SU1043285A2 - Building construction method - Google Patents

Building construction method Download PDF

Info

Publication number
SU1043285A2
SU1043285A2 SU792782246A SU2782246A SU1043285A2 SU 1043285 A2 SU1043285 A2 SU 1043285A2 SU 792782246 A SU792782246 A SU 792782246A SU 2782246 A SU2782246 A SU 2782246A SU 1043285 A2 SU1043285 A2 SU 1043285A2
Authority
SU
USSR - Soviet Union
Prior art keywords
floors
floor
building
walls
odd
Prior art date
Application number
SU792782246A
Other languages
Russian (ru)
Inventor
Иван Петрович Коскин
Original Assignee
Производственное Управление "Приморкрайсельстрой"
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Производственное Управление "Приморкрайсельстрой" filed Critical Производственное Управление "Приморкрайсельстрой"
Priority to SU792782246A priority Critical patent/SU1043285A2/en
Application granted granted Critical
Publication of SU1043285A2 publication Critical patent/SU1043285A2/en

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

Изобретение относитс  к строительству , а именно к возведению зда ний методом подъема этажей. По основному авт.св. If 85306 из вестен способ возведени  здани , включающий устройство фундамента, о новани  под полы первого этажа, изготовление на нем пакета плит перекрытий , наружных и внутренних стен, образующих развертки всех этажей, шарнирное соединение наружных стен с вышележащими и нижележащими перекрыти ми (или с фундаментом наружны стен первого этажа), шарнирное соединение внутренних стен каждого эта с вышележащими перекрыти ми, герметизацию стыков между наружными стенами и перекрыти ми (или с фундамен том) и последующий поэтажный, начина  с верхнего этажа, подъем здани  путем нагнетани  воздуха в полос ти между перекрыти ми и наружными стенами. Каждую наружную стену каждого этажа изготавливают из двух горизонтальных панелей одинаковой высоты, равной половине высоты этажа , панели между собой соедин ют шарнирно и стыки между панел ми герметизируют . I Однако способ применим дл  здани без оконных проемов или с проемами, расположенными в верхних или нижних половинах стен этажей . Кроме того, горизонтальные ишы по серединам стен этажей ухудшают архитектурные и конструктивные качества здани , увеличивают его материалоемкость , снижают производительность труда при возведении. Целью изобретени   вл етс  умень шение материалоемкости здани , увел чение производительности труда при его возведении и повышение качества здани . Эта .цель достигаетс  тем, что согласно способу элементы наружных стен изготавливают высотой на этаж, а их шарнирные соединени  располагают на уровн х перекрытий нечетных этажей,при этом подъем развертки здан производ т циклично по два этажа за каждый цикл путем подвешивани  перекрытий нечетных этажей к перекр ти м четных этажей с помощью гибких т г длиной, равной высоте этажа На фиг.1 изображено изготовление всех элементов здани  на нулевой отметке (первый этап); на фиг.2 подъем двух верхних этажей; на фиг.З подн ты два верхних , начат подъем двух нижележащих; на фиг. подн ты все этажи (условно показаны первые два этажа). - Возведение здани  осуществл ют в следующей последовательности. По.сле отрывки траншей под фундаменты 1 наружных и внутренних стен производ т бетонирование фундаментов и оснований 2 под полы первого этат жа, уплотн   уложенный бетон и заглажр ва  его поверхность с помощью механизма 3. При этом в фундаменты 1 наружных стен по периметру здани  закладывают анкера дл  креплени  шарниров 4, соедин ющих элементы 5 наружных стен первого этажа с фундаментами 1 . Далее на затвердевшее основание устанавливают бортоснастки 6-9 дл  бетонировани  наружных и внутренних стен первого этажа,арматуру наружных и внутренних стен и производ т их бетонирование, закладыва  анкера шарниров 10 ; и 11, соедин ющих соответственно элементы 5 наружных стен первого и второго этажей и внутренние стены с перекрытием первого этажа.После набора бетоном необходимой прочности бортоснастки 8 и 9 извлекают, перекрыва  образовавшиес  зазоры инвентарными щитами, например из тонколистной стали, а 6 и 7 поднимают и закрепл ют дл  бетонировани  перекрыти  12 первого этажа и элементов 5 наружых стен второго этажа. После армировани  и бетонировани  перекрыти  первого этажа и стен второго этажа все дальнейшие операции вплоть до бетонировани  перекрыти  13 самого верхнего этажа повтор ют аналогично предыдущим. Подъем плит перекрытий 12 и нечетных этажей осуществл ют с помощью гибких т г 15 и 16 длиной, равной высоте этажа, прикрепленных k перекрыти м 1 и 13 четных этажей . При этом т ги 15, прикрепленные к стеновым элементам 5 четных этажей несколько выше шарниров 10, соедин