JP4073428B2 - Underground construction method - Google Patents

Underground construction method Download PDF

Info

Publication number
JP4073428B2
JP4073428B2 JP2004291833A JP2004291833A JP4073428B2 JP 4073428 B2 JP4073428 B2 JP 4073428B2 JP 2004291833 A JP2004291833 A JP 2004291833A JP 2004291833 A JP2004291833 A JP 2004291833A JP 4073428 B2 JP4073428 B2 JP 4073428B2
Authority
JP
Japan
Prior art keywords
underground structure
buried
side shaft
pipe
arrival
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2004291833A
Other languages
Japanese (ja)
Other versions
JP2006104744A (en
Inventor
仁 藤田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Okumura Corp
Original Assignee
Okumura Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Okumura Corp filed Critical Okumura Corp
Priority to JP2004291833A priority Critical patent/JP4073428B2/en
Publication of JP2006104744A publication Critical patent/JP2006104744A/en
Application granted granted Critical
Publication of JP4073428B2 publication Critical patent/JP4073428B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

本発明は、軌道下や道路下を横断してこれらの軌道や道路直下の地盤中に地下道となる地下構造物を埋設、施工する方法に関するものである。   The present invention relates to a method for embedding and constructing an underground structure that becomes an underpass in the ground directly below these tracks and roads across a track and roads.

従来から、例えば軌道下の地盤中に、RCコンクリート構造物である地下構造物を推進によって埋設して地下道を築造する場合、特許文献1に記載しているように、まず、軌道を挟んでその軌道下の地下構造物埋設計画域の両側に地下構造物の発進側と到達側となる立坑を掘削したのち、この地下構造物の上床部の埋設計画位置に、上面にフリクションカット板を載置した角形鋼管を複数本、発進側から並列状態に推進、埋設して到達側に貫通したパイプルーフを形成し、しかるのち、地下構造物を発進側に設置してその上床部の前端面をパイプルーフの後端に当接させ、地下構造物の前方地盤を掘削しながら該地下構造物を推進して上記フリクションカット板を不動状態で残したまま、このフリクションカット板の下面に沿ってパイプルーフを到達側に押し出し、地下構造物を埋設計画域に埋設することが行われている。 Conventionally, for example, when an underground passage is built by propelling an underground structure that is an RC concrete structure in the ground under the track, as described in Patent Document 1, first, the track is sandwiched between After excavating shafts on the start side and the arrival side of the underground structure on both sides of the underground structure buried design area under the orbit, a friction cut plate is placed on the upper surface at the buried design drawing position of the upper floor of this underground structure A plurality of rectangular steel pipes are propelled and buried in parallel from the starting side to form a pipe roof that penetrates to the arrival side, and then the underground structure is installed on the starting side and the front end surface of the upper floor is piped While abutting against the rear end of the roof, excavating the ground in front of the underground structure and propelling the underground structure, leaving the friction cut plate in an immovable state, pipe pipe along the lower surface of the friction cut plate. The extruded arrival side have been made to bury the underground construction in embedded plan area.

特開昭60−62398号公報JP 60-62398 A

しかしながら、上記の方法によれば、発進側と到達側間の軌道直下の地盤における地下構造物の埋設計画域に、この地下構造物を推進、埋設するに先立ってパイプルーフ形成用の鋼管を推進、埋設するには、発進側から到達側に向かって鋼管を並列状に推進、埋設することによって行われており、この鋼管の推進、埋設によるパイプルーフの施工工事の終了を待って地下構造物の推進、埋設作業の準備を行っているのが現状である。 However, according to the above method, the steel pipe for forming the pipe roof is propelled before the underground structure is propelled and buried in the buried design area of the underground structure on the ground directly under the track between the starting side and the reaching side. To embed, steel pipes are pushed in parallel from the starting side to the arrival side, and the underground structure is waiting for the completion of the pipe roof construction work. Currently, we are preparing for the promotion and burial work.

地下構造物を発進側に設けるには、現場打ちの場合は、型枠の組立、形枠内への配筋、コンクリートの打設、養生、推進装置の設置等の作業を順次行う必要があり、これらの作業を上述したように、パイプルーフの施工工事が終わるのを待って行うものであるから、工事期間が著しく長期化すると共に工事費も高くなるといった問題点がある。   In order to install an underground structure on the start side, it is necessary to sequentially perform operations such as assembling the formwork, placing bars in the formwork, placing concrete, curing, installing propulsion equipment, etc. As described above, since these operations are performed after the pipe roof construction work is completed, there is a problem that the construction period is remarkably prolonged and the construction cost is increased.

