KR101228107B1 - A integral abutment continuous composite bridge using precast girder and the construction method thereof - Google Patents

A integral abutment continuous composite bridge using precast girder and the construction method thereof Download PDF

Info

Publication number
KR101228107B1
KR101228107B1 KR1020110055686A KR20110055686A KR101228107B1 KR 101228107 B1 KR101228107 B1 KR 101228107B1 KR 1020110055686 A KR1020110055686 A KR 1020110055686A KR 20110055686 A KR20110055686 A KR 20110055686A KR 101228107 B1 KR101228107 B1 KR 101228107B1
Authority
KR
South Korea
Prior art keywords
precast
girder
bridge
precast girder
concrete
Prior art date
Application number
KR1020110055686A
Other languages
Korean (ko)
Other versions
KR20120136639A (en
Inventor
박영희
구화원
Original Assignee
구호원
박영희
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 구호원, 박영희 filed Critical 구호원
Priority to KR1020110055686A priority Critical patent/KR101228107B1/en
Publication of KR20120136639A publication Critical patent/KR20120136639A/en
Application granted granted Critical
Publication of KR101228107B1 publication Critical patent/KR101228107B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/04Bearings; Hinges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 발명은 프리캐스트 거더를 이용한 교대 일체형 연속 합성형교 및 그 시공법에 관한 것으로, 2경간 이상의 연속 합성형교에서 교각부 내측지점에서 발생되는 부모멘트에 대해서는 내측지점의 1차 상승 및 하강에 의해 압축력을 도입시키고, 교대부 외측지점에서 발생되는 부모멘트에 대해서는 내측지점을 일부 다시 2차 상승시켜 압축력을 도입시킴으로써, 종래 시공법에서 도입시킬 수 없었던 교대 상부 슬래브 콘크리트에 압축력을 도입시킬 수 있기 때문에 구조적으로 안전한 교량의 건설을 이룰 수 있어 모멘트 분배 효과를 크게 하여 활하중에 의한 진동감소 효과와 내진성을 향상시킬 수 있다. 또한, 외력에 의해 발생되는 모멘트가 일체화된 교대에 분배됨으로써 프리캐스트 거더의 외력에 대한 부담이 감소되어 프리캐스트 거더의 형고와 지간장 면에서 각각 약 20% 정도의 감소효과 또는 연장효과를 기대할 수 있어 경제적인 교량의 시공을 이룰 수 있다. 또한 2차 상승 공정에 의해 교대부 상부 슬래브 및 기초 하부 콘크리트에 도입되는 프리스트레싱(압축력 및 인장력)은 일반 라멘 구조물의 교대에서 발생하는 부모멘트와 정모멘트에 반대되는 모멘트를 발생시켜 주어 더욱 안전하고 경제적인 교대 구조물의 설계 및 시공을 도모할 수 있다. The present invention relates to an alternate integral continuous composite bridge using a precast girder and a construction method thereof. In the continuous composite bridge of two or more spans, the parent force generated at the inner point of the pier is subjected to a compression force by the first rise and fall of the inner point. It is structurally safe because the compressive force can be introduced to the alternating upper slab concrete, which could not be introduced in the conventional construction method by introducing the compressive force by introducing the compressive force by partially raising the inner point again for the parent moment generated at the alternate outer point. As the bridge can be built, the moment distribution effect can be increased to improve the vibration reduction effect and the seismic resistance due to the live load. In addition, since the moment generated by the external force is distributed to the integrated shift, the burden on the external force of the precast girder is reduced, so that a reduction or extension effect of about 20% can be expected in terms of the height and the length of the precast girder, respectively. Economical bridge construction can be achieved. In addition, the prestressing (compression and tensile force) introduced to the upper slab of the alternating part and the concrete of the lower part of the foundation by the second rising process generates moments that are opposite to the parent and static moments occurring in the alternation of the general ramen structure. The design and construction of the shift structure can be planned.

Description

프리캐스트 거더를 이용한 교대 일체형 연속 합성형교 및 그 시공법{A integral abutment continuous composite bridge using precast girder and the construction method thereof}A integral abutment continuous composite bridge using precast girder and the construction method

본 발명은 프리캐스트 거더를 이용한 교대 일체형 연속 합성형교 및 그 시공법에 관한 것으로서, 더욱 상세하게는 구조적으로 안전하고 사용성에 있어서도 뛰어난 교량 및 교량을 건설하기 위한 시공법에 관한 것이다. BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to alternating integrated continuous composite bridges using precast girders and construction methods thereof, and more particularly to construction methods for constructing bridges and bridges that are structurally safe and excellent in usability.

종래의 철근 콘크리트 라멘교는 도 1에서 보는 바와 같이 슬래브(10)와 기둥(11) 만으로 이루어지기 때문에, 슬래브(10)와 기둥(11)이 서로 연결된 지점(12)에는 교량 자체에 작용하는 외력에 저항하기 위해서 단면을 증가시킨다. 하지만, 단면이 증가되면 고정하중의 증가와 교량의 형하 공간이 축소되는 등의 문제점이 발생하기 때문에 실질적으로 지간이 짧은 교량에만 슬래브 형식의 라멘교가 사용되고, 장지간을 필요로 하는 교량에는 프리캐스트 거더를 이용한 일반적인 형식을 사용하고 있는 실정이다.Since the conventional reinforced concrete ramen bridge is composed of only the slab 10 and the pillar 11 as shown in FIG. 1, the external force acting on the bridge itself at the point 12 where the slab 10 and the pillar 11 are connected to each other. Increase the cross section to resist. However, if the cross section is increased, problems such as increase of fixed load and reduction of the die space of the bridge occur. Therefore, the slab type ramen bridge is used only for bridges with short spans, and precast girders are used for bridges requiring long spans. The general form using is used.

상술한 라멘교의 장지간 적용성 문제를 해결하기 위한 일례로 대한민국 등록특허공보 제10-0543969호에는 "프리스트레스트 합성보를 라멘 교량의 슬래브의 중앙부에 설치하고 기둥의 상부에 설치된 강재와 연결하여 설치된 합성형 라멘 교량 및 이의 시공방법"(이하 '인용발명' 이라 한다)이 개시되어 있다.As an example for solving the long-term applicability problem of the ramen bridge, the Republic of Korea Patent Publication No. 10-0543969 describes the "synthesis installed by installing the prestressed composite beam in the center of the slab of the ramen bridge and connected to the steel installed on the top of the column Type Ramen Bridge and its construction method "(hereinafter referred to as 'quoting invention') are disclosed.

