SU850664A1 - Device for cast iron and slag outlet from blast furnace - Google Patents

Device for cast iron and slag outlet from blast furnace Download PDF

Info

Publication number
SU850664A1
SU850664A1 SU792761149A SU2761149A SU850664A1 SU 850664 A1 SU850664 A1 SU 850664A1 SU 792761149 A SU792761149 A SU 792761149A SU 2761149 A SU2761149 A SU 2761149A SU 850664 A1 SU850664 A1 SU 850664A1
Authority
SU
USSR - Soviet Union
Prior art keywords
iron
slag
chute
cast iron
channel
Prior art date
Application number
SU792761149A
Other languages
Russian (ru)
Inventor
Геннадий Петрович Лежнев
Юрий Викторович Сметанкин
Геннадий Васильевич Тивирев
Original Assignee
Магнитогорский Дважды Ордена Ленина Иордена Трудового Красного Знамениметаллургический Комбинат Им. B.И.Ленина
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Магнитогорский Дважды Ордена Ленина Иордена Трудового Красного Знамениметаллургический Комбинат Им. B.И.Ленина filed Critical Магнитогорский Дважды Ордена Ленина Иордена Трудового Красного Знамениметаллургический Комбинат Им. B.И.Ленина
Priority to SU792761149A priority Critical patent/SU850664A1/en
Application granted granted Critical
Publication of SU850664A1 publication Critical patent/SU850664A1/en

Links

Landscapes

  • Furnace Charging Or Discharging (AREA)

