CN110374014A - Big span continuous beam UHPC column construction method - Google Patents

Big span continuous beam UHPC column construction method Download PDF

Info

Publication number
CN110374014A
CN110374014A CN201910733636.XA CN201910733636A CN110374014A CN 110374014 A CN110374014 A CN 110374014A CN 201910733636 A CN201910733636 A CN 201910733636A CN 110374014 A CN110374014 A CN 110374014A
Authority
CN
China
Prior art keywords
segment
uhpc
number section
uhpc column
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910733636.XA
Other languages
Chinese (zh)
Other versions
CN110374014B (en
Inventor
杨纪
怀臣子
徐世俊
张阳
冯仲林
陈阳阳
杨磊
宋银平
黄毅
余方亮
魏星
黄泰鑫
赵海增
郭坤领
熊东
张铎
王睿
管曼羽
张小涛
高香玉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yellow River Engineering Consulting Co Ltd
Original Assignee
Yellow River Engineering Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yellow River Engineering Consulting Co Ltd filed Critical Yellow River Engineering Consulting Co Ltd
Priority to CN201910733636.XA priority Critical patent/CN110374014B/en
Publication of CN110374014A publication Critical patent/CN110374014A/en
Application granted granted Critical
Publication of CN110374014B publication Critical patent/CN110374014B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • E01D21/105Balanced cantilevered erection

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a kind of big span continuous beam UHPC column construction methods, step is that 1. 2. 0 number section UHPC column segment is installed in prefabricated U HPC column segment on main pier bracket, pour normal concrete, stretch-draw prestressing force beam, 3. assembled Hanging Basket installs 1 number section UHPC column segment on hanging basket formwork, 1 number section UHPC column segment is positioned by the U-shaped fixing steel plate of 0 number section UHPC column segment, and the opposite cast-in-place connector face structure of the two and U-shaped fixing steel plate constitute diamond shape casting chamber and are 4. poured intracavitary cast-in-place RPC to diamond shape, 1 number section normal concrete is poured again, stretch-draw prestressing force beam, and it is mobile, assembled Hanging Basket remaining design of 5. constructing has the concrete segment of UHPC column 6. to construct other common prestressed concrete segments and closure segment, complete construction.Structure of the invention is ingenious, easy to operate, convenient to carry out, reduces secondary formwork erection interference, ensure that UHPC prefabricated post pours effective combination of connector with after, solves the problems, such as that structure across prestressed concrete continuous beam greatly deforms sustainable growth due to shrinkage and creep bring.

