KR100691664B1 - Method of construction for girder bridge - Google Patents

Method of construction for girder bridge Download PDF

Info

Publication number
KR100691664B1
KR100691664B1 KR1020040053886A KR20040053886A KR100691664B1 KR 100691664 B1 KR100691664 B1 KR 100691664B1 KR 1020040053886 A KR1020040053886 A KR 1020040053886A KR 20040053886 A KR20040053886 A KR 20040053886A KR 100691664 B1 KR100691664 B1 KR 100691664B1
Authority
KR
South Korea
Prior art keywords
bridge
girder
main beam
cable
wired
Prior art date
Application number
KR1020040053886A
Other languages
Korean (ko)
Other versions
KR20050018589A (en
Inventor
구로사와료헤이
다나베게이조
야마다후미오
쓰키마치다카노부
Original Assignee
구로사와 겐세츠 가부시키가이샤
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 구로사와 겐세츠 가부시키가이샤 filed Critical 구로사와 겐세츠 가부시키가이샤
Publication of KR20050018589A publication Critical patent/KR20050018589A/en
Application granted granted Critical
Publication of KR100691664B1 publication Critical patent/KR100691664B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/02Bridges characterised by the cross-section of their bearing spanning structure of the I-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed
    • E01D2101/285Composite prestressed concrete-metal

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 발명은, 브리지 거더(bridge girder)의 스팬(span)을 크게 하는 한편, 거더 높이를 작게 할 수 있는 거더 브리지(girder bridge)의 구축 방법을 제공하는 것이다.The present invention provides a method for constructing a girder bridge which can increase the span of the bridge girder and reduce the height of the girder.

본 발명의 거더 브리지의 구축 방법은, 양 단부에 지지압 플랜지(7)를 구비한 복수개의 빔재 유닛(3)을 길이 방향으로 접합판(11)을 개재하여 접합하는 동시에, 길이 방향으로 배선한 내부 케이블(5)을 소정의 힘으로 긴장(緊張)시켜 프리스트레스(prestress)를 부여한 주빔(principal beam)(1)을 형성하고, 상기 주빔(1)의 양 단부에 있어서의 정착 플레이트(12) 사이에, 빔재 유닛의 지지압 플랜지(7)를 관통시켜 외부 케이블(14)을 배선한 후, 이 주빔(1)을 교대(橋臺)(2) 사이에, 폭방향으로 적당한 간극부(16)를 두고 복수개 설치하고, 상기 간극부(16)를 현장 치기(cast-in-place) 콘크리트(17) 또는 프리캐스트(precast) 콘크리트 부재(18)로 막아 브리지 거더(21)를 형성하고, 상기 브리지 거더(21)의 폭방향으로 배선한 횡 케이블(20)에 의해 주빔(1)을 결속한 후, 외부 케이블(14)을 소정의 힘으로 긴장시켜 브리지 거더(21) 전체에 프리스트레스를 부여하는 것이다.In the method for constructing the girder bridge of the present invention, a plurality of beam material units (3) having support pressure flanges (7) at both ends are joined to each other via a joining plate (11) in the longitudinal direction, and wired in the longitudinal direction. The inner cable 5 is tensioned with a predetermined force to form a principal beam 1 to which prestress is applied, and between the fixing plates 12 at both ends of the main beam 1. After passing through the support pressure flange 7 of the beam material unit to wire the external cable 14, the main beam 1 is alternately arranged between the bridges 2 in the widthwise direction 16. And a plurality of plural and the gap portion 16 is blocked by cast-in-place concrete 17 or precast concrete member 18 to form a bridge girder 21, and the bridge After binding the main beam 1 with the horizontal cable 20 wired in the width direction of the girder 21, the external cable 14 is disconnected. Positive tension is applied to prestress the entire bridge girder 21.

거더 브리지, 프리스트레스, 빔재 유닛, 주빔, 브리지 거더Girder bridge, prestress, beam ash unit, main beam, bridge girder

Description

거더 브리지의 구축 방법 {METHOD OF CONSTRUCTION FOR GIRDER BRIDGE}How to Build a Girder Bridge {METHOD OF CONSTRUCTION FOR GIRDER BRIDGE}

도 1은 주빔의 수평 방향의 단면도이다.1 is a cross-sectional view in the horizontal direction of the main beam.