Description

Изобретение относитс  к черной металлургии, в частности к производи ству чугуна в доменных печах и может быть использовано дл  отделени  чугуна от ишака при вьтуске металла из доменной печи. Известно устройство дл  разделени  чугуна и ышака в главном желобе доменной печи, содержащее шлаков ЗЙ желоб, желоб дл  выпуска чугуна, разделительную (скиммерную) плиту, перевалы дл  слива чугуна и шпака. В этом устройстве разделительна  (скиммерна ) плита устанавливаетс  за шлаковым желобом в главном жеЛобе так, чтобы между дном желоба и краем плиты осталс  небольшой проход дл  выпуска чугуна, отделенного от шлака. Дл  предохранени  разделитель ной плиты от разъедани  жидким чугуном она футеруетс  огнеупорным кирпичом. На рассто нии от разделительной плиты устанавливаетс  перева дл  слива чугуна, служащий дл  подн ти  уровн  чугуна и шлака в главном желобе до уровн  шлакового перевала l . Недостатками устройства дл  разде лени  чугуна и шлака в главном желобе  вл ютс  низкое качество отделени  чугуна от шлака и высокий разгар прохода между разделительной доской и дном желоба. Известно устройство дл  разделени  чугуна и шлака в главном желобе, содержащее желоб дл  выпуска, обработки металла и отделени  печного илака, расположенную за ним перегородку с зазором мезеду днищем 2j. Высокий разгар перевала уменьшен за счет выполнени  перевала с уклоном 10-45, высокий разгар скиммерной перегородки уменьшен за счет выполнени  в боковой стенке желоба дополнительней огнеупорной вставки, а качество отдалени  чугуна от шлака повышено благодар  тому, что скиммерна  перегородка заглублена в при мок , выполненный в желобе с уклону стен в продольном направлении 10-4 . Однако недостатками известных устройств дл  разделени  чугуна и шлака в главном желобе также  вл етс  некачественное отделение чугуна от шлака из-за попадани  шлака с чугуном в желоб дл  выпуска чугуна и высокий разгар скиммерного отверсти  и перевала дл - слива чУгуна. Наличие канала в одном из перевалов и выполнение канала с уклоном позвол ет снизить потери чугуна со шлаком, однако недостатком известных тезГнических ранений  вл етс  высокий разгар перевала в месте перелива чуг на с перевала в желоб вследствие р аэъединени  выступающей части перевала жидким чугуном. Наиболее близким по технической сущности к предлагаемому  вл етс  устройство дл  выпуска чугуна и шлака из доменной печи, содержащее .центральный желоб, желоб дл  выпуска чугуна, разделительную плиту, перевалы дл  слива чугуна и ишака, шлако , отверстие дл  спуска остатков чугуна из желоба. Разделительна  плита и чугунный перевал расположены в боковом желобе , наход щимс  под пр мым углом к центральному желобу 3|. : Существенным недостатком данного ус|тройства  вл етс  низка  степень отделени  чугуна от шлака в начале и Конце их выпуска, так как в начале выпуска чугуна и шлака, когда процес от|стаивани  еще не завер лилс  и чугу пс|лностью не заполнил отверстие меж ду плитой и дном желоба, шлак вмест с чугуном попадает в желоб дл  выпуска чугуна, в конце выпуска чугуна и 1илака слой шлака, опуска сь вместе с ;чугуном до уровн  кра  плиты, такж попадает с чугуном в желоб дл  выпуска Чугуна, Крсаде того, высокий разгар перевала дл  чугуна из-за разъедани  выступающей части перевала жидким чугуном приводит к изменению (уменьшению) уровн  перевала, а следовательно, и усювн  чугуна в центральном желобе. Цель изобретени  - повышение степени отделени  чугуна от шлака в на чале и конце их выпуска, предотвращбние разгас а перевала дл  чугуна путем создани  плс1вкого пеоелива чу гуна с перевала в желоб дл  чугуна. Указанна  цель достигаетс ,тем, что в устройстве дл  выпуска чугуна и шлака из доменной печи, содеожаше центральный желоб, желоб дл  выпуска чугуна, разделительную плиту, пе ревалы дл  слива чугуна и шлака и шлакоотвод, разделительна  плита выполнена в виде монолитного блока со сквозным канале, направленным под углом к дну центрального желоба при этом нижний край нижнего конца канала совмещен с дном центрального желоба, а нижний край верхнего конц канала - с дном желоба дл  выпуска чугуна. На фиг. 1 схематически изображен устройство дл  выпуска чугуна и шла ка из доменной печи, вид в плане| на фиг. 2 - вид по стрелке А на Фиг. 3 - разрез Б-Б на фиг. 1 на фиг. 4 - разрез В-В на фиг, 1. Устройство дл  выпуска чугуна и из доменной печи состоит из центрального желоба 1, желоба 2 дл  выпуска чугуна, разделительной плиты 3, перевала 4 дл  слива чугуна и перевала 5 дл  слива шлака и шлакоотвода 6. Разделительна  плита 3 выполнена в виде монолитного блока со сквозньви каналом 7, направленным под углом к дну 8 центрального желоба 1, при .