Description

Big span continuous beam UHPC column construction method
Technical field
The present invention relates to bridge construction technology fields, more particularly, to a kind of big span continuous beam UHPC column construction method.
Background technique
Big shrinkage and creep of the span continuous beam (continuous rigid frame) during operation due to concrete brings mid-span deflection to continue Increase as the common problem in science of bridge building.UHPC (Ultra-High Performance Concrete) is a kind of superelevation Can concrete material, with superelevation compression strength, flexural strength, toughness, compared to normal concrete, in UHPC process for preparation It joined reactive powder, the feature that shrinkage is extremely low, Creep Coefficient is small showed after thermal curing.Based on the feature, research Personnel, which imagine, is arranged UHPC column in continuous beam pressurized zone, to solve structure across prestressed concrete continuous beam greatly due to shrinking Bring of creeping deforms the problem of sustainable growth.However, how designing bridge structure, simplifying construction procedure, reduce construction cost It is applied to problem urgently to be resolved in the construction of big span continuous beam as UHPC.
Summary of the invention
To solve the above-mentioned problems, the present invention provides a kind of big span continuous beam UHPC column construction method, can take following skill Art scheme:
Big span continuous beam UHPC column construction method of the present invention, includes the following steps:
The first step, prefabricated U HPC column segment are provided with longitudinal reinforcement, the both ends setting of UHPC column segment in UHPC column segment There is cast-in-place connector face structure, and wherein one end of UHPC column segment is coated with the positioning of the U-shaped for connecting adjacent UHPC column segment Steel plate, the bottom plate of the U-shaped fixing steel plate, left plate are welded with WELDING STUDS inside and outside right side plate;
Second step sets up bracket by main pier, installs 0 number section UHPC column segment at bottom in template later, then pour 0 Number section normal concrete, after concrete strength reaches design requirement, 0 number section prestressing tendon of tensioning, and assembled symmetrical cantilever is applied Work Hanging Basket;
Third step, installs 1 number section UHPC column segment on hanging basket formwork, and 1 number section UHPC column segment passes through 0 number section UHPC column segment U-shaped fixing steel plate positioned, and the opposite cast-in-place connector face structure of the two and U-shaped fixing steel plate constitute diamond shape and are poured chamber;
4th step is poured intracavitary cast-in-place RPC to the diamond shape of third step, then pours 1 number section normal concrete, reaches to concrete strength To after design requirement, 1 number section prestressing tendon of tensioning, and mobile, assembled symmetrical cantilever construction Hanging Basket;
5th step, according to Step 3: four method, successively remaining design is completed in construction the concrete segment of UHPC column;
6th step is successively constructed other common prestressed concrete segments and closure segment according to conventional construction method, completes bridge Construction.
The total length that design described in every span centre has the concrete segment of UHPC column is the 1/4-1/5 of main span across footpath.
The design, which has the concrete segment of UHPC column to be arranged side by side along bridge wide direction, 1-10 root UHPC column segment.
The advantage of the invention is that it is clever structure, easy to operate, convenient to carry out, secondary formwork erection interference can be effectively reduced, Guarantee that UHPC prefabricated post pours effective combination of connector with after, is able to solve structure across prestressed concrete continuous beam greatly due to shrinking Bring of creeping deforms the problem of sustainable growth, provides technical support for the construction of big span continuous beam of UHPC column is arranged.
Detailed description of the invention
Fig. 1-7 is construction procedure schematic diagram of the invention.
Fig. 8 is the portion A enlarged drawing in Fig. 2.
Fig. 9 is the I-I sectional view of Fig. 8.
Specific embodiment
Big span continuous beam UHPC column construction method of the present invention is illustrated with specific embodiment below.
As shown in figs. 1-7, above-mentioned construction method includes the following steps:
The first step, prefabricated U HPC column segment 1 are provided with longitudinal reinforcement 1.1 in each UHPC column segment 1 as shown in Figure 8,9, The both ends of UHPC column segment 1 are provided with the cast-in-place connector face structure 1.2 of middle part indent, and wherein one end packet of UHPC column segment 1 It is covered with the U-shaped fixing steel plate 1.3 for connecting adjacent UHPC column segment, bottom plate, left plate, the right side plate of U-shaped fixing steel plate 1.3 Inside and outside be welded with WELDING STUDS 1.4;
Second step sets up bracket by main pier, and carries out precompressed to bracket, installs 0 number section at bottom in template later UHPC column segment, then 0 number section normal concrete is poured, after concrete strength reaches design strength 90%, 0 number section of tensioning is answered in advance Power beam, and the assembled symmetrical cantilever construction Hanging Basket 2 in 0 number section;Generally, according to design scheme, UHPC column segment is wide along bridge Direction, which is arranged side by side, 1-10 root.
Third step, installs 1 number section UHPC column segment on hanging basket formwork, and 1 number section passes through the U-shaped of 0 number section UHPC column segment Fixing steel plate 1.3 is positioned, and the cast-in-place connector face structure 1.2 and the composition diamond shape casting of U-shaped fixing steel plate 1.3 that the two is opposite Chamber 1.5(is shown in Fig. 8);
4th step, the cast-in-place RPC (Reactive Powder Concrete) into the diamond shape of third step casting chamber 1.5, makes two UHPC column segments It connects integral, then pours 1 number section normal concrete again, after concrete strength reaches design strength 90%, 1 number section of tensioning Prestressing tendon, and mobile, assembled symmetrical cantilever construction Hanging Basket 2;
5th step, according to Step 3: four method, successively remaining design is completed in construction the concrete segment of UHPC column;Generally Ground, in bridge often across design have UHPC column concrete segment total length be bridge main span across footpath 1/4-1/5, the present embodiment The middle concrete segment for having UHPC column that designs is 0-8 number section.
6th step is successively constructed other common prestressed concrete segments and closure segment according to conventional construction method, is completed Bridge construction.
Specifically, for common prestressed concrete segment, it is first poured normal concrete, when concrete strength reaches design After intensity 90%, then the tensioning segment prestressing tendon moves, assembled symmetrical cantilever construction Hanging Basket 2, repeats aforesaid operations, according to Secondary all common prestressed concrete segments of construction.
When carrying out closure segment construction, abutment pier collateral branch frame, and the pouring construction end bay beam section on bracket are first set up, then basis Sequence, closure segment of successively constructing are closed up in design.
Finally, striking, construction bridge deck, traffic engineering and other affiliated facilities, complete bridge construction.
Using the big span continuous beam constructed of the present invention, compared with common big span continuous beam, 10 years shrinkage and creeps it is caused across Middle vertical displacement reduces about 40%-50%, and hogging moment area structure corner reduces about 40%, can sufficiently avoid structure due to shrinking Xu The problem of becoming bring deformation sustainable growth, effectively improves service life greatly across prestressed concrete continuous beam.

