SU737600A1 - Method of making a floor in sliding form - Google Patents

Method of making a floor in sliding form Download PDF

Info

Publication number
SU737600A1
SU737600A1 SU782629114A SU2629114A SU737600A1 SU 737600 A1 SU737600 A1 SU 737600A1 SU 782629114 A SU782629114 A SU 782629114A SU 2629114 A SU2629114 A SU 2629114A SU 737600 A1 SU737600 A1 SU 737600A1
Authority
SU
USSR - Soviet Union
Prior art keywords
walls
reinforcement
slab
concreting
formwork
Prior art date
Application number
SU782629114A
Other languages
Russian (ru)
Inventor
Владимир Архипович Пономаренко
Владимир Ильич Папазов
Валерий Семенович Мурадов
Григорий Семенович Платок
Original Assignee
Макеевский Инженерно-Строительный Институт
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Макеевский Инженерно-Строительный Институт filed Critical Макеевский Инженерно-Строительный Институт
Priority to SU782629114A priority Critical patent/SU737600A1/en
Application granted granted Critical
Publication of SU737600A1 publication Critical patent/SU737600A1/en

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

(54) СПОСОБ ВОЗВЕДЕНИЯ ПЕРЕКРБ1ТИЯ В СКОЛБЗЯЩЕЙ Изобретение относитс  к области строительства и может быть использовано при возведении зданий в скольз щей опалубке. Известен способ возведени  перекрытий в здани х, возводимых в скольз щей опалубке , состо щий в том, что бетонирование стен прекращаетс  на уровне перекрыти  этажа, устанавливаетс  щитова  опалубка перекрыти , производитс  его бетонирование, а затем продолжаетс  бетонирование стен в скольз щей опалубке 1. Недостатком такого способа  вл етс  вынужденна  остановка скольз щей опалубки с потерей темпа возведени  стен и высока  трудоемкость возведени  перекрытий в св зи с необходимЪстью применени  мелкощитовой опалубки. Известен также способ возведени  перекрытий в скольз щей опалубке, предусматривающий устройство жесткой железобетонной опорной консоли дл  каждого перекрыти , армирование и бетонирование стен и перекрытий в вертикальном положении, последующий поворот плит перекрытий в горизонтальное положение и их закрепление 2.(54) METHOD OF CONSTRUCTING A SUBSTRUCTIVE SURFACE The invention relates to the field of construction and can be used in the erection of buildings in sliding formwork. There is a method of erecting floors in buildings erected in sliding formwork, which means that the concreting of the walls stops at the level of the floor overlap, the shield formwork of the floor is installed, concreting takes place, and then the concrete is concreted into the sliding formwork 1. The disadvantage of this The method consists in the forced stopping of a sliding formwork with a loss of the pace of wall erection and the complexity of the construction of floor slabs in connection with the need for the use of small-panel formwork. There is also known a method of erecting slabs in a sliding formwork, providing for the installation of a rigid reinforced concrete support console for each floor, reinforcement and concreting of walls and floors in a vertical position, subsequent rotation of the floor plates to a horizontal position and their fixation 2.

Claims (2)