этом нижний край 9 нижнего конца канала 7 совмещен с дном 8 центрального желоба 1, а нижний край 10 верхнего конца канала 7 - с дном 11 желоба 2 дл  выпуска чугуна. В донной части разделительной плиты 3 выполнено отверстие 12 дл  спуска остатков чугуна-после окончани  вьшуска чугуна и шлака из доменной печи. Разделительна  плита 3 закреплена сверху плитой 13, с боков зажата между стенкой 14 желоба 2 дл  выпуска чугуна и стенкой 15 центрального желоба 1 и плотно прижата к выступающей части 16 желоба 2 дл  слива чугуна. Разделительна  плита 3 расположена под углом к оси централь ного желоба 1, Устройство дл  вьшуска чугуна и шлака из доменной печи работает следующим образом. При выпуске чугуна и шлака из доменной печи в центральном желобе 1 до разделительной плиты 3 происходит накопление металла до уровн , определ емого нижним краем 10 верхнего конца канала 7 и отделение чугуна от шлака за счет разницы их удельных весов. Благодар  тому, что разделительна  плита 3 выполнена в виде монолитного блока со сквозным каналом 7, направленным под углом к дну 8 центрального желоба 1, нижний край 9 нижнего конца канала 7 совмещен с дном 8 центрального желоба 1, а нижний край 10 верхнего конца канала 7 - с дном 11 желоба 2 дл  выпуска чугуна,. Чугун (как более т желый : материал) осаждаетс  на наклонное лно 17 канала 7, а шлак (как более легкий материал) вытесн етс  (отталкиваетс ) чугуном. Таким образом, в начале и в конце вьшуска чугуна и шлака не происходит попадание шлака в желоб 2 дл  выпуска чугуна. В течение всего выпуска чугуна и шлака из доменной печи практически весь шлак всплывет на поверхность. По мере его накоплени  осуществл етс  полный отвод шлака в шлакоотвод 6 посредством разделительной плиты 3. Осевший чугун, пройд  через сквозной канал 7, попадает в желоб 2 дл  выпуска чугуна. Оставшийс  после окончани  выпуска в центральном желобе 1 чугун спускаетс  через отверстие 12, расположенное в донной части разделительной плиты 3.The invention relates to ferrous metallurgy, in particular, to the production of pig iron in blast furnaces and can be used to separate the iron from the donkey during the extraction of metal from the blast furnace. A device for the separation of iron and yishak in the main chute of a blast furnace is known, which contains slag ZY chute, a chute for the production of iron, a skimmer plate, passes for pouring iron and shpak. In this device, a separation (skimmer) plate is installed behind the slag chute in the main slab so that there is a small passage between the bottom of the chute and the edge of the slab for the production of pig iron separated from the slag. To prevent the separating plate from being eroded by liquid iron, it is fired by a refractory brick. At a distance from the dividing plate, a pass for casting iron is installed, which serves to raise the level of iron and slag in the main runner to the level of the slag pass l. The drawbacks of the device for separating the pig iron and slag in the main chute are the low quality of the separation of the iron from the slag and the high height of the passage between the dividing board and the bottom of the chute. A device for separating iron and slag in the main chute is known, comprising a chute for discharging, treating metal and separating furnace sludge, a partition located behind it with a gap mesedu bottom 2j. The high peak of the pass is reduced by making the pass with a slope of 10-45, the high height of the skimmer partition is reduced by making an additional refractory insert in the side wall of the groove, and the quality of iron removal from the slag is increased due to the fact that the skimmer partition is recessed in gutter with the slope of the walls in the longitudinal direction of 10-4. However, the disadvantages of the known devices for the separation of iron and slag in the main chute are also poor-quality separation of the iron from the slag due to slag with the iron in the chute for the production of iron and a high heat release hole and a pass to drain the iron. The presence of a channel in one of the passes and the implementation of a channel with a slope reduces the loss of pig iron with slag, however, the disadvantage of known tech- nical injuries is a high peak at the place of overflow of pig iron from one pass to the trough due to the connection of the protruding part of the pass with liquid iron. The closest in technical essence to the present invention is a device for discharging pig iron and slag from a blast furnace, comprising: a central chute, a chute for discharging pig iron, a dividing plate, passes for pouring iron and an asshole, slag, a hole for lowering the iron residues from