JPS6146610B2 - - Google Patents

Info

Publication number
JPS6146610B2
JPS6146610B2 JP118783A JP118783A JPS6146610B2 JP S6146610 B2 JPS6146610 B2 JP S6146610B2 JP 118783 A JP118783 A JP 118783A JP 118783 A JP118783 A JP 118783A JP S6146610 B2 JPS6146610 B2 JP S6146610B2
Authority
JP
Japan
Prior art keywords
pile
hollow
cavity
mortar
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP118783A
Other languages
Japanese (ja)
Other versions
JPS59126821A (en
Inventor
Hideo Tayama
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Daiwa Kogyo Co Ltd
Aoki Construction Co Ltd
Original Assignee
Daiwa Kogyo Co Ltd
Aoki Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Daiwa Kogyo Co Ltd, Aoki Construction Co Ltd filed Critical Daiwa Kogyo Co Ltd
Priority to JP118783A priority Critical patent/JPS59126821A/en
Publication of JPS59126821A publication Critical patent/JPS59126821A/en
Publication of JPS6146610B2 publication Critical patent/JPS6146610B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Description

【発明の詳細な説明】 本発明は基礎杭の建込み工法に関するものであ
る。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a foundation pile erection method.

一般に地盤直下に空洞のある場所に直接、構築
物を築造した場合、地盤の陥没や沈下が発生し、
その構築物は破壊される恐れがある。
Generally, when a structure is constructed directly in a place where there is a cavity directly under the ground, the ground will collapse or subside.
The structure is at risk of being destroyed.

そこで、従来はその空洞に、セメントモルタ
ル、生コンクリートやセメントバチルス等による
充填施工が実施されて来たが、次の様な問題があ
つた。即ち、(イ)充填が、その対象とする範囲に完
全に施工されたかどうかの確認が殆んど不可能か
又は非常に困難である。
Conventionally, the cavities have been filled with cement mortar, ready-mixed concrete, cement bacillus, etc., but the following problems have arisen. That is, (a) it is almost impossible or very difficult to confirm whether the filling has been completely applied to the target area.

(ロ)設計計画時に於いて、空洞の内容積が正確に
算定出来ない為充填数量の正確な把握等が殆んど
推定の域を出ず不確実である。(ハ)目的充填範囲外
への填充物の流出による地下水汚染の恐れがあ
る。
(b) At the time of design planning, the internal volume of the cavity cannot be accurately calculated, so accurate grasping of the filling quantity, etc. is almost beyond estimation and is uncertain. (c) There is a risk of groundwater contamination due to the filling material flowing out of the intended filling area.

そこで、かかる場合、確実な工法として、空洞
以深の地盤に支持層を求め、基礎杭により構築物
を支持する工法を採用するのがよいことになる地
盤直下に極めて透水性の高い層のある場合も同様
である。
Therefore, in such cases, as a reliable construction method, it is better to find a support layer in the ground deeper than the cavity and use a construction method that supports the structure with foundation piles. The same is true.

本発明は以上の工法を行うために創案されたも
ので、二重構造の杭、即ち外側に中空外管杭を、
内側に既製コンクリート杭又は鋼管杭、又は場所
打ち杭等からなる中空内管杭を使用する事によ
り、この様な地盤条件下での施工を可能にすると
共に、構築物の荷重は内側の杭で負担し、自然発
生的な、又は突発的な陥没等によつて発生する摩
擦力は外側の外管杭に作用させる様にした。
The present invention was created to carry out the above construction method, and has a double structure pile, that is, a hollow outer pipe pile on the outside.
By using hollow inner pipe piles such as ready-made concrete piles, steel pipe piles, or cast-in-place piles on the inside, it is possible to carry out construction under such ground conditions, and the load of the structure is borne by the inside piles. However, the friction force generated due to natural or sudden collapse was made to act on the outer pipe pile on the outside.

中空外管杭の建込み工法は、プレボーリング工
法であるが、その削孔の方法として泥水等の安定
液を使用する工法は、空洞の存在の為、泥水が完
全に流失して、削孔が出来なくなるばかりでな
く、地下水汚染をも招き適当でない。
The construction method for hollow outer pipe piles is the pre-boring method, but the method that uses a stabilizing liquid such as muddy water for drilling holes is difficult because the muddy water is completely washed away due to the existence of cavities. Not only will this not be possible, but it will also lead to groundwater contamination, which is inappropriate.

