CN108265620A - The Integral Abutment construction method and Integral Abutment of jointless bridge - Google Patents

The Integral Abutment construction method and Integral Abutment of jointless bridge Download PDF

Info

Publication number
CN108265620A
CN108265620A CN201810313523.XA CN201810313523A CN108265620A CN 108265620 A CN108265620 A CN 108265620A CN 201810313523 A CN201810313523 A CN 201810313523A CN 108265620 A CN108265620 A CN 108265620A
Authority
CN
China
Prior art keywords
abutment
section
integral
poured
changeover portion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810313523.XA
Other languages
Chinese (zh)
Inventor
王先前
刘培雷
林松
代亮
董桔灿
吴庆雄
薛俊青
夏少华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Municipal Design and Research Institute Co Ltd
Original Assignee
Shenzhen Municipal Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Municipal Design and Research Institute Co Ltd filed Critical Shenzhen Municipal Design and Research Institute Co Ltd
Priority to CN201810313523.XA priority Critical patent/CN108265620A/en
Publication of CN108265620A publication Critical patent/CN108265620A/en
Priority to CN201810985931.XA priority patent/CN108867344B/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of Integral Abutment construction methods of jointless bridge, are included in cushion cap upper end construction abutment supporting section, and cushion cap is fixedly connected on pile foundation upper end;Pour section template and temporary support system after placing abutment on abutment supporting section, and temporary support system be located at abutment after pour in section template, and back-up sand in section template is poured after abutment;Construction abutment changeover portion in the back-up sand in section template is poured after abutment, abutment changeover portion upper end is consolidated with girder for one-piece casting, after the completion of longitudinal prestressing steel Shu Zhangla in girder, wash out the back-up sand poured after abutment in section template, casting concrete in section template is poured after abutment to pour section after forming abutment and conserve, and section is poured after abutment changeover portion, abutment and abutment supporting section is from top to bottom sequentially connected and forms the Integral Abutment of jointless bridge.A kind of Integral Abutment of jointless bridge is also disclosed, the Integral Abutment construction method and Integral Abutment of the jointless bridge improve prestressed importing degree.