the chute. The separator plate and the cast-iron pass are located in the side gutter, which is located at a right angle to the central gutter 3 |. : A significant disadvantage of this device is the low degree of separation of pig iron from slag at the beginning and the end of their production, since at the beginning of production of iron and slag, when the process of settling was not yet completed, the iron did not fill the hole between slab and bottom of the gutter, slag together with the cast iron falls into the gutter for cast iron production, at the end of the cast iron and lilac discharge, the slag layer descends together with the cast iron to the same level as the edge of the slab, also falls with cast iron into the gutter for cast iron production, which is high the height of the pass for cast iron due to corroding ystupayuschey liquid iron parts pass causes a change (decrease) in the level of the saddle, and consequently usyuvn iron in the central groove. The purpose of the invention is to increase the degree of separation of pig iron from slag at the beginning and at the end of their production, preventing the cast iron from breaking down by creating a flat-bottom chuo guna from the pass to the cast iron chute. This goal is achieved by the fact that in a device for the production of iron and slag from a blast furnace, a central chute, a chute for production of iron, a dividing plate, turns to drain the iron and slag and slag removal, the dividing plate is made in the form of a monolithic block with a through channel at the same time, the lower edge of the lower end of the channel is aligned with the bottom of the central chute, and the lower edge of the upper end of the channel with the bottom of the chute for casting iron. FIG. 1 schematically shows a device for the production of iron and slag from a blast furnace, plan view | in fig. 2 is a view along arrow A in FIG. 3 shows a section BB in FIG. 1 in FIG. 4 shows a section B-B in FIG. 1. A device for discharging cast iron and from a blast furnace consists of a central chute 1, a chute 2 for discharging cast iron, a dividing plate 3, a pass 4 for pouring out cast iron and a pass 5 for draining slag and a slag extract 6. The separator plate 3 is made in the form of a monolithic block with a through channel 7 directed at an angle to the bottom 8 of the central groove 1, with the lower edge 9 of the lower end of the channel 7 aligned with the bottom 8 of the central groove 1, and the lower edge 10 of the upper end of the channel 7 - with a bottom 11 of the gutter 2 for the release of cast iron. In the bottom part of the separation plate 3, an opening 12 is made to descend the remains of iron — after the iron and slag is removed from the blast furnace. The separator plate 3 is fixed on top of the plate 13, laterally sandwiched between the wall 14 of the chute 2 for discharging the cast iron and the wall 15 of the central chute 1 and tightly pressed against the protruding part 16 of the chute 2 for pouring the iron. The separation plate 3 is located at an angle to the axis of the central groove 1. A device for extracting iron and slag from the blast furnace works as follows. When pig iron and slag are released from the blast furnace in the central groove 1 to the separation plate 3, metal accumulates to a level determined by the lower edge 10 of the upper end of the channel 7 and the iron is separated from the slag due to the difference in their specific weights. Due to the fact that the separation plate 3 is made as a monolithic block with a through channel 7 directed at an angle to the bottom 8 of the central groove 1, the lower edge 9 of the lower end of the channel 7 is aligned with the bottom 8 of the central groove 1, and the lower edge 10 of the upper end of the channel 7 - with a bottom 11 of the gutter 2 for the release of cast iron ,. The cast iron (as heavier: material) is deposited on the inclined bottom 17 of channel 7, and the slag (as lighter material) is forced out (repelled) by the cast iron. Thus, at the beginning and at the end of the iron and slag discharge, slag does not enter the chute 2 to release iron. During the entire production of pig iron and slag from the blast furnace, almost all of the slag will float to the surface. As it accumulates, the slag is completely withdrawn into slag removal 6 by means of a dividing plate 3. The settled cast iron, having passed through the through channel 7, enters the chute 2 to release cast iron. The remaining iron after the end of the release in the central gutter 1 is lowered through an opening 12 located in the bottom part of the separation plate 3.