도 2는 내부 케이블을 배선한 주빔의 정면도이다.2 is a front view of the main beam in which the internal cable is wired.

도 3은 빔재 유닛의 단면도이다.3 is a cross-sectional view of the beam material unit.

도 4는 (1)은 빔재 유닛의 접합부의 정면도, (2)는 동 평면도이다.4: (1) is a front view of the junction part of a beam material unit, (2) is a top view.

도 5는 (1)은 외부 케이블을 배선한 주빔의 정면도, (2)는 빔재 유닛의 접합부의 수평 방향의 단면도, (3)은 빔재 유닛의 접합부의 정면도이다.5 is a front view of the main beam in which the external cable is wired, 2 is a sectional view in the horizontal direction of the junction of the beam material unit, and 3 is a front view of the junction of the beam material unit.

도 6은 외부 케이블의 단부를 정착시킨 빔재 유닛의 단면도이다.6 is a cross-sectional view of the beam material unit in which the end of the external cable is fixed.

도 7은 (1)은 빔재 유닛을 교대 사이에 설치한 정면도, (2)는 동 수평 방향의 단면이다.FIG. 7: (1) is a front view which installed the beam material unit between turns, (2) is a cross section of the same horizontal direction.

도 8은 브리지 거더의 횡단면도이다.8 is a cross-sectional view of the bridge girder.

도 9는 도 8의 확대도이다.9 is an enlarged view of FIG. 8.

도 10은 (1)은 연속된 거더 브리지의 정면도, (2)는 동 수평 방향 단면도이다.(1) is a front view of a continuous girder bridge, (2) is sectional drawing in the same horizontal direction.

도 11은 (1)은 내부 케이블을 배선한 주빔의 정면도, (2)는 외부 케이블을 배선한 주빔의 정면도이다.11 is a front view of the main beam in which the internal cable is wired, and (2) a front view of the main beam in which the external cable is wired.

도 12는 주빔의 접합부의 단면도이다.12 is a sectional view of the junction of the main beam.

도 13은 (1)은 한 개의 외부 케이블을 배선한 주빔의 정면도, (2)는 주빔의 접합부의 단면도이다.Fig. 13 is a front view of the main beam in which one external cable is wired, and Fig. 2 is a sectional view of the junction of the main beam.

도 14는 종래의 거더 브리지의 정면도이다.14 is a front view of a conventional girder bridge.

본 발명은 거더 브리지의 구축 방법에 관한 것이다.The present invention relates to a method for constructing a girder bridge.

종래의 거더 브리지로서는, 예를 들면 일본국 특개 2003-213622호 공보의 발명이 있다. 또, 도 14에 나타낸 바와 같이, 주빔(principal beam)(30)이 폭방향으로 결속되어 형성된 브리지 거더(31)가 교대(橋臺;abutment)(32) 사이에 설치되고, 그 중앙부가 교각(pier)(33)에 의해 지지된 거더 브리지(34)가 있다.As a conventional girder bridge, there exists invention of Unexamined-Japanese-Patent No. 2003-213622, for example. As shown in Fig. 14, a bridge girder 31 formed by binding a principal beam 30 in the width direction is provided between the abutments 32, the center portion of which is a bridge ( There is a girder bridge 34 supported by pier 33.

이 주빔(30)은 콘크리트제의 빔재 유닛(35)이 길이 방향으로 접속되어 형성되어 있다. The main beam 30 is formed by connecting a beam material unit 35 made of concrete in the longitudinal direction.

그러나, 상기와 같은 거더 브리지의 스팬은, 브리지 거더의 자중에 의한 벤딩 모멘트가 증대하기 때문에 30~40m가 한계로 되어 있었다. 또한, 거더 높이 스팬(span)비(거더의 높이:가로폭)의 한계가 1/17.5이기 때문에, 거더 높이가 제한되어 있는 개소에 있어서 구축이 곤란했었다.However, the span of the girder bridge as described above has a limit of 30 to 40 m because the bending moment due to the weight of the bridge girder increases. In addition, since the limit of the girder height span ratio (height of the girder: the width of the girder) was 1 / 17.5, it was difficult to construct at the point where the girder height was limited.

