CN108517780B
CN108517780B CN201810298707.3A CN201810298707A CN108517780B CN 108517780 B CN108517780 B CN 108517780B CN 201810298707 A CN201810298707 A CN 201810298707A CN 108517780 B CN108517780 B CN 108517780B
Authority
CN
China
Prior art keywords
steel
limit beam
reinforced concrete
joining section
upper limit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201810298707.3A
Other languages
Chinese (zh)
Other versions
CN108517780A (en
Inventor
张培林
蒋玲茜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan University of Technology WUT
Original Assignee
Wuhan University of Technology WUT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan University of Technology WUT filed Critical Wuhan University of Technology WUT
Priority to CN201810298707.3A priority Critical patent/CN108517780B/en
Publication of CN108517780A publication Critical patent/CN108517780A/en
Application granted granted Critical
Publication of CN108517780B publication Critical patent/CN108517780B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of composite beam steel reinforced concrete joining section is firm and micromatic setting, including top jack mechanism, middle part connection screw thread steel and lower support bracket, top jack mechanism includes the upper limit beam being oppositely arranged and lower limit beam and the jack for connecting upper limit beam and lower limit beam, and crossbeam and cantilever beam are close to or are pushed down to lower limit beam;Lower support bracket is fixed on support jig, middle part connection screw thread steel from top to bottom sequentially passes through upper limit beam, lower limit beam and lower support bracket, and it is fixed by nut and lower support bracket, by the nut on upper limit beam as adjustable limit, the relative position of top jack mechanism and middle part connection screw thread steel is limited.Composite beam steel reinforced concrete joining section proposed by the present invention consolidates and micromatic setting, improve stability of the composite beam construction steel reinforced concrete joining section in asymmetric casting concrete, and it is highly-safe, the longitudinal absolute altitude and cross fall of fine position steel reinforced concrete joining section can also be jacked by adjusting jack.