本発明はこのような問題点に鑑みてなされたもので、その目的とするところは、パイプルーフの施工作業と並行して地下構造物の推進、埋設作業の準備を可能にし、工事期間の短縮と工事費の低減を図ることができる地下構造物の埋設施工方法を提供するにある。   The present invention has been made in view of such problems, and its purpose is to enable the promotion of underground structures in parallel with the construction work of the pipe roof and the preparation of the construction work, thereby shortening the construction period. And to provide an underground construction method that can reduce construction costs.

上記目的を達成するために、請求項1に係る地下構造物の埋設施工方法は、地下構造物の埋設計画域を挟んだ両側に地下構造物の発進側立坑と到達側立坑とを設け、これらの発進側立坑と到達側立坑間を貫通するように埋設計画域の地盤内に、上面にフリクションカット板を載置した複数本の鋼管を互いに並列させた状態となるように推進、埋設してパイプルーフを形成したのち、上記フリクションカット板を不動状態にしてこのフリクションカット板の下面に沿って地下構造物を前進させてパイプルーフと地下構造物とを置換させながら地下構造物を道路又は軌道の直下の地盤に埋設する方法において、上記発進側立坑の深さを地下構造物の推進、埋設作業が可能な深さにする一方、到達側立坑の深さを発進側立坑よりも深さが浅くて上記パイプルーフを形成するための鋼管が推進、埋設可能な深さに形成したのち、上記上面にフリクションカット板を載置した複数本の鋼管を上記到達側立坑から発進側立坑に向かって推進、埋設させることによりパイプルーフを形成する一方、このパイプルーフの施工中に上記発進側立坑において地下構造物の前進、埋設の準備作業を行い、しかるのち、フリクションカット板の下面に沿って地下構造物を埋設計画域に向かって推進し、この地下構造物の推進に従ってその推進長に応じた長さだけ上記深さの浅い到達側立坑に押し出される鋼管の長さ部分を撤去しながら発進側立坑から到達側立坑に貫通するように地下構造物を埋設することを特徴とする。 In order to achieve the above object, an underground structure embedding method according to claim 1 is provided with a start side shaft and an arrival side shaft of the underground structure on both sides of a buried design area of the underground structure, In the ground of the buried design area so as to penetrate between the starting side shaft and the arrival side shaft, the steel pipes with friction cut plates placed on the upper surface are propelled and buried so that they are in parallel with each other. After forming the pipe roof, the above-mentioned friction cut plate is fixed and the underground structure is advanced along the lower surface of the friction cut plate to replace the pipe roof with the underground structure. In the method of burying in the ground directly below, the depth of the start side shaft is set to a depth that allows the underground structure to be propelled and buried, while the depth of the arrival side shaft is less than that of the start side shaft. Shallow and above Promoted steel pipe for forming a Ipurufu, after forming the implantable depth, promoting the plurality of steel pipes mounted with the friction-cut plate to the upper surface toward the starting side pit from the arrival side pit, is buried while forming the pipe roof by advancing the underground construction in the starting side pit during construction of the pipe roof, and prepares work buried, after accordingly, buried underground construction along the lower surface of the friction-cut plate Proceed toward the planned area, and according to the promotion of this underground structure, remove the length of the steel pipe that is pushed out to the arrival side shaft with the shallow depth by the length corresponding to the length of the promotion while removing from the start side shaft An underground structure is buried so as to penetrate the shaft .

本発明の地下構造物の埋設施工方法によれば、地下構造物の埋設計画域を挟んだ両側に地下構造物の発進側立坑と到達側立坑とを設けたのち、到達側立坑から複数本の鋼管を発進側立坑に向かって推進、埋設してパイプルーフを形成することを特徴とするものであるから、このパイプルーフの施工作業に並行して、発進側立坑で地下構造物を築造する場合には、該地下構造物を築造するための型枠の組立や形枠内への配筋、コンクリートの打設、養生、推進装置の設置等の作業を行うことができ、地下構造物がプレキャストコンクリート構造物からなる場合であっても、コンクリートの養生や地下構造物の設置作業、推進装置の設置作業等を並行して行うことができるものであり、従って、地下構造物の埋設、施工作業が円滑且つ能率よく行うことができて工事期間を短縮することができると共に工事費の低減を図ることができる。 According to the underground construction method of the present invention, after providing the start side shaft and the arrival side shaft of the underground structure on both sides sandwiching the buried design area of the underground structure, a plurality of from the arrival side shaft promote steel towards the starting side pit, because characterized in that to form a pipe roof and buried in parallel to the construction work of the pipe roof, when construction of the underground construction with the starting side pit Can perform operations such as assembly of formwork to build the underground structure, reinforcement in the formwork, placement of concrete, curing, installation of propulsion equipment, etc. Even if it consists of concrete structures, concrete curing, installation work for underground structures, installation work for propulsion devices, etc. can be performed in parallel, so burying and construction work for underground structures Is smooth and efficient It is possible to reduce the construction costs it is possible to shorten the construction period can be.