본 발명은 상기와 같은 문제점을 감안하여 이루어진 것으로서, 그 목적은, 브리지 거더의 스팬을 크게 하는 한편, 거더 높이를 작게 할 수 있는 거더 브리지 의 구축 방법을 제공하는 것이다.The present invention has been made in view of the above problems, and an object thereof is to provide a method for constructing a girder bridge which can increase the span of the bridge girder and reduce the height of the girder.

본 발명의 거더 브리지의 구축 방법은, 양 단부에 지지압 플랜지를 구비한 복수개의 빔재 유닛을 길이 방향으로 접합판을 개재하여 접합하는 동시에, 길이 방향으로 배선한 내부 케이블을 소정의 힘으로 긴장(緊張)시켜 프리스트레스(prestress)를 부여한 주빔을 형성하고, 상기 주빔의 양 단부에 있어서의 정착 플레이트 사이에 빔재 유닛의 지지압 플랜지를 관통시켜 외부 케이블을 배선한 후, 상기 주빔을 교대 사이에, 폭방향으로 적당한 간극부를 두고 복수개 설치하고, 상기 간극부를 현장 치기(cast-in-place) 콘크리트 또는 프리캐스트(precast) 콘크리트 부재로 막아 브리지 거더를 형성하고, 상기 브리지 거더의 폭방향으로 배선한 횡 케이블에 의해 주빔을 결속한 후, 외부 케이블을 소정의 힘으로 긴장시켜 브리지 거더 전체에 프리스트레스를 부여하는 것을 특징으로 한다.According to the construction method of the girder bridge of the present invention, a plurality of beam material units having support pressure flanges at both ends are joined to each other via a joining plate in the longitudinal direction, and the inner cable wired in the longitudinal direction is tensioned with a predetermined force ( After forming the main beam to give prestress, and through the supporting pressure flange of the beam material unit between the fixing plates in the both ends of the said main beam, and wiring an external cable, the said main beam is alternately widened. Transverse cables provided with a plurality of suitable gaps in the direction, the bridges being covered with cast-in-place concrete or precast concrete members to form bridge girders, and wired in the width direction of the bridge girders. After binding the main beams, the external cables are tensioned with a predetermined force to impart prestress to the entire bridge girder. The features.

또 거더 브리지의 구축 방법은, 양 단부에 지지압 플랜지를 구비한 복수개의 빔재 유닛을 길이 방향으로 접합판을 개재하여 접합하는 동시에, 길이 방향으로 배선한 내부 케이블을 소정의 힘으로 긴장시켜 프리스트레스를 부여한 주빔을 형성하고, 상기 주빔의 양 단부에 있어서의 정착 플레이트 사이에 빔재 유닛의 지지압 플랜지를 관통시켜 외부 케이블을 배선한 후, 상기 주빔을 교대 사이에, 폭방향으로 적당한 간극부를 두고 복수개 설치하고, 상기 간극부를 현장 치기 콘크리트 또는 프리캐스트 콘크리트 부재로 막아 브리지 거더를 형성하고, 상기 브리지 거더의 폭방향으로 배선한 횡 케이블에 의해 주빔을 결속한 후, 외부 케이블을 소정의 힘으 로 긴장된 브리지 거더를 교각 사이에 차례로 설치한 후, 이들 브리지 거더를 연결하는 것을 특징으로 한다.The girder bridge construction method includes joining a plurality of beam material units having support pressure flanges at both ends via a joining plate in the longitudinal direction, and tensioning the internal cable wired in the longitudinal direction with a predetermined force to reduce prestress. After forming the provided main beam, and passing the support pressure flange of the beam material unit between the fixing plates at both ends of the main beam to wire an external cable, a plurality of the main beams are provided with appropriate gaps in the width direction between the shifts. Bridge gaps are formed by blocking the gaps with the field-cut concrete or precast concrete members, and the main beams are bound by the transverse cables wired in the width direction of the bridge girders, and the external cables are tensioned with a predetermined force. Are installed between the piers in turn, and then these bridge girders are connected. Shall be.

