EA009928B1 - Method of constructing strip foundations with longitudinal groove, a foundation element and holding/leveling device provided therefor - Google Patents

Method of constructing strip foundations with longitudinal groove, a foundation element and holding/leveling device provided therefor Download PDF

Info

Publication number
EA009928B1
EA009928B1 EA200601407A EA200601407A EA009928B1 EA 009928 B1 EA009928 B1 EA 009928B1 EA 200601407 A EA200601407 A EA 200601407A EA 200601407 A EA200601407 A EA 200601407A EA 009928 B1 EA009928 B1 EA 009928B1
Authority
EA
Eurasian Patent Office
Prior art keywords
foundation
elements
trench
longitudinal groove
strip
Prior art date
Application number
EA200601407A
Other languages
Russian (ru)
Other versions
EA200601407A1 (en
Inventor
Милован Скендзик
Бранко Смрчек
Original Assignee
Мара-Институт Д.О.О.
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Мара-Институт Д.О.О. filed Critical Мара-Институт Д.О.О.
Publication of EA200601407A1 publication Critical patent/EA200601407A1/en
Publication of EA009928B1 publication Critical patent/EA009928B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • E02D27/02Flat foundations without substantial excavation

Abstract

The present invention relates to the construction of foundations for industrial buildings, to some foundation parts which become integral parts of the foundation and devices for holding and leveling the foundation parts. The method of constructing strip foundation with longitudinal socket groove is characterized in that the longitudinal socket groove is formed of plurality of pre-cast socket elements (3) having longitudinal grooves and projecting reinforcement (3.3) each of them is temporarily hanged over the trench (8), around the perimeter of the building layout, on holding/leveling devices (5), until being finally adjusted and leveled by the same devices, subsequently poured with fresh concrete to form the strip footing (4) into which the said elements (3) are incorporated through projecting reinforcement (3.3). The use of said invention provides a considerable man power and material safe making the process of foundation construction is less dependent of weather conditions.

Description

Область техникиTechnical field

Настоящее изобретение относится к сооружению фундаментов для промышленных зданий и других зданий сходного типа из железобетона и, в частности, к некоторым сборным элементам, которые образуют составную часть указанных фундаментов.The present invention relates to the construction of foundations for industrial buildings and other buildings of a similar type of reinforced concrete and, in particular, to some precast elements that form an integral part of these foundations.

Область техники, к которой относится изобретение, описана в международной патентной классификации 1РС, класс Е 02Ό 27/00, который касается сооружения фундаментов в целом, или же более подробно в классе Е 02Ό 27/32.The technical field to which the invention relates is described in the international patent classification 1PC, class E 02Ό 27/00, which relates to the construction of foundations in general, or in more detail in class E 02Ό 27/32.

Предпосылки изобретенияBACKGROUND OF THE INVENTION

Настоящее изобретение касается сооружения специальных ленточных фундаментов с продольной канавкой (гнездом), предназначенных для большепролетных строительных конструкций со стенами, образованными вертикальными несущими консольными панелями, поддерживающими крышу с промежуточными перекрытиями или без них. В частности, настоящее изобретение касается способа, элемента фундамента и устройства для сооружения подземной части указанных фундаментов.The present invention relates to the construction of special strip foundations with a longitudinal groove (nest) intended for long-span building structures with walls formed by vertical supporting cantilever panels supporting the roof with or without intermediate ceilings. In particular, the present invention relates to a method, a foundation element and a device for constructing the underground part of these foundations.

В ходе традиционного процесса сооружения фундамент здания формируется из уложенного бетона, на что затрачивается несколько дней и значительное количество человеко-часов. Настоящее изобретение значительно делает более рациональным традиционный процесс, сокращая его продолжительность до одного дня; для выполнения значительно упрощенной задачи подготовки такого фундамента усовершенствованный процесс требует наличия крана, определенного специализированного оборудования и всего нескольких работников.During the traditional construction process, the foundation of the building is formed from laid concrete, which takes several days and a significant number of man-hours. The present invention significantly makes the traditional process more rational, reducing its duration to one day; To accomplish a much simplified task of preparing such a foundation, an improved process requires a crane, certain specialized equipment and only a few workers.

Традиционная процедура, которая вкратце описана здесь для сравнения с настоящим изобретением, начинается с того, что в грунте ниже линии промерзания выкапывается траншея необходимой глубины, расположенная по периметру разметки здания. Затем дно траншеи заливается тонким слоем бетона (на затвердевание которого уходит по меньшей мере день) для создания ровной и чистой поверхности, на которой можно будет точно разместить арматуру ленточного фундамента из сварной сетки и арматуру продольного канала (или гнезд). После этого бетономешалки доставляют бетон на строительную площадку и заливают бетон, формируя плиту ленточного фундамента. Затем, прежде чем предпринять следующие шаги, требуется еще один день для затвердевания залитого таким образом бетона. После того, как затвердеет бетон плиты ленточного фундамента, должен быть завершен монтаж арматуры (если это не было сделано ранее). После этого устанавливаются боковые формы для того, чтобы ограничить пространство под две тонкие стенки канала продольного гнезда. Наконец, заливается канал под гнездо, и требуется еще несколько дней, чтобы бетон затвердел в достаточной степени для того, чтобы на него можно было устанавливать панели.The traditional procedure, which is briefly described here for comparison with the present invention, begins with the fact that a trench of the required depth is located in the ground below the freezing line, located along the perimeter of the marking of the building. Then, the bottom of the trench is poured with a thin layer of concrete (which takes at least a day to solidify) to create a smooth and clean surface on which it will be possible to precisely place the reinforcement of the strip foundation from the welded mesh and the reinforcement of the longitudinal channel (or nests). After this, the concrete mixers deliver the concrete to the construction site and pour the concrete, forming a slab of the strip foundation. Then, before taking the next steps, it takes another day to harden the concrete thus poured. After the concrete of the slab of the strip foundation has hardened, the installation of the reinforcement should be completed (if this has not been done before). After that, lateral forms are installed in order to limit the space for two thin walls of the channel of the longitudinal socket. Finally, a channel is poured under the nest, and it takes a few more days for the concrete to solidify sufficiently so that the panels can be installed on it.