Claims (3)

1. a kind of big span continuous beam UHPC column construction method, characterized by the following steps:
The first step, prefabricated U HPC column segment are provided with longitudinal reinforcement, the both ends setting of UHPC column segment in UHPC column segment There is cast-in-place connector face structure, and wherein one end of UHPC column segment is coated with the positioning of the U-shaped for connecting adjacent UHPC column segment Steel plate, the bottom plate of the U-shaped fixing steel plate, left plate are welded with WELDING STUDS inside and outside right side plate;
Second step sets up bracket by main pier, installs 0 number section UHPC column segment at bottom in template later, then pour 0 Number section normal concrete, after concrete strength reaches design requirement, 0 number section prestressing tendon of tensioning, and assembled symmetrical cantilever is applied Work Hanging Basket;
Third step, installs 1 number section UHPC column segment on hanging basket formwork, and 1 number section UHPC column segment passes through 0 number section UHPC column segment U-shaped fixing steel plate positioned, and the opposite cast-in-place connector face structure of the two and U-shaped fixing steel plate constitute diamond shape and are poured chamber;
4th step is poured intracavitary cast-in-place RPC to the diamond shape of third step, then pours 1 number section normal concrete, reaches to concrete strength To after design requirement, 1 number section prestressing tendon of tensioning, and mobile, assembled symmetrical cantilever construction Hanging Basket;
5th step, according to Step 3: four method, successively remaining design is completed in construction the concrete segment of UHPC column;
6th step is successively constructed other common prestressed concrete segments and closure segment according to conventional construction method, completes bridge Construction.
2. big span continuous beam UHPC column construction method according to claim 1, it is characterised in that: design described in every span centre has The total length of the concrete segment of UHPC column is the 1/4-1/5 of main span across footpath.
3. big span continuous beam UHPC column construction method according to claim 1, it is characterised in that: the design has UHPC column Concrete segment along bridge wide direction be arranged side by side have 1-10 root UHPC column segment.
CN201910733636.XA 2019-08-09 2019-08-09 Construction method of long-span continuous beam UHPC column Active CN110374014B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910733636.XA CN110374014B (en) 2019-08-09 2019-08-09 Construction method of long-span continuous beam UHPC column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910733636.XA CN110374014B (en) 2019-08-09 2019-08-09 Construction method of long-span continuous beam UHPC column

Publications (2)

Publication Number Publication Date
CN110374014A true CN110374014A (en) 2019-10-25
CN110374014B CN110374014B (en) 2021-06-25

Family

ID=68258804

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910733636.XA Active CN110374014B (en) 2019-08-09 2019-08-09 Construction method of long-span continuous beam UHPC column

Country Status (1)

Country Link
CN (1) CN110374014B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111119071A (en) * 2020-01-16 2020-05-08 中建七局安装工程有限公司 Construction method for assembling precast concrete segment box girder
CN112081017A (en) * 2020-08-20 2020-12-15 河南五建建设集团有限公司 Construction method for assembling prefabricated cantilever on long-span segment of bridge to span existing bridge
CN112523061A (en) * 2020-11-24 2021-03-19 广西交通设计集团有限公司 UHPC stiffened prestressed concrete box girder bridge structure and construction process thereof