스팬이 70m이며, 또한 거더 높이의 스팬비(거더의 높이)의 한계가 1/30정도의 거더 브리지를 구축할 수 있고, 외부 케이블에 의해 긴장력을 도입하여 긴장된 코드빔(tightening chord beam)으로 함으로써 전체가 일체로 된 좌굴(buckling)이 없고, 인성(靭性)이 높은 거더 브리지가 된다.Girder bridge with a span of 70m and a span ratio of girder height of about 1/30 can be constructed, and a tensioning chord beam is introduced by introducing tension by an external cable. There is no integral buckling, and it becomes a girder bridge with high toughness.

양 단부에 지지압 플랜지를 구비한 복수개의 빔재 유닛을 내부 케이블에 의해 접합하여 형성한 빔재를 교대 사이에, 폭방향으로 복수개 설치하여 브리지 거더를 형성하고, 상기 브리지 거더의 폭방향으로 배선한 횡 케이블에 의해 빔재를 결속한 후, 외부 케이블을 소정의 힘으로 긴장시켜 브리지 거더 전체에 프리스트레스를 부여함으로써, 브리지 거더의 스팬을 크게 하는 한편, 거더 높이가 작아진 거더 브리지를 구축할 수 있다.A plurality of beam materials formed by joining a plurality of beam material units provided with supporting pressure flanges at both ends by internal cables are alternately provided in the width direction between shifts to form a bridge girder, and the wires are wired in the width direction of the bridge girder. After the beam material is bound by the cable, the external cable is tensioned with a predetermined force to impart prestress to the entire bridge girder, thereby increasing the span of the bridge girder and constructing a girder bridge having a smaller girder height.

본 발명의 거더 브리지의 구축 방법을 단일 거더 브리지에 기초하여 설명한다. 이 거더 브리지의 구축 방법은, 도 1에 나타내는 주빔(1)을 교대(2) 사이에 설치하여 행하는 것이며, 처음에, 이 주빔(1)을 제작한다. 이 주빔(1)은, 도 2에 나타낸 바와 같이, 길이 방향으로 접합된 5개의 빔재 유닛(3)이 길이 방향으로 배선된 내부 케이블(5)에 의해 결속되어 제작되며, 이 내부 케이블(5)에 의해 소정의 프리스트레스가 부여되어 있다.The construction method of the girder bridge of this invention is demonstrated based on a single girder bridge. The construction method of this girder bridge is performed by providing the main beam 1 shown in FIG. 1 between the shifts 2, and manufactures this main beam 1 first. As shown in Fig. 2, the main beam 1 is produced by being bound by the inner cable 5 in which the five beam material units 3 joined in the longitudinal direction are wired in the longitudinal direction, and the inner cable 5 Predetermined prestress is given by.

또한, 내부 케이블(5)은, 도 2 및 도 3에 나타낸 바와 같이, 주빔(1)의 상하부에 전체 길이에 걸쳐 6개가 배선되는 동시에, 중앙부의 3개의 빔재 유닛(3)에 걸쳐 2개가 배선되어 있다. 이와 같이 주빔(1)의 상하부에 배선된 내부 케이블(5)의 긴장력과, 상부에 매설된 철골(鐵骨)(이하 철골이라고 함)(6)에 의해, 주빔(1)에 매달아 올린 하중이 발생하여 사하중(dead load)의 응력만큼 상쇄된다.In addition, as shown in FIGS. 2 and 3, six internal cables 5 are wired over the entire length of the main beam 1 over the entire length, and two wires over the three beam material units 3 in the center portion. It is. In this way, the load suspended on the main beam 1 by the tension of the inner cable 5 wired to the upper and lower parts of the main beam 1 and the steel frame (hereinafter referred to as steel frame) 6 embedded in the upper portion Generated and canceled out by the stress of the dead load.