Длинные и тонкие полосы, образующие продольную канавку, непросто изготовить и точно выровнять; на это уходит значительное количество человеко-часов на строительной площадке - в частности, на сооружение и выравнивание огромного количества форм, установку арматуры, бетонирование в два этапа (фундамент и канавка по отдельности), а также на другие операции; при этом связанные с погодой осложнения могут замедлить выполнение различных этапов строительства.Long and thin strips forming a longitudinal groove are not easy to manufacture and precisely align; it takes a significant amount of man-hours at a construction site - in particular, for the construction and alignment of a huge number of forms, installation of reinforcement, concreting in two stages (foundation and groove separately), as well as other operations; however, weather-related complications can slow down the various stages of construction.

Заявляемый способ, являющийся альтернативой процессам возведения традиционных фундаментов, изготавливаемых отливкой на месте, обладает по сравнению с известным способом несколькими преимуществами с точки зрения выполнения задачи сооружения фундаментов. Поскольку потребность в упрощении процесса существует всегда, предлагаемое изобретение позволяет ускорить традиционную процедуру и уменьшить трудозатраты за счет использования каналов из сборных бетонных элементов, которые доставляются на строительную площадку, надлежащим образом выравниваются с помощью соответствующих приспособлений и сразу же бетонируются. Таким образом, более простой и быстрый способ, предлагаемый в рамках настоящего изобретения, приводит к значительной экономии рабочей силы и материалов, делая весь процесс сооружения фундамента менее зависимым от погодных условий.The inventive method, which is an alternative to the processes of erecting traditional foundations made by casting in place, has several advantages in comparison with the known method in terms of performing the task of constructing foundations. Since the need to simplify the process always exists, the present invention allows to accelerate the traditional procedure and reduce labor costs by using channels from prefabricated concrete elements that are delivered to the construction site, properly aligned using appropriate devices and immediately concreted. Thus, the simpler and faster method proposed in the framework of the present invention leads to significant savings in labor and materials, making the entire process of building the foundation less dependent on weather conditions.

Описание изобретенияDescription of the invention

Как указано выше, общим предметом настоящего изобретения является быстрый и экономичный способ сооружения ленточных фундаментов с продольной канавкой для вышеупомянутых типов зданий, хотя тот же способ и оборудование могут использоваться для сооружения нескольких различных типов фундаментов. Стандартная несущая сборная стена из панелей, установленная на ленточном фундаменте и служащая для поддержки данного конкретного типа здания, показана на фиг. 1. Высокие и тонкие стеновые панели вставляются в продольные канавки, проходящие по периметру здания, временно выравниваются и фиксируются там с помощью клиньев, а затем окончательно закрепляются бетоном, заливаемым обычным способом в зазор между панелями и тонкими стенками канавки.As indicated above, the general subject of the present invention is a quick and economical method of constructing strip foundations with a longitudinal groove for the above types of buildings, although the same method and equipment can be used to construct several different types of foundations. A standard load-bearing prefabricated wall of panels mounted on a strip foundation and serving to support this particular type of building is shown in FIG. 1. Tall and thin wall panels are inserted into the longitudinal grooves running around the perimeter of the building, temporarily aligned and fixed there with wedges, and then finally fixed with concrete, poured in the usual way into the gap between the panels and thin walls of the groove.

Таким образом, настоящее изобретение включает быстрое размещение таких длинных элементов фундамента из железобетона, которые будучи временно подвешены, удерживаются в заранее определенном положении с помощью множества приспособлений для фиксации, пока все (или определенная часть) элементов не будет собрана и точно выровнена. Установленные таким образом и надежно закрепленные элементы фундамента окончательно закрепляются в заливаемом бетоне ленточного фундамента, становясь частью фундамента, как показано на фиг. 2.Thus, the present invention includes the quick placement of such long reinforced concrete foundation elements that are temporarily suspended and held in a predetermined position using a plurality of fixtures for fixation until all (or a certain part) of the elements are assembled and precisely aligned. The foundation elements thus installed and securely fixed are finally fixed in the poured concrete of the strip foundation, becoming part of the foundation, as shown in FIG. 2.

В наиболее распространенных каркасных системах-прототипах колонны или каркасы, несущиеIn the most common wireframe prototype systems, columns or frames carrying

- 1 009928 конструкции крыш/перекрытий, опираются на отдельные фундаменты, а усилия и изгибающий момент передаются на фундамент сосредоточенно. В данной системе, где размещение и нагрузка стен/панелей осуществляются равномерно вдоль ленточного фундамента, вертикальная нагрузка и изгибающие моменты передаются достаточно равномерно (на единицу длины) по всему фундаменту. По сравнению с отдельными фундаментами, продольные ленточные фундаменты, благодаря уменьшенному и значительно более низкому давлению на поверхности соприкосновения бетона и грунта, могут сооружаться на меньшей глубине; при этом равномерное распределение нагрузки и изгибающего момента по длине ленточного фундамента позволяет использовать более тонкие и более широкие ленточные фундаменты.- 1 009928 roof / ceiling structures, rely on separate foundations, and the forces and bending moment are concentrated on the foundation. In this system, where the placement / loading of walls / panels is carried out uniformly along the strip foundation, the vertical load and bending moments are transmitted fairly evenly (per unit length) throughout the foundation. Compared with individual foundations, longitudinal strip foundations, due to the reduced and significantly lower pressure on the contact surface of concrete and soil, can be constructed at a shallower depth; while the uniform distribution of load and bending moment along the length of the strip foundation allows the use of thinner and wider strip foundations.

Продольные канавки, обеспечивающие соединение с защемлением стеновых панелей и фундамента, требуют максимально точного выравнивания общего дна, поэтому целесообразно отливать их в стабильных фабричных условиях - в частности с использованием точных форм, при наличии в одном месте всего необходимого оборудования и вне зависимости от погодных условий.Longitudinal grooves, providing a connection with the jamming of wall panels and the foundation, require the most accurate alignment of the common bottom, so it is advisable to cast them in stable factory conditions - in particular, using accurate forms, if all the necessary equipment is in one place and regardless of weather conditions.