Citations (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BE648279A (en) * 1963-05-25 1964-09-16
US5437072A (en) * 1992-01-23 1995-08-01 J. Muller International Rapid transit viaduct with post-tensioning cable system
KR20110047500A (en) * 2009-10-30 2011-05-09 고려대학교 산학협력단 Orthotropic steel bridge deck with improved fatigue strength having UHPC pavement and polyurethane foam tamping and constructing method of the same
CN203559329U (en) * 2013-11-11 2014-04-23 中铁第一勘察设计院集团有限公司 Steel-RPC (reactive powder concrete) combined bridge
CN104131510A (en) * 2014-07-17 2014-11-05 湖南大学 Prefabricated reactive powder concrete (RPC) beam joint connecting method
JP2015061967A (en) * 2006-12-21 2015-04-02 ラファルジュ Structural element and production process thereof
CN104746416A (en) * 2015-02-03 2015-07-01 湖南大学 Technology for solving long-term downwarping of large-span PC box girder bridge through prefabricated reactive powder concrete (RPC) columns
US20160060859A1 (en) * 2014-09-03 2016-03-03 Halfen Gmbh Structure having a strengthening element made of high-strength concrete for increasing punching shear strength
CN206328864U (en) * 2016-11-30 2017-07-14 上海建工二建集团有限公司 Assembled beam-column node structure
CN207277614U (en) * 2017-09-26 2018-04-27 华南理工大学 A kind of assembled steel plate concrete combined shear wall flat shape piecing connection structure
CN207277570U (en) * 2017-09-26 2018-04-27 华南理工大学 A kind of assembled steel plate concrete combined shear wall concave-convex piecing connection structure
US9988775B1 (en) * 2017-12-04 2018-06-05 The Florida International University Board Of Trustees Concrete i-beam for bridge construction
CN207700481U (en) * 2017-11-20 2018-08-07 中国航天建设集团有限公司 Concrete rib beam splice and assembly concrete girt strip
CN109057116A (en) * 2018-08-15 2018-12-21 湖南大学 A kind of ultra-high performance concrete sandwich floor slab and its manufacturing method
CN109281249A (en) * 2018-11-16 2019-01-29 福州大学 A kind of UHPC-NC overlapping trestle deck structrue and its construction method
CN208440963U (en) * 2018-06-07 2019-01-29 广州市市政工程设计研究总院有限公司 A kind of UHPC small box girder structure
CN109487686A (en) * 2018-12-29 2019-03-19 武汉理工大学 A kind of unit construction bridge panel transverse joint using UHPC grouting material
CN109763433A (en) * 2019-01-23 2019-05-17 开封市农村公路管理处 A kind of Fabricated Beam-Slab Bridge reinforcement means

Patent Citations (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BE648279A (en) * 1963-05-25 1964-09-16
US5437072A (en) * 1992-01-23 1995-08-01 J. Muller International Rapid transit viaduct with post-tensioning cable system
JP2015061967A (en) * 2006-12-21 2015-04-02 ラファルジュ Structural element and production process thereof
KR20110047500A (en) * 2009-10-30 2011-05-09 고려대학교 산학협력단 Orthotropic steel bridge deck with improved fatigue strength having UHPC pavement and polyurethane foam tamping and constructing method of the same
CN203559329U (en) * 2013-11-11 2014-04-23 中铁第一勘察设计院集团有限公司 Steel-RPC (reactive powder concrete) combined bridge
CN104131510A (en) * 2014-07-17 2014-11-05 湖南大学 Prefabricated reactive powder concrete (RPC) beam joint connecting method
US20160060859A1 (en) * 2014-09-03 2016-03-03 Halfen Gmbh Structure having a strengthening element made of high-strength concrete for increasing punching shear strength
CN104746416A (en) * 2015-02-03 2015-07-01 湖南大学 Technology for solving long-term downwarping of large-span PC box girder bridge through prefabricated reactive powder concrete (RPC) columns
CN206328864U (en) * 2016-11-30 2017-07-14 上海建工二建集团有限公司 Assembled beam-column node structure
CN207277614U (en) * 2017-09-26 2018-04-27 华南理工大学 A kind of assembled steel plate concrete combined shear wall flat shape piecing connection structure
CN207277570U (en) * 2017-09-26 2018-04-27 华南理工大学 A kind of assembled steel plate concrete combined shear wall concave-convex piecing connection structure
CN207700481U (en) * 2017-11-20 2018-08-07 中国航天建设集团有限公司 Concrete rib beam splice and assembly concrete girt strip
US9988775B1 (en) * 2017-12-04 2018-06-05 The Florida International University Board Of Trustees Concrete i-beam for bridge construction
CN208440963U (en) * 2018-06-07 2019-01-29 广州市市政工程设计研究总院有限公司 A kind of UHPC small box girder structure
CN109057116A (en) * 2018-08-15 2018-12-21 湖南大学 A kind of ultra-high performance concrete sandwich floor slab and its manufacturing method
CN109281249A (en) * 2018-11-16 2019-01-29 福州大学 A kind of UHPC-NC overlapping trestle deck structrue and its construction method
CN109487686A (en) * 2018-12-29 2019-03-19 武汉理工大学 A kind of unit construction bridge panel transverse joint using UHPC grouting material
CN109763433A (en) * 2019-01-23 2019-05-17 开封市农村公路管理处 A kind of Fabricated Beam-Slab Bridge reinforcement means