本発明の具体的な実施の形態を図面について説明すると、まず、道路又は軌道(以下、軌道1とする)を挟んでこの軌道1の一側方に地下構造物2の発進側3を、他側方に該地下構造物2の到達側4を形成する。この場合、発進側3と到達側4としては、図1に示すように、軌道1の両側に立坑を掘削している発進立坑と到達立坑とによって形成してもよいが、軌道1の両側に法面を対して広い空間部が存在する場合には、必ずしも立坑を掘削することなく一側方を上記発進側3に、他側方を到達側4にすればよい。   A specific embodiment of the present invention will be described with reference to the drawings. First, a start side 3 of an underground structure 2 is placed on one side of the track 1 across a road or a track (hereinafter referred to as a track 1). An arrival side 4 of the underground structure 2 is formed on the side. In this case, the start side 3 and the arrival side 4 may be formed by a start shaft and a reaching shaft that have excavated shafts on both sides of the track 1 as shown in FIG. When there is a wide space with respect to the slope, it is only necessary to set one side to the start side 3 and the other side to the arrival side 4 without necessarily excavating a shaft.

なお、発進側3や到達側4の立坑の掘削壁面に土留工10、11を施工すると共に立坑の底面に上面が平坦なベースコンクリート12、13を打設する。この際、発進側3の立坑(以下、単に発進側3とする)の深さを地下構造物2の推進、埋設作業が可能な深さにする一方、到達側4の立坑(以下、単に到達側4とする)の深さをパイプルーフ5を形成するための鋼管5aが推進、埋設可能な深さ、即ち、発進側の立坑よりも深さの浅い立坑に形成しておく。 The earth retaining works 10 and 11 are constructed on the excavation wall surfaces of the shafts on the start side 3 and the arrival side 4 , and the base concretes 12 and 13 having a flat upper surface are placed on the bottom surface of the shaft. At this time, the depth of the shaft on the start side 3 (hereinafter simply referred to as the start side 3) is set to a depth at which the underground structure 2 can be propelled and buried, while the shaft on the arrival side 4 (hereinafter simply referred to as reach). steel pipe 5a for forming a pipe roof 5 the depth of the side 4) is promoted, implantable depth, i.e., previously formed in a shallow pit depths than vertical shaft of the starting side.

このように、軌道1の両側方に発進側3と到達側4とを設けたのち、図2に示すように、到達側4から軌道下の地盤7の地下構造物埋設計画域における地下構造物2の上床部埋設高さ部分に、上面に帯鋼板からなるフリクションカット板6を載置した断面矩形状の鋼管5aを複数本、互いに並列状態となるように推進、埋設して到達側2に貫通したパイプルーフ5を形成する一方、このパイプルーフ5の施工中に発進側3において、地下構造物2の推進、埋設の準備作業を行う。   Thus, after providing the start side 3 and the arrival side 4 on both sides of the track 1, as shown in FIG. 2, the underground structure in the underground structure buried design area of the ground 7 from the arrival side 4 under the track. In the upper floor portion embedded in the upper floor portion 2, a plurality of rectangular steel pipes 5 a each having a friction cut plate 6 made of a strip steel plate placed on the upper surface are propelled and embedded so as to be in parallel with each other. While the pipe roof 5 penetrating is formed, on the start side 3 during the construction of the pipe roof 5, the underground structure 2 is propelled and buried.

到達側4から発進側3に向かって鋼管5aを推進、埋設するには、到達側4のベースコンクリート13上に鋼管5aのガイド架台14を設けてこのガイド架台14上に鋼管5aを発進側3に向けて長さ方向に摺動移動自在に設置すると共に、この鋼管5aを軌道下の地盤7中に推進、埋設する掘削推進機15を装着する。なお、ガイド架台14は、鋼管5aを軌道下の地盤7の地下構造物埋設計画域における地下構造物2の上床板の埋設高さ位置に相当する部分に推進、埋設させることができる高さに設置する。この際、地下構造物2を水平状に埋設する場合には、ガイド架台14もその鋼管ガイド面を水平となるように設置しておく。   In order to propel and embed the steel pipe 5a from the arrival side 4 toward the start side 3, a guide base 14 of the steel pipe 5a is provided on the base concrete 13 of the arrival side 4, and the steel pipe 5a is set on the start side 3 of the guide base 14. The excavator 15 is installed so as to be slidable and movable in the lengthwise direction, and the steel pipe 5a is propelled and buried in the ground 7 under the track. The guide gantry 14 has a height at which the steel pipe 5a can be propelled and buried in a portion corresponding to the buried height position of the upper floor board of the underground structure 2 in the underground structure buried design area of the ground 7 under the track. Install. At this time, when the underground structure 2 is embedded horizontally, the guide frame 14 is also installed so that its steel pipe guide surface is horizontal.