ОПАЛУБКЕ Недостатком такого способа  вл етс  его высока  трудоемкость из-за необходимости устройства в специальной опалубке железобетонных консолей. Целью изобретени   вл етс  сокращение трудоемкости возведени  перекрытий зданий , возводимых в скольз щей опалубке. Указанна  цель достигаетс  тем, что в способе возведени  перекрыти  в скольз щей опалубке, включающем установку опоры перекрыти , армирование стен и перекрыти , одновременное бетонирование стен и перекрыти  в вертикальном положении, поворот перекрыти  в горизонтальное положение и его закрепление, перед бетонированием стен и перекрыти  арматуру нижнего торца перекрыти  соедин ют с. арматурой стены горизонтальными стержн ми, а под ними устраивают опору из сыпучего материала, а после бетонировани  стен и перекрыти  удал ют опору из сыпучего материала. На фиг. 1 изображена скольз ща  опалубка дл  совмещенного возведени  стены и плиты перекрыти , общий вид; на фиг. 2 - поворот плиты перекрыти  из вертикального в горизонтальное положение на арматурных стержн х; на фиг. 3 - узел стыка перекрыти  со стеной здани . Способ возведени  перекрытий выполн етс  с применением скольз щей опалубки , состо щей из домкратных рам Г, к кото рым прикреплены наружные щиты 2 и внутренний щит 3. Внутренный щит 3 подвещен к домкратной раме 1 на. стержне 4, который пропущен через домкрат 5. , Воз8ёдение перекрыти  осуществл етс  следующим образом. На отметке установки будущего меж 27ЭТа ) перекрыти  в полость скольз щей опалубки стены укладывают бетонную смесь, а в полость перекрыти  подают сыпучий материал, например песок 6. Перед укладкой бетонной смеси в опалубку стены устанавливают закладные детали 7 и креп т их к арматуре стеньь Затем включают домкраты 5 и поднимают внутренние щиты 3 на высоту, обеспечивающую возможность установки горизонтальных стержней 8, сое Дин йщйх арматуру стены с арматурой нижнего торца плиты перекрыти . Расклинива ТОТЦанговые захваты на домкратах 5 и вклю чают в работу домкраты 9 подъема домкратной рамы с одновременным бетонированием стены 10 и плиты 11. При этом наружные щиты 2 опалубки перемещаютс  вверх, а внутренний щит 3 остаетс  неподвижным. Когда верхний торец щита 3 займет лйЖёние верхних торцов щитов 2, включают ПТГ Цэнговые захваты домкратов 5 и внутренний щит 3 начинает перемещатьс  совместно с наружньши щитами 2 при одновременной подаче бетонной смеси в стену 10 и плиту перекрыти  11 до верхнего ее торца. Следующий цикл изготовлени  плиты перекрытий очередного этажа производитс  аналогично. Поворот плиты перекрь ти  производитс  следующим образом. Удал ют песок 6, разрезают арматурные стержни 12 и концы их загибают. Затем краном осуществл ют поворот плиты 11 на арматурных стержн х 8, которые, изгиба сь, содают щарнир, удерживающий плиту в проектном положении, и приваривают концы стержней 12 к закладным детал м 7. Остальные тристороны плиты креп т к. стенам известным способом, например с помощью опорных столиков. Формула изобретени  Способ возведени  перекрыти  в скольз щей опалубке, включающий установку опоры перекрыти , армирование стен и перекрыти , одновременное бетонирование стен и перекрыти  в вертикальном положении, поворот перекрыти  в горизонтальное положение и его закрепление, отличающийс  тем, что, с целью сокращени  трудоемкости, перед бетонированием стен и перекрыти  арматуру нижнего торца перекрыти  соедин ют с арматурой стены горизонтальными стержн ми, а под ними устраивают опору из сыпучего материала, а после бетонировани  стен и перекрыти  удал ют опору из сыпучего ма-. териала. Источники информации, прин тые во внимание при экспертизе 1.Авторское свидетельство СССР № 372334, кл. Е 04 G 11/22, 1969. FORMWORK The disadvantage of this method is its high labor intensity due to the need for a device in a special formwork of reinforced concrete consoles. The aim of the invention is to reduce the laboriousness of erecting floors of buildings erected in sliding formwork. This goal is achieved by the fact that in the method of erection of a slab in a sliding formwork, including the installation of a support block, reinforcement of walls and blocking, simultaneous concreting of walls and blocking in a vertical position, turning the block into a horizontal position and fixing it, before concreting the walls and blocking the bottom reinforcement the end of the overlap is connected to. reinforcing the walls with horizontal rods, and below them arranging a support from the bulk material, and after concreting the walls and blocking, removing the support from the bulk material. FIG. Figure 1 shows sliding formwork for the combined construction of a wall and a floor slab, general view; in fig. 2 - rotation of the slab from the vertical to the horizontal position on the reinforcing bars; in fig. 3 - junction node with the wall of the building. The method of erection of floors is carried out using sliding formwork consisting of jacking frames G, to which external shields 2 and internal shielding 3 are attached. Inner shield 3 is connected to jacking frame 1 on. the rod 4, which is passed through the jack 5. The overlap is performed as follows. At the level of the installation of the future between 27ET), the concrete mix is placed in the cavity of the sliding formwork, and the bulk material, such as sand 6, is fed into the closing cavity. Before placing the concrete mix, the fixtures 7 are installed in the formwork and attached to the reinforcement. jacks 5 and raise the internal shields 3 to a height that provides the ability to install horizontal rods 8, soy Dynchyh wall reinforcement with reinforcement of the lower end of the slab. Rattling TOTsang grips on jacks 5 and turning on jacks 9 lifting the jacking frame while concreting the wall 10 and the plate 11. At the same time, the outer shields 2 of the formwork move upwards, and the inner shield 3 remains stationary. When the upper end of the shield 3 occupies the upper edge of the shields 2, turn on the PTG Zeng grips of the jacks 5 and the inner shield 3 begins to move together with the outer shields 2 while simultaneously supplying the concrete mix to the wall 10 and the slab 11 to its upper end. The next production cycle of the floor slab of the next floor is made similarly. The rotation of the skid plate is as follows. Sand 6 is removed, rebar 12 is cut and its ends are bent. Then, the crane rotates the plate 11 on the reinforcing rods x 8, which, bending, soda the hinge holding the slab in the design position, and weld the ends of the rods 12 to the embedded parts 7. The remaining tristoron plates are attached to the walls in a known manner, for example using support tables. Claims The method of erection of a slab in a sliding formwork, including the installation of a ceiling support, wall reinforcement and overlapping, simultaneous concreting of walls and overlapping in a vertical position, rotation of the overlap in a horizontal position and its fixation, characterized in that, in order to reduce labor intensity, before concreting the walls and the overlap reinforcement of the lower end of the overlap is connected to the reinforcement of the wall by horizontal rods, and under them arrange a support made of bulk material, and after concreting the walls and floors remove the support from the loose ma-. teriala. Sources of information taken into account during the examination 1. USSR author's certificate No. 372334, cl. E 04 G 11/22, 1969. 2.За вка Японии № 431050, НКИ 86С2, кл. Е 04 G 11/22, 68, публик. 46-15541, 71. .2. For Japan No. 431050, NCI 86C2, cl. E 04 G 11/22, 68, publ. 46-15541, 71.. JLJl 5five
SU782629114A 1978-06-07 1978-06-07 Method of making a floor in sliding form SU737600A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU782629114A SU737600A1 (en) 1978-06-07 1978-06-07 Method of making a floor in sliding form