또한, 빔재 유닛(3)은 양 단부에 지지압 플랜지(7)를 구비한 단면 I형의 콘크리트 블록이며, 상부에 2매의 L형 강판(8)으로 이루어지는 철골(6)이 매설되고, 이 철골(6)의 하면에 콘크리트(9)와 일체로 되도록 하는 스터드(stud) 볼트(10)가 돌출되어 있다. 또, 철골(6)의 양 단면에는, 도 4에 나타낸 바와 같이, 접합판(11)이 설치되는 동시에, 양 단부의 빔재 유닛(3)에 있어서의 철골(6)의 타단면에는 정착 플레이트(12)가 설치되어 있다. 이 접합판(11)이 전단(剪斷) 키(13)에 의해 접합되어 각 빔재 유닛(3)의 철골(6)들을 서로 1개로 연결하면, 마치 1개의 철골이 매설된 1개의 주빔(1)과 같이 된다.Moreover, the beam material unit 3 is a concrete block of cross section I type | mold provided with the support pressure flange 7 at both ends, and the steel frame 6 which consists of two L-shaped steel plates 8 is embedded in the upper part, A stud bolt 10 protrudes from the lower surface of the steel frame 6 so as to be integrated with the concrete 9. Moreover, as shown in FIG. 4, the joining plate 11 is provided in both end surfaces of the steel frame 6, and at the other end surface of the steel frame 6 in the beam material unit 3 of both ends, a fixing plate ( 12) is installed. When the joining plate 11 is joined by a shear key 13 to connect the steel frames 6 of each beam material unit 3 to each other, it is as if one main beam 1 is embedded with one steel frame. )

다음에, 도 5에 나타낸 바와 같이, 2개 1조의 외부 케이블(14)을 주빔(1)양측의 전체 길이에 걸쳐 배선한다. 이 외부 케이블(14)은 빔재 유닛(3)의 지지압 플랜지(7)의 관통공(4)을 관통하여 배선되고, 그 양 단부가 빔재 유닛의 정착 플레이트(12)에 정착되어 있다(도 6 참조). 또한, 이 외부 케이블(14)은 배선뿐이며, 아직도 긴장되어 있지 않다.Next, as shown in FIG. 5, two sets of external cables 14 are wired over the entire length of both sides of the main beam 1. This external cable 14 is routed through the through hole 4 of the support pressure flange 7 of the beam material unit 3, and both ends thereof are fixed to the fixing plate 12 of the beam material unit (FIG. 6). Reference). In addition, this external cable 14 is only wiring, and is not still tense.

이와 같이 내부 케이블(5)과 외부 케이블(14)이 배선된 주빔(1)이 완성된 후, 도 7에 나타낸 바와 같이, 이것을 크레인으로 매달아 올려 교대(2)사이에 설치한다. 그리고, 이 주빔(1)을 교대(2)의 폭방향으로 적당한 간극부(16)를 두고 6개 설치한다.Thus, after the main beam 1 which the inner cable 5 and the outer cable 14 were wired was completed, as shown in FIG. 7, it hangs with a crane and installs between the shifts 2, and so on. Then, six of the main beams 1 are provided with appropriate gaps 16 in the width direction of the alternate 2.

다음에, 이들 주빔 사이의 간극부(16)를 현장 치기 콘크리트(17) 또는 프리캐스트 콘크리트 부재(18)로 막아 소정 폭의 상판(床板)(19)을 형성한다.Next, the gap 16 between these main beams is blocked by the field-stretched concrete 17 or the precast concrete member 18 to form a top plate 19 having a predetermined width.

다음에, 도 8에 나타낸 바와 같이, 이 6개의 주빔(1)을 횡방향으로 배선한 횡 케이블(20)에 의해 결속하여 브리지 거더(21)를 형성한다. 이 브리지 거더(21)에는 횡 케이블(20)과 횡방향으로 소정의 프리스트레스가 부여된다.Next, as shown in FIG. 8, the bridge girder 21 is formed by binding these six main beams 1 by the horizontal cable 20 wired in the horizontal direction. The bridge girder 21 is provided with a predetermined prestress in the transverse direction with the transverse cable 20.

