JPS5869924A - Construction of sheathing wall having upper part consisting of underground continuous wall and lower part of pillar-row pile - Google Patents

Construction of sheathing wall having upper part consisting of underground continuous wall and lower part of pillar-row pile

Info

Publication number
JPS5869924A
JPS5869924A JP16946781A JP16946781A JPS5869924A JP S5869924 A JPS5869924 A JP S5869924A JP 16946781 A JP16946781 A JP 16946781A JP 16946781 A JP16946781 A JP 16946781A JP S5869924 A JPS5869924 A JP S5869924A
Authority
JP
Japan
Prior art keywords
underground continuous
continuous wall
wall
pillar
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP16946781A
Other languages
Japanese (ja)
Inventor
Yutaka Sasaki
豊 佐々木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP16946781A priority Critical patent/JPS5869924A/en
Publication of JPS5869924A publication Critical patent/JPS5869924A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/20Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE:To rationalize and economize the construction of a sheathing wall by making up the sheathing wall whose upper part consists of an underground continuous wall and whose lower part cosists of a pillar-row pile under the ground condition that the upper part is soft ground and the lower part is rock bed. CONSTITUTION:An iron bar cage 9, etc., are erected in an excavated trench formed in a soft ground, box-thrust steel pipes are erected at a given interval, and concrete 10, etc., is placed. After a hardening agent, e.g., concrete, etc., is hardened, the box-thrust pipes 8 are pulled out by jacks, etc., the holes 11 thus formed are inserted with drills, and holes 12 for pillar rows are drilled in the rock bed below the underground continuous wall 3. Then, iron bars, etc., are ercted into the holes 12 and then concrete is placed to form a pillar-row pile 4.

Description

【発明の詳細な説明】 この発明は上部が軟弱層、下部が岩盤からなる地盤条件
のもとで、岩盤までオープン掘削する場合の土留壁の施
工法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method of constructing an earth retaining wall in the case of open excavation down to bedrock under ground conditions where the upper part is a soft layer and the lower part is bedrock.

この種の地盤条件下において、土留め構造は上部の軟弱
層憎詔いては、土砂、′地下水の流出が生ずるため、地
下連続壁などの“面”で地山を抑える必要がある一方、
岩盤での連続壁の施工は施工性の上からも困離が伴なう
。また岩盤は強度も高く、地下連続壁などの“面”で地
山を抑える必要がなく、岩盤掘削に施工性の良いボーリ
このようなことり)らこの発明では上部が地下連続壁、
下部−が柱列杭から4なる土留壁を考え、部が地下連続
壁、下部が柱列杭からなる土留壁の施工法は掘削溝に所
定間隔をおいて箱抜パイプを纏込んだ状態で地下連続壁
を構築し、その後前記箱抜パイプを引抜き地下連続壁に
箱抜孔を設け、前記箱抜孔に穿孔機を挿入して地下連続
壁以下の地盤に掘削孔を設け、この掘削孔に杭を−込ん
で柱列杭を形成することを41黴とする。なお、前記箱
抜パイプ等の鋼材は嶋込みに際し、予め減摩剤を塗布し
てtくことにより、地下連続壁の施工後ジヤツキ等で容
易に引抜くことができることが確認されている。
Under this type of ground condition, the earth retaining structure will interfere with the upper soft layer, causing sediment and groundwater to flow out.
Constructing a continuous wall on bedrock presents difficulties in terms of workability. In addition, the strength of the bedrock is high, so there is no need to suppress the ground with a "surface" such as an underground continuous wall, and it is easy to construct a bowl for rock excavation.In this invention, the upper part is an underground continuous wall,
Considering an earth retaining wall whose lower part is made up of column piles, the construction method for an earth retaining wall whose lower part is an underground continuous wall and whose lower part is made of column piles is to insert boxed pipes into an excavated trench at predetermined intervals. Construct an underground continuous wall, then pull out the box pipe to make a box hole in the underground continuous wall, insert a drilling machine into the box hole to make an excavated hole in the ground below the underground continuous wall, and install piles in this excavated hole. It is considered as 41 mold to form a row of pillars by inserting them. It has been confirmed that steel materials such as the box-opened pipes can be easily pulled out by jacking or the like after construction of an underground continuous wall by applying an anti-friction agent beforehand.

