KR20070106836A - Excavation method of road and railroad lower part using deck unit jacking - Google Patents

Excavation method of road and railroad lower part using deck unit jacking Download PDF

Info

Publication number
KR20070106836A
KR20070106836A KR1020060039169A KR20060039169A KR20070106836A KR 20070106836 A KR20070106836 A KR 20070106836A KR 1020060039169 A KR1020060039169 A KR 1020060039169A KR 20060039169 A KR20060039169 A KR 20060039169A KR 20070106836 A KR20070106836 A KR 20070106836A
Authority
KR
South Korea
Prior art keywords
steel pipe
deck
support
space
railway
Prior art date
Application number
KR1020060039169A
Other languages
Korean (ko)
Other versions
KR100794810B1 (en
Inventor
허영부
Original Assignee
주식회사 도화종합기술공사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 도화종합기술공사 filed Critical 주식회사 도화종합기술공사
Priority to KR1020060039169A priority Critical patent/KR100794810B1/en
Publication of KR20070106836A publication Critical patent/KR20070106836A/en
Application granted granted Critical
Publication of KR100794810B1 publication Critical patent/KR100794810B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/005Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by forcing prefabricated elements through the ground, e.g. by pushing lining from an access pit

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

A method of excavating a pit below a roadway or a railway is provided to have an underground structure while maintaining flow of traffic on the roadway or the railway at a reduced cost in a reduced construction period. A method of excavating a pit below a roadway or a railway includes a step of excavating ground on both sides of a roadway(80) or a railway to prepare a launch pit(70), a step of installing a pipe(10) to be rammed, a step of installing a deck(20) on a deck frame(74), a step of preparing cutter grooves equally spaced along the desired width of the excavation, a step of installing a leading plate(30) to cover the top of space to be excavated, a step of excavating ground under the leading plate and installing beams and guide angles at the excavated space, a step of jacking the pipe along with the deck and the leading plate using a jack unit(72), and a step of repeating preparation of space and jacking of the pipe.

Description

데크압입을 이용한 도로 및 철도하부의 지하구조물 구축용 터파기 방법{Excavation method of road and railroad lower part using deck unit jacking}Excavation method of road and railroad lower part using deck unit jacking}

도 1 은 본 발명의 일실시예에 따른 도로하부에 지하구조물 구축하기 위한 터파기의 시공상태를 개략적으로 나타낸 예시도,1 is an exemplary view schematically showing a construction state of the trench for building the underground structure under the road according to an embodiment of the present invention,

도 2 은 본 발명의 데크유닛의 형상을 나타낸 사시도,Figure 2 is a perspective view showing the shape of the deck unit of the present invention,

도 3 는 본 발명의 선도판의 형상을 나타낸 저면사시도,3 is a bottom perspective view showing the shape of the lead plate of the present invention;

도 4 는 본 발명의 커터홈을 나타낸 단면도,4 is a cross-sectional view showing a cutter groove of the present invention;

도 5 는 본 발명의 터파기 작업시 막장면에서 바라본 정면도,5 is a front view as viewed from the close-up surface during the trench operation of the present invention,

도 6 은 본 발명의 강관 및 데크유닛의 압입상태를 나타낸 측면에서 바라본 개념도, 6 is a conceptual view as viewed from the side showing the press-fit state of the steel pipe and deck unit of the present invention,

도 7 은 도 6 의 A-A를 나타낸 단면도,7 is a cross-sectional view illustrating A-A of FIG. 6;

도 8 은 본 발명의 다른 실시예에 의한 철도의 하부에 지하구조물을 구축하기 위한 터파기의 시공상태를 개략적으로 나타낸 측면도,8 is a side view schematically showing a construction state of the trench for building the underground structure in the lower portion of the railway according to another embodiment of the present invention,

도 9 는 본 발명의 다른 실시예에 의한 철도상승수단의 설치상태를 개략적으로 나타낸 평면도.Figure 9 is a plan view schematically showing the installation state of the railway lifting means according to another embodiment of the present invention.

도 10 은 본 발명의 터파기 공간을 이용하여 2차구조물을 설치하는 것을 나타낸 개념도,10 is a conceptual diagram showing the installation of a secondary structure using the trench space of the present invention,

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

(10) : 강관 (20) : 데크유닛(10): steel pipe (20): deck unit

(21) : 데크 (22) : 받침대21: Deck 22: Pedestal

(30) : 선도판 (31) : 상부판30: leading plate 31: top plate

(32) : 키 (33) : 보강부재(32): key (33): reinforcing member

(40) : 지보 (41) : 하부받침40: support (41): lower support

(42) : 상부받침 (43) : 지지말뚝(42): upper support (43): support pile

(44) : 토류판(44): earth plate

(60) : 가이드앵글 (61) : 수평부60: guide angle 61: horizontal portion

(62) : 수직부 (63) : 네일(62): vertical portion 63: nail

(70) : 추진기지 (71) : 압입장치(70): propulsion base (71): indentation device

(72) : 잭유닛 (73) : 반력벽(72): Jack Unit (73): Reaction Wall

(74) : 데크거치대 (80) : 도로(74): deck stand 80: road

(81) : 커터홈 (90) : 2차구조물(81): cutter groove (90): secondary structure

(100) : 철도 (101) : 레일100: railway 101: rail

(102) : 침목 (110) : 철도상승수단(102): sleepers (110): railway ascending means

(111) : 지지부재 (112) : 받침대111: support member 112: support

(113) : 유압장치(113): Hydraulic

본 발명은 데크압입을 이용한 지하구조물 구축용 터파기 방법에 관한 것으로, 보다 상세하게는 강관을 추진하면서 선도판 밑에서 굴착작업과, 지보설치작업, 가이드앵글을 이용한 레일작업을 병행하면서 새로운 강관추진공간을 확보한 후 강관을 추진하고, 이 작업을 계속해서 수행하면서 굴착된 공간의 상부에 데크를 설치함으로써 차량통행이 가능하도록 하는 한편 지하에는 지하구조물을 설치하거나, 대형의 지하구조물을 구축할 수 있는 기초를 형성할 수 있게 되는 데크압입을 이용한 지하구조물 구축용 터파기 방법에 관한 것이다.The present invention relates to a method for digging underground structures using deck press-fitting, and more specifically, a new steel pipe propulsion space while carrying out excavation work, support installation work, and rail work using guide angle under the leading plate while promoting steel pipe. After securing the steel pipe, the steel pipe is pushed forward, and the work continues, and the deck is installed in the upper part of the excavated space to allow the vehicle to pass while the basement can be installed in the basement or a large underground structure can be built. It relates to an excavation method for building underground structures using deck indentation to be formed.

일반적으로 지하구조물을 형성하기 위한 공법으로는 개착공법과 비개착공법이 있다.In general, the construction method for forming the underground structure is an open method and a non-open method.

상기 개착공법은 지상에 구조물이 있을 경우 작업이 불가능하고 도로가 설치되어 있을 경우에는 우회도로를 건설해야하므로 토지비용과 민원이 발생하는 문제점이 있어, 기존 도로 및 철도 하부를 횡단해서 하수암거나 지하차도, 터널구조물 등을 설치해야 하는 경우 공사에 따른 지장물의 이전이 곤란하거나, 지장물 저촉, 차량 소통의 장애 등으로 개착이 불가능할 경우에는 비개착공법이 이용된다.The opening method is difficult to work if there is a structure on the ground, and if a road is installed, there is a problem in that land costs and civil complaints occur because of the construction of a bypass road, sewer rock or underground across existing roads and railways When it is necessary to install a roadway, a tunnel structure, etc., when it is difficult to transfer obstacles due to construction, or when it is impossible to attach due to obstacles or obstacles in vehicle communication, a non-opening method is used.