При использовании элементов фундамента, доставляемых на строительную площадку, возникает проблема их точного размещения и выравнивания по всей длине сформированного канала, состоящего из множества таких элементов, перед бетонированием ленточного фундамента. Для этого с целью окончательного формирования всей канавки, а также с целью обеспечения точной подготовки и идеального горизонтального выравнивания непрерывной продольной канавки используются фиксирующие приспособления, показанные на фиг. 7. Каждый элемент фундамента временно фиксируется парой таких приспособлений, как показано на фиг. 4. Будучи установлены таким образом, множество элементов фундамента, собранных в единую канавку, подвешиваются над дном траншеи на заранее заданной глубине. Таким образом, формируется подвешенная продольная канавка; нижние части концов соседних элементов 3 фундамента 4 могут быть расположены идеально близко друг к другу; эти элементы сделаны совместимыми, чтобы их выравнивание осуществлялось одними и теми же приспособлениями. Как показано на фиг. 4, балки 5.1 регулируемой длины приспособлений 5 для фиксации и выравнивания, перекинуты через траншею и опираются на две опоры 6, каждая из которых снабжена гидравлическим подъемником 6.1 для выравнивания по вертикали. Наклон элемента фундамента в траншее в поперечном направлении предотвращается за счет подвешивания на двух вертикальных тягах 5.3, длины которых заранее установлены равными. Наклон элемента 3 в продольном направлении регулируется с помощью гидравлических подъемников 6.1 опор 6. Движение элемента фундамента в направлении его оси, а также его поперечное поступательное движение обеспечивается роликами, расположенными между корпусами гидравлических подъемников 6.1 и опорными пластинами 6.4. Наиболее точные горизонтальные движения в обоих направлениях в горизонтальной плоскости осуществляются за счет скольжения корпуса опоры 6 по опорной пластине 6.4, обеспечиваемого гидравлическими приспособлениями или другими аналогичными средствами.When using the foundation elements delivered to the construction site, the problem arises of their exact placement and alignment along the entire length of the formed channel, consisting of many such elements, before concreting the strip foundation. For this purpose, with the purpose of the final formation of the entire groove, as well as with the aim of ensuring accurate preparation and perfect horizontal alignment of the continuous longitudinal groove, the fixing devices shown in FIG. 7. Each foundation element is temporarily fixed by a pair of such devices, as shown in FIG. 4. Being installed in this way, many foundation elements assembled into a single groove are suspended above the bottom of the trench at a predetermined depth. Thus, a suspended longitudinal groove is formed; the lower parts of the ends of adjacent elements 3 of the foundation 4 can be located perfectly close to each other; these elements are made compatible so that their alignment is carried out by the same devices. As shown in FIG. 4, beams 5.1 of adjustable length of fixtures 5 for fixing and leveling, are thrown over the trench and are supported by two supports 6, each of which is equipped with a hydraulic lift 6.1 for vertical alignment. The inclination of the foundation element in the trench in the transverse direction is prevented by hanging on two vertical rods 5.3, the lengths of which are previously set equal. The inclination of the element 3 in the longitudinal direction is controlled by means of hydraulic lifts 6.1 of the supports 6. The movement of the foundation element in the direction of its axis, as well as its transverse translational movement, is provided by rollers located between the cases of the hydraulic lifts 6.1 and the supporting plates 6.4. The most accurate horizontal movements in both directions in the horizontal plane are carried out by sliding the body of the support 6 along the supporting plate 6.4, provided by hydraulic devices or other similar means.

Чтобы обеспечить требуемое соединение между элементом фундамента и забетонированной полосой на строительной площадке, необходимо обеспечить соответствующее количество арматуры, выступающей со стороны основания элемента фундамента, как показано на фиг. 2. Элемент фундамента должен быть также оснащен определенным количеством продольной арматуры, которая предотвращает незначительные отклонения, вызванные подъемом и транспортировкой элемента, а также его нахождением над траншеей. После точного выравнивания такая временно подвешенная конструкция, образующая продольную канавку фундамента 4, заливается свежей бетонной смесью и таким образом надежно фиксируется.In order to provide the required connection between the foundation element and the concrete strip at the construction site, it is necessary to provide an appropriate amount of reinforcement protruding from the base side of the foundation element, as shown in FIG. 2. The foundation element must also be equipped with a certain amount of longitudinal reinforcement, which prevents minor deviations caused by the lifting and transportation of the element, as well as its location above the trench. After precise alignment, such a temporarily suspended structure, forming a longitudinal groove of the foundation 4, is poured with fresh concrete mix and thus securely fixed.

Главная цель настоящего изобретения - предложить элементы фундамента и методы, которые значительно облегчают и ускоряют сооружение фундамента здания указанного типа. Характер настоящего изобретения позволяет также сократить затраты рабочей силы, необходимой для сооружения фундамента. Нетрудно понять, что, если длина элементов фундамента составляет около 12 м, то для сооружения нескольких сотен метров готового фундамента за день достаточно всего нескольких квалифицированных рабочих. Еще одно преимущество заключается в конфигурации элементов фундамента, которые можно комбинировать множеством способов для создания широкого ассортимента планировок фундаментов с помощью комплекта элементов фундамента, которые могут быть доставлены на место проведения работ для быстрой сборки.The main objective of the present invention is to propose foundation elements and methods that greatly facilitate and accelerate the construction of the foundation of a building of this type. The nature of the present invention also reduces the labor costs required for the construction of the foundation. It is easy to understand that if the length of the foundation elements is about 12 m, then for the construction of several hundred meters of the finished foundation in a day, only a few skilled workers are enough. Another advantage is the configuration of the foundation elements, which can be combined in many ways to create a wide range of layouts of foundations using a set of foundation elements that can be delivered to the place of work for quick assembly.

Настоящее изобретение применимо, в частности, при сооружении фундаментов для большепролетных промышленных зданий и других зданий сходного типа, хотя те же элементы и методы могут использоваться и для любых других зданий, использующих ленточные фундаменты сходного типа.The present invention is applicable, in particular, in the construction of foundations for large-span industrial buildings and other buildings of a similar type, although the same elements and methods can be used for any other buildings using strip foundations of a similar type.

