JPS6250516A - Formation work of composite pile - Google Patents

Formation work of composite pile

Info

Publication number
JPS6250516A
JPS6250516A JP18902685A JP18902685A JPS6250516A JP S6250516 A JPS6250516 A JP S6250516A JP 18902685 A JP18902685 A JP 18902685A JP 18902685 A JP18902685 A JP 18902685A JP S6250516 A JPS6250516 A JP S6250516A
Authority
JP
Japan
Prior art keywords
concrete
pile
tip
pit
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP18902685A
Other languages
Japanese (ja)
Other versions
JPH051850B2 (en
Inventor
Akiyoshi Nojiri
野尻 明美
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP18902685A priority Critical patent/JPS6250516A/en
Publication of JPS6250516A publication Critical patent/JPS6250516A/en
Publication of JPH051850B2 publication Critical patent/JPH051850B2/ja
Granted legal-status Critical Current

Links

Abstract

PURPOSE:To enhance the bearing capacity of a composite pile by a method in which concrete is placed to the expanded tip portion of a prebored pit, and a custom-made reinforced concrete pile having reinforcing bars on its tip peripheral side is penetrated into and fixed to the concrete. CONSTITUTION:A prebored pit 1 is excavated in the ground, and an expanded bottom portion 2 is formed on the tip portion of the pit 1. In-situ concrete 3 is packed into the expanded bottom 2 of the pit 1, a custom-made reinforced concrete pile P having reinforcing bars 4 on its tip peripheral side is inserted into the pit 1, and its tip portion is penetrated into the concrete 3.

Description

【発明の詳細な説明】 産業上の利用分野 この発明は現場打ち鉄筋コンクリート杭と既製鉄筋コン
クリート杭との合成に係る複合杭の造成工法に関するも
のである。
DETAILED DESCRIPTION OF THE INVENTION Field of Industrial Application This invention relates to a method for constructing a composite pile by combining a cast-in-place reinforced concrete pile and a ready-made reinforced concrete pile.

従来技術と発明の解決しようとする問題点低振動、低騒
音の基礎杭埋設工法としてプレボーリング孔の底部を拡
大し、その孔内にセメントミルクを注入し、土砂と攪拌
してえられるフィルコンクリート中に既製杭を挿入し、
硬化したフィルコンクリートによって既製杭を支持させ
る方法が実用化されている。ところでこの工法も従来の
既製杭の打込工法よりも所定の低減した支持力しか認め
られない現状にある。その理由として拡底して球根とし
てあっても鉄筋による補強構造でないこと球根と既製杭
との一体化が充分でないこと等が一因となっている〇出
願人は前記問題点を解消しうる発明として特願昭53−
102455号(特開昭55−30040)に示す方法
を既に開発した。この発明はその発明をさらに発展改良
させて、杭としての支持力向上を図ったものである。
Problems to be solved by the prior art and the invention Fill concrete is obtained by enlarging the bottom of a pre-bored hole, injecting cement milk into the hole, and stirring it with earth and sand as a low-vibration, low-noise foundation pile burying method. Insert a ready-made stake inside,
A method of supporting ready-made piles with hardened fill concrete has been put into practical use. However, this construction method currently only allows a predetermined lower bearing capacity than the conventional method of driving ready-made piles. One of the reasons for this is that even though the bulb has an expanded base, it does not have a reinforced structure with reinforcing bars, and the bulb and the ready-made pile are not sufficiently integrated.〇The applicant has proposed an invention that can solve the above problems. Special application 1973-
We have already developed a method shown in No. 102455 (Japanese Unexamined Patent Publication No. 55-30040). This invention further develops and improves the invention to improve the supporting capacity of the pile.

問題点を解決するための手段 発明の要旨とする構成は特許請求の範囲の欄に記載の通
りであり、特にその主要部とするところは拡底したプレ
ボーリング孔内に現場打ちコンクリートを打設し、次い
で前記コンクリートの補強筋を付設した既製鉄筋コンク
リート杭をコンクリート中に挿入定着させて一体化する
ことζこよって複合杭を造成するものであり、現場打ち
コンクリート部分に鉄筋等の補強筋を埋設することによ
り、既製杭より大径とされた現場打ちコンクリートに耐
力を期待し、延いては杭全体の支持力を向上させたもの
である。
Means for Solving the Problems The gist of the invention is as described in the scope of the claims, and the main part thereof consists of pouring cast-in-place concrete into a pre-bored hole with an enlarged bottom. Next, the ready-made reinforced concrete pile with the concrete reinforcement attached is inserted into the concrete and fixed and integrated.Thus, a composite pile is created, and reinforcing bars such as reinforcing bars are buried in the cast-in-place concrete part. As a result, the cast-in-place concrete, which has a larger diameter than ready-made piles, is expected to have greater bearing capacity, which in turn improves the bearing capacity of the pile as a whole.