Description

The Integral Abutment construction method and Integral Abutment of jointless bridge
Technical field
The present invention relates to bridge technology field, more particularly to a kind of Integral Abutment construction method of jointless bridge And the Integral Abutment of jointless bridge.
Background technology
The common beam bridge in China is the bridge for having expansion joint and bearing at present.However, the rapid wears structure such as expansion joint and bearing Part is brought a great deal of trouble to bridge late maintaining and repair;Therefore, at present for overall length it is smaller in, foot bridge, designer by Gradually be keen to using the seamless beam bridge of monoblock type, i.e., the form consolidated using bridge pier, abutment and girder, eliminate bridge bearing and Expansion joint absorbs girder because of the longitudinal deformation under temperature action by pier, platform and back filling behind abutment soil.It is smaller by (one for span As be less than 20m) beam bridge, generally using ordinary reinforced concrete integral seamless beam bridge, but for the larger bridge of span, in order to Meet normal real requirement, generally can all apply certain longitudinal prestressing to girder.According to one-piece casting it is complete apply again it is pre- Stress, due to the hyperstatic influence of the seamless beam bridge of monoblock type, especially headwall rigidity is larger so that girder longitudinal prestressing can not It is effectively applied in girder, prestressing force importing degree is extremely inefficient, and headwall cracking even occurs in stretching process in some It may.Therefore how efficiently prestressing force is imported into girder, is the subject that a designer is worth research.
Invention content
The object of the present invention is to provide a kind of Integral Abutment construction method of jointless bridge and jointless bridges Integral Abutment, to solve the above-mentioned problems of the prior art, improve prestressed importing degree, solve post-stressed The construction difficult problem of monoblock type jointless beam bridge abutment.
To achieve the above object, the present invention provides following schemes:
The present invention provides a kind of Integral Abutment construction method of jointless bridge, includes the following steps:
Step 1:After pile foundation of constructing and cushion cap, abutment supporting section of constructing in the cushion cap upper end, the cushion cap is fixedly connected In the pile foundation upper end;
Step 2:Section template and temporary support system are poured, and described interim after abutment is placed on the abutment supporting section Support system is poured in section template, and back-up sand in section template is poured after abutment after being located at the abutment;
Step 3:It constructs abutment changeover portion, the abutment changeover portion is located in the back-up sand poured after the abutment in section template, The abutment changeover portion upper end is consolidated with the girder for one-piece casting, and the longitudinal prestressing steel Shu Zhangla in the girder is completed Afterwards, the back-up sand poured after the abutment in section template is washed out, is poured after the abutment after casting concrete forms abutment in section template It pours section and conserves, section is poured after the abutment changeover portion, the abutment and the abutment supporting section is from top to bottom sequentially connected and shape Into the Integral Abutment of the jointless bridge.
Preferably, the cushion cap and the abutment supporting section pour simultaneously, height and the nothing of the abutment supporting section The ratio of the height of the Integral Abutment of expansion joint bridge is [1/3,1/2].
Preferably, before the cushion cap casting concrete, the pre-buried abutment stress main reinforcement in the formwork for placing of the cushion cap, The abutment stress main reinforcement is not blocked from the cushion cap along the elongated setting of the Integral Abutment of jointless bridge height, The abutment stress main reinforcement upper end and girder reinforcement welding pre-buried in the formwork for placing of the girder.
Preferably, section template and the temporary support are poured after placing the abutment after the top surface dabbing of the abutment supporting section System.
Preferably, it is poured after the abutment in section template after back-up sand, the pre-buried connecting key in back-up sand, the connecting key is described in It is extended upwardly in back-up sand in the formwork for placing of the abutment changeover portion.
Preferably, it in step 3, washes out and the back-up sand in section template is poured after the abutment and to clean the abutment supporting section naked Behind the top surface of dew and the exposed bottom surface of the abutment changeover portion, the exposed bottom surface of abutment changeover portion described in dabbing.