Описание чертежейDescription of drawings

Фиг. 1 - общий вид стандартного здания на ленточном фундаменте с продольной канавкой по настоящему изобретению;FIG. 1 is a perspective view of a standard building on a strip foundation with a longitudinal groove of the present invention;

фиг. 2 - вид готового фундамента в поперечном разрезе с указанием элемента фундамента, соединенного с ленточным фундаментом в качестве его составной части;FIG. 2 is a cross-sectional view of the finished foundation with an indication of the foundation element connected to the strip foundation as an integral part thereof;

фиг. 3 - общий вид элемента фундамента;FIG. 3 - general view of the foundation element;

фиг. 4 - общий вид участка строительной площадки, где сооружается фундамент, иллюстрирующий процесс строительства. На чертеже элемент фундамента, еще подвешенный на стреле крана и поддержиFIG. 4 is a general view of the site of the construction site where the foundation is being constructed, illustrating the construction process. In the drawing, the foundation element, still suspended on the boom of the crane and support

- 2 009928 ваемый приспособлениями для фиксации и выравнивания, размещается в траншее перед выравниванием, и производится заливка бетона для формирования плиты ленточного фундамента;- 2 009928 installed by devices for fixing and leveling, placed in a trench before leveling, and concrete is poured to form a slab of a strip foundation;

фиг. 5 - чертеж в поперечном разрезе, иллюстрирующий этап процесса строительства, когда элемент фундамента, временно подвешенный над траншеей, поддерживается горизонтальным стержнем и двумя вертикальными тягами перед подвешиванием на балку указанного приспособления;FIG. 5 is a cross-sectional drawing illustrating a stage of the construction process when the foundation element temporarily suspended above the trench is supported by a horizontal rod and two vertical rods before hanging on the beam of the specified device;

фиг. 6 - чертеж в поперечном разрезе, иллюстрирующий этап процесса строительства, когда элемент фундамента, временно подвешенный над траншеей, подвешивается к предварительно выровненной балке указанного приспособления в ожидании бетонирования ленточного фундамента;FIG. 6 is a cross-sectional drawing illustrating a stage of a construction process when a foundation element temporarily suspended above a trench is suspended from a pre-aligned beam of said fixture in anticipation of concreting the strip foundation;

фиг. 7 - общий вид приспособления для фиксации и выравнивания с указанием его составных частей.FIG. 7 is a General view of the device for fixing and aligning with an indication of its components.

Описание предпочтительного варианта осуществления изобретенияDescription of a preferred embodiment of the invention

На фиг. 1 показана стандартная конструкция, собранная из несущих стеновых панелей на ленточном фундаменте с продольной канавкой в соответствии с настоящим изобретением. Вообще говоря, такие фундаменты, служащие опорой и поддержкой для данного конкретного типа конструкции, имеют непрерывные продольные канавки по всей длине ленточного фундамента 4. Вертикальные несущие панели 1, на которые опирается конструкция крыши (а также, возможно, одно или более промежуточных перекрытий) представляют собой на самом деле тонкостенные широкие колонны на консольном основании, охватывающие внутреннюю часть здания; нижние концы этих колонн прочно закреплены в элементе 3 фундамента 4, а на верхние концы могут свободно опираться конструкционные элементы перекрытий.In FIG. 1 shows a standard construction assembled from load-bearing wall panels on a strip foundation with a longitudinal groove in accordance with the present invention. Generally speaking, such foundations, which serve as a support and support for this particular type of structure, have continuous longitudinal grooves along the entire length of the strip foundation 4. The vertical load-bearing panels 1 on which the roof structure rests (as well as, possibly, one or more intermediate floors) represent it is actually thin-walled wide columns on a cantilever base, covering the inside of the building; the lower ends of these columns are firmly fixed in the element 3 of the foundation 4, and the structural elements of the floors can freely rest on the upper ends.

Элементы 3 фундамента 4, как показано на фиг. 2, заменяющие традиционно отливаемую на месте продольную канавку, что в случае строительства традиционными способами было бы наиболее трудоемкой частью в процессе сооружения фундамента, доставляются на строительную площадку и быстро устанавливаются в подготовленных траншеях, как показано на фиг. 4, 5 и 6. В качестве первого шага ниже линии промерзания по периметру разметки здания выкапывается траншея 8 заранее заданной ширины и глубины в соответствии с состоянием местного грунта и условиями строительной площадки. Широкие и мелкие траншеи выкапываются с помощью подходящего экскаватора. На фиг. 2 показано поперечное сечение траншеи. В очень вязком грунте предпочтительна форма траншеи должна быть такой, как показано пунктирной линией. Чем меньше вязкость грунта, тем более наклонными должны быть стенки траншеи во избежание их осыпания. В большинстве случаев, за исключением очень сыпучего грунта, возможно добиться плотных грунтовых стенок возле дна траншеи, куда заливается бетон полосового фундамента, так, что никаких дополнительных поперечных форм не требуется, как наглядно видно на фиг. 2. Как только траншея выкопана, процесс сооружения фундамента при наличии соответствующего оборудования и квалифицированной рабочей силы, продвигается быстро и непрерывно с малым числом рабочих.Elements 3 of the foundation 4, as shown in FIG. 2, replacing a longitudinal groove traditionally cast in place, which in the case of construction by traditional methods would be the most time-consuming part in the process of building the foundation, delivered to the construction site and quickly installed in the prepared trenches, as shown in FIG. 4, 5 and 6. As a first step below the freezing line, a trench 8 of a predetermined width and depth is dug out along the perimeter marking of the building in accordance with the state of the local soil and the conditions of the construction site. Wide and shallow trenches are excavated using a suitable excavator. In FIG. 2 shows a cross section of a trench. In very viscous soils, the preferred shape of the trench should be as shown by the dashed line. The lower the viscosity of the soil, the more inclined the walls of the trench should be to prevent them from shedding. In most cases, with the exception of very loose soil, it is possible to achieve dense soil walls near the bottom of the trench, where the concrete of the strip foundation is poured, so that no additional transverse shapes are required, as can be clearly seen in FIG. 2. As soon as the trench is dug up, the process of building the foundation, with the appropriate equipment and skilled labor, progresses quickly and continuously with a small number of workers.