도 2 내지 도 5는 상기 인용발명의 2경간 연속 합성형교의 시공법을 나타낸 것이다. 도면을 참조하면, 인용발명의 시공법은 일부 시공된 교대(13) 및 교각(14)의 상단부에 각각 외측지점 연결 강재(15)와 내측지점 연결 강재(16)를 설치한 후(도 2 참조), 미리 제작된 프리스트레스트 합성보(프리캐스트 거더)(17)를 외측지점 연결 강재(15) 및 내측지점 연결 강재(16)와 연결하고(도 3 참조), 이후 연결 강재(15, 16) 및 프리캐스트 거더(17)를 덮도록 슬래브 콘크리트(19)를 타설하여 교량을 완성한다(도 4 참조).2 to 5 show the construction method of the two-span continuous composite bridge of the cited invention. Referring to the drawings, the construction method of the cited invention, after installing the outer branch connecting steel 15 and the inner branch connecting steel 16 on the upper ends of some of the shift 13 and the pier 14 (see Fig. 2) , Connect the prefabricated prestressed composite beam (precast girder) 17 with the outer branch connecting steel 15 and the inner branch connecting steel 16 (see FIG. 3), and then the connecting steel 15, 16 and the pre The slab concrete 19 is poured to cover the cast girder 17 to complete the bridge (see FIG. 4).

그런데, 상술한 인용발명은 고정하중 및 활하중의 작용에 의하여 도 5와 같이 정모멘트인 Mp와 부모멘트인 Mn1 및 Mn2가 발생하는데 정모멘트인 Mp는 미리 제작된 프리캐스트 거더에 도입되어진 프리스트레스가 상쇄시켜 줄 수는 있겠으나, 외측 및 내측지점부에서 발생하는 부모멘트(Mn1, Mn2)는 상쇄 방법이 없어 각 지점부의 슬래브 콘크리트에 균열을 야기할 수 있어 교량의 사용성에 큰 영향을 미칠 수 있고 주기적인 유지관리를 해 주어야 하는 단점이 있었다.However, in the above-mentioned cited invention, the positive moment Mp and the parent moments Mn1 and Mn2 are generated by the action of the fixed load and the live load, and the positive moment Mp cancels the prestress introduced into the precast girder made in advance. Although it can be made, the parental moments (Mn1, Mn2) generated at the outer and inner points have no offset method, which can cause cracks in the slab concrete at each point, which can greatly affect the usability of the bridge. There was a drawback to having to maintain.

따라서 본 발명은 상술한 일반적인 라멘교 및 인용발명의 단점을 보완할 수 있는 새로운 시공법을 제시하고자 한다.Therefore, the present invention is to propose a new construction method that can supplement the above-mentioned disadvantages of the general ramen bridge and the invention.

본 발명은 상술한 종래 기술에 착안한 것으로, 본 발명의 목적은 종래 기술이 가지고 있는 외측지점 및 내측지점에서 발생하는 부모멘트를 상쇄시킬 수 있는 압축력을 도입시켜 구조적으로 안전한 프리캐스트 거더를 이용한 교대 일체형 연속 합성형교 및 그 시공법을 제공하는 데 있다. The present invention has been made in view of the above-described prior art, and an object of the present invention is to introduce a compressive force capable of canceling parent moments occurring at the outer and inner points of the prior art, thereby using a structurally safe precast girder. An integrated continuous composite bridge and its construction method are provided.

상기 목적을 달성하기 위해 본 발명에 따른 프리캐스트 거더를 이용한 교대 일체형 연속 합성형교는 2경간 이상의 연속 합성형교에 있어서, 교대 및 교각과, 교대의 상단에 마련되는 외측지점 가설재 및 교각의 상단에 마련되는 내측지점 가설재와, 내측지점 가설재 위에서 맞닿도록 외측지점 가설재 및 내측지점 가설재 상에 설치되며 미리 압축력이 도입된 프리캐스트 거더와, 내측지점 가설재 위에 프리캐스트 거더의 상승 상태를 유지할 수 있도록 마련되는 상승유지 고임재와, 프리캐스트 거더 위에 타설되는 슬래브 콘크리트와, 교대와 프리캐스트 거더 및 슬래브 콘크리트를 일체화시키는 교대 연결 콘크리트와, 교각과 프리캐스트 거더 사이에 설치되는 교좌장치를 포함하여, 교각부 내측지점에서 발생하는 부모멘트는 내측지점 가설재 위에서 맞닿은 두 개의 프리캐스트 거더를 서로 연결하고, 서로 연결된 프리캐스트 거더의 내측지점을 상승유지 고임재를 설치하여 1차 상승시킨 상태에서 슬래브 콘크리트를 타설하여 유지시킨 후, 1차 상승된 프리캐스트 거더를 하강시켜 도입되는 대응 압축력으로 상쇄시키고, 교대부 상부 슬래브 및 하부기초에서 발생하는 부모멘트 및 정모멘트는 내측지점을 다시 2차 상승시켜 도입되는 대응 프리스트레싱으로 상쇄시킨다. In order to achieve the above object, the alternate integral continuous composite bridge using the precast girder according to the present invention is provided at the upper end of the alternate point and the pier and the outer point temporary construction material and the pier provided at the top of the alternate bridge in the continuous composite bridge of at least two spans. A precast girder, which is installed on the outer branch temporary member and the inner branch temporary member to abut on the inner branch temporary member, the precast girder having a compression force introduced in advance, and a precast girder which is provided to maintain the rising state of the precast girder on the inner branch temporary member. Inner point of pier including retaining slabs, slab concrete placed on precast girders, alternating connecting concrete integrating alternating and precast girder and slab concrete, and bridge arrangements installed between piers and precast girders The parent moment occurs at the medial point hypothesis Connect the two precast girders that are in contact with each other, install and maintain the slab concrete in the state where the inner point of the precast girders connected to each other is first raised by installing the rising retaining material, and then the first raised precast girders are It is offset by the corresponding compressive force introduced by lowering, and the parent and static moments generated in the alternating upper slab and the lower foundation are offset by the corresponding prestressing which is introduced again by raising the inner point again.

또한, 상기 슬래브 콘크리트는 상기 프리캐스트 거더를 내측지점 가설재에서 상승유지 고임재를 이용하여 1차 상승시킨 후 타설되고, 상기 교대 연결 콘크리트는 상기 프리캐스트 거더를 하강시킨 후 타설된다. In addition, the slab concrete is poured after the precast girder is first raised by using the rising holding material from the inner point temporary construction material, the alternating connection concrete is poured after the precast girder is lowered.

또한, 상기 프리캐스트 거더의 2차 상승량은 1차 상승량보다 작다.In addition, the secondary lift amount of the precast girder is smaller than the primary lift amount.

또한, 경간별로 독립 제작되는 단위 프리캐스트 거더는 프리스트레스트 콘크리트 거더, 프리플렉스 거더, 강박스 거더 중 어느 하나를 포함한다. In addition, the unit precast girders independently produced by the span includes any one of prestressed concrete girder, preflex girder, steel box girder.