そこで本発明にあつては、削孔の方法を、ダウ
ンザホールハンマー、又は、アースオーガ(ロツ
クオーガー)等のドライドリリングにより行な
う。
Therefore, in the present invention, the hole drilling method is performed by dry drilling using a down-the-hole hammer, an earth auger, or the like.

この方法で所定の深度まで削孔した後、外側杭
である中空外管を建て込むが、空洞部及びその下
部の削孔が困難なときは、外側杭の外管を中掘り
工法で所定の深度まで設置する。
After drilling the hole to a specified depth using this method, the hollow outer pipe that is the outer pile is erected. However, if it is difficult to drill the hollow part and its lower part, the outer pipe of the outer pile is dug using the hollow drilling method. Install to depth.

外管建込み後その孔底に沈積しているスライム
をエアリフト等の方法により、充分排除する。孔
底の洗滌後、内側杭の既製コンクリート杭、又は
鋼管杭の建込み又は場所打ち杭の造成を行なうが
内側杭が既製コンクリート杭又は鋼管杭の場合
は、これらの杭の中空部に孔底まで達するパイプ
を降し、これより所定量のセメントミルクを注入
し、注入完了後その注入パイプを揚管して、セメ
ントミルクが硬化しない内に、前に建込んだ既製
コンクリート杭、又は鋼管杭を数十センチメート
ル引揚げて、中空部に貯溜していたセメントミル
クをその先端より流出させ中空外管と中空内管と
の間隙に充填する。
After constructing the outer pipe, thoroughly remove the slime deposited at the bottom of the hole using methods such as air lift. After cleaning the bottom of the hole, install ready-made concrete piles or steel pipe piles or cast-in-place piles as the inner piles. If the inner piles are ready-made concrete piles or steel pipe piles, the hole bottom is installed in the hollow part of these piles. After the injection is completed, the injection pipe is lifted up and the pre-built concrete pile or steel pipe pile that was erected before is removed before the cement milk has hardened. is pulled up several tens of centimeters, and the cement milk stored in the hollow part flows out from its tip and fills the gap between the hollow outer tube and the hollow inner tube.

又中空外管の外周へは、この外管の先端部分に
予め設けた数箇の開孔部より流出させる。
Further, the water flows out to the outer periphery of the hollow outer tube through several openings provided in advance at the tip of the outer tube.

その後、引揚げていた内側杭である既製コンク
リート杭又は鋼管杭を孔底まで降下し、セメント
ミルクが硬化しないうちに、内側杭をモンケン等
により打撃し、その先端が支持地盤に確実に着岩
する様にする。
After that, the ready-made concrete pile or steel pipe pile, which was the inner pile that had been pulled up, is lowered to the bottom of the hole, and before the cement milk has hardened, the inner pile is struck with a hammer etc. to ensure that its tip lands firmly on the supporting ground. do as you like.

その後、中空外管と中空内管との間隙を、砂等
により充填し、最後に、中空外管の外周の空洞よ
り上の部分をセメントミルク又はモルタル等によ
り充填するがこのとき、中空外管の所定の位置に
パツカーを設けてセメントミルクが空洞へ流失す
るのを防止する様にし、セメントミルクは外管口
元まで充填し空洞上部の地盤と鋼管を一体化させ
る。
After that, the gap between the hollow outer tube and the hollow inner tube is filled with sand, etc., and finally, the part of the outer periphery of the hollow outer tube above the cavity is filled with cement milk, mortar, etc. A packer is installed at a predetermined position to prevent the cement milk from flowing into the cavity, and the cement milk is filled up to the mouth of the outer pipe to integrate the steel pipe with the ground above the cavity.

本発明のものによれば外杭すなわち中空外管杭
を建て込む前にパツカーが外周に装着され、かつ
先端にスリツトを有する中空外管杭を打込むた
め、この杭を利用してモルタルを充填することが
できて空洞に向つてモルタルが流失することがな
い。
According to the present invention, before erecting the outer pile, that is, the hollow outer pipe pile, a packer is attached to the outer periphery, and in order to drive the hollow outer pipe pile having a slit at the tip, this pile is used to fill with mortar. This prevents mortar from being washed away into the cavity.