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
全国造价工程师执业资格培训教材编委会: "《建设工程技术与计量土木建筑工程》", 31 July 2017, 中国计划出版社 *
刘华江: "《设计师的材料清单 建筑篇》", 30 September 2017, 同济大学出版社 *
刘超等: "超高性能混凝土薄层加固法在槽形梁桥中的应用 ", 《桥梁建设》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111119071A (en) * 2020-01-16 2020-05-08 中建七局安装工程有限公司 Construction method for assembling precast concrete segment box girder
CN112081017A (en) * 2020-08-20 2020-12-15 河南五建建设集团有限公司 Construction method for assembling prefabricated cantilever on long-span segment of bridge to span existing bridge
CN112523061A (en) * 2020-11-24 2021-03-19 广西交通设计集团有限公司 UHPC stiffened prestressed concrete box girder bridge structure and construction process thereof

Also Published As

Publication number Publication date
CN110374014B (en) 2021-06-25

Similar Documents

Publication Publication Date Title
CN106677049B (en) Assembled steel-concrete combined structure bridge and construction method
CN109024225B (en) Ultra-high performance concrete truss arch piece unit, truss arch piece bridge and construction method
KR101177342B1 (en) Precast end segmet girder for continuous bridge, girder making method and bridge construction method using the same
CN110374014A (en) Big span continuous beam UHPC column construction method
CN101768916A (en) Lower flange improved corrugated steel web plate composite box girder and construction method thereof
CN110700089A (en) Cast-in-place wet joint structure and bridge
KR101886345B1 (en) CONSTRUCTION METHOD OF HYBRID RAILWAY BRIDGE USING PRESTRESSED CONCRETE FILLED TUBE and TRANSVERSE PRESTRESSED CONCRETE BLOCK
CN108951399A (en) A kind of Single-box multi-chamber box beam bridge and its construction method
KR200407182Y1 (en) Precasted concrete plate
KR101034973B1 (en) Bridge and its construction method using tide arch hybrid girders by connecting precast blocks
KR101196874B1 (en) Girder making methos for precast end seggement using end mold and girder therewith
CN114319065A (en) Main beam unit with UHPC (ultra high performance polycarbonate) formwork structure, main beam structure and construction method of main beam structure
KR20110067942A (en) Bridge having continuous arch hybrid girders and the bridge construction method using the same
CN106638265B (en) A kind of steel reinforced concrete beam rigid framed structure arch bridge
CN110004816B (en) Corrugated steel web prestress UHPC combined box girder and construction method thereof
CN201381470Y (en) Assembled variable cross-section composite continuous bridge
CN209114299U (en) A kind of Single-box multi-chamber box beam bridge
KR100462966B1 (en) Prestressed Concrete U-Girder of compositive girder bridge
CN216338993U (en) Longitudinal joint for steel-UHPC (ultra high performance concrete) assembled pi-shaped combination beam
KR100712622B1 (en) Continuous Preflex Girder Structure Using Prestress in Parent Section Using Expanded Concrete and Its Construction Method
JP2000104221A (en) Combined truss bridge and erection method of the same
KR102327700B1 (en) Girder structure and construction method for continuity of supporting portion of girder using the same
KR100975539B1 (en) Steel box continuous bridge with irruglar span or regular span and this construction technique
KR101038714B1 (en) Bridge and its construction method using tide arch hybrid girders having precast slabs
KR100469840B1 (en) Solid type Arch bridge using steel frame construction and this style of construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant