SU92852A1 - Metallic overlap for fencing workspace of the cleaning face from the collapsing side rocks - Google Patents

Metallic overlap for fencing workspace of the cleaning face from the collapsing side rocks

Info

Publication number
SU92852A1
SU92852A1 SU393596A SU393596A SU92852A1 SU 92852 A1 SU92852 A1 SU 92852A1 SU 393596 A SU393596 A SU 393596A SU 393596 A SU393596 A SU 393596A SU 92852 A1 SU92852 A1 SU 92852A1
Authority
SU
USSR - Soviet Union
Prior art keywords
overlap
fencing
workspace
cleaning face
coal
Prior art date
Application number
SU393596A
Other languages
Russian (ru)
Inventor
М.Ф. Мисик
Original Assignee
М.Ф. Мисик
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by М.Ф. Мисик filed Critical М.Ф. Мисик
Priority to SU393596A priority Critical patent/SU92852A1/en
Application granted granted Critical
Publication of SU92852A1 publication Critical patent/SU92852A1/en

Links

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Description

Изобретение относитс  к области способов разработкн мощных ьфутопадающих угольных пластов.The invention relates to the field of methods for developing high-power falling coal seams.

Известны способы и устройства - жесткие и эластичные щиты - дл  ограждени  рабочего пространства от обрушающихс  боковых пород при отработке мощных крутопадающих пластов. Однако применение известных жестких и эластичных щитов сильно усложн етс  в услови х измен ющейс  мощности пласта.Methods and devices are known — rigid and elastic shields — for protecting the working space from collapsing lateral rocks during mining of steeply dipping seams. However, the application of known rigid and elastic shields is greatly complicated under conditions of varying thickness of the formation.

Предлагаемое металлическое перекрытие отличаетс  от известных тем, что щирина и длина его могут измен тьс  и вследствие этого перекрытие может приспосабливатьс , в частности, к измен ющейс  мощности отрабатываемого пласта.The proposed metal overlap differs from the known ones in that the width and length of it can vary and as a result, the overlap can be adapted, in particular, to the varying thickness of the formation being worked.

На фиг. I изображена система разработки в продольном разрезе по А-А на фиг. 2; на фиг. 2 - то же, в поперечном разрезе по Б-Б на фиг. 1; на фиг. 3 -то же, в разрезе по Е-В на фиг. 1; на фиг. 4 - конструкци  перекрыти .FIG. I depicts a development system in longitudinal section along A-A in FIG. 2; in fig. 2 is the same in cross section along BB in FIG. one; in fig. 3 is the same, in section along E-B in FIG. one; in fig. 4 - overlap structures.

Мощный крутопадающий угольный пласт на уровне вентил ционного щтрека / перекрываетс  по всей мощности сплощным металлически .м полужестким перекрытием 2, которое в процессе выемки под ним угл  располагаетс  под углом 25-40° к горизонту. Выемка угл  под перекрытием ведетс  из специальных канав-проходов 3, располагаемых под жесткими звень ми балки 4 перекрыти  2.A powerful steeply dipping coal seam at the level of the ventilation flap / overlaps along the whole power with a flat metallic semi-rigid ceiling 2, which in the process of excavation underneath the coal is at an angle of 25-40 ° to the horizon. The excavation of the coal under the overlap is made of special ditch passages 3 located under the rigid links of the beam 4 of the overlap 2.

При этом возведение дополнительного креплени  под перекрытием не требуетс , так как жесткие звень  балки 4 опираютс  на целики 5 угл , что обеспечивает необходимое свободное рабочее пространство и безопасность работы в забо х. Непосредственно над опорными целиками 5 располагаютс  эластичные звень  - стальные канаты 5 перекрыти  2, с помощью которых соедин ютс  жесткие звень  перекрыти .At the same time, the construction of an additional attachment under the overlap is not required, since the rigid links of the beam 4 rest on the pillars of the 5th angle, which provides the necessary free working space and safety of work in the decals. Directly above the supporting pillars 5 are elastic links — steel ropes 5 of overlap 2, by means of which rigid overlapping links are connected.

Отбитый с помощью взрывчатых веществ или отбойных молотков уголь собственным весом спускаетс  по подощве канав-проходов 5 и поперечно-наклонных орт 7 в углеспускные скважины 8, по которым поступает на откаточный щтрек Я где и грузитс  в вагонетки. По мере ;ыемки угл  перекрытие спускаетс  вниз, достига  подощвы откаточ№ 92852The coal repulsed with explosives or jackhammers with its own weight descends along the base of the ditch passages 5 and of the cross-inclined ort 7 into the coal drainage wells 8, through which I go to the haulage I where it is loaded into trolleys. As the angle overlaps descends, it reaches the base number 92852

ного штрека, где в пункте 10 демонтируетс . Монтируетс  перекрытие в пункте //.where it is dismantled at point 10. The overlap in point // is mounted.

Бурение углеспускных скважин 8 производитс  с откаточного штрека, а ходовых вентил ционных печей 12 - с первого параллельного штрека. При выемке угл  с применением буровзрывных работ посередине высоты этажа у лежачего бока проводитс  еще один подэтажный штрек 13 дл  обеспечени  лучшего проветривани  очистных забоев.The coal wells 8 are drilled from the haulage drift, and the running ventilation furnaces 12 are drilled from the first parallel drift. When coal is excavated using drilling and blasting operations, in the middle of the height of the floor, at the side of the recumbent side, another sublevel drift 13 is carried out to ensure better ventilation of the working faces.

Перекрытие 2 представл ет собой полужесткий металлический кар кас, состо ш,ий из двутавровых балок 4 длиной по 3 м, уложенных р дами на рассто нии 1 м един от другого (по простиранию). Указанные балки соедин ютс  между собой стальными канатами 6 диаметром 18 мм, а по простиранию - канатами 14 диаметром 28 мм. Дл  предот вращени  прорыва под перекрытие обрушенных пород канатно-балочпый каркас его покрываетс  сверху канатной или проволочной сеткой 15, прикрепленной к каркасу скобами 16 и гайками 17. Дл  придани  жестким звень м перекрыти  большей устойчивости применены упорные кронштейны 18 посередине балок.The overlap 2 is a semi-rigid metal frame, consisting of I-beams 4 with a length of 3 m, arranged in rows 1 m apart from each other (along the strike). These beams are interconnected by steel ropes 6 with a diameter of 18 mm, and along strike are ropes 14 with a diameter of 28 mm. To prevent a breakthrough under the overlap of the collapsed rocks of the cable-beam frame, it is covered on top with a cable or wire mesh 15 attached to the frame with brackets 16 and nuts 17. To secure the hard links to block more stability, support brackets 18 in the middle of the beams are used.

Конструкци  перекрыти  позвол ет измен ть его размеры по ширине- за счет сокрашени  эластичных звеньев - до 30% общей ши рины перекрыти .The overlap design allows it to be resized in width due to the contraction of elastic links — up to 30% of the total overlap width.

Монтаж перекрыти  на верхнем горизонте, очистные работы и демонтаж перекрыти  на горизонте осуществл ютс  одновременно и иезависимо друг от друга.The installation of the ceiling on the upper horizon, the cleaning work and the dismantling of the ceiling on the horizon are carried out simultaneously and independently of each other.

Выемка угл  под перекрытием ведетс  путем последовательных углублений канав-проходов и разборки на такую же величину верхних частей опорных целиков. Каждый столб, ограниченный печами, вынимаетс  независимо от соседнего.Excavation of the coal under the overlap is carried out by successive recesses of the ditch passages and disassembling for the same amount the upper parts of the supporting pillars. Each pillar, bounded by furnaces, is removed independently of the adjacent.

Управление перекрытием осуществл етс  посредством увеличени  илп уменьшени  толщины вынимаемого иод ним сло  за один цикл. При углах падени  пластов ниже 70° выемка угл  должна производитьс  в пор дке, показанном пунктиром 19, т. е. так, чтобы углубление канавпроходов и разборка опорных целиков велись в направлении от лежачего бока пласта к вис чему. При этом перекрытие волнообразно будет перемещатьс  от лежачего к вис чему боку пласта.Overlap control is accomplished by increasing or decreasing the thickness of the layer removed by it in one cycle. At angles of incidence below 70 °, the coal shall be dredged in the order shown by dotted line 19, i.e., so that the deepening of the gangways and disassembly of the supporting pillars are in the direction from the recumbent side of the seam to the top. In this case, the overlap will move in a wave-like manner from the lying to the lateral layer.