이 브리지 거더(21)가 완성되면, 각 주빔(1)의 외부 케이블(14)을 소정의 힘으로 긴장시켜 프리스트레스를 부여하면, 브리지 거더(21)가 긴장된 코드빔으로 되어 매달아 올린 하중이 주어져, 활하중(live load)에 대응한다. 이와 같이 브리지 거더(21) 전체(활하중분)가 일체로 되어 들어올릴 수 있으면, 좌굴이 없고 인성이 높은 거더 브리지(22)가 된다.When the bridge girder 21 is completed, when the external cable 14 of each main beam 1 is tensioned with a predetermined force to impart prestress, the bridge girder 21 becomes a tensioned cord beam and a suspended load is given. Corresponds to the live load. Thus, if the whole bridge girder 21 (live load part) can be lifted integrally, the girder bridge 22 without buckling and with high toughness will be provided.

다음에, 연속된 거더 브리지의 구축 방법에 대하여 설명한다. 이 연속거더 브리지의 구축 방법도, 상기의 단일 거더 브리지의 구축 방법과 대략 같고, 도 10에 나타낸 바와 같이, 주빔(1)을 교대(2)와 교각(26) 사이에 6개 설치하여 브리지 거더(21)(도 7과 같음)를 형성한 후, 다음의 교각(26) 사이에 상기와 같은 방법으로 같은 브리지 거더(21)를 형성한다. 그리고, 각 교각(26) 사이에 브리지 거더(21)를 차례로 형성한 후, 이 브리지 거더(21)들 사이를 서로 접합하여 연속거더 브리지(23)를 구축하는 것이다.Next, a method of constructing a continuous girder bridge will be described. The method of constructing the continuous girder bridge is also substantially the same as the method of constructing the single girder bridge. As shown in Fig. 10, six main beams 1 are provided between the alternating portions 2 and the pier 26 to form a bridge girder. After forming 21 (as shown in FIG. 7), the same bridge girders 21 are formed between the following piers 26 in the same manner as described above. The bridge girders 21 are sequentially formed between the bridge piers 26, and then the bridge girders 21 are joined to each other to form a continuous girder bridge 23.

상기의 주빔(1)은, 도 11에 나타낸 바와 같이, 상기의 도 2에 나타낸 것과 같고, 사하중에 대응하는 내부 케이블(5)과 활하중에 대응하는 외부 케이블(14)이 배선되어 있다.As shown in FIG. 11, the main beam 1 is the same as that shown in FIG. 2 above, and the inner cable 5 corresponding to the dead load and the outer cable 14 corresponding to the live load are wired.

이 브리지 거더(21)의 접합은, 각 주빔(1)들 사이를 서로 접합한 것이며, 도 12에 나타낸 바와 같이, 교각(26) 상에 설치된 주빔(1)의 철골(6)을 연결재(28)로 연결하는 동시에, 주빔(1)의 단부를 PC강봉(鋼棒)(29) 또는 PC케이블(29)과 접합한 후, 주빔(1) 사이에 현장 치기 콘크리트(27)를 타설하여 행한다.Bonding of the bridge girders 21 is a joint between the respective main beams 1, and as shown in FIG. 12, the steel frame 6 of the main beam 1 provided on the bridge 26 is connected to the connecting member 28. And the ends of the main beam 1 are joined to the PC steel bar 29 or the PC cable 29, and then the field-stretched concrete 27 is poured between the main beams 1.

또, 도 13은 상측의 외부 케이블을 1개의 장대한 외부 케이블(24)로 한 것이며, 상기와 같이 브리지 거더(21)를 서로 접합한 후, 이 접합한 브리지 거더(21)전체 길이에 걸쳐 장대한 외부 케이블(24)을 배선하고, 이것을 소정의 힘으로 긴장시켜 프리스트레스를 부여함으로써, 거더 브리지(22)의 활하중에 대응시키는 것이다.In addition, in FIG. 13, the external cable of the upper side is made into one massive external cable 24, and after joining the bridge girder 21 together as mentioned above, the pole is extended over the full length of this bonded bridge girder 21. As shown in FIG. One external cable 24 is wired and tensioned by a predetermined force to impart prestress to correspond to the live load of the girder bridge 22.

이러한 방법에 의해 좌굴이 없고 인성이 높은 거더 브리지를 구축할 수 있으므로, 45m 이상의 하천, 도로, 철도를 횡단하며, 또한 거더 높이가 제한되는 거더 브리지를 구축할 수 있다.In this way, a buckling-free, high-tough girder bridge can be constructed, and thus a girder bridge can be constructed that traverses rivers, roads, and railways of 45 m or more, and whose girder height is limited.