Preferably, the clapboard that the rear portion of section template tilts backwards setting from the bottom to top for one, and institute are poured after the abutment The bottom end for stating clapboard is flushed with the rear end face of the abutment supporting section, and the upper end of the clapboard is located at the abutment changeover portion 10~15cm of rear end face rear forms grout groove between the abutment changeover portion, and the upper end of the clapboard is higher by the bridge Platform changeover portion 10~15cm of bottom surface is so as to pour the bottom that section top of the platform back of the body envelopes the abutment changeover portion platform back of the body after the abutment End.
Preferably, it is poured after the abutment and gas vent is offered in section template, poured section after the abutment and vibrate and pour.
The present invention also provides a kind of Integral Abutment of jointless bridge, the Integral Abutments of the jointless bridge For being connected to cushion cap upper end, the cushion cap is connected to pile foundation upper end, and the Integral Abutment of the jointless bridge is uses The Integral Abutment construction method of jointless bridge as described above is constructed the Integral Abutment of jointless bridge to be formed, The Integral Abutment of the jointless bridge pours section and abutment after including sequentially connected abutment supporting section, abutment from the bottom to top Changeover portion, the abutment changeover portion are used to consolidate with the girder one-piece casting of bridge, pour to be provided in section after the abutment and are used for The temporary support system that section pours abutment changeover portion described in front support is poured after the abutment, section is poured after the abutment as the master Longitudinal prestressing steel Shu Zhangla in beam pours section after completing the abutment that after-pouring is formed.
Preferably, the height that section is poured after the abutment is 50~70cm, and the temporary support system includes multiple shaped steel branch Component is supportted, the junction of the abutment changeover portion and the girder forms transition chamfered section.
The present invention achieves following technique effect relative to the prior art:
The Integral Abutment construction method of jointless bridge provided by the invention and the beam front axle of jointless bridge Platform pours section after girder completes tensioning longitudinal prestressing steel beam and then pours abutment, makes girder that system transition occur with abutment And it is integrally formed connection.Tensioning longitudinal prestressing steel beam, prestressing force are mainly acted on girder before system transition, system transition Main beam structure close to statically determinate structure body, prestressed tensioning second inner force very little, therefore can reduce in prestressed tensioning time Power, so as to lose prestressing force on abutment, thus most prestressing force can be imported in girder, and it is pre- to effectively increase longitudinal direction The importing degree of stress.The Integral Abutment construction method of jointless bridge provided by the invention and the entirety of jointless bridge Formula abutment, using wet seam principle, simply, connection is reliable, maintenance is convenient;Nothing is effectively reduced by the method for system transition to stretch The tensioning second inner force of the Integral Abutment of contracting seam bridge, improves prestressed importing degree, solves post-stressed entirety The construction difficult problem of formula jointless beam bridge abutment.
Description of the drawings
It in order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to institute in embodiment Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the present invention Example, for those of ordinary skill in the art, without creative efforts, can also obtain according to these attached drawings Obtain other attached drawings.
Fig. 1 is the front view of the Integral Abutment of jointless bridge provided by the invention;
Fig. 2 is the A-A sectional views of the Integral Abutment of the jointless bridge in Fig. 1;
Fig. 3 pours the close-up schematic view of section after the abutment for the Integral Abutment of the jointless bridge in Fig. 2;
Fig. 4 is the B-B sectional views of the Integral Abutment of the jointless bridge in Fig. 2;
In figure:1- pile foundations;2- cushion caps;3- abutment supporting sections;Section is poured after 4- abutments;41- clapboards;5- abutment changeover portions; 6- abutment stress main reinforcements;7- temporary support systems;8- connecting keys;9- girders;11- longitudinal prestressing steel beams;13- abutment sidewalls.
Specific embodiment
Below in conjunction with the attached drawing in the embodiment of the present invention, the technical solution in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained every other without making creative work Embodiment shall fall within the protection scope of the present invention.