В предлагаемом устройстве разделительна  плита 3 выполнена из монолитного блока, у которого высота равна высоте центрального желоба 1 и вь соте желоба 2 дл  выпуска чугуна, ширина равна ширине желоба 2 дл  вы пуска чугуна, а толщина равна 600 мм. Диаметр сквозного канала 7 выбран из услови  обеспечени  минимального сопротивлени  прохождению чугуна по каналу 7.In the proposed device, the separation plate 3 is made of a monolithic block, whose height is equal to the height of the central chute 1 and upper cell of the chute 2 for cast iron production, the width is equal to the width of the chute 2 for cast iron production, and the thickness is 600 mm. The diameter of the through channel 7 is selected from the condition of ensuring the minimum resistance to the passage of iron through the channel 7.

Известно, что.площадь поперечногоIt is known that the area of the transverse

канала 7 должна составсечени  Schannel 7 should be a section S

попpop

л ть менее п ти плснцадей сечени  канала чугунной-летки (дл  создани  минимального напора в канале 7).less than five cast iron-gon channel sections (to create a minimum head in channel 7).

При диаметре чугунной летки 150 м диаметр канала 7 разделительной плиты 3 составл ет 300 мм. С уменьшением диаметра канала 7 увеличиваетс  скорость прохождени  по нему чугуна, что ведет к образованию воронки и зат гиванию в канал 7 шлака,With a cast-iron notch diameter of 150 m, the diameter of the channel 7 of the separation plate 3 is 300 mm. With a decrease in the diameter of the channel 7, the speed of passage of the iron through it increases, which leads to the formation of a funnel and to the slag in the channel 7

При чрезмерном увеличении толщи ны разделительной плиты 3 увеличиваетс  длина канала 7, что повышает со противление потоку чугуна и увеличивает величину напора, о.бразующегос  в результате различных уровней рас плава до и после разделительной плиты 3,With an excessive increase in the thickness of the dividing plate 3, the length of the channel 7 increases, which increases the resistance to the flow of cast iron and increases the pressure produced by different levels of melting before and after the dividing plate 3,

Оптимальна  высота перевала 4 дл  слива чугуна определ етс  из сооношени The optimum height of the pass 4 for casting iron is determined from the coupling

. - Гцуг 1 2.- хУа1А. - Htsug 1 2.- XUA1A

И,TitVr UIAAnd, TitVr UIA

Н - высота сло  чугуна и H - the height of the layer of iron and

где шлака до разделительной плиты 3)where is slag to separation plate 3)

h, - высота сло  чугунаh, - the height of the layer of iron

после разделительной плиты 3;after separation plate 3;

h - высота перевала 4, рана  высоте сло  чугуна до разделительнойh - the height of the pass 4, the wound to the height of the layer of cast iron to the separation

плиты 3; . plates 3; .

Т.T.

- удельные веса чугунов - specific gravities of cast iron

UJAUja

4vr и шлака соответственно .4vr and slag respectively.

и составл етand is

7-60-ОО-а ,7-60-oo-a,

Ч- 7-2 SOH 7-2 SO

при высоте Н 130 CMJ Нд, 60 см; г/смг . 2 г/см.with a height of H 130 CMJ Nd, 60 cm; g / smg 2 g / cm.

Дл  предохранени  канала 7 разделительной плиты 3от разгара монолиный блок выполнен из двух половин: верхней и нижней, с разъемом по оси канала, что позвол ет быстро и без больших затрат производить его замену .To protect channel 7 of the separation plate 3 from the height, the monolith block is made of two halves: the upper and the lower, with a connector along the axis of the channel, which allows it to be replaced quickly and inexpensively.

Предлагаемое устройство позвол е по сравнению с известным увеличить выход товарного чугуна ориентировочно на 0,488% в год.The proposed device allows, compared with the known, to increase the yield of commercial iron approximately 0.488% per year.

Экономи  товарного чугуна в тоннах составл ет, ориентировочно,. 18000 т и в рубл х 920000 руб.Saving commercial iron in tonnes is approximately. 18,000 tons and in rubles x 920000 rubles.

Кроме того, предлагаемое устройство по сравнению с известным проще по конструкции, надежнее и удобнее в экспулатации, позволит сэкономить средства по ремонту перевала дл  чугуна и,может быть использовано на любых металлургических агрегатах |ДЛЯ разделени  продуктов плавки, имек цих различные удельные веса.In addition, the proposed device, in comparison with the known one, is simpler in design, more reliable and easier to operate, it will save money on repairing the pass for cast iron and can be used on any metallurgical units | FOR the separation of smelting products, and various specific weights.