鋼管5a内にはスクリューオーガからなる掘削手段(図示せず)が抜き取り可能に挿入配設されていて、そのオーガヘッドによって発進側3に向けている鋼管5aの開口端側の切羽地盤を掘削すると共に掘削土砂をスクリューによって到達側4に排出するように構成している一方、上記掘削推進機15は、推進ジャッキよりなる推進手段(図示せず)と上記掘削手段の回転駆動手段とを備えてなり、ガイド架台14上を発進側3に向かって移動自在に且つ移動後の位置に固定して鋼管5aの推進と掘削手段の回転駆動とを行えるように構成している。なお、鋼管5a内の掘削はスクリューオーガによることなく、人力によっても行うことができる。   A drilling means (not shown) made of a screw auger is removably inserted in the steel pipe 5a, and the face ground on the open end side of the steel pipe 5a facing the starting side 3 is excavated by the auger head. The excavation propulsion unit 15 includes propulsion means (not shown) made of a propulsion jack and rotation drive means for the excavation means. Thus, the guide frame 14 is configured to be movable toward the start side 3 and fixed to the position after the movement so that the steel pipe 5a can be propelled and the excavating means can be driven to rotate. In addition, excavation in the steel pipe 5a can be performed by human power without using a screw auger.

また、鋼管5a上に載置したフリクションカット板6はその発進側3に向けた先端を鋼管5aの先端に溶接またはボルト等によって固着してあり、この鋼管5aを上記掘削推進機15によって到達側4から発進側3に向かって軌道1下の地盤の上記所定高さ位置に推進、埋設したのち、この鋼管5aの一側面に沿って次の鋼管5aを同様にして掘削推進機15により推進、埋設する。鋼管5aの両側面における上下部には図7に示すように、互いに係合可能な間隔を存して断面L字状の上下一対の係合突条16、16:17、17をそれぞれ全長に亘って管軸方向に平行に突設してあり、到達側4から発進側3に向かって推進、埋設された鋼管5aの係合突条16、16に次の鋼管5aの対向側面に突設している係合突条17、17を係合させて互いに並列状態となるように該鋼管5aを推進、埋設する。   Further, the friction cut plate 6 placed on the steel pipe 5a has a tip directed toward the starting side 3 fixed to the tip of the steel pipe 5a by welding or a bolt or the like, and this steel pipe 5a is connected to the reaching side by the excavator 15. After propulsion and burying from 4 to the starting side 3 at the above-mentioned predetermined height position of the ground below the track 1, the next steel pipe 5a is similarly propelled by the excavating propulsion machine 15 along one side surface of this steel pipe 5a. Buried. As shown in FIG. 7, a pair of upper and lower engaging protrusions 16, 16: 17, 17 having an L-shaped cross section are provided at the upper and lower portions on both side surfaces of the steel pipe 5 a to the full length. Projecting parallel to the pipe axis direction, projecting from the reaching side 4 toward the starting side 3, projecting on the opposite side of the next steel pipe 5a on the engaging ridges 16 and 16 of the steel pipe 5a The steel pipe 5a is propelled and embedded so that the engaging protrusions 17 and 17 engaged with each other are engaged to be in a parallel state.

なお、地下構造物2の埋設計画域の長さ、即ち、発進側3と到達側4との間の距離が鋼管5aの数倍の長さである場合には、その距離を数分割した長さを有する鋼管5aを順次、直列状に継ぎ足しながら且つ先頭の鋼管5a上のフリクションカット板6のみを該鋼管5aの先端にその先端を固着する一方、継ぎ足すことによって一体に連結される前後鋼管5a、5a上のフリクションカット板6、6を互いに溶接によってあたかも一枚のフリクションカット板となるように一体に連結しながら、掘削推進機15によって推進、埋設する。こうして、先端が発進側3に達した鋼管5aを複数本、並列状態に埋設することによって、図3に示すように、軌道下の地盤7の地下構造物埋設計画域における地下構造物2の上床部2aの埋設高さ位置に相当する部分に地下構造物2と略同幅のパイプルーフ5を形成する。   In addition, when the length of the buried design area of the underground structure 2, that is, the distance between the start side 3 and the arrival side 4 is several times the length of the steel pipe 5a, the length obtained by dividing the distance into several parts The steel pipe 5a having a thickness is sequentially added in series, and only the friction cut plate 6 on the front steel pipe 5a is fixed to the tip of the steel pipe 5a while the front and rear steel pipes are integrally connected by adding them. The friction cut plates 6 and 6 on 5a and 5a are propelled and buried by the excavator 15 while being integrally connected to each other so as to form one friction cut plate by welding. In this way, by embedding a plurality of steel pipes 5a whose tips reach the starting side 3 in parallel, as shown in FIG. 3, the upper floor of the underground structure 2 in the underground structure embedding design area of the ground 7 under the track. A pipe roof 5 having substantially the same width as that of the underground structure 2 is formed at a portion corresponding to the buried height position of the portion 2a.