以下この発明を図示した実施例に基づいて説明する。The present invention will be described below based on illustrated embodiments.

第1allはロックアンカー土留めに利用した場合の実
施例を示したもので、軟弱層1に構築した地下連続壁5
とこの地下連続−以下の岩盤2に施工した柱列杭4とを
一体の土留壁として内部掘削および内部施工を行なう。
The first all shows an example in which rock anchors are used for earth retaining, and the underground continuous wall 5 constructed in the soft layer 1
Internal excavation and internal construction will be carried out using this underground continuity and column piles 4 constructed on the bedrock 2 below as an integral earth retaining wall.

図中5はロックアンカーを示し、亀は内部掘削面である
In the figure, 5 indicates a rock anchor, and the tortoise indicates an internal excavation surface.

また第2゛図は円形逆巻土留めに利用した場合の実施例
を示したもので、上部が地下連続壁3、下部が柱列杭4
からなる土留壁を構築し、内部掘削を行ないながら逆巻
コンクリートを打設し、逆巻リング6を形成して行く。
In addition, Figure 2 shows an example in which it is used for circular reverse winding earth retention, with the upper part being an underground continuous wall 3 and the lower part being columnar piles 4.
An earth retaining wall is constructed, and reverse-wound concrete is placed while internal excavation is performed to form a reverse-wound ring 6.

第3図〜第8図はこの土留壁の施工手順を示した概念図
であり、次のような手順で作業が行なわれる。
Figures 3 to 8 are conceptual diagrams showing the construction procedure for this earth retaining wall, and the work is carried out in the following steps.

(1)  まず軟弱地盤1に地下連続壁を構築するため
の掘削#17を掘削する(第3図参照)。溝壁安定のた
めには通常ベントナイト泥水等の泥水を用いることが多
い。
(1) First, excavation #17 is excavated to construct an underground continuous wall in soft ground 1 (see Figure 3). To stabilize trench walls, muddy water such as bentonite muddy water is often used.

(2)掘削溝7に鉄筋機等必要な鋼材を建込み、同時に
所定間隔をおいて鋼管等の箱抜パイプ8を建込む。その
後コンクIJ −ト10等を打設する(第4図参照)。
(2) Necessary steel materials such as reinforcing steel are erected in the excavated trench 7, and at the same time, boxed pipes 8 such as steel pipes are erected at predetermined intervals. After that, concrete IJ-10 etc. are poured (see Figure 4).

コンクリート10の代わりにフィルセメントその他の硬
化材を用いても喪い。なお、前述したように箱抜パイプ
8には予め減摩剤を塗布しておくことにより、施工が容
易となる。
Even if fill cement or other hardening material is used instead of concrete 10, it will not deteriorate. Note that, as described above, by applying an anti-friction agent to the box-opening pipe 8 in advance, construction becomes easier.

(5)  コンクIJ −) 10等の硬化材の硬化後
、箱抜パイプ8をジヤツキ等で引き抜く(第5図参照)
(5) Conc IJ -) After curing the hardening material such as 10, pull out the boxed pipe 8 with a jack or the like (see Figure 5).
.

(41箱抜パイプ8の引き抜きにより形成さ九た箱抜孔
11にボーリングマシン等の穿孔機を挿入し、地下連続
壁1以下の岩盤2の柱列部を穿孔する(第6図参照)。
(41) A drilling machine such as a boring machine is inserted into the box hole 11 formed by pulling out the box pipe 8, and the columnar part of the bedrock 2 below the underground continuous wall 1 is bored (see Fig. 6).

(5)上記゛(4)によって得られた掘削孔12に鉄筋
15もしくは鋼材を建込み(第7図参照)、コンクリー
トを打設し柱列杭4を形成する(纂8図参照)。
(5) Reinforcing bars 15 or steel materials are placed in the excavated hole 12 obtained in (4) above (see Figure 7), and concrete is poured to form column piles 4 (see Figure 8).

なおこの実施例では柱列杭4を場所打ち鉄筋コンクリー
ト杭としているが、これに限るものではない。
In this embodiment, the column piles 4 are cast-in-place reinforced concrete piles, but are not limited to this.