본 발명의 다른 측면에 따르면 교대와, 교좌장치가 설치되지 않은 교각의 교좌받침 콘크리트 상단에 각각 외측지점 가설재와 내측지점 가설재를 설치하는 단계; 경간별로 독립되어 제작된 단위 프리캐스트 거더를 상기 외측지점 가설재와 내측지점 가설재 위에 거치시키는 단계; 거치된 각각의 프리캐스트 거더를 내측지점 가설재 위에서 서로 연결시키는 단계; 연결된 프리캐스트 거더를 내측지점 가설재에서 1차 상승시키는 단계; 슬래브 콘크리트를 타설 및 양생시키는 단계; 1차 상승시킨 프리캐스트 거더를 하강시키는 단계; 교대와 프리캐스트 거더 및 슬래브 콘크리트를 일체화시키는 교대 연결 콘크리트를 타설 및 양생시키는 단계; 및 1차 상승 후 하강시킨 프리캐스트 거더를 2차 상승시키고 교좌장치를 설치하는 단계;로 이루어진 프리캐스트 거더를 이용한 교대 일체형 연속 합성형교의 시공법을 제공한다. According to another aspect of the invention, each of the shift and the top of the pedestal concrete of the bridge where the shift device is not installed Installing an outer branch temporary member and an inner branch temporary member; Mounting unit precast girders independently manufactured by spans on the outer branch temporary members and the inner branch temporary members; Connecting each of the mounted precast girders to each other on the medial point provisional member; Firstly raising the connected precast girder at the medial point provisional member; Placing and curing slab concrete; Lowering the first raised precast girder; Placing and curing alternating connecting concrete integrating the shift with the precast girder and the slab concrete; And a second step of raising the precast girder, which is lowered after the first rise, and installing a stabilization device. The construction method of the alternate continuous continuous composite bridge using the precast girder is provided.

또한, 외측지점부인 교대와 프리캐스트 거더의 연결에 있어서, 상기 프리캐스트 거더 단부의 측면에는 거더노출철근을 하면에는 연결플레이트가 설치된 프리캐스트 거더를 교대 위 가설재에 거치시킨 후, 연결플레이트와 인발방지 플레이트를 서로 관통하여 연결되는 연결철근를 설치하고, 교대에서 노출되어진 교대연결철근과 프리캐스트 거더 단부의 측면에서 노출되어진 거더노출철근을 서로 연결하고, 교대 단부에서 노출되어진 교대 단부 연결철근과 슬래브 콘크리트에서 노출되어진 슬래브 콘크리트 연결 철근을 서로 연결한 후, 상기 모두를 감싸는 연결콘크리트를 타설하여 교대와 거더를 일체화시키도록 한다. In addition, in the connection between the shift portion and the precast girder, which is the outer point, the precast girder is installed on the side of the end of the precast girder and the connecting plate is installed on the temporary construction material on the alternating surface, and the connection plate and the pull-out prevention Install connecting bars that connect the plates through each other, connect the alternating connecting bars exposed at the shift and the exposed girder bars at the sides of the precast girder end, and at the alternating end connecting bars and slab concrete exposed at the alternating ends. After connecting the exposed slab concrete connecting bars to each other, the connecting concrete covering all of the above to be cast to integrate the shift and the girder.

또한, 4경간 이상의 교대 일체형 합성형교를 2경간 또는 3경간의 연속 합성형교 형태로 시공하여 연속 합성형교의 끝단이 교각 위에 위치할 때 교각과 빔은 일체화시키지 않고 연속화하며, 교각 위에 위치하는 2경간 또는 3경간의 연속 합성형교의 끝단은 교좌장치 위에 설치된다. In addition, construct a composite composite bridge of four or more spans in the form of a continuous composite bridge between two or three spans, and when the ends of the continuous composite bridges are located on the bridges, the bridges and beams are not integrated, and the two bridges located on the bridges. Alternatively, the end of the three span continuous composite bridge is installed on the bridge device.

본 발명에 따른 프리캐스트 거더를 이용한 교대 일체형 연속 합성형교 및 그 시공법은 종래 어떤 방식에서도 도입할 수 없었던 압축력을 교대 상부 슬래브 콘크리트에 도입시킬 수 있어 구조적으로 안전한 교량의 건설을 이룰 수 있으며, 교량의 하부 구조물인 교대와 프리캐스트 거더의 일체화를 통해 더욱 큰 부정정 차수를 가지는 구조물을 이룰 수 있어 모멘트 분배 효과를 크게 하여 활하중에 의한 진동감소 효과와 내진성을 향상시킬 수 있다. 또한, 외력에 의해 발생되는 모멘트가 일체화된 교대에 분배됨으로써 프리캐스트 거더의 외력에 대한 부담이 감소되어 프리캐스트 거더의 형고와 지간장 면에서 각각 약 20% 정도의 감소효과 또는 연장효과를 기대할 수 있어 경제적인 교량의 시공을 이룰 수 있다. 또한 2차 상승 공정에 의해 교대부 상부 슬래브 콘크리트에 도입되는 압축력, 교대 하부 기초에 도입되는 인장력은 일반 라멘 구조물의 교대에서 발생하는 부모멘트와 정모멘트에 반대되는 모멘트를 발생시켜 주어 더욱 안전하고 경제적인 교대 구조물의 설계 및 시공을 도모할 수 있다.The alternate integral continuous composite bridge and its construction method using the precast girder according to the present invention can introduce a compressive force, which could not be introduced in any conventional method, to the alternating upper slab concrete, thereby achieving the construction of a structurally safe bridge. Through the integration of the lower structure shift and the precast girder, it is possible to achieve a structure having a larger degree of indefinite order, thereby increasing the moment distribution effect and improving the vibration reduction effect and the seismic resistance due to the live load. In addition, since the moment generated by the external force is distributed to the integrated shift, the burden on the external force of the precast girder is reduced, so that a reduction or extension effect of about 20% can be expected in terms of the height and the length of the precast girder, respectively. Economical bridge construction can be achieved. In addition, the compressive force introduced to the alternating upper slab concrete by the second ascending process and the tensile force introduced to the lower alternating foundation generate moments opposite to the parent and static moments occurring in the alternation of the general ramen structure, making it safer and more economical. The design and construction of the shift structure can be planned.

도 1은 종래의 철근 콘크리트 라멘교를 개략적으로 도시한 도면이다.
도 2 내지 도 5는 종래의 2경간 연속 라멘교의 시공법을 도시한 도면이다.
도 6 내지 도 14는 본 발명의 일 실시예에 따른 2경간 프리캐스트 거더를 이용한 연속 합성형교 및 그 시공법을 도시한 도면이다.
도 15 내지 도 23은 본 발명의 다른 실시예에 따른 3경간 프리캐스트 거더를 이용한 연속 합성형교 및 그 시공법을 도시한 도면이다.
도 24 내지 도 28은 본 발명에 따른 프리캐스트 거더를 이용한 연속 합성형교 및 그 시공법에 있어서 외측지점부인 교대와 프리캐스트 거더의 연결방법을 도시한 도면이다.
도 29 내지 도 33은 본 발명의 프리캐스트 거더를 이용한 교대 일체형 연속 합성형교 및 그 시공법의 또 다른 실시예를 나타낸 것이다.
1 is a view schematically showing a conventional reinforced concrete ramen bridge.
2 to 5 are views showing a construction method of a conventional two-span continuous ramen bridge.
6 to 14 are views showing a continuous composite bridge using a two-span precast girder and a construction method thereof according to an embodiment of the present invention.
15 to 23 are views illustrating a continuous composite bridge using a three-span precast girder and a construction method thereof according to another embodiment of the present invention.
24 to 28 are views showing a method of connecting the alternating portion and the precast girder in the continuous composite bridge using the precast girder and the construction method thereof according to the present invention.
29 to 33 show another embodiment of an alternate integral continuous composite bridge using the precast girder of the present invention and a construction method thereof.

이하, 본 발명의 바람직한 실시예를 첨부한 도면을 참조하여 상세히 설명하기로 한다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 6 내지 도 14와, 도 15 내지 도 23은 각각 본 발명의 일 실시예에 따라 프리캐스트 거더를 이용한 교대 일체형 2경간 및 3경간 연속 합성형교 및 그 시공법을 시공순서에 따라 도시한 것이다.6 to 14 and 15 to 23 show alternately integrated two-span and three-span continuous composite bridges using precast girders and construction methods thereof according to an embodiment of the present invention, respectively.

도면들을 참조하면, 일 실시예인 2경간 프리캐스트 거더를 이용한 연속 합성형교를 시공하기 위해서는, 먼저 도 6과 같이 일부 시공된 교대(13)와 시공이 완료되어 교좌장치만 설치되지 않은 교각(14)의 교좌받침 콘크리트(21) 상단에 각각 미리 압축력이 도입되어 제작된 프리캐스트 거더(33)를 거치 및 연결함과 동시에 슬래브 콘크리트에 압축력을 도입시키기 위한 설계상의 상승 및 하강량을 고려한 일정 높이의 외측지점 가설재(31) 및 내측지점 가설재(32)를 거치시킨 후, 내측지점 가설재(32) 위에서 맞닿은 2개의 프리캐스트 거더(33)를 서로 연결한다(도 7 참조). 여기서 교대(13) 단부에는 추후 도 11에서와 같이 상부 구조물인 프리캐스트 거더 및 슬래브 콘크리트와 일체화될 수 있도록 하는 교대 단부 연결철근(38)을 미리 돌출시켜 놓는다. Referring to the drawings, in order to construct a continuous composite bridge using a two-span precast girder as an embodiment, as shown in FIG. The outside of a certain height in consideration of the design rise and fall amount to mount and connect the precast girder 33, which is produced by compressive force in advance on the top of the bridge bearing concrete 21, and to introduce the compressive force into the slab concrete. After mounting the point temporary member 31 and the inner point temporary member 32, the two precast girders 33 abutting on the inner point temporary member 32 is connected to each other (see Fig. 7). Here, alternate end 13 reinforces the alternate end connecting reinforcement 38 to be integrated with the precast girder and the slab concrete, which are later structures as shown in FIG. 11.

이어서, 도 8과 같이 서로 연결된 프리캐스트 거더(33)를 내측지점에서 ΔH1 만큼 1차 상승시키고 내측지점 가설재(32) 위에 상기 상승량을 유지시킬 수 있는 상승유지 고임재(35)를 설치하고, 도 9와 같이 슬래브 콘크리트(36)를 타설한다. 이때 타설하는 슬래브 콘크리트는 교대(13) 측 양단부의 슬래브 콘크리트 연결 철근(37)이 일부분 노출되도록 타설하는데, 이는 추후 교대(13)와 프리캐스트 거더(33) 및 슬래브 콘크리트(36)를 일체화시키기 위함이다.Subsequently, as shown in FIG. 8, the precast girders 33 connected to each other are first raised by ΔH1 at the inner point and a rising holding stub 35 is provided to maintain the lift amount on the inner point temporary member 32. As shown in 9, the slab concrete 36 is poured. At this time, the slab concrete to be poured is placed so that the slab concrete connection reinforcing bar 37 at both ends of the alternating part 13 is partially exposed, so that the alternating 13 and the precast girder 33 and the slab concrete 36 are integrated later. to be.

타설한 슬래브 콘크리트가 양생되면, 도 5에 도시한 바와 같이 내측지점부에서 발생하는 부모멘트 Mn2에 대응하는 압축력을 교각 상부 슬래브 콘크리트(36)에 도입시키기 위해 1차 상승시킨 프리캐스트 거더(33)를 하강시킨다(도 10 참조). 이때의 하강은 1차 상승량 ΔH1과 도 5에 도시한 Mn1에 대응하는 압축력을 도입하기 위한 2차 상승량 ΔH2를 고려한 량인 ΔH1+ΔH2이다. 여기서, 참고로 ΔH2는 ΔH1의 15∼30%이다. 그 이유는 활하중 하에 있는 연속 합성형교에서 외측지점부인 교대부에서 발생하는 부모멘트가 내측지점부인 교각부에서 발생하는 부모멘트보다 작기 때문이고, 또한 ΔH2는 외측지점부인 교대부가 상부 구조물과 일체화되어 부정정 차수가 2개 차수 커진 상태에서 시행되므로, 적은 상승량으로도 교대부 슬래브 콘크리트에 압축력 도입 효과가 커지기 때문이다. 여기서 상승량은 적지만 상승력은 커지게 된다.When the poured slab concrete is cured, the precast girder 33 is first raised to introduce the compressive force corresponding to the parent moment Mn2 generated at the inner branch portion into the pier upper slab concrete 36 as shown in FIG. 5. Is lowered (see FIG. 10). The fall at this time is ΔH1 + ΔH2 which is an amount in consideration of the first rising amount ΔH1 and the second rising amount ΔH2 for introducing a compressive force corresponding to Mn1 shown in FIG. 5. Here, ΔH2 is 15 to 30% of ΔH1. The reason is that in the continuous composite girder bridge under live load, the parent moment occurring at the alternating part of the outer point is smaller than the parent moment occurring at the inner part of the pier, and ΔH2 is negative because the alternating part of the outer point is integrated with the superstructure. This is because the effect of the compression force is increased in the alternating slab concrete even with a small rise because the order is carried out in two orders of magnitude. The rise is small but the rise is large.

이어서, 도 11과 같이 교대(13) 단부에서 돌출되어 나온 교대 단부 연결철근(38)과 교대 단부쪽 슬래브 콘크리트에서 돌출된 슬래브 콘크리트 연결철근(37)을 서로 연결한 후, 도 12와 같은 공정도에 따라 교대(13)와 프리캐스트 거더(33) 및 슬래브 콘크리트(36)를 모두 일체화시킬 수 있도록 교대 연결 콘크리트(39)를 타설하여 일체화시킨다.Subsequently, as shown in FIG. 11, after connecting the alternating end connecting bars 38 protruding from the end of the alternating 13 and the slab concrete connecting bars 37 protruding from the alternating end side slab concrete, the process diagram as shown in FIG. In accordance with the alternating 13 and precast girder 33 and the slab concrete (36) in order to integrate all of the alternating connection concrete 39 is integrated.

타설한 교대 연결 콘크리트(39)가 양생되면, ΔH1+ΔH2만큼 하강시켰던 프리캐스트 거더(33)를 통상의 유압잭(미도시)을 이용하여 다시 내측지점인 교각(14) 위에서 ΔH2만큼 2차 상승시킨다(도 13 참조). 그러면, 도 14와 같은 모멘트가 발생하여 2경간 연속 합성형교에서 발생하는 도 5의 모멘트도에서의 Mn1에 대응하는 압축력이 교대의 단부에 도입되는 것이다. 교대의 기초 부분에도 사용하중 중에 발생되는 모멘트에 상반되는 부모멘트가 도입된다.When the alternating alternate concrete 39 is cured, the precast girders 33, which have been lowered by ΔH1 + ΔH2, are secondly raised by ΔH2 on the inner side of the pier 14 by using a normal hydraulic jack (not shown). (See Figure 13). Then, the moment as shown in FIG. 14 is generated, and the compressive force corresponding to Mn1 in the moment diagram of FIG. The parent part opposite to the moment generated during the working load is also introduced in the shift base part.