このように、到達側4において、該到達側4から発進側3に達するパイプルーフ5の形成作業を行う一方、発進側3においては、このパイプルーフ5の形成作業に並行して地下構造物2を発進側3から到達側4に向かって推進、埋設するための準備作業を行う。具体的には、到達側4で鋼管5aのガイド架台14の配置作業やガイド架台14上への掘削推進機15の配設作業、この掘削推進機15による複数本の鋼管5aの推進、埋設作業等の作業を行っている間に、発進側3において、地下構造物2を築造する場合にはその型枠の組立作業、型枠内への配筋作業、コンクリートの打設、養生、地下構造物2の推進装置8の設置作業等を行う。   In this way, on the arrival side 4, the pipe roof 5 reaching from the arrival side 4 to the start side 3 is formed, while on the start side 3, the underground structure 2 is parallel to the pipe roof 5 formation operation. Preparatory work for propelling and burying the vehicle from the start side 3 toward the arrival side 4 is performed. Specifically, the guide side 14 of the steel pipe 5a is arranged on the arrival side 4, the excavation propulsion unit 15 is arranged on the guide base 14, and the plural pipes 5a are propelled and buried by the excavation propulsion unit 15. When building the underground structure 2 on the start side 3 during the work, etc., the assembly work of the formwork, the rebaring work in the formwork, concrete placement, curing, underground structure Installation work of the propulsion device 8 for the object 2 is performed.

なお、地下構造物2はプレキャストコンクリート構造物からなる場合は、上記パイプルーフ5の形成作業と並行して該地下構造物2の発進側3内への搬入、据え付け作業、複数本の推進ジャッキからなる推進装置8の設置作業等の地下構造物2の推進、埋設の準備作業を行う。また、パイプルーフ5の両側に、地下構造物2の推進、埋設時における該地下構造物2の両側上方の地盤の安定を図るために、到達側4から複数本の断面円形の張出鋼管5b(図3に示す)を並列状に埋設しておく。この張出鋼管5bは地下構造物2の推進、埋設時にも地中に残しておくものである。   When the underground structure 2 is made of a precast concrete structure, the underground structure 2 can be carried into the start side 3 in parallel with the pipe roof 5 forming operation, installed, and a plurality of propulsion jacks can be used. The propulsion of the underground structure 2 such as the installation work of the propulsion device 8 and preparation work for burial are performed. Further, in order to stabilize the ground above both sides of the underground structure 2 at the time of propulsion and burial of the underground structure 2 on both sides of the pipe roof 5, a plurality of circular steel pipes 5b having a circular cross section from the arrival side 4 are provided. (Shown in FIG. 3) are embedded in parallel. This overhanging steel pipe 5b is left in the ground when the underground structure 2 is propelled and buried.

パイプルーフ5の形成作業と地下構造物2の推進、埋設の準備作業とが完了すると、次に、地下構造物2の推進、埋設作業に移る。この際、予め、発進側3に突出しているパイプルーフ5の全ての鋼管5aの先端からフリクションカット板6の先端の固着を解いて全てのフリクションカット板6の先端を図4に示すように、発進側3後方の土留工10等の不動地点に固定材19を介して固定しておくと共に到達側4においてはガイド架台14を撤去しておく。また、地下構造物2における到達側4に向けた前端開口部(到達側方向を前側とする)に刃口9を装着しておく。   When the work for forming the pipe roof 5, the promotion of the underground structure 2, and the preparation work for the burial are completed, the process proceeds to the promotion and burial of the underground structure 2. At this time, as shown in FIG. 4, the tips of the friction cut plates 6 are released from the tips of all the steel pipes 5a of the pipe roof 5 protruding to the starting side 3 in advance. The guide frame 14 is removed on the arrival side 4 while being fixed to a fixed point such as the earth retaining work 10 behind the start side 3 via a fixing member 19. Moreover, the blade edge 9 is attached to the front end opening (the arrival side direction is the front side) facing the arrival side 4 in the underground structure 2.