Description

Composite beam steel reinforced concrete joining section consolidates and micromatic setting
Technical field
It is consolidated the present invention relates to technical field of bridge construction more particularly to a kind of composite beam steel reinforced concrete joining section and fine tuning fills It sets.
Background technique
Steel structure bridge is a kind of bridge for using steel as major bearing structures, with the continuous improvement of technical level, Mountable steel bridge is all widely applied all over the world.
Currently, concreting is symmetrical in being extremely difficult on joining section girder steel in steel reinforced concrete joining section work progress, exist It topples possibility.Concreting when on joining section girder steel generally using unilateral counterweight or it is interim it is affixed by the way of steel reinforced concrete is connected Section plays firm effect.In other side increase equivalent counterweight to keep balancing while unilateral counterweight method is casting concrete, Have the advantages that it is easy to operate, do not injure girder steel base material, but counterweight loading velocity and quantity are not easy to control, and safety coefficient It is low.Temporarily affixed method is by welding that girder steel is temporarily affixed with bracket, forms girder steel and lower bracket and stablizes entirety, has Advantage easy for construction, at low cost, still, this method is high to lower bracket stability requirement and welding operation injures girder steel mother Material, limiting factor are more.Steel reinforced concrete joining section mostly as the controlling component being connect with steel structure bridge closure section, longitudinal absolute altitude and Cross fall directly influences the difficulty or ease and integral linear of closure section installation, the absolute altitude and slope using closure section itself general at present Degree adjustment is used as closure section installation method, but the method is unresolved for steel reinforced concrete joining section absolute altitude and gradient offset issue, construction Difficulty is big, installs linear poor.
Summary of the invention
The main purpose of the present invention is to provide a kind of composite beam steel reinforced concrete joining section is firm and micromatic setting, it is intended to improve folded Stability of the beam construction steel reinforced concrete joining section in asymmetric casting concrete is closed, and highly-safe, it can also be vertical to steel reinforced concrete joining section It is finely adjusted to absolute altitude and cross fall.
To achieve the above object, the present invention provides that a kind of composite beam steel reinforced concrete joining section is firm and micromatic setting, including top Jack mechanism, middle part connection screw thread steel and lower support bracket, wherein
The top jack mechanism include the upper limit beam being oppositely arranged and lower limit beam and connection upper limit beam and The crossbeam and cantilever beam that need to consolidate or finely tune component are close to or are pushed down to the jack of lower limit beam, lower limit beam;
The lower support bracket is fixed on support jig, and middle part connection screw thread steel from top to bottom sequentially passes through upper limit Beam, lower limit beam and lower support bracket, upper limit beam, the reserved required screw thread of lower limit beam and lower support bracket middle part Hole, and fixed by nut and lower support bracket, by the nut on upper limit beam as adjustable limit, limit top thousand The relative position of Jin Ding mechanism and middle part connection screw thread steel.
Preferably, the lower limit beam is Two bors d's oeuveres i-beam frame.
Preferably, the jack is stood on lower limit beam, is pushed down at the top of jack by upper limit beam.
Preferably, the lower support bracket includes the steel pipe pile bracket being fixed on support jig, is placed on middle part connection Gasket and steel nut on screw-thread steel.
Preferably, the steel pipe pile bracket is fixed by welding with support jig.
Preferably, the junction of the middle part connection screw thread steel and upper limit beam and lower limit beam is provided with gasket.
Preferably, multiple jack are installed between the upper limit beam and lower limit beam.
Composite beam steel reinforced concrete joining section proposed by the present invention consolidates and micromatic setting, and structure is simple, swift to operate, improves Stability of the composite beam construction steel reinforced concrete joining section in asymmetric casting concrete, it is highly-safe, and girder steel base material is not injured, at This is low, and the longitudinal absolute altitude and cross fall of fine position steel reinforced concrete joining section can also be jacked by adjusting jack, reduces closure section Difficulty of construction guarantees that bridge installation is linear.
Detailed description of the invention
Fig. 1 consolidates for composite beam steel reinforced concrete joining section of the present invention and the structural schematic diagram of micromatic setting preferred embodiment;
Fig. 2 consolidates for composite beam steel reinforced concrete joining section of the present invention and the structural representation of micromatic setting middle and upper part jack mechanism Figure;
Fig. 3 consolidates for composite beam steel reinforced concrete joining section of the present invention and micromatic setting middle and lower part supports the structural schematic diagram of bracket.
In figure, the top 1- jack mechanism, the middle part 2- connection screw thread steel, 3- lower support bracket, 4- girder steel, 5- branch support Frame, 11- upper limit beam, 12- jack, 13- lower limit beam, 31- steel pipe pile bracket, 32- gasket, 33- steel nut.
The embodiments will be further described with reference to the accompanying drawings for the realization, the function and the advantages of the object of the present invention.
Specific embodiment
It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not intended to limit the present invention.
It should be noted that in the description of the present invention, term " transverse direction ", " longitudinal direction ", "upper", "lower", "front", "rear", The orientation or positional relationship of the instructions such as "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outside" is based on attached drawing institute The orientation or positional relationship shown, is merely for convenience of description of the present invention and simplification of the description, and is not the dress of indication or suggestion meaning It sets or element must have a particular orientation, be constructed and operated in a specific orientation, therefore should not be understood as to limit of the invention System.
Referring to figs. 1 to Fig. 3, in this preferred embodiment, a kind of composite beam steel reinforced concrete joining section is firm and micromatic setting, including upper Portion's jack mechanism 1, middle part connection screw thread steel 2 and lower support bracket 3, wherein
Top jack mechanism 1 includes the upper limit beam 11 being oppositely arranged and lower limit beam 13 and connection upper limit beam 11 With the jack 12 of lower limit beam 13, crossbeam and cantilever beam are close to or are pushed down to lower limit beam 13;
Lower support bracket 3 is fixed on support jig 5, and middle part connection screw thread steel 2 from top to bottom sequentially passes through upper limit Beam 11, lower limit beam 13 and lower support bracket 3, upper limit beam 11, lower limit beam 13 and 3 middle part of lower support bracket are reserved (upper limit beam 11, lower limit beam 13 and lower support bracket 3 are cased with required threaded hole with 2 junction of middle part connection screw thread steel Nut), and it is fixed by nut and lower support bracket 3, by the nut on upper limit beam 11 as adjustable limit, limitation The relative position of top jack mechanism 1 and middle part connection screw thread steel 2.
Specifically, lower limit beam 13 is Two bors d's oeuveres i-beam frame, and frame is between adjacent gooseneck.Upper limit beam 11 uses I-steel It is made.Jack 12 is stood on vertically on lower limit beam 13, is pushed down at the top of jack 12 by upper limit beam 11.
Referring to Fig. 3, lower support bracket 3 includes the steel pipe pile bracket 31 being fixed on support jig 5, is placed on middle part connection Gasket 32 and steel nut 33 on screw-thread steel 2.Steel pipe pile bracket 31 is fixed with support jig 5 by welding.Steel pipe pile bracket 31 bottom plate reserved screwed hole, so that middle part connection screw thread steel 2 passes through.
The junction of middle part connection screw thread steel 2 and upper limit beam 11 and lower limit beam 13 is provided with gasket 32.
Referring to Fig. 2, it is equipped between upper limit beam 11 and lower limit beam 13 in multiple jack 12(the present embodiment figures with two For a).
This composite beam steel reinforced concrete joining section is firm and micromatic setting the use process is as follows.
1, whole device is put up according to drawing, middle part connection screw thread steel 2 is passed through into steel pipe pile bracket 31, and tighten steel spiral shell Cap 33 is allowed to fixed with steel pipe pile bracket 31.
2, the steel nut 33 on upper limit beam 11 is tightened, jack 12 jacks up upper limit beam 11, makes the bottom of lower limit beam 13 It is close to or pushes down crossbeam and cantilever beam in portion.
3, longitudinal direction absolute altitude and cross fall according to needed for closure section construction, by the jacking position for being adjusted in synchronism jack 12 And the relative position of steel nut 33 and middle part connection screw thread steel 2, increase reversal interlocking relay was discharged, the work for adjusting longitudinal absolute altitude is played With, pass through it is asynchronous adjust arranged on left and right sides jack 12 jacking position and steel nut 33 and middle part connection screw thread steel 2 opposite position It sets, formation left and right pulling force is poor, plays the role of adjusting cross fall.
4, after full-bridge closure, confirmation lower limit beam 13 is compressed, and tightens the steel nut 33 on lower limit beam 13, fixed lower limit Position beam 13 position, after concreting, steel nut 33 on loose upper limit beam 11 withdraws from upper limit beam 11 and jack 12 .
The composite beam steel reinforced concrete joining section that the present embodiment proposes consolidates and micromatic setting, and structure is simple, swift to operate, improves Stability of the composite beam construction steel reinforced concrete joining section in asymmetric casting concrete, it is highly-safe, and it is female not injure girder steel 4 Material, it is at low cost, the longitudinal absolute altitude and cross fall of fine position steel reinforced concrete joining section can also be jacked by adjusting jack, are reduced and are closed Imperial section difficulty of construction guarantees that bridge installation is linear.
The above is only a preferred embodiment of the present invention, is not intended to limit the scope of the invention, all to utilize this hair Equivalent structure transformation made by bright specification and accompanying drawing content is applied directly or indirectly in other relevant technical fields, Similarly it is included within the scope of the present invention.

