GB2320737A - Semi precast method of construction of multi-storey buildings - Google Patents
Semi precast method of construction of multi-storey buildings Download PDFInfo
- Publication number
- GB2320737A GB2320737A GB9626126A GB9626126A GB2320737A GB 2320737 A GB2320737 A GB 2320737A GB 9626126 A GB9626126 A GB 9626126A GB 9626126 A GB9626126 A GB 9626126A GB 2320737 A GB2320737 A GB 2320737A
- Authority
- GB
- United Kingdom
- Prior art keywords
- facade
- unit
- cross walls
- construction
- brackets
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/16—Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material
- E04B1/161—Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material with vertical and horizontal slabs, both being partially cast in situ
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
A method of construction of multi-storey buildings using precast faGade and precast floor panels to eliminate water seepage, without the use of sealants, between the faGade panels and superstructure of the building by eliminating all external joints between the faGade and superstructure. The faGade 1 is installed on the superstructure before structural cross walls 2 are cast. The cross walls 2 are cast to embed the edges of the faGade 1. The faGade 1 is supported and held in place by the cross walls 2. Brackets 6 are provided on the sides of the faGade which interconnect with brackets of the faGade above. The interconnected brackets are embedded in the cross walls 2. Reinforced precast slabs 3 are laid on top of the cross walls 2 and act as formwork thereby minimizing the need for internal framework. Reinforced concrete is then laid on top of the precast slabs 3 to cast the floor of the unit above.
Description
SEMI PRECAST METHOD OF CONSTRUCTION
OF MULTI-STOREY BUILDINGS
This invention relates to a method of construction of multi-storey buildings using precast facade panels and precast floor panels in a manner so as to eliminate water seepage through joints and to substantially reduce time to complete construction of the multi-storey building.
The traditional method of construction of multi-storey buildings using precast concrete facade involves the erection of structural walls first. Once the structural walls are in place the floor is then laid on top. The walls require formwork to be erected around reinforcement, into which concrete can be poured. The floor requires formwork, which may consists of plywood or timber batons, to be erected and this formwork has to be supported by a system of framework. Steel reinforcements are laid on the formwork and concrete is then placed on to the formwork to cast the floor. Once the concrete has set the formwork and the supporting framework can be removed.
This has to be carried out from the floor below. Table formwork can be used in place of plywood or timber batons to cast the floor above. The disadvantage with the use of table formwork is that in order for the formwork to be removed, once the floor has set the unit must have a suitable opening.
Therefore the facade cannot be erected until the table formwork has been removed from the unit.
Once the cross walls and floor have been cast, precast facade units are then lifted into place and attached to the superstructure by mechanical means at the appropriate place. This can be in the form of brackets and bolts connection or interlocking of reinforcement encased by grout or concrete. The joint between the facade unit and the superstructure is filled with grout or concrete and is sealed with rubber strips between the facade and the superstructure and finally mastic pointing is provided to provide a waterproof seal. Once the facade has been put into place only then can the internal and external finishing work commence.
The problem inherent with this method of construction is water seepage through the joint where the facade is joined to the superstructure. In addition this method requires external scaffolding to be erected around the superstructure, to enable the facade panels to be fitted and grouted and also internal framework to be erected to support formwork for the floor panels. As a result more workers are required at the construction site and completion times are longer. The necessity to erect formwork requires a large supply of plywood and timber beams and the erection of the formwork for the floor takes time.
The internal and external finishing work cannot be commenced until the facade unit has been put into place and the formwork, together with supporting framework for the floor panel, removed.
The semi-precast method of construction overcomes the problems inherent with the traditional method of construction. It is an object of the present invention to eliminate water seepage through the joint where the facade is attached to the superstructure by eliminating all external joints.
In addition the semi-precast method of construction eliminates the need for external scaffolding around the building as well as the need for formwork for floor slabs. Further the need for internal supporting framework to support the floor of the unit vertically above is minimized.
Unlike the traditional method of construction with the present method a precast facade is erected first. This is followed by the construction of the structural cross walls, which are cast into the facade so as to embed the edges of the facade and thereby support and hold the facade. Once the facade and the cross walls have been erected the precast floor slabs are placed on the top of the cross walls. The precast floor slab is then topped with concrete to form the floor of the unit above.