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU782629114A SU737600A1 (en) 1978-06-07 1978-06-07 Method of making a floor in sliding form

Publications (1)

Publication Number Publication Date
SU737600A1 true SU737600A1 (en) 1980-05-30

Family

ID=20770336

Family Applications (1)

Application Number Title Priority Date Filing Date
SU782629114A SU737600A1 (en) 1978-06-07 1978-06-07 Method of making a floor in sliding form

Country Status (1)

Country Link
SU (1) SU737600A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2618817C1 (en) * 2016-05-30 2017-05-11 Александр Александрович Титов Method of erecting framework for structures
RU2699087C1 (en) * 2019-03-04 2019-09-03 Алексей Леонидович Торопов Method of structure carcassing

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2618817C1 (en) * 2016-05-30 2017-05-11 Александр Александрович Титов Method of erecting framework for structures
WO2017209650A1 (en) * 2016-05-30 2017-12-07 Александр Александрович ТИТОВ Method for erecting framework of structures
US11002004B2 (en) * 2016-05-30 2021-05-11 Titov Aleksandr Aleksandrovich Method for erecting framework of structures
RU2699087C1 (en) * 2019-03-04 2019-09-03 Алексей Леонидович Торопов Method of structure carcassing

Similar Documents

Publication Publication Date Title
SU737600A1 (en) Method of making a floor in sliding form
EA009928B1 (en) Method of constructing strip foundations with longitudinal groove, a foundation element and holding/leveling device provided therefor
JPH0455118Y2 (en)
GB2320737A (en) Semi precast method of construction of multi-storey buildings
RU2043470C1 (en) Method for erecting monolithic elements of a building, preferentially floor, and concrete form to implement it
SU1067174A1 (en) Sliding forms
RU1805191C (en) Formwork for erecting low-rise buildings
SU844732A1 (en) Method of constructing multistorey building in slide form
SU977644A1 (en) Method for erecting cast-in-place buildings
SU1661335A1 (en) Method of constructing ferroconcrete vaults on pneumatic formwork
SU1004576A1 (en) Method of erecting a building
SU1079785A1 (en) Method of constructing a multistorey building by adding floors from below
JP2877881B2 (en) How to build a reinforced concrete basement
SU1557295A1 (en) Method of erecting multistorey building by method of storey lifting
SU863810A1 (en) Three-dimensional shiftable form
RU2239691C2 (en) Method of reinforced concrete structure, mainly wall, forming with the use of sliding form and vibratory cantledge
SU927938A1 (en) Building construction method
SU1048093A1 (en) Method of erecting multistorey building by floor-rising technique
SU1406323A1 (en) Mobile forms for constructing solid houses
SU1043285A2 (en) Building construction method
SU1731921A1 (en) Movable shuttering
SU1740591A1 (en) Method of erecting monolithic building
RU55399U1 (en) FORMWORK SYSTEM
SU691545A1 (en) Shield form for the erection of cast-in-place reinforced concrete walls lined with a tile material
SU755968A1 (en) Method of erecting multistorey building with suspended storeys