SU927938A1 - Building construction method - Google Patents

Building construction method Download PDF

Info

Publication number
SU927938A1
SU927938A1 SU802983086A SU2983086A SU927938A1 SU 927938 A1 SU927938 A1 SU 927938A1 SU 802983086 A SU802983086 A SU 802983086A SU 2983086 A SU2983086 A SU 2983086A SU 927938 A1 SU927938 A1 SU 927938A1
Authority
SU
USSR - Soviet Union
Prior art keywords
walls
formwork
floor
concrete
height
Prior art date
Application number
SU802983086A
Other languages
Russian (ru)
Inventor
Вальтер Ашотович Атанесян
Original Assignee
Ереванский политехнический институт им.К.Маркса
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ереванский политехнический институт им.К.Маркса filed Critical Ереванский политехнический институт им.К.Маркса
Priority to SU802983086A priority Critical patent/SU927938A1/en
Application granted granted Critical
Publication of SU927938A1 publication Critical patent/SU927938A1/en

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

1one

Изобретение относитс  к строитель ству и предназначено дл  воздействи  зданий с монолитными стенами и сборными перекрыти ми.The invention relates to construction and is intended to affect buildings with monolithic walls and prefabricated floors.

Известен способ возведени  зданий с использованием скольз щей опалубки , предусматривающий возведение.монолитных стен в скольз щей опалубке и последующий монтаж с замоноличиванием сборных перекрытий. С целью создани  опорных участков дл  перекрыти  в 1стенах оставл ют гнезда при их формировании. Плиты перекрытий устанавливают на временные монтажные и замоноличивают. Ь результате получают прерывистое опирание перекрытий на стены и неравнопрочные узлы сопр жени  t1.There is a known method of erecting buildings using sliding formwork, which involves the erection of monolithic walls in sliding formwork and the subsequent installation with monolithic prefabricated ceilings. In order to create support sites for the overlap in 1 wall, nests are left when they are formed. Floor slabs are installed on temporary mounting and monolithic. As a result, intermittent overlap of the ceilings on the walls and unequal joints t1 is obtained.

Недостатком указанного способа  вл етс  то, что- монтаж перекрытий в большинстве случаев становитс  возможным только после окончани бетонировани  стен на всю высоту и демонтажа -рабочего настила. Это значительно усложн ет устройство перекрытий и удлин ет сроки строительства. Монтаж сборных перекрытий в процессе подъема скольз щей опалубки с некоторым отставанием от возведени , стен св зан с р дом затруднений. Кроме того, требуютс  дополнительные работы, св занные с монтажом и демонтажом монтажных столиков и созданием гнезд .The disadvantage of this method is that the installation of floors in most cases becomes possible only after the completion of concreting of walls to the full height and dismantling of the working floor. This greatly complicates the construction of floors and lengthens the construction time. The assembly of prefabricated floors in the process of lifting sliding formwork with a certain lag behind the erection of the walls is associated with some difficulties. In addition, additional work is required related to the assembly and disassembly of the installation tables and the creation of sockets.

fOfO

Наиболее близким к изобретению, по технической сущности и достигаемому результату  вл етс  способ возведени  зданий, включающий монтаж щитовой опалубки, бетонирование стен редством опалубки и укладку перекрыти  23. The closest to the invention, according to its technical essence and the achieved result, is the method of erection of buildings, including the installation of panel formwork, concreting walls with formwork and laying the ceiling 23.

Недостатком указанного способа  вл етс  то, что не обеспечиваетс  необходима  монолитность и равнопрочJO ность стыковых соединений.перекрыти  с монолитной стеной из-за образовани  технологических швов, тогда как эти участки наиболее нагруженные. Возникают трудности в процессе непрерывности армировани  стен. Кроме того, бетон укладывают в опалубку высотой в этаж и при сбрасывании наблюдаетс  процесс расслоени .The disadvantage of this method is that the solidity and equal strength of the butt joints are not required. The ceiling is blocked with a monolithic wall due to the formation of technological joints, while these sections are the most loaded. Difficulties arise in the continuity of the reinforcement of the walls. In addition, the concrete is laid in a formwork with a height to the floor and when it is dropped, the process of delamination is observed.