The object of the present invention is to provide a kind of Integral Abutment construction method of jointless bridge and jointless bridges Integral Abutment, to solve the above-mentioned problems of the prior art, improve prestressed importing degree, solve post-stressed The construction difficult problem of monoblock type jointless beam bridge abutment.
In order to make the foregoing objectives, features and advantages of the present invention clearer and more comprehensible, it is below in conjunction with the accompanying drawings and specific real Applying mode, the present invention is described in further detail.
As shown in figures 1-4, the present invention provides a kind of Integral Abutment construction method of jointless bridge, including following Step:
Step 1:After pile foundation 1 of constructing and cushion cap 2, abutment supporting section 3 of constructing above cushion cap 2, cushion cap 2 is above pile foundation 1 It sets and is fixedly connected with pile foundation 1;
Step 2:Section template and temporary support system 7, and temporary support system are poured after placing abutment on abutment supporting section 3 System 7 is poured in section template, and back-up sand in section template is poured after abutment after being located at abutment, and 7 later stage of temporary support system does not remove;
Step 3:It constructs abutment changeover portion 5 and girder 9, abutment changeover portion 5 is located at the back-up sand poured after abutment in section template On, 5 upper end of abutment changeover portion is consolidated with 9 one-piece casting of girder girder;
After the concrete that abutment changeover portion 5 and girder 9 pour reaches predetermined age, the longitudinal direction in tensioning girder 9 in advance should Power steel beam 11, the general longitudinal prestressing steel beam 11 using in jack tension girder, middle longitudinal prestressing steel beam 11 in girder 9 After completing tensioning, you can remove jack;After the completion of 11 tensioning of longitudinal prestressing steel beam in girder 9, section is poured after washing out abutment Back-up sand in template, and clean the exposed top surface of abutment supporting section 3 and the exposed bottom surface of abutment changeover portion 5;
It pours casting concrete in section template after abutment to pour section 4 after forming abutment and conserve, after abutment changeover portion 5, abutment It pours section 4 and abutment supporting section 3 is from top to bottom sequentially connected and forms the Integral Abutment of jointless bridge.
The Integral Abutment of jointless bridge provided by the invention, it is non-telescope for monoblock type using wet joint form Bridge is stitched, the Integral Abutment of jointless bridge is for being connected to cushion cap upper end, and cushion cap is connected to pile foundation upper end, such as Fig. 1~4 Shown, the Integral Abutment of jointless bridge after sequentially connected abutment supporting section 3, abutment from the bottom to top including pouring 4 and of section Abutment changeover portion 5, girder 9, abutment changeover portion 5 are consolidated with 9 one-piece casting of girder, and the girder 9 of bridge is prestressed concrete Box beam, girder 9 is interior to be equipped with longitudinal prestressing steel beam 11, pours to be provided in section 4 after abutment and be propped up for being poured after abutment before section pours 4 The temporary support system 7 of abutment changeover portion is supportted, after the completion of section 4 is poured after abutment as 11 tensioning of longitudinal prestressing steel beam in girder 9 Section is poured after pouring the abutment to be formed.
The Integral Abutment construction method of jointless bridge provided by the invention is constructed in monoblock type jointless beam bridge In the process, section 4 is poured after girder 9 completes tensioning longitudinal prestressing steel beam 11 and then pours abutment, girder 9 is made to be sent out with abutment Raw system transition is simultaneously integrally formed connection.Tensioning longitudinal prestressing steel beam 11 before system transition, prestressing force mainly acts on master On beam 9, the main beam structure of system transition can reduce pre- close to statically determinate structure body, prestressed tensioning second inner force very little The tensioning second inner force of stress, so as to lose prestressing force on abutment, thus most prestressing force can be imported in girder 9, Effectively increase the importing degree of longitudinal prestressing.The Integral Abutment construction method of jointless bridge provided by the invention, is adopted With wet seam principle, simply, connection is reliable, maintenance is convenient;Jointless bridge is effectively reduced by the method for system transition Integral Abutment tensioning second inner force, improve prestressed importing degree, it is non-telescope to solve post-stressed monoblock type Stitch the construction difficult problem of beam bridge abutment.
During the Integral Abutment construction of jointless bridge provided by the invention, cushion cap and abutment supporting section pour simultaneously, The ratio of the height of abutment supporting section and the height of the Integral Abutment of jointless bridge is [1/3,1/2].