Claims (2)

삭제delete 양 단부에 지지압 플랜지를 구비한 복수개의 빔재 유닛을 길이 방향으로 접합판을 개재하여 접합하는 동시에, 길이 방향으로 배선한 내부 케이블을 소정의 힘으로 긴장(緊張)시켜 프리스트레스(prestress)를 부여한 주빔(principal beam)을 형성하고, 빔재 유닛의 상부에 매설된 철골을 연결재로 서로 연결하고, 상기 주빔의 양 단부에 있어서의 정착 플레이트 사이에 빔재 유닛의 지지압 플랜지를 관통시켜 외부 케이블을 배선하고, 상기 공정을 복수회 반복하여 복수개의 주빔을 작성한 후, 상기 복수개의 주빔을, 폭방향으로 적당한 간극부를 두고 교대(橋臺) 사이에 설치하고, 상기 주빔의 간극부를 현장 치기(cast-in-place) 콘크리트 또는 프리캐스트(precast) 콘크리트 부재로 막아 브리지 거더(bridge girder)를 형성하고, 상기 브리지 거더의 폭방향으로 배선한 횡 케이블에 의해 주빔을 결속한 후, 형성된 브리지 거더 내의 외부 케이블을 소정의 힘으로 긴장시켜 주빔에 프리스트레스를 부여하고,A main beam which is bonded to a plurality of beam material units having supporting pressure flanges at both ends via a joining plate in the longitudinal direction, and is prestressed by tensioning the inner cable wired in the longitudinal direction with a predetermined force. (principal beam) is formed, the steel frame embedded in the upper part of the beam material unit is connected to each other by a connecting material, and the external cable is wired through the supporting pressure flange of the beam material unit between the fixing plates at both ends of the main beam, After repeating the above process a plurality of times to produce a plurality of main beams, the plurality of main beams are provided between alternating bridges with appropriate gaps in the width direction, and cast-in-place the gaps of the main beams. ) Bridge girder formed by concrete or precast concrete member, and wired in the width direction of the bridge girder. After binding the main beam by the cable, the external cable in the formed bridge girder is tensioned with a predetermined force to impart prestress to the main beam, 상기 공정을 다음의 교대 사이에서 반복하여, 다음의 브리지 거더를 형성하고, 이어서 각 주빔의 철골을 연결재로 연결하는 동시에, 상기 주빔의 단부를 PC강봉(鋼棒) 또는 PC케이블과 접합하여 브리지 거더를 서로 접합한 후, 주빔 사이에 현장 치기 콘크리트를 타설하고, 접합한 연속된 브리지 거더의 전체 길이에 걸쳐 장대한 외부 케이블을 배선하고, 상기 장대한 외부 케이블을 긴장시켜 프리스트레스를 부여하는 것을 특징으로 하는 연속된 거더 브리지의 구축 방법.The process is repeated between the following shifts to form the next bridge girder, which then connects the steel frame of each main beam with a connecting material, and joins the ends of the main beam with a PC steel bar or PC cable to bridge bridging. Are bonded to each other, and then cast the field-stroke concrete between the main beams, wiring the grand external cable over the entire length of the continuous bridge girder bonded, and give the prestress by tensioning the grand external cable. How to build a continuous girder bridge.
KR1020040053886A 2003-08-08 2004-07-12 Method of construction for girder bridge KR100691664B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JPJP-P-2003-00290016 2003-08-08
JP2003290016A JP2005060964A (en) 2003-08-08 2003-08-08 Construction method for girder bridge

Publications (2)

Publication Number Publication Date
KR20050018589A KR20050018589A (en) 2005-02-23
KR100691664B1 true KR100691664B1 (en) 2007-03-09

Family

ID=34368168

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020040053886A KR100691664B1 (en) 2003-08-08 2004-07-12 Method of construction for girder bridge

Country Status (3)