Как показано на фиг. 4, кран 10 соответствующей грузоподъемности движется вдоль траншеи; к крану непрерывно подаются элементы 3, доставляемые автотранспортом 11 на строительную площадку. Небольшая группа рабочих размещается возле траншеи, сопровождая кран, и они осуществляют крепление приспособлений 5 для фиксации и выравнивания к элементам фундамента. Таким образом, все еще подвешенный на стропах крана элемент 3 фундамента 4, поддерживаемый двумя приспособлениями 5, может таким образом крепиться на этих приспособлениях над траншеей, куда его помещает кран с помощью той же группы рабочих. После того, как элемент 3 размещен указанным образом, стропы крана отцепляют, и кран поднимает следующий элемент, продолжая работу. Элемент 3 фундамента 4, уже помещенный в траншею описанным выше образом, затем выравнивается другой группой рабочих с помощью приспособлений для фиксации и выравнивания. Затем бетономешалка заливает бетон в траншею под подвешенные элементы 3 фундамента 4, которые, как показано на фиг. 4, образуют основание ленточных фундаментов 4, прочно соединяющееся благодаря выступающей арматуре 3.3 элемента 3 фундамента 4, как показано на фиг. 2 и 3. Кратко описанный выше процесс продолжается дальше с продвижением вдоль траншеи; при этом на каждые двадцать метров длины готового фундамента (20 м - длина сборного элемента) уходит не более 15 мин. Организованная таким образом процедура при наличии квалифицированных рабочих, в отсутствие помех осуществляется равномерно со скоростью около 1 м/с, что составляет 60 м/ч.As shown in FIG. 4, the crane 10 of the corresponding carrying capacity moves along the trench; elements 3 are continuously fed to the crane, delivered by truck 11 to the construction site. A small group of workers is located near the trench, accompanying the crane, and they fasten devices 5 for fixing and leveling to the elements of the foundation. Thus, the foundation element 4, still suspended on the slings of the crane, supported by two devices 5, can thus be mounted on these devices above the trench, where the crane places it with the help of the same group of workers. After the element 3 is placed in this way, the slings of the crane are uncoupled, and the crane lifts the next element, continuing to work. The element 3 of the foundation 4, already placed in the trench in the manner described above, is then leveled by another group of workers using devices for fixing and leveling. Then, the concrete mixer pours concrete into the trench under the suspended elements 3 of the foundation 4, which, as shown in FIG. 4, form the base of the strip foundations 4, which is firmly connected due to the protruding reinforcement 3.3 of the element 3 of the foundation 4, as shown in FIG. 2 and 3. Briefly described above, the process continues further along the trench; at the same time, for every twenty meters of the length of the finished foundation (20 m is the length of the precast element) it takes no more than 15 minutes The procedure thus organized, in the presence of skilled workers, in the absence of interference, is carried out uniformly at a speed of about 1 m / s, which is 60 m / h.

Дальнейшая процедура будет описана более подробно с указанием необходимых деталей. Приспособление для фиксации и выравнивания 5, показанное на фиг. 7, состоит из главной балки 5.1, длина которой чуть больше ширины траншеи, с выдвижными концевыми элементами 5.2, опирающимися на подставки 6.5, покоящиеся на паре регулируемых опор 6, расположенных по обе стороны траншеи, как показано на фиг. 6. Балки 5.1, которые легко могут переносить два человека, перебрасываются через траншею, удерживая подвешенный элемент 3 фундамента 4 в траншее 8 над ее дном. Обе опоры 6 оснащены гидравлическими подъемниками 6.1, используемыми для движения вверх-вниз в вертикальной плоскости и расположенными внутри стального корпуса 6.2 с расширенным основанием 6.3, которое способно смещаться в двух взаимно перпендикулярных направлениях в горизонтальной плоскости. Расширенное основание 6.3 корпуса опирается на опорную пластину 6.4 с помощью комплекта роликов, движение которых ограничено в пределах площади опорной пластины (на чертежах не показано, поскольку это имеет лишь второстепенное значение для данного изобретения).The further procedure will be described in more detail with the necessary details. The fixation and alignment device 5 shown in FIG. 7, consists of a main beam 5.1, the length of which is slightly larger than the width of the trench, with retractable end elements 5.2, supported by supports 6.5, resting on a pair of adjustable supports 6 located on both sides of the trench, as shown in FIG. 6. Beams 5.1, which can easily be transported by two people, are thrown through the trench, holding the suspended element 3 of the foundation 4 in the trench 8 above its bottom. Both supports 6 are equipped with hydraulic lifts 6.1, used to move up and down in the vertical plane and located inside the steel casing 6.2 with an expanded base 6.3, which can move in two mutually perpendicular directions in the horizontal plane. The expanded base 6.3 of the casing is supported by a support plate 6.4 with a set of rollers whose movement is limited within the area of the support plate (not shown in the drawings, since this is only of secondary importance for the present invention).

- 3 009928- 3 009928

Элемент 3 фундамента 4 горизонтально подвешивается на двух стержнях 7 прямоугольного сечения, пропущенных через прямоугольные отверстия 3.2 в обеих тонких стенках с этого элемента 3. Прямоугольные отверстия 3.2 используются вместо круглых во избежание вращения стержня вокруг своих осей, что позволяет им принять вертикальное положение после крепления к сборному элементу 3.Foundation element 3 is horizontally suspended on two rods 7 of rectangular cross-section, passed through rectangular holes 3.2 in both thin walls from this element 3. Rectangular holes 3.2 are used instead of round ones to prevent the rod from rotating around its axes, which allows them to take a vertical position after attaching to prefabricated element 3.

Стержень 7 подвешивается на двух тягах 5.3, пропущенных вертикально через главную балку 5.1 симметрично относительно ее середины пролета. Длина обеих тяг 5.3 может регулироваться с целью достижения необходимого положения элемента 3 фундамента 4 по высоте над дном траншеи. Выбранная длина отрезка обеих вертикальных тяг 5.3 между верхней частью балки 5.1 и требуемой высотой горизонтального стержня 7 фиксируется двумя гайками 5.4. Будучи закрепленным таким образом на некоторой высоте гайками 5.4 одновременно на обоих приспособлениях, элемент фундамента висит без наклона в поперечном направлении и готов к выравниванию.The rod 7 is suspended on two rods 5.3, passed vertically through the main beam 5.1 symmetrically relative to its mid-span. The length of both rods 5.3 can be adjusted in order to achieve the required position of the element 3 of the foundation 4 in height above the bottom of the trench. The selected length of the segment of both vertical rods 5.3 between the upper part of the beam 5.1 and the required height of the horizontal rod 7 is fixed by two nuts 5.4. Being so fastened at a certain height with nuts 5.4 simultaneously on both devices, the foundation element hangs without tilting in the transverse direction and is ready for alignment.