상기 비개착공법으로는 콘크리트 구조물을 제작한 뒤 유압잭으로 구조물을 시공 지점으로 밀어넣는 공법인 FJ공법(Front Jacking Method), 강관 측면을 절개한 후 하부에는 거푸집을 설치하여 철근을 조립하고 상부에는 관을 이어 용접시켜 방수케 하며 콘크리트를 타설하는 공법인 NTR공법(New Tubular Roof Method), As the non-opening method, after manufacturing the concrete structure, the FJ method (Front Jacking Method), which is a method of pushing the structure to the construction point with a hydraulic jack, cuts the side of the steel pipe, installs formwork at the bottom to assemble the reinforcing bar and pipe at the top. Next, the NTR method (New Tubular Roof Method), which is a method of welding and waterproofing and placing concrete,

소형강관을 지중에 압입하고 철근으로 강관의 연결부를 보강한 후 모르타르를 타설하여 종,횡으로 일체화된 강관 슬래브를 형성한 후 내부를 부분 굴착하여 구조물을 축조하는 뉴파이프루프공법(New Pipe Roof Method)등이 있으나,New Pipe Roof Method presses small steel pipe into the ground, reinforces the connection of steel pipe with reinforcing steel, and then casts mortar to form longitudinal and horizontally integrated steel pipe slab, and then excavates the inside to construct the structure. ), But

상기 FJ공법은 공사기간이 길고, 공사비가 과다하며, 토층에 많은 제한을 받으며, 전단면이 프리캐스트 콘크리트이므로 방향전환이 어려운 문제점이 있다.The FJ method has a problem in that the construction period is long, the construction cost is excessive, the soil layer is restricted a lot, and the shear surface is difficult to change direction because of the precast concrete.

또한 상기 NTR공법은 연암이상의 지층이 연속될 경우에는 공기가 길어지고, 설계가 정확해야하며, 전문가의 자문이 필요함은 물론 시공실적이 적어 실제 현장시공이 어려운 문제점이 있다.In addition, the NTR method has a problem in that the air is long, the design must be accurate, and the expert's advice is required, as well as the actual site construction is difficult when the layers above the soft rock are continuous.

또한 상기 뉴파이프루프공법은 공사기간이 길고, 비용이 많이 들게 되어 실제시공이 매우 어려운 문제점이 있다.In addition, the new pipe-proof method has a long construction period, the cost is high, the actual construction is very difficult problem.

본 발명은 상기와 같은 종래의 문제점을 해결하기 위하여 창출되는 것으로, 지상에 선도판을 설치한 후 그 하부에 강관을 추진하면서 굴착작업을 하고 굴착된 공간에 지보를 설치하면서 새로운 추진공간을 확보하며 선도판의 후방으로 데크를 연속적으로 압입 설치함으로써, 지상의 이동은 유지하면서 데크의 저면에는 다양한 지하구조물을 설치할 수 있으며, 또한 지하구조물 구축을 위한 기초를 제공하며 비개착에서와 같이 지표의 침하가 없으며 시공이 간편하여 공사기간, 공사비가 절감되도록 하는 데크압입을 이용한 지하구조물 구축용 터파기 방법을 제공함을 목적으 로 한다.The present invention is created in order to solve the conventional problems as described above, while installing the leading plate on the ground, while propelling the steel pipe to the lower part of the excavation work and installing a support in the excavated space while securing a new propulsion space By continuously indenting the deck to the rear of the leading plate, it is possible to install various underground structures on the bottom of the deck while maintaining ground movement. It also provides the basis for building underground structures and sinking of the surface as in non-adhesive It aims to provide a method of digging underground constructions using deck press-fitting, which allows construction to be simplified, thereby reducing construction period and construction costs.

상기 목적을 달성하기 위한 본 발명은, 도로의 외부 양측에 터파기 하여 추진기지를 형성하고 일측의 추진기지에 압입장치 및 데크거치대를 설치하는 추진기지 형성단계; 상기 추진기지 내에서 도로를 가로지르도록 압입되는 강관을 위치시키는 강관설치단계; 상기 데크거치대에 데크유닛을 안착시킨 후 상기 강관의 상부면에 연결하여 강관의 압입과 동시에 데크유닛이 압입되도록 하는 데크설치단계; 상기 도로면에 굴착하고자 하는 폭 만큼의 간격으로 이격되는 커터홈을 형성하는 커터홈형성단계; 상기 데크유닛의 선단에 상기 커터홈을 통해 가이드되면서 전진하는 선도판을 설치하여 굴착될 공간의 상부면을 덮어주도록 하는 선도판 설치단계; 상기 일측의 추진기지에서 강관의 전진방향으로 소정의 거리만큼 선도판의 하부를 굴착하고, 굴착된 공간의 양측에 지보를 설치하여 무너짐을 방지하며, 상기 지보의 상부에 가이드앵글을 설치하여 데크유닛의 전진이 용이하도록 하는 강관전진공간 확보단계; 상기 압입장치를 이용하여 강관을 강관전진공간으로 압입함으로써 데크유닛 및 데크유닛 선단의 선도판이 전진하게 되는 강관압입단계; 상기 강관전진공간 확보 및 강관압입단계를 반복시공하여 도로면에 데크유닛에 의해 덮여지는 지하구조물 구축공간이 확보되도록 하는 단계; 로 이루어진 것을 특징으로 한다.The present invention for achieving the above object, the propulsion base forming step of forming a propulsion base by digging on the outer both sides of the road and installing the indentation device and the deck bracket on one side of the propulsion base; A steel pipe installation step of placing a steel pipe press-fitted to cross the road in the propulsion base; A deck installation step of seating the deck unit on the deck holder and connecting the upper surface of the steel pipe to press the deck unit at the same time as the steel pipe is press-fitted; A cutter groove forming step of forming cutter grooves spaced at intervals of the width to be excavated to the road surface; Lead plate installation step to cover the upper surface of the space to be excavated by installing a leading plate to be guided through the cutter groove at the front end of the deck unit; Excavate the lower part of the leading plate by a predetermined distance in the forward direction of the steel pipe from the propulsion base of the one side, install the support on both sides of the excavated space to prevent the collapse, and install a guide angle on the top of the support deck deck unit Steel pipe advancement space to facilitate the advancement of the; A steel pipe press-in step of pressing the steel pipe into the steel pipe advancement space by using the press-fit device to advance the deck unit and the leading plate of the deck unit tip; Repeating the securing of the steel pipe advance space and the steel pipe pressing step to ensure an underground structure building space covered by the deck unit on the road surface; Characterized in that consisting of.

또한 상기 강관전진공간 확보단계에서 지보를 설치하는 방법은, 강관의 외부양측을 하부방향으로 터파기하여 하부받침을 설치하는 단계; 상기 하부받침의 상부 에 지지말뚝을 수직하게 설치하는 단계; 상기 지지말뚝의 상부에 상부받침을 설치하는 단계; 상기 하부받침 지지말뚝 상부받침을 되메워주는 단계; 로 이루어진 것을 특징으로 한다.In addition, the method of installing the support in the steel pipe advance space securing step, the step of installing the lower support by digging the outer both sides of the steel pipe in the lower direction; Vertically installing a support pile on an upper portion of the lower support; Installing an upper support on an upper portion of the support pile; Filling the lower bearing support pile upper bearing; Characterized in that consisting of.

또한 상기 지보의 설치시 지반의 성질에 따라 상기 지보와 지보 사이에 토류판을 더 설치하는 것을 특징으로 한다.In addition, according to the nature of the ground when installing the support, characterized in that the earth plate is further installed between the support and the support.

또한 상기 선도판은, 상부판과, 상기 상부판의 하부에 소정의 간격으로 형성되어 상기 커터홈에 걸려지도록 하는 다수의 키와, 상기 키를 가로지르도록 상기 상부판의 하부에 형성되는 다수의 보강대로 이루어져 굴착될 공간의 상부를 덮어주는 것을 특징으로 한다.In addition, the lead plate, a plurality of keys formed at a predetermined interval in the lower portion of the upper plate and the upper plate to be caught in the cutter groove, and a plurality of keys formed in the lower portion of the upper plate to cross the key It consists of a reinforcing rod to cover the upper portion of the space to be excavated.

또한 상기 데크유닛은, 하부에 받침대가 구비되어 상기 가이드앵글 상에서 보다 손쉽게 마찰되어 압입되는 것을 특징으로 한다.In addition, the deck unit is provided with a pedestal at the bottom is characterized in that the friction is more easily pressed on the guide angle.

한편 본 발명은 철도의 외부 양측에 터파기 하여 추진기지를 형성하고 일측의 추진기지에에 압입장치 및 데크거치대를 설치하는 추진기지 형성단계; 상기 철도의 하부에 철도상승수단을 설치하여 철도를 상승시킴으로써 열차의 통행이 가능하면서 철도의 하부를 굴착할 수 있는 철도상승수단 설치단계; 철도상승수단을 설치하여 철도를 소정의 높이로 상승시켜주는 단계; 상기 일측의 추진기지내에 철도의 하부를 가로지르도록 압입되는 강관을 위치시키는 강관설치단계; 상기 데크거치대에 데크유닛을 안착시키고 상기 강관의 상부면에 연결하여 강관의 상기 강관의 압입과 동시에 데크유닛이 압입되도록 하는 데크설치단계; 상기 데크유닛의 선단부 에 걸려지고 굴착위치의 상부면에 안착되는 선도판을 설치하여 굴착될 공간의 상부를 덮어주는 선도판 설치단계; 상기 일측의 추진기지에서 강관의 전진방향으로 소정의 거리만큼 선도판의 하부를 굴착하고, 굴착된 공간의 양측에 지보를 설치하여 무너짐을 방지하며, 상기 지보의 상부에 가이드앵글을 설치하여 데크유닛의 전진이 용이하도록 하는 강관전진공간 확보단계; 상기 압입장치를 이용하여 강관을 강관전진공간으로 압입함으로써 데크유닛 및 데크유닛 선단의 선도판이 전진하게 되는 강관압입단계; 상기 강관전진공간 확보 및 강관압입단계를 반복시공하여 철도의 하부에 데크유닛에 의해 덮여지는 지하구조물 구축공간을 형성한 후 상기 철도상승수단을 제거하여 철도가 바닥면에 안착되도록 하는 철도하강단계; 로 이루어진 것을 특징으로 한다.Meanwhile, the present invention provides a propulsion base forming step of forming a propulsion base by discharging on both sides of the outside of the railway and installing a press-fitting device and a deck bracket on one side of the propulsion base; Installing a rail lift means for installing a rail lift means below the rail to allow the train to pass and to excavate the lower rail; Installing a railway ascending means to elevate the railway to a predetermined height; A steel pipe installation step of placing a steel pipe press-fitted to cross the lower part of the railway in the propulsion base of the one side; A deck installation step of seating the deck unit on the deck holder and connecting the upper surface of the steel pipe to press the deck unit at the same time as the steel pipe is press-fitted; A leader plate installation step of covering a top portion of a space to be excavated by installing a leader plate which is hooked to the front end of the deck unit and seated on an upper surface of an excavation position; Excavate the lower part of the leading plate by a predetermined distance in the forward direction of the steel pipe from the propulsion base of the one side, install the support on both sides of the excavated space to prevent the collapse, and install a guide angle on the top of the support deck deck unit Steel pipe advancement space to facilitate the advancement of the; A steel pipe press-in step of pressing the steel pipe into the steel pipe advancement space by using the press-fit device to advance the deck unit and the leading plate of the deck unit tip; Repeating the steel pipe advancement space and the steel pipe pressurizing step to form an underground structure building space covered by the deck unit at the bottom of the railway, and then the railway lowering step to remove the railway ascending means to be seated on the floor; Characterized in that consisting of.

또한 상기 철도상승수단은 철도의 폭방향 하부에 소정의 간격으로 설치되되, 양단이 상기 추진기지상으로 연장되도록 위치하는 다수의 지지부재를 설치하고, 상기 지지부재들의 양단부를 각각 연결해주는 받침대를 설치하며, 상기 추진기지에 구비되어 받침대를 상승시켜 줌으로써 철도가 상승되도록 하는 유압장치로 이루어지는 것으로 열차의 동행이 가능하면서 철도의 하부를 굴착할 수 있도록 해주는 것을 특징으로 한다.In addition, the railway ascending means is installed at a predetermined interval in the lower width direction of the railway, and install a plurality of support members positioned so that both ends extend on the propulsion base, and installs a pedestal for connecting both ends of the support members, respectively It is characterized in that the propulsion base is provided with a hydraulic device that allows the railway to be raised by raising the pedestal so that the train can be accompanied while the bottom of the railway can be excavated.

이하 본 발명의 실시예인 그 구성과 작용을 첨부도면에 연계시켜 상세히 설명하면 다음과 같다. Hereinafter, the configuration and operation of the embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1 은 본 발명의 일실시예에 따른 도로하부에 지하구조물 구축하기 위한 터파기의 시공상태를 개략적으로 나타낸 예시도, 도 2 은 본 발명의 데크유닛의 형상을 나타낸 사시도, 도 3 는 본 발명의 선도판의 형상을 나타낸 저면사시도, 도 4 는 본 발명의 커터홈을 나타낸 단면도, 도 5 는 본 발명의 터파기 작업시 막장면에서 바라본 정면도, 도 6 은 본 발명의 강관 및 데크유닛의 압입상태를 나타낸 측면에서 바라본 개념도, 도 7 은 도 6 의 A-A를 나타낸 단면도로서Figure 1 is an exemplary view schematically showing the construction of the trench for building underground structures under the road according to an embodiment of the present invention, Figure 2 is a perspective view showing the shape of the deck unit of the present invention, Figure 3 is a present invention 4 is a cross-sectional view showing a cutter groove of the present invention, FIG. 5 is a front view as viewed from a close face during the trench work of the present invention, and FIG. 6 is a view of a steel pipe and a deck unit of the present invention. 7 is a cross-sectional view showing the AA of FIG.

이와 같은 본 발명은 도 1 의 일실시예와 같이 먼저 도로(80)의 외부양측에 강관을 추진할 수 있는 추진기지(70)를 형성한다. 상기 추진기지(70)중 어느 하나의 추진기지(70) 내부에는 강관(10)을 압입할 수 있도록 압입장치(71)를 설치하며, 터파기될 도로(80)의 상부를 덮어 차량의 통행이 가능하도록 하는 데크유닛(20)을 굴착되는 공간으로 연속적으로 압입할 수 있도록 데크거치대(74)를 설치한다.As described above, the present invention forms a propulsion base 70 capable of propelling steel pipes on both outer sides of the road 80. In the propulsion base 70 of any one of the propulsion base 70 is installed a press-fit device 71 to press the steel pipe 10, and covers the upper portion of the road 80 to be destroyed, the traffic of the vehicle The deck mounting bracket 74 is installed to continuously press the deck unit 20 to be excavated into the excavated space.

상기 압입장치(71)는 상기 강관(10)을 압입시킬 수 있도록 설치되는 잭유닛(72)과, 상기 잭유닛(72)의 강관(10) 압입에 의해 발생되는 반력을 받쳐주는 반력벽(73)으로 이루어지는 통상의 강관 압입장치이다.The press-fitting device 71 is a jack unit 72 installed to press-fit the steel pipe 10 and a reaction force wall 73 supporting the reaction force generated by the press-fitting of the steel pipe 10 of the jack unit 72. It is a common steel pipe indentation device consisting of

이렇게 추진기지(70)의 시공이 완료되면 상기 추진기지(70)에 압입하고자 하는 강관(10)을 위치시키기고, 상기 데크거치대(74)상에 데크유닛(20)을 안착시킨 후 상기 강관(10)의 상부에 데크유닛(20)을 연결하여 강관(10)의 압입과 동시에 데크유닛(20)이 압입될 수 있도록 한다.When the construction of the propulsion base 70 is completed, the steel pipe 10 to be press-fitted to the propulsion base 70 is positioned, and the deck unit 20 is seated on the deck holder 74 and the steel pipe ( The deck unit 20 is connected to the upper portion of the 10 to allow the deck unit 20 to be press-fitted at the same time as the steel pipe 10 is press-fitted.

여기서 상기 데크유닛(20)은 도 2 에서와 같이 차량의 통행이 가능하도록 공장제작 되는 데크(21)와, 상기 데크(21)의 하부면 가장자리를 따라 설치되어 데크유닛(20)의 압입시 미끄러짐이 용이하도록 하는 받침대(22)로 이루어지며, 그 구조 는 콘크리트 PC(Precast)구조, 철근조립식판, 유리섬유와 복합소재를 이용한 패널구조 등을 사용할 수 있다. Here, the deck unit 20 is installed along the deck 21 which is factory-manufactured to enable the passage of the vehicle as shown in FIG. 2, and the lower surface edge of the deck 21 to slide when the deck unit 20 is press-fitted. It is made of a pedestal 22 to facilitate this, the structure can be used, such as concrete PC (Precast) structure, reinforced plate, panel structure using glass fibers and composite materials.

이와 같이 지중으로 강관(10)을 압입하기 위한 준비가 완료되면 도로(10)의 상부면에 터파기 하고자 하는 방향, 즉 도로(10)의 폭방향으로 커터홈(81)을 형성한다.When the preparation for press-fitting the steel pipe 10 into the ground is completed as described above, the cutter groove 81 is formed in the direction to break through the upper surface of the road 10, that is, in the width direction of the road 10.

상기 커터홈(81)은 도 4 에서와 같이 지중을 향해 소정의 깊이로 형성되고 상기 강관(10)에 의해 터파기 되는 도로(80)의 폭만큼의 간격으로 이격되도록 형성되는 것이다.The cutter groove 81 is formed to have a predetermined depth toward the ground as shown in Figure 4 and is formed to be spaced apart at intervals of the width of the road 80 to be broken by the steel pipe (10).

이렇게 도로(80)의 상부면에 커터홈(81)이 형성되면, 상기 데크유닛(10)의 선단에 선도판(30)을 연결한다. When the cutter groove 81 is formed on the upper surface of the road 80, the lead plate 30 is connected to the tip of the deck unit 10.

상기 선도판(30)은 도 3 에서와 같이 강관(10) 내부의 막장을 통해 굴착하고자 하는 공간의 상부를 덮어주어 굴착작업 공간을 제공하는 한편, 차량이 굴착공간의 상부로 이동할 수 있도록 설치되는 것으로, 상부판(31)과, 상기 커터홈(81)에 끼워지도록 설치될 수 있도록 상부판(31)의 하부면 전방에 소정의 간격으로 이격되어 돌출되는 다수의 키(32)와, 상기 상부판(31)의 하부에 상기 키(32)를 가로지르도록 설치되는 다수의 보강부재(33)로 이루어지며, 상기 키(32)가 커터홈(81)에 가 끼워져 커터홈(81)을 따라 가이드되면서 전진하게 된다.The leading plate 30 is provided to cover the upper portion of the space to be excavated through the membrane inside the steel pipe 10 to provide an excavation work space, as shown in Figure 3, the vehicle can be moved to the upper portion of the excavation space The upper plate 31 and the plurality of keys 32 spaced apart at predetermined intervals in front of the lower surface of the upper plate 31 so as to be fitted to the cutter groove 81, and the upper portion It is composed of a plurality of reinforcing members 33 installed to cross the key 32 in the lower portion of the plate 31, the key 32 is fitted into the cutter groove 81, along the cutter groove 81 Moved forward guided.

상기와 같이 강관(10), 데크유닛(20), 선도판(30)의 설치가 완료되면 일측의 추진기지(70)에서 강관(10)의 전진방향으로 소정의 거리만큼 선도판(30)의 하부를 굴착하여 강관전진공간을 형성한다. When the installation of the steel pipe 10, the deck unit 20, the lead plate 30 as described above is completed by the predetermined distance in the forward direction of the steel pipe 10 from the propulsion base 70 of one side of the lead plate 30 Excavate the lower part to form the steel pipe forward space.

다음으로 압입장치(71)를 이용하여 상기 강관전진공간으로 강관(10)을 압입한다. 이때 상기 강관(10)에 연결되어 있는 데크유닛(20)이 강관(10)을 따라 지반의 내측으로 압입되고 상기 데크유닛(20)이 상기 선도판(30)을 밀게 되어 선도판(30)이 전방으로 전진하게 되는 것이다.Next, the steel pipe 10 is press-fitted into the steel pipe advance space using the press-fit device 71. At this time, the deck unit 20 connected to the steel pipe 10 is pressed into the ground along the steel pipe 10 and the deck unit 20 pushes the lead plate 30, the lead plate 30 is You will move forward.

즉 강관(10)을 압입할 수 있도록 지반내부를 굴착하게 되면 지면이 강관전진공간으로 무너져 내리면서 선도판(30)이 전진할 수 있는 공간 및 강관(10)의 전진공간이 확보되어 강관(10)과 데크유닛(20), 선도판(30)이 전진하게 되는 것이다.That is, when the ground is excavated so that the steel pipe 10 can be press-fitted, the ground collapses into the steel pipe advancement space and the space for the leading plate 30 to move forward and the advancement space of the steel pipe 10 are secured. ) And deck unit 20, the lead plate 30 is to be advanced.

또한 상기 강관전진공간 형성시 굴착되는 공간의 양측에 지보(40)를 설치하여 굴착되는 공간이 무너져 내리지 않도록 한다.In addition, the support pipe 40 is installed on both sides of the space to be excavated when the steel pipe advancement space is formed so that the excavated space does not collapse.

아울러 상기 지보(40)의 상부에 상기 데크유닛(20)이 강관전진공간으로 손쉽게 미끄러져 압입될 수 있도록 하는 가이드앵글(60)을 설치한다.In addition, a guide angle 60 is installed at the upper portion of the support 40 to allow the deck unit 20 to slide easily into the steel pipe advance space.

이렇게 굴착작업과, 지보(40)의 설치작업, 가이드앵글(60)의 설치한 후 강관을 압입하는 과정을 반복시행하면서, 압입되는 강관(10)과 데크유닛(20)의 후방으로 또 다른 강관(10)과 데크유닛(20)을 연속적으로 연결하여 압입함으로써 도로(80)의 타측에 형성된 추진기지(70)까지 관통하는 터파기가 완료되는 것이다.This excavation work, the installation work of the jibo 40, the installation of the guide angle 60 and repeating the process of press-fitting the steel pipe, another steel pipe to the rear of the press-fitted steel pipe 10 and the deck unit 20 By continuously connecting the 10 and the deck unit 20 and press-fitted, the trenches penetrating to the propulsion base 70 formed on the other side of the road 80 are completed.

본 발명은 상기와 같은 방법으로 도로(80)를 굴착함으로써 굴착공간의 상부면에 데크유닛(20)이 설치되어 데크유닛(20)의 하부에서는 지하구조물을 구축할 수 있는 작업공간이 제공되는 것이다.The present invention is to provide a work space for the construction of an underground structure at the bottom of the deck unit 20 is installed deck unit 20 on the upper surface of the excavation space by excavating the road 80 in the same way as described above. .

또한 본 발명은 선도판(30)을 이용하여 지상의 이동을 유지하면서 도로(80)를 굴착할 수 있으므로, 종래의 비개착에서의 지면의 붕괴에 의한 토피문제를 해결 할 수 있게 되는 것이다.In addition, the present invention can excavate the road 80 while maintaining the movement of the ground using the lead plate 30, it is possible to solve the toffee problem due to the collapse of the ground in the conventional non-adhesion.

한편 상기 지보(40)를 설치하는 방법은 선도판(30) 하부에 형성되는 굴착공간의 바닥면을 하부방향으로 더 터파기하여 하부받침(41)을 설치하고, 상기 하부받침(41)의 상부면에 지지말뚝(43)을 수직하게 설치하며, 상기 지지말뚝(43)의 상부에 상부받침(42)을 설치한 후 상기 하부받침(41), 지지말뚝(43), 상부받침(42)을 토사로 되메움 함으로써 완료된다.On the other hand, the method of installing the support 40 is to further excavate the bottom surface of the excavation space formed in the lower plate 30 in the downward direction to install the lower support 41, the upper surface of the lower support 41 The support pile 43 is installed vertically in the upper support 42, the upper support 42 is installed on the lower support 41, the support pile 43, the upper support 42 Complete by backfilling with.

또한 상기 지보(40)의 설치시 지반의 성질에 따라 지보(40)와 지보(40) 사이에 토류판(44)을 더 설치하여 굴착공간의 양측면이 붕괴되는 것을 방지한다. 즉 상기 지지말뚝(43)과 지지말뚝(43) 사이에 토류판(44)을 설치하여 굴착공간의 양측면이 붕괴되는 것을 방지하게 되는 것이다.In addition, according to the property of the ground when the support 40 is installed, the earth plate 44 is further installed between the support 40 and the support 40 to prevent the collapse of both sides of the excavation space. That is, by installing the earth plate 44 between the support pile 43 and the support pile 43 to prevent the collapse of both sides of the excavation space.

상기 가이드앵글(60)은 'L'자 형상으로써, 상기 지보(40)의 상부받침(42)에 결합되는 수평부(61)와, 상기 수평부(61)의 일측단에서 수직하게 형성되는 수직부(62)로 구성되며, 지보(40)의 상부에서 서로 마주보도록 설치된다.The guide angle 60 has a 'L' shape, the horizontal portion 61 is coupled to the upper support 42 of the support 40, and vertically formed at one end of the horizontal portion 61 It is composed of a portion 62, is installed to face each other at the upper portion of the jibo (40).

한편 상기 가이드앵글(60)에는 수직부(62)를 통해 하향경사지게 지중으로 삽입되는 네일(63)을 설치하여 지반이 붕괴되는 것을 방지할 수 있다.Meanwhile, the guide angle 60 may be provided with a nail 63 inserted into the ground to be inclined downward through the vertical portion 62 to prevent the ground from being collapsed.

이렇게 가이드앵글(60)이 설치됨으로써 상기 데크유닛(20)이 가이드앵글(60)을 레일화 하여 굴착공간으로 미끄러지도록 설치되는 것이다.As the guide angle 60 is installed as described above, the deck unit 20 is installed to slide into the excavation space by railing the guide angle 60.

또한 상기와 같이 설치되는 데크유닛(20)에 의해 굴착공간의 상부면을 덮어주어 차량의 통행이 가능하도록 할 뿐만 아니라, 상기 지보가 굴착공간의 내측으로 전도되지 않도록 수평지보의 역할 또한 해주게 되는 것이다.In addition, the deck unit 20 is installed as described above to cover the upper surface of the excavation space not only to allow the passage of the vehicle, but also to serve as a horizontal support so that the support does not fall inside the excavation space. .

즉 상기 가이드앵글(60)사이에 데크유닛(20)이 끼워짐으로써 수직으로 설치되는 지보(40)가 토압에 의해 전도되지 않도록 하게 되는 것이다.That is, the deck unit 20 is inserted between the guide angles 60 so that the vertical support 40 is not inverted by earth pressure.

한편 도 8과 도 9 는 본 발명의 다른 실시예에 의한 철도의 하부에 지하구조물을 구축하기 위한 터파기의 시공상태를 개략적으로 나타낸 평면도 및 측면도로서,8 and 9 are a plan view and a side view schematically showing the construction state of the trench for building the underground structure in the lower portion of the railway according to another embodiment of the present invention,

도면에서와 같이 본 발명은 철도(100)의 열차통행이 가능한 상태로 철도의 하부를 가로지르는 터파기를 시공하는 것으로, 먼저 철도(100)의 외부 양측에 터파기를 추진기지(70)를 형성하고 일측의 추진기지(70)에 압입장치(71) 및 데크거치대(74)를 설치한다.As shown in the drawing, the present invention is to construct a trench that traverses the lower portion of the railway in a state where trains of the railway 100 can pass, first, forming a trench 70 on both sides of the railway 100 outside the propulsion base and The press base device 70 and the deck mounting bracket 74 are installed at the propulsion base 70.

이렇게 추진기지(70)가 형성되면 터파기 작업시 철도의 하부를 터파기 하는 동안 철도의 레일(101)을 받쳐주는 철도상승수단(110)을 설치하여 철도(100)를 바닥면에서 소정의 높이로 상승시킨다. When the propulsion base 70 is formed in this way, the railroad 100 is installed at a predetermined height at the bottom surface by installing a rail lift means 110 that supports the rail 101 of the railroad while digging the lower part of the railroad during the trenching operation. Raise to.

상기와 같이 철도(100)를 상승시킨 후 일측의 추진기지(70)에 강관(10)을 위치시키고, 상기 데크거치대(74)에 데크유닛(20)을 안착시킨 후 상기 데크유닛(20)을 강관(10)의 상부면에 연결하여 강관(10)의 압입과 동시에 데크유닛(20)이 압입되도록 하는 한편, 상기 데크유닛(20)의 선단부에 연결되는 선도판(30)을 설치한다.After raising the railway 100 as described above, the steel pipe 10 is positioned on the propulsion base 70 on one side, and the deck unit 20 is seated on the deck mount 74, and then the deck unit 20 is mounted. The deck unit 20 is press-fitted at the same time as the steel pipe 10 is press-fitted by connecting to the upper surface of the steel pipe 10, and a leader plate 30 connected to the distal end of the deck unit 20 is installed.

상기 선도판(30)은 굴착될 공간의 상부를 덮어주는 것으로, 상기 데크유닛(20)의 전진에 의해 전방으로 전진하게 된다. The lead plate 30 covers the upper portion of the space to be excavated and is advanced forward by the advancing of the deck unit 20.