Предмет изобретени Subject invention

Металлическое перекрытие дл  ограждени  рабочего пространства очистного забо  от обрушающихс  боковых пород, отличающеес  тем, что, в цел х обеспечени  возможности регулировани  щирины и длины перекрыти , оно составл етс  из отдельных металлических жестких звеньев, соединенных между собой вкрест простирани  и по простиранию пласта стальными канатами.Metallic overlap to enclose the working space of the cleaning slab from collapsing lateral rocks, characterized in that, in order to ensure the possibility of adjusting the width and the length of the overlap, it is composed of separate metallic rigid links interconnected in the middle of the strike and the strike of the formation with steel cables.

по ff-йby ff-th

-ff -ff

// f. // f.

W rr-:7r -sriR2a2DTr-. мсжэ4 7 ЗЙГ V:t, .О a , -Л .,i .W rr-: 7r -sriR2a2DTr-. Mszhe4 7 ZYG V: t, .O a, -L., i.

AA&O.jJs 5 - A:::Jt iAra:iA2A; AA & O.jJs 5 - A ::: Jt iAra: iA2A;

feai-r b.2|pg::;;.fp-sp± feai-r b.2 | pg :: ;;. fp-sp ±

no H ti gno H ti g

trimtrim

gS5gS5

5 ffi5 ffi

dJvdJv

SU393596A 1949-03-17 1949-03-17 Metallic overlap for fencing workspace of the cleaning face from the collapsing side rocks SU92852A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU393596A SU92852A1 (en) 1949-03-17 1949-03-17 Metallic overlap for fencing workspace of the cleaning face from the collapsing side rocks

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU393596A SU92852A1 (en) 1949-03-17 1949-03-17 Metallic overlap for fencing workspace of the cleaning face from the collapsing side rocks

Publications (1)

Publication Number Publication Date
SU92852A1 true SU92852A1 (en) 1950-11-30

Family

ID=48368465

Family Applications (1)

Application Number Title Priority Date Filing Date
SU393596A SU92852A1 (en) 1949-03-17 1949-03-17 Metallic overlap for fencing workspace of the cleaning face from the collapsing side rocks

Country Status (1)

Country Link
SU (1) SU92852A1 (en)

Similar Documents

Publication Publication Date Title
US10662771B2 (en) Drill and blast method and apparatus for the same
RU2461713C1 (en) Development method of thick steeply inclined coal formation in strips as to inclination
SU92852A1 (en) Metallic overlap for fencing workspace of the cleaning face from the collapsing side rocks
SU97852A1 (en) The method of increasing the strength of dyes with oxyazo dyes obtained on the fiber to friction
RU2384708C2 (en) Removal method of powered mining face complexes
RU2563003C1 (en) Method of excavation of thick flat coal beds
RU2263213C1 (en) Method for thick steeply inclined fire-hazardous bed mining with caving
RU168978U1 (en) Roadheader
SU881322A1 (en) Method of working pillars at chamber-and-pillar excavating routine
SU1624177A1 (en) Flexible canopy
SU95492A1 (en) Development system of high-grade steeply dipping seams with horizontal layers
SU848661A1 (en) Flexible roof
RU2234609C1 (en) Method for preventing unexpected salt and gas outburst
SU926328A1 (en) Portable form
SU631657A1 (en) Method of excavating thick orebodies
SU899956A1 (en) Method of mining sloping and steep fire-hazardous coal beds
SU143761A1 (en) The system for the development of heavy coal seams with pillars in the fall
SU58469A1 (en) Device to protect people working in the face from the dam rock
SU877081A1 (en) Method of erecting man-made ceiling
SU896196A1 (en) Large-panel building constructed on poor soil
SU693017A1 (en) Method of mining mineral deposits
SU777232A1 (en) Pneumatic shell roof support
SU684142A1 (en) Method of exacavating roof-supporting ore pillars
SU142255A1 (en) The method of construction of fastening in the rising workings
SU97031A1 (en) The method of construction of the overlap of wire mesh in the development of powerful, oblique coal seams