Country Link
JP (1) JP2005060964A (en)
KR (1) KR100691664B1 (en)
CN (1) CN1580412A (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7827642B2 (en) * 2004-09-25 2010-11-09 Han Man-Yop Hollow prestressed concrete (HPC) girder and spliced hollow prestressed concrete girder (s-HPC) bridge construction method
JP4739072B2 (en) * 2006-03-15 2011-08-03 オリエンタル白石株式会社 Girder structure and construction method when multiple simple girder bridges are used as one simple girder bridge
JP2009041271A (en) * 2007-08-09 2009-02-26 Ps Mitsubishi Construction Co Ltd Construction method for bridge
JP2009041272A (en) * 2007-08-09 2009-02-26 Ps Mitsubishi Construction Co Ltd Construction method for bridge
CN104674650B (en) * 2015-02-16 2016-05-25 西安公路研究院 Based on bridge floor seamless process retractor device and the construction method thereof of the type transverse joint plate of putting more energy into
CN108265620A (en) * 2018-04-10 2018-07-10 深圳市市政设计研究院有限公司 The Integral Abutment construction method and Integral Abutment of jointless bridge

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20000012533A (en) * 1999-12-10 2000-03-06 김근택 A psc beam having above typed anchor blocks and connecting method thereof
KR20030052239A (en) * 2001-12-20 2003-06-26 구로사와 겐세츠 가부시키가이샤 Girder bridge

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20000012533A (en) * 1999-12-10 2000-03-06 김근택 A psc beam having above typed anchor blocks and connecting method thereof
KR20030052239A (en) * 2001-12-20 2003-06-26 구로사와 겐세츠 가부시키가이샤 Girder bridge

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
1020000012533 *
1020030052239 *

Also Published As

Publication number Publication date
CN1580412A (en) 2005-02-16
KR20050018589A (en) 2005-02-23
JP2005060964A (en) 2005-03-10

Similar Documents

Publication Publication Date Title
KR101012759B1 (en) Box Girder Having Hybrid Cantilever and Bridge Using Such Box Girder
KR100349864B1 (en) The Structural Continuity Method for Prestreseed Concrete Bridge of Composite I-Beam
KR101318773B1 (en) T-shaped composite girder segment integrated by i-shaped girder filled with concrete and slab and construction method of slab by prefabrication of the t-shaped composite girder segment
KR101366903B1 (en) Girder having truss section and construction method of bridge and pedestrian overpass using it
KR100982974B1 (en) Method for manufacturing multi-span continuous re-prestressed preflex composite bridge
KR101242842B1 (en) Construction method for corrugated steel plate web-psc composite beam
KR20160012672A (en) Precast modular bridge and its construction method
KR100936944B1 (en) Continuity Girder, Continuity Structure of Girder and Construction Method of the Same
KR101200563B1 (en) A Steel Composite Bridge Having Steel Plates Connected by Using Concrete Cross Beams and Its Constructing Method
JP2001182016A (en) Construction method of truss structure bridge
KR100691664B1 (en) Method of construction for girder bridge
JP3737475B2 (en) Box girder bridge structure and construction method
KR101688517B1 (en) Continuous bridge construction method using support pier girder and continuous tendon of pier
KR101693266B1 (en) Hybrid girder
KR100767145B1 (en) Construction method of prestressed concrete temporary bridge that can be assembled and dismantled using lateral steel wire
JP2004068286A (en) Laying method for steel pc composite bridge
KR100393132B1 (en) Construction method of composite steel-box bridge using prestress
JP3703760B2 (en) Girder bridge
KR100458046B1 (en) Struture for continuing intermediate support of compositive girder bridge
KR101228107B1 (en) A integral abutment continuous composite bridge using precast girder and the construction method thereof
KR20150083446A (en) Construction methods for bridges of rahmen types by using precast P.S girder and steel box girder
KR101182541B1 (en) Multi-Span Continuous Prestressed Concrete I-Girder Bridges and Construction Method of Such Bridges
KR100720997B1 (en) Continuous bridge construction method using concrete slab
KR102536770B1 (en) Prestressed composite girder made of steel and concrete and method thereof
KR102471342B1 (en) Steel-concrete girder and construction method thereof

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20121122

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20131120

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20141202

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20151116

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20161111

Year of fee payment: 15