しかるのち、地下構造物2の後端と発進側3の後壁面との間に設置した上記推進装置8を構成している複数本の推進ジャッキを伸長させて地下構造物2を軌道1下の埋設計画域に向かって推進し、刃口9を地盤に圧入すると共に地下構造物2の上床部2aの上面がパイプルーフ5上のフリクションカット板6の下面に接するように該上床部2aの前端面をパイプルーフ5の後端面(突出端面)に押し付けた状態にして埋設計画域に埋設していく。   After that, the plurality of propulsion jacks constituting the propulsion device 8 installed between the rear end of the underground structure 2 and the rear wall surface of the start side 3 are extended to move the underground structure 2 below the track 1. The front end of the upper floor 2a is pushed toward the buried design area, press-fitting the blade 9 into the ground, and the upper surface 2a of the underground structure 2 is in contact with the lower surface of the friction cut plate 6 on the pipe roof 5. The surface is pressed against the rear end surface (projecting end surface) of the pipe roof 5 and embedded in the embedded design area.

推進装置8の推進ジャッキを伸長させると共に地下構造物2の前方地盤を掘削しながら地下構造物2を軌道下の地盤7中における埋設計画域に一定長、推進、埋設させると、パイプルーフ6を形成している全ての鋼管5aがその推進長に応じた長さだけ到達側4に押し出されるので、その長さ部分を撤去する。また、地下構造物2が一定長、推進、埋設させられる毎に、推進装置8の推進ジャッキのピストンロッドを収縮させると共に推進装置8と発進側3の後壁面との埋設計画域に反力受スペーサ18を介在させて図5に示すように、再び推進ジャッキを伸長させることにより地下構造物2を推進させる。なお、地下構造物2によって築造すべき地下道の長さが長い場合には、地下道の長さを複数分割した長さを有する地下構造物を順次、接続しながら推進、埋設させればよい。   When the propulsion jack of the propulsion device 8 is extended and the underground structure 2 is excavated in front of the underground structure 2 and is propelled and buried in the buried design area in the ground 7 under the track, the pipe roof 6 is Since all formed steel pipes 5a are pushed out to the reaching side 4 by a length corresponding to the propulsion length, the length portion is removed. Further, every time the underground structure 2 is propelled and buried for a certain length, the piston rod of the propulsion jack of the propulsion device 8 is contracted and the reaction force is received in the buried design area between the propulsion device 8 and the rear wall of the start side 3. As shown in FIG. 5 with the spacer 18 interposed, the propulsion jack is extended again to propel the underground structure 2. In addition, when the length of the underground passage to be built by the underground structure 2 is long, the underground structure having a length obtained by dividing the length of the underground passage may be promoted and buried while sequentially connecting.

こうして、フリクションカット板6の下面に沿って軌道1下の地盤7中に発進側3から到達側4に貫通した地下構造物2を埋設して地下道を構築する。しかるのち、図6に示すように発進側3と到達側において、ベースコンクリート12、13をそれぞれ撤去したのち、発進側3内と到達側内とを埋め戻しすることによって地下構造物2内の通路の両開口端から地上に達するスロープ20、21をそれぞれ形成して地下構造物2からなる地下道の施工作業を完了する。   Thus, the underground passage 2 is constructed by burying the underground structure 2 penetrating from the start side 3 to the arrival side 4 in the ground 7 below the track 1 along the lower surface of the friction cut plate 6. After that, as shown in FIG. 6, the base concrete 12 and 13 are removed on the starting side 3 and the reaching side, respectively, and then the inside of the starting side 3 and the inside of the reaching side are backfilled, thereby passing the passage in the underground structure 2 Slopes 20 and 21 that reach the ground from both open ends are respectively formed, and the construction work of the underground passage composed of the underground structure 2 is completed.

なお、側壁ルーフとして、図8に示すように、丸形鋼管5bを複数本、縦方向に並列状に埋設することによって形成しておいてもよい。この場合、この側壁ルーフ5Bは、地下構造物2の両側壁部2b、2bに対応する部分に埋設しておくのではなく、該地下構造物2の両側壁部2b、2bの外側に両側壁部2b、2bを挟むようにして埋設する。そして、埋設計画域に地下構造物2を埋設したのちも撤去しなくてもよい。 As shown in FIG. 8 , the side wall roof may be formed by embedding a plurality of round steel pipes 5b in parallel in the vertical direction. In this case, the side wall roof 5B is not embedded in the portion corresponding to the both side wall portions 2b, 2b of the underground structure 2, but the both side walls are formed outside the both side wall portions 2b, 2b of the underground structure 2. It is buried so as to sandwich the parts 2b and 2b. And after burying underground structure 2 in a buried design area, it is not necessary to remove.