그리고, 상승시킨 프리캐스트 거더와 교좌받침 콘크리트 사이에 교좌장치(22)를 설치하면 본 발명의 프리캐스트 거더를 이용한 교대 일체형 연속 합성형교 및 그 시공법의 2경간 연속 합성형교가 완성된다. Then, when the bridge device 22 is provided between the raised precast girder and the bridge support concrete, the alternate integral continuous composite bridge using the precast girder of the present invention and the two-span continuous composite bridge of the construction method are completed.

도 15 내지 도 23까지는 본 발명의 다른 실시예에 따른 프리캐스트 거더를 이용한 3경간 연속 합성형교의 시공법을 나타낸 것이다. 15 to 23 illustrate a method of constructing a three-span continuous composite bridge using a precast girder according to another embodiment of the present invention.

시공법에 대한 단계적 설명은 2경간 연속 합성형교의 시공법을 공정에 따라 나타낸 일 실시예와 같다. 본 실시예의 프리캐스트 거더를 이용한 연속 합성형교 및 그 시공법의 3경간 연속 합성형교의 시공법은 일반 2경간 교량과 3경간 교량 구성 차이와 같이 1개가 더 추가된 교각과 이 교각에 설치되는 내측지점 가설재, 상승유지 고임재 등이 추가로 각각 1개씩 더 있다는 점과 내측지점부에서의 1차 상승과 하강, 2차 상승 공정이 2개의 교각에서 동시에 이루어진다는 점만 다를 뿐이다.Stepwise description of the construction method is the same as the embodiment showing the construction method of the two-span continuous composite bridge according to the process. The continuous composite bridge using the precast girder of the present embodiment and the construction method of the three-span continuous composite bridge in the construction method are constructed of a bridge with an additional one and the inner point temporary construction installed in the bridge, such as a general two-span bridge and a three-span bridge configuration difference. The only difference is that there is one additional uphill retaining material, and that the first ascending and descending, and the second ascending process at the inner point are simultaneously performed in two piers.

이상으로 본 발명에 따른 프리캐스트 거더를 이용한 교대 일체형 연속 합성형교를 요약하면 다음과 같다.The summary of the integral integral continuous composite bridge using the precast girder according to the present invention as follows.

본 발명은 2경간 이상의 연속교에서 교각부 내측지점에서 발생하는 부모멘트는 내측지점의 1차 상승 및 하강에 의해 압축력을 도입시키고, 외측지점부인 교대부 상부 슬래브 및 기초하부에서 발생하는 모멘트는 내측지점을 다시 2차 상승, 즉 수평 또는 이보다 약간 상승시켜 프리스트레싱(압축력 및 인장력)을 도입시킨 프리캐스트 거더를 이용한 교대 일체형 연속 합성형교이다.In the present invention, in the continuous bridge of two spans or more, the parent moment generated at the inner side of the pier is introduced into the compressive force by the first rise and fall of the inner side, and the moment generated at the alternating upper slab and the lower base of the outer side is the inner side. Alternate integral continuous composite bridges using precast girders that introduce a prestressing (compression and tensile force) with a second rise, ie horizontal or slightly higher.

또한 본 발명의 프리캐스트 거더를 이용한 교대 일체형 연속 합성형교 및 그 시공법에서 적용되는 프리캐스트 거더는 프리스트레스트 콘크리트 거더, 프리플렉스 합성형 거더, 강박스 거더 등에 적용이 가능하다. In addition, the shift integrated continuous composite bridge using the precast girder of the present invention and the precast girder applied in the construction method can be applied to prestressed concrete girder, preflex composite girder, steel box girder and the like.

다음은 본 발명의 프리캐스트 거더를 이용한 교대 일체형 연속 합성형교 및 그 시공법에서 외측지점부인 교대와 프리캐스트 거더의 연결방법을 제시한다.The following is an alternate integrated continuous composite bridge using the precast girder of the present invention and a method of connecting the shift and the precast girder, which are outer point portions, in the construction method thereof.

도 24 내지 도 28은 본 발명의 프리캐스트 거더를 이용한 교대 일체형 연속 합성형교 및 그 시공법에 있어서 외측지점부인 교대과 프리캐스트 거더의 연결방법에 대한 일례를 도시한 것이다.24 to 28 show an example of an alternate integral continuous composite bridge using the precast girder of the present invention and a method of connecting the shift and the precast girder, which are outer points in the construction method thereof.

도 24는 프리캐스트 거더(33)의 교대와 연결되어지는 단부 하단에 일정 간격으로 철근가설구멍(51)이 뚫린 연결플레이트(52)와 거더노출철근(53)을 설치한 사시도를 나타낸 것이다. 연결플레이트(52)는 도 27과 같이 추후 교대(13)과 프리캐스트 거더(33)를 연결하는데 필요한 연결철근(54)과 프리캐스트 거더(33)를 연결하기 위한 역할을 하는 것이며, 거더노출철근(53)은 도 26에 나타낸 것과 같은 교대(13)의 시공 시 배근되어 교대의 표면 위로 노출된 교대연결철근(65)과 연결하기 위함이다. 도 25는 미리 제작된 프리캐스트 거더(33)를 교대(13)에 거치하기 전 교대(13)에 설치된 외측지점 가설재(31)와 교대(13)의 시공 시 배근되어 교대의 표면 위로 노출된 교대연결철근(65)을 나타낸 사시도이다. 여기서, 교대(13)의 경우에는 프리캐스트 거더의 끝단 쪽으로 거더 위의 슬래브 콘크리트(36)에서 노출된 슬래브 콘크리트 연결철근(37)과 연결하기 위한 교대 단부 연결철근(66)이 추가로 노출되어 있다.24 is a perspective view showing the connection plate 52 and the girder exposed reinforcing bar 53 in which rebar temporary holes 51 are drilled at predetermined intervals at the lower end portions connected to the alternation of the precast girder 33. The connecting plate 52 serves to connect the connecting reinforcing bar 54 and the precast girder 33 necessary for connecting the alternating 13 and the precast girder 33 later, as shown in FIG. 27. Reference numeral 53 is for connecting with the alternating connecting reinforcement 65, which is placed at the time of construction of the shift 13 as shown in FIG. 26 and exposed on the surface of the shift. FIG. 25 shows the shifts exposed to the surface of the shifts when the prefabricated girders 33 are mounted on the shifts 13 and the outer point temporary material 31 and shifts 13 installed on the shifts 13 are mounted on the shifts 13. It is a perspective view which shows the connecting bar 65. Here, in the case of the shift 13, the alternate end connecting bars 66 for connecting with the slab concrete connecting bars 37 exposed in the slab concrete 36 on the girder toward the end of the precast girder are further exposed. .