したがつて、根固めモルタル注入施工時及び中
空外管外周モルタル填充施工時において空洞内へ
モルタルが流亡し、地下水層の水質に影響を及ぼ
すことがなく、堅固な基礎杭がえられるという特
徴がある。
Therefore, the mortar does not flow into the cavity during the pouring of foot protection mortar and the filling of mortar around the outer circumference of the hollow outer pipe, which does not affect the water quality of the groundwater aquifer, and a strong foundation pile can be obtained. be.

以下図面に示す実施例について説明する。 The embodiments shown in the drawings will be described below.

第1図は、本発明の施工法によつて完成された
基礎杭を示すもので1は中空内管杭となる既製コ
ンクリート杭等であつて、これにより構築物2を
支持する。3は中空外管杭の鋼管杭であり、4は
地盤中に形成された空洞を示すものである。5は
プレボーリングされた孔であつて、これに前記内
側杭と外側の鋼管杭とからなる二重構造の杭が建
込まれ、孔5と杭1及び杭3の空洞下部分、孔5
と杭3の空洞上部分には、セメントミルク又はモ
ルタル6が填充され、更に杭1と杭3の間隙には
砂7が填充される。このとき、セメントミルク又
はモルタル6aが空洞4へ流失するのをパツカー
8で防止し、セメントミルク又はモルタル6bが
鋼管3の外周へ填充される為に開孔部9を設けて
おく。パツカー8はスポンジ、軟型プラスチツク
又は木材製である。
FIG. 1 shows a foundation pile completed by the construction method of the present invention, in which 1 is a ready-made concrete pile or the like that becomes a hollow inner pipe pile, and supports a structure 2. 3 is a steel pipe pile with a hollow outer pipe pile, and 4 is a hollow formed in the ground. Reference numeral 5 is a pre-bored hole, into which a double structure pile consisting of the inner pile and outer steel pipe pile is built, and the hole 5, the hollow lower part of pile 1 and pile 3, and the hole 5
The upper part of the cavity of the piles 3 is filled with cement milk or mortar 6, and the gap between the piles 1 and 3 is filled with sand 7. At this time, a packer 8 prevents the cement milk or mortar 6a from flowing into the cavity 4, and an opening 9 is provided in order to fill the outer periphery of the steel pipe 3 with the cement milk or mortar 6b. The packer 8 is made of sponge, soft plastic or wood.

次に施工の順序について説明する。 Next, the order of construction will be explained.

先ず、第2図イの様に、ダウンザホールハンマ
ー又はアースオーガー(ロツクオーガー)等の循
環泥水を使わない方法でプレボーリングをし、所
定深度(支持地盤)まで達する孔5を設ける。次
に外側の鋼管杭3を第2図ロに示したように建込
むが、このとき鋼管杭3には予めパツカー8と開
孔部9を設けて置く。建込み完了後、孔5bの底
部のスライムは、エアリフト等の方法により完全
に排除する。
First, as shown in Figure 2A, pre-boring is performed using a method that does not use circulating mud, such as a down-the-hole hammer or an earth auger, to form a hole 5 that reaches a predetermined depth (supporting ground). Next, the outer steel pipe pile 3 is erected as shown in FIG. After the construction is completed, the slime at the bottom of the hole 5b is completely removed by a method such as an air lift.

そして第2図ハに示した様に中空内管杭1を建
込んだ後この中空内管杭1の中空部に孔底まで達
するパイプ10によりセメントミルク6を注入す
る。セメントミルクは第2図ニに示した様に空洞
4へ流失しない量だけ注入する。
After erecting the hollow inner pipe pile 1 as shown in FIG. 2C, cement milk 6 is injected into the hollow part of the hollow inner pipe pile 1 through a pipe 10 reaching the bottom of the hole. Cement milk is injected into the cavity 4 in an amount that does not flow away as shown in FIG. 2D.