ющих стеновые элементы между собой, и к перекрыти м четных этажей и переброшенные через блоки 18, прикрепленные к перекрыти м нечетных этажей , одновременно служат дл  принудительной установки наружных стеновы « панелей поворачивающихс  вокруг шарниров i в вертикальное положение..The invention relates to the construction, in particular to the erection of buildings by the method of lifting floors. According to the main auth. If 85306 of the well-known method of erecting a building, which includes the construction of the foundation, the construction of a package of floor slabs, exterior and interior walls forming sweepings of all floors, the hinged connection of exterior walls with overlying and underlying floors (or the foundation external walls of the first floor), a hinged connection of the internal walls of each one with overlying floors, sealing of joints between external walls and floors (or with the foundation) and the subsequent floor by floor, starting from the top its floor rise building by pumping air into five bands overlap between the E and the outer walls. Each outer wall of each floor is made of two horizontal panels of the same height, equal to half the height of the floor, the panels are connected to each other by a hinge, and the joints between the panels are sealed. However, the method is applicable to a building without window openings or with openings located in the upper or lower half of the walls of the floors. In addition, horizontal isha along the middle of the walls of the floors worsens the architectural and constructive qualities of the building, increases its material consumption, and reduces labor productivity during construction. The aim of the invention is to reduce the material consumption of the building, increase labor productivity in its construction and improve the quality of the building. This goal is achieved by the fact that, according to the method, the exterior wall elements are made to a height on the floor, and their articulated joints are located on the floor levels of the odd floors, while the elevation of the building sweeps is performed cyclically over two floors in each cycle by hanging the floors of the odd floors to the intersections TI m even floors using flexible t g length equal to the height of the floor In figure 1 shows the manufacture of all elements of the building at the zero mark (first stage); in Fig.2 the rise of the two upper floors; in FIG. 3, the two upper ones are raised, the two lower ones have begun to rise; in fig. lift all floors (the first two floors are conventionally shown). - The construction of the building is carried out in the following sequence. After the fragments of the trenches for the foundations 1 of the outer and inner walls, the foundations and foundations of the foundations and the foundations 2 are made under the floors of the first floor, the concrete is compacted and the surface is smoothed using the mechanism 3. At the same time, anchors are laid in the foundations 1 of the outer walls for fastening the hinges 4 connecting the elements 5 of the outer walls of the first floor with the foundations 1. Next, the rigging 6–9 for concreting the exterior and interior walls of the first floor, the reinforcement of the exterior and interior walls are installed on the hardened base, and the concreting of the exterior and interior walls is performed, laying the anchors of the hinges 10; and 11, connecting, respectively, elements 5 of the outer walls of the first and second floors and the inner walls with the first floor overlapping. After the concrete has set the required strength, the board equipment 8 and 9 are removed, blocking the gaps created with inventory shields, for example from sheet steel, and 6 and 7 are lifted and fixed for concreting the ceiling 12 of the first floor and the elements 5 of the outer walls of the second floor. After reinforcing and concreting the overlap of the first floor and the walls of the second floor, all further operations, up to concreting overlapping of the 13th uppermost floor, are repeated as before. The lifting of the floor slabs of 12 and odd floors is carried out with the help of flexible bars of 15 and 16 lengths equal to the height of the floor, attached k overlaps of 1 and 13 even floors. At the same time, the rods 15 attached to the wall elements of 5 even floors are slightly higher than the hinges 10 connecting the wall elements to each other, and to the overlaps of even floors and transferred through the blocks 18 attached to the overlaps of odd floors. wall panels turning around hinges i in a vertical position ..