The present method of construction significantly reduces the time required to complete the construction compared to the traditional method of construction.
In addition this method of construction requires fewer workers as the need for external scaffolding and external grouting are eliminated. The absence of external scaffolding also increases safety at the construction site. Further the need for internal supporting framework is minimized.
The semi-precast method of construction consists of several distinct steps.
These steps will be now be described in detail.
Precast facade construction and design
Each semi-precast facade unit is constructed by the use of suitably designed moulds. Window frames are cast in situ in the mould ie. they are fixed into the mould at the appropriate place and reinforcement is placed in the mould.
Concrete is then poured into the mould and is finished off. Once the concrete is set the mould and the precast facade is then covered and steam cured to ensure a better quality of final product.
The width of the facade is wider than the internal width of the unit it covers and the sides of the facade are then embedded into the cross walls during construction.
The height of the facade is such that it may be of the same height as the opening it covers, or it may have an overhang on the outer face of the facade, which overhangs and may partly or wholly cover the outer face of the concrete floor of the unit, covered by the facade.
Vertically disposed brackets, which may be made of steel, are cast into either side of the facade at the top edge and project above the height of the facade and horizontally disposed steel brackets are cast into either side of the facade at the bottom edge. The disposition of these brackets is such that the vertically disposed brackets at the top of the facade unit interconnect with the horizontally disposed brackets at the bottom edge of the facade unit which is located directly above ie. vertically adjacent. These interconnected brackets are mechanically locked together. These brackets also provide support to the facade during the installation process and they are cast into the structural cross walls.
The facade itself may be of the same height as the opening that it covers, or the facade may have an overhang on the bottom of the outer face, so that it overhangs the size of the opening that it covers.
Precast floor slabs
Each precast floor slab unit is constructed by the use of suitably designed moulds. Steel reinforcement is laid along the mould and concrete is then poured on to the mould to cover the reinforcement. The concrete is then compacted by vibration. The floor panel is then lifted together with the mould and transferred to a steam curing chamber where it is cured. Once the floor slab panels have been steam cured they are removed from the curing chamber and stacked on site until required for use.
Construction
As stated previously in the traditional method of construction the structural walls are erected primarily and the floor unit is laid on top of this. With the semi-precast method of construction the precast facade unit is erected first, before the structural cross walls are constructed.
The facade is initially lifted into place. The facade is supported temporarily during the installation by the brackets built into the facade and this allows the facade to be placed into position.
During the installation process the vertically disposed brackets, located at the top of the facade on either side, from the facade unit below, interconnect with the horizontally disposed brackets, located at the bottom of the facade on either side, from the facade unit above, and are mechanically locked together.
Once the facade has been installed into place the structural cross walls are cast. Steel reinforcement is erected for the cross walls and this is interlinked with the reinforcement from the facade. The reinforcement is then encased in formwork and concrete is then poured into the formwork to cast the cross walls. The width of the facade is greater than the width between the cross walls and as a result the structural cross walls are cast into the facade ie the projecting edges of the facade are embedded in the concrete of the cross walls. This creates a concrete to concrete construction joint which is water tight. There are thus no joints between the supporting cross walls and the facade. Water seepage is thus eliminated.
The brackets in the facade units are cast into the cross wall and the facade is itself supported and held in place by the cross walls. The height of the cross walls is the same as the height of the facade and as a result the vertically disposed brackets at the top edges of the facade project out vertically from the cross wall. The horizontally disposed brackets, at the bottom edges of the facade, from the facade unit above, interlock with the vertically disposed brackets projecting vertically from the facade unit below. The interlocked brackets are locked mechanically and the locked brackets are fully embedded in the cross walls.
Once the facade has been cast into the cross walls, supporting frames are inserted between the cross walls. A precast floor panel is then lowered on to the supporting frames. The size of the floor slab is such that it overlaps the structural cross walls and rests thereon. Slab reinforcement is then laid on top of the precast floor slab unit and concrete is poured around the reinforcement.
The concrete is then compacted by vibration and the surface is smoothed.
This then forms the basis for the floor of the unit above. The precast floor slabs eliminate the need for formwork to be erected inside the structure to support the floor above and minimizes the need for internal supporting framework. The precast floor slab acts as the formwork on which the floor for the unit above is cast by supporting the slab reinforcement and the concrete for the floor above.