注入完了後はパイプ10を撤去し、セメントミ
ルクが硬化しないうちに第2図ニの様に内側杭1
のみを孔底より数十センチメートル引き揚げる。
こうすることによつてセメントミルク6bは杭1
の下端より流出し杭1と鋼管杭3の間隙を埋め、
更にスリツト9を通つて孔5bと鋼管3の間隙を
も充填することになる。そしてセメントミルク6
bが硬化しないうちに第2図ホに示した様に中空
内管杭1を元の状態に戻し、モンケン11により
適度な打撃をし、杭1の先端が支持地盤に完全に
密着する様にした後、セメントミルク6bの硬化
を待つて第2図ヘの様に中空内管杭1と中空外管
杭3との間隙を砂7で充填し、最後に杭3の外周
と削孔壁5aの間隙にセメントミルク又はモルタ
ル6aを充填するがこのとき、充填物6aが空洞
4に流失するのを防止する為、杭3の所定の位置
にパツカー8をセツトしておく。
After the injection is completed, remove the pipe 10 and insert the inner pile 1 as shown in Figure 2 D before the cement milk hardens.
The chisel is pulled up several tens of centimeters from the bottom of the hole.
By doing this, the cement milk 6b is attached to the pile 1.
It flows out from the bottom end and fills the gap between pile 1 and steel pipe pile 3.
Furthermore, the gap between the hole 5b and the steel pipe 3 is also filled through the slit 9. and cement milk 6
Before b has hardened, return the hollow inner pipe pile 1 to its original state as shown in Figure 2 e, and give it a moderate blow with the Monken 11 so that the tip of the pile 1 is in complete contact with the supporting ground. After that, after waiting for the cement milk 6b to harden, the gap between the hollow inner pipe pile 1 and the hollow outer pipe pile 3 is filled with sand 7 as shown in Fig. 2, and finally the outer periphery of the pile 3 and the drilled wall 5a are filled. Cement milk or mortar 6a is filled into the gap between the piles 3 and 3. At this time, a packer 8 is set at a predetermined position on the pile 3 in order to prevent the filling material 6a from flowing into the cavity 4.

以上の様に、本発明の方法によれば空洞のある
地盤中に公害を発生させる事なく、空洞上の地盤
の沈下、陥没を防止出来、構築物を確実に支持す
る基礎杭を築造する事が出来るのである。
As described above, according to the method of the present invention, it is possible to prevent the subsidence and collapse of the ground above the cavity without causing pollution in the ground where there is a cavity, and it is possible to construct foundation piles that reliably support the structure. It can be done.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明工法になる基礎杭の切断面図第
2図イ〜ヘは本発明工法の動作順序を示す説明図
である。 1……中空内管杭(既製コンクリート杭、鋼管
杭等)、2……構築物、3……中空外管杭(鋼管
杭)、4……空洞、5……プレボーリングによる
孔、6……セメントミルク又はモルタル、7……
砂、8……パツカー、9……スリツト、10……
注入パイプ、11……モンケン。
FIG. 1 is a cross-sectional view of a foundation pile according to the method of the present invention. FIG. 1... Hollow inner pipe pile (ready-made concrete pile, steel pipe pile, etc.), 2... Structure, 3... Hollow outer pipe pile (steel pipe pile), 4... Hollow, 5... Hole by pre-boring, 6... Cement milk or mortar, 7...
Suna, 8...Patzka, 9...Slit, 10...
Injection pipe, 11...Monken.

Claims (1)

【特許請求の範囲】[Claims] 1 基礎杭を建込む地盤中に空洞又は極めて透水
性の高い層の存在する場合先ず該空洞又は極めて
透水性の高い層の下部の堅固な地層まで穿孔を行
ない次に該孔に建て込んだ場合にその位置が空洞
又は極めて透水性の高い層の頂部の直上位置にあ
るように途中にパツカーを外周に装着しかつ先端
にスリツトを有する中空外管を建て込み、この中
空外管内に更に中空内管を建て込み、該中空内管
の内部へモルタルを注入して下端開口部より溢流
させ更に外管のスリツトを通つて中空外管の外部
へもモルタルを通して根固めを行い引き続いて外
管頂部より外管と孔壁との間の空隙内にモルタル
を充填して前記パツカー以降からモルタルが空洞
又は極めて透水性の高い層に向つて溢流しないよ
うにした基礎杭の建込み工法。
1. When there is a cavity or an extremely permeable layer in the ground where the foundation pile is to be erected, a hole is first drilled to the solid stratum below the cavity or an extremely permeable layer, and then the foundation pile is built into the hole. A hollow outer tube with a slit at the tip and a packer attached to the outer periphery is installed in the middle so that the position is directly above the top of the cavity or an extremely permeable layer. The pipe is erected, mortar is injected into the hollow inner pipe and overflows from the lower end opening, and the mortar is passed through the slit in the outer pipe to the outside of the hollow outer pipe for foot hardening, and then the top of the outer pipe is poured. A method for constructing foundation piles in which mortar is filled in the gap between the outer pipe and the hole wall to prevent mortar from overflowing from the packer onward toward the cavity or an extremely permeable layer.
JP118783A 1983-01-10 1983-01-10 Erection work of foundation pile Granted JPS59126821A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP118783A JPS59126821A (en) 1983-01-10 1983-01-10 Erection work of foundation pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP118783A JPS59126821A (en) 1983-01-10 1983-01-10 Erection work of foundation pile