Before 2 casting concrete of cushion cap, pre-buried abutment stress main reinforcement 6, abutment stress main reinforcement in the formwork for placing of cushion cap 2 6 do not block from cushion cap 2 along the elongated setting of the Integral Abutment of jointless bridge height.
It is poured after abutment in section template after back-up sand, pre-buried connecting key 8, connecting key 8 are extended upwardly to from back-up sand in back-up sand In the formwork for placing of abutment changeover portion 5, connecting key 8 selects reinforcing bar, can enhance the company that section 4 and abutment changeover portion 5 are poured after abutment Connect performance.Abutment steel bar stress 6 is welded with main force's main reinforcement in girder 9.
During the Integral Abutment construction of jointless bridge provided by the invention, put after the top surface dabbing of abutment supporting section 3 Section template and temporary support system 7 are poured after putting abutment.After washing out the back-up sand poured after abutment in section template, dabbing abutment changeover portion 5 Exposed bottom surface.
The exposed bottom surface dabbing of the top surface dabbing and abutment changeover portion 5 of abutment supporting section 3 can enhance the bridge of after-pouring The switching performance between section 7 and abutment supporting section 6 below and the abutment changeover portion 5 of top is poured after platform, enhances the steady of abutment It is qualitative.
During the Integral Abutment construction of jointless bridge provided by the invention, pour after abutment the rear portion of section template for one by Under the supreme clapboard 41 for tilting backwards setting, and the bottom end of clapboard 41 is flushed with the rear end face of abutment supporting section 3, clapboard 41 upper end is located at 5 10~15cm of rear end face rear of abutment changeover portion and grout groove, clapboard is formed between abutment changeover portion 5 41 upper end is higher by 5 10~15cm of bottom surface of abutment changeover portion so that the top that 4 back ofs the body of section are poured after abutment envelopes abutment changeover portion 5 The bottom end of the platform back of the body.
Section 4 is poured after abutment in mold process is poured, passes through the clapboard 41 of template rear end so that poured after abutment section template with Grout groove is formed between abutment changeover portion 5, convenient for pouring pouring for section 4 after abutment;The upper end of clapboard 41 is located at abutment changeover portion 5 10~15cm of rear end face rear so that the platform back of the body that section 4 forms wedge-type shape is poured after abutment, the upper end of clapboard 41 is higher by abutment mistake Cross 5 10~15cm of bottom surface of section so that poured after abutment section 4 formation wedge-type shape platform the back of the body be also higher by abutment after pour 5 bottom of section 10~15cm of face so that the tops that the back of the body of section 4 is poured after abutment envelope the bottom ends of 5 back ofs the body of abutment changeover portion, poured after abutment section 4 with It is very close to each other between abutment changeover portion 5, it ensure that the density of the two contact.
During the Integral Abutment construction of jointless bridge provided by the invention, poured after abutment and exhaust is offered in section template Hole, pours section 4 after abutment and vibrates and pour.It pours section 4 after abutment to pour using microdilatancy pea gravel concreten, pouring concrete after can improving Density, and the connection for improving new-old concrete structure connects energy.It is poured after abutment and offers gas vent in section template so that after abutment Pouring can realize in 4 casting process of section and fully vibrate, and ensure to pour the density of the concrete of section 4 after abutment.
The height that section 4 is poured after abutment is 50~70cm, and temporary support system 7 includes multiple type steel support components, abutment mistake Cross section 5 and the transition chamfered section of the junction formation 100cm*100cm of girder 9;Abutment sidewall 13 is located on cushion cap 2, and is located at To stop that 2 rear of cushion cap is banketed, abutment sidewall 13 is connect respectively with cushion cap 2, abutment and girder 9 for the side of abutment and girder 9.
Specific case is applied in the present invention to be expounded the principle of the present invention and embodiment, above example Illustrate to be merely used to help understand method and its core concept of the invention;Meanwhile for those of ordinary skill in the art, according to According to the thought of the present invention, in specific embodiments and applications there will be changes.In conclusion the content of the present specification It should not be construed as limiting the invention.