Цель изобретени  - повышение качества возводимых сооружений за счет обеспечени  равнопрочности узлов сопр жени  стен с перекрытием и предотвращени  расслоени  бетонной смеси . The purpose of the invention is to improve the quality of the erected structures by ensuring equal strength of the wall-joints with overlapping and preventing the separation of the concrete mix.

Эта цель достигаетс  тем, что согласно способу возведени  Зданий,включающему монтаж щитовой опалубки, бетонирование стен посредством опалубки и укладку перекрыти , стены бетониру .ют на неполную высоту этажа, после .; чего укладывают перекрытие с зазором от с.тен и с опиранием их на щиты опалубки, а затем бетонируют стены на оставшуюс  высоту с одновременным заполнением зазоров между стенаи образованием ма ми и перекрытием ков. На чертеже изображена опалубка дл  25 ва. возведени  зданий предлагаемым способом . Способ осуществл етс  следующим образом. Сначала устанавливают опалубки, наклон ют верхние Г-образные части 1 одного из их щитов (показано пунктиром на чертеже) относительно нижни частей 2 вокруг оси 3 посредством винтовых подкосов , в полученную воронку заливают бетонную смесь и бетонируют стены на неполную высоту например на высоту, равную высоте нижней половины этажа. Далее привод т верхние части 1 щитов в исходное положение, их фиксируют с помощью крепежных элементов 5 и ст жек 6, ук ладывают сборные междуэтажные перекрыти  7 на некотором рассто нии от стены, т.е. с зазором (на сравнитель но мало нагруженной зоне) с опиранием на опалубочные щиты 1 и одновременно бетонируют стену на оставшуюс  высоту (на верхнюю половину этажа ) , заполнЯют зазоры между стеной и покрытием с образованием ма ков. После приобретени  бетоном необходимой прочности производ т распалубку щитов опалубки, дл  чего удал ют крепежные элементы 5 и ст жки 6, подThis goal is achieved by the fact that according to the method of erection of buildings, including the installation of shield formwork, concreting walls by means of formwork and laying the floor, the walls are concreted to an incomplete floor height, after.; This is done by laying the ceiling with a gap from the sten and leaning them on the formwork panels, and then concreting the walls for the remaining height while simultaneously filling the gaps between the walls to form the masses and the floor slabs. The drawing shows the formwork for 25 VA. construction of buildings by the proposed method. The method is carried out as follows. First, formworks are installed, the upper L-shaped parts 1 of one of their shields (shown by a dotted line in the drawing) are tilted relative to the lower parts 2 around axis 3 by means of screw struts, the concrete mix is poured into the resulting funnel and the walls are concrete cast at an incomplete height, for example, a height equal to height of the lower half of the floor. Next, the upper parts 1 of the shields are brought to their initial position, they are fixed with the help of fastening elements 5 and sht 6, indicate prefabricated intermediate floors 7 at some distance from the wall, i.e. with a gap (on a comparatively little loaded area) with a support on the formwork boards 1 and at the same time concrete the wall to the remaining height (on the upper half of the floor), fill in the gaps between the wall and the floor to form macuses. After the concrete has acquired the required strength, the formwork panels are dismantled, for which purpose the fastening elements 5 and the strips 6 are removed, under

нимают домкраты 8 и винтовые стабилизирующие устройства 9, при необходимости вращают также винты подкосов k. Щиты под собственной т жестью отрываютс , опира сь на колесики 10 и выкатываютс  из отформованной  чейки.Дл  увеличени  оборачиваемости опалубок и дл  поддержани  перекрытий используют временные стойки 11. Сборные перекрыти  снабжены арматурными выпусками , которые обеспечивают св зь плит перекрыти  между собой и со стеной. Так как бетонную смесь укладывают на неполную высоту стен и одновременноjacks 8 and screw stabilizing devices 9 are attached, if necessary, also rotate brackets k. The panels under their own weight are detached, resting on the wheels 10 and rolling out of the formed cell. To increase the turnover of the formwork and to maintain the overlap, temporary racks 11 are used. The prefabricated overlaps are provided with reinforcements connecting the overlap between themselves and the wall. Since the concrete mixture is placed on the incomplete height of the walls and at the same time

Claims (2)