Для подъемных работ и выравнивания в стенках каждого сборного элемента 3 имеется по две пары отверстий, расположенных примерно в четверти его длины от концов, в частности, пара внутренних 3.1 и пара прямоугольных наружных 3.2 отверстий, как показано на фиг. 3. Внутренняя пара отверстий 3.1 используется для крепления элемента фундамента к стропам крана. В ходе процедуры, показанной на фиг. 4, элемент 3 фундамента 4, закрепленный с помощью крюков во внутренних отверстиях 3.1, поднимается с грузового автомобиля краном, который поворачивается к траншее и продолжает удерживать подвешенный на стропах элемент 3 над траншеей, пока рабочие не пропустят стержень 7 через оба концевых отверстия 5.5 двух вертикальных тяг 5.3 и отверстия 3.2 в обеих стенках элемента 3. После того, как обе вертикальных тяги 5.3 примут вертикальное положение (благодаря тому, что стержень прямоугольного сечения препятствует их вращению, как указано выше), кран постепенно опускает элемент 3 фундамента 4 в траншею до тех пор, пока рабочие не смогут дотянуться руками до верхних частей вертикальных тяг. Затем балка 5.1 крепится к обоим вертикальным тягам 5.3 с помощью гаек 5.4 и укладывается на опоры 6. Теперь элемент 3 фундамента 4, подвешенный на двух приспособлениях, поддерживаемых с обеих сторон траншеи, может быть освобожден от строп крана. Для обеспечения доступа к приспособлениям используется доска 15, переброшенная через траншею.For lifting work and alignment, the walls of each prefabricated element 3 have two pairs of holes located about a quarter of its length from the ends, in particular, a pair of internal 3.1 and a pair of rectangular outer 3.2 holes, as shown in FIG. 3. The inner pair of holes 3.1 is used to fasten the foundation element to the crane slings. During the procedure shown in FIG. 4, element 3 of the foundation 4, fixed with hooks in the internal holes 3.1, rises from the truck with a crane that turns to the trench and continues to hold the element 3 suspended on the slings above the trench until the workers pass rod 7 through both end holes 5.5 of two vertical rods 5.3 and holes 3.2 in both walls of element 3. After both vertical rods 5.3 have a vertical position (due to the fact that the rod of rectangular cross section prevents their rotation, as indicated above), the crane gradually continuously lowers foundation element 3 to 4 into the trench until workers can not reach hands to the upper parts of the vertical rods. Then, the beam 5.1 is attached to both vertical rods 5.3 with the help of nuts 5.4 and laid on the supports 6. Now the element 3 of the foundation 4, suspended on two devices supported on both sides of the trench, can be released from the crane slings. To provide access to the devices used board 15, thrown through a trench.

Точное выравнивание осуществляется после того, как элементы 3 фундамента 4 будут временно и довольно грубо установлены. Перед выравниванием точное положение устанавливаемого в данный момент элемента 3 достигается его одновременным перемещением на всех четырех опорах 6 вдоль его продольной оси или перпендикулярно ей. Как указано выше, каждая опора позволяет осуществить такое движение за счет скольжения основания корпуса 6.3 по опорной пластине 6.4.Precise alignment is carried out after the elements 3 of the foundation 4 are temporarily and rather roughly installed. Before alignment, the exact position of the currently installed element 3 is achieved by its simultaneous movement on all four supports 6 along its longitudinal axis or perpendicular to it. As indicated above, each support allows this movement to occur due to the sliding of the base of the housing 6.3 along the base plate 6.4.

Выравнивание с целью добиться нулевого наклона элемента 3 фундамента 4 в продольном направлении осуществляется на опорах 6 с помощью пары гидравлических подъемников 6.1. Действуя одновременно, указанная пара подъемников 6.1 на каждом из концов элемента 3 может приподнять или опустить его в вертикальной плоскости. Если сборный элемент наклонен в поперечной плоскости, незначительная корректировка осуществляется одним нажатием на одну сторону стержня 7. Расположенное таким образом множество элементов 3 фундамента 4, подвешенных на стержнях 7, образуют точно расположенную продольную канавку всего фундамента. Положение элементов 3 можно регулировать вновь и вновь, пока не будет достигнута нужная точность. Указанная точность расположения продольной канавки имеет важное значение на более позднем этапе сооружения стен, когда производится монтаж и выравнивание панелей в вертикальном положении.Alignment in order to achieve a zero inclination of the element 3 of the foundation 4 in the longitudinal direction is carried out on the supports 6 using a pair of hydraulic lifts 6.1. Acting simultaneously, the indicated pair of lifts 6.1 at each of the ends of the element 3 can raise or lower it in a vertical plane. If the prefabricated element is inclined in the transverse plane, a slight correction is carried out with one click on one side of the rod 7. The multiple elements 3 of the foundation 4 located in this way, suspended on the rods 7, form a precisely positioned longitudinal groove of the entire foundation. The position of the elements 3 can be adjusted again and again until the desired accuracy is achieved. The specified accuracy of the location of the longitudinal grooves is important at a later stage of wall construction, when the panels are mounted and aligned in a vertical position.

Наконец, после того, как подвешенная над траншеей продольная канавка будет идеально выровнена, ее заливают свежей бетонной смесью для фиксации в грунте; фиксацию осуществляет группа рабочих, которые вслед за выравнивающей группой завершают работу, обрабатывая бетон шаблоном или вибробрусом. Бетонируемый на месте ленточный фундамент 4 заполняет промежуток между элементами 3 фундамента 4, подвешенными и надежно закрепленными на некотором расстоянии от дна траншеи, и дном траншеи 8. После того, как бетон ленточного фундамента 4 затвердел, приспособления 5 для фиксации и выравнивания элементов фундамента убирают.Finally, after the longitudinal groove suspended above the trench is perfectly aligned, it is poured with fresh concrete mixture for fixing in the ground; fixing is carried out by a group of workers who, following the leveling group, complete the work by treating concrete with a template or a vibratory beam. An in situ concrete foundation 4 fills the gap between the elements 3 of the foundation 4, suspended and securely fixed at a certain distance from the bottom of the trench, and the bottom of the trench 8. After the concrete of the strip foundation 4 has hardened, the devices 5 for fixing and leveling the foundation elements are removed.