Claims (10)

1. a kind of Integral Abutment construction method of jointless bridge, it is characterised in that:Include the following steps:
Step 1:After pile foundation of constructing and cushion cap, abutment supporting section of constructing in the cushion cap upper end, the cushion cap is fixedly connected on institute State pile foundation upper end;
Step 2:Section template and temporary support system, and the temporary support are poured after placing abutment on the abutment supporting section System is poured in section template, and back-up sand in section template is poured after abutment after being located at the abutment;
Step 3:It constructs abutment changeover portion, the abutment changeover portion is located in the back-up sand poured after the abutment in section template, described Abutment changeover portion upper end is consolidated with the girder for one-piece casting, after the completion of the longitudinal prestressing steel Shu Zhangla in the girder, The back-up sand poured after the abutment in section template is washed out, casting concrete in section template is poured after the abutment and pours section after forming abutment And conserve, section is poured after the abutment changeover portion, the abutment and the abutment supporting section is from top to bottom sequentially connected and forms institute State the Integral Abutment of jointless bridge.
2. the Integral Abutment construction method of jointless bridge according to claim 1, it is characterised in that:The cushion cap It is poured simultaneously with the abutment supporting section, the height of the abutment supporting section and the Integral Abutment of the jointless bridge The ratio of height is [1/3,1/2].
3. the Integral Abutment construction method of jointless bridge according to claim 1, it is characterised in that:The cushion cap Before casting concrete, the pre-buried abutment stress main reinforcement in the formwork for placing of the cushion cap, the abutment stress main reinforcement is described in Is not blocked along the elongated setting of the Integral Abutment of jointless bridge height in cushion cap, the abutment stress main reinforcement upper end with Pre-buried girder reinforcement welding in the formwork for placing of the girder.
4. the Integral Abutment construction method of jointless bridge according to claim 1, it is characterised in that:The abutment Section template and the temporary support system are poured after the abutment is placed after the top surface dabbing of supporting section.
5. the Integral Abutment construction method of jointless bridge according to claim 1, it is characterised in that:The abutment After pour in section template after back-up sand, the pre-buried connecting key in back-up sand, the connecting key extends upwardly to the bridge from the back-up sand In the formwork for placing of platform changeover portion.
6. the Integral Abutment construction method of jointless bridge according to claim 4, it is characterised in that:Step 3 In, it pours the back-up sand in section template after washing out the abutment and cleans the exposed top surface of the abutment supporting section and the abutment transition Behind the exposed bottom surface of section, the exposed bottom surface of abutment changeover portion described in dabbing.
7. the Integral Abutment construction method of jointless bridge according to claim 1, it is characterised in that:The abutment The clapboard that the rear portion of section template tilts backwards setting from the bottom to top for one, and the bottom end of the clapboard and the abutment are poured afterwards The rear end face of supporting section flushes, the upper end of the clapboard be located at the abutment changeover portion rear end face 10~15cm of rear with institute State and grout groove formed between abutment changeover portion, the upper end of the clapboard be higher by 10~15cm of the abutment changeover portion bottom surface so that The bottom end that section top of the platform back of the body envelopes the abutment changeover portion platform back of the body is poured after the abutment.
8. the Integral Abutment construction method of jointless bridge according to claim 1, it is characterised in that:The abutment After pour gas vent offered in section template, pour section after the abutment and vibrate and pour.
9. a kind of Integral Abutment of jointless bridge, the Integral Abutment of the jointless bridge is used to be connected to cushion cap Upper end, the cushion cap are connected to pile foundation upper end, it is characterised in that:The Integral Abutment of the jointless bridge is using right The jointless bridge to be formed it is required that the Integral Abutment construction method of the jointless bridge described in any one of 1~8 is constructed Integral Abutment, the Integral Abutment of the jointless bridge includes sequentially connected abutment supporting section, bridge from the bottom to top Section and abutment changeover portion are poured after platform, the abutment changeover portion is used to consolidate with the girder one-piece casting of bridge, be poured after the abutment It is provided with to pour the temporary support system that section pours abutment changeover portion described in front support, the abutment after the abutment in section It pours afterwards after section completes the abutment of after-pouring formation for the longitudinal prestressing steel Shu Zhangla in the girder and pours section.
10. the Integral Abutment of jointless bridge according to claim 9, it is characterised in that:Section is poured after the abutment Height for 50~70cm, the temporary support system includes multiple type steel support components, the abutment changeover portion and the master The junction of beam forms transition chamfered section.
CN201810313523.XA 2018-04-10 2018-04-10 The Integral Abutment construction method and Integral Abutment of jointless bridge Pending CN108265620A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201810313523.XA CN108265620A (en) 2018-04-10 2018-04-10 The Integral Abutment construction method and Integral Abutment of jointless bridge
CN201810985931.XA CN108867344B (en) 2018-04-10 2018-08-28 Integral bridge abutment construction method of bridge without expansion joint and integral bridge abutment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810313523.XA CN108265620A (en) 2018-04-10 2018-04-10 The Integral Abutment construction method and Integral Abutment of jointless bridge