Claims (1)

Формула изобретени Invention Formula Устройство дл  выпуска чугуна и шлака из доменной печи, содержащее центральный желоб, желоб дл  слива чугуна,- шлакоотвод, разделительную плиту, перевалы дл  чугуна и шлака, отличающеес  тем, что, с целью повышени  степени отделени  «угуна от шлака, предотвращени  разгара перевала дл  чугуна, разделительна  плита выполнена в виде монолитного блока со,сквозным наклонным каналом, нижний край нижнего конца которого совмещен с дном центрального желоба, а нижний край верхнего конца канала совмещен с дно желоба дл  выпуска чугуна.A device for discharging pig iron and slag from a blast furnace, containing a central chute, a chute for casting iron, slag removal, separation plate, passes for iron and slag, characterized in that, in order to increase the degree of separation of "coal from slag, prevent the height of the pass for cast iron, the separation plate is made as a monolithic block with a through inclined channel, the lower edge of the lower end of which is aligned with the bottom of the central gutter, and the lower edge of the upper end of the channel is aligned with the bottom of the gutter to release the cast iron. Источники информации, прин тые во внимание при экспертизеSources of information taken into account in the examination 1,Ефименко Г.Г. и др. Металлурги чугуна. К. 1974, с 366-369,1, Efimenko G.G. and others. Metallurgists of cast iron. K. 1974, from 366-369, 2,Авторское свидетельство СССР 600187, кл, С 21 В 5/04, 1978,2, USSR Copyright Certificate 600187, class, C 21 V 5/04, 1978, 3,Авторское свидетельство СССР № 336347, кл, С 21 В 7/14, 1972.3, USSR Author's Certificate No. 336347, class, C 21 B 7/14, 1972.
SU792761149A 1979-03-22 1979-03-22 Device for cast iron and slag outlet from blast furnace SU850664A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU792761149A SU850664A1 (en) 1979-03-22 1979-03-22 Device for cast iron and slag outlet from blast furnace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU792761149A SU850664A1 (en) 1979-03-22 1979-03-22 Device for cast iron and slag outlet from blast furnace

Publications (1)

Publication Number Publication Date
SU850664A1 true SU850664A1 (en) 1981-07-30

Family

ID=20825584

Family Applications (1)

Application Number Title Priority Date Filing Date
SU792761149A SU850664A1 (en) 1979-03-22 1979-03-22 Device for cast iron and slag outlet from blast furnace

Country Status (1)

Country Link
SU (1) SU850664A1 (en)

Similar Documents

Publication Publication Date Title
US4385931A (en) Method and furnace for refining of magnesium
SU850664A1 (en) Device for cast iron and slag outlet from blast furnace
EP0233404A1 (en) Method and plant for continuous production of steel from ore
SU901275A1 (en) Main chute of blast furnace
SU1135766A1 (en) Method for tapping melt from hearth steel smelting unit
RU2024618C1 (en) Main chute of blast furnace
SU802376A1 (en) Chute for outlet and treatment of liquid metal
US6174492B1 (en) Forebay for am Metallurgical furnace
SU846553A1 (en) Main hearth chute of blast furnace
SU939562A1 (en) Main trough of blast furnace
SU865908A1 (en) Main chute of blast furnace
SU1222680A1 (en) Device for separating cast iron and slag
SU896073A1 (en) Blast furnace chute device
JPH0783575A (en) Molten metal tapping runner
JPS6383208A (en) Separation of blast furnace iron and slag
SU973618A1 (en) Apparatus for separating melts
SU934182A1 (en) Chute for treating and discharging metal out of melting furnace
US1717813A (en) Melting furnace
SU998524A2 (en) Main trough of blast furnace
SU1323577A1 (en) Method of discharging ferroalloys from furnace
US4000071A (en) Apparatus for separating phosphorus furnace slag and ferrophosphorus from one another
RU2101125C1 (en) Steel tapping launder for mixing steel with refinery slag
SU885774A1 (en) Trough for discharging silicate melt
RU2027772C1 (en) Device for smelting product tapping
SU1006490A1 (en) Device for continuously discharging smelting products from blast furnace