Publications (2)

Publication Number Publication Date
JPS59126821A JPS59126821A (en) 1984-07-21
JPS6146610B2 true JPS6146610B2 (en) 1986-10-15

Family

ID=11494444

Family Applications (1)

Application Number Title Priority Date Filing Date
JP118783A Granted JPS59126821A (en) 1983-01-10 1983-01-10 Erection work of foundation pile

Country Status (1)

Country Link
JP (1) JPS59126821A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111549775A (en) * 2020-05-29 2020-08-18 贵州建工集团第一建筑工程有限责任公司 Hole pile construction method under karst geological condition

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102162249B (en) * 2011-05-20 2013-01-23 大连宜华建设集团有限公司 Construction method of pre-stressed high-strength concrete (PHC) pipe piles in deep ocean backfill area
JP6302288B2 (en) * 2014-03-04 2018-03-28 鹿島建設株式会社 Formwork installation method, formwork and underwater structure
CN104563147B (en) * 2014-08-29 2017-01-11 上海市政工程设计研究总院(集团)有限公司 Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation
JP6542036B2 (en) * 2015-06-02 2019-07-10 株式会社トーヨーアサノ Pile foundation structure
JP6539566B2 (en) * 2015-10-29 2019-07-03 大亜ソイル株式会社 Construction method of cast-in-place concrete pile
CN106049467A (en) * 2016-08-02 2016-10-26 中铁六局集团有限公司 Method for treating slurry leakage of bored pile through percussion drill under complex geology
CN108894214B (en) * 2018-08-27 2020-09-01 孙德明 Karst cave geological environment cast-in-place pile and pile-forming construction method thereof
CN113338259B (en) * 2021-06-02 2022-08-23 中地君豪高科股份有限公司 Construction method for treating karst cave of pile bottom bearing stratum

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111549775A (en) * 2020-05-29 2020-08-18 贵州建工集团第一建筑工程有限责任公司 Hole pile construction method under karst geological condition

Also Published As

Publication number Publication date
JPS59126821A (en) 1984-07-21

Similar Documents

Publication Publication Date Title
CN107023002A (en) Down-the-hole impacts churning composite pile pile making method
JPS6146610B2 (en)
JPS5985028A (en) Steel pipe pile and laying work thereof
JPS5847823A (en) Construction of in-place concrete pile
JP4872561B2 (en) Construction method of ready-made piles
JPH04185813A (en) Formation of soil-cement composite pile
JPH0841870A (en) Method of connection precast concrete pile
JPS601451B2 (en) Water stop mountain stop wall construction method using Benoto pile excavator
JPH0464618A (en) Pit excavation work method
JP2002054164A (en) Center of column and construction method therefor
JP3099041B2 (en) Pile construction method
JPS58120918A (en) Burying method for pile
JPS6147929B2 (en)
JPS6042114Y2 (en) embedded steel pipe pile
JPH0641956A (en) Execution method for high proof stress cast-in-place concrete pile, etc.
JPH0442493B2 (en)
JPS6312962B2 (en)
JP2783719B2 (en) Construction method of ground anchor hole under pressurized water
JPS5869924A (en) Construction of sheathing wall having upper part consisting of underground continuous wall and lower part of pillar-row pile
JPH10140557A (en) Construction method of cast-in-place diaphragm wall with hollow
JPH0415849B2 (en)
JPH08177060A (en) Buried-in pile, and buried-in pile method
JPS6130090B2 (en)
JPS62202118A (en) Burying work of pile
JPH02144410A (en) Foundation practice combining premolded pile and soil cement, etc.