Claims (1)

СПОСОБ ВОЗВЕДЕНИЯ ЗДАНИЯ / по авт.св. № 853064, о т л и ч а юц.и й с я тем, что , с целью умень шения материалоемкости здания, увеличения производительности труда при его возведении и повышения качества, элементы наружных стен изготавливают высотой на этаж, а их шарнирные соединения располагают на уровнях перекрытий нечетных этажей, при этом подъем развертки здания производят циклично по два этажа за каждый цикл путем подвешивания перекрытий нечетных этажей к перекрытиям четных этажей с помощью гибких тяг длиной, равной высоте этажа.METHOD OF BUILDING A BUILDING / by auth. No. 853064, due to the fact that, in order to reduce the material consumption of the building, increase labor productivity during its construction and improve quality, the elements of the outer walls are made up to the floor, and their joints are placed on the levels of the floors of odd floors, while the building sweep is raised cyclically two floors per cycle by suspending the floors of odd floors to the floors of even floors using flexible rods with a length equal to the floor height. SU 104.3285SU 104.3285 1 1043285 21 1043285 2
SU792782246A 1979-06-25 1979-06-25 Building construction method SU1043285A2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU792782246A SU1043285A2 (en) 1979-06-25 1979-06-25 Building construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU792782246A SU1043285A2 (en) 1979-06-25 1979-06-25 Building construction method

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
SU853064 Addition

Publications (1)

Publication Number Publication Date
SU1043285A2 true SU1043285A2 (en) 1983-09-23

Family

ID=20834682

Family Applications (1)

Application Number Title Priority Date Filing Date
SU792782246A SU1043285A2 (en) 1979-06-25 1979-06-25 Building construction method

Country Status (1)

Country Link
SU (1) SU1043285A2 (en)

Similar Documents

Publication Publication Date Title
US2043697A (en) Building structure
EA000593B1 (en) Pre-cast concrete panels for construction of a building
US3956859A (en) Foundation of a heated building without a cellar
SU1043285A2 (en) Building construction method
RU2107789C1 (en) Shuttering for walls
US4029286A (en) Apparatus for the construction of ceiling in multi-story concrete buildings
RU2678750C1 (en) Buildings and structures with bearing monolithic reinforced concrete structures construction method using the reinforced concrete wall panels
GB2320737A (en) Semi precast method of construction of multi-storey buildings
WO1986000043A1 (en) Building system and portable masonry plant suitable therefor
SU853064A1 (en) Method of erecting buildings
RU2387763C1 (en) Method for erection of monolithic walls of residential buildings, housings and structures in combined curb
RU2192522C2 (en) Process of manufacture of monolithic floor panels and gear for its realization
SU910979A1 (en) Pneumatic inflatable form for erecting monolithic ferroconcrete structures
EP1103663B1 (en) Pile wall capping
JPH06200533A (en) Bent pc foundation form and foundation construction method using it
RU2136827C1 (en) Method for erection of three-span structure with pneumatic shuttering
SU607926A1 (en) Method of constructing multistory buildings
RU2343251C1 (en) Wall
SU1411381A1 (en) Method of constructing a building or structure
SU652296A1 (en) Building construction method
RU2300609C1 (en) Method for laminated building block production
SU941516A1 (en) Method of constructing ferroconcrete vault on pneumatic form
SU1079785A1 (en) Method of constructing a multistorey building by adding floors from below
RU2232676C1 (en) Method of combined reinforced structural unit production and reinforced structural unit
SU1408034A1 (en) Multistorey building