Claims (7)

1. a kind of composite beam steel reinforced concrete joining section consolidates and micromatic setting, which is characterized in that connect including top jack mechanism, middle part Connect screw-thread steel and lower support bracket, wherein
The top jack mechanism includes the upper limit beam being oppositely arranged and lower limit beam and connection upper limit beam and lower limit The crossbeam and cantilever beam that need to consolidate or finely tune component are close to or are pushed down to the jack of position beam, lower limit beam;
The lower support bracket is fixed on support jig, middle part connection screw thread steel from top to bottom sequentially pass through upper limit beam, Lower limit beam and lower support bracket, upper limit beam, the reserved required threaded hole of lower limit beam and lower support bracket middle part, and It is fixed by nut and lower support bracket, by the nut on upper limit beam as adjustable limit, limits top jack The relative position of mechanism and middle part connection screw thread steel.
2. composite beam steel reinforced concrete joining section as described in claim 1 consolidates and micromatic setting, which is characterized in that the lower limit beam For Two bors d's oeuveres i-beam frame.
3. composite beam steel reinforced concrete joining section as described in claim 1 consolidates and micromatic setting, which is characterized in that the jack is vertical In on lower limit beam, pushed down at the top of jack by upper limit beam.
4. composite beam steel reinforced concrete joining section as described in claim 1 consolidates and micromatic setting, which is characterized in that the lower support Bracket include the steel pipe pile bracket being fixed on support jig, be placed on middle part connection screw thread steel on gasket and steel nut.
5. composite beam steel reinforced concrete joining section as claimed in claim 4 consolidates and micromatic setting, which is characterized in that the steel-pipe pile ox Leg is fixed by welding with support jig.
6. composite beam steel reinforced concrete joining section as described in claim 1 consolidates and micromatic setting, which is characterized in that the middle part connection The junction of screw-thread steel and upper limit beam and lower limit beam is provided with gasket.
7. the composite beam steel reinforced concrete joining section as described in any one of claim 1 to 6 is firm and micromatic setting, feature exist In being equipped with multiple jack between the upper limit beam and lower limit beam.
CN201810298707.3A 2018-04-04 2018-04-04 Composite beam steel reinforced concrete joining section consolidates and micromatic setting Expired - Fee Related CN108517780B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810298707.3A CN108517780B (en) 2018-04-04 2018-04-04 Composite beam steel reinforced concrete joining section consolidates and micromatic setting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810298707.3A CN108517780B (en) 2018-04-04 2018-04-04 Composite beam steel reinforced concrete joining section consolidates and micromatic setting