In this manner no table formwork or internal supporting framework is required in order to lay the floor. As a result internal works in the unit can commence after the precast floor slab has been laid.
In order that the semi-precast method of construction may be more fully understood it will now be described by reference to the drawings.
Fig 1. Is a perspective view of the precast facade unit with vertically and horizontally disposed steel brackets on either side of the facade.
Fig 2. Is a perspective view of a completed unit illustrating the cross walls, precast floor slab and the facade.
Fig 3. Is a perspective view of two vertically adjacent units illustrating the cross walls, precast floor slabs and the facade units.
Fig 4. Is a plan view of the facade unit cast into the cross walls.
Fig 4A. Is a detailed view of the interlinking of the reinforcement of the facade and the cross walls.
Fig 5. Is a cross section of the floor slabs cast into the cross walls.
Fig 6. Is a detailed cross-sectional view of the joint between the precast floor slab and the facade unit of two vertically adjacent units.
The vertically (4) and horizontally (5) disposed brackets on either side of the top and bottom of the facade unit (1) are illustrated in Fig. 1 as is the overhang (13) on the outer face of the facade. From this illustration the window frames cast into the facade is also clearly seen.
The overall arrangement of two completed vertically adjacent units can be seen in Fig. 3 which clearly shows the relationship between the precast facade (1), cross walls (2), precast floor slabs (3), the vertically disposed brackets (4) located at the top edge of the facade and the horizontally disposed brackets (5) located at the bottom edge of the facade. Fig. 3 further shows the interconnection of the vertically disposed bracket from the facade unit below with the horizontally disposed bracket of the facade unit above (6) and further shows the disposition of the vertically disposed bracket once it has been embedded in the cross wall (4A).
The disposition of the precast floor slab in relation to the cross walls and the facade can be seen in Figs. 2 and 3. Fig. 5 shows a cross section across the face of a unit showing the relationship of the precast floor slabs cast into the cross walls. Fig 6 shows cross section detail of the joint between the facade unit, the precast slab and the concrete floor laid on the precast slab. It can be seen from Figs. 2 and 3 that the precast floor slabs rest on, and are supported by, the cross walls of the unit.
The joint between the cross walls and the facade can be seen in Fig. 4. It can be seen that the edges of the facade are embedded into the cross walls. Fig.
4A shows the interlinking of the reinforcement of the facade (11) and the reinforcement of the cross wall (12) surrounded by the concrete of the facade (1) and the concrete of the cross wall (2).
During installation a facade unit (1) is lowered, by suitable lifting means, onto the concrete floor of the unit under construction. The facade is held in place by the vertical (4) and horizontal (5) brackets and is adjusted to a vertical position. The horizontally disposed metal brackets (5), situated at bottom edges of the facade, interconnect with the vertically disposed brackets (4) at the top edges of the facade, from the facade unit below. The interconnected brackets are then locked mechanically.
With the facade in place, steel reinforcement is then erected to form the cross walls. The reinforcement of the cross walls (12) is interlinked with the reinforcement of the facade unit (11) and the cross wall is then cast, using suitable formwork, so as to embed the edges of the facade (12) and fully embed the interlocked brackets (6) of the vertically adjacent facade units. This creates a concrete construction joint between the cross walls and the facade which is watertight. There is therefore no external joint between the facade and the cross walls. The cross walls support and hold the facade units in place.
The height of the cross walls are level with the height of the facade and as a result the vertically disposed brackets (4) of the facade project out of the cross walls (4A) and can receive the horizontal brackets of the facade unit to be placed vertically adjacent.
A precast floor slab (3) is then lowered on to the top of the cross walls. The precast floor slab is supported by the cross walls. The precast floor slab acts as the formwork on which the floor of the unit vertically adjacent (9) can be cast.
Reinforcement is then laid on the precast slab and concrete poured onto the reinforcement to cast the floor of the unit above.
Claims (9)
1. A method of construction of multi-storey buildings using precast facade
panels and precast floor slabs wherein external joints between the
precast facade and the superstructure of the building are eliminated and
wherein the use of external scaffolding and formwork for floor slabs is
eliminated and the need for supporting framework inside the unit to
support the floor of the unit above is minimized.
2. A method of construction as claimed above wherein the edges of the
precast facade are cast into and embedded in the structural cross walls
of each unit in the building thereby creating a concrete construction
joint between the facade and the cross walls which is watertight.