実施例 先ず泥水工法を使用する掘削機によってプレボーリング
孔1を掘削し、掘削機の拡翼ビットによって先端部を拡
底孔2とする。その−例が第1図に示す通りであり、プ
レボーリング孔の断面積Aに対し、拡底孔断面積は2A
であり、深さは4〜5D以上とする。
Embodiment First, a pre-boring hole 1 is excavated by an excavator using a muddy water method, and the tip portion is made into an enlarged bottom hole 2 using a wing-expanding bit of the excavator. An example of this is shown in Figure 1, where the cross-sectional area of the pre-bored hole is A, while the cross-sectional area of the expanded hole is 2A.
and the depth is 4 to 5D or more.

次いで拡底孔2内に現場打ちコンクリート3を充填する
。第2図に示す既製鉄筋コンクリート杭Pの先端部外周
には4D以上の長さに相当する補強筋4が付設しておく
、この補強筋4としては短冊状の帯鉄板をもって形成し
、それらの外周にはスパイラル鉄筋5を工場で溶接して
おく。
Next, the expanded bottom hole 2 is filled with cast-in-place concrete 3. A reinforcing bar 4 corresponding to a length of 4D or more is attached to the outer periphery of the tip of the ready-made reinforced concrete pile P shown in Fig. 2.The reinforcing bar 4 is formed of strip-shaped iron strips, and the outer periphery of the reinforcing bar 4 is Spiral reinforcing bars 5 are welded at the factory.

他の発明として既製鉄筋コンクリート杭Pの先端部に4
D以上の長さの鋼管6を溶接して接続し、その外周には
スパイラル鉄筋5を工場で溶接しておく。なお鋼管6に
は内外コンクリートを連通させる透孔を形成しておくと
か、鋼管6を凹凸状に形成してコンクリートとの付着力
を増大させることができる。
As another invention, at the tip of a prefabricated reinforced concrete pile P,
Steel pipes 6 having a length of D or more are welded and connected, and a spiral reinforcing bar 5 is welded to the outer periphery at a factory. Note that the adhesion force with the concrete can be increased by forming a through hole in the steel pipe 6 to communicate the inner and outer concrete, or by forming the steel pipe 6 into an uneven shape.

以上の杭Pをプレボーリング孔1内に挿入し、その先端
部を現場打ちコンクリート6中に挿入する。
The above pile P is inserted into the pre-bored hole 1, and its tip is inserted into the cast-in-place concrete 6.

その際必要に応じて棒状パイブレーク−を杭先端部付近
まで降下させて振動させ、杭Pと周辺コンクリートとの
付着の向上を図ることもある。
At this time, if necessary, the rod-shaped pie break may be lowered to the vicinity of the tip of the pile and vibrated to improve the adhesion between the pile P and the surrounding concrete.

なお現場打ちコンクリート6の上部にセメントミルクを
注入しておくとプレボーリング孔1と杭Pの周辺に充填
される。
If cement milk is poured into the upper part of the cast-in-place concrete 6, the area around the pre-bored hole 1 and the pile P will be filled.

発明の効果 この発明は以上の構成からなり、既製鉄筋コンクリート
杭の先端部外周に補強筋を付設し、あるいは既製鉄筋コ
ンクリート杭の先端に鋼管を付設し、プレボーリング孔
の拡底部に打設したコンクリート中に挿入することによ
り、既製杭の下部に、所要の鉄筋比、例えば0.4%以
上鉄筋比を有する大径の現場打ち杭が造成されているの
で従来のセメントミルク根固工法よりも大きい支持力が
期待できる。
Effects of the Invention The present invention has the above-mentioned configuration, and includes reinforcing bars attached to the outer periphery of the tip of a ready-made reinforced concrete pile, or a steel pipe attached to the tip of a ready-made reinforced concrete pile, and placed in the expanded bottom of a pre-bored hole. By inserting a large diameter cast-in-place pile at the bottom of the ready-made pile, a large diameter cast-in-place pile with a required reinforcing bar ratio, for example, 0.4% or more, is created, which provides greater support than the conventional cement milk foundation method. You can expect power.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図はプレボーリング孔の断面図、第2図、第3図は
施工完了状態の断面図、第4図、第5図は杭先端部の詳
細図で、一部所面図である。 1・・プレボーリング孔、2・・拡底孔、3・・現場打
ちコンクリート、P・・杭、4・・補強筋、5・・スパ
イラル鉄筋、6・・鋼管。 第1図  乃2u  ’:;3:: 第4図 、15 ロ
FIG. 1 is a cross-sectional view of the pre-bored hole, FIGS. 2 and 3 are cross-sectional views of the completed construction state, and FIGS. 4 and 5 are detailed views of the tip of the pile, which are partial views. 1. Pre-boring hole, 2. Expanded hole, 3. Cast-in-place concrete, P. Pile, 4. Reinforcement bar, 5. Spiral reinforcing bar, 6. Steel pipe. Figure 1 ノ2u':;3:: Figure 4, 15 ro

Claims (2)