Publications (2)

Publication Number Publication Date
CN108517780A CN108517780A (en) 2018-09-11
CN108517780B true CN108517780B (en) 2019-11-26

Family

ID=63431896

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810298707.3A Expired - Fee Related CN108517780B (en) 2018-04-04 2018-04-04 Composite beam steel reinforced concrete joining section consolidates and micromatic setting

Country Status (1)

Country Link
CN (1) CN108517780B (en)

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101935985B (en) * 2010-09-19 2011-11-23 湖南路桥建设集团公司 Mid-span closure method for steel box girder of cable stayed bridge
KR101228107B1 (en) * 2011-06-09 2013-02-01 구호원 A integral abutment continuous composite bridge using precast girder and the construction method thereof
CN102691266B (en) * 2012-06-03 2014-04-16 中交第四公路工程局有限公司 Construction method for ultrahigh combined support for bridge side span cast-in-situ section
CN105735138A (en) * 2016-04-12 2016-07-06 上海公路桥梁(集团)有限公司 Construction method for steel-concrete joint section of bridge
CN106759880A (en) * 2016-12-29 2017-05-31 上海建工五建集团有限公司 Prefabricated superposed beam quickly positions adjustment frock and method with prefabricated post junction
CN107841951B (en) * 2017-09-28 2023-08-01 苏交科集团股份有限公司 Preloading device for controlling pier top concrete cracks of steel-concrete composite girder bridge and construction method

Also Published As

Publication number Publication date
CN108517780A (en) 2018-09-11

Similar Documents

Publication Publication Date Title
CN106120568B (en) The construction method of cross a river Main Bridge bridge pier secondary locking temporary consolidation structure
CN206722404U (en) Horizontal reinforcing apparatus of narrow end wall unilateral formwork
CN105971272B (en) Assembled aluminum template masonry shearwalls reinforced concrete structural column and construction method
CN106836547B (en) The construction method of prefabricated assembled shear wall structure
CN107558730A (en) The formwork support method and support system of Super High girder with rolled steel section en cased in concrete
CN112538822A (en) Bridge rectangular high-pier single-pier capping beam triangular bracket system and construction method
CN109680568A (en) The linear adjustment equipment of track girder and method
CN107859058A (en) A kind of cast-in-place concrete retaining wall anti-incline anti-floating large steel moulding plate device and installation method
CN108590177A (en) K plates bracing means and its reinforcement means
CN111622482A (en) Simple support frame for steel structure overhanging plate edge and mounting method thereof
CN109235265A (en) System for track girder of constructing
CN108517780B (en) Composite beam steel reinforced concrete joining section consolidates and micromatic setting
CN207700669U (en) A kind of bracing means of builder's jack and laminated floor slab
CN208456130U (en) K plate bracing means
CN211341789U (en) Wall form reinforcing tool
CN106567538B (en) A kind of positioning mold of toilet concrete flanging
CN108708297A (en) Punching stick anchor ear support device
CN206397136U (en) Assembled aluminum template masonry shearwalls reinforced concrete structural column
CN208668289U (en) Punching stick anchor ear support device
CN107023154A (en) A kind of new builder's jack component and its construction method
CN205975377U (en) Structure is concretied in locking of cross a river bridge owner pier secondary temporarily
CN206512744U (en) Gallery formwork-support device in a kind of concrete dam body
CN212773372U (en) Simple support frame for steel structure overhanging plate edge
CN206971267U (en) The mobile device of underground pipe gallery formwork
CN108457193B (en) Box beam skew web plate formwork erecting structure and its erection method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191126

Termination date: 20200404

CF01 Termination of patent right due to non-payment of annual fee