도 25와 같은 상태의 교대 위에 도 23과 같이 제작된 프리캐스트 거더(33)를 외측지점 가설재(31) 위에 거치시키면 도 26과 같은 상태가 이루어진다. 여기서, 도면의 인식성을 높이기 위해 도 25에 도시한 교대(13)의 시공 시 배근되어 교대의 표면 위로 노출된 교대연결철근(65)과 교대 단부 연결철근(66)의 표시는 생략하기로 한다. When the precast girder 33 manufactured as shown in FIG. 23 is mounted on the outer point temporary member 31 on the alternating state as shown in FIG. 25, the state as shown in FIG. Here, in order to increase the recognition of the drawings, the display of the alternating connecting bars 65 and the alternating end connecting bars 66, which are arranged when the shift 13 shown in FIG. 25 is exposed and exposed on the surface of the shift, will be omitted. .

프리캐스트 거더(33)를 도 26과 같이 거치한 후, 교대(13)와 프리캐스트 거더(33)를 연결하는데 필요한 연결철근(54)을 연결플레이트(52)에 설치된 철근가설구멍(51)을 관통하여 설치하고 설치된 연결철근(54)이 한꺼번에 연결되고 상부 하중의 재하 시 프리캐스트 거더(33)에 발생되는 인발을 방지하기 위한 인발방지 플레이트(56)를 설치하며(도 27 참조), 이와 동시에 도 28과 같이 상부 구조물인 프리캐스트 거더(33)와 하부구조물인 교대(13)를 서로 연결하여 완전 일체화된 구조물을 만들기 위해 교대(13)의 시공 시 배근되어 교대의 표면 위로 노출된 교대연결철근(65)과 프리캐스트 거더(33)에서 노출되어 설치된 거더노출철근(53)을 서로 연결하고, 타설 후 양생된 슬래브 콘크리트(36)에서 노출된 슬래브 콘크리트 연결철근(37)과 교대 단부 연결철근(66)을 연결한다. 여기서, 도 28에서는 도면의 인식성을 높이기 위해 도 27에 도시한 연결철근(54) 및 인발방지 플레이트(56)의 표시는 생략하였다. After the precast girder 33 is mounted as shown in FIG. 26, the rebar temporary holes 51 provided in the connecting plate 52 are connected to the reinforcing bar 54 necessary for connecting the shift 13 and the precast girder 33. The connecting reinforcing rods 54 installed and installed through the connecting rods are connected at one time, and a pull-out prevention plate 56 is installed to prevent the pulling out of the precast girder 33 when the upper load is loaded (see FIG. 27). Alternating connecting bars exposed on the surface of the alternating rods during construction of the shifts 13 to connect the precast girders 33, which are the upper structures, and the shifts 13, which are the lower structures, to form a fully integrated structure as shown in FIG. (65) and the girder exposed rebar (53) exposed and installed in the precast girder (33), and the slab concrete connecting reinforcement (37) exposed in the cured slab concrete (36) after pouring and alternating end connecting reinforcement ( 66) . Here, in FIG. 28, in order to increase the recognition of the drawings, the markings of the connecting bar 54 and the pull-out plate 56 shown in FIG. 27 are omitted.

이어서, 도 12 및 도 21에 나타낸 것과 같이 도 24 내지 도 28의 공정에서 기술한 모든 부분을 둘러싸는 교대 연결 콘크리트(39)를 타설하여 상부 구조물인 프리캐스트 거더(33)와 하부 구조물인 교대(13)를 완전히 일체화시킨다.Subsequently, as shown in FIGS. 12 and 21, alternating concrete 39 surrounding all parts described in the processes of FIGS. 24 to 28 is poured to alternate the precast girder 33 as the upper structure and the lower structure as the lower structure. 13) are fully integrated.

도 29 내지 도 33은 본 발명의 프리캐스트 거더를 이용한 교대 일체형 연속 합성형교 및 그 시공법의 또 다른 실시예를 나타낸 것이다.29 to 33 show another embodiment of an alternate integral continuous composite bridge using the precast girder of the present invention and a construction method thereof.

예컨대, 도 29는 상술한 2경간 교대 일체형 연속 합성형교를 연속시켜 4경간 연속 합성형교에 적용하였을 때를 도시한 도면이다. 도 6 내지 도 14의 2경간 교대 일체형 연속 합성형교를 2개 연속으로 실시하면 2경간이 끝나는 부분인 장경간 합성형교의 조인트부(70)에 교대가 아닌 교각이 존재하게 되므로, 이 위치에서는 교대에 일체화하는 시공법을 실시할 수가 없게 된다. 따라서 도 30과 같이 한쪽 교대(13)만 상부 구조물과 일체화시킴으로써 교대 일체형 합성형교의 특성을 살린 본 발명의 또 다른 실시예를 구현할 수 있다. For example, FIG. 29 is a diagram showing a case where the above-described two-span alternate integral continuous composite bridge is continuously applied to the four-span continuous composite bridge. If the two-span alternating integral continuous composite bridge of FIGS. 6 to 14 is carried out in succession, the pier instead of the alternating pier exists in the joint portion 70 of the long-span composite bridge which is the end of the two spans. Construction method to be integrated into the Therefore, as shown in FIG. 30, only one shift 13 may be integrated with the upper structure to implement another embodiment of the present invention utilizing the characteristics of the shift integrated composite bridge.

도 31은 상술한 3경간 교대 일체형 연속 합성형교를 연속시켜 6경간 연속 합성형교에 적용하였을 때를 도시한 도면이다. 도 15 내지 도 23의 3경간 교대 일체형 연속 합성형교를 2개 연속으로 실시하면 3경간이 끝나는 부분(70)에 교대가 아닌 교각이 존재하게 되므로, 이 위치에서는 교대에 일체화하는 시공법을 실시할 수가 없게 된다. 따라서 도 32와 같이 한쪽 교대(13)만 상부 구조물과 일체화시킴으로써 교대 일체형 합성형교의 특성을 살린 본 발명의 또 다른 실시예를 구현할 수 있다. FIG. 31 is a diagram showing a case where the above-described three-span alternate integral continuous composite bridge is applied to the six-span continuous composite bridge. If two continuous three-stage integral composite composite bridges of Figs. 15 to 23 are carried out in succession, instead of alternating piers exist in the portion 70 at the end of the three spans, the construction method of integrating to the alternation can be performed at this position. There will be no. Accordingly, as shown in FIG. 32, only one shift 13 may be integrated with the upper structure to implement another embodiment of the present invention utilizing the characteristics of the shift integrated composite bridge.

또한, 도 30의 실시예와 도 32의 실시예를 조합하게 되면 도 33과 같은 5경간 연속 합성형교에도 적용할 수 있다. In addition, when the embodiment of FIG. 30 and the embodiment of FIG. 32 are combined, the present invention may also be applied to a five-span continuous composite bridge as shown in FIG. 33.