3. A method of construction as claimed above wherein the facade is
installed on the superstructure first before the structural cross walls are
cast and wherein the reinforcement of the cross walls is interlinked with
the reinforcement of the facade prior to the cross walls being cast.
4. A method of construction wherein the facade is disposed with brackets
cast into either side of the facade at the top and bottom edges and
wherein the brackets at the top of the facade are disposed vertically in
relation to the side of the facade and which project above the height of
the facade and wherein the brackets at the bottom of the facade are
disposed horizontally in relation to the side of the facade and wherein
the said vertical and horizontal brackets are provided with means to
lock together.
5. A method of construction as claimed above wherein the vertically
disposed brackets of the facade unit interconnect during installation with
the horizontally disposed brackets of the facade unit vertically above
and wherein the said interconnected vertical and horizontal brackets are
mechanically locked together.
6. A method of construction wherein the interlocked brackets at the
bottom edge of the facade are fully embedded in the structural cross
walls and wherein the vertically disposed brackets at the top edge of the
facade is partly embedded in the cross walls and partly projects
vertically out of the cross walls so as to interconnect with the
horizontally disposed brackets of the facade unit vertically above and
wherein the cross walls hold and support the facade unit in place.
7. A method of construction as claimed above wherein the facade may
have an overhang on the outer face of the facade which projects below
the base of the facade and which overhangs and partly or wholly covers
the outer face of the concrete floor of the unit, covered by the facade.
8. A method of construction as claimed above wherein a precast floor slab
is laid on top of the cross walls of the unit such that it rests on top of and
is supported by the cross walls and wherein the precast floor slab is
made of reinforced concrete and wherein the precast floor slab acts as
the formwork for the floor of the unit above thereby minimizing the
need for supporting framework within the unit.
9. A method of construction as claimed above wherein reinforcement is
laid on top of the precast floor slab and the floor of the unit above is cast
on the precast floor slab.
Priority Applications (5)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB9626126A GB2320737B (en) | 1996-12-17 | 1996-12-17 | Semi precast method of construction of multi-storey buildings |
SG1997004425A SG71072A1 (en) | 1996-12-17 | 1997-12-12 | Semi precast method of construction of multi-storey buildings limited |
MYPI9706059 MY115475A (en) | 1996-12-17 | 1997-12-16 | Semi precast method of construction of multi- storey buildings. |
CN 97125767 CN1120926C (en) | 1996-12-17 | 1997-12-17 | Semi precast method of construction of multi-storey buildings |
HK98113268A HK1011875A1 (en) | 1996-12-17 | 1998-12-14 | Semi precast method of construction of multi-storey buildings |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB9626126A GB2320737B (en) | 1996-12-17 | 1996-12-17 | Semi precast method of construction of multi-storey buildings |
Publications (3)
Publication Number | Publication Date |
---|---|
GB9626126D0 GB9626126D0 (en) | 1997-02-05 |
GB2320737A true GB2320737A (en) | 1998-07-01 |
GB2320737B GB2320737B (en) | 2000-11-08 |
Family
ID=10804537
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
GB9626126A Expired - Fee Related GB2320737B (en) | 1996-12-17 | 1996-12-17 | Semi precast method of construction of multi-storey buildings |
Country Status (5)
Country | Link |
---|---|
CN (1) | CN1120926C (en) |
GB (1) | GB2320737B (en) |
HK (1) | HK1011875A1 (en) |
MY (1) | MY115475A (en) |
SG (1) | SG71072A1 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2330860A (en) * | 1997-10-31 | 1999-05-05 | Leighton Contractors | A method of constructing a multi-storey building |
SG94837A1 (en) * | 2001-02-14 | 2003-03-18 | Gammon Finance Ltd | Module |
CN101851979A (en) * | 2010-04-02 | 2010-10-06 | 清远市建巢工业设计有限公司 | Prefabricated reinforced concrete unit body for construction and method for building construction |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102230338A (en) * | 2011-03-17 | 2011-11-02 | 有利华建筑预制件有限公司 | Prefabricated toilet and construction method and installation method thereof |