이렇게 강관(10)을 압입하기 위한 준비가 완료되면 상기 일측의 추진기지(70)에서 강관의 전진방향, 즉 철로(100)의 폭방향으로 소정의 거리만큼 선도판(30)의 하부를 굴착한 후 굴착된 공간의 양측에 일실시예에서와 같은 방법으로 지보(40)를 설치하여 굴착되는 공간이 무너지는 것을 방지함으로써 강관전진공간을 확보한다. When the preparation for press-fitting the steel pipe 10 is completed, the lower portion of the lead plate 30 is excavated by a predetermined distance in the forward direction of the steel pipe, that is, the width direction of the railway line 100, from the propulsion base 70 on one side. After installing the jibo 40 on both sides of the excavated space in the same manner as in one embodiment to secure the steel pipe advance space by preventing the excavated space to collapse.

또한 상기 지보(40)의 상부에 가이드앵글(60)을 설치하여 상기 지보(40)의 상부로 이동하는 데크유닛(20)을 받쳐줌으로써 데크유닛(20)의 전진이 용이하도록 한다.In addition, by installing the guide angle 60 in the upper portion of the support 40 to support the deck unit 20 to move to the upper portion of the support 40 to facilitate the advance of the deck unit 20.

이후 상기 압입장치(71)를 이용하여 강관(10)을 강관전진공간으로 압입함으로써 데크유닛(20) 및 선도판(30)이 전진하게 된다. 이렇게 강관전진공간을 확보한 후 강관(10)을 압입하는 과정을 연속적으로 시공함으로써 철도(100)의 하부를 가로지르며 데크유닛(20)에 의해 덮여지는 구축공간을 형성한다.Thereafter, the deck unit 20 and the lead plate 30 are advanced by pressing the steel pipe 10 into the steel pipe advance space by using the press-fit device 71. After securing the steel pipe advance space by continuously constructing the process of pressing the steel pipe 10 to form a building space that is covered by the deck unit 20 across the lower portion of the railway (100).

이렇게 철도(100) 하부의 굴착이 완료되면 상기 철도상승수단(110)을 하강시켜 철도(100)가 바닥면에 안착되도록 한 후 철도상승수단(110)을 제거함으로써 완료된다.When the excavation of the lower railroad 100 is completed, the railroad lifting means 110 is lowered to allow the railroad 100 to be seated on the floor, and then the railroad lifting means 110 is removed.

상기 철도상승수단(110)은 철도(100)의 폭방향으로 레일(101)의 하부에 소정의 간격으로 설치되는 다수의 지지부재(111)와, 상기 지지부재(111)들의 양단부를 각각 연결해주는 받침대(112)와, 상기 받침대(112)를 상승시켜 지지부재(111)에 받쳐지는 철도(100)가 상승되도록 하는 유압장치(113)로 이루어진다.The railroad rising means 110 connects both end portions of the support members 111 and the support members 111 installed at predetermined intervals in the lower portion of the rail 101 in the width direction of the railroad 100, respectively. The pedestal 112 and the hydraulic device 113 for raising the pedestal 112 to raise the railway 100 supported by the support member 111.

이때 상기 지지부재(111)는 양단이 철도(100)의 양측에 형성되는 추진기 지(70)까지 연장되며, 상기 유압장치(113)는 추진기지(70)에 구비되어 받침대(112)를 상승시켜 줌으로써 상기 받침대(112)에 받쳐지는 지지부재(111)가 상승하고 상기 지지부재(111)에 레일(101)이 받쳐져 상승됨으로서 철도(100)가 바닥면에서 상승하게 되는 것이다.At this time, the support member 111 is extended to the propulsion base 70 is formed at both ends of the railroad 100, the hydraulic device 113 is provided in the propulsion base 70 to raise the pedestal 112 By supporting, the support member 111 supported by the pedestal 112 is raised and the rails 101 are supported by the support member 111 to be lifted to raise the railroad 100 from the bottom surface.

한편 상기 지지부재(111)는 열차의 통행시 철도(100)를 안전하게 지지할 수 있도록 침목(102)과 침목(102) 사이에 하나씩 설치하는 것이 바람직하다.On the other hand, the support member 111 is preferably installed between the sleeper 102 and the sleeper 102 so as to safely support the railway 100 when the train passes.

상기와 같은 실시예에 의한 본 발명의 강관(10)은 지반이 굴착공간의 내측으로 붕괴되는 것을 방지하고, 강관(10)의 내부를 통해 지반을 굴착함으로써, 굴착공간을 제공해주며, 상기 강관(10)의 전진으로 데크유닛(20) 및 선도판(30)이 전진하게 됨으로써 데크유닛(20)이 굴착공간의 상부에 설치될 수 있도록 하는 것이다.Steel pipe 10 of the present invention according to the embodiment as described above prevents the ground from collapsing to the inside of the excavation space, by excavating the ground through the interior of the steel pipe 10, provides an excavation space, the steel pipe ( The deck unit 20 and the lead plate 30 are advanced by the advance of the 10 so that the deck unit 20 can be installed in the upper portion of the excavation space.

또한 본 발명은 도 10 에서와 같이 상기 굴착공간을 소정의 간격으로 이격하여 시공한 후 상기 굴착공간을 기초로 하여 양단이 고정되는 교량 등과 같은 2차구조물(90)을 시공할 수 있다.In addition, according to the present invention, as shown in FIG. 10, after the excavation spaces are spaced at predetermined intervals, a secondary structure 90 such as a bridge having both ends fixed to the excavation space may be constructed.

즉 본 발명의 강관(10)이 압입되어 굴착공간을 통해 상하수도파이프, 통신선로 등의 지하구조물을 시공할 수 있으며, 다수의 굴착공간을 형성하여 상기 굴착공간을 기초로 교량 등과 같은 대형의 2차구조물(90)을 설치할 수 있게 되는 것이다.That is, the steel pipe 10 of the present invention may be press-fitted to construct underground structures such as water and sewage pipes, communication lines, etc. through excavation spaces, and form a plurality of excavation spaces based on the excavation spaces. The structure 90 will be able to install.

본 발명은 상술한 특정의 바람직한 실시예에 한정되지 아니하며, 청구범위에 서 청구하는 본 발명의 요지를 벗어남이 없이 당해 발명이 속하는 기술분야에서 통상의 지식을 가진 자라면 누구든지 다양한 변형실시가 가능한 것은 물론이고, 그와 같은 변경은 청구범위 기재의 범위 내에 있게 된다.The present invention is not limited to the above-described specific preferred embodiments, and various modifications can be made by any person having ordinary skill in the art without departing from the gist of the present invention claimed in the claims. Of course, such changes will fall within the scope of the claims.

상기와 같은 구성 및 작용에 의해 기대할 수 있는 본 발명의 효과는, 지상이 이동이 가능한 상태로 굴착공정이 가능하고, 굴착 후 상하수도파이프, 통신선로, 전력구 등의 다양한 지하구조물을 설치할 수 있으며, 별도의 우회도로를 건설하지 않아 공기가 단축되고 공사비가 절감되며, 최소 작업장의 확보로 민원이 해소됨은 물론 비개착공법에서의 토피문제를 해결할 수 있을 뿐만 아니라, 지중에 대형 구조물을 건설할 경우 기초로서의 사용이 가능한 매우 유용한 발명이다.The effect of the present invention can be expected by the configuration and action as described above, the excavation process is possible in the state that the ground is movable, and after the excavation can be installed a variety of underground structures, such as water and sewage pipes, communication lines, power outlets, By not constructing a separate bypass road, the air is shortened and construction cost is reduced, and the civil service is solved by securing a minimum workplace, and the toffee problem in the non-opening method can be solved. It is a very useful invention that can be used as.