с  однородность бетона стен и равнопрочность узлов сопр жени . Кроме того, в св зи с тем, что перекрыти  укладывают на опалубку сраву после бетонировани  половины стен, не до кида сь набора прочности стенами и распалубки (как в известных способах), значительно растет темп строительс-тis бетонируют стены и части перекрыти  (т.е. заполн ют зазоры) обеспечиваетЛегко обеспечиваетс  непрерывность армировани  стен. Формула изобретени  Способ возведени  зданий, включаюций монтаж щитовой опалубки, бетонирование стей посредством опалубки и укладку перекрыти , отличающийс  тем, что, с целью повышени  качества возводимых сооружений за счет обеспечени  равнопрочности узлов сопр жени  стен с перекрытием и предотвращени  расслоени  бетонной смеси, стены бетонируют на не полную высоту этажа, после чего укладывают перекрытие с зазором от стен и с опиранием их на щиты опалубки , а затем бетонируют стены на оставшуюс  высоту с одновременным заполнением зазоров между стенами и рекрытием и образованием ма ков. Источники информации, прин тые во внимание при экспертизе 1.Индустриальное домостроение из монолитного бетона. М., Стройиздат , 1976, с. 28-35. with the homogeneity of concrete walls and equal strength of the junctions. In addition, due to the fact that the slabs are laid on the formwork after half of the walls have been concreted, the strength and walls of the blocks (t. e. fill the gaps) ensures the continuity of the reinforcement of the walls. Claims The method of erection of buildings, including the installation of panel formwork, concreting the steels by means of formwork and laying the floor, characterized in that, in order to improve the quality of the erected structures by providing equal strength of the wall joints with the floor and prevent stratification of the concrete mix, the walls are concrete the full height of the floor, after which the floor is laid with a gap from the walls and supported by them on the formwork panels, and then the walls are concreted to the remaining height with simultaneous filling Zorov between the walls and the overlap of and formation of beacons. Sources of information taken into account in the examination 1. Industrial housing construction of solid concrete. M., stroiizdat, 1976, p. 28-35. 2.Авторское свидетельство СССР № 773229, кл. Е Qi G 11/00, 19792. USSR author's certificate number 773229, cl. E Qi G 11/00, 1979 1-ft-tr1-ft-tr
SU802983086A 1980-09-19 1980-09-19 Building construction method SU927938A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU802983086A SU927938A1 (en) 1980-09-19 1980-09-19 Building construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU802983086A SU927938A1 (en) 1980-09-19 1980-09-19 Building construction method

Publications (1)

Publication Number Publication Date
SU927938A1 true SU927938A1 (en) 1982-05-15

Family

ID=20918140

Family Applications (1)

Application Number Title Priority Date Filing Date
SU802983086A SU927938A1 (en) 1980-09-19 1980-09-19 Building construction method

Country Status (1)

Country Link
SU (1) SU927938A1 (en)

Similar Documents

Publication Publication Date Title
AP1026A (en) Precast concrete panels for construction of a building.
US2043697A (en) Building structure
SU927938A1 (en) Building construction method
EP0065793B1 (en) Reinforcement structure for reinforced-concrete buildings
EA009928B1 (en) Method of constructing strip foundations with longitudinal groove, a foundation element and holding/leveling device provided therefor
AU2019203603B1 (en) Stair assembly and method
SU737600A1 (en) Method of making a floor in sliding form
RU2353735C2 (en) Method for erection of solid-cast frame buildings
SU1004576A1 (en) Method of erecting a building
RU2087650C1 (en) House-building combine
EP0054524A2 (en) A casting form system consisting of modular members for the construction of buildings, storey by storey
Tarczewski Construction Work in the Mosque Building (Throne Hall) in Seasons 2015–2017
SU977644A1 (en) Method for erecting cast-in-place buildings
RU2308587C1 (en) Method for timber floor structure reconstruction
SU958642A1 (en) Flue erecting method
RU2325487C1 (en) Method of constructing framework without longitudinal girder
RU2065907C1 (en) Framework and method for erection of building
SU903532A1 (en) Method of stagewise construction of buildings of solid ferroconcrete
SU1008391A1 (en) Method for erecting building with cantilevered floors
RU2694662C1 (en) Erection method of lined building
RU2696737C1 (en) Method of facade alignment in monolithic housing construction
RU3952U1 (en) SLIDING FORMWORK FOR ESTABLISHING WALLS AND FLOORS
SU1131984A1 (en) Prefabricated multivoid floor panel
SU1726702A1 (en) Method of construction skeleton of a building
SU761684A1 (en) Method of erecting monolythic ferroconcrete structure in slide form