CN102230339A (en) * | 2011-03-17 | 2011-11-02 | 有利华建筑预制件有限公司 | Prefabricated kitchen and construction and installation method thereof |
CN102296837B (en) * | 2011-07-13 | 2013-04-10 | 有利华建筑预制件有限公司 | Multistoried building with prefabricated members and semi-prefabricating construction method of multistoried building |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2051198A (en) * | 1979-06-19 | 1981-01-14 | Collins L D | Method of Constructing a Multi-storey Building |
-
1996
- 1996-12-17 GB GB9626126A patent/GB2320737B/en not_active Expired - Fee Related
-
1997
- 1997-12-12 SG SG1997004425A patent/SG71072A1/en unknown
- 1997-12-16 MY MYPI9706059 patent/MY115475A/en unknown
- 1997-12-17 CN CN 97125767 patent/CN1120926C/en not_active Expired - Lifetime
-
1998
- 1998-12-14 HK HK98113268A patent/HK1011875A1/en not_active IP Right Cessation
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2051198A (en) * | 1979-06-19 | 1981-01-14 | Collins L D | Method of Constructing a Multi-storey Building |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2330860A (en) * | 1997-10-31 | 1999-05-05 | Leighton Contractors | A method of constructing a multi-storey building |
GB2330860B (en) * | 1997-10-31 | 2002-03-13 | Leighton Contractors | A method of constructing a building |
SG94837A1 (en) * | 2001-02-14 | 2003-03-18 | Gammon Finance Ltd | Module |
CN101851979A (en) * | 2010-04-02 | 2010-10-06 | 清远市建巢工业设计有限公司 | Prefabricated reinforced concrete unit body for construction and method for building construction |
CN101851979B (en) * | 2010-04-02 | 2012-11-14 | 清远市建巢工业设计有限公司 | Prefabricated reinforced concrete unit body for construction and method for building construction |
Also Published As
Publication number | Publication date |
---|---|
MY115475A (en) | 2003-06-30 |
GB2320737B (en) | 2000-11-08 |
HK1011875A1 (en) | 1999-07-23 |
GB9626126D0 (en) | 1997-02-05 |
CN1195064A (en) | 1998-10-07 |
CN1120926C (en) | 2003-09-10 |
SG71072A1 (en) | 2000-03-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20020059763A1 (en) | Pre-fabricated bathroom | |
US7185467B2 (en) | Modular system of permanent forms for casting reinforced concrete buildings on site | |
CN106013811B (en) | A kind of installation method of assembled architecture | |
CA2227258C (en) | Apparatus and process for casting large concrete boxes | |
CN101818527B (en) | Assembled integral shear wall structure system and construction method thereof | |
CN105781125B (en) | A kind of installation method of assembled architecture | |
US4799982A (en) | Method of molding monolithic building structure | |
CN108005387B (en) | Synchronous construction method for cast-in-place main body of assembled wallboard and short-limb shear wall | |
CN112854813A (en) | Profile steel tray structure for ancient building translation and underpinning method | |
EP1757750A1 (en) | Construction system based on prefabricated plates | |
US20080005990A1 (en) | Modular system of permanent forms for casting reinforced concrete buildings on site | |
US4408434A (en) | Multi-storey building and a prefabricated panel for such a building | |
JPH08209825A (en) | Outer wall panel for building and wall face construction method for building | |
GB2320737A (en) | Semi precast method of construction of multi-storey buildings | |
WO1991019055A1 (en) | A method of erecting a foundation structure for a building substructure | |
CN110219366A (en) | Assembled architecture heat preserving formwork integral structure and construction method | |
CN109339100A (en) | A kind of open trench tunnel falsework system and construction | |
CN214090002U (en) | Basement outer wall post-cast strip is enclosed construction in advance | |
CN111379337B (en) | Secondary structure anti-seepage and anti-leakage construction method | |
CN210369293U (en) | Integrated structure of assembled building heat preservation formwork | |
WO1986000043A1 (en) | Building system and portable masonry plant suitable therefor | |
SU1067174A1 (en) | Sliding forms | |
GB2065192A (en) | Method of constructing a multi- storey building | |
RU1805191C (en) | Formwork for erecting low-rise buildings | |
CN219909046U (en) | Assembled retaining wall post-cast strip plugging member |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
730 | Substitution of applicants allowed (sect. 30/1977) | ||
PCNP | Patent ceased through non-payment of renewal fee |
Effective date: 20031217 |