Claims (3)

ФОРМУЛА ИЗОБРЕТЕНИЯCLAIM 1. Способ сооружения ленточного фундамента с продольной канавкой, предназначенной для установки несущих панелей стен, характеризующийся тем, что указанную продольную канавку формируют из множества элементов (3) фундамента (4), имеющих продольные пазы и выступающую со стороны их основания арматуру (3.3), каждый из которых временно подвешивают над траншеей (8) по периметру разметки здания на двух приспособлениях (5) для фиксации и выравнивания элемента фундамента, расположение этих элементов (3) регулируют и окончательно выравнивают с помощью указанных приспособлений так, что пазы этих элементов образуют продольную канавку фундамента (4); а затем промежуток между собранными таким образом элементами (3) и дном траншеи (8) и расположенную в этом промежутке арматуру (3.3) элемента (3) заливают свежеприготовленной бетонной смесью для образования ленточного фундамента (4).1. A method of constructing a strip footing with a longitudinal groove designed to install bearing wall panels, characterized in that said longitudinal groove is formed from a plurality of foundation elements (3) (4) having longitudinal grooves and a reinforcement (3.3) protruding from their base, each of which is temporarily suspended above the trench (8) around the perimeter of the building marking on two devices (5) for fixing and leveling the foundation element, the arrangement of these elements (3) is adjusted and finally leveled with the MC adaptive devices so that the grooves of these elements form a longitudinal groove of the foundation (4); and then the gap between the elements (3) thus assembled and the bottom of the trench (8) and the reinforcement located in this gap (3.3) of the element (3) is poured with freshly prepared concrete mix to form a strip foundation (4). 2. Элемент фундамента, составляющий основную часть ленточного фундамента с продольной ка2. The element of the foundation, constituting the main part of the strip foundation with a longitudinal frame. - 4 009928 навкой, характеризующийся тем, что он имеет продольный паз, расположенный между его боковыми стенками и основанием, поперечно расположенные в концевых частях его стенок две пары внутренних отверстий (3.1) и две пары наружных прямоугольных отверстий (3.2), служащих соответственно для отсоединения от строп крана и присоединения к приспособлениям (5) для фиксации и выравнивания элемента фундамента, и арматуру (3.3), выступающую со стороны основания элемента (3) фундамента (4).- 4 009928 navkah, characterized by the fact that it has a longitudinal groove located between its side walls and base, transversely located in the end parts of its walls two pairs of internal holes (3.1) and two pairs of external rectangular holes (3.2), which serve respectively for detaching from the crane sling and attachment to devices (5) for fixing and leveling the foundation element, and reinforcement (3.3), protruding from the base of the element (3) of the foundation (4). 3. Приспособление для фиксации и выравнивания элемента фундамента, характеризующееся тем, что оно включает размещаемую над траншеей (8) балку (5.1) с выдвижными концевыми элементами (5.2) и двумя тягами (5.3), вертикально устанавливаемыми в отверстиях балки (5.1) симметрично относительно середины её пролета, две регулируемые опоры (6), которые содержат гидравлические подъемники (6.1) с подставками (6.5) для размещения концевых элементов (5.2) балки (5.1) и с расширенным основанием (6.3), смонтированным на опорной пластине (6.4) с возможностью перемещения в горизонтальной плоскости в двух перпендикулярных направлениях, и два прямоугольных стержня (7), предназначенных для установки в наружных отверстиях (3.2) элемента (3) фундамента (4), при этом нижние концы обеих тяг (5.3) имеют прямоугольные отверстия (5.5) для размещения в них концов стержней (7), а верхние резьбу с гайками (5.4) для регулирования положения концов стержней (7) по высоте с обеспечением за счет этого и за счет регулирования положения опор (6) требуемого расположения элемента (3) фундамента.3. A device for fixing and leveling the foundation element, characterized in that it includes a beam (5.1) placed above the trench (8) with retractable end elements (5.2) and two rods (5.3) vertically installed in the holes of the beam (5.1) symmetrically with respect to the middle of its span, two adjustable supports (6), which contain hydraulic lifts (6.1) with supports (6.5) to accommodate the end elements (5.2) of the beam (5.1) and with an extended base (6.3) mounted on the support plate (6.4) with possibility of moving to horiz an axial plane in two perpendicular directions, and two rectangular rods (7) intended to be installed in the external openings (3.2) of the element (3) of the foundation (4), while the lower ends of both rods (5.3) have rectangular openings (5.5) for placement the ends of the rods (7) are in them, and the upper threads with nuts (5.4) for adjusting the position of the ends of the rods (7) in height, thereby ensuring and by adjusting the position of the supports (6) of the desired location of the element (3) of the foundation.
EA200601407A 2004-02-12 2004-02-12 Method of constructing strip foundations with longitudinal groove, a foundation element and holding/leveling device provided therefor EA009928B1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/HR2004/000003 WO2005078198A1 (en) 2004-02-12 2004-02-12 Method of constructing strip foundations with longitudinal socket

Publications (2)

Publication Number Publication Date
EA200601407A1 EA200601407A1 (en) 2006-12-29
EA009928B1 true EA009928B1 (en) 2008-04-28

Family

ID=34856824

Family Applications (1)

Application Number Title Priority Date Filing Date
EA200601407A EA009928B1 (en) 2004-02-12 2004-02-12 Method of constructing strip foundations with longitudinal groove, a foundation element and holding/leveling device provided therefor

Country Status (7)

