo de via ferrea para ejecucion de pasos inferiores.
EP0990768A1 (de) * 1998-09-30 2000-04-05 Bilfinger + Berger Bauaktiengesellschaft Verfahren zum Erstellen eines Tunnelbauwerks unter einer bestehenden Gleisanlage
US6795992B2 (en) 2002-10-03 2004-09-28 Paul H. Markelz Bridge construction method
WO2006074992A1 (en) * 2005-01-11 2006-07-20 Salvatore Matarrese Spa Method to construct underpasses in an artificial tunnel
WO2017136918A1 (en) * 2016-02-12 2017-08-17 Grade Separation Systems Inc. Construction methods and systems for grade separation structures
US10435853B2 (en) 2016-02-12 2019-10-08 Grade Separation Systems Inc. Construction methods and systems for grade separation structures
US10435854B2 (en) 2016-02-12 2019-10-08 Grade Separation Systems Inc. Construction methods and systems for grade separation structures

Also Published As

Publication number Publication date
CH544191A (fr) 1973-11-15
DE2233263A1 (de) 1973-02-01
FR2146731A5 (es) 1973-03-02
BE785735A (fr) 1972-10-16
IT962964B (it) 1973-12-31
ES404629A1 (es) 1975-06-16
AT329623B (de) 1976-05-25
SE380312B (sv) 1975-11-03
ATA621872A (de) 1975-08-15

Similar Documents

Publication Publication Date Title
CN106758841B (zh) 一种双塔双索面矮塔斜拉桥的整体施工工艺
KR102056345B1 (ko) 철도운행선 선로의 법면 경사를 조절한 노반구조물 및 그 시공방법
CN211144503U (zh) 一种高陡地形桥隧相接段明洞接长结构
CN110439590A (zh) 隧道施工方法
US3843988A (en) Method for excavating an underpass beneath an existing roadway
JP6170268B1 (ja) バラスト軌道の路盤形成方法
CN108708290B (zh) 小半径铁路曲线单元的箱桥架空结构及现浇施工方法
KR100532248B1 (ko) 피에스씨 판넬과 강재 거더를 이용한 복개아치합성구조물및 그 시공방법
CN108978673A (zh) 一种立交桥桩基托换的基坑支护结构及施工方法
CN216765941U (zh) 一种偏压状态下隧道减压减载结构
US11686198B2 (en) Reinforcement system at railway tunnel section passing through karst cave with large dip angle and construction method
US20190071825A1 (en) Construction methods and systems for grade separation structures
Koyama Railway construction in Japan
CN113293665B (zh) 一种铁路桥涵接长侧路基加固方法
CN113833022A (zh) 铁路线加固系统及施工方法
Prentis et al. Underpinning: its practice and applications
CN113389218A (zh) 一种地道桥出入口挡墙结构及其施工方法
JP5073960B2 (ja) 地下構造物の構築法および地下構造物
Lunardi The cellular arch method: technical solution for the construction of the Milan railway's venezia station
Clarkson et al. PIPE-JACKING APPLIED TO LARGE STRUCTURES.
KR102272494B1 (ko) 지지력과 긴장력을 이용한 사면 보강 구조물 및 이의 시공 방법
CN214737080U (zh) 一种铁路桥涵接长侧路基的加固结构
KR101288602B1 (ko) 결속밴드로 머리가 연결된 기성 콘크리트 말뚝을 이용한 지하차도 및 그의 시공방법
JP3380302B2 (ja) 高架橋施工方法
Prodanov DISRUPTIVE TECHNOLOGY FACILITY OPTIONS IN A COMPLEX INFRASTRUCTURE ENVIRONMENT