この丸形鋼管5bは上記のように地下構造物2の両側壁部2b、2bの外側方に位置する地盤中に縦方向に埋設するものであるから、上記到達側4からのパイプルーフ5の形成作業に並行して発進側3側で行われる地下構造物2の推進、埋設の準備作業に殆ど影響を及ぼすことがないので、立坑の深さが到達側4よりも深い発進側3を利用して該発進側3から到達側4に向かって推進、埋設することできる。 Since the round steel pipe 5b is buried in the vertical direction in the ground located outside the both side walls 2b, 2b of the underground structure 2 as described above, the pipe roof 5 from the arrival side 4 is Uses start side 3 where the depth of the shaft is deeper than the arrival side 4 because it has little effect on the propulsion and burial preparation work of the underground structure 2 performed on the start side 3 side in parallel with the formation work to driven towards reaching side 4 from the start side 3, it can be embedded.

軌道の両側に発進側と到達側とを設けた状態の簡略縦断側面図。The simplified vertical side view of the state which provided the start side and the arrival side on both sides of the track. パイプルーフを形成している状態の簡略縦断側面図。The simplified vertical side view of the state which forms the pipe roof. パイプルーフの簡略縦断正面図。The simplified longitudinal front view of a pipe roof. 地下構造物の推進、埋設を行う直前状態を示す簡略縦断側面図。The simplified vertical side view showing the state immediately before the underground structure is promoted and buried. 地下構造物を推進、埋設している状態のの簡略縦断側面図。A simplified longitudinal side view of a state where an underground structure is propelled and buried. 地下道を形成した状態の簡略縦断側面図。The simplified longitudinal side view of the state that formed the underpass. 鋼管の縦断正面図。The longitudinal front view of a steel pipe. 本発明の変形例を示す簡略縦断正面図。The simplified vertical front view which shows the modification of this invention.

符号の説明Explanation of symbols

1 軌道
2 地下構造物
3 発進側
4 到達側
5 パイプルーフ
5a 鋼管
6 フリクションカット板
8 推進装置
15 掘削推進機
1 Track 2 Underground structure 3 Starting side 4 Arrival side 5 Pipe roof
5a Steel pipe 6 Friction cut plate 8 Propulsion device
15 Excavator

Claims (1)

地下構造物の埋設計画域を挟んだ両側に地下構造物の発進側立坑と到達側立坑とを設け、これらの発進側立坑と到達側立坑間を貫通するように埋設計画域の地盤内に、上面にフリクションカット板を載置した複数本の鋼管を互いに並列させた状態となるように推進、埋設してパイプルーフを形成したのち、上記フリクションカット板を不動状態にしてこのフリクションカット板の下面に沿って地下構造物を前進させてパイプルーフと地下構造物とを置換させながら地下構造物を道路又は軌道の直下の地盤に埋設する方法において、上記発進側立坑の深さを地下構造物の推進、埋設作業が可能な深さにする一方、到達側立坑の深さを発進側立坑よりも深さが浅くて上記パイプルーフを形成するための鋼管が推進、埋設可能な深さに形成したのち、上記上面にフリクションカット板を載置した複数本の鋼管を上記到達側立坑から発進側立坑に向かって推進、埋設させることによりパイプルーフを形成する一方、このパイプルーフの施工中に上記発進側立坑において地下構造物の前進、埋設の準備作業を行い、しかるのち、フリクションカット板の下面に沿って地下構造物を埋設計画域に向かって推進し、この地下構造物の推進に従ってその推進長に応じた長さだけ上記深さの浅い到達側立坑に押し出される鋼管の長さ部分を撤去しながら発進側立坑から到達側立坑に貫通するように地下構造物を埋設することを特徴とする地下構造物の埋設施工方法。 In the underground structure, the start side shaft and the arrival side shaft are provided on both sides of the buried design area, and the ground of the buried design area so as to penetrate between the start side shaft and the arrival side shaft , After the pipe roof is formed by propelling and embedding a plurality of steel pipes on which the friction cut plates are placed in parallel with each other, the bottom surface of the friction cut plates is made with the friction cut plates fixed. The underground structure is embedded in the ground directly under the road or track while the underground structure is moved forward along the pipe roof and the underground structure is replaced . While making the depth possible for propulsion and embedding work, the steel pipe for forming the pipe roof is formed to a depth that allows propulsion and embedding because the depth of the arrival side shaft is shallower than the start side shaft. later Promoting a plurality of steel pipes mounted with the friction-cut plate to the upper surface toward the starting side pit from the arrival side pit, while forming a pipe roof by embedding, the starting side pit during construction of the pipe roof Then, the underground structure is advanced and the preparation work for burial is carried out, and then the underground structure is propelled along the lower surface of the friction cut plate toward the buried design area. Underground structure characterized in that underground structure is buried so as to penetrate from start side shaft to reaching side shaft while removing the length of steel pipe pushed out to reach side shaft with shallow depth above Burial method.
JP2004291833A 2004-10-04 2004-10-04 Underground construction method Active JP4073428B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004291833A JP4073428B2 (en) 2004-10-04 2004-10-04 Underground construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004291833A JP4073428B2 (en) 2004-10-04 2004-10-04 Underground construction method