Country Link
US (1) US20080006003A1 (en)
EP (1) EP1721048A1 (en)
CN (1) CN100529274C (en)
EA (1) EA009928B1 (en)
HR (1) HRP20060296A2 (en)
TW (1) TW200532076A (en)
WO (1) WO2005078198A1 (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101550764B (en) * 2008-04-06 2012-12-05 孙长顺 Concrete pouring machine
CN101818501B (en) * 2009-07-29 2011-11-16 兰州理工大学 Construction method of reinforced concrete foundation on top of large-scale trenched pipe culvert
US8925282B2 (en) 2011-07-08 2015-01-06 Contech Engineered Solutions LLC Foundation system for bridges and other structures
KR20140047118A (en) 2011-07-08 2014-04-21 콘텍 엔지니어드 솔루션스 엘엘씨 Foundation system for bridges
MX358690B (en) 2011-09-16 2018-08-31 Goss Construction Inc Concrete forming systems and methods.
ITPI20120001A1 (en) * 2012-01-04 2013-07-05 Alessandro Bertocchi METHOD FOR THE PRODUCTION OF PUREE, OR JUICE, FROM FOOD PRODUCTS WITH HIGH CAPACITY AND MACHINE THAT ACTIVES THIS METHOD
AU2013359540B2 (en) * 2012-12-13 2017-04-20 Contech Engineered Solutions LLC Foundation system for bridges and other structures
US9695558B2 (en) 2012-12-13 2017-07-04 Contech Engineered Solutions LLC Foundation system for bridges and other structures
US11174614B2 (en) 2017-08-14 2021-11-16 Contech Engineered Solutions LLC Metal foundation system for culverts, buried bridges and other structures
CN109505309B (en) * 2019-01-07 2023-09-26 浙江大学城市学院 Pipe gallery segment displacement system and pipe gallery installation method using same

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH032422A (en) * 1989-05-29 1991-01-08 San Aroo Plan:Kk Construction of foundation sill
FR2659592A1 (en) * 1990-03-19 1991-09-20 Hourdeaux Jacques Modular mould for tank
GB2254099A (en) * 1991-02-12 1992-09-30 Robert Michael Sloma Formwork apparatus.
FR2777923A1 (en) * 1998-04-22 1999-10-29 Philippe Blanc Foundation module that is prefabricated
US20020017068A1 (en) * 1996-07-17 2002-02-14 Mose Monachino Foundation element, methods for the construction of prefabricated structures including these elements, particularly prefabricated tunnels, and prefabricated structures made by these methods

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3228679A (en) * 1963-08-08 1966-01-11 Kansas Sheet Metal Co Inc Apparatus for supporting conduits in trenches
US3207465A (en) * 1963-09-13 1965-09-21 Lawrence E Papin Foundation form apparatus

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH032422A (en) * 1989-05-29 1991-01-08 San Aroo Plan:Kk Construction of foundation sill
FR2659592A1 (en) * 1990-03-19 1991-09-20 Hourdeaux Jacques Modular mould for tank
GB2254099A (en) * 1991-02-12 1992-09-30 Robert Michael Sloma Formwork apparatus.
US20020017068A1 (en) * 1996-07-17 2002-02-14 Mose Monachino Foundation element, methods for the construction of prefabricated structures including these elements, particularly prefabricated tunnels, and prefabricated structures made by these methods
FR2777923A1 (en) * 1998-04-22 1999-10-29 Philippe Blanc Foundation module that is prefabricated

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
PATENT ABSTRACTS OF JAPAN vol. 0151, no. 05 (M-1092), 13 March 1991 (1991-03-13) & JP 3 002422 A (SAN AROO PLAN:KK), 8 January 1991 (1991-01-08) abstract; figures 12, 13 *

Also Published As

Publication number Publication date
EA200601407A1 (en) 2006-12-29
WO2005078198A1 (en) 2005-08-25
TW200532076A (en) 2005-10-01
HRP20060296A2 (en) 2006-10-31
US20080006003A1 (en) 2008-01-10
CN100529274C (en) 2009-08-19
CN1914381A (en) 2007-02-14
EP1721048A1 (en) 2006-11-15

Similar Documents

Publication Publication Date Title
US10094101B1 (en) Precast concrete system with rapid assembly formwork
US6223480B1 (en) Pre-cast concrete panels for construction of a building
GB1451611A (en) Building construction
US20140223851A1 (en) Prefabricated reinforced concrete wall panel and installation method
TW200532076A (en) The quick method of constructing strip foundations with longitudinal socket
RU2552506C1 (en) Method for construction of monolithic structures of buildings and non-removable universal modular formwork system
RU2220258C1 (en) Process of erection of multilevel underground structure ( variants )
CN109267578B (en) Inclined plane plain concrete structure and construction method thereof
CN116378428A (en) Construction method of longitudinal rib superimposed shear wall structure wall
JP7189001B2 (en) How to construct the foundation of a building
JP2022161709A (en) Precast concrete foundation material for forming mat foundation, forming device for forming precast concrete foundation material, forming method for precast concrete foundation material using forming device, and forming method for mat foundation using precast concrete foundation material
CN210857277U (en) Assembled underground structure
US3552080A (en) Method for erecting multistory buildings
CN113235645A (en) Tower crane foundation reserved joint bar assembly type forming die construction method
WO2017187452A1 (en) System for connecting a precast column to a precast beam and method therefor
US7073300B1 (en) Reinforced concrete part for producing foundations of buildings
RU221195U1 (en) Glass-type precast reinforced concrete column sill
JPH10219708A (en) Precast concrete block for continuous footing and continuous footing method by use thereof
RU68039U1 (en) RECONSTRUCTION METHOD FOR BRICK BUILDINGS
CN217267635U (en) Backfill regional well step system
RU190916U1 (en) UNDERGROUND EQUIPMENT
SU1682472A1 (en) Strip foundation
RU2571770C2 (en) Tiered method of erection of underground facilities
EP1233123A2 (en) A bricklaying method and an arrangement for the implementation thereof
RU2617813C2 (en) The method of erection of prefabricated multi-storey reinforced concrete frame of a building

Legal Events

Date Code Title Description
MM4A Lapse of a eurasian patent due to non-payment of renewal fees within the time limit in the following designated state(s)

Designated state(s): KG MD TJ TM

MM4A Lapse of a eurasian patent due to non-payment of renewal fees within the time limit in the following designated state(s)

Designated state(s): AM AZ BY KZ RU