Claims (9)

도로의 외부 양측에 터파기 하여 추진기지를 형성하고 일측의 추진기지에 압입장치 및 데크거치대를 설치하는 추진기지 형성단계;Propulsion base forming step of forming a propulsion base by digging on both sides of the road and installing the indentation device and deck bracket on one side of the propulsion base; 상기 추진기지 내에서 도로를 가로지르도록 압입되는 강관을 위치시키는 강관설치단계; A steel pipe installation step of placing a steel pipe press-fitted to cross the road in the propulsion base; 상기 데크거치대에 데크유닛을 안착시킨 후 상기 강관의 상부면에 연결하여 강관의 압입과 동시에 데크유닛이 압입되도록 하는 데크설치단계;A deck installation step of seating the deck unit on the deck holder and connecting the upper surface of the steel pipe to press the deck unit at the same time as the steel pipe is press-fitted; 상기 도로면에 굴착하고자 하는 폭 만큼의 간격으로 이격되는 커터홈을 형성하는 커터홈형성단계;A cutter groove forming step of forming cutter grooves spaced at intervals of the width to be excavated to the road surface; 상기 데크유닛의 선단에 상기 커터홈을 통해 가이드되면서 전진하는 선도판을 설치하여 굴착될 공간의 상부면을 덮어주도록 하는 선도판 설치단계;Lead plate installation step to cover the upper surface of the space to be excavated by installing a leading plate to be guided through the cutter groove at the front end of the deck unit; 상기 일측의 추진기지에서 강관의 전진방향으로 소정의 거리만큼 선도판의 하부를 굴착하고, 굴착된 공간의 양측에 지보를 설치하여 무너짐을 방지하며, 상기 지보의 상부에 가이드앵글을 설치하여 데크유닛의 전진이 용이하도록 하는 강관전진공간 확보단계;Excavate the lower part of the leading plate by a predetermined distance in the forward direction of the steel pipe from the propulsion base of the one side, install the support on both sides of the excavated space to prevent the collapse, and install a guide angle on the top of the support deck deck unit Steel pipe advancement space to facilitate the advancement of the; 상기 압입장치를 이용하여 강관을 강관전진공간으로 압입함으로써 데크유닛 및 데크유닛 선단의 선도판이 전진하게되는 강관압입단계;A steel pipe press-in step of pressing the steel pipe into the steel pipe advancement space by using the press-fit device to advance the deck unit and the leading plate of the deck unit tip; 상기 강관전진공간 확보 및 강관압입단계를 반복시공하여 도로면에 데크유닛에 의해 덮여지는 지하구조물 구축공간이 확보되도록 하는 단계; 로 이루어진 것을 특징으로 하는 데크압입을 이용한 도로 하부의 지하구조물 구축용 터파기 방법.Repeating the securing of the steel pipe advance space and the steel pipe pressing step to ensure an underground structure building space covered by the deck unit on the road surface; Dig method for building underground structures of the lower part of the road using deck indentation, characterized in that consisting of. 제 1 항에 있어서,The method of claim 1, 상기 강관전진공간 확보단계에서 지보를 설치하는 방법은, 강관의 외부양측을 하부방향으로 터파기하여 하부받침을 설치하는 단계;The method of installing the support in the steel pipe advance space securing step, the step of installing the lower support by digging the outer both sides of the steel pipe in the downward direction; 상기 하부받침의 상부에 지지말뚝을 수직하게 설치하는 단계;Vertically installing a support pile on the lower support; 상기 지지말뚝의 상부에 상부받침을 설치하는 단계;Installing an upper support on an upper portion of the support pile; 상기 하부받침 지지말뚝 상부받침을 되메워주는 단계; 로 이루어진 것을 특징으로 하는 데크압입을 이용한 도로 하부의 지하구조물 구축용 터파기 방법.Filling the lower bearing support pile upper bearing; Dig method for building underground structures of the lower part of the road using deck indentation, characterized in that consisting of. 제 1 항에 있어서,The method of claim 1, 상기 지보의 설치시 지반의 성질에 따라 상기 지보와 지보 사이에 토류판을 더 설치하는 것을 특징으로 하는 데크압입을 이용한 도로 하부의 지하구조물 구축용 터파기 방법.When the installation of the support, according to the nature of the ground earth ground plate construction method using a deck press-fitting, characterized in that the earth plate is further installed between the support and the support. 제 1 항에 있어서,The method of claim 1, 상기 선도판은, 상부판과, 상기 상부판의 하부에 소정의 간격으로 형성되어 상기 커터홈에 걸려지도록 하는 다수의 키와, 상기 키를 가로지르도록 상기 상부판의 하부에 형성되는 다수의 보강대로 이루어져 굴착될 공간의 상부를 덮어주는 것을 특징으로 하는 데크압입을 이용한 도로 하부의 지하구조물 구축용 터파기 방법.The lead plate includes a top plate, a plurality of keys formed at predetermined intervals below the top plate to engage the cutter groove, and a plurality of reinforcement bars formed below the top plate to cross the keys. Dig method for building underground structures of the lower part of the road using deck indentation, characterized in that for covering the upper portion of the space to be excavated. 제 1 항에 있어서,The method of claim 1, 상기 데크유닛은, 하부에 받침대가 구비되어 상기 가이드앵글 상에서 보다 손쉽게 마찰되어 압입되는 것을 특징으로 하는 데크압입을 이용한 도로 하부의 지하구조물 구축용 터파기 방법.The deck unit is provided with a pedestal in the lower portion of the trench structure for the construction of the underground structure of the lower road using the deck press-in, characterized in that more easily rubbed on the guide angle. 철도의 외부 양측에 터파기 하여 추진기지를 형성하고 일측의 추진기지에에 압입장치 및 데크거치대를 설치하는 추진기지 형성단계;Protruding base forming step of forming a propulsion base by digging on both sides of the railroad and installing a press-fitting device and deck bracket on one side of the propulsion base; 상기 철도의 하부에 철도상승수단을 설치하여 철도를 상승시킴으로써 열차의 통행이 가능하면서 철도의 하부를 굴착할 수 있는 철도상승수단 설치단계;Installing a rail lift means for installing a rail lift means below the rail to allow the train to pass and to excavate the lower rail; 철도상승수단을 설치하여 철도를 소정의 높이로 상승시켜주는 단계;Installing a railway ascending means to elevate the railway to a predetermined height; 상기 일측의 추진기지내에 철도의 하부를 가로지르도록 압입되는 강관을 위치시키는 강관설치단계; A steel pipe installation step of placing a steel pipe press-fitted to cross the lower part of the railway in the propulsion base of the one side; 상기 데크거치대에 데크유닛을 안착시키고 상기 강관의 상부면에 연결하여 강관의 상기 강관의 압입과 동시에 데크유닛이 압입되도록 하는 데크설치단계;A deck installation step of seating the deck unit on the deck holder and connecting the upper surface of the steel pipe to press the deck unit at the same time as the steel pipe is press-fitted; 상기 데크유닛의 선단부에 걸려지고 굴착위치의 상부면에 안착되는 선도판을 설치하여 굴착될 공간의 상부를 덮어주는 선도판 설치단계; A leader plate installation step of covering a top portion of a space to be excavated by installing a leader plate which is hooked to the front end of the deck unit and seated on an upper surface of an excavation position; 상기 일측의 추진기지에서 강관의 전진방향으로 소정의 거리만큼 선도판의 하부를 굴착하고, 굴착된 공간의 양측에 지보를 설치하여 무너짐을 방지하며, 상기 지보의 상부에 가이드앵글을 설치하여 데크유닛의 전진이 용이하도록 하는 강관전진공간 확보단계;Excavate the lower part of the leading plate by a predetermined distance in the forward direction of the steel pipe from the propulsion base of the one side, install the support on both sides of the excavated space to prevent the collapse, and install a guide angle on the top of the support deck deck unit Steel pipe advancement space to facilitate the advancement of the; 상기 압입장치를 이용하여 강관을 강관전진공간으로 압입함으로써 데크유닛 및 데크유닛 선단의 선도판이 전진하게 되는 강관압입단계;A steel pipe press-in step of pressing the steel pipe into the steel pipe advancement space by using the press-fit device to advance the deck unit and the leading plate of the deck unit tip; 상기 강관전진공간 확보 및 강관압입단계를 반복시공하여 철도의 하부에 데크유닛에 의해 덮여지는 지하구조물 구축공간을 형성한 후 상기 철도상승수단을 제거하여 철도가 바닥면에 안착되도록 하는 철도하강단계; 로 이루어진 것을 특징으로 하는 데크압입을 이용한 철도 하부의 지하구조물 구축용 터파기 방법.Repeating the steel pipe advancement space and the steel pipe pressurizing step to form an underground structure building space covered by the deck unit at the bottom of the railway, and then the railway lowering step to remove the railway ascending means to be seated on the floor; Deburring method for building underground structures of the lower railway using deck indentation, characterized in that consisting of. 제 6 항에 있어서,The method of claim 6, 상기 철도상승수단은 철도의 폭방향 하부에 소정의 간격으로 설치되되, 양단이 상기 추진기지상으로 연장되도록 위치하는 다수의 지지부재를 설치하고, 상기 지지부재들의 양단부를 각각 연결해주는 받침대를 설치하며, 상기 추진기지에 구비되어 받침대를 상승시켜 줌으로써 철도가 상승되도록 하는 유압장치로 이루어지는 것으로 열차의 동행이 가능하면서 철도의 하부를 굴착할 수 있도록 해주는 것을 특 징으로 하는 데크압입을 이용한 철도 하부의 지하구조물 구축용 터파기 방법.The railway ascending means is installed at a predetermined interval in the lower width direction of the railway, install a plurality of support members positioned so that both ends extend on the propulsion base, and installs a pedestal for connecting both ends of the support members, respectively, The underground structure of the lower part of the railway using deck press-fitting, which is provided with the propulsion base, is made of a hydraulic device that raises the pedestal so that the railway can be raised, and it is possible to accompany the train and to excavate the lower part of the railway. Construction excavation method. 제 6 항에 있어서,The method of claim 6, 상기 강관전진공간 확보단계에서 지보를 설치하는 방법은, 강관의 외부양측을 하부방향으로 터파기하여 하부받침을 설치하는 단계;The method of installing the support in the steel pipe advance space securing step, the step of installing the lower support by digging the outer both sides of the steel pipe in the downward direction; 상기 하부받침의 상부에 지지말뚝을 수직하게 설치하는 단계;Vertically installing a support pile on the lower support; 상기 지지말뚝의 상부에 상부받침을 설치하는 단계;Installing an upper support on an upper portion of the support pile; 상기 하부받침 지지말뚝 상부받침을 되메워주는 단계; 로 이루어진 것을 특징으로 하는 데크압입을 이용한 철도 하부의 지하구조물 구축용 터파기 방법.Filling the lower bearing support pile upper bearing; Deburring method for building underground structures of the lower railway using deck indentation, characterized in that consisting of. 제 8 항에 있어서,The method of claim 8, 상기 지보의 설치시 지반의 성질에 따라 상기 지보와 지보 사이에 토류판을 더 설치하는 것을 특징으로 하는 데크압입을 이용한 철도 하부의 지하구조물 구축용 터파기 방법.According to the nature of the ground when the support is installed according to the nature of the earth plate between the jibo and the jibo further characterized in that the trench construction method for the underground structure construction under the railway using deck indentation.
KR1020060039169A 2006-05-01 2006-05-01 Excavation method of road and railroad lower part using deck unit jacking KR100794810B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020060039169A KR100794810B1 (en) 2006-05-01 2006-05-01 Excavation method of road and railroad lower part using deck unit jacking

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020060039169A KR100794810B1 (en) 2006-05-01 2006-05-01 Excavation method of road and railroad lower part using deck unit jacking

Publications (2)

Publication Number Publication Date
KR20070106836A true KR20070106836A (en) 2007-11-06
KR100794810B1 KR100794810B1 (en) 2008-01-15

Family

ID=39062466

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020060039169A KR100794810B1 (en) 2006-05-01 2006-05-01 Excavation method of road and railroad lower part using deck unit jacking

Country Status (1)

Country Link
KR (1) KR100794810B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102068441B1 (en) * 2019-07-01 2020-01-20 박상원 Temporary Strcuture of Underpass Traverse Construction for Traffic Facilities and Tunnel Construction Method Using by This

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102105229B1 (en) 2017-09-25 2020-04-27 주식회사 포스코건설 Temporary facility construction method for underground construction fo railroad track lower pass

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR0181965B1 (en) * 1991-06-18 1999-04-01 마고도 우에무라 Underground construction
JP2954808B2 (en) * 1993-04-19 1999-09-27 株式会社奥村組 Round pipe for pipe roof
JP4073428B2 (en) 2004-10-04 2008-04-09 株式会社奥村組 Underground construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102068441B1 (en) * 2019-07-01 2020-01-20 박상원 Temporary Strcuture of Underpass Traverse Construction for Traffic Facilities and Tunnel Construction Method Using by This

Also Published As

Publication number Publication date
KR100794810B1 (en) 2008-01-15

Similar Documents

Publication Publication Date Title
KR100834076B1 (en) None open cut tunnelling method and tunnel
JP4881555B2 (en) Construction method of underground structure
CN113756330A (en) Foundation pit support construction method close to existing operation railway
JP4317322B2 (en) Arch support structure
JP6944882B2 (en) How to build an invert in an existing tunnel
KR100794810B1 (en) Excavation method of road and railroad lower part using deck unit jacking
KR100976621B1 (en) Construction method for basement extention
KR101234270B1 (en) Method for non excavated excavating construction using steel pipe and steel pipe with hole
KR20190038244A (en) Underground road way construction method
KR102289576B1 (en) Top-down type underground structure construction method using earth support plate
CN209958372U (en) Railway newly-added second-line platform back way foundation pile pipe curtain supporting structure
KR100756681B1 (en) Steel pipe roof construction method of road and railroad lower part
JP3380301B2 (en) Viaduct construction method
KR100902640B1 (en) Waterway culvert using steel sheet piles and its construction method
CN109914478A (en) A kind of Blasting Excavation continued access diaphram wall construction subway station method
JP4889993B2 (en) Construction method of widening shaft
KR102610909B1 (en) Method and structure of steel pipe propulsion using anchor installation inside steel pipe to prevent sinking
KR101206996B1 (en) The tunnel construction method for which point moving roof cell was used
JP5167578B2 (en) Construction method for underground structures
KR102087978B1 (en) A method of pressurizing steel pipe and a method of constructing an underground structure in a lower toe pipe section
KR200331521Y1 (en) None open cut tunnelling of arch type with with hume pipe and con&#39;c rib
CN211547751U (en) Municipal pipe network slot excavation supporting device
JP5209546B2 (en) Construction method of the structure under the track
JP4195215B2 (en) Mountain retaining method and foundation construction method
KR200290860Y1 (en) apparatus for constructing unexcavated underground tunnel for railroad traverse

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130103

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20131227

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20141230

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20151224

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20161229

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20171228

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20181227

Year of fee payment: 12