この発明は以上の構成からなり、上部が軟弱地盤、下部
が岩盤という地盤条件において、上部を地下連続壁、下
部を柱列杭上する土留壁を構築するので、合理的かつ経
済的な施工が可能である。また地下連続壁の構築後、箱
抜パイプの引き抜きによって得られた箱抜孔を柱列杭の
施工に利用でき、かつ箱抜パイプは繰り返し便用できる
This invention has the above-mentioned configuration, and in the ground condition where the upper part is soft ground and the lower part is rocky ground, an earth retaining wall is constructed in which the upper part is an underground continuous wall and the lower part is on column piles, so it is possible to construct it rationally and economically. It is possible. Further, after constructing the underground continuous wall, the box holes obtained by pulling out the box pipe can be used for constructing column piles, and the box pipe can be used repeatedly.

【図面の簡単な説明】[Brief explanation of the drawing]

図面はこの発明の実施例を示したもので、第1図はロッ
クアンカー土留めに利用した場合の縦断面図、第2図は
円型逆巻き土留めに利用した場合の縦断面における斜視
−、第3図〜第8図は施工手順の概略を示す縦断面にお
ける斜視図である。 1・・軟弱層、2・・岩盤、3・・地下連続壁、4・・
柱列杭、5ssアンカー、6・・逆巻リング、7・・掘
削溝、8・・箱抜パイプ、9・・鉄筋、10・・コンク
リート、11・・箱抜孔、12・・掘削孔、13・・鉄
筋。 代   理   人  久   門      知第1
図 第3111 第2図 第4図 第5図 第 7  f゛−1 第61′4 11  11 第81¥J
The drawings show an embodiment of the present invention, and FIG. 1 is a vertical cross-sectional view when it is used for rock anchor earth retaining, and FIG. 2 is a perspective view of the vertical cross-section when it is used for circular reverse winding earth retaining. FIGS. 3 to 8 are perspective views in longitudinal section showing the outline of the construction procedure. 1. Soft layer, 2. Bedrock, 3. Underground continuous wall, 4.
Column pile, 5ss anchor, 6... Reverse winding ring, 7... Excavation groove, 8... Box punched pipe, 9... Rebar, 10... Concrete, 11... Box punched hole, 12... Drilled hole, 13 ...Reinforced steel. Agent Tomoichi Hisakado 1
Figure 3111 Figure 2 Figure 4 Figure 5 Figure 7 f゛-1 61'4 11 11 81\J

Claims (1)

【特許請求の範囲】 (1)  掘削溝に所定間隔をおいて箱抜パイプを娼込
んだ状態で地下連続壁を構簗し、その後前記箱抜パイプ
を引抜き地下連続−に箱抜孔牽設け、前記箱抜孔に穿孔
機を挿入して地下連続壁以下の地盤に掘削孔を設け、こ
の掘削孔に杭を建込んで柱列杭を形成することを特徴と
する上部が地下連続壁、下部が柱列杭からなる土留壁の
施工法。 (2)  箱抜パイプには纏込みに際し、予め減摩剤を
塗布してお”<*1lv−請求の範1i1Q1項記載の
上部が地下連続壁、下部が柱列杭からなる土留壁の施工
法。 (5)柱列杭は場所打ち鉄筋コンクリート杭である特許
請求の範囲第1項または第2項記載の上部が地下連続壁
、下部が柱列杭からなる土留壁の施工法。
[Scope of Claims] (1) An underground continuous wall is constructed with boxed pipes inserted at predetermined intervals in an excavated trench, and then the boxed pipes are pulled out to create boxed holes in the underground continuity; A drilling machine is inserted into the box hole to make an excavation hole in the ground below the underground continuous wall, and piles are erected in the excavated hole to form column piles.The upper part is the underground continuous wall and the lower part is the underground continuous wall. A construction method for earth retaining walls consisting of rows of column piles. (2) When bundling the boxed pipes, apply an anti-friction agent in advance.''<*1lv-Construction of an earth retaining wall consisting of an underground continuous wall in the upper part and columnar piles in the lower part as described in claim 1i1Q1. (5) The construction method of an earth retaining wall whose upper part is an underground continuous wall and whose lower part is a column pile according to claim 1 or 2, wherein the column pile is a cast-in-place reinforced concrete pile.
JP16946781A 1981-10-23 1981-10-23 Construction of sheathing wall having upper part consisting of underground continuous wall and lower part of pillar-row pile Pending JPS5869924A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16946781A JPS5869924A (en) 1981-10-23 1981-10-23 Construction of sheathing wall having upper part consisting of underground continuous wall and lower part of pillar-row pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16946781A JPS5869924A (en) 1981-10-23 1981-10-23 Construction of sheathing wall having upper part consisting of underground continuous wall and lower part of pillar-row pile