Publications (2)

Publication Number Publication Date
JP2006104744A JP2006104744A (en) 2006-04-20
JP4073428B2 true JP4073428B2 (en) 2008-04-09

Family

ID=36374797

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004291833A Active JP4073428B2 (en) 2004-10-04 2004-10-04 Underground construction method

Country Status (1)

Country Link
JP (1) JP4073428B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102031736A (en) * 2010-06-12 2011-04-27 中铁十六局集团有限公司 Construction technology for under-passing existing line under complicated geological condition
CN111305847A (en) * 2019-12-06 2020-06-19 中国人民解放军军事科学院国防工程研究院工程防护研究所 Dynamic ultimate strength control method for ultra-shallow-buried underground excavation construction of urban underground engineering

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100794810B1 (en) 2006-05-01 2008-01-15 주식회사 도화종합기술공사 Excavation method of road and railroad lower part using deck unit jacking
JP4759532B2 (en) * 2007-03-23 2011-08-31 株式会社奥村組 Widening method of existing underground structure
JP5175559B2 (en) * 2008-01-10 2013-04-03 鹿島建設株式会社 Box propulsion method with roof protection
JP5188383B2 (en) * 2008-12-25 2013-04-24 株式会社奥村組 Box thrust transmission member and method of constructing underground structure using the same
KR101348785B1 (en) * 2013-05-08 2014-01-15 (주)나우기술 Underground space development of methods for the construction of high-speed rail line and close
KR101408667B1 (en) 2014-02-26 2014-06-17 김동수 Method of constructing new tunnel using pre-existing tunnel structure
CN113530557A (en) * 2021-08-09 2021-10-22 中建一局集团建设发展有限公司 Subway transfer passage structure without receiving well and construction method
CN114352804B (en) * 2022-03-17 2022-06-24 中铁九局集团第四工程有限公司 Construction method for underground small-space corrugated pipe to pass through pipeline by using track pulley
CN115492161B (en) * 2022-07-01 2023-11-14 上海建工一建集团有限公司 Construction method for building basement storey-adding three-side surrounding pipe curtain of existing building

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102031736A (en) * 2010-06-12 2011-04-27 中铁十六局集团有限公司 Construction technology for under-passing existing line under complicated geological condition
CN111305847A (en) * 2019-12-06 2020-06-19 中国人民解放军军事科学院国防工程研究院工程防护研究所 Dynamic ultimate strength control method for ultra-shallow-buried underground excavation construction of urban underground engineering

Also Published As

Publication number Publication date
JP2006104744A (en) 2006-04-20

Similar Documents

Publication Publication Date Title
JP4073428B2 (en) Underground construction method
JP2007284895A (en) Underground railway construction method
JP4698458B2 (en) Construction method for underground structures
JP4350113B2 (en) Box roof used in the construction method of underground structures
KR101156613B1 (en) The Construction Method of Shield Tunneling for long distacne
KR101351784B1 (en) Underground structure construction method using the cutting channel
JPH01304297A (en) Reconstruction of existing underground structure
CN108979641B (en) Construction method for underground structure
JP4698459B2 (en) Construction method for underground structures
CN110295616B (en) Open caisson construction method
JPH073155B2 (en) How to build an underground structure
JPH0415360B2 (en)
JP2007154571A (en) Pipe for pipe roof
JP4599303B2 (en) Underpass construction method
JPH07197781A (en) Propulsion guide member for underground structure and burying method for the structure
JP3070919B2 (en) Tunnel lining method and drilling equipment
JP4557918B2 (en) Pipe roof construction equipment
JP5976728B2 (en) Widening method for existing structures
JP3245529B2 (en) Method of forming roof for building underground structures
JP2013217160A (en) Open shield machine utilizing concrete box body and open shield method
KR102191503B1 (en) The Tunnel construction method to use retangular pipe
JP3131118B2 (en) Shell construction method for underground structures
JP4874290B2 (en) Steel shell element construction method
JP3946720B2 (en) How to bury underground structures
JP3105744B2 (en) Pipe roof and construction method

Legal Events

Date Code Title Description
A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070130

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070330

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20070717

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070914

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20071009

A911 Transfer to examiner for re-examination before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A911

Effective date: 20071012

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20071225

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080122

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110201

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 4073428

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140201

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250