Publications (1)

Publication Number Publication Date
CN108265620A true CN108265620A (en) 2018-07-10

Family

ID=62777504

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201810313523.XA Pending CN108265620A (en) 2018-04-10 2018-04-10 The Integral Abutment construction method and Integral Abutment of jointless bridge
CN201810985931.XA Active CN108867344B (en) 2018-04-10 2018-08-28 Integral bridge abutment construction method of bridge without expansion joint and integral bridge abutment

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201810985931.XA Active CN108867344B (en) 2018-04-10 2018-08-28 Integral bridge abutment construction method of bridge without expansion joint and integral bridge abutment

Country Status (1)

Country Link
CN (2) CN108265620A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110983983A (en) * 2019-12-20 2020-04-10 同济大学建筑设计研究院(集团)有限公司 Construction method of fixed end beam and fixed end beam structure

Family Cites Families (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100555433B1 (en) * 2003-06-17 2006-02-24 주식회사 국민씨아이 Structure of Integral Abutment with Concrete Filled Composite Pile for Jointless Bridge and Its Construction Method
JP2005060964A (en) * 2003-08-08 2005-03-10 Kurosawa Construction Co Ltd Construction method for girder bridge
KR100972884B1 (en) * 2008-05-13 2010-07-28 한국도로공사 Construction method of semi-integral abutment bridge using steel box girder
KR100891979B1 (en) * 2008-11-28 2009-04-08 주식회사 승화이엔씨 Jointless bridge using duplicate abutment
CN102061667B (en) * 2011-01-27 2012-10-17 河南省新开元路桥工程咨询有限公司 Method for arranging semi-integral hidden expansion joint for abutment and bridge girder
RU119752U1 (en) * 2012-05-17 2012-08-27 Блум Интернешионал, ЛЛК SEAMLESS BRIDGE
CN202705923U (en) * 2012-07-17 2013-01-30 中铁二十三局集团有限公司 Assembling platform installed close to bridge abutment roadbed
JP5784573B2 (en) * 2012-11-02 2015-09-24 柳沢コンクリート工業株式会社 Floor slab bridge
CN104612173B (en) * 2015-01-29 2016-05-04 福州大学 A kind of seamless bridge neotectonics and construction method thereof that adopts ultra-high performance concrete stake
CN204551448U (en) * 2015-02-05 2015-08-12 福州大学 A kind of composite and flexible stake and the Integral Abutment Bridge based on it construct
CN104631436B (en) * 2015-02-05 2016-05-04 福州大学 Improve the method for Integral Abutment supporting pile stress performance with H type concrete-pile
CN104831618B (en) * 2015-04-20 2016-07-06 福州大学 A kind of abutment reaming structure optimizing Integral Abutment Bridge deformability
KR101653606B1 (en) * 2015-09-25 2016-09-02 우경기술주식회사 Method for constructing integral abutment bridge
CN105442457B (en) * 2016-01-06 2017-02-01 福州大学 Construction structure and method for extending bridge floor plate bridge filled with fine sand
CN105970800B (en) * 2016-05-23 2017-12-26 长安大学 The abutment connecting structure and its construction method of monoblock type combination beam is seamless bridge
CN106065564B (en) * 2016-06-07 2018-01-12 长安大学 A kind of seamless bridge of steel-concrete combined structure monoblock type
CN207143733U (en) * 2017-04-28 2018-03-27 山西省交通科学研究院 A kind of simple-supported thencontinuous bridge system converting system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110983983A (en) * 2019-12-20 2020-04-10 同济大学建筑设计研究院(集团)有限公司 Construction method of fixed end beam and fixed end beam structure
CN110983983B (en) * 2019-12-20 2021-11-16 同济大学建筑设计研究院(集团)有限公司 Construction method of fixed end beam and fixed end beam structure

Also Published As

Publication number Publication date
CN108867344B (en) 2023-07-28
CN108867344A (en) 2018-11-23

Similar Documents

Publication Publication Date Title
CN106677049B (en) Assembled steel-concrete combined structure bridge and construction method
CN108999097B (en) Modification structure and construction method of existing bridge abutment in bridge jacking
CN102995572B (en) The method of attachment of Thin-wall Hollow Pier and former pier stud and device thereof after bridge jacking
CN104674660A (en) Novel hollow plate hinge joint structure and construction method thereof
CN201447669U (en) Road bridge after reinforcement construction by removing beam and adding rib
CN216765936U (en) Cast-in-place concrete frame beam regularization template structure
CN107916625B (en) Widening structure and method for wide cantilever box girder
CN110374014A (en) Big span continuous beam UHPC column construction method
CN204491412U (en) A kind of hollow sheet hinge crack structure
CN108265620A (en) The Integral Abutment construction method and Integral Abutment of jointless bridge
CN102936953B (en) Construction method of a bridging-arm stiffened steel structure template
CN104532759B (en) A kind of double curvature arched bridge bridge floor widen reinforcement process method
CN208815396U (en) The Integral Abutment of jointless bridge
CN213681700U (en) Improved bridge expansion joint width construction structure
CN211446552U (en) Steel-concrete combined section structure of steel box arch bridge arch rib
CN108708285B (en) By adjusting temporary rest pier improvement combination beam internal force at bridge method
CN110847057A (en) Flexible connection structure for continuous box girder cantilever casting
CN112064487A (en) Non-prestressed continuous bridge pier top continuous section structure and construction method
CN210238900U (en) Cavity haunching large plate structure
CN219690284U (en) Steel tube concrete rigid frame bridge for high-speed railway
CN219364742U (en) Reinforced structure suitable for basic cushion cap
CN216405069U (en) High-speed railway continuous beam arch composite structure of quick construction
CN218234014U (en) Ultra-long concrete building structure provided with connector prestressed tendons
CN216428794U (en) Assembled multi-cavity composite concrete frame column
CN211848948U (en) Sliding consolidation structure for continuous box girder cantilever pouring

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180710

WD01 Invention patent application deemed withdrawn after publication