Publications (1)

Publication Number Publication Date
JPS5869924A true JPS5869924A (en) 1983-04-26

Family

ID=15887097

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16946781A Pending JPS5869924A (en) 1981-10-23 1981-10-23 Construction of sheathing wall having upper part consisting of underground continuous wall and lower part of pillar-row pile

Country Status (1)

Country Link
JP (1) JPS5869924A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1035634C (en) * 1992-03-19 1997-08-13 中国建筑第一工程局建筑科学研究所 Flexible rope pile bulkhead tech.
JP2018035604A (en) * 2016-09-01 2018-03-08 鹿島建設株式会社 Construction method for earth retaining wall combining impervious wall with soldier beam
CN112861208A (en) * 2021-01-07 2021-05-28 青岛理工大学 Analysis method for converting row pile supporting system into underground continuous wall supporting structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1035634C (en) * 1992-03-19 1997-08-13 中国建筑第一工程局建筑科学研究所 Flexible rope pile bulkhead tech.
JP2018035604A (en) * 2016-09-01 2018-03-08 鹿島建設株式会社 Construction method for earth retaining wall combining impervious wall with soldier beam
CN112861208A (en) * 2021-01-07 2021-05-28 青岛理工大学 Analysis method for converting row pile supporting system into underground continuous wall supporting structure
CN112861208B (en) * 2021-01-07 2022-08-16 青岛理工大学 Analysis method for converting row pile supporting system into underground continuous wall supporting structure

Similar Documents

Publication Publication Date Title
KR100964796B1 (en) Method for constructing the steel pipe-concrete composite pile structurized of burying and unifying into the bedrock, and a pile construction
US4496268A (en) Method and apparatus for constructing reinforced concrete walls in the earth
US6616380B1 (en) Subterranean structures and methods for constructing subterranean structures
KR100618597B1 (en) Cast in place concrete pile using vibro magnetic shovel hammer, and the construction method of this
JPH0960028A (en) Method for increasing strength of existing steel pipe pile
JP2000352296A (en) Method o constructing passage just under underground structure
KR200362565Y1 (en) Earth Retaining Wall Structure Using Precast Concrete Pile and Construction Method Thereof
JPS5869924A (en) Construction of sheathing wall having upper part consisting of underground continuous wall and lower part of pillar-row pile
KR101021913B1 (en) A method for constructing cut-off temporary structure for sheathing work
JPS5847823A (en) Construction of in-place concrete pile
KR101047257B1 (en) Construction method of earth wall using composite sheet pile
JPS5869923A (en) Construction of underground continuous wall with drain layer
KR100654973B1 (en) Earth Retaining Wall Structure Using Precast Concrete Pile and Construction Method Thereof
JPS61134425A (en) Method of forming foundation pile
JPH02266015A (en) Constructing underground continuous wall
JPS601451B2 (en) Water stop mountain stop wall construction method using Benoto pile excavator
JPS60141919A (en) Method of building continuous pillar-shaped landslide protection wall
JPH09111754A (en) Soldier pile cut-of wall construction method
JP2874906B2 (en) Shaft construction method
KR200375610Y1 (en) Cast in place concrete pile using vibro magnetic shovel hammer
JPS6250516A (en) Formation work of composite pile
JP2764482B2 (en) Construction method of large depth human hole
JPS6124491B2 (en)
JPH10252064A (en) Method for constructing cast-in-site pile
JPH09125405A (en) Deep foundation for inclined tower leg