10 : 슬래브
11 : 기둥
13 : 교대
14 : 교각
15 : 외측지점 연결 강재
16 : 내측지점 연결 강재
17 : 프리캐스트 거더
19 : 슬래브 콘크리트
21 : 교좌받침 콘크리트
22 : 교좌장치
31 : 외측지점 가설재
32 : 내측지점 가설재
33 : 프리캐스트 거더
35 : 상승유지 고임재
36 : 슬래브 콘크리트
37 : 슬래브 콘크리트 연결철근
38 : 교대 단부 연결철근
39 : 교대 연결 콘크리트
40 : 교각 연결 콘크리트
51 : 철근가설구멍
52 : 연결플레이트
53 : 거더노출철근
54 : 연결철근
55 : 교각연결철근
56 : 인발방지 플레이트
65 : 교대연결철근
66 : 교대 단부 연결철근
70 : 장경간 합성형교에서의 조인트부
10: slab
11: pillar
13: shift
14: pier
15: outside point connecting steel
16: inner point connecting steel
17: Precast Girder
19: slab concrete
21: pedestal concrete
22: teaching device
31: Outer point temporary construction
32: medial point temporary material
33: Precast Girder
35: rising holding
36: slab concrete
37: slab concrete connecting bar
38: alternate end connecting rebar
39: alternating connection concrete
40: pier connecting concrete
51: rebar temporary hole
52: connecting plate
53: girder exposed rebar
54: connecting rebar
55: pier connecting bars
56: pull out plate
65: alternate connecting rebar
66: alternate end connecting rebar
70: Joint part in long span composite girder bridge

Claims (8)

2경간 이상의 연속 합성형교에 있어서,
교대 및 교각과, 상기 교대의 상단에 마련되는 외측지점 가설재 및 상기 교각의 상단에 마련되는 내측지점 가설재와, 상기 내측지점 가설재 위에서 맞닿도록 외측지점 가설재 및 내측지점 가설재 상에 설치되며 미리 압축력이 도입된 프리캐스트 거더와, 상기 내측지점 가설재 위에 프리캐스트 거더의 상승 상태를 유지할 수 있도록 마련되는 상승유지 고임재와, 상기 프리캐스트 거더 위에 타설되는 슬래브 콘크리트와, 상기 교대와 프리캐스트 거더 및 슬래브 콘크리트를 일체화시키는 교대 연결 콘크리트와, 상기 교각과 프리캐스트 거더 사이에 설치되는 교좌장치를 포함하여,
교각부 내측지점에서 발생하는 부모멘트는 상기 내측지점 가설재 위에서 맞닿은 두 개의 프리캐스트 거더를 서로 연결하고, 서로 연결된 프리캐스트 거더의 내측지점을 상기 상승유지 고임재를 설치하여 1차 상승시킨 상태에서 슬래브 콘크리트를 타설하여 유지시킨 후, 1차 상승된 프리캐스트 거더를 하강시켜 도입되는 대응 압축력으로 상쇄시키고, 교대부 상부 슬래브 및 하부기초에서 발생하는 부모멘트 및 정모멘트는 내측지점을 다시 2차 상승시켜 도입되는 대응 프리스트레싱으로 상쇄시킨 프리캐스트 거더를 이용한 교대 일체형 연속 합성형교.
In continuous composite bridges with two or more spans,
Alternating and pier, an outer point temporary member provided at the upper end of the shift and an inner point temporary member provided at the upper end of the pier, and installed on the outer point temporary member and the inner branch temporary member to abut on the inner branch temporary member, the compressive force is introduced in advance The precast girder, a rising holding solid material provided to maintain the precast girder on the inner point temporary member, the slab concrete placed on the precast girder, the shift, the precast girder and the slab concrete. Including alternate connection concrete to integrate and a bridge device installed between the pier and the precast girder,
The parent cement generated at the inner point of the pier connects two precast girders contacted with each other on the inner point temporary member and the slab in the state where the inner point of the connected precast girders is first elevated by installing the rising holding material. After pouring and maintaining concrete, the first raised precast girder is lowered and offset by the corresponding compressive force introduced, and the parent and static moments generated in the alternating upper slab and lower foundation raise the inner point second again. Alternating-integrated continuous composite bridge using precast girders offset by the corresponding prestressing introduced.
제 1항에 있어서,
상기 슬래브 콘크리트는 상기 프리캐스트 거더를 내측지점 가설재에서 상승유지 고임재를 이용하여 1차 상승시킨 후 타설되고,
상기 교대 연결 콘크리트는 상기 프리캐스트 거더를 하강시킨 후 타설되는 프리캐스트 거더를 이용한 교대 일체형 연속 합성형교.
The method of claim 1,
The slab concrete is poured after the precast girder is first raised by using the rising holding material from the inner point temporary construction material,
The alternating connection concrete alternately integrated continuous composite bridge using a precast girder that is poured after the precast girder is lowered.
제 2항에 있어서,
상기 프리캐스트 거더의 2차 상승량은 1차 상승량보다 작은 프리캐스트 거더를 이용한 교대 일체형 연속 합성형교.
The method of claim 2,
The second ascending amount of the precast girder is alternately integrated using the precast girder smaller than the first ascending amount. Continuous composite bridge.
제 1항 내지 제 3항 중 어느 한 항에 있어서,
경간별로 독립 제작되는 단위 프리캐스트 거더는 프리스트레스트 콘크리트 거더, 프리플렉스 거더, 강박스 거더 중 어느 하나를 포함하는 프리캐스트 거더를 이용한 교대 일체형 연속 합성형교.
4. The method according to any one of claims 1 to 3,
Unit precast girders independently manufactured by span are alternate integral continuous composite bridges using precast girders including any one of prestressed concrete girders, preflex girders, and steel box girders.
교대와, 교좌장치가 설치되지 않은 교각의 교좌받침 콘크리트 상단에 각각 외측지점 가설재와 내측지점 가설재를 설치하는 단계;
경간별로 독립되어 제작된 단위 프리캐스트 거더를 상기 외측지점 가설재와 내측지점 가설재 위에 거치시키는 단계;
거치된 각각의 프리캐스트 거더를 내측지점 가설재 위에서 서로 연결시키는 단계;
연결된 프리캐스트 거더를 내측지점 가설재에서 1차 상승시키는 단계;
슬래브 콘크리트를 타설 및 양생시키는 단계;
1차 상승시킨 프리캐스트 거더를 하강시키는 단계;
교대와 프리캐스트 거더 및 슬래브 콘크리트를 일체화시키는 교대 연결 콘크리트를 타설 및 양생시키는 단계; 및
1차 상승 후 하강시킨 프리캐스트 거더를 2차 상승시키고 교좌장치를 설치하는 단계;로 이루어진 프리캐스트 거더를 이용한 교대 일체형 연속 합성형교의 시공법.
On the top of the bridge bearing concrete of the bridges and bridges without bridges Installing an outer branch temporary member and an inner branch temporary member;
Mounting unit precast girders independently manufactured by spans on the outer branch temporary members and the inner branch temporary members;
Connecting each of the mounted precast girders to each other on the medial point provisional member;
Firstly raising the connected precast girder at the medial point provisional member;
Placing and curing slab concrete;
Lowering the first raised precast girder;
Placing and curing alternating connecting concrete integrating the shift with the precast girder and the slab concrete; And
Constructing a shift integrated continuous composite bridge using a precast girder;
제 5항에 있어서,
외측지점부인 교대와 프리캐스트 거더의 연결에 있어서,
상기 프리캐스트 거더 단부의 측면에는 거더노출철근을 하면에는 연결플레이트가 설치된 프리캐스트 거더를 교대 위 가설재에 거치시킨 후, 연결플레이트와 인발방지 플레이트를 서로 관통하여 연결되는 연결철근를 설치하고, 교대에서 노출되어진 교대연결철근과 프리캐스트 거더 단부의 측면에서 노출되어진 거더노출철근을 서로 연결하고, 교대 단부에서 노출되어진 교대 단부 연결철근과 슬래브 콘크리트에서 노출되어진 슬래브 콘크리트 연결 철근을 서로 연결한 후, 상기 모두를 감싸는 연결콘크리트를 타설하여 교대와 거더를 일체화시키도록 한 프리캐스트 거더를 이용한 교대 일체형 연속 합성형교의 시공법.
6. The method of claim 5,
In the connection of the shift part of the outer branch and the precast girder,
On the side of the end of the precast girder, when the girder exposed rebar is mounted, the precast girder on which the connecting plate is installed is mounted on the temporary placing material on the shift, and then the connecting rebar is connected to each other through the connecting plate and the pull-out plate, and is exposed from the shift. Connect the exposed girder bar and the exposed girder bar on the side of the precast girder end, connect the exposed end bar and the slab concrete bar in slab concrete. Construction method of continuous integral composite bridges using alternating precast girders, incorporating alternating wrap concrete to integrate shifts and girders.
제 5항에 있어서,
4경간 이상의 교대 일체형 합성형교를 2경간 또는 3경간의 연속 합성형교 형태로 시공하여 연속 합성형교의 끝단이 교각 위에 위치할 때, 교각과 빔을 일체화시키지 않고 연속화시키는 프리캐스트 거더를 이용한 교대 일체형 연속 합성형교의 시공법.
6. The method of claim 5,
Alternating continuous continuous bridge using precast girders to construct continuous composite bridges of four or more spans in the form of two or three spans of continuous composite bridges. Construction method of composite bridge.
제 7항에 있어서,
교각 위에 위치하는 상기 2경간 또는 3경간의 연속 합성형교의 끝단은 교좌장치 위에 설치되는 프리캐스트 거더를 이용한 교대 일체형 연속 합성형교의 시공법.
8. The method of claim 7,
The end of the two-span or three-span continuous composite bridge is located on the bridge piers construction method of the alternate integral continuous composite bridge using a precast girder installed on the bridge device.
KR1020110055686A 2011-06-09 2011-06-09 A integral abutment continuous composite bridge using precast girder and the construction method thereof KR101228107B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110055686A KR101228107B1 (en) 2011-06-09 2011-06-09 A integral abutment continuous composite bridge using precast girder and the construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110055686A KR101228107B1 (en) 2011-06-09 2011-06-09 A integral abutment continuous composite bridge using precast girder and the construction method thereof