【特許請求の範囲】[Claims] (1)先端部を拡底したプレボーリング孔を形成し、次
いで、前記プレボーリング孔の先端拡底部に現場打ちコ
ンクリートを打設し、次いで前記コンクリートの補強筋
を先端部外周に付設した既製鉄筋コンクリート杭を前記
コンクリート中に挿入定着させて一体化することを特徴
とする複合杭の造成工法。
(1) A pre-bored hole with an enlarged bottom end is formed, then cast-in-place concrete is poured into the bottom end of the pre-bored hole, and reinforcing bars of the concrete are attached to the outer periphery of the tip end of the ready-made reinforced concrete pile. A method for constructing a composite pile, characterized by inserting and fixing into the concrete and integrating it.
(2)先端部を拡底したプレボーリング孔を形成し、次
いで、前記プレボーリング孔の先端拡大部に現場打ちコ
ンクリートを打設し、次いで前記コンクリートの補強筋
となる鋼管を先端部に付設した既製鉄筋コンクリート杭
を前記コンクリート中に挿入定着させて一体化すること
を特徴とする複合杭の造成工法。
(2) A pre-bored hole with an enlarged tip is formed, then cast-in-place concrete is poured into the enlarged tip of the pre-bored hole, and a steel pipe is attached to the tip to serve as reinforcement for the concrete. A construction method for a composite pile, characterized by inserting and fixing a reinforced concrete pile into the concrete and integrating it.
JP18902685A 1985-08-28 1985-08-28 Formation work of composite pile Granted JPS6250516A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP18902685A JPS6250516A (en) 1985-08-28 1985-08-28 Formation work of composite pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP18902685A JPS6250516A (en) 1985-08-28 1985-08-28 Formation work of composite pile

Publications (2)

Publication Number Publication Date
JPS6250516A true JPS6250516A (en) 1987-03-05
JPH051850B2 JPH051850B2 (en) 1993-01-11

Family

ID=16234053

Family Applications (1)

Application Number Title Priority Date Filing Date
JP18902685A Granted JPS6250516A (en) 1985-08-28 1985-08-28 Formation work of composite pile

Country Status (1)

Country Link
JP (1) JPS6250516A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6475715A (en) * 1987-09-18 1989-03-22 Nippon Kokan Kk Soil cement composite pile
JPH01312120A (en) * 1988-06-13 1989-12-15 Mitani Sekisan Co Ltd Pile embedding method and pile thereof
KR20060042370A (en) * 2004-11-09 2006-05-12 송기용 Pile with an extended head reinforced cement paste or concrete
JP2006249928A (en) * 2001-03-29 2006-09-21 Jfe Steel Kk Supporting structure of foundation pile and construction method of foundation pile
JP2011226264A (en) * 2001-03-29 2011-11-10 Jfe Steel Corp Steel pipe pile and supporting structure and construction method using the same

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5530040A (en) * 1978-08-23 1980-03-03 Kajima Corp Working for foundation pile

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5530040A (en) * 1978-08-23 1980-03-03 Kajima Corp Working for foundation pile

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6475715A (en) * 1987-09-18 1989-03-22 Nippon Kokan Kk Soil cement composite pile
JPH01312120A (en) * 1988-06-13 1989-12-15 Mitani Sekisan Co Ltd Pile embedding method and pile thereof
JP2006249928A (en) * 2001-03-29 2006-09-21 Jfe Steel Kk Supporting structure of foundation pile and construction method of foundation pile
JP2011226264A (en) * 2001-03-29 2011-11-10 Jfe Steel Corp Steel pipe pile and supporting structure and construction method using the same
KR20060042370A (en) * 2004-11-09 2006-05-12 송기용 Pile with an extended head reinforced cement paste or concrete

Also Published As

Publication number Publication date
JPH051850B2 (en) 1993-01-11

Similar Documents

Publication Publication Date Title
KR20110041391A (en) Pile structure
KR100618597B1 (en) Cast in place concrete pile using vibro magnetic shovel hammer, and the construction method of this
JPS5985028A (en) Steel pipe pile and laying work thereof
JP2003119775A (en) Construction of foundation pile
JPH0960028A (en) Method for increasing strength of existing steel pipe pile
JPS6250516A (en) Formation work of composite pile
JP4724879B2 (en) Foundation pile structure
JP4154487B2 (en) Foundation pile construction method, foundation pile
JPH02289718A (en) Drilling method of expanded head pile hole, constructing method of expanded head pile and pile hole drill
JPH08184037A (en) Double pipe steel pipe pile
JPH09324422A (en) Cast-in-place compound pile and building method therefor
JP3586839B2 (en) In-situ formed concrete pile and its forming method
JPH0721196B2 (en) Reverse construction method of underground structure
JPH1046573A (en) Bottom enlarged cast-in-place pile and its construction method
JP3772915B2 (en) Foundation pile construction method and foundation pile
JP2004162346A (en) Pile head connection structure of prefabricated pile
JPH08199565A (en) Pile head joint construction of cast-in-place concrete pile
JPH01102125A (en) Placement of concrete pile at site
JP4178273B2 (en) Construction method of structural pillars using ready-made piles
KR200375610Y1 (en) Cast in place concrete pile using vibro magnetic shovel hammer
JPS6049733B2 (en) Foundation pile construction method
JPH0351365Y2 (en)
JP4223781B2 (en) Ground improvement foundation method for soft ground.
JPS59210124A (en) Burying work of pile
JPH0641956A (en) Execution method for high proof stress cast-in-place concrete pile, etc.