Publications (2)

Publication Number Publication Date
KR20120136639A KR20120136639A (en) 2012-12-20
KR101228107B1 true KR101228107B1 (en) 2013-02-01

Family

ID=47903969

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110055686A KR101228107B1 (en) 2011-06-09 2011-06-09 A integral abutment continuous composite bridge using precast girder and the construction method thereof

Country Status (1)

Country Link
KR (1) KR101228107B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101405040B1 (en) * 2013-08-30 2014-06-27 구민세 Method making prestressed concrete/steel compositive girder and method constructing the girder bridge using prestressed concrete/steel compositive girder

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108517780B (en) * 2018-04-04 2019-11-26 武汉理工大学 Composite beam steel reinforced concrete joining section consolidates and micromatic setting

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR960009273B1 (en) * 1993-04-01 1996-07-16 구민세 P.s composite beam for making continuous beam and construction method by p.s composite baem
KR100328320B1 (en) 1998-10-08 2002-07-03 구민세 The Construction and Repair Method of Continuous Girder Bridges by lifting and lowering the inner support.

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR960009273B1 (en) * 1993-04-01 1996-07-16 구민세 P.s composite beam for making continuous beam and construction method by p.s composite baem
KR100328320B1 (en) 1998-10-08 2002-07-03 구민세 The Construction and Repair Method of Continuous Girder Bridges by lifting and lowering the inner support.

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101405040B1 (en) * 2013-08-30 2014-06-27 구민세 Method making prestressed concrete/steel compositive girder and method constructing the girder bridge using prestressed concrete/steel compositive girder

Also Published As

Publication number Publication date
KR20120136639A (en) 2012-12-20

Similar Documents

Publication Publication Date Title
KR100941066B1 (en) Prestressed-precast-segmental open spendral concrete arch bridge and its constructing method
KR101042674B1 (en) Continuous composite rahmen bridge using precast girder and the construction method thereof
KR100958014B1 (en) Construction method of steel composite girder bridge
KR100889273B1 (en) Construction method for rhamen bridge
KR101178876B1 (en) Prestressed composit rahmen bridge construdtion method
JP2007077630A (en) Continuous girder using precast main-girder segment, and its erection method
KR100522170B1 (en) Method of constructing simple and continuous composite bridges
KR101208231B1 (en) Method for constructing continuous supporting structure of corrugated steel web PSC beam
KR101182084B1 (en) Method making the prestressed precast girder of Rahmen structure induced a compressive stress by a support with hinge and method constructing Rahmen bridge thereof
KR20090115481A (en) Construction method using arch type hybrid girder
KR100974305B1 (en) Continuous beam bridge construction method using girder for multi-span
KR20120065218A (en) The rahmen bridge construction technique for which tendon and the connection support stand was used
KR20120053869A (en) Bridge construction method using precast end-block with girder connection member
KR101243777B1 (en) Rahmen bridge using composite structure of corrugated steel web and concrete member and constructing method thereof
KR100894650B1 (en) Rahmen bridge with preflexion load and manufacturing method the same
KR100911148B1 (en) Lightened Coping for bridge
KR101165572B1 (en) Middle span plate girder bridge and construction method thereof
KR100909004B1 (en) Hybrid composite girder continuous bridge and constructing method therefor
KR101228107B1 (en) A integral abutment continuous composite bridge using precast girder and the construction method thereof
KR101232329B1 (en) Integral bridge and construction method using arched and concrete-filled tube
KR101607485B1 (en) Curved-psc girder with outrigger and curved-psc girder bridge construction method therewith
KR101067717B1 (en) Process for producing prestressed concrete girder and concrete girder structure
KR20090072876A (en) Manufacturing method of prestressed concrete beams with additional prestress introduced by H-beam and steel plate
KR100724739B1 (en) Construction method of PSC Girder bridge using Retensionable and Detensionable anchorage with unbonded tendon
KR101358176B1 (en) Continuous precast girder bridge and the construction method thereof

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20151109

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20161221

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20171127

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20181115

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20191204

Year of fee payment: 8